Electromagnetic Coordination Study Objectives for Railroad and Electric Utility Shared Corridors

Similar documents
ECET Distribution System Protection. Overcurrent Protection

OSHA Update. Electric Power Generation, Transmission and Distribution Standard (Part 1910 & 1926)

2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding

Reducing. with Current. arc flash note 2. points of interest. Why Use Current Limiting Fuses. By mike lang, Principal field engineer

Why Electric Safety Standards

Electrical Test of STATCOM Valves

Jaeshininformation Co., of Korea Distributor

Engineering Considerations. Glenn Stapleton - Senior Electrical Design Engineer Lines

III. Substation Bus Configurations & Substation Design Recommendations

4-Day Power System Analysis, Coordination, System Studies

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Please use the Q & A utility to ask us any questions concerning the material being presented.

Safe, fast HV circuit breaker testing with DualGround technology

Independent Testing Laboratory for High Voltage Equipment

Auxiliary Relay (7PJ11) and Trip Relay (7PJ12)

3.2. Current Limiting Fuses. Contents

Earthing Calculation. Contents. Introduction. From Open Electrical

/12/$ IEEE. M. Bashir M.Sc student, Student Member, IEEE Ferdowsi University of Mashhad Mashhad, Iran

The New 2017 National Electric Safety Code Overview and Significant Changes. Presented by. Mickey Gunter October 28, 2016

ElectricCourseCatalog.

Power System Stability Analysis on System Connected to Wind Power Generation with Solid State Fault Current Limiter

RESIDUAL CURRENT CIRCUIT BREAKER

6/4/2017. Advances in technology to address safety. Thomas A. Domitrovich, P.E., LEED AP VP, Technical Sales Eaton

Electrical Safety and Overcurrent Protection

MCE TM Product Information 5 kv Electric Motor Analyzer

Advanced Protective Relay Training

EMC Issues in Electric Drives

Selective Coordination

Features. LED Driver. RACT09 9 Watt. TRIAC Dimmable. Single Output RACT09- AC/DC Converter

Dual Power. Protection. Protection

Pretest Module 29 High Voltage Unit 1

The Evolution of Arc Fault Circuit Interruption

EMC System Engineering of the Hybrid Vehicle Electric Motor and Battery Pack

Range 16A to 63A. Sensitivity 30mA, 100mA, 300mA, 500mA. Execution Double Pole, Four Pole. Specification IEC / IS : 2000

34 th Hands-On Relay School

Tests are conducted in accordance with IEEE Standard 386. ac 60 Hz 1 Minute Withstand 50

Copyright 2003 Advanced Power Technologies, Inc.

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

ELECTRICAL POWER and POWER ELECTRONICS

Arc flash hazard mitigation

STEEL CASING OVERHEATING ANALYSIS OF OPERATING POWER PIPE-TYPE CABLES

Impulse Voltage Test System, Q Structure, kV

Deadbreak Apparatus. connectors. 600 A 15/25 kv Class GENERAL

INSTALLATION PRODUCTION TESTS

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Chapter 6 Generator-Voltage System

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards

CHAPTER 3 CAUSES AND EFFECTS OF ELECTRICAL FAULTS

Net Metering Interconnection Requirements

Electrical Hazards in Construction

INTRODUCTION. The plug-in connection on the cables and lightning arrestors, allows for easy installation and replacement.

On_Disc. 2 o/c1 BS 7671 applies to a lift installations b highway equipment c equipment on board ships d electrical equipment of machines.

K-Limiter high ampere Companion II fuse

White Paper. Ground Fault Application Guide. WL Low Voltage Power Circuit Breakers

Unit Protection System for Pumped-Storage Power Stations

VFD Best Practices: Getting the Most from Your VFD Investment

Hydro Stator End Winding Accelerometer System

RSC-G-004-B Guidelines For The Design Of Section 3 3 ELECTRIC TRACTION SYSTEMS 2

Motor Protection Fundamentals. Motor Protection - Agenda

KV4-300 mk2. KV5-200 mk2. KV5-100T mk2. KV3-250 mk2

Hydro Stator End Winding Accelerometer System

Transmission & Distribution Glossary of Electrical Terms

Fluke 438-II Power Quality and Motor Analyzer

Future Proof Your Arc Flash Assessment

Type SIMOPRIME A4, up to 24 kv, Air-Insulated Medium-Voltage Switchgear

RECOMMENDATIONS FOR USING FREQUENCY INVERTERS WITH POSITIVE DISPLACEMENT REFRIGERANT COMPRESSORS

TRAC-3 TENSION READOUT AND CONTROL

NZQA unit standard version 8 Page 1 of 5. Apply and remove earths from conductors on electricity supply networks

ABB n.v Power Quality in LV installations

University of Jordan School of Engineering Electrical Engineering Department. EE 219 Electrical Circuits Lab

Case 2 Induced Harmonics From a Wind Farm

HGM1750 Genset Security Module USER MANUAL Smartgen Technology

Not all Low Voltage Switchgear is created equal

E-15 Uninterruptible Power Systems (UPS)

Electrical Workplace Safety

SYSTEM EARTHING & PROTECTIVE EARTHING

Contents. 1 Introduction. 2 General Product Information. 3 General Test Requirements

The University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 6

ELECTRICAL ENGINEERING & COMPUTER SCIENCE NEWSLETTER Volume

High Voltage Surge Arresters Buyer s Guide Section Transmission Line Arrester PEXLINK

Inductive. SeekTech Clamp WARNING! Operator s Manual

Electrical Safety in Die Casting

Targeted Application of STATCOM Technology in the Distribution Zone

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS

TECHNICAL GUIDE FOR PROXIMITY SENSORS DEFINITIONS YAMATAKE PROXIMITY SENSOR CATEGORIES

Characteristics of LV circuit breakers Releases, tripping curves, and limitation

Ch 4 Motor Control Devices

Electrical Measuring Instruments

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Electrical Hazard Three factors determine the resistance of a substance to the flow of electricity: conductors insulators extreme caution

Not all Low Voltage Switchgear is created equal

City of Palo Alto (ID # 6416) City Council Staff Report

Appendix B PCC Electrical Safety Training

MREC Mark A. Cook General Manager, REPS PSCW. Farm Wiring Programs and Transmission Underbuild Issues

VariSTAR Type AZE station-class surge arresters for systems through 345 kv IEEE certified

Matrix APAX. 380V-415V 50Hz TECHNICAL REFERENCE MANUAL

INSTITUTE OF AERONAUTICAL ENGINEERING Dundigal, Hyderabad

METEOROLOGICAL INSTRUMENTS

Preparing the Site. Information About the Site Requirements CHAPTER

SF6 GAS INSULATED METAL ENCLOSED SWITCHGEAR (GIS)

Transcription:

Electromagnetic Coordination Study Objectives for Railroad and Electric Utility Shared Corridors Eilis M. Logan UPRR Marvin J. Frazier Corr. Comp Co.

Electromagnetic Interference Magnet and Paper Clip Field Rather than Circuit View Point Passive Conductors - Rails Vital Signals - Railroad Systems

Electromagnetic Interference Coexist Simultaneously Source - Electric & Magnetic Fields Coupling Mechanism Receptor May Be Susceptible

Electromagnetic Interference Source - Power System Coupling Paths: Capacitive, Conductive, Inductive Susceptible Receptor - Railroad

Discussion Coupling Mechanisms Power System Influence Railroad Personnel Safety Criteria Equipment Compatibility Electrical Coordination Process

Coupling Mechanisms Capacitive - Electrostatic Personnel Safety Pole line, Crossing Gate, Signal Light Structures Conductive - Fault & Other Short Duration Conditions Personnel Safety & Equipment Compatibility High Local Earth Surface Potentials Magnetic - Inductive Personnel Safety & Equipment Compatibility Significant - Paralleling Power Line and Rails

Power System Influence Two Operating Conditions Steady-State - Normal Conditions Magnetic & Electrostatic Coupling Personnel Safety - Conductor-to-Earth Voltages Equipment Compatibility - Conductor-to-Conductor Voltages

Power System Influence Two Operating Conditions Fault and Other Short Duration Conditions Magnetic & Conductive Personnel Safety - Step & Touch Rails, Rolling Stock, Track-side Housing Equipment Compatibility - Rail Current - Surge Arrester Rating

Railroad Personnel Safety Signal and Track Maintenance Conductor-to-Earth Different Levels Are Acceptable Steady-State Fault or Short Duration

Railroad Personnel Safety Three Classifications Threshold - Tingling Startle - Annoying - Not Harmful Primary Shocks - 99.5% Voluntarily Let-Go Ventricular Fibrillation

Railroad Personnel Safety Conductor-to-Earth Objective Based on Primary Shocks: Minimize the Chance Power System Steady-State - Body Current Higher than Let Go Power System Fault - Ventricular Fibrillation

Railroad Personnel Safety Steady-State Operation Region of Electric Field Analyzed by the Shock Current NESC = 5 ma ac rms General Population Including Children Railroad Facilities Capacitive Induction NESC = 5 ma ac rms

Railroad Personnel Safety Steady-State Operation Conductor-to-Earth 25V Rail-to-Ground Each Side of Insulated Joints Rail Cut Locations Slide Fence Conductor Pole Line Conductor Underground Cable, Conductor, Metallic Shield

Railroad Personnel Safety IEEE Std 80 Safety Guide AC Substation Grounding Design Work Safely Around Substation Touch Voltage Hand-to-Feet Touching an Energized Object Step Voltage Between Feet Elevated Earth Surface Potential

Railroad Personnel Safety Power System Fault & Short Duration Conditions Hand-to-Feet Hand-to-Feet Near Near Earth Earth Signal Signal Houses Houses Rail Rail -- Railroad Railroad Work Work Zones Zones 25 25 Feet Feet Center Center Track Track By By Hand Hand or or Object Object Electrically Electrically Connected Connected to to Rail Rail

Railroad Personnel Safety Power System Fault & Short Duration Conditions Hand-to-Feet Hand-to-Feet Near Near Earth Earth Insulated Insulated Joints Joints Rail Rail Cut Cut Locations Locations Hand-to-Hand Hand-to-Hand Insulated Insulated Joints Joints Rail Rail Cut Cut Locations Locations

Railroad Personnel Safety Substation - Railroad Different Environments Substations Enclosed - Chain Link Fence Employees Aware Hazards Electrical Characteristics Inspected & Tested

Railroad Personnel Safety Application IEEE Std 80 Railroad Environment Reevaluation of Parameters Assess Safe Touch & Step Resistive Stone Covering not Ballast Region Protected - Railroad Work Zones Size of a Person - Body Impedance & Weight

Railroad Personnel Safety Application IEEE Std 80 Railroad Environment Ballast Resistivity Railroad Work Zone Electrical Characteristics Not Specified Ballast may not be Present Rotating Ballast Regulator 180-17 ft Disturb or Remove During Maintenance

Railroad Personnel Safety Application IEEE Std 80 Railroad Environment Body Impedance Railroad 24 hours a Day, 7 days a Week All Weather Conditions No Insulating Properties of Shoes or Gloves Standing in Bare Moistened Feet Per Std 80-1000 ohms Body Impedance

Railroad Personnel Safety Application IEEE Std 80 Railroad Environment - Body Weight IEEE Std 80 used United States IEEE Std 80 Considers Size - Weight Railroad Operational & Construction Criteria Smaller Sized Person - UPRR Railroad Occupational Safety = 100 LB

Equipment Compatibility Equipment Compatibility -- Susceptibility Signal System -- Abnormal Operation False Activation or Activation Failure Different Types -- Different Levels Power System Steady-State & Fault

Equipment Compatibility Power System Steady-State Operation 60 Hz & Harmonics Voltage and Current Must be Less Than Tolerance Level Equal Excitation Paired Conductors Day-to-Day Unbalance Conditions Nearby Power Line Differential Voltage

Equipment Compatibility Maximum Steady-State Operation Coupled Conductor-to-Conductor for UPRR Balanced Track Conditions Shorted Insulated Joint Electrically Broken Rail, Conductor Grounded Rail, Conductor Presence of a Train

Equipment Compatibility Power Line Fault Conditions Rail-to-Near Earth Potentials With and Without Arresters Operation AREMA Performance Guidelines Lightning Wave Form - Short Duration Power Line Fault Wave Form - Long Duration Rail Current Less Than Arrester Rating Based on Power System Fault Clearing Times

Electrical Coordination - Process Electromagnetic Coordination Study Resolve Interference Problems Location, Design, Construction, Operation & Maintenance of Power & Railroad Systems Three Phases

Electrical Coordination - Process Phase 1 Meeting Railroad, Utility, Consultant Scope of Investigation Acceptable Mitigation Modeling Assumptions Design Criteria

Electrical Coordination - Process Phase 2 - Generate Study Railroad & Power System Data Public & Personnel Safety Criteria Equipment Impedance & Susceptibility Data Computer Models - Steady-State & Fault Mitigation Design - Limit Coupled Voltages

Electrical Coordination - Process Phase 3 - Approval Power Utility Company Railroad Equipment Supplier Railroad Finance Operating & Engineering

Summary - Electromagnetic Study Defines Physical & Electrical Parameters Provide Predictive Assessment of Coupled Voltages & Currents Power System Conditions Steady-State & Fault Personnel Safety Equipment Compatibility Mitigation

Technology Races On Thank You

Questions?