Superconducting Fault Current Limiter Project

Similar documents
2G HTS Wire and Device Demonstration Programs at SuperPower: Recent Progress and Continuous Improvement Programs

Introducing Nexans Superconducting Fault Current Limiters (SCFCLs)

Review paper on Fault analysis and its Limiting Techniques.

Advanced Cooling Technologies, Inc. Low-Cost Radiator for Fission Power Thermal Control NETS Conference

Superconducting Cable Systems for Urban Areas AmpaCity Project - Germany

Decision on Merced Irrigation District Transition Agreement

Independent Testing Laboratory for High Voltage Equipment

AmpaCity Project Update 40 MVA HTS Cable and Fault Current Limiter Installation in City Center

Advanced Superconductor Motor Demonstrator (ASuMED)

Microgrid solutions Delivering resilient power anywhere at any time

Technological Viability Evaluation. Results from the SWOT Analysis Diego Salzillo Arriaga, Siemens

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund

GRID MODERNIZATION INITIATIVE PEER REVIEW

SuperPower 2G HTS Wire for Demanding Electric Power Applications

Development of a Superconducting High-Speed Flywheel Energy Storage System

Merger of the generator interconnection processes of Valley Electric and the ISO;

Fault Current Limiters for Distribution and Subtransmission Electricity Networks

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

DHS S&T s Recovery Transformer (RecX)

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

BROCHURE. End-to-end microgrid solutions From consulting and advisory services to design and implementation

THE Gersh Budker Prize PRIZE FOR.THE SUCCESSFUL CONSTRUCTION AND COMMISSIONING OF THE SPALLATION NEUTRON SOURCE

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

SuperPower 2G HTS Wire for Demanding Electric Power Applications

HIGH VOLTAGE, HIGH CURRENT, HIGH DI/DT SOLID STATE SWITCH

Cost Benefit Analysis of Faster Transmission System Protection Systems

ILLINOIS COMMERCE COMMISSION

OTC/MANE-VU. 19 November 2014

2006 IEEE PES General Meeting June 2006, Montreal, Canada Paper 06GM0613. Fault Current Limiters - Report on the Activities of Cigre WG A3.

Review and update on MAGLEV

Alternative and Renewable Fuel and Vehicle Technology Program. Advisory Committee Meeting

UNCLASSIFIED: Distribution Statement A. Approved for public release.

Design Development and Testing of the Ground Renewable Expeditionary ENergy System

METRO CNG Program Phase I Update. Customer Service Committee April 2014

Pre-saturated Core Fault Current Limiter (PCFCL) Project

Master of Engineering

FUSES. Safety through quality

Development and Operational Advantages of a Solid State Circuit Breaker with Current Limiting

Smart Grid and Energy Efficiency in the U.S.

Improving Maintenance Safety Through Collaboration

GRID MODERNIZATION INITIATIVE PEER REVIEW GMLC Control Theory

City of Palo Alto (ID # 6416) City Council Staff Report

Interconnection System Impact Study Report Request # GI

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE

EU Procurement of In Vessel Components for ITER

SCHURTER Fuses for Space Circuit Protection Solutions for future space applications

Solano County Transit

MEDIUM VOLTAGE PRODUCTS. Fault Current Limiters I S. -limiter and FC-Protector The worldʼs fastest switching devices

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

The Regional Municipality of York. Purchase of Six Battery Electric Buses

Power System Stability Analysis on System Connected to Wind Power Generation with Solid State Fault Current Limiter

Reactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal

Extra-High-Voltage SF 6 Gas-Insulated Switchgear

Electricity Transmission Infrastructure Development in New England

NERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016

Prospective of Applications of Superconducting Fault Current Limiters in Chinese Power Grids

Green Line LRT: Beltline Segment Update April 19, 2017

American Electric Power s Energy Storage Deployments

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

ADVANCED VEHICLE TECHNOLOGIES RESEARCH

PV inverters in a High PV Penetration scenario Challenges and opportunities for smart technologies

July 28, 2009 Presentation to the Illinois Statewide Smart Grid Collaborative

Transportation Electrification Public Input Workshop. August 3, 2016

TORONTO TRANSIT COMMISSION REPORT NO.

A fully integrated 3 phase IGBT switching assembly with a very low loss DC Link Capacitor -- Ed Sawyer, SBE Inc. Scott Leslie, Powerex Inc.

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

Modernising the Great Western railway

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010

DC Arc-Free Circuit Breaker for Utility-Grid Battery Storage System

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

PHYSICAL MODEL TESTS OF ICE PASSAGE AT LOCKS

New 115 kv Disconnect Switches at Bloomsburg MTS

ABB POWER SYSTEMS CONSULTING

Topic Small Projects (< 100 kw) Large Projects (>100 kw)

- Status Report - System Power Determination of Electrified (Light Duty) Vehicles. Subgroup Leader: Germany, Korea. EVE-17 meeting

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Electric Transportation Initiatives. PSC Workshop: Electric Vehicle Charging September 6, 2012 Christopher Gillman

STAFF REPORT ACTION REQUIRED

Guidelines for Modernizing Existing Electrical Switchgear in LV and MV Networks

HDV CO2 emission certification 1 st meeting of the Editing board

Understanding the Performance of Parallel Temporary Protective Grounds

Medium-voltage fuses 3 kv 40.5 kv, 0.4 A 315 A

Co-Optimization of Fuels and Engines

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

Cryocooler with Cold Compressor for Deep Space Applications

Sacramento Municipal Utility District s EV Innovators Pilot

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Smart Charging and Vehicle Grid Integration Silicon Valley Leadership Group PEV Forum December 16, 2014

From: Tito R. Nagrampa Jr, P.E. Approved by: /s/ General Manager Juan M. Ulloa, P.E. Engineering Supervisor

Precision Station Stopping Progress Update

80+ Power Supply Program for Computers

Peninsula Corridor Electrification Project (PCEP)

RI Power Sector Transformation Con Edison Experiences. May 31 st, 2017

Washington Metropolitan Area Transit Authority Recommended Contracting Actions For Up To 217 Hybrid Electric & Clean Diesel Buses

Low Beta Cryomodule Development at Fermilab. Tom Nicol March 2, 2011

Considerations for Reducing Emissions from the In-Use Diesel Fleet

Draft Results and Recommendations

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016

Battery Electric Bus Technology Review. Victoria Regional Transit Commission September 19, 2017 Aaron Lamb

TRANSMISSION PLANNING CRITERIA

Transcription:

Superconducting Fault Current Limiter Project Roger A. Farrell, SuperPower, Inc. Ed Garcia, The BOC Group, Inc. Albert Keri, American Electric Power Randy Shaw, Sumitomo Electric U.S.A., Inc. HTS Solutions for a New Dimension in Power Superconductivity for Electric Systems 2006 Annual DOE Peer Review

HTS Fault Current Limiters New Technology for a Growing Problem As new sources of generation are added, utilities are faced with the threat of higher levels of fault current HTS Fault Current Limiters (FCLs) address the market pull to cost-effectively correct fault current over-duty problems at the transmission voltage level of 138kV and higher The HTS FCLs will reduce the available fault current to a lower, safer level so existing switchgear can still protect the grid Utility market needs at the transmission level: Accommodate increasing fault currents due to added generation Avoid adverse side effects imposed by existing solutions Prevent breaker failures and & problems (e.g., welded contacts, bus bracing, etc.) Reduce through fault stresses on aging infrastructure Maintain flexibility to accommodate load growth and open access Avoid need for expensive 80kA breakers HTS FCLs will be needed for most commercial AC HTS cable systems Discussions with 20+ utilities have consistently validated the need! 2006 DOE Peer Review 1

Superconducting Fault Current Limiter (SFCL): An Alternative New concept with no conventional counterpart: Source Impedance Z S AC Fault Current Limiting Impedance Z FCL Normal Operation Z FCL = 0 Fault Condition Z FCL = Z 0 Load Impedance Z L Passive (no active controls for insertion in system), No Burden on system during normal operation Modular and Scalable Environmental benefit and no SF6 Substation A Z line Under fault conditions critical current is exceeded and the superconductor transitions to a resistive state, introducing current limiting impedance into the grid with a parallel inductor New Generator MFCL Addition of one SC Fault Current Limiter avoids multiple breaker upgrades when adding new generation sources Substation C Substation B 2006 DOE Peer Review 2

Project Description & Research Integration Goal: Demonstrate SFCL feasibility at transmission level voltage 138kV Cost Original $12.2M project cost estimate, with $6.1M DOE and $600K EPRI support Now estimating project cost $23.6M, based on switch from melt cast BSCCO to 2G ($2.4M) and one year program extension (total of two years one for RES and one to optimize 2G for application) Schedule Project started 6/02, original completion 6/06 Completion now estimated to be 6/09 Project Team: SuperPower, Inc.: Program Lead, supply of 2G matrix material Sumitomo Electric Industries, Ltd. (SEI) High voltage bushings and cryostat electrical insulation system The BOC Group, inc. Cryogenic refrigeration system American Electric Power (AEP) Utility host, system studies DOE National Labs CRADA executed with ORNL (High voltage, cryogenics), CRADA pending with LANL (HTS element evaluation) 2006 DOE Peer Review 3

Research Integration (cont d.) Technical Advisory Board (TAB): Evaluate and guide project in conjunction with DOE Readiness Review Utility members: AEP, New York Power Authority, Southern California Edison, Con Edison, Entergy Academia: Rensselaer Polytechnic Institute (RPI) Funding sponsors: DOE and EPRI National Electrical Energy Testing, Research And Applications Center (NEETRAC) Periodic reviews with 5 utilities with an interest in the project: Florida Power and Light, Exelon, Southern Company, Baltimore Gas and Electric, Entergy Conference calls in March, June and July 2006 NEETRAC project manager sits on TAB Use existing specialized facilities: KEMA Power Test, Chalfont, PA, for short circuit testing 2G module tested in June 2006 Waukesha Electric for Impulse testing up to 900kV not this year during RES High Voltage Working Group SEI, RPI, AEP and ORNL Total of 5 US patents granted on SFCL technology 2006 DOE Peer Review 4

Milestone Driven Program Major Milestone Concept Feasibility & Application Studies Proof-of- Concept Demonstration Alpha Prototype Objectives Complete Conceptual Design Study application requirements and perform power system studies Scaled hardware non-grid demonstration of matrix concept Focus: Scale up for non-grid demonstration at high voltage Rating: 138kV, single phase, AEP application requirements Beta Prototype Focus: In-grid demonstration for specific utility application Rating: 138kV, three phase, AEP Sporn Application Completion Date Completed June 2003 Completed July 2004 ON HOLD ON HOLD Fabrication of full scale prototypes on hold in July 2005 pending further developments in focus areas: 1. High Voltage & 2. HTS elements 2006 DOE Peer Review 5

Alpha Prototype Development - Main Components High Voltage Insulation System 1. Bushings, 2. Cryostat insulation system, 3. Matrix internal insulation Bushings Cryostat Matrix Assembly 1. HTS Elements, 2. Connections of HTS elements and current limiting coils Cryostat System 1. Vessels to provide stable pressurized sub-cooled environment, 2. Cryogens and cryocoolers R 11 R 21 R m1 HTS Element L 11 L 21 L m1 Matrix Assembly Shunt Impedance R 12 R 22 R m2 L 12 L 22 L m2 B C Elements R 1n R 2n R mn Single Phase of Alpha L 1n L 2n L mn Simplified Matrix Assembly Schematic 2006 DOE Peer Review 6

Program Status At last year s Peer Review it was announced that the SFCL Program was being placed on hold (Alpha prototype design) due to: Concerns about the reliability of the melt cast BSCCO-2212 elements* Need for a partner with high voltage expertise* Escalating program cost * Both areas were identified at the 6/28/05 DOE Readiness Review as needing more priority Shortly thereafter (September) stakeholders were informed that the program would be placed on Reduced Effort Status (RES) while SuperPower Investigated the feasibility of utilizing 2G material in the SFCL application Obtained an industrial partner with high voltage expertise who is willing to share in the financial risk of the program RES to last no later than 6/30/06 Reengage the program at full speed, or Terminate the program 2006 DOE Peer Review 7

Program Status (cont d.) In the last year during the RES The BOC Group, Inc. joined the project with responsibility for the cryogenic system design, development and device monitoring Sumitomo Electric Industries, Ltd. (SEI) joined the project as the high voltage partner with responsibility for the bushings and cryostat electrical insulation system Reconfirmed AEP participation as the beta prototype host site although the previously selected Sporn substation may change Reaffirmed interest of TAB and NEETRAC utility members in the SFCL Retained DOE and EPRI financial support albeit at a reduced levels Obtained additional DOE support via the GridWorks program to specifically address optimization of 2G for the SFCL application Demonstrated through in house and KEMA Power Lab testing that 2G is feasible for the SFCL application Conclusions All conditions established to reengage the program at full pace have been fulfilled The use of the same industrial partner team as the Albany Cable Project will build upon the close working relationships already established by world class organizations 2006 DOE Peer Review 8

Melt Cast BSCCO Element Performance Testing of the BSCCO tube elements @ KEMA prior to last year s Peer Review High probability of failure Low N value - typically I > 10 Ic Limited cooling surface area - long recovery time typically of the order of 10s of Seconds Melt cast BSCCO tube length = 20 cm 2006 DOE Peer Review 9

2G SFCL Elements High Current and High Voltage Test @ KEMA Objectives Demonstrate the suitability of 2G tapes for current limiting at currents and voltages comparable to utility requirements provided for alpha and beta prototype SFCLs Verify in-house test results at higher currents and voltages Dynamic resistance of the 2G tape Failure mechanisms and performance limits maximum current, voltage, energy, volts/cm and temperature rise Life expectancy of the tape To carry out limited design studies of SFCL modules - Shunt coil design, spacing between 2G elements 2006 DOE Peer Review 10

2G SFCL 12 Element Module Assembly & KEMA Test 2G SFCL Mockup assembly components 12 elements, 40 cm long with 4 2G tapes in parallel per element 12 elements connected in series 2 sets of 6 shunt coils of 10 mω and 5 mω Test Voltage and Current Ranges Total Voltage = V1 + V2 + V3 + + V12 I_total V1 +V2 I sh1 V 1-4 = V1 + V2 + V3 + V4 1 2 3 4 8 7 6 5 9 10 11 12 Equivalent Circuit V3 + V4 Voltage range from 120 V rms to 1200 V rms Fault current ranges from 3 ka peak to 100 ka peak Device Short Circuit Tests Start with the lowest fault current setup ( 5kA rms at 480 V rms ) and lowest supply voltage setting, 120 V rms, and gradually step the voltage up to a maximum of 1200 V rms Repeat the above procedure with the 10 ka rms and 15 ka rms prospective fault currents Record voltage and current waveforms 2006 DOE Peer Review 11

2G Material Element Test Summary Testing of non optimized 2G material elements @ SuperPower & KEMA this year V 1-4 = V1 + V2 + V3 + V4 V1 +V2 V3 + V4 Total Voltage = V1 + V2 + V3 + + V12 I_total I sh1 1 2 3 4 8 7 6 5 9 10 11 12 High N value means Iquench = 2-3 Ic High cooling surface area means shorter recovery time, ~ 4 6 seconds Tested 2G elements are 40 cm long, this will be extended to ~ 1 m Flexibility to optimize 2006 DOE Peer Review 12

Melt Cast BSCCO vs. 2G Summary Melt Cast BSCCO - 2212 Ceramic with no substrate is more fragile Low n-value (8-12) quench current is much higher than the critical current, > 10 x Ic Producing elements longer than 20 cm is a big challenge Using short elements increases number of parts reduced reliability, increased complexity & cost Bulk material with limited cooling surface area BSCCO tubes, length = 20 cm, Cross-sectional area = 1.20 cm 2, Volume = 24 cm 3 Current [ka] 40 30 20 10 0-10 -20-30 -40 Typical test result at 80 ka peak prospective fault current, BSCCO- 2212, Ic = 1500 A, I_limited = 40 ka peak, I_sh = 36 ka peak, I_HTS = 25 ka peak = 16.7Ic, Energy = 1405 J/cm/element 700 5 15 25 35 45 55 65 75 85 95 Time [ms] 600 500 400 300 200 100 0-100 Voltage across HTS [V] Limited Fault Current Current through HTS Shunt Current Voltage across HTS 2G Tape - YBCO HTS is a small fraction of the tape mostly metallic substrates & stabilizers increase mechanical strength High n-value (20-40) quench current is around 2 3 x Ic, limiting fault current faster Overall mass of 2G < BSCCO for same current Manufacturing longer elements or continuous conductors is less challenging significant reduction in connection losses Larger cooling surface area faster recovery 2G tape, length = 40 cm, Cross-sectional area 0.012 cm 2, Volume 0.48 cm 3 Current [ka] 30 20 10 0-10 -20-30 2GFCL - 12 elements mockup test results at KEMA (Test #49), 960 V supply, 15kArms (80 ka peak) prospective current, limited to 28.48 ka peak ( I_2G = 3.02 ka peak, Ish = 26.20 ka peak), Energy = 32.89 J/cm/tape 5.0 0 20 40 60 80 100 Time [ms] I_total_KEMA I_HTS Ish V_total_KEMA 4.0 Voltage across HTS elements [kv] 3.0 2.0 1.0 0.0-1.0 2006 DOE Peer Review 13

Optimization of 2G for The SFCL 2G by its very nature is adaptable to the SFCL application Reduced metal content substrate and stabilizer thickness Addition of a thermal heat sink Increased surface area reduced conductor width or patterning Increased Ic conductor thick film multilayers SuperPower has received an award to perform this optimization under DOE s GridWorks program GridWorks and SPI are complementary programs and fully integrated GridWorks develops optimized 2G matrix elements and elements for the SFCL SPI designs, builds and tests 2G 1φ Alpha and 3φ Beta prototypes and installs and tests the beta prototype on the AEP grid 2006 DOE Peer Review 14

Integrated GridWorks/SPI Program Schedule CY 2006 2007 2008 2009 Task # Task Description pre J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 1.0 SFCL Specification Development 2.0 2G Development 2.1 Modification of metal content of the conductor 2.2 Addition of high resistance heat sink 2.3 Modification of surface area of conductor 2.4 High current conductor 2.5 Long length integrated conductor 3.0 2G SFCL Matrix Development 4.0 2G Pre-prototype Matrix Assembly Design, Fabrication and Test 4.1 Design 4.2 Fabrication 4.3 Test 5.0 2G Prototype Conceptual Design 5.1 Alpha 5.2 Beta 5.3 Phase 3 6.0 2G Program Management 7.0 Alpha Prototype Development RES 7.1 Component design and prototyping 7.2 Detail design 7.3 Fabrication 7.4 Non-grid test and evaluation 8.0 Beta Prototype Development 8.1 System studies and specification development 8.2 Component upgrade Detail design 8.3 Fabrication Re-engage 8.4 Non-grid qualification tests Program 8.5 Installation and commissioning Extended 9.0 Beta Prototype Operation, Evaluation and Site Restoration Operation 9.1 Operation Evaluation 9.2 Site Restoration tbd 10.0 SPI Program Management Stage gate milestone - go/no go decision point 2G Project Schedule - Phase 1 (Alpha) 65 % of 2G dev effort 2G Project Schedule - Phase 2 (Beta) 2G Project Schedule - Phase 3 25 % of 2G dev effort 10 % of 2G dev effort HTS FCL Project Schedule Reduced Effort Status Operational Extension 2006 DOE Peer Review 15

SFCL FY 07 Milestones* 1.0A 1.0B 2.0A 3.0A 4.0A 5.0A 7.1A 7.1B 7.1C 7.1D Complete AEP grid SFCL specifications Identify representative U.S. utilities for study Select 2G configuration for alpha prototype Complete optimized 2G element configuration for alpha prototype Complete optimized 2G matrix configuration for alpha prototype Complete alpha prototype conceptual design Complete alpha prototype cryogenic system development Complete alpha prototype HV bushing and cryostat electrical insulation system development Complete alpha prototype HV matrix insulation development Complete overall integrated alpha prototype design review November 2006 November 2006 December 2006 February 2007 April 2007 May 2007 June 2007 June 2007 June 2007 June 2007 * Schedule subject to revision pending further review by SuperPower, SEI, BOC, AEP and DOE 2006 DOE Peer Review 16

SFCL FY 07 Milestones (cont d.) * 7.2A 7.2B 7.2C 7.2D Complete alpha prototype HV matrix design Complete alpha prototype bushing and cryostat electrical insulation system design Complete alpha prototype cryogenic system design Stage Gate Review Alpha prototype design review August 2007 August 2007 August 2007 August 2007 * Schedule subject to revision pending further review by SuperPower, SEI, BOC, AEP and DOE 2006 DOE Peer Review 17

SFCL Project Roles Partner SuperPower Project Role Overall project management Systems integration SFCL matrix design and development 2G material and matrix component supply SEI Alpha and beta prototype design, fabrication and test Bushing and cryostat electrical insulation system design, development and manufacturing Participate in prototype designs AEP AEP and U.S. utility grid generalized SFCL specifications Select beta prototype site and define specifications Support beta prototype system studies and specification development Substation design and engineering, procure and install beta prototype support equipment Support beta prototype installation, commissioning, testing, data collection and analysis 2006 DOE Peer Review 18

SFCL Project Roles (cont d.) Partner BOC Project Role Cryogenic system design and development Cryogenic system instrumentation and overall system monitoring LN 2 supply Support prototype assembly and testing ORNL Specialized design and testing support for high voltage matrix components in a cryogenic environment Cryogenic consulting LANL Investigate methods to incorporate a heat sink and improve surface area of 2G conductor Assist SuperPower by testing 2G elements Support matrix testing and conceptual designs 2006 DOE Peer Review 19

Conclusion SuperPower and its team are poised to restart the SFCL program at full pace with added expertise in high voltage (SEI) and cryogenics (BOC) using superior 2G material 2006 DOE Peer Review 20