Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules

Similar documents
CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Inverter Advancements in UL1741 and UL 62109

Improving DER Interconnection with Updated Standards and Codes, Smart Inverters, and Distribution System Design

Microgrid solutions Delivering resilient power anywhere at any time

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

Submission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia

PV Grid Integration Research in the U.S.

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

Session 8: Distributed Energy Resources Utility Concerns, Grid Impacts and Mitigation Strategies October 21, 2015 Santiago, Chile

Overview of State Distributed Generation Interconnection Rules

IEEE SCC21 Overview/Status IEEE Standards Coordinating Committee 21 on Fuel cells, Photovoltaics. Dispersed Generation, and Energy Storage

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

Small Generator Interconnection Program Interconnection Technical Requirements

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

DISTRIBUTED ENERGY RESOURCE MANAGEMENT SYSTEM. ABB Ability DERMS Operational confidence.

Umatilla Electric Cooperative Net Metering Rules

Interconnection and Net Metering Service in Ohio

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Grid Stability Analysis for High Penetration Solar Photovoltaics

Utility Distribution Planning 101

Renewable Grid Integration Research in the U.S.

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Residential Smart-Grid Distributed Resources

TD-2306B-001, Interconnecting Large 2-20MW Generation Systems. Employees involved with generation interconnection on electric distribution circuits.

Enabling Smart Grid Interoperability: A System of Systems Approach via IEEE P2030 TM and IEEE 1547 TM

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

IEEE* American National Standards

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

DG Standard Updates. IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18

3.0 Radial Distribution Systems

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Advice Pertaining to ERC Resolution No.16 and the Role of Hybrid Generation Advice with respect to specific questions from PIPPA

Rhode Island Division of Public Utilities and Carriers & Office of Energy Resources. Power Sector Transformation

Impact of Distributed Energy Resources on Transmission System Reliability

Net Metering Policy Framework. July 2015

S T A F F R E P O R T

Smart Grid Progress and Plans

SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

National Grid New Energy Solutions (NES)

DISTRIBUTED SOLAR+STORAGE PROBLEM STATEMENT. A.F.Mensah, Inc

Guidelines for connection of generators:

Regenerative Utility Simulator for Grid-Tied Inverters

Powering the most advanced energy storage systems

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Facilitated Discussion on the Future of the Power Grid

Louisville Gas and Electric Company

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

Definitions. Scope. Customer Generation Interconnection Requirements

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

Presentation to the PJM NEMSTF Interconnection Issues. Interconnecting Solar Projects on the PSE&G Distribution System

Implementation of Distributed Generation

Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014

Guideline on Energy Storage

SCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010

Small Electrical Systems (Microgrids)

Business Models and Compensation Framework for the Utility Transformation August 16, 2017

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Breakout Session 1 Report-out presentations

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Technology Roadmap for zzzzzzzzz Grid Automation

Interconnection System Impact Study Report Request # GI

Smart Grid Automation and Centralized FISR

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

RESERVOIR SOLUTIONS. GE Power. Flexible, modular Energy Storage Solutions unlocking value across the electricity network

Impact of Islanding and Resynchroniza?on on Distribu?on Systems

Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections

TRANSMISSION PLANNING CRITERIA

Issue 23 draft for Nuvve

Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

EPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011

Grid Energy Storage: Policies

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Electric Networks/Ina Lehto Updated Original 12/2011

Electric Vehicle Grid Integration Research Analyzing PHEV Impacts on Distribution Transformers in Hawaii

Model-Based Integrated High Penetration Renewables Planning and Control Analysis

Agility in energy Ahead of the challenge, ahead of the change

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

NW Energy XP Project

Portland General Electric

IEEE Workshop Microgrids

2017 Southeastern Tri Regional SAME Training Symposium Microgrids What are they, lessons learned 8/30/2017 Dan Dorn Eaton Corp

The Power Potential Project A guide to participating

Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

RESILIENT SOLAR CASE STUDY: SUNY New Paltz NYPA Integrated Grid Pilot

RE: Comments on Proposed Mitigation Plan for the Volkswagen Environmental Mitigation Trust

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

Transcription:

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules Submitted to New Jersey Board of Public Utilities By Qado Energy Power Engineering Team August 12, 2011 1

Table of Contents Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules... 3 Basis of 10% or 15% Screening Rules... 4 Non-Exporting Generation... 5 Use of Monitored Load Data... 5 Role of Impact Studies... 5 Expansion of IEEE Standard 1547... 5 Accommodating More Solar Generation... 6 Proposed solution to the problem... 6 2

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules In comments dated April 29, 2011, the Solar Alliance (SA) proposed changes to New Jersey s Interconnection Rules (IC Rules). The New Jersey Administrative Code (NJAC) currently defines the screening criteria for three levels of distributed renewable energy sources, in NJAC 14:8-5.4 through 5.6. Solar already receives preferential treatment in the IC Rules. In addition to streamlining processes, the SA proposes these increases in solar generation to be accepted without review: Aggregate solar nameplate capacity up to 23% of the circuit peak load. Currently, the limit is 15% for solar and 10% for other sources. For additional non-exporting solar generation using reverse power relays, accept aggregate nameplate capacity up to 50% of the circuit peak load. When real-time load monitoring is available, accept aggregate nameplate capacity up to 75% of the actual circuit s minimum load between the hours of 10 a.m. and 3 p.m. None of these proposals should be accepted as no-study criteria. It is recommended that circuitlevel monitoring and analysis be considered to maximize renewable energy penetration levels, possibly with per-mw charges to interconnect on advanced circuits. Figure 1 below illustrates two radial circuits which include a variety of renewable energy sources, shown in green. Most of the renewable sources in Figure 1 are photovoltaic (PV), but the circuits may also include combined heat and power (CHP), wind, fuel cells, landfill gas (LFG), and other types not shown. The circuits are segmented by circuit breakers, automatic reclosers, and fuses, shown in red. The circuits also include voltage regulators and switched capacitors, shown in blue. Figure 1 - Segmented Radial Circuits with a Variety of Distributed Generation 3

Figure 1 illustrates two key factors overlooked in the SA proposal: 1. Solar is not the only renewable energy source contemplated or allowed in New Jersey. The other sources follow different time profiles than solar, and changes to the screening levels must not be based on solar time profiles alone. The SA proposal does not account for up to 10% of peak load in non-solar sources that may be connected to the circuit. 2. The IC Rules currently apply screening levels only to the feeder breakers in Figure 1. In fact, the circuits are segmented into switched sections, which may not have uniform distributions of renewable sources. For example, one fused single-phase lateral in Figure 1 has significantly more PV than the other two. Screening should actually be applied segment-bysegment. Basis of 10% or 15% Screening Rules The purpose of a screening rule, on percentage capacity, is to conservatively rule out the possibility of unintentional electrical islanding for more than 2 seconds. Such islands are likely to cause damaging overvoltages and frequency excursions. According to IEEE 1547 and 1547.2, one way to rule out islands is to ensure that distributed generation (DG) is no more than 1/3 of the minimum load in a Local EPS. In terms of Figure 1, this applies to each segment delineated by red switching devices, any of which might open (or melt) to create the island. The 1/3 minimum load criteria comes from a 1987 IEEE paper by Gish, Feero, and Greuel, which found that under lighter loads than that, ferroresonance can sustain islands with induction or synchronous generators. Ferroresonance is a non-linear phenomenon, which is difficult to analyze for each case, but the screening rule is based on both laboratory tests and simulations. One might argue that PV inverters would behave differently than rotating machines, but in the absence of published studies and adequate inverter models, the IEEE 1547 working groups have not contemplated changing the 1/3 minimum load criteria. One might also argue that PV inverters can use the UL 1741 test as a means of islanding detection, but this doesn t help other types of DG that may be connected to the circuit. IEEE 1547 and 1547.2 go on to describe that for some circuits, it may be appropriate to assume the minimum load is ½ of the peak load. But for most electric distribution companies (EDC), the typical circuit minimum load is 35-40% of the circuit peak load. In any case, the SA proposal should state that the safety factor is 3x, not 2x, while the rule-of-thumb ratio of peak to minimum load is still 3:1. In general, 10% would be an appropriate and conservative screening threshold for any type of DG, and the IC Rules already specify 10% for non-solar. By allowing an extra 5% of solar DG, the IC Rules may already be allowing for time coincidence of solar output and load peaks, and relaxing the 3:1 peak to minimum load ratio. Some jurisdictions apply 15% screening thresholds for all types of DG, but those jurisdictions apply the screen to each switched or fused circuit segment. 4

Non-Exporting Generation The SA proposal argues that non-exporting generation, if equipped with reverse power relays, can be safely embedded in the circuit beyond the screening threshold. However, reverse power relays only prevent the local DG from islanding. They are one of several islanding detection methods listed in IEEE 1547 and 1547.2, along with the 1/3 minimum load criteria. The reverse power relays don t prevent other DG on the circuit from islanding. For example, according to the SA proposal, suppose there is 27% non-exporting solar with reverse power relays on the circuit, and another 23% without. The total aggregate solar capacity would be 50% of circuit peak load. During an island condition, the 27% non-exporting solar would not produce reverse power flow, and would stay on line. The other 23% solar DG units actually see 50% aggregate solar on the circuit, and not the intended 23%. The screening criteria would be violated for that first 23% of non-exporting solar that was approved for the circuit. Use of Monitored Load Data The SA proposal suggests that more solar can be accommodated on circuits with historic load data. This is a good idea. In fact, most if not all EDCs have feeder-level load data, typically at 15-minute intervals, monitored at feeder breakers within the substation. However, very few EDCs have such data from reclosers, sectionalizers, and fuses out on the circuit. In terms of Figure 1, this means that minimum loads are not monitored within each segment. That argues against the aggressive upper limit at 75% of monitored minimum load, from 10 a.m. to 3 p.m., which SA proposes. Role of Impact Studies The SA proposal requests guidance and specification on the scope of impact studies, when required. The IC Rules already mention load flow, transient stability, and short-circuit protection. For variable power sources like solar and wind, the following topics are of special interest: 1. Voltage fluctuations, voltage regulation, reactive power control, and the possible increase in numbers of tap changes and capacitor switching operations. 2. 3. Islanding and temporary overvoltages. The solar vendors could help in this area by providing better models and more data on the behavior of their products under islanding and backfeed conditions. The UL 1741 standard currently tests only one device in isolation with matched load, but on actual circuits there are many devices of different size, type, and manufacture. Expansion of IEEE Standard 1547 The SA proposal suggests that the New Jersey Board of Public Utilities (BPU) relax the requirement for strict adherence to IEEE Std. 1547, particularly in regard to active voltage regulation. Under the admittedly long title, IEEE has already begun a standards development project P1547.8 Draft Recommended Practice for Establishing Methods and Procedures that Provide Supplemental Support for Implementation Strategies for Expanded Use of IEEE Standard 1547. This project is about 1.5 years through its 4-year lifetime. The purpose is to allow for high penetration levels and smart grid applications of DG, including but not limited to: 5

1. Active voltage regulation 2. Alternative islanding detection and fault detection methods 3. Monitoring and communications 4. DG data requirements 5. Power quality 6. Aggregate capacity up to 20 MW 7. Optimizing grouped behaviors of DG The standards development process includes semiannual working group meetings, on-line writing group sessions, formal comments, and formal ballots. Representatives from EDCs, vendors, universities, renewable advocates, and consultants all participate. The process should result in a technically sound document, and after final ballot resolution, the BPU could adopt 1547.8 in addition to the base 1547 standard. Accommodating More Solar Generation It is desirable to integrate higher levels of renewable energy on distribution circuits, and make it more compatible with integrated volt/var control (blue devices in Figure 1) and other smart grid applications. In order to do that safely, a holistic view of the circuit should be taken: 1. Real-time load monitoring of each switched segment, at the red locations in Figure 1. 2. Consider time-dependent output profiles of all renewable energy sources actually connected to the circuit. 3. EDCs to provide rapid assembly of up-to-date circuit models to perform impact studies. 4. Vendors to provide adequate models for islanding and overvoltage analysis with multiple DG units connected to the circuit. 5. Possible participation of DG in volt/var control or optimal power dispatch. 6. Allow more DG capacity than the screening thresholds, whenever the circuit parameters and impact study results warrant it. 7. Update the circuit-level impact study as loads change, more DG is added, more smart grid applications are deployed, etc. Some of these items could be relatively expensive, and the cost might be shared among all DG units that are connected to the circuit. Proposed solution to the problem Qado Energy proposes that the New Jersey BPU fund a project that would enable all four NJ Utilities to leverage a centralized multi-agent modeling and simulation platform to accelerate and transform the Interconnection application and study process. We propose that each utility work closely with the platform providers power engineers and software experts in the selection of 12-15 feeders from their coverage area. The selected feeders should be able to be categorized into 5 class types and they should have different characteristics such as; 6

Length Overhead or Underground Load Levels and Types Mix of DG assets Number of assets This classification of feeders will enable the utilities to be able to state they have X percent of feeders with Y characteristics and the corresponding models and behaviors of said classified feeders will provide the utilities and the BPU a firmer basis to set Distributed Generation targets and policy. The 48-60 feeders will be modeled and simulated with the Qado Distribution Grid Analytics platform. The feeder data will all be stored in the IEC DCIM standards format and provided back to each utility. Each feeder analysis will answer the following questions: 1. How much solar can be added to the feeder as is? 2. How can more solar generation be added to the feeder? 3. What are the costs of upgrading the feeder to accommodate more solar? The modeling and simulation of the feeders will also be made available in real time to the utilities and the BPU via a secure website for ongoing review. As the circuits are updated over time their models can be automatically updated and validated providing each utility a fresh baseline to support decision making. This dynamic library of circuit models will enable the utilities to visualize the static and dynamic states of the feeders as well as analyze other key factors. With on-going load data being provided to the platform, all parties will be able to find answers to the broader set of questions posed by the changing distribution grid and called out in the 7 line items defined in the Accommodating More Solar Generation section above. In addition, the on-going use of the platform will enable utilities to automate the analysis of new feeders, creating an every growing library of up to date circuits which will further accelerate the interconnection fulfillment process. This platform approach will help alleviate the expert resource burden and decision bottlenecks being experienced in the Distributed Generation Interconnection process in the State. Just as importantly it will create a standards based modeling, simulation and monitoring application that all utilities will be able to leverage, bringing consistency and repeatability to the interconnection process statewide. This will offer the utilities, developers and BPU a new level of understanding and transparency in the process of setting policy and targets. If the BPU chooses, the platforms multi-agent modeling capabilities may also be extended to model the market impacts of new policies and targets. For example, the platforms library of distribution feeder data could be leveraged to help policy makers model various costs per kw charges for interconnections in order to create a fair and balanced fee structure for all concerned parties. For more information please contact us: information@qadoenergy.com 7