Chief Capital Management Officer s Report

Similar documents
Transit Project Delivery Status Report. Significant Issues

I-405 Sepulveda Pass Improvements Project

30-Day Look Ahead Summary August 2011

Project Budget and Schedule Status

I-405 Sepulveda Pass Improvements Project. Community Advisory Committee July 28, 2011

Click to edit Master text styles

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition

I-405 Sepulveda Pass Improvements Project

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014

Mobility Corridor Updates. Transit & Active Transportation Projects

Exposition Light Rail Transit Project

Pomona Rotary December 19, 2017

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011

Mobility Corridor Updates. Transit & Active Transportation Projects

Sepulveda Pass Corridor Systems Planning Study Update

quarterly project status report

quarterly project status report

Phase 2 Exposition Metro Line Project

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014

CITY OF BEVERLY HILLS STAFF REPORT

AIRPORT HAYVENHURST HAYVENHURST MANDEVILLE CANYON BRENTWOOD SANTA MONICA CARLYLE 20TH 17TH 17TH 14TH MONTANA 11TH LINCOLN 7TH 7TH WILSHIRE

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

Metro Highway Program

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015

Sepulveda Pass Corridor Systems Planning Study

Develop ground transportation improvements to make the Airport a multi-modal regional

Rolling Road (Route 638) Widening Project

Business Advisory Committee. July 7, 2015

Corridor Management Committee. March 7, 2012

Business Advisory Committee. November 3, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

LAX Specific Plan Amendment Study. CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006

Exposition Corridor Transit Project

congestion management program

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015

Chapter 7. Transportation Capital Improvement Projects. Chapter 7

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

SAN RAFAEL CITY COUNCIL AGENDA REPORT

Westside Subway Extension Final EIS/EIR. January 2011 Community Update Meetings

Project Status Update January 2017

Community Open Houses November 29 December 7, 2017

Key Project Elements Status Report

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017

Wentzville Parkway South Phase 2 & 2A

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan

Study Area, Related Projects and Travel Markets

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017

East San Fernando Valley Transit Corridor. Community Meetings April/May, 2012

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT FEBRUARY 2015

West Broadway Reconstruction/LRT Design. March 19, 2015

Committee Report. Transportation Committee. Business Item No

2.4 Build Alternatives

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016

Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019

Delta Kappa Gamma January 22, 2018

Metro Gold Line Eastside Extension Review Advisory Committee March 12, 2009

DART Priorities Overview

US 67 WIDENING PROJECT

City of Grand Forks Staff Report

Why coordinate the Van Nuys and Sepulveda Pass project studies together?

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Balancing the Transportation Needs of a Growing City

Peninsula Corridor Electrification Project (PCEP)

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012

Janice Fortunato Senior Director Business Partnerships

Letter EL652 City of Mercer Island. Page 1. No comments n/a

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

One Gateway Plaza Los Angeles, CA

STH 60 Northern Reliever Route Feasibility Study Report

Peninsula Corridor Electrification Project (PCEP)

FREQUENTLY ASKED QUESTIONS

I-225 Rail Line Iliff and Florida Stations Information Meeting

Capital Improvement Plan Review

Purple Line Extension Section 1 Construction Community Meeting April 19, 2018

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study

Community Meetings June 2018

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes

FREQUENTLY ASKED QUESTIONS

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017

I-225 Rail Line 2 nd /Abilene Station Design Public Meeting

engineering phase and during the procurement of design build contracts.

Project Scoping Open House Welcome

Southern California - CHSRA

Purple Line Light Rail P3 Project

CPG is pleased to report the following accomplishments this quarter:

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina

Purple Line Extension Section 1 Construction Community Meeting January 17, 2019

Update on Transportation Activities in Fairfax County

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013

Federal Way Link Extension

Mobility Management: Caltrain

SEPULVEDA PASS CORRIDOR

Transportation Improvement Program (TIP) Candidate Project List for Public Review

ACTION TRANSMITTAL No

Transcription:

Item 40 Chief Capital Management Officer s Report Construction Committee April 15, 2010 1

Metro Gold Line Eastside Extension Project Update April 2010 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro Gold Line $898.8 million On-Time/Within Budget Over 4.3 million Safe Work Hours Opened to the Public November 15, 2009 Gold Line 2

Metro Gold Line Eastside Extension Pomona/Atlantic Station Parking The 266-space parking structure opens to the public on April 16, 2010. MTA Media Relations will issue a press release announcing the opening to all media outlets with an emphasis in East Los Angeles, Montebello, Monterey Park and surrounding communities. Banners will be placed at the temporary parking lots directing Metro patrons to the new Atlantic Station parking structure, as the temporary parking lots will be closed after April 15, 2010 Gold Line 3

Metro Gold Line Eastside Extension Pedestrian Barrier Fencing Installation 1 st /Mission near the Mendez Learning Center 1 st Street between Lorena and Indiana Streets The installation of the 4 high steel picket pedestrian barrier fencing has been completed. 3 rd Street near the East LA Civic Center Gold Line 4

Metro Gold Line Eastside Extension End of Presentation Gold Line 5

Metro Orange Line Extension Project Update April 2010

Metro Orange Line Extension Four miles Busway and Bikeway Three routes with connection to Chatsworth Metrolink Station Four new stations Three Bridges Landscaping similar to Orange Line Budget $215.6 million Estimated completion summer 2012

Metro Orange Line Extension Design-Build Contract C0943: Issued Notice to Proceed to Brutoco Engineering & Construction, Inc. effective March 1, 2010 Continues to provide initial submittals Commenced design of busway, street crossings, stations and remaining bridges Staff and contractor have moved into Integrated Project Management Office

Metro Orange Line Extension Complete construction of new privacy fence at Chatsworth Mobil Home Park in May 2010 SCRRA to substantially complete modifications of rail signals in April 2010 LADWP to complete temporary power relocation at Chatsworth Station in April 2010 Removed 26 billboard signs. Relocated 50 businesses. Last 2 relocations by end of April 2010 Finalizing Union Pacific Easement agreement

Metro Orange Line Extension Rail signal modification work by SCRRA s contractor at Chatsworth Station

I-405 Sepulveda Pass Widening Project Project Update - April 2010 11

I-405 Sepulveda Pass Widening Project Project Update - April 2010 Design/Build Project to close the HOV Lane gap between the 10 Freeway and 101 Freeway 10 Miles of freeway work North bound Southbound Lane Standardization (2.5 Miles - North and South ends) Widening of 12 Bridge Structures 8 Replacement Ramp Structures 3 Full Bridge Replacements Reconstruct 17 on/off ramps 18 Miles of Retaining Wall & Sound Wall $1.034 Billion Project Budget Estimated Completion 2013 12

I-405 Sepulveda Pass Widening Project Status Current available funds are $372M Design Build Contractor Kiewit Notice to Proceed occurred June 2, 2009 Project Commencement August 31, 2009 IPO Staffing levels (end of October 2009) Kiewit 115 (+) HNTB (Kiewit's designer) 140 (+) MTA /CT 40 (+) Baseline schedule approved January 20 13

I-405 Sepulveda Pass Widening Project Summary Schedule 14

I-405 Sepulveda Pass Widening Project Funding Plan (in $ Million) Source Programmed Available Expended Unexpend. Remaining State TCRP $90.0 $42.0 $42.0 -* $48.0 State CMIA $614.0 - - - $614.0 Federal SAFETEA-LU $117.0 $117.0 18.0 $99.0 - Federal ARRA $189.9 $189.9 56.2 $133.7 - Federal RSTP $10.1 $10.1 - $10.1* - Prop C 25% $13.0 $13.0 $1.6 $9.8 - TOTALS $1,034.0 $372.0 $117.8 $252.6 $662.0 * $10.1 million currently available for termination costs; the options for securing the balance of $5.9 million include: 1. Private Placement Bonds 2. LONP against $48.0 million of future TCRP 3. Reserve $6.0 million out of Prop 1B Bond 4. Caltrans Statewide Highway Program Funding 15

I-405 Sepulveda Pass Widening Project Status Field work: Pothole work for design will be completed in mid-may. Drainage CCTV and cleaning is on-going and expected to be completed by the end of April 2010. Re-stripe of the N/B 405 freeway is now completed. Re-stripe of the S/B 405 will start in one week and will take 16 days to complete the work. Saw-cut and Grinding of the existing pavement will be completed end of May. 16

I-405 Sepulveda Pass Widening Project Status Field work: K-Rail installation is scheduled tentatively to start this week and will continue for two (2) months Sunset Bridge demo prep work is tentatively scheduled to start by mid-may and the actual bridge demo will be the end of April Sewer relocation at VA is scheduled to start April 19, 2010 Pile driving work for Wilshire Bridge 6A (SB 405 to EB Wilshire will begin May 03, 2010) Utility under-grounding work will begin later this month and will be completed in one (1) month. Under grounding of DWP overhead power lines on Sepulveda Blvd. between Montana Ave. and Sunset Blvd., started in March. Church Lane widening (between Sunset Blvd. and Sepulveda Blvd.) planned to occur in April. Sunset Bridge demolition (half at a time) planned to occur in May. 17

I-405 Sepulveda Pass Widening Project Status Field work: (cont d) MSE Panel fabrication began mid-march, 775 panels fabricated Soil nail wall 1836, 1992, and 2004 are scheduled to start May 1 st Design: HNTB Design continues Quality System development continues Over-the-shoulder reviews continue 18

I-405 Sepulveda Pass Widening Project Status Community Activities: Held meetings with 23 Homeowners in Westwood Hills to update on Sepulveda retaining wall and on individual properties. Coordinated Elected Official Briefing, monthly Community Advisory Committee (CAC) meeting and a quarterly meeting. Also, additional meetings with The Getty Center, Santa Monica Mountain Conservancy, LADWP, Bus Operations, Westwood Recreation Center and Los Angeles Homeless Service Authority. 19

I-405 Sepulveda Pass Widening Project Status Community Activities: (cont d) Distributed four construction notices regarding partial lane closures, CCTV drain work, K-rail placement and potholing along Sepulveda (between Montana and Sunset). Coordinated construction activities with 25 residents. Attended & presented to: Sherman Oaks Home-Owners Association Sherman Oaks Neighborhood Watch Mulholland Education Corridor Association Valley Vista Home-Owners Association 20

I-405 Sepulveda Pass Widening Project Status Community Activities: (cont d) Attended & presented to: Bel Air Crest Masters Association Board of Directors West LA Bureau of Traffic Brentwood Community Council UCLA Began a social media campaign: Maintained the project Facebook page with 500 friends Maintained the project Nixle account Tweeted daily about construction activities 21

I-405 Sepulveda Pass Widening Project Status City of Los Angeles Working on a revised master cooperation agreement Refining the submittal review/design coordination process Continued work on Reversible Lane project coordination with City of LA (COLA) County of Los Angeles Continued work on resolving Department of Public Work s design comments 22

I-405 Sepulveda Pass Widening Project Status Potential issues and path forward: Westwood Hills Task Force Tolling Agreement to avoid a lawsuit Project staff in negotiations with the Westwood Hills Task Force regarding the impact of realigning Sepulveda Blvd and impacts to adjacent residential properties. A mitigation plan has been presented and an agreement is anticipated by April of 2010. MWD 96 waterline Kiewit Pacific submitted a Value Engineering (VE) proposal to realign the freeway that would allow the MWD water line to remain in place. The VE is presently being reviewed by project staff. 23

I-405 Sepulveda Pass Widening Project Status Potential issues and path forward: (cont d) GSA (Federal Building at Wilshire) Metro continues to coordinate with GSA on utility identification and location; continued clarification of property and project alignment. Kiewit Pacific continued work on design of ramp bridges in this area. County of L.A. 12x12 Drainage Structure Kiewit has been developing options for protect in place alternatives for the Box; Metro is asking for solutions that include Box Relocation and/or Replacement. The responsibilities belong to the Contractor. The path forward for the 12x12 box between Constitution Ave. and Moraga Dr., is to be left in place and designed around and protected in place. May want to explain the path forward in your area; it is relocate foundation. 24

Expo Line Transit Project Exposition Light Rail Transit Project Monthly Project Status Update April 15, 2010 25

Phase 1 Expo Line Transit Project Major Issues Project Status Schedule Contractor s latest schedule shows a 58-week project delay Although there are numerous areas of work that are behind schedule, the critical activities continue to be: La Cienega Bridge Ballona Creek Bridge Farmdale Crossing There are a number of activities that could result in further delay Changes to the Farmdale Avenue grade crossing Blue Line Tie-in S&I Facility Installation of Automatic Train Protection

Expo Line Transit Project Expo Phase 1 Delay Impacts Blue Line Tie-In 7 mo delay (Metro Enhancements) Ven/Rob Aerial Structure & Station 19 mo delay (Authority) La Cienega Aerial Structure 13 mo delay (DWP) Dorsey High School 4-18 mo delay (CPUC) I-110 Bridge 9 mo delay (Caltrans) LA Trade Tech 10 mo delay (CPUC) Automatic Train Protection 10 mo delay (Metro) Storage & Inspection Facility 13 mo delay (Metro)

Phase 1 Expo Line Transit Project Major Issues (cont.) Project Budget Project Status The awarded construction packages are currently within budget There are a number of areas that pose significant risk to the budget Project Delays Venice Robertson Aerial Station Foshay Safety Enhancements Changes to the Farmdale Avenue grade crossing Blue Line Tie-in S&I Facility Professional Services Third Parties Additional changes to Project Scope Installation of Automatic Train Protection

Phase 1 Expo Line Transit Project Construction Progress Flower Adams Overcrossing

Phase 1 Expo Line Transit Project Construction Progress Installation of Fencing and Precast Concrete ADA Truncated Tiles at the Western Avenue Station

Phase 1 Expo Line Transit Project Construction Progress Removal of Falsework at the La Cienega Aerial Structure

Phase 1 Expo Line Transit Project Construction Progress MSE Walls From La Cienega Aerial Structure to Ballona Creek Bridge Structure

Expo Line Transit Project February 2010 Summary of Jobs Program Activities LOCAL JOBS PROGRAM KEY ACCOMPLISHMENTS Local residents worked a total of 35.7% of the construction work hours in February 2010 and a total of 25.1% of all construction work hours on the project to date. The contractor projects that they will meet the 30% goal of construction hours worked by local residents. Local residents comprised 30% of all workers on the project in February 2010. 143 of the 477 workers utilized on the project in the month of February were local residents.

Phase 2 Expo Line Transit Project Project Status Design-Build Procurement Finalizing scope and contract for the 2 most qualified design-build firms to conduct Preliminary Engineering and compete for final design and construction Technical Design Kick-Off meeting was held on March 25 with both firms Notice to proceed (NTP) for PE will be issued in mid-april Anticipate completion of Preliminary Engineering in November 2010 Third Party Coordination/Outreach Met with City of Santa Monica to discuss project status and areas of concern Met with City of Los Angeles, City of Santa Monica and CPUC to discuss atgrade crossings on the bikeway Toured Kilroy properties located adjacent to project alignment to follow up on noise and vibration discussions