Eyre Peninsula electricity supply options investigation

Similar documents
Eyre Peninsula Electricity Supply Options

Northern South Australia Region Voltage Control

REGIONAL VICTORIAN THERMAL CAPACITY UPGRADE RIT-T PROJECT ASSESSMENT CONCLUSION REPORT

South Australia Victoria (Heywood) Interconnector Upgrade. RIT-T: Project Specification Consultation Report

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

Powering Sydney s Future

Revenue Stacking in the NEM

For personal use only

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Emerald Reactive Support Alternative Solution Expressions of interest

15 Nelson-Marlborough Regional Plan

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By

15 Nelson-Marlborough Regional Plan

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

Jemena Electricity Networks (Vic) Ltd

CRYPTOCURRENCY MORATORIUM SMALL MINER RATE IMPACT. September 4, 2018

UNLOCKING VALUE: MICROGRIDS AND STAND ALONE SYSTEMS

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

RENEWABLES INTEGRATION STATUS REPORT

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

TORONTO TRANSIT COMMISSION REPORT NO.

The Energy Queensland Group Notice of no non-network options

100 MW Wind Generation Project

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

National Seniors Association 18 October 2010 Jo Benvenuti David Stanford

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

The Development of Competitive Renewable Energy Zones in Texas

The Gambia National Forum on

Transmission Connection and Charging Methodologies for Integration of Renewable Energy in Australia

Proposed Dounreay - Mybster 275 kv / 132 kv

Final Project Assessment Report (FPAR)

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

2015 Grid of the Future Symposium

ABB POWER SYSTEMS CONSULTING

Developments in Retail Electricity Markets

Basic Connection Services Application and Price Guide

Electricity Networks Inter-regional market co-ordination (Session 8)

Copyright and Disclaimer

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION

The Grid Link Project. Summary of the Report for the Independent Expert Panel

RIIO-T2 Energy Scenarios

Merger of the generator interconnection processes of Valley Electric and the ISO;

Distributed Energy Resources Grid Connection Guidelines

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

JEA Distributed Generation Policy Effective April 1, 2018

CHAPTER 8 - GAS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY

CHAPTER 2 - NETWORK DEVELOPMENT UPDATES FOR 2011

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Broken Hill Solar Plant. Community Information Session 9 September 2015

Annual Distribution Pricing Proposal For 1 July 2018 to 30 June 2019 Overview

Generation Connections Industry Workshop 2017

The Green Line Project

New 115 kv Disconnect Switches at Bloomsburg MTS

GRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT

RENEWABLE ENERGY IN JORDAN What had to be done 8 Oct 2017

New Mexico Transmission Expansion Concepts For Wind Resources

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

PSE Attachment K Puget Sound Area Transmission Meeting

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Net Metering Policy Framework. July 2015

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Key DRAFT OPERATING CODE 2 LEGAL TEXT

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Addressing ambiguity in how electricity industry legislation applies to secondary networks

Statement of Expected Price Trends

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

AER Issues Paper Regulating innovative energy selling business models under the National Energy Retail law

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Street Lighting Procurement Stage 2

Electricity industry structure and capacity growth trends

SUPPLEMENTARY EVIDENCE FROM SCOTTISH AND SOUTHERN ENERGY

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

Discussing the Ratepayer Benefits of EVs On the Electrical Grid

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

BUILDING A LEVEL PLAYING FIELD FOR LOCAL ENERGY WITH LOCAL NETWORK CREDITS AND VIRTUAL NET METERING

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Rule 21 WG #3 Issue #23. V2G Interconnection Issue Proposal Follow-Up January 17, 2019

Decision on Merced Irrigation District Transition Agreement

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Western NY Public Policy Transmission Planning Report

WESTERN EIM BENEFITS REPORT Second Quarter 2018

Overview of ISO New England and the New England Wholesale Power Markets

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

City of Palo Alto (ID # 6416) City Council Staff Report

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

Sunnyside Yard Master Plan. RFQ Information Session September 13, 2017

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Behind the Meter Net Generation Model Cost Allocation for BTM Loads

Large Embedded Generation User Guide A

WHEREAS, LADWP seeks to enable the continued growth of customer generation, including solar-powered generation; and

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Bohn to Kettle River Transmission Project

Transcription:

20 November 2017 South Australia s electricity transmission specialist Eyre Peninsula electricity supply options investigation Project Assessment Draft Report Port Lincoln Public Forum electranet.com.au

Purpose ElectraNet is committed to running an open and transparent process to find the best options for affordable and reliable electricity supply > Present the findings of the Project Assessment Draft Report (PADR) published on 16 November 2017 > Provide the opportunity to clarify understanding > Invite feedback from customers and stakeholders as input to the next phase of ElectraNet s investigation 2

Outline Item Presenter/ Facilitator 1. Background and overview Rainer Korte 2. Options considered Brad Parker 3. Economic assessment and key outcomes Ann Whitfield and Tom Graham from HoustonKemp 4. Q & A session Rainer Korte 5. Next steps Rainer Korte 3

20 November 2017 South Australia s electricity transmission specialist Background and overview Rainer Korte Executive Manager Asset Management electranet.com.au

Eyre Peninsula transmission network > Existing radial line is close to full capacity with limited potential to meet increased demand > Asset condition challenges with line >45 years old Current maximum demand is about 55 MW southwest of Cultana with about 35 MW at Port Lincoln > Port Lincoln supply reliability includes network support from 3 x 25 MW diesel-fired gas turbines 5

Identified need Providing reliable electricity supply to Port Lincoln most cost effectively in the future Key drivers: > The need to replace existing transmission line components in the next few years > The upcoming expiry of the network support arrangement at Port Lincoln (at end 2018) ElectraNet is investigating the best option for meeting this need via a formal Regulatory Investment Test for Transmission (RIT-T) process under the National Electricity Rules 6

Eyre Peninsula reliability standards Electricity Transmission Code 1 specifies minimum reliability standards Exit point Description 2 Middleback (Category 1) Wudinna and (Category 2) Port Lincoln (Category 3) Provide N equivalent line and transformer capacity for 100% of contracted demand (i.e. with all transmission elements in service) Provide N equivalent line capacity for 100% of contracted demand (i.e. with all transmission elements in service) Provide N-1 equivalent transformer capacity for 100% of contracted demand (i.e. with any one element out of service) Provide N-1 equivalent line and transformer capacity for 100% of contracted demand (i.e. with any one element out of service), including the use of post-contingent network support operation 1 TC09 July 2018 2 Restoration standards also apply in each case For more information see www.escosa.sa.gov.au 7

Regulatory Investment Test (RIT-T) > The economic cost benefit test that applies to all major network investments in the National Electricity Market > Is overseen by the Australian Energy Regulator (AER) > Applies to network investments expected to cost more than $6m > Considers all technically and economically feasible options to meeting an identified need (such as a network limitation or constraint) > Both network and non-network solution options are considered > Involves an open and transparent public consultation process For more information see www.aer.gov.au 8

RIT-T process TNSP identifies network limitation and possible options TNSP prepares project assessment draft report (PADR) TNSP prepares project specification consultation report (PSCR) TNSP assesses submissions and makes adjustments as necessary TNSP assesses submissions and determines credible options 12 weeks for submissions We are here (PADR published 16 Nov 2017) TNSP issues project assessment conclusions report (PACR) 6 weeks for submissions 30 days to raise a dispute TNSP undertakes cost benefit assessment and determines preferred option AER undertakes dispute process if the outcome is disputed TNSP = Transmission Network Service Provider 9

Consultation to date Milestone Timing Project consultation report (PSCR) published 28 April 2017 Public forums (Port Lincoln and Adelaide) 26 and 29 June 2017 Submissions on PSCR (15 received) 21 July 2017 Draft report (PADR) published 16 Nov 2017 Public forums (Port Lincoln and Adelaide) 20 and 27 Nov 2017 Submissions due on PADR 19 Jan 2018 Final report (PACR) April 2018 AER makes ruling on final report Mid-2018 10

Key issues in submissions to PSCR Issue Raised A 500 kv line option should be considered, to enable the connection of more renewable generation Eyre Peninsula should be considered for inclusion as a Renewable Energy Zone in the Integrated Grid Plan recommended by the Finkel Review The ability for new wind farms to export renewable energy to the Eastern States will be influenced by whether or not a new interconnector to the eastern states is constructed There are community concerns about the historical performance of the existing Port Lincoln Power Station Battery storage should be considered as a short-term option ElectraNet Comment ElectraNet will assess whether the additional benefits of a 500 kv option would exceed the additional costs We agree and are working with AEMO on development of an Integrated Grid Plan Economic analysis will consider scenarios with and without a new interconnector We are analysing a range of generation and other technology proposals that were received in response to the PSCR 11

Key issues in submissions to PSCR Issue Raised There are potential future large mining load connections on the Eyre Peninsula There is significant uncertainty regarding whether potential new projects will proceed A ring route for the Eyre Peninsula should be considered Upgrades to the Eyre Peninsula transmission system will be paid for by South Australian consumers more broadly, and need to be considered in the light of recent extreme electricity price increases ElectraNet Comment We are assessing option value of staged developments as a component of the economic analysis The viability of new transmission line options including from Cultana to Port Lincoln via Wudinna has been explicitly considered in the analysis Full line replacement would proceed only if benefits to customers exceed costs 12

Draft report overview > Report considers most economic long-term electricity supply solution for the Eyre Peninsula > Variants of five credible options have been assessed, including staged options for future proofing > Report finds that building a new transmission line to supply the Eyre Peninsula is the most cost effective long-term solution > We ve tested this draft conclusion under a range of alternative assumptions about the future and with detailed sensitivity analysis > We seek your feedback on the draft report and its findings 13

Draft preferred option 1 Wudinna Cultana Davenport Central Middleback Stony Pt > A new double circuit 275 kv transmission line from Cultana to and a new double circuit 132kV line from to Port Lincoln > Estimated to cost $300m Legend 275 kv Pt Lincoln Sleaford Cathedral Rocks West Mt Millar 1 The preferred option is the one that delivers the greatest expected net benefits under the RIT-T economic assessment > Adding less than $3 to transmission component of the annual electricity bill for average residential customer in SA > Net market benefits of $120m over 20 years > Broader economic benefits will also be realised 14

20 November 2017 South Australia s electricity transmission specialist Options considered Brad Parker Network Planning Manager electranet.com.au

Five broad options considered Supply Option Option 1 Option 2 Option 3 Option 4 Option 5 Description Replace components of the existing single-circuit line between Cultana and Port Lincoln and continue network support at Port Lincoln Replace the existing single-circuit line between Cultana and Port Lincoln with a new double-circuit line Replace the existing single-circuit line between Cultana and Port Lincoln with two new single-circuit lines along different routes Replace the existing single-circuit line between Cultana and Port Lincoln with a new double-circuit line, at least part of which is capable of 275 kv operation Replace the existing single-circuit line between Cultana and Port Lincoln with two new single-circuit lines along different routes, at least some of which are capable of 275 kv operation 16

Option 1 Davenport Cost: $80 million Wudinna Cultana Central Middleback > New long-term network support arrangement required at Port Lincoln Mt Millar > Maintains existing capacity Legend 275 kv Section to be re-conductored Network support arrangement Cathedral Rocks Sleaford Pt Lincoln > No capability to connect potential future medium or large mining loads > Any new generators likely to be significantly constrained 17

Option 2 Wudinna Davenport Cultana Stony Pt Central Middleback Cost: $220 million > Each new line would have about 300 MVA capacity Legend 275 kv Mt Millar > Capable of accommodating potential future small to medium mining loads Cathedral Rocks Pt Lincoln Sleaford > Can facilitate new generator connections of up to about 300 to 400 MW 18

Option 3 Davenport Cost: $390 million Wudinna Cultana Central Middleback Stony Pt > Each new line would have about 300 MVA capacity Legend 275 kv Cathedral Rocks Sleaford Pt Lincoln Mt Millar > Capable of accommodating potential future small to medium mining loads > Can facilitate new generator connections of up to about 300 to 400 MW 19

Option 4A Davenport Cost: $390 million Wudinna 275kV Cultana Middleback Central Stony Pt > Each new 275 kv line would have about 600 MVA capacity 275kV Mt Millar > Capable of accommodating potential future large mining loads Legend 275 kv Cathedral Rocks Pt Lincoln Sleaford > Can facilitate new generator connections of up to about 1000 MW 20

Option 4B Davenport Cost: $300 million Wudinna West Mt Millar Cultana Stony Pt Central Middleback > Each new line would have about 300 MVA capacity > Each new 275 kv line would have about 600 MVA capacity Legend 275 kv > Capable of accommodating potential future large mining loads Pt Lincoln Sleaford Cathedral Rocks > Can facilitate new generator connections of up to about 1000 MW 21

Option 4C Cost: $310 million Legend 275 kv Wudinna 275kV energised at 275kV energised at Mt Millar Cultana Middleback Davenport Central Stony Pt > Each new line would initially be operated at, with a capacity of about 300 MVA > If upgraded to 275 kv in future, each line would have capacity of about 600 MVA > Capable of accommodating potential future large mining loads Cathedral Rocks Pt Lincoln Sleaford > Can facilitate new generator connections of up to about 1000 MW after upgrade to 275 kv 22

Option 4D Cost: $270 million Wudinna 275kV energised at Mt Millar Davenport Cultana Stony Pt Central Middleback > Each new line would initially be operated at, with a capacity of about 300 MVA > If upgraded to 275 kv in future, each line would have capacity of about 600 MVA Legend 275 kv > Capable of accommodating potential future large mining loads Cathedral Rocks Pt Lincoln Sleaford > Can facilitate new generator connections of up to about 1000 MW 23

Option 5A Wudinna Cultana Central Middleback Davenport Stony Pt Cost: $610 million > Each new 275 kv line would have capacity of about 600 MVA West Mt Millar > Capable of accommodating potential future large mining loads Legend 275 kv Cathedral Rocks Sleaford Pt Lincoln North Pt Lincoln > Can facilitate new generator connections of up to about 1000 MW 24

Option 5B Legend 275 kv Cathedral Rocks Wudinna Sleaford Pt Lincoln Mt Millar Davenport Cultana Stony Pt Central Middleback Cost: $450 million > Each new line would have a capacity of about 300 MVA > Each new 275 kv line would have capacity of about 600 MVA > Capable of accommodating potential future large mining loads > Can facilitate new generator connections of up to about 400 to 600 MW 25

Option 5C Legend 275 kv Wudinna 275kV energised at Cathedral Rocks Sleaford 275kV energised at 275kV energised at Pt Lincoln 275kV energised at Mt Millar Cultana Davenport Central Middleback Stony Pt Cost: $500 million > Each new line would initially be operated at, with a capacity of about 300 MVA > If upgraded to 275 kv in future, each line would have capacity of about 600 MVA > Capable of accommodating potential future large mining loads > Can facilitate new generator connections of up to about 1000 MW 26

20 November 2017 South Australia s electricity transmission specialist Economic assessment and key outcomes Ann Whitfield and Tom Graham HoustonKemp electranet.com.au

Q & A session 28

Next steps ElectraNet is committed to running an open and transparent process to find the best option for affordable and reliable electricity supply Milestone Timing Project consultation report (PSCR) published 28 April 2017 Public forums (Port Lincoln and Adelaide) 26 and 29 June 2017 Submissions on PSCR (15 received) 21 July 2017 Draft report (PADR) published 16 Nov 2017 Public forums (Port Lincoln and Adelaide) 20 and 27 Nov 2017 Submissions due on PADR 19 Jan 2018 Final report (PACR) April 2018 AER makes ruling on final report Mid-2018 29