Progress of the JT-60SA Project

Similar documents
JT-60SA Newsletter. Cryoplant arrives at the JAEA Naka Site. No. 65, 31 May Headline

KSTAR Assembly. National Fusion Research Center, Daejeon, Korea

No. 64, 30 April 2015

EU Procurement of In Vessel Components for ITER

PF Coil 2-6 Supply. Main technical aspects. P. Valente

THE Gersh Budker Prize PRIZE FOR.THE SUCCESSFUL CONSTRUCTION AND COMMISSIONING OF THE SPALLATION NEUTRON SOURCE

UPDATES ON ARIES-ACT1 POWER CORE CONFIGURATION

JT-60SA Newsletter No. 80, 31 August 2016

Approaches to Maintenance. S. Malang

Status of ITER at the Transition to Construction

ITER G A0 FDR R1.0

ITER PROJECT J. FARINEAU ITER ORGANIZATION. September 29th, 2010 SOFT PORTO: ITER-ORG 1

ITER Magnets Update European perspective

CONFIGURATION DESIGN AND MAINTENANCE APPROACH FOR THE ARIES-CS STELLARATOR POWER PLANT

Recent progress on R&D toward Neutral Beam Injector for ITER and JT-60SA

GENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon September 2018

ITER Vacuum Vessel Loads. Jake Blanchard October 2011

Power and Particle Control in JT-60SA to Support and Supplement ITER and DEMO

Presented by B. Nelson for the QPS team QPS Conceptual Design Review June 23-24, 2003 ORNL

GENERAL ATOMICS ITER CENTRAL SOLENOID MODULE FABRICATION

EU TF coils status. A.Bonito Oliva F4E Magnets Project Manager

DEMO FUSION CORE ENGINEERING: Blanket Integration and Maintenance

PRELIMINARY ACT-2 POWER CORE DESIGN DEFINITION

Future opportunities for Industry

INTEGRATION OF THE MODULAR DUAL COOLANT PB-17LI BLANKET CONCEPT IN THE ARIES-CS POWER PLANT

ITER Shield Blanket Design Activities At SWIP

GENERAL ATOMICS ITER CEnTRal SolEnoId ModulE FabRICaTIon August 2016

The Results of the KSTAR Superconducting Coil Test

Design Description Document: DDD 11 ITER_D_22HV5L v2.2. Magnet

Mu2e Solenoids! Michael Lamm! L2 for the Mu2e Solenoid! July 27, 2015!

UPDATE ON THE LHC MAIN MAGNETS. Lucio Rossi CERN - LHC MAC 15

Barcelona, 26/06/2018

Neutronic Performance Issues of the Breeding Blanket Options for the European DEMO Fusion Power Plant

The Electron Cyclotron Heating & Current Drive (EC H&CD) Power Supply Procurement. F. Albajar, T. Bonicelli (F4E)

Key Stellarator Engineering Issues and Constraints

Costing of Test Articles Ancillary Equipment and Costing Methodology

Hall C SHMS Progress

M. A. Green, and S. Yu Lawrence Berkeley National Laboratory, Berkeley CA 94720, USA

Power converters for ITER

Overview of the ITER In-Vessel coil (IVC)

Technical Summary for BOP-Group 5 Installation Works The BOP Group 5 works include installation and commissioning of all the Items included in

Preliminary ARIES-RS-DCLL Radial Build for ASC

Dual-Cooled Blanket Modular Replacement Design Approach

Draft Working List to be done at CERN for ATLAS Central Solenoid. Originated, Dec. 4, 2001 Revised, Dec.5, 2001 Akira Yamamoto (KEK)

Vacuum pumps for the ESRF EBS project Michael Hahn

Low Beta Cryomodule Development at Fermilab. Tom Nicol March 2, 2011

Created: 4/23/2003 Page: 1 of 12. Abstract

Pumping Systems for ITER, FIRE and ARIES

Impact of Medium-Temperature Magnet and 2-FP Configuration on Radial Build

High Availability Remote Maintenance Approach for the European DEMO Breeder Blanket options

Technical Specifications (In-Cash Procurement)

Solenoid Magnets for the Front End of a Neutrino Factory

Grain LNG: A Collaborative Approach To LNG Terminal Business Performance Improvement

9-O-3A-4 Cryogenic system for the 43 T Hybrid Magnet at LNCMI Grenoble From the needs to the commissioning

Design and manufacturing status of Trim Coils for the Wendelstein 7-X stellarator experiment

Interconnected Power Systems with Superconducting Magnetic Energy Storage

System Status Briefing

TEMPERATURE AND STRESS IN ALCATOR C-MOD DUE TO THE DIVERTOR UPGRADE

State-of-the-Art 3-D Assessment of Elements Degrading TBR of ARIES-ACT SiC/LiPb Blanket

Energy Performance Information Request Timeline

Strategy for Promoting Centers of Excellence (CoE) Activities

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Magnet. Status Report. Pablo Campero Detector Support Group

Development of Full-size Mockup Bushing for 1 MeV ITER NB System

FACILITY DEVELOPMENT AND OPERATIONS

Supported by. NSTX Liquid Lithium Divertor Status, Plans, and Future Liquid Lithium R&D Needs

Review and update on MAGLEV

Status of the Nuclotron-M project

This chapter gives details of the design, development, and characterization of the

2016 ADVISORY PANEL SUPERCONDUCTING & OTHER ROTATING MACHINES. Jon Hahne Center for Electromechanics The University of Texas at Austin 5/10/2016

Torus Coil. Construction and Geometry for Modeling. D. Kashy CLAS12 Collaboration Meeting March 6, 2018

CALL FOR IDEAS FOR THE RE-USE OF THE MARS EXPRESS PLATFORM PLATFORM CAPABILITIES. D. McCoy

The Wendelstein 7-X trim coil system

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 BACKGROUND

HTS Machines for Applications in All-Electric Aircraft

Making Electricity since December Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada

Super-Critical Water-cooled Reactor

Case Study. Modernising gas fired power plant boiler damper drives and damper bearings

Ghassan Y. Antar University of California San Diego

ITER International Partnerships - France & China -

Rojas Manyame General Manager: Regulation Electricity Control Board (ECB) Namibia

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

Fueling System Proposal for KSTAR

600 A CURRENT LEADS WITH DRY AND COMPACT WARM TERMINALS

Technical Manual Index

SOFE

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL BACKGROUND

Collaboration between CELLS in Barcelona and BINP in Novosibirsk in the construction of ALBA Synchrotron

SAE Mini BAJA: Suspension and Steering

EU Interregional Cooperation

Asymmetry of W7-X magnet system introduced by torus assembly

AMBR* Engine for Science Missions

F4E NEWS CARDBOARD VIRTUAL REALITY GLASSES INSIDE! ITER Worksite Contracts Components Innovation Events

Artesis MCM Case Studies. March 2011

Update on superconducting high-speed flywheel energy storage systems

Conceptual Design Report on JT-60SA Fuelling System Gas Fuelling System

MIRI Cooler System Design Update

Preliminary Neutronics Assessment of Molten Salt Blanket Concepts

Product Brochure Fan coil units for suspended ceilings HyPower-Geko. Energy efficient Powerful Hygienic Low noise

NanoRacks External Payload Platform

Transcription:

Progress of the JT-60SA Project P. Barabaschi, Y. Kamada, H. Shirai For the JT-60SA Integrated Project Team EU: F4E-CEA-ENEA-CNR/RFX-KIT-CIEMAT-SCKCEN JA: QST C.R.FRASCATI- ITALY 1

JT-60SA Project Agreement signed in 2007 Redesigned to meet cost targets in 2008-2009 Mission: contribute to early realization of fusion energy by addressing key physics and engineering issues for ITER and DEMO 1. Support ITER using break- even- equivalent class high temperature D-plasmas lasting for a duration (typically 100s) 2. Supplement ITER toward DEMO with long sustainment (~100s) of high pressure steady-state plasmas necessary in DEMO 3. Foster Next Generation playing leading roles in ITER & DEMO

Machine Parameters Basic machine parameters Plasma Current 5.5 MA P-NBI Cryostat P-NBI Toroidal Field, B t 2.25 T Major Radius, R p 2.96 ECH Minor Radius, a 1.18 Elongation, X 1.95 Triangularity, X 0.53 Aspect Ratio, A 2.5 N-NBI Shape Parameter, S 6.7 Safety Factor, q 95 ~3 Flattop Duration 100 s Heating & CD Power 41 MW N-NBI 10 MW P-NBI 24 MW ECRF 7 MW Divertor wall load 15 MW/m 2

Sharing

Progress since 2016 Procurement and delivery largely completed All TF coils tested, delivered Basic Torus Assembly Completed Individual commissioning of many plant systems completed Integrated Commissioning started Preparing plans for enhancements and operation

JT-60SA timeline 18 TF + 6EF coils Mar., 2013 Cryostat Base TF Coil Cold Test Facility Jan., 2014 Lower Poloidal Field Coils Aug., 2015 Sep., 2016 Aug., 2018 Vacuum Vessel VV thermal shield TF Coils Upper Poloidal Field Coils and Central Solenoid JT-60SA Cryostat Current Lead Cryostat QPC TF Coils power supplies MG SCMP S SNU cryoplant NBI First Plasma Sep. 2020 ECRF diagnostics, etc

Present Status of Tokamak Assembly TF Coils of 18 are successfully assembled with the high accuracy of ±1mm. EF Coil and port thermal shield are under installation. VV Closed

Vacuum Vessel closed with high accuracy VV Assembly was taken account of welding shrinkage (4mm/line, total 52mm/13 lines) in toroidal direction. Aug. 2015 10 m 110 Block 6.4mm D07 D09 6.4mm D01 D08 2.4mm D06 D02 D05 D03 D04 120 Block welding 2.4mm 110 Block direct welding D07 D09 D08 D01 340 D06 Splice-plate welding D02 D03 D05 D04 Sector connection by direct welding and splice-plate welding. 6.6 m Requirement Achieved Inboard ±10 mm ±4 mm Outboard ±10 mm +8/-2 mm High dimensional accuracy was achieved by careful welding work.

JT-60SA in-vessel components Upper divertor = Open, activecooled CFC FW:Start with Carbon,=> Full metal-coated ~2030 Lower divertor = ITER-shaped, active-cooled monoblock, Cryopump Stabilizing Plate Fast Plasma Position Control coil 18 Error Field Correction Coils RWM Control coil: 18 coils MGI valves as DMS

EF & CS: SC coils with high accuracy (~10-4 ) winding Deviation of current center from exact circle Achieved CS2 module 1.6m 2.0m CS4 module CS1 module 6 EF coils : completed by August 2016. 4 CS modules: completed by March 2018. Integration of 4 CS modules will be finished by December 2018. 1.6m 2.0m CS3 module EF1 EF2 EF3 EF4 EF5 EF6 CS1 CS2 CS3 CS4 0.3 mm 0.4 mm 0.2 mm 0.6 mm 0.6 mm 1.3 mm 0.3 mm 0.4 mm 0.4 mm 0.4 mm

TF Coils Cable in Conduit Conductor, 72 turns, 25.7kA each 6 double pancakes, 6 turns/pancake. Helium inlets in high field side joints in external low field side Windings enclosed in steel casings Steel casings inboard wedged, connected in inboard curved regions by Inner Intercoil Structure Steel casings sliding radially but supported toroidally by Outer Intercoil Structure JT-60SA ITER JET

Design concept

TF Coils: Cold testing concluded All 18 +2 spare TF coils have been tested Electrical insulation tests, warm->cold->test->warm Full current tests, joint resistance (nohm range), prior and after quench tests Quench test, Tcs<7.47 consistent and in accordance to predictions Hydraulic flow resistance tests Cryostat and valve box

Air Transportation of last 2 TF coils 15 Feb.:loading at Vatry Airport 21 st Feb. At Naka 17 Feb at Nagoya airport

Assembly: Standing & lifting

Assembly: Rotation

Assembly: Inner Intercoil Structures

Assembly: Outer Intercoil Structure

Assembly: 20 gap for final sector insertion

Assembly: Final sector insertion

Assembly: Final sector inserted 23

Torus Assembly Mechanical assembly of the TF magnet completed in summer 2018 Assembly considered throughout the design process All interfaces adjustable and all machined with respect to winding pack centrelines High assembly accuracy helped keep winding pack centreline positions within acceptable limits

Cryogenic System & Cryodistribution system The cryogenic system was completed by Oct. 2016. Cryolines, all Valve Boxes(VB),all Coil Terminal Boxes(CTB) fabricated. 25

Cryostat Vessel Body Cryostat Top Lid, Delivery to Naka in Sep. 2019. Cylindrical Section: completed

High Temp Superconductor Current Leads HTS-CL decreases required capacity of the cryoplant by 20%. All 26 HTS-CL Fabricated at KIT tested at KIT CuLTKa facility Delivered in Naka 27

Magnet PS ~ close to completion C.R.FRASCATI- ITALY (20 ka, 5 kv) C.R.FRASCATI- ITALY Typical PF coil PS circuit (CS1) SNU (High-voltage Generation Circuit) Completion of Magnet PS system is planned in Mar 2019. Quench Protection Circuits (QPC) Switching Network Units (SNU) Superconducting Magnet PSs (Base PS) Booster PSs (reused) Motor Generator (reused) Water Cooling Systems for Magnet PSs Major Component Quantity Current Status CS1 4, EF1 6, TF1 3 13 units Ready for Operation CS1 4 4 units Ready for Operation EF3,4 2 units Ready for Operation EF2 5, TF 5 units Ready for Operation CS1 4, EF1,6 8 units On site Tests on going EF1,2,5,6 H MG 4 units 1 unit Maintenance and Modification ongoing Overhaul Completed, Ready for Operation PF, TF 2 units Ready for Operation DC Feeders PF, TF 11 circuits Ready for Operation PS Supervisory Control Systems PS SC, PS IPS, PS SIS, PS PLC 4 units Development on going

JT-60SA Research Phases Operation-1: Integrated Commissioning + Equilibrium Controllability of MA-class diverted plasmas BA Phase II 34MW x 100s

IPT Structure BA Agreement foresees Very limited size central team with mainly coordination functions Procurement Arrangements signed between Implementing Agencies -> collaboration between EU and JA Considering this arrangement, a Common Management and Quality Program was developed 10 yrs ago to define R&R and common processes, including the sharing of integration functions EURATOM JA Government C.R.FRASCATI- ITALY STP Project Committee Broader Approach Steering Committee (SC) Project Team IPT EU Home Team F4E+CEA+ENEA +CRPP+SCK -CEN +CIEMAT+FZK JA Home Team JAEA

Management model worked out well The IPT Competent and committed persons from many institutions A light but integrated set of common processes valid for all Agile & motivated team able to quickly tackle the many technical and administrative problems which were encountered This is a software success story which should be valued as much as the hardware produced Thank you all in the JT-60SA IPT for your good will and dedication

BA Phase 2 BA Agreement does not end in 2020 Scope of additional activities for a further 5 years prepared and under approval by Parties o Maintenance/Operation o Scientific Exploitation o Enhancements o And IFMIF/EVEDA (mainly LIPAc in Rokkasho) o And IFERC (DEMO related) IPT Management model to be extended to Research and Operation activities 32

Conclusions TF Coils tested, delivered, last sector assembled Overall delivery mostly completed, 90% the credit value accepted Torus assembly nearly completed Commissioning underway First Plasma planned for Sept 2020 IPT Management model successful JT-60SA research plan elaborated Onward plans under approval C.R.FRASCATI- ITALY