POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

Similar documents
POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

POWER SYSTEM INCIDENT REPORT: OVERLOAD OF WAUBRA- HORSHAM 220 KV TRANSMISSION LINE AND INSECURE OPERATION OF THE SYSTEM ON 13 DECEMBER 2012

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

Final Capacity Auction Results 2018/2019 T-1 Capacity Auction. Date 26/01/2018 Version 1.0

Final Capacity Auction Results 2019/2020 T-1 Capacity Auction. Date 01/02/2019 Document: FCAR1920T-1 Version 1.0

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

Guideline for Parallel Grid Exit Point Connection 28/10/2010

SUBSTATION INTERLOCKING SCHEMES

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Procedure PR D Electrical Permits. Engineering Procedure Electrical Distribution Unit. Version 1.0. Date in Force: 4 November 2015

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

ELECTRICITY TRANSMISSION USE OF SYSTEM PRICES - 1 JULY 2014 TO 30 JUNE 2015

Jemena Electricity Networks (Vic) Ltd

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Guidelines for connection of generators:

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Investigation into UK socket-outlets incorporating USB charging points

Summary of Revision, IEEE C , Guide for Breaker Failure Protection of Power Circuit Breakers

Engineering Instruction

Eyre Peninsula electricity supply options investigation

Feasibility Study for the Q MW Solar Project

DESCRIPTION OF REQUIREMENTS FOR GENERATION SYSTEMS SEEKING TO PROVIDE SYSTEM RESTART SERVICES

Interconnection System Impact Study Report Request # GI

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

South Australia Victoria (Heywood) Interconnector Upgrade. RIT-T: Project Specification Consultation Report

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

Climate change drivers for a single and smart EU grid

Case Study on On EHV Circuit Breaker Flashover NTPC-SINGRAULI

Managing Electrical Safety on Boats

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY

1 This instrument must only be used by a competent and trained person and operated in strict accordance with the instructions.

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

Bald Hill on track to start lithium concentrate production this quarter

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Breaker-failure protection RAICA

Installation Power Management Unit Battery Cables and Battery Harness

Protection with distributed generation, experience with the Mont-Soleil wind farm project

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 Lihue, Kauai, Hawaii Original Sheet 5 RULE NO. 2 CHARACTER OF SERVICE

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Small Generator Interconnection Program Interconnection Technical Requirements

Metrohm E3640 FLASH TESTER INSTRUCTION MANUAL. Martindale Electric Co Ltd.

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Failure of Transformer Cable box A case study

EROAD Inspect In-Vehicle User Guide

Emerald Reactive Support Alternative Solution Expressions of interest

Functional Specification Revision History

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

Guidelines when working near TasNetworks electrical assets

Conductor Strength Tests on ACCR 1622TW T13 Pecos Conductor

Shippensburg University

ELECTRICAL SAFETY INSPECTION REPORT

80V 300Ah Lithium-ion Battery Pack Data Sheet

GHA. Gas-Insulated Switchgear. Gas-Insulated Switchgear. Switchgear extension and replacement of a panel

KD LV Motor Protection Relay

Company Directive STANDARD TECHNIQUE: SD4O/1. Standard HV Connection Arrangements

The Energy Queensland Group Notice of no non-network options

TRANSMISSION PLANNING CRITERIA

Presented to the IAPMO Standards Review Committee on December 9, 2013

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

COPPERBELT ENERGY CORPORATION EXPERIENCES ON TWO FAILURES OF MERLIN GERIN TYPE SB6 72 CIRCUIT BREAKERS

Smart Grid Automation and Centralized FISR

100 MW Wind Generation Project

Eyre Peninsula Electricity Supply Options

SERVICES INNOVATION. Montreal Symposium March 29, Jack Simpson Director, Generation & Capacity Planning

EDS FUSE RATINGS AT DISTRIBUTION SUBSTATIONS

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Feasibility Study for the Q MW Solar Project

List of exemptions from compliance with the Technical Rules granted by Western Power after 1 July 2007

PIRS Electrical / electronic

This qualification has been reviewed. The last date to meet the requirements is 31 December 2020.

CHAPTER 4 PROTECTION REQUIREMENTS

HYDRONIC LIFT SOLUTION FOR A3 AMENDMENT

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

Scania Used Vehicle Extended Driveline Warranty

PIX-H Metal-clad switchgear up to 17.5kV

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

EE064D: Circuit Breakers & Switchgears: Design, Testing, Commissioning, Maintenance, Repair & Troubleshooting

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Transcription:

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010 PREPARED BY: Electricity System Operations Planning and Performance FINAL

Disclaimer (a) Purpose - This report has been prepared by the Australian Energy Market Operator Limited (AEMO) for the sole purpose of meeting obligations in accordance with clause.8.15 (c) of the National Electricity Rules. (b) No Reliance or warranty This report contains data provided by third parties and might contain conclusions or forecasts and the like that rely on that data. This data might not be free from errors or omissions. While AEMO has used due care and skill, AEMO does not warrant or represent that the data, conclusions, forecasts or other information in this report are accurate, reliable, complete or current or that they are suitable for particular purposes. You should verify and check the accuracy, completeness, reliability and suitability of this report for any use to which you intend to put it, and seek independent expert advice before using it, or any information contained in it. (c) Limitation of liability - To the extent permitted by law, AEMO and its advisers, consultants and other contributors to this report (or their respective associated companies, businesses, partners, directors, officers or employees) shall not be liable for any errors, omissions, defects or misrepresentations in the information contained in this report, or for any loss or damage suffered by persons who use or rely on such information (including by reason of negligence, negligent misstatement or otherwise). If any law prohibits the exclusion of such liability, AEMO s liability is limited, at AEMO s option, to the re-supply of the information, provided that this limitation is permitted by law and is fair and reasonable. 2011 - Australian Energy Market Operator Ltd. All rights reserved 11 January 2011 Page 2 of 6

1 Introduction At 1119 hrs on 26 September 2010 a busbar fault caused busbars 1 and 2 at the 66 kv New Osborne substation to trip. Both the gas and steam turbines of Osborne power station tripped resulting in 116 MW of generation being disconnected from the power system. Approximately 29 MW of load was also interrupted in the Adelaide region. The 66 kv New Osborne substation was restored by 1326 hrs on 26 September 2010. At 1100 hrs on 27 September Osborne power station was available for dispatch at maximum availability. All references to time in this report refer to Market time (Australian Eastern Standard Time). ElectraNet and Origin Energy have provided relevant information to AEMO for this power system incident investigation. Data from AEMO s Energy Management and Market Systems has also been used in investigating the event. 2 Pre-Contingent System Conditions Prior to the incident at 1119 hrs on 26 September 2010 all network elements connected to the New Osborne 66 kv busbar at the New Osborne substation were in service. The pre-incident state of the busbar can be seen in figure 1. Torrens Osborne Power Osborne Power Torrens 3 (Steam Turbine) (Gas Turbine) 2 Busbar Protection Zone 3 Busbar Protection Zone 2 Busbar Protection Zone 1 Pt. Adelaide 66 kv Busbar 3 66 kv Busbar 2 66 kv Busbar 1 5572 5533 5532 5530 5529 5528 CT 66 kv Busbar 3 5537 66 kv Busbar 2 5536 66 kv Busbar 1 551 5539 5575 552 1 Blackpool Glanville Transformer 5536 Earth Leakage Zone 5535 Largs 2173 11 kv Bus 8 11 kv Bus 9 2170 Closed Circuit Breaker Open Circuit Breaker Energised Conductor De-energised Conductor Figure 1 - New Osborne 66 kv substation at 1119 hrs on 26 September 2010 prior to the incident Prior to the incident the Osborne power station gas turbine was generating at approximately 91 MW and the Osborne power station steam turbine generating at 27 MW. 3 Summary of Events At 1119 hrs on 26 September 2010 busbars 1 and 2 at the 66 kv New Osborne substation tripped due to faults. 11 January 2011 Page 3 of 6

The initial high voltage fault occurred on circuit breaker 5536 C phase current transformer. Following the initial fault another high voltage fault developed on the B-phase current transformer. Both faults were initially located within the bus section 2 protection zone. Consequently bus section 2 protection operated to trip all network elements connected to it. The high voltage fault on the B phase current transformer then spread to bus section 1 protection zone. Busbar 1 protection then operated to trip all network elements connected to bus section 1. The state of the 66 kv busbar at the New Osborne substation after tripping of No.1 and 2 busbar sections is shown in figure 2. Torrens Osborne Power Osborne Power Torrens 3 (Steam Turbine) (Gas Turbine) 2 Busbar Protection Zone 3 Busbar Protection Zone 2 Busbar Protection Zone 1 Pt. Adelaide 5572 5533 5532 5530 5529 5528 CT 66 kv Busbar 3 5537 66 kv Busbar 2 5536 66 kv Busbar 1 551 5539 Flashover 5575 552 1 Blackpool Glanville Transformer 5536 Earth Leakage Zone 5535 Largs 2173 11 kv Bus 8 11 kv Bus 9 2170 Closed Circuit Breaker Open Circuit Breaker Energised Conductor De-energised Conductor Figure 2 - New Osborne 66 kv Substation at 1119 hrs on 26 September 2010 after the operation of busbar 1 and 2 protection systems Protection systems also operated to trip Torrens No. line at the Torrens end. The operation of the busbar 2 protection disconnected the Osborne Power gas turbine from the power system. This caused the Osborne Power steam turbine also to be disconnected. At the time of disconnection Osborne power station was generating 116 MW. Approximately 29 MW of load was also interrupted within the ETSA Utilities network following tripping of busbar 1 and busbar 2 at New Osborne Substation. All connections to the New Osborne busbar were restored by 1326 hrs on 26 September 2010. All load interrupted in the ETSA Utilities network was restored by 119 hrs on 26 September 2010. Osborne Power was made available for dispatch by 1100 hrs on 27 September. Management of Power System Security A bird nest on circuit breaker 5536 C phase current transformer caused a flashover on the primary terminals of the current transformer. This flashover caused another flashover on the primary terminals of the B-phase current transformer. Both flashovers were external to the current 11 January 2011 Page of 6

transformer and caused phase-to-ground faults. Both faults were located in the busbar section 2 protection zone. New Osborne 66 kv busbar 2 earth leakage protection tripped circuit breakers 5530, 5532, 5539, 551, 5536, 5537 and 2173. This caused busbar 2 to be disconnected from, respectively, the: No. Torrens -New Osborne 66 kv line Osborne Power gas turbine New Osborne No. 66/11 kv transformer No.2 Glanville-New Osborne 66 kv line New Osborne 66 kv busbar 1 New Osborne 66 kv busbar 3 The fault was cleared from busbar 2 in 3 ms. The flashover on the B phase current transformer extended to the busbar 1 causing a phase-toground fault in the busbar 1 protection zone. Busbar 1 earth leakage protection tripped circuit breakers 5528, 5529 and 5535. This caused busbar 1 to be disconnected from, respectively, the: No.2 LeFevre-New Osborne 66 kv line Port Adelaide - New Osborne 66 kv line Largs - New Osborne 66 kv line The fault was cleared from busbar 1 in a further 31 ms. Total fault clearance time for the New Osborne 66 kv substation was 65 ms. Fault clearance times met the requirements specified by the National Electricity Rules 1. The Set 2 protection on the No. New Osborne-Torrens 66kV line operated unexpectedly to trip the line from the Torrens end. The trip was initiated by the Set 2 protection at the Torrens substation. At the time of publication of this report ElectraNet was investigating the operation of the Set 2 protection during the incident. At 1218 hrs on 26 September ElectraNet staff arrived at the New Osborne substation to carry out a visual inspection of the faulted equipment. At 1323 hrs ElectraNet began re-energising busbars 1 and 2 of the New Osborne 66 kv substation. By 1338 all circuit breakers connected to New Osborne 66 kv busbar 1 and busbar 2 had been closed with the exception of circuit breaker 5536. Circuit breaker 5536 was isolated so that the faulted equipment could be inspected and repaired. Both the steam and gas turbines of Osborne Power remained out of service. When circuit breaker 5532 opened as a result of the fault in New Osborne Substation the Osborne Power control systems initiated an islanding sequence. The islanding sequence allows the gas turbine to remain in operation whilst being disconnected from the power system. Whilst islanded the gas turbine operates at minimum load and supplies the power station s house load. The islanding sequence also trips steam turbine as the steam turbine is not able to operate when the gas turbine is operating at minimum load. At 1333 hrs permission was given to Osborne power station for the gas turbine to be resynchronised through circuit breaker 5532. However circuit breaker 5532 was not able to be closed due to a synchronisation inhibit signal being received by the station s control system. 1 See Schedule S5.1a.8(b) of the National Electricity Rules. 11 January 2011 Page 5 of 6

At 130 hrs staff at Osborne Power attempted to synchronise through the generator circuit breaker rather than through circuit breaker 5532. The generator circuit breaker was opened and circuit breaker was 5532 closed to prepare for synchronisation through the generator circuit breaker. Attempts to synchronise the gas turbine at 1350 hrs and 139 hrs through the generator circuit breaker were not successful due to the continued presence of synchronisation inhibit signal. At 2130 hrs the Osborne power station staff determined that the reason for the synchronisation inhibit signal associated with the generator circuit breaker was caused by a faulty relay switch. The generator circuit breaker and associated faulty relay switch are both located within the Osborne Power. By 2330 hrs the faulty relay had been repaired and tested. The Gas Turbine was started at 0800 on 27 September and Osborne Power was made available for dispatch at 1100 hrs on 27 September. 5 Follow-up Actions Circuit breaker 5536 B phase current transformer was replaced on 18 October 2010. The top sections of circuit breaker 5537 current transformers were cleared of bird nests on 29 September 2010 and the top sections of circuit breaker 5536 current transformers were cleared of bird nests on 10 October 2010. The Osborne power station synchronisation inhibit signal associated with the circuit breaker 5532 was found to be caused by the way the generator control system had been programmed. The synchronisation inhibit had been programmed in this manner to prevent the unintentional remote synchronisation of the gas turbine. Operating procedures at Osborne Power have since been updated to reflect the control system programming. At the time of publication of this report ElectraNet was investigating the operation of the No. New Osborne-Torrens 66kV line Set 2 protection during the incident. ElectraNet intend to complete the investigation by the end of January 2011. 6 Recommendations ElectraNet will inform AEMO of the outcome of its investigation of the operation of the Set 2 protection at Torrens by the end of January 2011. It is recommended that AEMO raise the outcomes of ElectraNet s review of the operation of the Set2 protection at Torrens with other transmission network service providers. 11 January 2011 Page 6 of 6