Small Generator Interconnection Program Interconnection Technical Requirements

Similar documents
Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Overview of State Distributed Generation Interconnection Rules

INTERCONNECTION REQUIREMENTS POLICY

PUD ELECTRIC SYSTEM INTERCONNECTION

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

INTERCONNECTION for GENERATING FACILITIES Up to 20 MW

Feasibility Study Report

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

MICHIGAN ELECTRIC UTILITY

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Interconnection System Impact Study Report Request # GI

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

MICHIGAN ELECTRIC UTILITY

Umatilla Electric Cooperative Net Metering Rules

MICHIGAN ELECTRIC UTILITY

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

Guidelines for connection of generators:

Interconnection Feasibility Study Report GIP-226-FEAS-R3

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

Feasibility Study Report

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Exelon Energy Delivery Interconnection Guidelines for Generators 2 MVA or less

STATE OF NORTH DAKOTA DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS TABLE OF CONTENTS

DAKOTA ELECTRIC ASSOCIATION DISTRIBUTED GENERATION INTERCONNECTION REQUIREMENTS

Presentation to the PJM NEMSTF Interconnection Issues. Interconnecting Solar Projects on the PSE&G Distribution System

Transformer Protection

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620

Generator Interconnection System Impact Study For

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules

TD-2306B-001, Interconnecting Large 2-20MW Generation Systems. Employees involved with generation interconnection on electric distribution circuits.

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

GENERATING FACILITY INTERCONNECTION APPLICATION. Part 1 Introduction and Overview

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Implementing a Microgrid Using Standard Utility Control Equipment

201 S. Anaheim Blvd. Page No Anaheim, CA RULE NO. 2 DESCRIPTION OF SERVICE

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016

MILLIGAN SOLAR PROJECT

Feasibility Study for the Q MW Solar Project

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Louisville Gas and Electric Company

REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDING 50 kw

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

Appendix A2: Technical Requirements for Distributed Generators > 10 kw to be Connected to Kitchener-Wilmot Hydro Inc. s Distribution System

CUSTOMER/ TWIN ARROWS PROJECT

PV System Impact Guide

Q64. Photovoltaic Solar Generation Project Interconnection. Facilities Study. APS Contract No

Net Metering Interconnection Requirements

Feasibility Study Report

WELLS RURAL ELECTRIC COMPANY Adopted: March 1976 Revised: March 21, 2017 Reviewed: August 21, 1998 RULE NO. 2

Chapter 7 General Specifications for Rotating Non-Utility Generators (NUGs) Table of Contents

SANTA CLARA CITY RENEWABLE NET METERING & INTERCONNECTION AGREEMENT

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Guideline for Parallel Grid Exit Point Connection 28/10/2010

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

MICHIGAN ELECTRIC UTILITY

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

TRANSMISSION PLANNING CRITERIA

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

Duke Energy Carolinas North Carolina Interconnection Request Checklist

Technical Considerations Covering Parallel Operations of Customer Owned Generation

Switchgear and Distribution Systems for Engineers and Technicians

Solid Dielectric, Three Phase Reclosers CATALOG VS11

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power

Session 8: Distributed Energy Resources Utility Concerns, Grid Impacts and Mitigation Strategies October 21, 2015 Santiago, Chile

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

3.0 Radial Distribution Systems

Q0044 interconnection at

100 MW Wind Generation Project

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Section SWITCHBOARDS. Introduction. Part 1 - General. Related Work

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Copyright 2003 Advanced Power Technologies, Inc.

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _

Small Electrical Systems (Microgrids)

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Adopted: September 24, 2015 Version: Version 1.0

TECHNICAL REQUIREMENTS FOR PARALLEL OPERATION OF MEMBER-OWNED GENERATION

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

Consulting Agreement Study. Completed for Transmission Customer

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

Consumer Guidelines for Electric Power Generator Installation and Interconnection

JEA Distributed Generation Policy Effective April 1, 2018

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Feasibility Study for the Q MW Solar Project

Transcription:

General Program Information What is the purpose of the PGE Small Generator Interconnection Program? How do I initiate a distribution interconnection request for my project? The purpose of our Small Generator Interconnection Program is to comply with state and/or federal regulations and requirements to provide a means to interconnect generators to PGE s electric power system while ensuring the safety, reliability and power quality of PGE s electric power system. To initiate an interconnection request, you must submit the following to us: Interconnection application Application fee (make checks payable to Portland General Electric Co.) One-line diagram Site plan (this should include property lines, switchgear location, distances, driveway/gravel area, fencing, solar panel layout and proposed point of interconnection) Proof of site control Manufacturer technical specification sheet for all lab-tested system components FERC Notice of Self Certification for Qualifying Facility (QF) if applicable Projects with a nameplate rating greater than 3 MW must include communication equipment product sheets, protocol, and designs to meet the telemetry requirements of OAR 860-082-0070(5) All documents should be sent via email to Small.PowerProduction@pgn.com or they can be mailed to the following address: Attn: Small Power Production Portland General Electric 121 SW Salmon St, 3WTC0402 Portland, OR 97204 How long does the interconnection process take? The interconnection process will take approximately 30 to 36 months to complete. This includes approximately 12 months to complete the study process and approximately 18 to 24 months for preliminary design, detailed engineering, procurement, and construction. Depending on the specifics of your project and how it will interconnect with our system, the process may take longer. 1

What studies does PGE perform to evaluate the impact of my project on the PGE electric system? Do you allow studies to be skipped? Is detailed engineering performed as part of the Facilities Study? Who do I contact if I have questions? We will conduct three studies when evaluating your interconnection request: Feasibility Study o Identifies potential adverse system impacts System Impact Study o Short-circuit analysis o Stability analysis o Power flow analysis o Voltage drop and flicker studies o Protection and set point studies o Grounding review o The underlying assumptions of the study o The results of the analysis o Any potential impediments to providing the requested interconnection service Facility Study o Interconnection facilities and system upgrade requirements o Cost estimate for facilities and upgrade requirements o Schedule estimate to procure, construct, and install interconnection facilities and system upgrades Each project entering the interconnection queue should expect to complete the Feasibility Study, System Impact Study, and Facility Study prior to receiving an Interconnection Agreement. This ensures that all applicants are treated in an equal manner and each interconnection request is properly reviewed. There may be instances in which studies can be skipped, as determined by PGE at our sole discretion. We will complete preliminary design as part of the interconnection study process with sufficient detail to determine the scope and budget for any required interconnection facilities and system upgrades. Detailed engineering will be completed after the Interconnection Agreement is executed. For questions about the small-generator interconnection queue, contact us at Small. PowerProduction@pgn.com or call the Small Power Production Specialists at 503-464-8300. 2

Protection Information Why do you require provisions for a transfer trip? A transfer trip will quickly remove the Project from PGE s system for a trip of the feeder breaker, a transformer lockout or a fault on the transmission system to support the safe and reliable operation of the system. Transfer trips are industry accepted practice and prevent unintentional islanding by the generation project. They also trip the generation project for reliability events that the project can t detect and are used to remove the project from PGE s system when switching or other system work is required. Why do you require use of fiber optic communication for transfer trips rather than an alternative such as PLC/telco/radio? Why do you require the use of SEL 487E relays rather than a less expensive alternative? Why are you requiring substation and line modifications when my DER project meets the requirements of IEEE1547 and IEEE1547.1? Are you conforming to IEEE 1547.2? Our current standard is to use fiber communication for transfer trip schemes. We have not installed a new PLC or telco scheme for many years due to concerns regarding speed, maintenance and reliability. We don t currently have the infrastructure for a radio solution that will provide the required level of reliability. We exclusively use Schweitzer Engineering Laboratories (SEL) microprocessor-based protective relays. Our protection engineers have determined that the SEL-487E Transformer Protection Relay is the only SEL relay that has the functionality for generator interconnection protection required by PGE design standards. The SEL-487E is the standard transformer protective relay used on our system. IEEE1547 is a performance standard specifying the requirement of the generator at the point it electrically connects to the utility. IEEE1547.1 is a standard that defines the testing required to determine if a generator is compliant with the performance requirements in IEEE1547. The IEEE 1547 standards do not address the system modifications we require to interconnect the generator. IEEE1547.2 is an application guide that describes the various mitigation techniques available. We have taken IEEE1547.2 into consideration in developing our interconnection requirements. 3

What equipment is required to mitigate the risk of 3VO voltage rise? Overvoltage conditions can result from a fault on the high side of a substation transformer when there is back feed through the transformer from a generation project. Overvoltage conditions can damage transformers and line insulators, and impact power quality to existing customers. To rapidly detect the overvoltage condition and trip the generator, the following is required: 3 phase VT on the high side of the substation transformer Circuit switcher or circuit breaker on the high side of the substation transformer Dual SEL-487E relays for overall transformer protection Transfer trip to the generator via mirror bits Distribution Equipment Information Why do you require the replacement of circuit breakers rather than just replacing the protective relays? Why do you require replacement of fuses with electronic reclosers? Why not a larger fuse? Circuit breakers are replaced when the circuit breaker is incompatible with the protective relays to be installed or PGE s Asset Management evaluation determines it is more cost effective to replace the circuit breaker and associated relay protection package rather than replacing only the protective relays in an aging circuit breaker. Bringing an aging circuit breaker up to our current standards is typically more expensive than replacing the circuit breaker. Depending on the size and location of the generator, an electronic recloser might be required instead of a fuse to allow for effective coordination with other protective devices and ensure the safety and reliability of our distribution system. Electronic reclosers are protective devices that can be programmed to provide the protection needed to effectively isolate the distribution system during unplanned power quality/reliability events to minimize impact, and speed restoration of service. On our system, fuses are limited to tapline/service transformer load sizes and do not have voltage sensing capability. 4

Why do you require replacement of hydraulic reclosers? Can reclosers be retrofitted rather than replaced? Depending on the size and location of the generator, an electronic recloser might be required instead of a hydraulic recloser. On our system, hydraulic recloser ratings are limited to feeder tapline load sizes and do not have voltage sensing capability. In addition to not being rated for higher ampacities, hydraulic reclosers have considerable maintenance requirements when compared to electronic reclosers. PGE does not retrofit reclosers. Our current distribution design standards require voltage sensing equipment on both the line and load sides of the recloser to allow for synchronizing capability. It is cost prohibitive to retrofit existing reclosers, so our practice is to replace a recloser that does not meet our current standards. Why do you require reconductoring of primary feeders for some interconnection projects? Due to the interconnected nature of PGE s distribution system, some interconnection projects may require reconductoring of an entire /primary feeder mainline loop. To ensure that no system equipment is damaged, we evaluate interconnecting generators at full capacity while the surrounding load is modeled at a minimum. Some generation and load scenarios can create significant current flow onto our primary distribution system. This current flow can, in some cases, exceed the rating of existing conductors, requiring a primary feeder reconductor. Distribution Planning Information How are peak loading conditions defined? How are light loading conditions defined? A peak loading condition is defined as the highest coincidental daytime loading condition for a grouping of feeders served from the same substation during a season when loading is at its highest level. A light loading condition is defined as the lowest coincidental daytime loading condition for a grouping of feeders served from the same substation during a season when loading is at its lowest level. 5

Do you evaluate flicker in System Impact Studies? What tool is used? Voltage fluctuation (flicker) are evaluated by comparing two states (QF off/qf on) with field and substation voltage control devices disabled during simulation to determine the voltage delta. CYME power engineering software (CYMDIST) is the modeling tool used to perform system impact studies on the distribution system. Permissible variations in service levels on our primary distribution system are limited to 1.5 percent assuming not more than four fluctuations per hour. Our power quality guidelines are established in PGE design standards, ANSI C84.1-1989, and IEEE 141-1993. Do you evaluate and report available fault current at the point of interconnection? How is daytime minimum load factored into substation transformer loading evaluation? Do you provide the author of studies that are completed by a third party? We evaluate and report available fault current at the point of interconnection (before and after QF is installed) and at equipment locations up to and including the corresponding substation bus. This information is documented in the System Impact Study. Interconnection studies are performed for daytime minimum loading levels for peak system loading conditions and light system loading conditions consistent with PGE and Western Electricity Coordinating Council (WECC) planning standards. Heavy daytime conditions (summer) and light daytime conditions (spring) are collected at hourly intervals for individual feeders and are applied in the model used to simulate the distribution system. For peak loading conditions, the highest coincidental system load is selected and compared to corresponding weather conditions and system configuration. If ideal weather conditions and configurations match, then the affected feeder loadings are applied. For light loading conditions, the lowest coincidental daytime system load is selected and compared to corresponding weather conditions and system configuration. If ideal weather conditions and configurations match, then the affected feeder loadings are applied. We may contract with third parties to perform certain parts of the studies. These studies are reviewed by the third party s lead engineer and subsequently reviewed by PGE engineers responsible for the substations the QF is interconnected with. We do not provide the contact information of the third parties that we engage. *PGE reserves the right to make changes to this FAQ and its requirements, standards, and policies at any time. 6