Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620

Similar documents
INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES

INTERCONNECTION for GENERATING FACILITIES Up to 20 MW

INTERCONNECTION REQUIREMENTS POLICY

Net Metering Program

To complete the process for a net metering interconnection, please follow the steps below:

Umatilla Electric Cooperative Net Metering Rules

TILLAMOOK PEOPLE S UTILITY DISTRICT

SANTA CLARA CITY RENEWABLE NET METERING & INTERCONNECTION AGREEMENT

Louisville Gas and Electric Company

Application for Interconnection and Net Metering Revision: 1 Revised: November 7, 2017

INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS

3. Customer shall provide space for metering equipment and meter base as per Springville City Power requirements.

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

FRENCH BROAD ELECTRIC MEMBERSHIP CORPORATION RATE SCHEDULES

To complete the process for a net metering interconnection, please follow the steps below:

Municipality Generator Interconnection Application Single Meter Application Part I

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Columbia Water & Light Interconnection & Net Metering Agreement Electrical Facility

SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board

To complete the process for a net metering interconnection, please follow the steps below:

NET METER REQUEST FORM

White River Electric Association, Inc. Net Metering Information & Service Requirements

Rider : NET METERING SERVICE AND ELECTRICAL SYSTEM INTEGRATION

Montana-Dakota Utilities Co. A Division of MDU Resources Group, Inc. 400 N 4 th Street Bismarck, ND 58501

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

Interconnection and Net Metering Service in Ohio

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _

MEMBER RELATIONS POLICY NO SUBJECT: INTERCONNECTION OF CUSTOMER GENERATION RESOURCES

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Douglas Electric Cooperative Roseburg, Oregon

Adopted: September 24, 2015 Version: Version 1.0

Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE

CHOCTAWHATCHEE ELECTRIC COOPERATIVE, INC RESIDENTIAL SERVICE--NET METERING RIDER

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

December 13, This document was filed with the Board of Public Utilities on December 13, It is awaiting final approval by BPU staff.

WOLFEBORO MUNICIPAL ELECTRIC DEPARTMENT NET METERING PILOT PROGRAM. Customer-Owned Renewable Energy Generation Resources (25 Kilowatts or Less)

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources

Senate Substitute for HOUSE BILL No. 2101

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

HydroGenerations PROGRAM HANDBOOK

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

Consumer Guidelines for Electric Power Generator Installation and Interconnection

TERMS AND CONDITIONS

WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

P.S.C.U. No. 50 Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO. 136 STATE OF UTAH

SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & INTERCONNECTION AGREEMENT

Louisiana Net Metering Service. Customer Information Package

MISSOURI SERVICE AREA

WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM

COMMUNITY SOLAR PROGRAM

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

City of Banning Electric Utility - Residential Self Generating Facility Program (Photovoltaic Systems <48kW)

City of San Juan Capistrano Agenda Report

Noble County Rural Electric Membership Corporation

Definitions. Scope. Customer Generation Interconnection Requirements

RATE 765 RENEWABLE FEED-IN TARIFF

S T A F F R E P O R T

MCCOOK PUBLIC POWER DISTRICT McCook, Nebraska BOARD POLICY NUMBER 488

First Revision of Sheet No P.S.C.U. No. 50 Canceling Original Sheet No ROCKY MOUNTAIN POWER ELECTRIC SERVICE SCHEDULE NO.

BC Hydro Rate Schedule 1289 Revision 1 Effective: April 20, 2018 Page 6-1

Application to Amend Net Metering Service under RS Appendix B. Revised RS 1289 Clean and Black-lined

PUD ELECTRIC SYSTEM INTERCONNECTION

S T A T E O F M I C H I G A N BEFORE THE MICHIGAN PUBLIC SERVICE COMMISSION * * * * *

Electric Vehicle Charging Station Incentives PROGRAM HANDBOOK

Customer Name : Account Number: Customer Service Address (Street, City, State, ZIP Code): Customer Mailing Address: Customer Telephone Number:

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

City of Washington, Kansas Electric Department. Net Metering Policy & Procedure For Customer-Owned Renewable Energy Resources

ENGINEERING SPECIFICATION

DIVISION 311 MISCELLANEOUS ELECTRICAL RULES

ARKANSAS PUBLIC SERVICE COMMISSION NET-METERING RULES

Noble County Rural Electric Membership Corporation

To complete the process for a net metering interconnection, please follow the steps below:

24. SOLAR INCENTIVE PROGRAM II

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

Schedule SP SOLAR PURCHASE (Experimental)

Overview of State Distributed Generation Interconnection Rules

Duke Energy Carolinas North Carolina Interconnection Request Checklist

Distributed Generation Interconnection Policy

REVISION NO.: 7 EFFECTIVE: 07/07/16

BC Hydro Rate Schedules Effective: August 1, 2015 Fourth Revision of Page 30

Interconnection of Distributed Generation Net Metering (Excluding Solar*Rewards) DATE: August 17, 2015

JEA Distributed Generation Policy Effective April 1, 2018

ORDINANCE TOWN OF ALBANY. Revised 8/19/03 GREEN COUNTY WISCONSIN

Schedule No. NMR-405 NET METERING RIDER-405 APPLICABLE

MICHIGAN ELECTRIC UTILITY

City of San Juan Capistrano Agenda Repo_rt

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power

ORDINANCE NO

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

CITY OF SASKATOON ADMINISTRATIVE POLICY

RENEWABLE ENERGY PROGRAM Step 1, Section 1 ENROLLMENT FORM FOR LEASED RESIDENTIAL AND SMALL COMMERCIAL PHOTOVOLTAIC AND WIND TURBINE SYSTEMS

SCHEDULE 84 CUSTOMER ENERGY PRODUCTION NET METERING SERVICE

Net Metering Service. Customer Information Package

Interconnection Process for Generation Systems

SCHEDULE 62 COGENERATION AND SMALL POWER PRODUCTION SCHEDULE - IDAHO

M.P.S.C. No. 2 Electric Third Revised Sheet No. 65 (Rate Case) Cancels Second Revised Sheet No. 65

Transcription:

Policy Bulletin No. 25 Net Metering Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620 Interconnection Standards For Residential Net Energy Metering With Electric Generating Facilities Of 25 Kilowatts Or Less ------------------------------------- This Policy shall allow for interconnection of Residential Net Energy Metering customers only unless previously authorized by the Klickitat PUD (Utility) Board of Commissioners. 1. PURPOSE AND SCOPE 1.1 The purpose of this document is to establish rules for determining the terms, conditions, technical requirements, processes and charges governing the interconnection of residential electric generating facilities with a nameplate rating of no greater than 25 kw to the electric distribution system over which the Utility has jurisdiction. 1.2 These rules govern the terms and conditions under which the Customer-Generator generating facility will interconnect with, and operate in parallel with, the Utilities electric system. These rules apply only to the physical interconnection of a generating facility to the Utilities electrical system. They do not govern, or grant the right to sell or purchase, or deliver any power generated by the Customer-Generator's generating facility. 1.3 The specifications and requirements in these rules are intended to mitigate possible adverse impacts caused by a generating facility on the Utility equipment and personnel and on other customers of the Utility. They are not intended to address protection of the Customer-Generator s generating facility, facility personnel, or internal load. It is the responsibility of the Customer-Generator to comply with the requirements of all appropriate standards, codes, statutes and authorities to protect its own facilities, personnel, and loads. 1.4 Electric Generating Facilities are defined as residential solar, wind, fuel cell, hydropower and other emerging technologies as approved by the Utility and limited to 25 Kilowatts or less. 1.5 Applicable policies pertaining to Net Energy Metering must be met by the Customer- Generator. Those policies are: Policy Bulletin No. 25 Page 1

Policy Bulletin No. 16-Line extensions- Electric Policy Bulletin No. 21-Customer Service Policy-Electric Policy Bulletin No. 43- Electrical Interconnection Requirements 2. APPLICATION OF RULES 2.1 These rules include various requirements applicable to the Utility, the Customer- Generator and the Generating Facility. 2.2 These rules modify, if necessary, any existing interconnection rules of the Utility, including but not limited to, rules implementing 80.60 RCW, Net Metering of Electricity. 2.3 These rules do not apply to interconnection of standby or backup generators that are not intended to operate in parallel with the Utilities system. Such interconnections will be negotiated on a case-by-case basis with the Utility and such generators will only be interconnected on terms and conditions prescribed by the Utility. 3. APPLICATION FOR INTERCONNECTION 3.1 An Interconnection Application form for net metered installations, 25 kw and below can be found on the Utilities web site (www.klickitatpud.com). 3.2 When a Customer-Generator requests interconnection from the Utility, the Customer- Generator will be responsible for conforming to the rules and regulations that are in effect. The Customer-Generator seeking to interconnect a generating facility under these rules must fill out and submit a signed Interconnection Application form to the Utility. Information must be accurate, complete, and approved by the Utility; however approval of the application as complete does not constitute approval to interconnect. 3.3 If a project is to be installed in a phased manner, the Customer-Generator may choose to submit application for approval of the final project size, or may choose to submit applications at each stage of the project. Each application will be evaluated based on the nameplate rating stated on the application. 3.4 Application processing charge. A nonrefundable Interconnection Application processing charge is set by the Utility according to facility size. 3.5 Non-Discrimination. All generating facility Interconnection Applications pursuant to this policy will be processed by the Utility in a non-discriminatory manner, consistent with other service requests and in a manner that does not delay other service requests. 3.6 Application evaluation. All generating facility interconnection requests pursuant to this policy will be reviewed by the Utility for compliance with the rules of its policies. If the Utility in its sole discretion finds that the application does not comply with the Policy Bulletin No. 25 Page 2

rules of its policies, the Utility may reject the application. If the Utility rejects the application, it will provide the Customer-Generator with written or electronic mail notification stating its reasons for rejecting the application. All applications will be prioritized on a first-come first-served basis with no preference given. The application will be processed in a time frame where the applicant will be notified if the application is complete or incomplete within ten (10) business days. * If incomplete: The Customer-Generator shall provide a complete application to the Utility within fifteen (15) business day of the notice. The Utility may, but is not required to, grant an extension in writing if requested. If the Customer-Generator fails to complete the application, the application expires at the end of the incomplete application period. * If Completed: Within twenty (20) business days after a complete application notice is sent to a Customer-Generator, the Utility shall approve, approve with conditions, or deny with written justification. The Utility shall include an executable Interconnection Agreement. 3.7 Connection Timeline. A Customer-Generator must interconnect and operate the generating facility within one (1) year from the date of approval of the application, or the application expires. 3.8 Withdraw of application. If an application is withdrawn, the application fee shall be applied to a request for re-application submitted within thirty (30) business days of the withdrawal. After that time frame it will no longer be made available to the applicant for other uses or refund. 4. TECHNICAL REQUIREMENTS 4.1 All Customer-Generating systems installed and used by a Customer-Generator shall include, at the Customer-Generator s own expense and liability, all equipment necessary to meet applicable safety, power quality and interconnection requirements established by the National Electrical Code, National Electrical Safety Code, the Institute of Electrical and Electronic Engineers, Underwrite Laboratories, American National Standards Institute, Klickitat PUD policies, and local, state and federal building codes. 4.2 All safety and operating procedures for joint use equipment shall be in compliance with the Occupational Safety and Health Administration Standard 29, CFR 1910.269, the National Electrical Code, Washington Administrative Code rules, the Washington Industrial Safety and Health Administration Standard, and equipment manufacture s safety and operating manuals. 4.3 The Customer-Generator shall be responsible to obtain all applicable permit(s) for the equipment installations and modifications on their property at their expense. 4.4 the Customer-Generator shall have a dedicated circuit breaker between sources of alternating-current, i.e. between inverter(s) or other power conditioning unit(s) and the Utility distribution system. Policy Bulletin No. 25 Page 3

4.5 The Customer-Generator s overcurrent device at the service panel shall be visible and marked to indicate power source, i.e. label disconnect breaker for the output of power conditioning unit to the Utility distribution system and, if separate, label disconnect breaker for Utility power to overcurrent device. 4.6 The Customer-Generator s power production control system shall comply with applicable NEC requirements, Institute of Electrical and Electronics Engineers (IEEE) Standards, and Underwriter Laboratories (UL), and shall meet minimum specifications and standards for parallel operation with the Utility, in particular the: a. Power output control system shall automatically disconnect from the Utility source upon loss of Utility voltage and not reconnect until the Utility voltage has been restored by the Utility. This system must be UL 1741 safety approved standard inverter, converter and controlling equipment. b. Power output control system shall automatically disconnect from the Utility source if the Utility voltage fluctuates beyond plus or minus 10% (ten percent). c. Power output control system shall automatically disconnect from the Utility if frequency fluctuates plus or minus 2 cycles (Hertz). d. Inverter output distortion shall meet IEEE 519. 4.7 The meter serving the Customer-Generator shall be labeled to indicate potential electric current back feed. The Utility will provide labels when the Customer-Generator s electric system is approved for interconnection and meter is set. 5. COMPLETION PROCESS The interconnection process is complete; the generating facility can begin operation, if and only if: 5.1 The applicant and the Utility execute an Interconnection Agreement; 5.2 A notice of approval showing inspection of the system by the electrical inspector designated by Washington State Labor & Industries; 5.3 All requirements and conditions of the Interconnection Agreement have been satisfied and approved by the Utility and permission has been granted by the Utility to proceed with operation. 5.4 Final step is the installation of a Utility owned bi-directional meter. Meaning, at no point can the Customer-Generator commence with parallel operation with the Utilities meter until written permission is given. Failure to comply shall result in a termination of the Interconnection Agreement. For billing purposes no credit for customer generation will be given for generation produced prior to KPUD written approval. The Customer- Generator will be responsible for any financial consequences as a result of generation occurring prior to approval including generation that may be treated as consumption by KPUD metering. Policy Bulletin No. 25 Page 4

6. REFERENCE DOCUMENTS The following documents further define the process and requirements for requesting interconnection to the Klickitat PUD electrical system. 1. Electric Rate Schedule No. 1a Residential Net Energy Metering 25kw and less. 2. Residential Net Energy Metering Customer Generation Interconnection Agreement 3. Application for Residential Net Energy Metering Interconnection and Appendices 4. Policy Bulletin No. 16-Line Extensions 5. Policy Bulletin No. 21-Customer Service Policy- Electric 6. Policy Bulletin No. 43-Electrical Interconnection Requirements Adopted by the Board of Commissioners: 2/8/00 Revisions Approved: 07/25/00 and 3/09/2010 Revision Approved: 03/27/2018 Randy L. Knowles, President ATTEST: Dan G. Gunkel, Vice President Doug B. Miller, Secretary Policy Bulletin No. 25 Page 5