Relative Power Factor Correction costs

Similar documents
Feasibility Study Report

3 Existing National Grid

Feasibility Study Report

ABB POWER SYSTEMS CONSULTING

Feasibility Study Report

Georgia Transmission Corporation Georgia Systems Operations Corporation

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

EC Forum on Model Approaches to Distribution Pricing. June 2009

15 Nelson-Marlborough Regional Plan

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

SSF Section Location of Change SSF Issue Change(s) Comments Chapter Part B All Multiple Formatting, spelling and minor Changes applied -

Draft Guideline for the connection of smallscale inverter based distributed generation. EEA Asset Management Forum 22 June 2016 Dr Richard Strahan

Group 3: Pricing from 1 April 2018 and load management

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

New 115 kv Disconnect Switches at Bloomsburg MTS

Targeted Application of STATCOM Technology in the Distribution Zone

15 Nelson-Marlborough Regional Plan

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

100 MW Wind Generation Project

Electricity Transmission network charging

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

rectification of poor power factor

MYPD3 tariff restructuring plan use-of-system charges. Brochure

Introduction to Charging: Which Parties Pay Which Charges?

Electrical Handbook Fault Calculations Using The Mva Method

Wind Generators Evolving Technology

Dynamic Reactive Power Control for Wind Power Plants

ABB Wind Power Solution

System Impact Study Report

PES Cook Islands KEMA Grid Study Final Report

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

Interconnection System Impact Study Report Request # GI

ECE 740. Optimal Power Flow

MIPSYCON 2014 Can a Grid be Smart without Communications? A Look at an Integrated Volt Var Control (IVVC) Implementation

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

ABB November 16, 2016 Slide 1

1. Thank you for the opportunity to comment on the Low Emissions Economy Issues Paper ( Issues Paper ).

Rate Impact of Net Metering. Jason Keyes & Joseph Wiedman Interstate Renewable Energy Council April 6, 2010

The North Carolina solar experience: high penetration of utility-scale DER on the distribution system

Guideline for Parallel Grid Exit Point Connection 28/10/2010

MILLIGAN SOLAR PROJECT

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

2016 Load & Capacity Data Report

Reliability-related matters from the GREEN Grid project

Smart Grid Implementation Strategies. Ray Gogel February 2010

Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Electrification Asset Usage Charge. Presentation to TESG. Matt Skinner, Development Manager 11 th March 2013

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Power Purchase and Grid Connection Procedures

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

Supplemental Report on the NCTPC Collaborative Transmission Plan

Indicative Gas Transportation Charges from 1 April 2012 for East of England, London, North West and West Midlands Distribution Networks

2016 INTEGRATED TRANSMISSION PLAN SCHEDULES SEPTEMBER 2016

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV

Evaluating Losses in Electrical Equipment Focus on Transmission Utilities. CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E.

Underpinning Research Power Electronics in Distribution Networks

11. Electrical energy tariff rating

Essential Reliability Services From PV Plants

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Power System Economics and Market Modeling

Introduction to PowerWorld Simulator: Interface and Common Tools

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership

Dynamic Reactive Power Control. By V. R. Kanetkar Full Time Consultant Technical Services at Veretiv Energy Private Limited Thane (West)

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

TransWest Express Project

CUSTOMER/ TWIN ARROWS PROJECT

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

MONTHLY NEW RESIDENTIAL SALES, APRIL 2017

Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

The Isle of Gigha Flow Battery Project

NYCA LOLE Violations (Methods D and E )

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Electricity Network pricing schedule. Module 15 Effective April 1, 2011 for Electricity line charges. Version

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

kvah Billing - Frequently Asked Questions (FAQs)

Interconnection System Impact Study Final Report February 19, 2018

POWER FACTOR IMPROVEMENT CONCEPT FOR LARGE MOTORS

EFFECT OF SOLAR PV ON VOLTAGE MANAGEMENT IN NEW ZEALAND

EPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011

Washington Clean Energy Fund (CEF) II OPALCO Community Solar and Energy Storage on Decatur Island

Unrestricted. Air Core Reactor Applications Current Limiting Reactors

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

Compliance of Solar PV Installation with the New Renewables SA Grid Code Jimmy Goulding, Electrical Technologist, Aurecon, South Africa

Electricity Transmission Infrastructure Development in New England

Transcription:

SSG REF: S026 Friday 19 th October 2007 TO: John Gleadow Senior Adviser Transmission Electricity Commission FROM: David Hume Ranil de Silva System Studies Group NZ Ltd Relative Power Factor Correction costs 1. Introduction In this report we compare the costs of installing HV grid connected capacitors on the transmission system versus LV power factor correction capacitors on the distribution system. Our study is based on the premise that the demand is in a region that requires voltage support to meet the peak load (this situation currently exists in the Upper North Island and Upper South Island). We assume that any dynamic reactive support is installed on the transmission system and that the overall demand power factor is to be corrected to unity by either : a) Installing HV grid connected capacitors close to the GXP b) Installing LV power factor correction capacitors within the distribution network close to the demand Page 1 of 5

2. Simplified Model Figure 1 shows the simplified model we have used to represent the distribution network connected to the transmission system. The transmission system at 220 kv or 110 kv feeds the 33 kv distribution system via supply transformers. The distribution system is represented as a lumped impedance feeding a lumped demand of 100 MW peak and 62 MW average at 11 kv. The HV grid capacitors are connected to the 220 kv or 110 kv bus whilst the LV power factor correction capacitors are connected to the 11 kv bus. (We do not consider power factor correction at lower voltages such as 240 V). We have assumed that the supply transformers and distribution network have a lumped resistance of 0.078 pu (relative to the peak demand). This value of resistance is based on a review of distribution loss factors published by Orion 1. 3. Cost Assumptions We have assumed a long run marginal cost for losses at $100 / MWh. We have assumed that grid connected capacitors will cost about $16,480 / MVAR for a dual bus connected capacitor at 220 kv or 110 kv. This is based on 2006 ODV information published by Transpower with a CPI of 3% 2. We have assumed that distribution power factor correction capacitors will cost about $34,690 / MVAR for switched 11 kv zone substation capacitors. This is based on 2004 ODV information published by Vector with a CPI of 3% 3. 1 Distribution Loss Factors (applying from 1 October 1999, text updated 1 February 2007), Orion New Zealand Limited 2 2006 Report of the Optimized Deprival Valuation of Transpower s System Fixed Assets as at 30 June 2006, Transpower New Zealand Limited, November 2006. 3 Vector Optimized Deprival Valuation - Auckland, Wellington, and Lichfield Electricity Networks, Vector Limited, 31 March 2004. Page 2 of 5

Figure 1. Simplified Model for Distribution Network Transmission System 220 kv or 110 kv bus Grid Connected Capacitors Supply Transformers 33 kv bus Lumped distribution network and transformers 11 kv bus Power Factor Correction Capacitors Lumped Demand 100 MW Peak 62 MW Average pf 0.95 1.00 Page 3 of 5

4. Analysis To gain an appreciation for the difference in correcting power factor on either the LV or HV networks we compare the annualized cost of each, including benefits associated with reduction in distribution losses. Our example assumes the system in Figure 1 with a lumped demand of 100 MW peak and 62 MW average on the lumped LV network with a demand power factor ranging from 0.95 to 1.00 4. The distribution resistance has been estimated from average distribution loss factors supplied by Orion 1. Figure 2 shows the annualized costs for correcting peak demand power factor to unity. HV capacitors generally tend to be about half the total cost of LV capacitors, but on the other hand correcting power factor on the LV network appears to have significant loss benefits. For example, if the demand on our simplified network has a power factor of 0.97 lagging at peak then, from Figure 2, the annualized cost of capacitors to correct power factor to unity on the HV network would be around $40,000 and on the LV network around $80,000 5. However, LV correction would also provide an annual loss benefit of $165,000 giving a total annual benefit of $85,000 for LV correction. Figure 2 also indicates that there is an economic benefit in correcting LV power factor to about 0.99 even if there is no requirement to support transmission. Note that correcting power factor on both the HV and LV networks improves the losses in the transmission grid but that these benefits are common to both the HV and LV compensation options and are therefore not taken into account. 4 With lower power factors the total current is greater than 1 pu, while with unity power factor the current is 1 pu. Hence, the losses, defined by I 2 R are higher with lower power factors, improving to unity. 5 Assuming a Capital Recovery Factor (CRF) of 0.1. Page 4 of 5

Figure 2. Annualized Costs for HV and LV Unity Power Correction (To Supply 100 MW Peak Demand) 200 150 Costs (NZ$000/year) 100 50 0 0.95 0.96 0.97 0.98 0.99 1.00-50 LV Power Factor -100-150 -200-250 -300 Cost of LV Capacitors to Correct to Unity PF Loss Benefit from LV Correction Cost of HV Capacitors to Correct to Unity PF Total LV Correction Cost (LV Capacitor Cost + Loss Benefit) 5. Summary The results of our simplified analysis suggest that if demand power factor correction is required to support transmission then it is more economic to correct power factor to unity on the LV distribution network rather than the HV transmission grid. This is because the lower cost of HV capacitors are outweighed by the reduced losses associated with LV capacitors. Furthermore, the results suggest that there is an economic benefit in correcting LV power factor to about 0.99 even if there is no requirement to support transmission. Note that this is a simplified preliminary analysis and SSG would welcome comment on our assumptions and methodology. Page 5 of 5