Sulzer Dowding & Mills

Similar documents
Your Service Partner Service Solutions for Renewable Power Generation

The new generation ABB Motor and Generator Service

Electrical Machine Service. Overhaul, Conditioning, On-Site Service and Diagnostics. Excellent Technology, Efficiency and Quality

Fletcher Moorland Ltd. Electric Motor Repair Specification

Gas turbine outage Sept 2012 Bad things happen to a well planned outage

Double earth fault in a PSP during back to back launching sequence

LEAP - Life Expectancy Analysis Program For Electrical Rotating Machines. Marcio Gennari ABB Brazil Automation Products Machines Service Osasco

Excitation system is of Static Silicon Excitation System, including excitation transformer, thyristors, and AVR.

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

Customer presentation, PG Service, BU Motors and Generators ABB LEAP Stator Winding-Condition & Lifetime assessment

TURBO GENERATORS BEST QUALITY FOR THERMAL POWER PLANTS

NEIL Turbine Generator Risk Assessment. Todd Raymond Loss Risk Analysis Manager Nuclear Service Organization April 16-17, 2013

Large Air Cooled Generator Failure

Kontakt. Turnkey solutions for hydropower plants An overview of the ABB portfolio

McNary Northshore Fishway Hydro Project. History & Lessons Learned

New Robotic Technologies for Inspecting Two Pole Electric Generators while the Rotor Remains in Place

UNIT-I ALTERNATORS PART-A

Unit - I AN ISO 9001 : 2008 COMPANY

Service and Rehabilitation Electrical Power Systems

Intersel Dowding and Mills FZCO Company Profile - Aug 2015

Performance Service Centres. ABB Performance Services. Power and productivity for a better world TM

INTER PLANT STANDARD STEEL INDUSTRY. CODE OF PRACTICE FOR REPAIR OF SQUIRRELCAGE HT MOTORS (6.6 kv) (First Revision) Corresponding IS does not exist

Generator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project. NWHA Spokane October 30, 2014

Turbogenerators. With Top Performance for Steam and Gas Applications. Specifically tailored 4-pole Synchronous Turbogenerators

High Quality Coil Manufacturing

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Alstom Grid provides smart, efficient and environmentally-friendly solutions to deliver electricity reliably across the world GRID

CERTIFICATES OF COMPETENCY IN THE MERCHANT NAVY - MARINE ENGINEER OFFICER

APPENDIX B SPECIFICATION FOR GENERATOR OVERHAUL EMD MODEL AR10 D18... B-1

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

SDS Enclosed Star-Delta Starter User Guide

Steam Turbine Generator Core Isolation Issues at the Redhawk Combined Cycle Plant

Steam Turbine performance improvement solutions for Indian fleets

STEAM TURBINE MODERNIZATION SOLUTIONS PROVIDE A WIDE SPECTRUM OF OPTIONS TO IMPROVE PERFORMANCE

Brochure. Synchronous generators for steam and gas turbines Proven generators reliable power

REAP CARE ROTATING ELECTRICAL ASSET PROGNOSTIC CARE

Implementation of Safety Initiatives

ABB MEASUREMENT & ANALYTICS. Predictive Emission Monitoring Systems The new approach for monitoring emissions from industry

Organization Structure

ANZSASI 2000 CHRISTCHURCH ENGINEERING ANALYSIS. Vlas Otevrel

Turbine Lubricant Varnish Removal Case Studies using SVR

About PT. SARANA KREASI TEKNIK

THERMAL GENERATION PROJECTS

Primary Heat Transport (PHT) Motor Rotor Retaining Ring Failure

Pressurized Air Cooled Generators

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

EVANS ENTErprises, Inc.

MCE TM Product Information 5 kv Electric Motor Analyzer

INSTALLATION OPERATION & MAINTENANCE INSTRUCTIONS For THREE-PHASE INDUCTION MOTORS TYPE HJN / HJA

AGN Single Phase Loading for Re- Connectable 3-Phase Windings

ELIMINATION OF REPETITIVE THRUST BEARING FAILURES ON A PROCESS AIR COMPRESSOR

100 MW Wind Generation Project

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Abrupt Stoppage of Turbine Rotor, running on Barring after Major Overhauling

REVELSTOKE - 1 YEAR DOWN. Applied to Equipment Instruction Number R Class-Group Generate Date: 11 March 2004

BHARAT ALUMINIUM COMPANY LTD. SPECIFICATIONS FOR SYNCHRONOUS GENERATOR GENERAL Make : Jinan Power Equipment Factory Type : WX2

1. SPECIFICATION. Altitude of motor installation. Information: Resistance and temperature specifications of the PTC thermistor / posistor/.

Slow Steaming. Benefiting retrofit solutions from MAN PrimeServ

Industrial RB211 Gzero Gas Turbines

MSD Axially Split Multistage Pump

Refurbishment Solutions

OBJECTIVES LCC HVDC SYSTEMS VSC HVDC SYSTEMS COMMON EQUIPMENT DIFFERENT OPTIONS ECONOMIC IMPACTS CONCLUSIONS

Inspection Testing Repair

Global VPI Insulated Indirectly Hydrogen-Cooled Turbine Generator for Single-Shaft Type Combined Cycle Power Generation Facilities

DESIGN CONSIDERATIONS FOR ROTATING UNIONS SEALING TECHNOLOGIES

Generator Services. WGGS Capabilities Presentation

Geothermal Plant Life Extension

HRSG Operational Challenges and Siemens Solutions

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

DC Substation Solutions For Metal Processing Applications

Sulzer Rotating Equipment Services (Canada) Ltd. Your Service Partner for Innovative Solutions

Long-Term Corporate Resilience

Power Generation Services Solutions for challenging Markets

UNBALANCED MAGNETIC PULL AND AIR-GAP MONITORING FOR LARGE HYDROGENERATORS

Your Service Partner Service Solutions for the Rail Industry

Extended requirements on turbogenerators

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

EP4-Platform: E-126 EP4 / E-141 EP4. Arno Hildebrand, Programm Manager EP4 ENERCON Research & Development

Brochure. Synchronous generators for diesel and gas engines Proven generators reliable power

50 years experience in offering tailor made solutions to suit every customer s need.

PRAIRIE MINES AND ROYALTIES PAINTEARTH MINE MARION 8200 DRAGLINE ELECTRICAL UPGRADES

ABB in primary aluminium From mine to market

HT SERIES SMOKE VENTING EQUIPMENT

MARIM Steam Turbines. Engineering the Future - since MAN Diesel & Turbo

CONTENTS. TECHNOLOGY FOR THE FUTURE... 3 Kongsberg EmPower... 4 GLOBAL CUSTOMER SUPPORT... 7

INTRODUCTION GENERAL GUIDELINES ATTACHING THE DRIVE PARTS

Life Cycle Management of Motors and Generators

(With the possibility of conversion to HFO firing)

Pepco & Delmarva Power. Commercial & Industrial Energy Savings Program Small Business Program October 3, 2012

Authorized Field Change AFC G-06919

Shop and Service Center Motors

RIKT 71 Isothermal Turbocompressor

TURBINE OILS GST PREMIUM 32 CALTEX LUBRICANTS FORMULATED TO FIGHT SLUDGE AND VARNISH

JABIRU AIRCRAFT PTY LTD P.O. Box 5186 Phone: Bundaberg West Fax: Queensland, Australia.

MECHANICAL INTEGRITY CHECKING OF GENERATOR STATOR OVERHANG BY NATURAL FREQUENCY MEASUREMENT

ISCORMA-3, Cleveland, Ohio, September 2005

Company presentation

Appendix 4.7 Mirrlees Assessment Report

SGT-2000E gas turbine series

Sub:EE6604/DESIGN OF ELECTRICAL MACHINES Unit V SYNCHRONOUS MACHINES. 2. What are the two type of poles used in salient pole machines?

Transcription:

Sulzer Turbo Services Company overview

Sulzer today Sulzer Pumps Market leader in pump technology and solutions Sulzer Metco Market leader in surface technology Sulzer Chemtech Market leader for separation, mixing and service solutions Sulzer Turbo Services Leading independent service provider for rotating equipment Main markets served: Main markets served: Main markets served: Main markets served: Oil and gas Transportation Oil and gas Oil and gas Power Power Power Water Transportation Full year 2012: Sales of CHF 4 billion 17 900 employees 2013 <Copyright Sulzer> slide 2

October 2010, S West A selection of case studies for Sulzer Turbo Services Services for rotating equipment Mechanical Turbines and compressors Electro-mechanical Generators and motors Electro-mechanical Turbine or compressor repair Gas turbine component repair Replacement parts (e.g., blades) Field service Technical supervision Turbine/compressor control retrofits Modifications and upgrades Installation services Long-term service agreements Compressor or motor repair Component repair Replacement parts (e.g., coils) Site service Technical supervision Control retrofits Modifications and upgrades Long-term service agreements

POWER GENERATION? How electricity is generated STATOR ARMATURE WINDING TERMINALS 2013 <Copyright Sulzer> slide 4

Dunlin Alpha - Generator Rehabilitation Graeme Robertson - April 2013

Production Platform Generation Problems 2013 <Copyright Sulzer> slide 6

Overview Total generation capacity of 35MW from 5 Generators GT 4 was to be returned to Service after period of inactivity, this was a 15MW, 6.6kv, 4 pole Generator driven by an Avon Engine Provided critical power for Salt Water Injection Pump motors Platform required SWI Motors running to support production Module Roof was not watertight! Generator Anti-Condensation Heaters were defective! 2013 <Copyright Sulzer> slide 7

Bringing back to service Pre-commission checks identified very low IR and no PI. 1000v DC Test IR value 0.2MΩ & breaking down after 4 minutes As our engineers were being mobilised to site, platform staff spun the turbine generator for a period of 4 hours unexcited to determine if dampness / condensation was the issue. Retest did not show any difference in the IR or PI levels Complete winding was wet with an earth fault present 2013 <Copyright Sulzer> slide 8

Investigating the problem Our Service Engineers then carried out a methodical check: opened alternator for internal inspection of rotor / stator for any evidence of ingress of contamination cables and all connections from the cubicle to the alternator terminal box removed all clamps / post connections disconnected the star point / split phase connections 2013 <Copyright Sulzer> slide 9

Investigating the problem internally inspected & tested each phase split low reading phase coils to from 2 halves for inspection & test continue to split until defective coil or coils were located identify the defective area / coil section 2013 <Copyright Sulzer> slide 10

The Defective Coil The defective coil was identified by a process of elimination, and located at 4 o'clock position when viewed from DE, fault was specific to one diamond coil. The stator winding had 66 coils connected in 2 parallel circuits The winding had 5 & 6 coil groups We proposed an in-situ repair potentially saving 16 weeks on time scale and circa 700k on rewind costs A primary objective was to minimise outage time to get SWI pumps operating ASAP. 2013 <Copyright Sulzer> slide 11

The Turbo Generator Generator with end covers partially removed to expose Stator Winding 2013 <Copyright Sulzer> slide 12

Source of the Problem Generator Stator Coils ready for splitting to locate defective coil 2013 <Copyright Sulzer> slide 13

Winding Modification C 1 A 1 Failed Coil 4 pole 3 Phase Generator 66 Slots & 66 Coils 2 Parallel Circuit Star 12 Coil Groups 5 coils & 6 Coils 2 Coil Groups in each parallel path 1 with 5 coils the other with 6 coils Failed coil 2 nd in 6 coil group B 1

Winding Modification C 1 A 1 Failed Coil 4 pole 3 Phase Generator 66 Slots & 65 Coils 2 Parallel Circuit Star 12 Coil Groups 5 coils & 6 Coils 2 Coil Groups in each parallel path 1 with 5 coils the other with 6 coils Failed coil 2 nd in 6 coil group B 1 Jumper introduced to take failed coil out of circuit This jumper on its own would leave circulating currents and unbalanced voltages

Winding Modification C 1 A 1 Failed Coil 4 pole 3 Phase Generator 66 Slots & 60 Coils 2 Parallel Circuit Star 12 Coil Groups all 5 coils 6 Jumpers introduced to take failed coil & 5 other coils out of circuit B 1

Source of the Problem Generator Stator Coils Where jumpers are introduced 2013 <Copyright Sulzer> slide 17

Our Solution.. We calculated what would be the effect of cutting out 6 coils, 2 per phase, on the performance of the Generator It was necessary to take 2 coils from each phase, to prevent circulating currents and kept the winding balanced We assessed that a maximum 10 % loss of output Results were relayed to Client who approved the process and methodology of repair. 2013 <Copyright Sulzer> slide 18

The Completion.. Work was completed in 14 Days utilising 24 hr working :- The generator was part dismantled, rotor remained in position An environmental habitat was erected around the stator Stator winding configuration was changed and reconnected, the defective coil and 5 other coils removed from circuit. Stoving heaters were applied to dry the rest of winding The stator winding was cleaned, dried, and spray varnished The machine was fully built and prepared for test 2013 <Copyright Sulzer> slide 19

Testing & Hand Over Insulation Resistance Test gave PI values of >4 with IR levels commencing at 4GΩ on 5kV Megger Phase Resistance was tested and found to be within 5% range Generator returned to service with slow increase of load from 2 MW to 7MW over a shift and then up to 13.8MW Machine was handed back to client after successful commissioning test, with some alterations to protection relays and AVR settings. 2013 <Copyright Sulzer> slide 20

Conclusion Drilling Program was at risk due to lack of generation capacity Failure to complete the well work-over in time put the complete well at risk, including future oil revenues Failure to provide power for the SWI Motors would result in loss of oil production Generator Repair saved 16 Weeks of down time and circa 700k in repair costs but no estimate of production loss cost?? M/day Work competed to Timeline & Budget, the future revenues from an oil well secured! 2013 <Copyright Sulzer> slide 21

Planta Centro, Venezuela 400 MW Kraftwerk Union Steam Turbine Train Rotor Rewind Siemens Westinghouse Turbo Rotor 2012

Removing End Bell 2013 <Copyright Sulzer> slide 23

Siemens Westinghouse 400MW Turbo Rotor 2013 <Copyright Sulzer> slide 24

Siemens Westinghouse 400MW Turbo Rotor 2013 <Copyright Sulzer> slide 25

Stripping of Rotor 2013 <Copyright Sulzer> slide 26

Siemens Westinghouse 400MW Turbo Rotor 2013 <Copyright Sulzer> slide 27

Siemens Westinghouse 400MW Turbo Rotor 2013 <Copyright Sulzer> slide 28

Siemens Westinghouse 400MW Turbo Rotor 2013 <Copyright Sulzer> slide 29

Transport to Machine Workshop 2013 <Copyright Sulzer> slide 30

Siemens Westinghouse 400MW Turbo Rotor 2013 <Copyright Sulzer> slide 31

Siemens Westinghouse 400MW Turbo Rotor 2013 <Copyright Sulzer> slide 32

Siemens Westinghouse 400MW Turbo Rotor 2013 <Copyright Sulzer> slide 33

Cross Section Layout 1 Modified Retaining Ring Attachment OriginalRetaining Ring Attachment 2013 <Copyright Sulzer> slide 34

New Landing Area 2013 <Copyright Sulzer> slide 35

New Landing Area 2013 <Copyright Sulzer> slide 36

New Landing Area 2013 <Copyright Sulzer> slide 37

New Landing Area 2013 <Copyright Sulzer> slide 38

Machining New Landing Area s 2013 <Copyright Sulzer> slide 39

Grinding Land Area 2013 <Copyright Sulzer> slide 40

New Landing Area 2013 <Copyright Sulzer> slide 41

Clean Room 2013 <Copyright Sulzer> slide 42

QA of New Materials 2013 <Copyright Sulzer> slide 43

New J Lead 2013 <Copyright Sulzer> slide 44

Cleaning Coils 2013 <Copyright Sulzer> slide 45

Rewinding 2013 <Copyright Sulzer> slide 46

Rewinding 2013 <Copyright Sulzer> slide 47

Rewinding 2013 <Copyright Sulzer> slide 48

Rewinding 2013 <Copyright Sulzer> slide 49

Blocking 2013 <Copyright Sulzer> slide 50

Wedging 2013 <Copyright Sulzer> slide 51

Blocking 2013 <Copyright Sulzer> slide 52

Curing 2013 <Copyright Sulzer> slide 53

Curing 2013 <Copyright Sulzer> slide 54

Curing Ends 2013 <Copyright Sulzer> slide 55

Curing 2013 <Copyright Sulzer> slide 56

Oven 2013 <Copyright Sulzer> slide 57

Curing 2013 <Copyright Sulzer> slide 58

Wedging 2013 <Copyright Sulzer> slide 59

Wedges 2013 <Copyright Sulzer> slide 60

Wedging 2013 <Copyright Sulzer> slide 61

Wedges 2013 <Copyright Sulzer> slide 62

Wedges 2013 <Copyright Sulzer> slide 63

Wedges 2013 <Copyright Sulzer> slide 64

Insulating End Windings 2013 <Copyright Sulzer> slide 65

Insulating End Windings 2013 <Copyright Sulzer> slide 66

Overspeed and Balancing 2013 <Copyright Sulzer> slide 67

Overspeed and Balancing 2013 <Copyright Sulzer> slide 68

Complete Rewind ready for Transport Return 2013 <Copyright Sulzer> slide 69

Transport back to site 2013 <Copyright Sulzer> slide 70

Benefits for Insurers Quick response Outage duration minimisation Service approach with customers Listen, analyse & provide solution Independent advise on repair or replace Wide range of repair capabilities & expertise Knowledge of all manufacturers product Experts in reverse engineering & re-manufacture Machine performance as original machine performance as a minimum Competitive pricing 2013 <Copyright Sulzer> slide 71