Power Arc Testing on Insulator Sets

Similar documents
TEKNISK RIKTLINJE TR05-10E

Switching Impulse Flashover Tests and Analysis for 765kV Jumper V-strings with Damaged Insulators

Glass insulators for kv overhead lines and substations. Global Insulator Group

ENERGY /// TRANSMISSION LINE SURGE ARRESTERS IEC. Bowthorpe EMP Transmission Line Surge Arresters (IEC)

Successful New Technology Introduction and Applications of Rotary Steerable System.

Key elements of the AS3000 Wiring standards and some of the recent changes.

IEC Standard Compliant Vacuum Circuit-Breaker (12 kv, 24 kv) for Southeast Asian Markets

Extremely High Load Capacity Tapered Roller Bearings

High Voltage Surge Arresters Buyer s Guide Section Line Surge Arrester PEXLINK

High Voltage Technology & Testing

High voltage products PASS M0S 252 kv Innovative solution for transmission substation up to 252 kv

SKF Explorer spherical roller bearings Optimized for superior field performance

Electric Field Modelling of Non-Ceramic High Voltage Insulators

INTERNATIONAL STANDARD

Regenerative Utility Simulator for Grid-Tied Inverters

Accelerating the Development of Expandable Liner Hanger Systems using Abaqus

Exceeding the standards with MNS

New fem model for thermal analysis of medium voltage fuses

The comprehensive portfolio of the testing laboratories at Schaltwerk Berlin siemens.com/energy/psw

MHI Integrally Geared Type Compressor for Large Capacity Application and Process Gas Application

Protecting the environment and your bottom line

APPLICATION NOTE. Selecting Inductors for DC-DC Converters and Filters in Automotive Applications INTRODUCTION. 9/13 e/ic1338

ELECTRIC STRESS ANALYSIS ON 11KV INSULATOR

CONTRIBUTION TO THE CINEMATIC AND DYNAMIC STUDIES OF HYDRAULIC RADIAL PISTON MOTORS.

CAE Analysis of Passenger Airbag Bursting through Instrumental Panel Based on Corpuscular Particle Method

Life cycle services for protection and control relays Full support from start to finish

Traffic Micro-Simulation Assisted Tunnel Ventilation System Design

Chapter 6 Generator-Voltage System

Interruption Technology of Breakers for High-voltage Direct Current

Role of Aerodynamics and Thermal Management in the Vehicles of Tomorrow

High Voltage Surge Arresters Buyer s Guide Section Transmission Line Arrester PEXLINK

RODURFLEX LAPP INSULATOR COMPANY LLC THE POWER OF RELIABILITY THE COMPOSITE INSULATOR SYSTEM. Over 30 Years Experience with the RODURFLEX System

Implementation of low inductive strip line concept for symmetric switching in a new high power module

All-SiC Module for Mega-Solar Power Conditioner

Zero Energy Verification An Alternative Approach. Timothy Snow CESCP Electrical Safety Officer

Simulation of Structural Latches in an Automotive Seat System Using LS-DYNA

produces and delivers products worldwide can provide the optimal solution for your requirements. are dedicated to supplying you with

Effect of Compressor Inlet Temperature on Cycle Performance for a Supercritical Carbon Dioxide Brayton Cycle

Automated Seat Belt Switch Defect Detector

Modeling the Lithium-Ion Battery

Outdoor Distribution (15 kv through 25 kv) S&C Fault Tamer Fuse Limiter

Cost Benefit Analysis of Faster Transmission System Protection Systems

Research Brief. Simulation and verification of results from 125mph current collection modelling for two pantographs. T841 - January 2011.

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Diagnostic Experience on HV Bushings Retired from Service MANUEL GUZMÁN-V

Breaking new ground. A circuit breaker with the capacity to switch 15 large power plants

S&C Fault Tamer Fuse Limiter. Outdoor Distribution (15 kv through 25 kv)

Xiria 12 kv Ring Main Unit in IEC and ENATS design

Transforming Transforming Advanced transformer control and monitoring with TEC

Xiria the smart solution

CATALOG NUMBER 081 BALTIMORE, MARYLAND

Reviewed: DD Month University Code of Practice for Electrical Safety. PART B - Design and Construction of Electrical Equipment within the University

Low-torque Deep-groove Ball Bearings for Transmissions

RICHARD BERGNER ELEKTROARMATUREN GMBH & CO. KG

For Electrical Networks

ALWAYS ON THE SAFE SIDE

ISA. for greater social responsibility and better competitiveness

VEIKI-VNL Electric Large Laboratories Ltd. H-1158-Budapest, Vasgolyó utca 2-4. HUNGARY

INFLUENCE OF TEMPERATURE ON THE PERFORMANCE TOOTHED BELTS BINDER MAGNETIC

POLYMER INSULATOR. Index

DEPARTMENT OF ELECTRICAL ENGINEERING DIT UNIVERSITY HIGH VOLTAGE ENGINEERING

RTM COMPOSITE LUGS FOR HIGH LOAD TRANSFER APPLICATIONS

Latest Results in the CVT Development

Anti-Icing System on Nordex wind turbines - lightning protection and operating experience. Dr. J. Birkemeyer. Winterwind

INTERNATIONAL STANDARD

CONTENTS. Precision Technology Inside P. 4. Bearing Tables P. 8 P. 78 P. 84 P. 102 P. 112 P Engineering P. 134 P. 143 P. 150 P. 162 P.

Balancing of aeroderivative turbine

Gasket Simulations process considering design parameters

AC..CS SAFETY WIREWOUND RESISTOR

Reliability determination of ignition system of rocket platform using reliability block diagram and FMEA analysis

Pantograph and catenary system with double pantographs for high-speed trains at 350 km/h or higher

Is Low Friction Efficient?

SUBSTATION OPERATION. Maintenance Techniques. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

CHAPTER 5 FAILURE ANALYSIS OF MAIN BEARING

Xiria the smart solution

Live-line transmission lines upgrade projects. First-in-Africa project

Electrical Safety. Facilitator Guide

Safety factor and fatigue life effective design measures

BHATINDA CERAMICS PRIVATE LIMITED (Mfrs/Exporters of High Tension Porcelain Insulators)

TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH

Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA

A manufacturer s view of bushing reliability, testing and analysis. Lars Jonsson Håkan Rudegard

Xiria 24 kv Ring Main Unit

ABB low voltage wind turbine converters Reliable technology for wind power

Transmission Line Arrester TLA

ECHO* String Trimmer Technical Study

Type HS PEXLIM-P Surge Arresters Maximum System Voltage 123 kv to 800 kv

Overcoming Motor Driver Heat-Transfer Challenges in Robotic Applications

I Surge Arresters. UltraSIL Polymer-Housed VariSTAR Type U3 Surge Arrester for Systems through 275 kv IEC 10 ka; Line Discharge Class 3 GENERAL

Evaluation of a Gearbox s High-Temperature Trip

Tips & Technology For Bosch business partners

A CASE STUDY ON IMPLEMENTATION OF HYDRAULIC JACK TO HEAVY LOADED VEHICLES

PORCELAIN INSULATORS

H U B B ELL L ABOR ATORIES CAPABILITY GUIDE

TERMINATION TECHNOLOGIES FOR HAZARDOUS AREAS A practical guide

Air Oil Lubrication Bearings with Re-lubricating Hole on the Outer Ring for Machine Tool

HIGH VOLTAGE CURRENT LIMITING FUSE-LINKS CAPABLE OF BREAKING ALL CURRENTS THAT CAUSE MELTING OF THE FUSE-ELEMENT. D. van der Scheer H.F.J.

High Capacity Tapered Roller Bearings

This presentation focuses on Biodiesel, scientifically called FAME (Fatty Acid Methyl Ester); a fuel different in either perspective.

PROJECTS $500K AND OVER FOR 2014

Transcription:

Power Arc Testing on Insulator Sets Abstract:Insulator sets are among the most common components in transmission networks and their quality and performance play a vital role in ensuring a reliable electricity supply. A key part of that is their behaviour when exposed to a power arc. Poor design with respect to power arc behaviour can significantly reduce the lifetime of the insulator set and increase the likelihood of supply interruptions. There are a wide variety of insulating material options and environments in which insulator sets are used. As such, insulator set designs vary considerably and may even need to be tailored for specific applications. Even the smallest differences in design can affect the power arc behaviour of a string. Physical testing is the most reliable way to assess a string s power arc behavior and therefore utilities increasingly demand that insulator sets undergo power arc testing before they commit to installing them on their networks. Over the last several years, KEMA Laboratories, Prague carried out over 160 power arc tests on insulator sets of various types. These tests were performed according to IEC 61467:2008. In addition to revealing the most common failure modes for different types of insulator sets, this overview contributed by Robert Jech highlights a potential issue with how IEC 61467:2008 is currently defined. This is an issue that could impact the value utilities derive from today s tests. The insight gained from this will provide insulator set manufacturers with useful input into how best to design strings to increase the chances of first-time success in testing and thereby reduce the time and money spent on redesigns. It may also stimulate discussion around the specification of the standard to ensure it meets the needs of manufacturers and utilities equally.

Description of Power Arc Tests Power arc testing of insulator sets at KEMA is performed according to the IEC 61467:2008 standard. This standard applies to insulator strings or sets comprised of ceramic, glass or composite materials that will be mounted on metallic poles or towers and used in AC overhead lines with a nominal voltage above 1000 V. The standard defines methods, parameters, circuits etc. for power arc tests on both insulator sets and short strings. Different test arrangements are allowed within the standard and choice depends on the final application of the insulator sets, according to customer requirements. The test circuit and series should be chosen based on factors such as geometry and type of insulator, its position on the line and type of tower. Test Arrangements A set s intended position on a line determines whether it should be tested with a balanced or unbalanced supply circuit and, depending on line parameters, short-circuit current to be used during testing. If the insulator set will be positioned in the first or last 5% of a line, it should be tested with an unbalanced supply circuit while sets to be located between the 5% and 95% points of the line require a balanced supply circuit for testing. Similarly, sets for the middle section (i.e. from 24% to 76% of the line length) require only 20% of the rated short-circuit current of the network. Sets for use at locations between the 5% and 24% points or 76% and 95% points require 50% and sets in the first or last 5% require the full short-circuit current of the network. Meanwhile, type of tower governs choice of a balanced or unbalanced return circuit during testing. Sets to be used in the center phase window of a tower require testing with a balanced return circuit

(referred to as test series X). For outer positions on the tower or where there is no center phase window, an unbalanced return circuit is used (referred to as test series Y). Furthermore, the number of tests to be performed depends on whether the customer intends the same type of set to be used throughout the line (in which case the complete test series X or Y is performed) or in just along part of the line. Fig. 1 shows a typical test arrangement for a V-string set with composite insulator This test arrangement comprises balanced supply and return circuits. The arrangement pictured simulates an insulator set position between the 5% and 95% points of the line in the center phase window of the tower. Depending on type of insulator set, IEC 61467:2008 standard may also require that it undergo verification tests in addition to the power arc test, the main being the mechanical failing load test (MFLT). This is performed on the insulator units to ensure they can withstand mechanical forces after a power arc is applied. Insulator sets may also be required to undergo a dry power frequency flashover (DPFF) test to ensure the insulator does not suffer punctures at voltages below the flashover voltage. Additional electrical tests may be performed on the fittings and conductors within the insulator set to verify withstand capabilities. Statistical Overview of Tests Analysis of results of tests carried out on 162 insulator sets over a five-year period is shown below: Types of Insulator Sets & Components Insulator sets come in a number of different design types and insulating materials, depending on the intended application. The insulator sets tested during the five-year period comprised:

92 suspension sets 49 tension sets 17 V strings 4 cross-arm insulators In terms of the insulating material used and insulator design, insulator sets tested included: 81 composite 34 glass, cap & pin 12 glass, cap & pin (short string) 27 porcelain, long rod 8 porcelain, cap & pin Failure Rates As shown in Fig. 2, 66% of components tested successfully completed a full test sequence. Only one set suffered a separation failure during the arc test. DPFF tests were not performed on an additional 35 sets and no MFLT was performed on an additional 10 sets. These 45 sets are not included among those sets that successfully completed testing even if no failure occurred during those tests. IEC 61467:2008 specified an MFLT for all 162 insulator sets tested. One set failed before the MFLT could be performed and the results for the remaining 161 sets are shown in Fig. 3. Of these, MFLTs were not required by the customer for 10 sets. Consequently, 151 MFLTs were performed during the period covered, with 145 sets passing and 6 failing. Similarly, the standard specified DPFF tests for 54 of the sets, and the results are summarized in Fig. 4. DPFF tests were not required by the

customer for 36 sets and therefore 18 DPFF tests were carried out with no failures. Keywords: Power, Arc Testing, Insulator