Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur , CIN-U40109MP2001SGC01

Similar documents
MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

MP POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, JABALPUR

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

MP POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, JABALPUR

Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur , CIN-U40109MP2001SGC01

No.07-05/SG-9B-II/4084 Jabalpur, dated:

No.07-05/SG-9B-II/1594 Jabalpur, dated

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

In view of the above list of important grid element & exception list is as below:-

MINUTES OF THE 47 th SLCF MEETING HELD ON

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR

No.07-05/SG-9B-II/ 1179 Jabalpur, dated been uploaded on the website of SLDC and can be downloaded.

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner

Case No. 109 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

Renewable Regulatory Fund (RRF) Mechanism : -

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

STATE LOAD DISPATCH CENTRES (SLDC)

Guidelines for Solar Grid Power Projects

Annex_Tumkur In-principle(Phase-I) 1)Minutes of the meeting held on )In-principle Approval_Tumkur Phase-I

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

The Electric Power System

In-House Paper on the implementation of Single Part Tariff in Power Distribution

Policy & Regulatory Issues : Solar & Wind. Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014

Intra-State Availability Based Tariff (ABT)

Case No. 163 of In the matter of

CASE No. 35 of In the matter of

Before the. Case No. 106 of 2009

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Merger of the generator interconnection processes of Valley Electric and the ISO;

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

Agenda of 11 th System Studies Meeting in NER

Need Assessment Document (NAD) DDUGJY

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

BANGALORE ELECTRICITY SUPPLY COMPANY LIMITED

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

IJRASET 2013: All Rights are Reserved

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Case Nos. 12 & 48 of 2009

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Petition No. 1051, 1054 & 1055 of 2015 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW Date of Order :

TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min

UTTARAKHAND POWER CORPORATION LIMITED

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Enhancing Grid Stability in India

RATE ORDER 2015 UNIFORM ELECTRICITY TRANSMISSION RATES January 08, 2015

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

HARYANA POWER GENERATION CORPORATION LIMITED Regd. Office C-7, Urja Bhawan, Sector-6, Panchkula Corporate Identity Number: U45207HR1997SGC033517

GC108: EU Code: Emergency & Restoration: Black start testing requirement

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

DETAILED NOTICE INVITING TENDER WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED. (A Govt of West Bengal Enterprise)

Department of Market Quality and Renewable Integration November 2016

Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region

Bharat Heavy Electricals Limited (High Pressure Boiler Plant) Tiruchirappalli , TAMIL NADU, INDIA CAPITAL EQUIPMENT / MATERIALS MANAGEMENT

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)

Decision on Merced Irrigation District Transition Agreement

Summer Reliability Assessment Report Electric Distribution Companies Perspective

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

Bharat Heavy Electricals Limited, Electronics Division, Bangalore, India.

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

Operational Opportunities to Minimize Renewables Curtailments

Key DRAFT OPERATING CODE 2 LEGAL TEXT

City of Palo Alto (ID # 6416) City Council Staff Report

Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India

Exemptions currently in force

SAUDAMINI, Plot No.2, Sector-29, Gurgaon, Haryana Powergrid Corporation of India Ltd., SAUDAMINI, Plot No.2, Sector-29, Gurgaon

R.S.USHA CHIEF ENGINEER/ PLANNING & RC. Encl: Report and detailed estimate. To The Chief Engineer/D/Madurai Region

GOVERNMENT OF NCT OF DELHI

Ministry of New and Renewable Energy (Jawaharlal Nehru National Solar Mission) Form B for Project Proposals for

Power Sector Trends: Focus on States

THE ELECTRICAL POWER SECTOR IN THE REPUBLIC OF BULGARIA

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008

Article 2.- The benefits offered by this Agreement to the automotive industries are aimed at:

BACS APPROVED BUREAU SCHEME SUPPORT GUIDELINES

SPP Notification to Construct

POWER DEVELOPMENT DEPARTMENT OF JAMMU AND KASHMIR JANIPUR, JAMMU TEL: FAX: PUBLIC NOTICE

HONOLULU AUTHORITY FOR RAPID TRANSPORTATION CITY AND COUNTY OF HONOLULU ADDENDUM NO. 1 TO THE REQUEST FOR INFORMATION FOR THE

DETAILS OF THE EXPRESSION OF INTEREST(EOI) NO.: PL.G03.EOI

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Asset Category Batteries LPN

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

CASE No. 114 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE

ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT

Implementation procedure for certification and continued airworthiness of Beriev Be-200E and Be-200ES-E

Transcription:

MADHYA PRADESH POWER TRANSMISSION COMPANY LIMITED STATE LOAD DESPATCH CENTRE, NAYAGAON, RAMPUR, JABALPUR Telephone: (0761) 2970089 Fax: (0761) 2664343/2970119 e-mail sldcmpjbp@gmail.com vkbz,l vks : 9001-2008 Corporate office: Madhya Pradesh Power Transmission Co. Ltd., Block No.2, Shakti Bhawan, Rampur, Jabalpur 482008, CIN-U40109MP2001SGC01 No.07-05/SG-9B-II/110 ISO: 9001-2008 Jabalpur, dated:13.04.2017 To As per distribution list Sub: Minutes of 56 th meeting of Operation and Coordination Committee of MP. The Minutes of 56 th meeting of the Operation and Coordination Committee of MP was held on 8 th March 2017 at Hotel Kalchuri, South Civil Line, Jabalpur has been uploaded on the website of SLDC www.sldcmpindia.com and can be downloaded. (K.K.Parbhakar) Memebr Secretary OCC SLDC, MPPTCL, Jabalpur

Distribution List 1. The Chief Engineer (Works), MP Power Transmission Co. Limited, Shakti Bhawan, Jabalpur, emailceehtmi@yahoo.com. 2. The Chief Engineer (T&C), MP Power Transmission Co. Limited, Jabalpur. Fax No- 0761-2665593, 2702710 Email- cetandc@gmail.com 3. The Chief Engineer (Transmission-East Zone), MP Power Transmission Co. Limited, Shakti Bhawan, Jabalpur. Email- sk.gaikwad@mptransco.nic.in. 4. The Chief Engineer (Transmission-West Zone), MP Power Transmission Co. Limited, Indore. 5. The Chief Engineer (Transmission-Central Zone), MP Power Transmission Co. Limited, Bijlee Nagar, Govindpura, Bhopal, email- setncbpl@gmail.com. 6. The Chief Engineer (Plg & Des), MP Power Transmission Co. Limited, Jabalpur, Fax No- 0761-2660908 Email- ceps321@yahoo.com 7. The Chief Engineer (Procurement.), MP Power Transmission Co. Limited, Jabalpur,.Fax No- 0761-2660908 Email substation_vi@yahoo.com 8. The Executive Director (O & M:Gen), MP Power Generating Company Limited, Jabalpur. Fax No- 0761-2664749, Email- gcc.mppgcl@gmail.com, Email- edomg_mpeb@rediffmail.com 9. The Chief Engineer (O&M:Hydel), MP Power Generating Co. Ltd, Jabalpur, Fax No-0761-2664749. 10. The General Manager(PM), MPPMCL, Jabalpur Email gm_pm@mptradeco.com controlroom.tradeco@gmail.com 11. The Superintending Engineer (GCC), MPPGCL, Jabalpur Email segcc.mppgcl@gmail.com gcc.mppgcl@gmail.com. 12. The General Manger (DCC-EZ), DISCOM Control Centre, MP Poorva Kshetra Vidyut Vitaran Co.Limited, Jabalpur, Fax No- 0761-2668503, Email cmdez_ld@yahoo.co.in. 13. The Dy. General Manager (DCC CZ), DISCOM Control Centre, MP Madhya Kshetra Vidyut Vitaran Co. Limited, Bhopal, Fax No-0755-2580611,Email- plm.mpcz@gmail.com. 14. The Executive Engineer (DCC-WZ), DISCOM Control Centre, MP Paschim Kshetra Vidyut Vitaran Co. Limited, Near Polo Ground, Jail Road, Indore, Fax No- 0731-2421554, Email- dccindore@gmail.com. 15. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Indore, Fax No- 0731-2874515, Email eesubldcind@yahoo.com. 16. The Executive Engineer, Sub Load Despatch Centre, MPPTCL, Bhopal, Fax No- 0755-2885220, Email aldc_bpl@yahoo.co.in 17. The General Manger(RO), MPPMCL, In front of Bhojpur Club, E-4, Arera Colony,Bhopal, Fax No-0755-2423046, Email-Rajeev_keskar@rediffmail.com 18. The Chief Engineer (PM&C), Narmada Hydroelectric Development Corpn. Ltd, NHDC Parisar, Shamla Hills, Bhopal 462013., Fax No- 0755-4030130,Email vinodnhdc@rediffmail.com 19. The Chief Electrical Distribution Engineer, West Central Railway (WCR), General Manager s Office, Electrical Department, Jabalpur-482001 (MP), Fax: 0761-2627629, Email- cede@wcr.gov.in, dyceetrdwcr@gmail.com, M-9752415312, Mr.Satyendra Kumar (Dy.CE), Mob.9752415301 (CEDE, WCR). 20. The General Manager, Indira Sagar Power Station, NHDC Office complex, PO : Narmada Nagar, Distt : Khandwa (MP) 450 119, Fax No- 07323-284080, Email nhdc-isp@rediffmail.com 21. The General Manager, Omkareshwar Power Station, Prashsnik Bhawan, Urja Vihar, Sidhwarkut, Distt : Khandwa (MP) 450 554, FaxNo-07280-271703, Email- omkareshwar.nhdc@gmail.com 22. The Director (Projects), BLA Power Limited, At : Niwari, PO: Khorsipan, Tah : Gadarwara, Distt ; Narsinghpur 487 551, Fax No. 07791-243667 / 243669, Email manish@bla.co.in 23. The Sr. Vice President, Jaiprakash Power Ventures Ltd., Village Sirchopi Subpost Office-Agasod, Post Office-Bina- 470113 Distt- Sagar, Fax No. 07580-277200, Email jptpp.switchyard@jalindia.com 24. The Chief Executive Officer, Kalpataru Satpura Transco Pvt. Ltd., Satpura Colony, Betul Road, Old Itarsi, Distt. Hoshangabad, Email cbhandari@kalpatarupower.com 25. M/s Ujaas Energy Ltd. 701, NRK Business park, Vijay Nagar Sqaure, Indore 452010, Email id :- solar@ujaas.com 26. M/s Suzlon Global Services Ltd., 1090, Scheme no. 114, Park-2, Ring Road, Universal Hospital Row, Email- deepesh.sankwa@suzlon.com, Indore 452010, Badree.hirve@suzlon.com

MINUTES OF 56 TH MEETING OF OPERATION & COORDINATION COMMITTEE OF MP HELD AT HOTEL KALCHURI, SOUTH CIVIL LINE, JABALPUR AT 11:00 A.M. ON 08 th MARCH 2017. The 56 th meeting of Operation & Coordination Committee of MP was held on 08 th March 2017 at 11:00 AM at hotel Kalchuri, Jabalpur under the Chairmanship of Shri P.A.R. Bende C.E.(SLDC) & Chairman OCC. The list of participants is enclosed at Annexure -1.0. Shri Vijay Kumar Tripathi Dy. Manager on behalf of NHDC, the host of 56 th OCCM welcomed S/Shri P.A.R. Bende C.E.(SLDC) & Chairman OCC, K.K.Parbhakar Member Secretary OCC & Addl. C.E.(SLDC), S. Sanyal GM, NHDC and S Pagare, C.E, OSP with bouquet of flowers followed by opening ceremony of 56 th OCCM of M.P by lighting of lamp (Deep Prajavalan). He also welcomed all the guests and participants. Further, he requested Shri S. Sanyal GM, NHDC, Bhopal to address the gathering. Shri S.Sanyal welcomed Shri P.A.R. Bende C.E.(SLDC) & Chairman OCC, Shri K.K.Parbhakar Member Secretary, OCC and all the guest & participants on behalf of the NHDC. Thereafter he apprised the participants about achievements of NHDC. He also informed the committee that in 2014-2015 CAG performed the audit of all hydel power stations and NHDC was considered as one of the best maintained Hydel Power station (PSU). He further stated that NHDC figures one of the best public sector having less than 1% outage in last five years. Moreover, it is also playing vital role in generating clean energy and serving the nation. Further he thanked Shri P.A.R. Bende C.E.(SLDC) & Chairman OCC for giving an opportunity to NHDC for hosting the 56 th OCCM of M.P. Thereafter Shri Vijay Kumar Tripathi Dy. Manager, NHDC requested Shri P.A.R. Bende C.E.(SLDC) & Chairman OCC to address the gathering and to take up the proceedings of meeting. Shri P.A.R.Bende C.E.(SLDC) & Chairman OCC welcomed all the participants present for attending the 56 th OCCM of M.P. He stated that first OCCM of M.P was held in the year 2009 and this forum has resolved all matters/disputes amicably related with grid operation and other related matters. He further informed that there are 9 HPS in MP and Black Start Mock Drills have been conducted at 7 HPS successfully. M.P is the first state which has conducted highest no. of Mock Drills in India (i.e., 19 Numbers at various HPS of MP). Black Start Mock Drill of Manikheda and Rajghat Hydel Power Stations is proposed to be conducted in Rainy Season. The operational staff of Gandhisagar, Bargi, Pench and ISP have got expertize in conducting Black Start Mock Drill. In future, Black Start Mock Drill of these Hydel Power Stations shall be conducted by the Power House staff and SLDC will not depute any engineer to these Power Stations for this purpose. Chairman OCC stated that Percentage of time frequency remained within the permissible range of 49.9-50.5Hz was 69.58% for the month of Dec 2016 and 70.46% for the month of Jan 2017. The average frequency for the month of Dec 2016 & Jan 2017 was 49.99 Hz. and 50.00 Hz respectively. The percentage of time frequency above 50.05 Hz. for the month of Jan 2016 is slightly larger 23.35 % in comparison to 19.38 % in the month of December 2016. The percentage of time frequency below 49.9 Hz was 6.19% for the month of Dec 2016 and was quite higher 11.04 % for the month of Jan 2017. Chairman OCC also stated that high frequency period increased and recorded above 19 % in the month of Dec 2016 Jan 2017. The percentage of time Frequency above 50.05 Hz has increased considerably/unevenly due to the increased injection by wind generators, which is unpredictable. Thereafter Chairman OCC requested Member Secretary, OOC to take up the agenda points. Minutes of 56th OCCM of MP 1

ITEM NO. 1 : CONFIRMATION OF MINUTES : Member Secretary OCC informed the committee that the Minutes of 55 th meeting of Operation & Coordination Committee of MP held on 22 nd December, 2016 at Hotel Vijan Mahal, Tilhari, Mandla Road, Jabalpur were forwarded to the committee members vide No. 07-05/SG-9B-II/3871 dated 27.01.2017. No comments have been received to SLDC, committee confirms the minutes. ITEM NO. 2 : 2017. REVIEW OF SYSTEM OPERATION DURING THE MONTHS Dec 2016 TO JAN 2.1 Frequency Particulars: Member Secretary OCC informed the committee that during January 2017 the system frequency was below 49.9 Hz for 6.19% of time against 11.04% of time during Dec 2016. The system frequency was above 50.05 Hz for 23.35% of time during Jan 2017 against 19.38% of time during Dec 2016. The system frequency was within the IEGC range of 49.9-50.05 Hz for 70.46% of the time during Jan 2017 against 69.58% of time during Dec 2016. The average monthly frequency was 49.99 Hz during month of Dec 2016 and 50.00 Hz during month of Jan 2017. The system frequency did not touch 49.20 Hz during the above period. The detailed frequency particulars for the month of Dec 2016 and Jan 2017 are enclosed at Annexure-2.1. The brief detail of frequency profile is given here under: Month Average Minimum Maximum Instantaneous Instantaneous frequency integrated integrated Minimum Maximum frequency over frequency over Frequency Frequency an hour an hour Dec 2016 49.99 Hz 49.82 Hz 50.11 Hz 49.67 Hz 50.31 Hz Jan 2017 50.00 Hz 49.88 Hz 50.21 Hz 49.71 Hz 50.33 Hz 2.2 Operational Matters 2.2.1 Operational Discipline : Member Secretary OCC informed the committee that the system operated in terms of frequency profile for the months Dec 2016 and Jan 2017 is as given below for discussion by the committee : 2.2.2 Month % of time Frequency Below 49.9 Hz % of time Frequency above 50. 05 Hz % of time frequency within the permissible range of 49.9-50.05 Hz Average monthly frequency No. of times frequency dipped below 49.2 Hz Dec 2016 11.04 % 19.38 % 69.58 % 49.99 Hz 0 Jan 2017 6.19 % 23.35 % 70.46 % 50.00 Hz 0 2.3.1 Voltage Profile: Member Secretary OCC informed the committee that during the months Dec 2016 and Jan 2017, the maximum and minimum voltage as recorded at following important 400 KV s/s in MP Grid- Minutes of 56th OCCM of MP 2

Dec 2016 Jan 2017 Max. Voltage Min. Voltage Max. Voltage Min. Voltage Name of observed Observed Observed Observed Sr 400 KV Volt Voltag No Substation Voltage ag Voltage Date e Date Date Date KV e KV KV KV 1 Indore 423 16.12.16 393 09.12.16 424 19.01.17 394 13.01.17 2 Itarsi 418 14.12.16 389 08.12.16 420 19.01.17 389 09.01.17 3 Bina 419 13.12.16 395 08.12.16 420 19.01.17 393 09.01.17 4 Gwalior 418 25.12.16 389 17.12.16 420 30.01.17 387 09.01.17 5 Nagda 425 25.12.16 397 24.12.16 427 13.01.17 398 16.01.17 6 Satpura 426 29.12.16 404 08.12.16 427 26.01.17 403 16.01.17 7 Birsinghpur 427 27.12.16 408 30.12.16 430 07.01.17 407 09.01.17 8 ISP 428 16.12.16 404 09.12.16 429 19.01.17 407 16.01.17 2.3.2 Status of Capacitor Banks in sub-transmission system: Member Secretary OCC informed the committee that the updated information of the status of capacitor banks in sub-transmission system as on 31st Jan 2017 as submitted by DISCOMs is detailed below: DISCOM Capacitor bank Capacitor Capacitor Req Requirem Capacitor Balance installed in Banks bank installed Uirem ent against banks capacitor good condition healthy but but defective & ent of non- already banks to be (No) not in service are repairable Repair repairable covered covered in due to control (No) Again capacitor under ADB Other bank ckt problem St s T-V schemes Each (No) Unit 600 1200 1500 600 120 0 1500 600 1200 1500 No of 600 120 0 600 1200 600 1500 KV KVA KVA KVA KVA KVA A KVA KVA KVA 100 KVA KVA KVA KVA KVA KVA R R R R R R R R R KVAR R R R R R R Units Require d EZ 404 145 32 27 10 0 18 4 0 29 - - - - - 77 CZ 5 687 686 0 0 0 0 0 0 0 0 0 0 588 0 0 WZ 630 542 535 19 15 04 17 20 85 228 2 10 - - - 62 2.3.3 Status of Shunt Capacitor Banks installed at various EHV Transmission Substation: Member Secretary OCC informed the committee that the updated information of the status of installed capacitor banks (in MVAR) in EHV transmission system as on 31.01.2017 as submitted by MPPTCL is given below:- Minutes of 56th OCCM of MP 3

Voltage Capacitor bank Capacity Class installed as on Added after 30.11.16 (MVAR) Last OCC Meeting (MVAR) Capacitor banks already covered under ADB T-V Total capacity as on 31.01.2017 Capacitor Bank Installed but defective & are not repairable (No & MVAR) 220 KV 100.00 MVAR 0.00 100.00 MVAR All in Service 132 KV 1205.00 MVAR 33.00 1238.00 MVAR 33 KV 4456.50 MVAR 24.00 4480.50 MVAR Total 5761.50 MVAR 57.00 5818.50 MVAR 2.3.4 Status of completion of ongoing Transmission Schemes being executed by MPPTCL: Member Secretary OCC informed the committee that the various ongoing Transmission Schemes completed during the current financial year 2016-2017 (up to Jan. 2017) and plan for completion of various ongoing Transmission Schemes for the Year 2016-2017 is enclosed as Annexure 2.3.4(i) and 2.3.4(ii). 2.3.5 U/F and df/dt Relay Operation (i) (ii) U/F and df/dt Relay Operation: Member Secretary OCC informed the committee that Frequency did not touch 49.20 Hz during Dec 2016 and Jan 2017. There was no df/dt operation during the same period. Defective u/f, df/dt relays: Member Secretary OCC informed the committee that MPPTCL has informed that all the df/dt relays are in good/healthy working condition and where the U/F relays are not available, the numerical relays programmed for under frequency operation. 2.4 Power Cuts / Load restrictions/differential Load Shedding by DISCOMS & group allocation to 33 KV feeders : (i) Member Secretary OCC informed the committee that details of DISCOM wise Power supply given to various domestic categories during the period Dec 2016 and Jan 2017 is enclosed at Annexure 2.4(i). (iii) Group Allocation to Newly Commissioned existing EHV substations:- Member Secretary OCC informed the committee that the region wise list of 33 KV feeders emanating from various newly commissioned/existing EHV substations for which groups have not been allocated is given in Annexure 2.4 (ii). The DISCOM wise details of pending group allocation to 33 KV feeders is given below:- SN DISCOM Region No of 33 KV feeders for which groups to be allocated 01 Jabalpur 15 02 EAST Sagar 00 03 Rewa 11 04 Total 26 05 Indore 16 Minutes of 56th OCCM of MP 4

06 WEST Ujjain 06 07 Total 22 08 Bhopal 07 09 CENTRAL Gwalior 07 10 Total 14 TOTAL Grand Total 62 Representative from East Discom informed the committee that group have been allocated for all 26 No. feeders. Representative from West Discom informed the committee that only one no. feeder s group allocation has been done and correspondence for the remaining 21 no. feeders with field nodal offices is being done. Chairman OCC advised the representative of West Discom for completion of group allocation to the remaining 21 no. of feeders at the earliest. Representative from Central Discom informed the committee that Groups have been allocated to 2 No. feeders in Bhopal Region and matter has been taken up with concerned authorities of Discom for group allocation to remaining 12 no. of feeders. ITEM NO. 3 : OPERATIONAL PLANNNING: 3.1 Generating Units under planned outage and proposed maintenance programme : Member Secretary OCC informed the committee that the annual maintenance /outages of thermal generating units of MPPGCL during March.2017 to April 17 is Nil as intimated by ED(O&M:Gen.), MPPGCL, Jabalpur. 3.2 Proposed shutdown programme of Transmission lines / Transformers: Member Secretary OCC informed the committee that the proposed shutdown of transmission elements for the period 01.03.2017 to 30.04.2017 submitted by MPPTCL is enclosed as Annexure-3.2. 3.3 Long Outages of transmission elements and protections : Member Secretary OCC informed the committee that the status submitted by MPPGCL /MPPTCL are given below:- S. No Line / Transformer etc. under long Outage 1. 220 KV Bus bar protection scheme at SGTPS Birsinghpur 2. Main Breaker of 400 KV Nagda-Rajgarh-II. Outage date 07.09.20 16 Reason Due to mal-operation 220 KV Bus Bar Protection kept out. 23.07.15 Y-phase CT burst/ BKR Problem Response from Utility The 220 KV Bus Bar Protection Scheme of M/s GE India, Bangalore has been put into service on 09.02.2017 as intimated by MPPGCL along with LBB. Chairman OCC stated that consent/permission of SLDC should be obtained before putting out protection. 400 KV Rajgarh II is charged from 400 KV Main Bus-I, for ensuring connectivity with Main Bus-II. The work is in progress with work of providing Reactor Minutes of 56th OCCM of MP 5

3. 315 MVA, 400/220 kv ICT-I at 400 kv S/s Bina 4. 315 MVA, 400/220 KV ICT at 400 KV S/s, Julwaniya. 5. 315 MVA, 400/220 KV X mer II (TELK make) Main Breaker at 400 KV S/s Katni 6. 12.5 MVA, 132/66/33 KV X mer CGL make Sr. No. 23615 at 132 KV S/s Pichhore 15.10.15 Differential Due to Buchholtz relay alarm. on ISP Bay 400 KV Rajgarh-I is shifted in diameter of 315 MVA ICT-IV, which has facility to connect on Main Bus-I and Main Bus-II. This will impact when outage of Bus-II occurs in outage of Nagda- Rajgarh II circuit. Representative from MPPTCL informed the committee that the panel has been received and the main breaker will be taken in service by end of March 2017. The transformer bank is out of circuit from 02.08.2015. 2 No. 105 MVA Units of these banks have failed. The 315 MVA X mer Sr. No. 6005210 is out of circuit from 15.10.2015. The Transformer has been shifted from Bina to M/s BHEL works for repairs. MPPTCL representative informed the committee that the testing and inspection of X mer at M/s BHEL has been completed and DI has been issued. He also informed the committee that the commissioning of X mer is expected by April 2017. 05.01.2016 The ICT has been removed for installation at Bina 400 KV S/s and commissioned there at 16:49 Hrs. on dtd. 05.01.2016. New Transformer of 315 MVA, 400/220 KV EMCO make has been commissioned on dated 14.02.2017 as intimated by MPPTCL. 03.11.2015 X mer commissioned through bus coupler breaker since commissioning. 19.05.2016 Transformer failed on 19.05.2016 as intimated by T&C, MPPTCL. It has come to notice that the transformer-ii has been connected through bus coupler breaker both side (400 KV & 220 KV) and there is no main breaker for this 315 MVA X mer-ii. In 54 th OCCM MPPTCL informed the committee work of 220 KV Ckt breaker has been completed and 400 KV Ckt. Bkr. work is under progress. MPPTCL informed the committee that the work will be completed by end of April 2017. The load is manageable through (1x20 + 1x40) MVA X mers in running condition at S/s Pichhore. Hence replacement of failed X mer is not required as intimated by MPPTCL. In 52 nd 53 rd 54 th & 55 th OCCM, Chairman OCC requested MPPTCL, P&D to submit the letter for removal of transformer from Minutes of 56th OCCM of MP 6

7. 12.5MVA, BBL Make (Sr. No.-1428/3) at 132 KV S/s Chapda. 8. 40 MVA, ECE Make X mer (Sr. N0.-86020) at 132 KV S/s Shajapur. 9. 50 MVAR Line Reactor of 400 KV Katni Damoh Ckt at 400 KV S/s Damoh (PGCIL). 10. 160 MVA, 220/132 KV BHEL X mer at 220 KV S/s Jabalpur 11. 63MVAR 400KV Bus reactor-ii at STPS, Sarni 12. 160 MVA, 220/132 KV NGEF X-mer Sr.No. 6800000075 at 220 KV S/s Neemuch Asset. Chairman OCC stated that T&C and P&D will perform load grow / load assessment study prior to decommissioning and intimate to SLDC. Not intimated X mer failed It has been proposed to withdraw the X mer from system as intimated by MPPTCL. Representative from T&C informed the committee that correspondence is being done with P&D, MPPTCL for load grow study and decommissioning of the 14.06.2016 Tripped in differential indication. Not intimated. Tan- of the bushing was not correct. transformer. X mer is under investigation and testing. Internal Inspection of X mer shall be done as soon as monsoon permits. Another 40 MVA BBL make Transformer has been commissioned on dated 22.12.2016 as intimated by MPPTCL. 50 MVAR line reactor put into service at 08:38 Hrs. on 01.02.2017 as intimated by MPPTCL. 30.09.2016 Not intimated Representative from MPPTCL informed the committee that X mer has to be sent to M/s BHEL for detailed inspection. 06.09.2016 Not intimated The Bus-reactor is ready. However its 400 KV SF6 gas Circuit Breaker has got irregularities in closing & tripping timings. Further, tender for servicing with replacement of required spares, testing & commissioning work of its GCB, has been opened and under process, as intimated by MPPGCL. Representative from MPPGCL informed the committee that the reactor will be taken in service by 21.11.2016 Tripped on Buchholtz and PRV indications. June 2017. After replacement of broken OLTC drive rod, 160 MVA NGEF X-mer charged on dtd. 03.02.2017, as intimated by MPPTCL. ITEM NO. 4 : OPERATIONAL STATISTICS FOR THE MONTH OF DEC 2016 AND JAN 2017: Member Secretary OCC informed the committee that the details of actual generation, Schedule from Central Sector, demand etc. are given in the following Annexures: Annex. 4.1 Annex. 4.2 Annex. 4.3 Annex. 4.4 Unit wise actual Generation of MPPGCL thermal Units and station wise Generation of MPPGCL & NHDC Hydel Units. Power Supply Position. Hourly Average of Availability and Demand. Hourly average schedule Vs Drawal of DISCOMs. Minutes of 56th OCCM of MP 7

ITEM NO. 5.0 : SYSTEM DISTURBANCE IN MP DURING DEC 2016 AND JAN 2017 : Member Secretary OCC informed the committee that there was no major grid disturbance in MP during Dec 2016 and Jan 2017. Moreover, the Grid Disturbances and Grid Incidents in MP during these months are given in Annexure 5.0. ITEM NO. 6.0 : IMPORTANT OPERATIONAL ISSUES:- 6.1 STATUS OF COMPLETION OF ONGOING SCHEMES FOR COMMISSIONING OF REACTORS / TRANSMISSION ELEMENTS:- Member Secretary OCC informed the committee that the present status regarding schedule and commissioning of reactors / transmission elements is as below:- S.No. 400 KV S/s Size MVAR Implementing Agency Expected Date of Commissioning as intimated in last OCC 1. Bus Reactor : ISP 2. Line reactor at Nagda-ISP line at Nagda end 3. Line Reactor on 400 kv Satpura ISP line at STPS 4. Bus Reactor at SSTPS 125 MVAR NHDC Representative from NHDC informed the committee that delivery of all equipment is expected by June 2017. Thereafter erection & commissioning work will be carried out. It is expected that the reactor will be in service by July 2017 as informed by NHDC. 50 MVAR MPPTCL 50 MVAR Line Reactor has been charged on 31.03.2017. 50 MVAR MPPGCL 125 MVAR MPPGCL Representative from MPPGCL informed the committee that procurement of line reactor is under tendering stage and expected to be commissioned by Oct-2017. Work will be carried out under PSDF as intimated by MPPGCL. Representative from MPPGCL informed the committee that purchase tender will be opened on 31.03.2017 and the commissioning of reactor is expected by Oct-2017. 6.2 Provision of synchronization facility at EHV sub-stations of MPPTCL:- Member Secretary OCC informed the committee that as per Grid Code, the synchronization facility should be available at all the Power Stations, 400 KV Sub-stations and 220 KV Sub-stations and 132 KV sub-stations in the path of black start. In last OCC meeting MPPTCL representative informed the committee that order for 69 no. synchronization trolleys has been placed and 1 no. synchronization trolley has been delivered for checking and testing purpose at 220KV S/S Barwaha. As desired by MPPTCL, SLDC has already forwarded list of 27 Nos EHV substations on 04.01.2017 where synchronization trolleys are to be installed on priority. This list enclosed all the 400 KV substations and 220 KV /132 KV substations which falls on the routes of black start. The status of installation and commissioning of synchronization trolleys at the 27 EHV substations has not been intimated by the MPPTCL till this date. Minutes of 56th OCCM of MP 8

Representative from MPPTCL informed the committee that for installation of synchronization trolley at 132 KV sub-stations which falls on black start path requires installation of line CVT. Further he also informed the committee that the inspection has been offered for synchronization trolley. Chairman OCC requested MPPTCL to install line CVT on the lines/substations which falls on black start path at the earliest. Further he also stated that the line CVT on 132 KV Pench-Seoni, 132 KV Seoni Lakhnadon Ckt, 132 KV Bargi Lakhnadon Ckt and 132 KV Bargi Jabalpur Ckt I&II shall be installed on priority basis so that synchronization facility is made available at Seoni, Lakhnadon or Jabalpur S/s for conducting Black Start Mock Drill. 6.3 Ten Daily Reservoir operation table of MPPGCL HPS:- Member Secretary OCC informed the committee that in the meeting held in Regional Office of MPPMCL at Bhopal on 24.09.2016 to discuss availability from Sardar Sarovar Project, ISP & OPS and State Hydel Plants for Rabi season, MPPGCL had agreed to obtain ten daily reservoir operation table from WRD and NVDA for operation of their hydro generators. In last 54 th & 55 th OCCM, request has been made to MPPGCL for furnishing the same to SLDC within a week, but it has not yet been provided by MPPGCL. It is requested that MPPGCL in coordination with NVDA and WRD to, prepare the ten daily reservoir operation table of all their hydel power stations and submit to SLDC at the earliest for optimum utilisation of available water in the reservoirs during the summer season. Member Secretary informed the Committee that Ten daily Reservoir Operation Table of Tons and Bargi have been provided by MPPGCL. He also requested the representative of MPPGCL to submit the Ten Daily Reservoir Operation Table of remaining HPSs at the earliest. 6.4 Operation of LBB and Bus Bar Protection and delay in restoration at ISP:- Member Secretary OCC informed the committee that at 11.18 Hrs on 20.02.2017, while stopping machine no. 7 of ISP, Local Breaker Backup protection operated of Unit No. 7 resulting in operation of 400 KV Main Bus-II Bus Bar protection. 400 KV ISP-Indore-II and 400 KV STPS-ISP lines, which were on Main Bus-II also tripped. The restoration of 400 KV ISP-Indore-II and 400 KV STPS-ISP lines was done at 12.35 hrs and 12.25 hrs respectively. ISP did not intimate the reason for delay in charging of these important 400 KV lines. It is indicate that 400 KV ISP-Indore-II and 400 KV STPS-ISP lines form important corridor for transfer of power from Central to West MP and outage of this critical corridor for such a long period without any justified reason is not desirable for safe, secure and reliable operation of the State Grid. The ISP is requested to avoid unwarranted delay in charging transmission elements in future. NHDC representative from informed the committee that the above tripping occurred as the breaker of Unit #7 was stuck. He also confirmed the committee that in future the instance of delayed reporting will be taken care of. 6.5 Non-compliance of SLDC instructions by Gandhisagar HPS Member Secretary OCC informed the committee that on 09.02.2017, Wind Power generation in MP was suddenly increased to 1000 MW from 140 MW during the evening peak hours. SLDC had to accommodate such a huge additional power in the system by maintaining the grid parameter within operational limits. As Minutes of 56th OCCM of MP 9

emergency measures hydro generation is to be curtailed immediately which is the only possible solution for keeping the grid security intact till the effect of backing down / surrender of power in thermal generating stations is obtained. Gandhisagar Hydel Power Station was instructed to stop three machines for which code were issued at 20:25 Hrs through GCC. The shift officials of Gandhisagar HPS were reluctant to stop the machines even during emergency conditions despite SLDC request to act immediately. After repeated persuasion machines were not stopped by Operation staff Gandhisagar. Finally the matter was brought in the notice of CE (O&M:Hydel) and after his intervention, the machines were stopped at 21:01 Hrs, 21:05 Hrs & 21:10 Hrs. This act of the shift officials of Gandhisagar is violation of Clause 3.83 of MPEGC, Clause 5.1 (d) of IEGC and Sec. 29 of EA-2003 i.e. non-compliance of SLDC instructions. It is requested that the shift officials of Hydel Power Stations may be instructed to follow the instructions of SLDC promptly in future. Member Secretary OCC requested MPPGCL to issue instructions to Gandhisagar officials to comply with SLDC instruction for safe & secure grid operation.. 6.6 Scheduling of DVC and Inter-state IPP Power :- Member Secretary OCC informed the committee that scheduling of DVC and Interstate IPP is being done by the WRLDC. Under day ahead scheduling these entities furnished entitlement of MP to SLDC and these entitlements are forwarded to MPPMCL Control Room for preparing requisitions. The requisition received from MPPMCL again forwarded to DVC / IPPs for obtaining their consent to the power requisitioned by the MPPMCL. On receiving the correspondence from DVC / IPPs the same is again forwarded to MPPMCL. Finally, MPPMCL again gives comments (agreed/ Not Agreed) on the revised quantum of power in 15 minutes time block agreed by the generator. Now SLDC punched the final requisition submitted by MPPMCL in WRLDC web based Scheduling Portal and forwarded to the concern. Similar procedure is also being adopted during the real time scheduling. This procedure of scheduling is not mandated in IEGC / MPEGC / BSC 2015 and also consumes the valuable time of system operators of SLDC which is otherwise required for smooth system operation. Also during real time scheduling such procedural delay is causing on scheduling of power from designated time block. MPPMCL in future submit requisition to SLDC only after obtaining the consent of DVC / Interstate IPPs and SLDC shall not make communication with these entities for obtaining consent on the requisition furnished by the MPPMCL and the same requisition shall be treated as final and punched on the web based scheduling portal of WRLDC. Representative of MPPMCL has agreed to the proposed procedure of SLDC for scheduling of DVC, Jaypee Nigrie and Jhabua Thermal Power Stations. Chairman OCC requested MPPMCL to obtain the consent of IPPs for revision in requisition before furnishing their revised requisition to SLDC. It would ensure revision of schedule from the Minutes of 56th OCCM of MP 10

designated time block. Further, he also stated that if any commercial dispute/matter arises regarding scheduling of DVC the sole responsibility will lie on MPPMCL. 6.7 Questionnaire on Hydro Generating Stations :- Member Secretary OCC informed the committee that as per decision taken in 18 th meeting of Forum of Load Despatcher (FOLD) held on 21 st November 2016, working Group on Hydro for studying the various aspects of hydro Stations may be formed. NLDC has furnished a a questionnaire on Hydro generating stations which is to be filled and submitted in respect of each hydro generating station to NLDC, New Delhi within a week time on following email Id, SLDC vide letter no. 07-05/RPC-28A/4187 dtd 21.02.2017 (alongwith Questionnaire enclosed as Annexure-6.7), requested MPPGCL, ISP, OSP and NHDC to submit the reply directly to NLDC under intimation to this office and WRLDC Representative from MPPGCL and ISP/OSP/NHDC informed the committee that the desired information will be provided soon. 6.8 : MONITORING OF SCHEMES FUNDED FROM PSDF :- Chairman OCC informed the committee that it was decided in the 6th meeting of NPC held on 19th December 2016 at Bengaluru, that all the RPCs in the monthly OCC meetings may follow up with the utilities to expedite the completion of schemes by giving due priority. The implementation of most of the schemes is based on the recommendation of the enquiry committee on grid disturbance of July 2012 headed by Chairperson, CEA. Therefore timely implementation of these schemes would enhance the grid security and reliability. Accordingly the details of grant sanctioned from PSDF for the schemes of MP are enclosed at Annexure- 6.8A. The status of implementation of above schemes (physical as well as financial progress) may please be reviewed and the entities are requested to expedite implementation of the schemes. The utilities were advised to furnish the information in the format enclosed at Annexure 6.8B by first week of every month on regular basis to Member Convener, PSDF project monitoring group (AGM, NLDC, POSOCO) with a copy to NPC, WRPC division and SLDC. The matter was discussed in the meeting and Chairman requested MPPGCL & MPPTCL for informing timely as per mentioned above to all the concerned authority under intimation to SLDC. 6.9 MAPPING OF FEEDERS WIRED UNDER AUFLS TO SLDC SCADA :-. Chairman OCC informed the committee that in the 4th, 5th & 6th NPC meetings, mapping of the Feeders / Lines covered under AUFLS on SCADA systems of SLDC's/RLDC's was discussed. NPC have desired that monitoring of the feeders / loads under the AUFLS shall be done at SLDC's / RLDC's, so as to ascertain that the desired results are ensured during the events, frequency falling below the AUFLS frequency settings. In the 6th NPC meeting it was therefore desired that all the loads/feeders wired under the AUFLS is monitored in Western Region also and the progress be submitted to NPC. A list of feeders/loads implemented under AUFLS in WR was compiled at WRPC in 2014 and same is uploaded in website of WRPC under news section and PCM Minutes section. MPPTCL is requested to initiate the process of mapping these feeders in the SCADA System so that same shall be made available to WRLDC. MPPTCL is requested to update the list of feeders under AUFLS and intimate the feeders which have Minutes of 56th OCCM of MP 11

already been mapped in their SCADA System and are monitored on line by them. Also constraints, if any, faced in mapping AUFLS feeders in their SCADA System may be intimated. \ Chairman OCC requested MPPTCL to send above desired information to SLDC at the earliest. 6.10 REPORTING OF FLASH REPORT, DR and EL FOR 400KV, Interstate Transmission Elements & Detailed Tripping Report:- Chairman OCC informed the committee that as per the provisions of Regulation 5.2 (r) of CERC (Indian Electricity Grid Code) Regulations 2010 and Regulation of 5(9) of CERC (Indian Electricity Grid Code) (First Amendment) Regulations, 2012 all the Regional Entities of the Region shall furnish the tripping details including DR & SEL output to RLDC with in 24 hrs of the event for analysis and identify the real time measures required in future to ensure secured grid operation. The flash report is also required to be furnished to SLDC within an hour of tripping. It is observed that FLASH REPORT, DR & EL of station is not made available during tripping of transmission grid element by the State Grid Entities and the flash report is also sent after repeated pursuation. All intra-state entities are requested to submit the FIR, DR & EL of station during tripping of transmission grid elements. Chairman OCC requested all the concerned entities to instruct the field staff to comply with the above regulations for safe & secure grid operation and provide details/reports within stipulated time. 6.11 Status of ADMS system :- Chairman OCC informed the committee that the ADMS system did not operate during over-drawal by MP on 06th and 7th February during morning hours. In this reference it is to bring to notice that vide various correspondence, SLDC had given its clearance for activation of ADMS on completion of some formalities like modification of ADMs logic, completion of ADMS Reports, round the clock monitoring of control centers from where ADMS is operating, Proper configuration of groups and feeders information as provided by DISCOMs and arrangement for modification of group/feeder information in case of change, Availability of infrastructure at DCC for monitoring of ADMS activities, Familiarization of DCC /SLDC control room officers for using ADMS system information.. It appears that the activation of ADMS is still pending. The present status of ADMS /time schedule for putting system in operation may please be informed. Representative of MPPTCL informed the committee that testing of ADMS has already been completed in the presence of SLDC officers and requested SLDC to give approval for implementation of ADMS. Thereafter Chairman OCC stated that the testing of ADMS system shall again be done in presence of SLDC officers so that the issues which remained unresolved (i.e., breaker did not operated due to GPS link failure and breaker spring charging problem at site) during the previous testing may be resolved and some logics were still to be tested. Minutes of 56th OCCM of MP 12

6.12 Extension of RGMO/FGMO signal to SLDC/WRLDC:- Chairman OCC informed the committee that as per IEGC 5.2(f), RGMO/FGMO is mandatory for all thermal units above 200 MW and hydro units above 10 MW. Further considering the high penetration of renewable to grid and also the Government target to achieve 175 GW, it is essential to monitor operation of RGMO/FGMO at SLDC/RLDC for ensuring grid security and compliance of regulation. Subsequently SLDC vide letter no. 07-05/RPC-27/3739 dated 18-01-2017 and letter No. SE/LD:E&T/693 dated 23-01-2017 requested MPPGCL/NHDC for integration of telemetry of RGMO/FGMO in RTU installed at power station and forward the object address configured in RTU so that same may also be configured in SLDC SCADA and RGMO/FGMO status may be displayed in SCADA system. However, no feedback in the matter is received, so far. The matter was discussed in length and the Chairman OCC advised OSP to obtain exemption from implementation of RGMO/FGMO from the Commission as the machines are operation below MDDL. Further he stated that remaining all the generators shall take necessary action at the earliest so that the integration of telemetry of RGMO/FGMO in RTU installed at power station can be done and the same may also be configured in SLDC SCADA and RGMO/FGMO status may be displayed in SCADA system by April 2017. 6.13 Availing of outage of Interstate and 400 KV transmission elements: Member Secretary OCC informed the committee that the standard procedure for availing outages on interstate and 400 KV transmission elements has been devised by WRPC and WRLDC in line with guidelines of CEA and NLDC. This process is approved in OCC meeting of WRPC. This procedure has already been communicated to state grid entities for strict compliance by the SLDC. Matter was discussed in various meetings of MP also. As per standard procedure of WRPC, all the proposed outages of interstate and 400 KV transmission elements of next month should be got approved in the OCC meeting of WRPC in the current month. All the constituents of WR shall inform to the WRLDC for readiness for availing outage of transmission elements on D-3 basis i.e. three days before the date of approved outage. During 491st OCC meeting it was decided that non-occ outages should be discouraged. Only under exceptional cases, the request for transmission outage after issue of OCC minutes must be posted through email for concurrence of the WRPC members (OCC group Email) at least three days in advance (D-3). WRPC members may respond back in email within three hours. After three hours the proposal shall deemed to have been concurred by WRPC for further processing by WRLDC. A detailed procedure for approval of transmission lines /elements outage planning procedure in Western Region is attached at Annexure 6.13. The above procedure will be implemented w.e.f. 01st March, 2017. It has been noticed that the standard procedure for availing outages on interstate and 400 KV transmission elements is not followed by the MPPTCL. WRLDC repeatedly instructed MP SLDC to adhere to the approved procedure of outages and stop requesting for routine nature outages in real time of operation. It is requested that the standard procedure finalized in OCC meetings of MP and WRPC must be followed strictly for availing outages on interstate and 400 KV transmission elements, in future and SLDC shall not forward any outage message to WRLDC during the real time of operation except of emergency nature. Chairman OCC requested all the Stage Grid entities to apply for the shut downs as per guidelines stipulated in the procedure enclosed as Annexure 6.13. All the planned outages of 400 KV Minutes of 56th OCCM of MP 13

lines and Interstate lines should be got approved in OCCM of WR. WRLDC shall not allow any planned outage if it is not approved by OCCM of WR. Only emergency nature shut down will be accepted in real time. The planned outage of the State Grid shall also be submitted to SLDC well in advance so that system reliability could be ensured by the SLDC. He also requested all the concerned entities for wide circulation of procedures among field staff to comply with. 6.14 Integration of New Transmission Elements into the Grid:- Member Secretary OCC informed the committee that the transmission system in Madhya Pradesh is growing at a rapid pace. The process of integration/charging of new transmission elements belonging to each entity requires compliance of certain regulatory requirements and sharing of information/submission of documents to SLDC/RLDC. Therefore mandatory documents and not limited to, to be submitted to SLDC/RLDC prior to issue of charging code for new transmission element are as follows:- 1. Copy of approval by Electrical Inspector. 2. Intimation by Transmission Licensee Regarding anticipated charging of new elements (Annexure 6.14-A) 3. List Of Elements to be charged and Element Rating details. (Annexure- 6.14-B). 4. Undertaking by Transmission Licensee in respect of Telemetry and communication (Annexure- 6.14-C). All the intra-state entities are requested to provide the above data in prescribed formats (enclosed) to SLDC/RLDC prior to charging of new transmission elements. The matter has already been discussed and brought to the notice of all entities during 54 th & 55 th OCCM. However, the desired information is still not being furnished for all the new transmission elements. All the intra-state entities are again requested to furnish the required information for integration of all new transmission elements into the grid, to SLDC/RLDC prior to their charging. SLDC representative informed the committee about the matter for timely compliance of regulatory requirement. 6.15 Certification of Declared Capacity of Hydro Generators by SLDC :- Member Secretary OCC informed the committee that CERC vide order dtd 20.12.2016 in petition No. 40/MP/2016 filed by NHDC, has issued following directions :- Quote Regulation 31 (3) of 2014 Tariff Regulations requires that the declared capacity for any day of the month should correspond to the capacity which a generating station can deliver for at least three hours as certified by the nodal load despatch centre after the day is over. Since the petitioner has declared the capacity based on machine and water availability, MPSLDC cannot restrict the PAFM on the ground that machines were not operated as per the directions of the local authorities. The calculation of PAFM by RLDC/SLDC has to be based on capacity declared by the generator considering machine and water availability finalized by SSRRC. Accordingly, the PAFM of ISPS for the period from 14.2.2015 to 17.2.2015 and for all the instances till date shall be recalculated by MPSLDC based on capacity declared by the generator in place of restrictions imposed by local authorities. MPSLDC is further directed to revise the SEA(s) of ISPS and OPS in the light of the above direction Unquote Minutes of 56th OCCM of MP 14

Accordingly, NHDC has submitted the revised PAFM for the year 2014-15 to 2016-17 and MPPGCL has submitted the revised PAFM wef 2009-10 to 2016-17 for certification by SLDC. The verification of PAFM submitted by NHDC and MPPGCL is under progress and shall be completed by the end of March 2017. The matter was discussed in the meeting. ITEM NO. 7: BLACK-START MOCK DRILL OF HYDEL POWER STATIONS : Black Start mock drill of Hydel stations of MPPGCL :- Member Secretary OCC informed the committee that the last black start mock drill of Gandhisagar Bargi, Pench, Indira Sagar Power Station (ISP), Omkareshwar Power Station (OSP), Tons HPS and Birsinghpur HPS were successfully completed during the year 16-17. As per IEGC Black Start Mock Drill shall be conducted in every 6 months duration. MPPGCL and NHDC are requested to submit the plan for carrying out black start mock drill of Gandhisagar Bargi, Pench, Indira Sagar Power Station (ISP), Omkareshwar Power Station (OSP), Tons HPS and Birsinghpur HPS for the year 2017-18. Suitable dates may be communicated to SLDC well in advance for making necessary arrangements. Chairman OCC stated that 19 No. of Mock Drills has been conducted in MP at various HPS. The Mock Drill at Rajghat & Madhikheda shall be conducted by June 2017. MPPGCL agreed for conducting Black Start at Madhikheda in the month of April 2017. Representatives of MPPGCL and NHDC requested SLDC to give suitable dates for Mock Drill Exercise of their Hydel Power Stations. Member Secretary, OCC stated that Black Start Mock Drill of all the Hydel Power Stations except Rajghat could be conducted in the month of May & June, 2017. ITEM NO 8: ALLOCATION OF THE POWER TO DISCOM, EAST DISCOM REGARDING: Member Secretary OCC informed the committee that SLDC is allocating the power to DISCOMs of MP as per GoMP Notification dtd. 19.03.2013 effective from 01.04.2013 and MPPMCL is allocating the unallocated power to DISCOMs on day ahead and real time basis as per the forecasted demand furnished by the DCCs. However, the Energy Deptt. Govt. of MP vide notification No.2211/F-3-13/2016/XIII dtd. 21st March, 2016 has allocated all existing and future generating capacity to MPPMCL for maintaining uniform tariff across the State w.e.f. April 2016. Due to more allocation of power to East Discom and less to West Discom the East Discom remains in under drawal and West Discom in over drawal. These leads to gap between average cost of supply (ACS), resulting increase in average revenue realization (ARR) per unit in East Discom. It is requested to provide a solution so as to minimize the under drawal of East Discom and over drawal of West Discom. The date wise under drawal/over drawal of Discoms for the month of Feb.2017 Annexure-8. (upto 26.02.2017) is enclosed as East Discom representative informed that allocation to them is not proper by MPPMCL and the matter was discussed with the committee. Minutes of 56th OCCM of MP 15

Chairman OCC requested MPPMCL & Discoms to mutually disuss the matter and resolve the issue with common consensus. ITEM NO 9:Non-reporting of tripping incidence occurred on 25.02.2017 at 220 KV S/S Sabalgarh:- Member Secretary OCC informed the committee that At around 14.19 hrs on dtd. 25.02.2017, 220Kv Shivpuri-Sabalgarh feeder-ii tripped with following indication: Shivpuri - ACN, zone-iii, FT-1, trip ABC Sabalgarh - No indication It is gathered that 160MVA, 220/132Kv transformer No.I&II at 220KV S/S Sabalgarh also tripped at the same time with O/C R phase, E/F indication resulting total failure of 132Kv supply at Sabalgarh, Shivpurkalan and Baroda substations. It has come to notice that officials on duty at Sabalgarh S/s had not intimated about above incidence by 18.00 hrs to upper substation (220Kv S/S Shivpuri). Thus, the officials on duty at 220KV Shivpuri S/s, Sub-LDC Bhopal and SLDC Jabalpur were in dark about these tripping incidence, resulting delay in normalization of system. It is also gathered that above tripping occurred during shifting of load of 132 KV Shivpurkalan ckt-i to Auxiliary bus at Sabalgarh S/s.Non-reporting of tripping of transmission elements after incidence occurred, is not in the interest of safe,secure and reliable operation of integrated grid. Chairman OCC stated that the above incident is not an isolated incident in Gwalior region as in past many incidences have been observed about non-reporting and charging of elements without obtaining code from SLDC. He also requested MPPTCL to issue suitable instructions to field offices to adhere the grid code for maintaining safe & secure grid operation and avoid the repeatance of such incidences. ITEM NO. 10: AVAILABILITY BASED TARIFF (ABT) RELATED ISSUES: 10.1 Status of AMR system installed at SLDC: SLDC representative informed the Committee about the status of AMR data received through AMR system in the month of Jan 2017. He informed that the complete data of 555 meters was received through AMR system and data of 68 Nos meters (Monthly-51 & Partial 17) was not received through AMR system. The incomplete data is received due to site related issues such as network problem, modem switched off, meter defective or replaced, misalignment of optical cable or due to some other problems. The status of data received through AMR system is invariably sent to all concerned offices including SE(T&C) offices through email for furnishing the missing data alongwith monthly JMR data latest by 4th of every month. Further following points are discussed and resolved as under:- 1. SLDC requested the CE(T&C) office to take up the matter with M/s Secure Meters Ltd for resolving the site related issues such as time drift in meters, meter defective, network problem Minutes of 56th OCCM of MP 16