Illinois State Report

Similar documents
New Jersey State Report

2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017)

Pennsylvania State Report

2016 Load & Capacity Data Report

Reliability Analysis Update

Energy Policy Implications: PJM Planning

Market Efficiency Update

Reliability Analysis Update

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

Market Efficiency Update

Transmission Expansion Advisory Committee

Market Efficiency Update

Merger of the generator interconnection processes of Valley Electric and the ISO;

100 MW Wind Generation Project

Sub Regional RTEP Committee - Southern. August 19, 2011

New 115 kv Disconnect Switches at Bloomsburg MTS

Market Efficiency Update

4.7: New Jersey RTEP Overview

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Sub Regional RTEP Committee Western Region ATSI

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Sub Regional RTEP Committee South

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Sub Regional RTEP Committee Mid-Atlantic

Supplemental Report on the NCTPC Collaborative Transmission Plan

Sub Regional RTEP Committee South

Feasibility Study Report

Sub Regional RTEP Committee Mid-Atlantic

Sub-Regional RTEP Committee PJM South

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Market Efficiency RTEP Proposal Window

Transmission Expansion Advisory Committee. Reliability Analysis Update

SERTP rd Quarter Meeting

Falcon-Midway 115 kv Line Uprate Project Report

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012

ATTACHMENT Y STUDY REPORT

Interconnection Feasibility Study Report GIP-226-FEAS-R3

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

ELECTRIC TRANSMISSION 101: Operational Characteristics. Wayne Galli, Ph.D., P.E. Executive Vice President Clean Line Energy Partners LLC

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Feasibility Study Report

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Designated Entity Pre-Qualification Materials. Exelon Corporation

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Manual 3: Transmission Operations Updates Version 52

The Transmission Lay of the Land

Feasibility Study Report

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

PJM Regional Transmission Expansion Planning (RTEP) Process

Transmission Expansion Advisory Committee

Decision on Merced Irrigation District Transition Agreement

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

West Virginia Energy Plan and Becoming an Electric Generator

Manual 3: Transmission Operations Updates Version 52

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

Western Area Power Administration

GRID INNOVATION CAUCUS CO-CHAIRS

NATIONAL CONFERENCE of STATE LEGISLATURES. October 9 th, 2009 Ervan Hancock

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Generation Deactivation Notification Update

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Sub Regional RTEP Committee Mid-Atlantic

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Effects of Smart Grid Technology on the Bulk Power System

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

2018 Load & Capacity Data Report

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

PSE Attachment K Puget Sound Area Transmission Meeting

2015 Grid of the Future Symposium

Sub Regional RTEP Committee Mid-Atlantic

APPENDIX F: Project Need and Description

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

MILLIGAN SOLAR PROJECT

Facilities Study for Alberta to US Available Transfer Capability

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Appendix D Black Hills Project Summary

Impacts of MISO DPP-2016-August Projects on PJM Facilities

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Interconnection System Impact Study Report Request # GI

System Impact Study Report

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Interconnection Feasibility Study Report GIP-369-FEAS-R1

EXCEPTIONS TO RELIABILITY RULES REVISION 4 MAY 8, 2015

3 Existing National Grid

Impact of Distributed Energy Resources on Transmission System Reliability

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

FERC 101 for Environmental Lawyers. Linda L. Walsh Hunton & Williams LLP February 11, 2015

NYISO Market Initiatives

Sub Regional RTEP Committee - Southern

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Transcription:

July 2016 Illinois State Report

Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2

Executive Summary (July 2016) Existing Capacity: Nuclear represents 41 percent of the total installed capacity in Illinois while natural gas represents 42 percent. This differs from PJM where natural gas and coal are relatively even at 34 and 35 percent respectively. Interconnection Requests: Natural gas represents 91 percent of new interconnection requests in Illinois. Deactivations: Approximately 251 MW of capacity in Illinois retired in 2015. This represents two percent of the 10,200 MW that retired RTO-wide in 2015. Load Forecast: Illinois load growth is nearly flat, averaging less than one percent per year over the next 10 years. This aligns with PJM RTO load growth projections. Natural Gas: About 31 percent (3,300MW) of Illinois s natural gas generation is behind a local distribution company. 3

PJM Evolution State-specific data in this deck only applies to the PJM portion of Illinois 4

PJM Service Area Illinois (December 31, 2015) PJM operates the bulk electric system facilities (and others monitored at lower voltages), in northern Illinois. This map includes those of Commonwealth Edison (ComEd). Northern Illinois s transmission system delivers power to customers from native generation resources and those throughout the RTO arising out of PJM market operations as well as power imported interregionally from systems outside PJM. 5

Planning Generation Portfolio Analysis 6

Illinois - Existing Installed Capacity (Capacity Rights, December 31, 2015) Summary: Nuclear represents 41 percent of the total installed capacity in Illinois while natural gas represents 42 percent. Overall in PJM, natural gas and coal are relatively even at 34 percent and 35 percent respectively. * Gas Contains Natural Gas Other Gas 10,670 MW 12 MW 7

PJM - Existing Installed Capacity (Capacity Rights, December 31, 2015) In PJM, natural gas and coal make up nearly 70 percent total installed capacity. * Gas Contains Natural Gas Other Gas 57,735 MW 399 MW 8

Natural gas represents 91 percent of new interconnection requests in Illinois. Total MW Capacity by Fuel Type Illinois - Interconnection Requests (Requested Capacity Rights, December 31, 2015) MW # of Projects Active 5,650.2 38 Under Construction 240.4 11 Suspended 142.0 2 Total 6,032.6 51 Fuel as a Percentage of Projects in Queue 9

MW Illinois - Interconnection Requests (Requested Capacity Rights, December 31, 2015) Active In Service Suspended Under Construction Withdrawn Total Sum # of Projects MW # of Projects MW # of Projects MW # of Projects MW # of Projects MW # of Projects Biomass 0 0 0 0 0 0 0 0 90 3 90 3 Coal 0 0 0 0 0 0 0 0 3652 5 3652 5 Diesel 0 0 22 2 0 0 0 0 0 0 22 2 Hydro 0 0 0 0 0 0 22.7 2 0 1 22.7 3 Methane 30.8 3 20.44 4 0 0 15.3 1 51.17 12 117.71 20 Natural Gas 5,410.3 16 1,335.6 11 0 0 80 4 2,385 6 9,210.9 37 Nuclear 0 0 385.8 10 0 0 0 0 782 5 1,167.8 15 Oil 0 0 0 0 0 0 0 0 0 0 0 0 Solar 0 0 3.4 1 0 0 0 0 32.25 7 35.65 8 Storage 0 8 0 4 0 0 0 1 0 4 0 17 Wind 209.1 11 579 19 142 2 122.4 3 2,110.025 86 3,162.525 121 Wood 0 0 0 0 0 0 0 0 0 0 0 0 Other 0 0 20 1 0 0 0 0 0 0 20 1 Total 5,650.2 38 2,366.24 52 142 2 240.4 11 9,102.45 129 17,501.29 232 10

Illinois - Progression History Interconnection Requests (Requested Capacity Rights, 2003 2015) Following agreement (ISA/WMPA) execution, 844 MW of capacity withdrew from PJM's interconnection process. Another 382 MW have executed agreements but were not in service as of December 31, 2015. Overall, 20 percent of requested capacity in the PJM portion of Illinois reaches commercial operation. The PJM average over this time is 10% 11

Illinois 2015 Generation Deactivations (MW Capacity, December 31, 2015) Unit MW Capacity TO Zone Age Will County 3 251 ComEd 57 4/15/2015 Generation announced future deactivation in 2015 Will County 4 510 ComEd 52 5/31/2018* * On 6/3/2016, Will County 4 submitted a new projected deactivation of 5/31/2020. Summary: Actual/Projected Deactivation Date 251 MW of capacity in Illinois retired in 2015. This represents more than 2 percent of the 10,800 MW that retired RTO-wide in 2015. The unit age was 57 years. 510 MW of capacity in Illinois announced in 2015 plans to retire in 2020. 12

Illinois 2015 Generation Deactivations (MW Capacity, December 31, 2015) 13

Planning Transmission Infrastructure Analysis 14

Illinois - RTEP Baseline Projects (Approved in 2015, greater than $10 million) Baseline Projects are transmission enhancements identified as part of reliability criteria tests, operational performance issues and market efficiency studies that identify upgrade need driven by thermal, voltage, short circuit, stability and light load issues 15

Baseline Load Growth / Deliverability & Reliability Congestion Relief Economic Operational Performance Generator Deactivation TO Criteria Violation Illinois - RTEP Baseline Projects (Approved in 2015, greater than $10 million) IL Baseline Project Drivers Map ID Project ID Project Date Cost ($M) TO Zone(s) 2015 TEAC Review b2692.1 Replace station equipment at Nelson, ESS H-471 and Quad Cities. June 2019 ComEd 9/10/2015 1 b2692.2 Upgrade conductor ratings of Cordova-Nelson, Quad Cities-ESS H-471 and ESS H-471-Nelson 345 kv lines and mitigating sag limitations. June 2019 $24.60 ComEd 9/10/2015 16

Baseline Load Growth / Deliverability & Reliability Congestion Relief Economic Operational Performance Generator Deactivation TO Criteria Violation Illinois - RTEP Baseline Projects (Approved in 2015, greater than $10 million) IL Baseline Project Driver Map ID Project ID Project Date Cost ($M) TO Zone(s) 2015 TEAC Review 2 b2699.1 Replace 5 Powerton 345 kv circuit breakers with 2 cycle IPO breakers, install one new 345 kv circuit breaker; swap line 0302 and line 0303 bus positions; reconfigure Powerton 345 kv bus as single ring configuration. June 2018 $15.00 ComEd 10/8/2015 b2699.2 Remove SPS logic at Powerton that trips generators or sectionalizes bus under normal conditions; minimal SPS logic will remain. June 2018 ComEd 10/8/2015 3 b2728 Mitigate sag limitations on Loretto- Wilton Center 345 kv Line and replace station conductor at Wilton Center. June 2019 $11.50 ComEd 1/7/2016 17

RTEP 2015 Network Enhancements - Illinois (Greater than $10 Million) Network Projects are transmission upgrades identified as part of the interconnection process System Impact Studies. Network upgrades are necessary to interconnect new generation and merchant transmission facilities to the existing transmission grid or to provide new long-term firm transmission service. 18

Generation Interconnection Merchant Transmission Interconnection Long-term Firm Transmission Service Illinois - RTEP Network Projects (Approved in 2015, greater than $10 million) 0 IL Network Project Drivers Map ID Project ID Project Date Cost (M) TO Zone(s) 2015 TEAC Review 1 n4348 To mitigate sag limitations to achieve full conductor thermal capability. W4-005 December 2016 $16.70 ComEd 9/10/2015 19

RTEP 2015 Supplemental Enhancements - Illinois (Greater than $10 Million) 20

Map ID RTEP 2015 Supplemental Enhancements - Illinois (Greater than $10 Million) Project ID Project Date 1 s0880 Reconductor 9.5 miles of 345 kv line 1311 from Goodings Grove to Crawford. 2 s0885 Rebuild 138 kv line 0902 for 19 miles from Davis Creek to the Davis Creek tap. 3 s0886 Prospect Heights Replace 345/138 kv transformer 81 and move the capacitor bank from the Transformer 81 tertiary winding to 138 kv bus 1. IL Supplemental Projects Cost ($M) TO Zone(s) 2015 TEAC Review December 2015 $14.60 ComEd 3/5/2015 December 2015 $23.10 ComEd 3/5/2015 December 2015 $10.80 ComEd 3/5/2015 4 s0888 Collins station Replace 765/345 kv transformer 92. February 2016 $18.80 ComEd 3/5/2015 5 s0894 Cherry Valley Install three 345 kv circuit breakers and expand 345 kv ring. 6 s0896 Dresden Replace 345/138 kv Transformer 83, install high side 345 kv circuit breaker, replace 138 kv circuit breakers 1205, 1206, 0903, 0904. 7 s0897 Bedford Park Replace 345/138 kv transformer 82, move capacitor bank from tertiary to 138 kv bus 3, replace transformer 84 high side 345 kv MOD with a circuit breaker. December 2016 $16.30 ComEd 3/5/2015 December 2016 $18.30 ComEd 3/5/2015 December 2015 $21.20 ComEd 3/5/2015 21

Map ID RTEP 2015 Supplemental Enhancements - Illinois (Greater than $10 Million) Project ID Project Date 8 s0898 Electric Junction Replace 345/138 kv Transformer 81, install 345 kv high side circuit breaker, move capacitor bank from tertiary to 138 kv bus 1, install Transformer 82 & 84 high side 345 kv circuit breakers, replace 345 kv 11126 circuit breaker. IL Supplemental Projects Cost ($M) TO Zone(s) 2015 TEAC Review December 2016 $28.70 ComEd 3/5/2015 9 s0899 Des Plaines Install 4 Transformer high side 345 kv circuit breakers for transformer 81, 82, 83, 84, replace 138 kv bus tie 2-3. 10 s0900 Cherry Valley Replace 345/138 kv Transformer 81, install high side 345 kv circuit switcher, move capacitor bank from tertiary to 138 kv bus 1. December 2016 $12.70 ComEd 3/5/2015 December 2015 $21.50 ComEd 3/5/2015 11 s1077 Build a new 138 kv distribution station at Normantown Road. June 2016 $34.90 ComEd 11/20/2015 12 s1078 Add 4th 345/138 kv Transformer at Goodings Grove. June 2016 $15.70 ComEd 11/20/2015 22

Illinois - Merchant Transmission Project Requests (December 31, 2015) Queue Project Name MW Status Schedule TO AB1-024 Loretto-Wilton Ctr 50 Active 42887 ComEd AB1-029 Loretto-Pontiac 35 Active 42887 ComEd AB1-121 Byron 345kV 0 Active 44531 ComEd 23

Planning Load Forecast 24

Illinois* - 2016 Load Forecast Report (December 31, 2015) Summer Peak (MW) T. O. 2016 2026 Winter Peak (MW) Growth Rate (%) 2015/16 2025/26 Growth Rate (%) Commonwealth Edison Company 22,001 23,633 0.7% 15,579 16,974 0.9% PJM RTO 130,243 140,912 0.8% 152,131 161,891 0.6% * PJM notes that it does not serve the entire state of Illinois. 25

Operations Gas Pipeline Information 26

Gas Generators Illinois - Natural Gas Statistics (March 31, 2016) Dual Fuel Capable (MW) Total Generator (MW) Connected to Interstate Pipelines 500 7,300 (69%) Behind the Local Distribution Company 0 3,300 (31%) Total Gas Fired Generators 500 10,600 Interstate Pipelines ANR Pipeline Northern Border Pipeline National Fuel Gas Supply Corporation (NFG) Vector Pipeline Local Distribution Companies MidAmerican Energy Company Nicor Gas People s Natural Gas 27