White River Electric Association, Inc. Net Metering Information & Service Requirements

Similar documents
Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

CHOCTAWHATCHEE ELECTRIC COOPERATIVE, INC RESIDENTIAL SERVICE--NET METERING RIDER

SANTA CLARA CITY RENEWABLE NET METERING & INTERCONNECTION AGREEMENT

Louisville Gas and Electric Company

Columbia Water & Light Interconnection & Net Metering Agreement Electrical Facility

Springfield Utility Board Net Metering Policy Adopted on February 13, 2008 (Resolution 08-1)

Consumer Guidelines for Electric Power Generator Installation and Interconnection

NET METER REQUEST FORM

Douglas Electric Cooperative Roseburg, Oregon

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

SCHEDULE 62 COGENERATION AND SMALL POWER PRODUCTION SCHEDULE - IDAHO

Montana-Dakota Utilities Co. A Division of MDU Resources Group, Inc. 400 N 4 th Street Bismarck, ND 58501

TERMS AND CONDITIONS

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

Net Metering Program

Rider : NET METERING SERVICE AND ELECTRICAL SYSTEM INTEGRATION

S T A F F R E P O R T

Noble County Rural Electric Membership Corporation

COMMUNITY SOLAR PROGRAM

Louisiana Net Metering Service. Customer Information Package

SCHEDULE NO. ACG33 NET METERING SERVICE

SCHEDULE 6 RESIDENTIAL SERVICE ON-SITE GENERATION

SERVICE CLASSIFICATION "CEF" COMMUNITY ENERGY FACILITY

SCHEDULE 84 CUSTOMER ENERGY PRODUCTION NET METERING SERVICE

FRENCH BROAD ELECTRIC MEMBERSHIP CORPORATION RATE SCHEDULES

Noble County Rural Electric Membership Corporation

BC Hydro Rate Schedule 1289 Revision 1 Effective: April 20, 2018 Page 6-1

Application to Amend Net Metering Service under RS Appendix B. Revised RS 1289 Clean and Black-lined

P.S.C.U. No. 50 Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 136 STATE OF UTAH

Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO.

To complete the process for a net metering interconnection, please follow the steps below:

NET ENERGY METERING RIDER Rider NEM. Certain words, when used in this Rider NEM shall be understood to have the following meanings:

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

RENEWABLE ENERGY PROGRAM Step 1, Section 1 ENROLLMENT FORM FOR LEASED RESIDENTIAL AND SMALL COMMERCIAL PHOTOVOLTAIC AND WIND TURBINE SYSTEMS

M.P.S.C. No. 2 Electric Third Revised Sheet No. 65 (Rate Case) Cancels Second Revised Sheet No. 65

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

JEA Distributed Generation Policy Effective April 1, 2018

To complete the process for a net metering interconnection, please follow the steps below:

ATTACHMENT 14 RESOLUTION NO. 5888(14) Supersedes Schedule NEM of Resolution No. 5592(09) Schedule NEM NET ENERGY METERING

Umatilla Electric Cooperative Net Metering Rules

Distributed Generation Interconnection Policy

ROANOKE ELECTRIC COOPERATIVE RATE SCHEDULES

MISSOURI SERVICE AREA

RIDER NM NET METERING

TILLAMOOK PEOPLE S UTILITY DISTRICT

3. Customer shall provide space for metering equipment and meter base as per Springville City Power requirements.

TERMS AND CONDITIONS XXV. NET METERING CUSTOMERS AND SMALL AGRICULTURAL GENERATORS

MEMBER RELATIONS POLICY NO SUBJECT: INTERCONNECTION OF CUSTOMER GENERATION RESOURCES

INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS

SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board

24. SOLAR INCENTIVE PROGRAM II

2lr1344 CF 2lr1396. Drafted by: Heide Typed by: Rita Stored 02/02/12 Proofread by Checked by By: Senator Pinsky A BILL ENTITLED

SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & INTERCONNECTION AGREEMENT

JACKSON ELECTRIC COOPERATIVE POLICY NO. 305

ELECTRIC DIVISION CUSTOMER-OWNED RENEWABLE GENERATION INFORMATION PACKAGE

BC Hydro Rate Schedules Effective: August 1, 2015 Fourth Revision of Page 30

City of Banning Electric Utility - Residential Self Generating Facility Program (Photovoltaic Systems <48kW)

Definitions. Scope. Customer Generation Interconnection Requirements

WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM

MCCOOK PUBLIC POWER DISTRICT McCook, Nebraska BOARD POLICY NUMBER 488

Schedule No. NMR-405 NET METERING RIDER-405 APPLICABLE

RAPPAHANNOCK ELECTRIC COOPERATIVE SCHEDULE NEM-8 NET ENERGY METERING RIDER

City of Washington, Kansas Electric Department. Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources

Buy All Sell All Rider for Interconnection of Renewable Generation

LIBERTY UTILITIES (CALPECO ELECTRIC) LLC SOUTH LAKE TAHOE, CALIFORNIA 3rd Revised CPUC Sheet No. 137 Canceling 2nd Revised CPUC Sheet No.

REVISION NO.: 7 EFFECTIVE: 07/07/16

Schedule SP SOLAR PURCHASE (Experimental)

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

STATE CORPORATION COMMISSION DIVISION OF PUBLIC UTILITY REGULATION. May 22, 2018

ORDINANCE NO

REVISED 8/1/2018 SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & WGC INTERCONNECTION AGREEMENT

WOLFEBORO MUNICIPAL ELECTRIC DEPARTMENT NET METERING PILOT PROGRAM. Customer-Owned Renewable Energy Generation Resources (25 Kilowatts or Less)

A Bill Regular Session, 2015 HOUSE BILL 1004

To complete the process for a net metering interconnection, please follow the steps below:

WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources

EAU CLAIRE ENERGY COOPERATIVE FALL CREEK, WI Issue Date: 05/28/2014 Subject: New Distributed Generation Post May 28, 2014

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power

THE PUBLIC SERVICE COMMISSION OF MARYLAND

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Interconnection Process for Generation Systems

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

CITY OF SASKATOON ADMINISTRATIVE POLICY

Municipality Generator Interconnection Application Single Meter Application Part I

(2) Scope. 220 CMR applies to all Distribution Companies subject to the jurisdiction of the Department.

Panola-Harrison Electric Cooperative, Inc. Louisiana Tariff Effective: March 3, 2004

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620

COMMERCIAL RATE SCHEDULES

HOUSE BILL 801. (0lr2294) ENROLLED BILL Economic Matters/Finance

Adopted: September 24, 2015 Version: Version 1.0

SMALL POWER PRODUCER RIDER (Net Energy Billing Rate)

Renewable Net Metering Program Appendix ESD APX 001 1

Net Metering Service. Customer Information Package

MISSOURI SERVICE AREA

Transcription:

White River Electric Association, Inc. Net Metering Information & Service Requirements What is Net Metering? Net Metering is an electric policy and service for consumers who own and utilize renewable energy facilities (such as wind, solar power or hydroelectric power) to generate electricity that offsets electric energy provided by the electric utility. Residential systems up to 10 kw in capacity and commercial and industrial systems up to 25 kw are credited for any net excess generation produced by their system. A Consumer-Generator is subject to the terms and conditions of the WREA Net Application & Agreement, the WREA Net Metering Policy and associated WREA Net Metering Tariff. If you are interested in Net Metering, please call WREA and ask to speak to a WREA Field Representative for additional information. 1. WREA Net Metering Application and Agreement: The WREA Net Metering Application & Agreement must be completed, executed, returned to WREA and approved by WREA prior to interconnection and participation in the WREA Net Metering program. 2. Maximum Capacity: A Consumer-Generator must have a rated capacity of 10 kw or less for residential installations or 25 kw or less for commercial installations to qualify for Net Metering. 3. Safety and Performance Standards: WREA requires that a generating system used by a Consumer-Generator to meet all applicable safety and performance standards established by the National Electric Code (NEC), the Institute of Electrical and Electronics Engineers (IEEE), Underwriters Laboratory (UL), the National Electric Safety Code (NESC) and all other applicable regulations or standards. 4. Photovoltaic and Inverters: When an inverter is used the Consumer-Generator will be required to use an inverter that is listed with and in compliance with Underwriters Laboratory (UL) 1741 Standard. Photovoltaic systems must be installed in compliance with IEEE Standard 929-2000 and in compliance with the relevant NEC articles for Solar 1

Photovoltaic Systems. An approved State inspection of the new service and/or PV system is required prior to the interconnection of the system. 5. Liability Insurance: The Consumer-Generator shall carry no less than threehundred thousand dollars ($300,000) of liability insurance that provides for coverage of all risk and liability for personal injuries (including death) and damage to property arising out of or caused by the Consumer-Generators systems of 10 kw or smaller; or two million dollars ($2,000,000.00) for systems between 11-25 kw. WREA shall be named as an additional insured on the insurance policies for Consumer-Generator systems between 11-25 kw. Insurance may be in the form of a new insurance policy or an endorsement on an existing insurance policy. Proof of insurance is required prior to interconnection and annually thereafter. 6. Interconnection Costs: WREA will provide the Consumer-Generator with an estimate of WREA s interconnection costs. The Consumer-Generator shall reimburse WREA in full for WREA s interconnection costs prior to interconnection. The interconnection costs shall include all costs of connection, switching, metering, transmission, distribution, safety provisions and administrative costs incurred by WREA directly related to the installation and maintenance of the physical facilities necessary to permit interconnected operations with the Consumer-Generator. Reimbursement costs shall be paid to the WREA in full prior to interconnection. 7. Interconnection: Interconnection is permitted only after all of WREA s requirements are met including but not limited to WREA s signed approval of the WREA Net Metering Application & Agreement. Interconnection will not be approved until all WREA interconnection costs are fully reimbursed by the Consumer-Generator. The Consumer-Generator shall remain responsible for the installation, operation and maintenance of the facilities at all times and shall own, maintain and operate its facilities in a responsible and safe manner. If in WREA s opinion, the Consumer-Generator fails to meet WREA requirements or fails to operate and maintain the facilities in a responsible or non-qualifying manner, WREA shall notify the Consumer-Generator of its non-compliance. Based upon non-compliance WREA shall cease to operate in parallel and shall not purchase any capacity and energy made available and may require the Consumer-Generator to disconnect the generating facilities from WREA s system. In the event the Consumer-Generator fails to immediately correct operations or to comply with a disconnect notice, WREA reserves the right to make such disconnection including the termination of electric service if necessary. 8. WREA Access: WREA employees and authorized representatives shall have the right to enter the Consumer-Generator's property at any reasonable time to insure continued compliance with WREA s safety and operating standards and the accuracy of its meters. Such inspection by WREA shall not relieve the Consumer-Generator from the responsibility of installing, operating and maintaining the facilities in a responsible and safe manner. 9. Disconnect Requirements: In order to provide for the safety of WREA s employees and authorized representatives when performing certain operation and maintenance the following two requirements shall be met upon disconnection: 2

a. The Consumer-Generator s facilities shall be designed and operated to automatically disconnect or shut down during scheduled or unscheduled outages to insure that it will not back feed on to any part of WREA s distribution system. b. That a means be available to positively disconnect the Consumer- Generator s facilities from the system such that there is no possibility that the generator could back feed through the service transformer and energize the primary system. This requirement shall be met with a Consumer-Generator furnished and installed Underwriter's Laboratory (UL) listed manual disconnect switch, which shall be located between the Consumer's Consumer-Generator and WREA s system. The location of the switch shall meet all code requirements and be approved by WREA and shall be housed in an approved enclosure which can be secured with a padlock or locking device. 10. Emergency Isolation of Qualifying Facility: WREA reserves the right to open the disconnect switch (i.e., isolating the Consumer-Generator) without prior notice for any of the following reasons: a. System emergency and/or maintenance operations require such action, and b. A potentially hazardous condition relating to the Consumer-Generator is discovered. 11. Normal Isolation of Qualifying Facility: Upon 24 hours notice by WREA, the Consumer-Generator agrees to disconnect its facilities from WREA s system for maintenance, or normal operations. 12. Single-Phase Limitations: The rated capacity of the Consumer-Generator to be connected in parallel with a low voltage service shall be no greater than 10 kw for single-phase installations unless, in the sole determination of WREA, a larger singlephase installation is acceptable. 13. Quality of Service: The operation of the Consumer-Generator s facilities must not cause any reduction in the quality of service to other WREA consumers nor interfere with the operation of WREA s overall distribution and transmission system. The Consumer- Generator shall be responsible for taking whatever corrective action may be required and/or reimbursing WREA for the cost of any corrective action deemed necessary by WREA. 14. Electrical Characteristics: The electrical characteristics of the Consumer- Generator shall conform to standards established by WREA. The standards shall include voltage, current, frequency, harmonics, and automatic synchronization, etc. Wherever possible WREA will base its standards on industry wide standards. 15. Power Factor: The Consumer shall endeavor to operate its facilities as near unity power factor as possible. For Consumer-Generators with rated capacity above 10 kw, WREA reserves the right to require the Consumer to install power factor correction equipment or reimburse WREA for its cost of installing power factor correction equipment. 3

16. Metering: WREA will meter the Consumer-Generator in order to obtain billing data as well as the energy purchased by the Consumer and sold by the Consumer to WREA. Consumer-Generator shall be required to pay for any metering costs incurred by WREA. Net Metering Applicability, Availability and Definitions: Applicability: Applicable to all eligible Consumer-Generators whose electric service is supplied by WREA and who comply with the terms and conditions of a fully executed and approved WREA Net Metering Application & Agreement. Availability: Net Metering is available to WREA customers located within the Association's service territory who own, operate, lease or otherwise control an Eligible Renewable Energy Generation System. Consumer-Generator: A WREA customer who generates electricity on the customer's side of the meter using eligible energy sources. Net Generation: The measured difference, in kilowatt hours (kwh) between the electricity supplied to a Consumer-Generator by the Association and the electricity generated by the Consumer-Generator and delivered to the Association at the same point of interconnection that is in excess of the electricity used at the same location. Net Purchaser: The measured difference, in kilowatt hours (kwh) between the electricity supplied to a Consumer-Generator by the Association and the electricity generated by the Consumer-Generator and delivered by the Association at the same point of interconnection that is in excess of the electricity produced by the Consumer- Generator's system. Rates & Charges: At the end of the each annual period, WREA shall pay the Consumer-Generator for any remaining unused credited kwh balance accumulated during the previous twelve months. The rate for payment shall be WREA s most recent Average Cost of Power. The Average Cost of Power shall be calculated annually using the previous 12 month s wholesale power bill. The calculation shall be the total cost of purchased power divided by the total kwh s purchased by the Association. The Association shall issue a check for any credited kwh balance within 60 days after the end of each annual period. The rates and charges for retail electric service to Consumer- Generators shall be based on the Association's applicable rate tariff for the customer's premises. In those months where the Consumer-Generator is a net purchaser of electric energy from the Association, the Consumer-Generator will be billed by the Association based on the net metered kwh usage for the month and the terms of the rate schedule. In those months where the Consumer-Generator is a net generator of electric energy to the Association, a kwh credit balance for the net energy received by the Association will be carried forward to the next month. WREA will bill the Consumer-Generator for the applicable customer service charge and other applicable charges of the rate schedule but with zero kwh usage for the month. For purposes of this Net Metering tariff only, the annual period shall be July 1st to June 30th of the following year. At the end of the each annual period, WREA shall pay the Consumer-Generator for any remaining unused credited kwh balance accumulated during the previous twelve months and shall issue a check for any credited kwh balance within 60 days after the end of each annual period. 4

Eligible Generation System: An electric generating system which: has a total aggregate nameplate generating capacity, from a single or multiple generators, of 10 kilowatts (kw) or less for residential installations; or has a total aggregate nameplate generating capacity, from single or multiple generators, of 25 kw or less for commercial installations; and uses as its energy source solar, wind, biomass, hydropower, geothermal or other qualifying renewable resources; and is intended primarily to offset part or all of the Consumer-Generator's electric energy requirements at the same location; and is located on the premises that are owned or leased by the Consumer- Generator; and operates in parallel with the WREA electric distribution system; and shall not be used to offset or provide credits for electric consumption at another location of the Consumer-Generator or for any other customer; and meets all WREA safety and performance requirements and applicable regulations and standards. 5