Impacts of Fast Charging of Electric Buses on Electrical Distribution Systems

Similar documents
Impact Analysis of Fast Charging to Voltage Profile in PEA Distribution System by Monte Carlo Simulation

Electric Vehicles Coordinated vs Uncoordinated Charging Impacts on Distribution Systems Performance

Y9. GEH2.3: FREEDM Cost Benefit Analysis based on Detailed Utility Circuit Models

Increasing PV Hosting Capacity in Distribution Networks: Challenges and Opportunities. Dr Andreas T. Procopiou

TECHNICAL IMPACTS OF ELECTRIC VEHICLES CHARGING ON AN ITALIAN DISTRIBUTION NETWORK

NORDAC 2014 Topic and no NORDAC

LOCAL VERSUS CENTRALIZED CHARGING STRATEGIES FOR ELECTRIC VEHICLES IN LOW VOLTAGE DISTRIBUTION SYSTEMS

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Design Modeling and Simulation of Supervisor Control for Hybrid Power System

INCREASING electrical network interconnection is

Planning of electric bus systems

HOMER OPTIMIZATION BASED SOLAR WIND HYBRID SYSTEM 1 Supriya A. Barge, 2 Prof. D.B. Pawar,

Optimized solution for Electric Transit Buses

Electric Power Engineering, Chalmers

GRID PLANNING BY INTEGRATE CUSTOMER METERS

Economics of Vehicle to Grid

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

PV and opportunistic electric vehicle charging in a Swedish distribution grid

The potential for local energy storage in distribution network Summary Report

Power Balancing Under Transient and Steady State with SMES and PHEV Control

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation

Island Smart Grid Model in Hawaii Incorporating EVs

Battery Energy Storage

ECONOMIC EXTENSION OF TRANSMISSION LINE IN DEREGULATED POWER SYSTEM FOR CONGESTION MANAGEMENT Pravin Kumar Address:

Real-Time Simulation of A Modular Multilevel Converter Based Hybrid Energy Storage System

Reactive power support of smart distribution grids using optimal management of charging parking of PHEV

Technological Viability Evaluation. Results from the SWOT Analysis Diego Salzillo Arriaga, Siemens

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Smart Grids and Mobility

3.17 Energy Resources

Design and Implementation of Reactive Power with Multi Mode Control for Solar Photovoltaic Inverter in Low Voltage Distribution System

The Swedish Government Inquiry on Smart Grids

Coordinated Charging of Plug-in Hybrid Electric Vehicles to Minimize Distribution System Losses

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

An Improved Powertrain Topology for Fuel Cell-Battery-Ultracapacitor Vehicles

Zero Emission Bus Impact on Infrastructure

THE alarming rate, at which global energy reserves are

INTEGRATING PLUG-IN- ELECTRIC VEHICLES WITH THE DISTRIBUTION SYSTEM

Research Needs for Grid Modernization

EV - Smart Grid Integration. March 14, 2012

Battery Electric Bus Technology Review. Victoria Regional Transit Commission September 19, 2017 Aaron Lamb

Analysis of a Hybrid Energy Storage System Composed from Battery and Ultra-capacitor

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014

Energy Management for Regenerative Brakes on a DC Feeding System

STABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL

Role of solar PV prosumers in enabling the energy transition towards a fully renewables based power system for India

Power Management with Solar PV in Grid-connected and Stand-alone Modes

Electric Vehicle-to-Home Concept Including Home Energy Management

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

A simulation tool to design PV-diesel-battery systems with different dispatch strategies

Energy Storage for the Grid

Power Consump-on Management and Control for Peak Load Reduc-on in Smart Grids Using UPFC

Electric vehicles a one-size-fits-all solution for emission reduction from transportation?

Analyse Cost Effectiveness of Different Charging Systems for Electric Buses

Transit Vehicle (Trolley) Technology Review

Dual power flow Interface for EV, HEV, and PHEV Applications

OPF for an HVDC feeder solution for railway power supply systems

MEDIA RELEASE. June 16, 2008 For Immediate Release

ENERGY STORAGE SOLUTIONS FOR IMPROVING THE ENERGY EFFICIENCY OF PUBLIC TRANSPORT VEHICLES

Modelling of demand response in distribution systems

Impact of electric vehicles on the IEEE 34 node distribution infrastructure

Optimal Placement of EV Charging Station Considering the Road Traffic Volume and EV Running Distance

Charging Electric Vehicles in the Hanover Region: Toolbased Scenario Analyses. Bachelorarbeit

Underpinning Research Power Electronics in Distribution Networks

A flywheel energy storage system for an isolated micro-grid

Performance of Batteries in Grid Connected Energy Storage Systems. June 2018

USAGE OF ACCUMULATION TO SUSTAIN THE DAILY DIAGRAM OF ELECTRICITY PRODUCTION IN PHOTOVOLTAIC POWER PLANT

Study Results Review For BPU EV Working Group January 21, 2018

Optimal and Modular Configuration of Wind Integrated Hybrid Power Plants for Off-Grid Systems

Grid Impact of Electric Vehicles with Secondary Control Reserve Capability

Implementation of Bidirectional DC-DC converter for Power Management in Hybrid Energy Sources

TRANSNATIONAL ACCESS USER PROJECT FACT SHEET

Decentralized Battery Energy Management for Stand-Alone PV- Battery Systems

An approach for estimation of optimal energy flows in battery storage devices for electric vehicles in the smart grid

EV Strategy. OPPD Board Commitee Presentation May 2018 Aaron Smith, Director Operations

Modeling and Comparison of Dynamics of AC and DC Coupled Remote Hybrid Power Systems

Electrical Energy Engineering Program EEE

American Electric Power s Energy Storage Deployments

OPF for an HVDC Feeder Solution for Railway Power Supply Systems

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

Smart Grids and Integration of Renewable Energies

Electric Mobility in Africa Opportunities and Challenges. African Clean Mobility Week, Nairobi/Kenya, March

Applications of flow batteries in Africa

Cost Benefit Analysis of Faster Transmission System Protection Systems

Batteries vs Cables ELIN BERGSTEDT, SOFIA NYSTRÖM. Master s thesis in Electric Power Engineering

Presentation of Electricity Market Model by TU Vienna

INTERNATIONAL JOURNAL OF ELECTRICAL ENGINEERING & TECHNOLOGY (IJEET)

Distribution Feeder Upgrade Deferral Through use of Energy Storage Systems

DISTRIBUTED GENERATION FROM SMALL HYDRO PLANTS. A CASE STUDY OF THE IMPACTS ON THE POWER DISTRIBUTION NETWORK.

ECEN 667 Power System Stability Lecture 19: Load Models

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

Sizing of Ultracapacitors and Batteries for a High Performance Electric Vehicle

MVDC link in a 33 kv distribution network

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

Energy Management Through Peak Shaving and Demand Response: New Opportunities for Energy Savings at Manufacturing and Distribution Facilities

TECHNO-ECONOMIC EVALUATION OF VOLTAGE DEPENDENT ACTIVE AND REACTIVE POWER CONTROL TO REDUCE VOLTAGE VIOLATIONS IN DISTRIBUTION GRIDS

RI Power Sector Transformation Con Edison Experiences. May 31 st, 2017

Technology from the New Product SANUPS K for a Smart Grid Society

Part funded by. Dissemination Report. - March Project Partners

ABB POWER SYSTEMS CONSULTING

Transcription:

Impacts of Fast Charging of Electric Buses on Electrical Distribution Systems ABSTRACT David STEEN Chalmers Univ. of Tech. Sweden david.steen@chalmers.se Electric buses have gained a large public interest lately. In Gothenburg, Sweden a demonstration project is currently underway where electrical and hybrid electric buses are being tried. This paper investigates the impacts on the electrical distribution system from the fast charging stations used to power the electric buses. Alternatives to mitigate the impacts including demand response and energy storage at the charge location have also been investigated in the paper. A case study has been performed for the distribution system of Chalmers University of Technology where a charging station is located. The study results show that in all of the simulated areas, the grid could handle a 300 kw charge station without any problems. Energy storage and demand response could, to some extent, support the grid to manage the fast charging stations but would be limited by the utilization factor of the charger. INTRODUCTION Electric buses are being considered an attractive alternative to reduce global CO 2 emissions as well as local pollution and noise in modern cities [1]. They have lately gained increasing attention recently by various stakeholders, including city authority, bus manufacturers, and distribution network companies. Compared to the conventional bus, the electric bus uses electricity for propulsion and needs to be charged from the electrical grid. Currently there are three main alternative designs of the bus/charge system, including overnight charging, opportunity charging, and flash charging [2]-[3]. The overnight charging is used for buses with large batteries that could cover the fully daily distance and mainly charge during the night when the bus is parked. Flash charging refers to charging at the bus stops at a high power level. This system requires less energy to be stored in the bus, but on the other hand, a more expensive charge infrastructure. The opportunity charging can be seen as something in between, the buses are being charged during normal pauses in the time table, e.g. at the end stops. This requires less expensive infrastructure but larger batteries compared to the flash charging [2]. Due to the high requirements on electric energy, electric buses could have a substantial impact on the electrical distribution system [3] [6]. In [3], the impact was found to be less severe for overnight charging compared to the other two alternatives, mainly due to the lower power requirements and the lower electricity demand during Le Anh TUAN Chalmers Univ. of Tech. Sweden tuan.le@chalmers.se night time. The high power requirement and short charge time for flash and opportunity charging will result in an uneven charge profile for the charge station [3]. Even by considering a number of chargers covering several bus routes, the instantaneous peak demand could be substantially higher than the hourly average demand [5], [6]. To decrease the grid impact of the charger, the charge station could be equipped with an energy storage system (ESS) [2]. In [4], the value of adding an energy storage was investigated for a fast charging station. The results indicate that from a cost perspective it could be beneficial to invest in an ESS. In Sweden a project called ElectriCity is currently underway where a new bus line in Gothenburg is operated using electric and plug-in hybrid electric buses [7]. The project aims to demonstrate and evaluate the potential benefits with electric public transportation such as indoor bus stations, but will also serve as a platform to test and verify new research concepts. This paper will present measurements from an existing fast charging station located at the campus of Chalmers University. The measurements are used to estimate the impact on different parts of the local distribution grid. Furthermore, alternatives to reduce the impact have been investigated, including ESS and demand response (DR). The paper is organized as follows, Section I present the data and assumptions used in the study. Section II presents the approach and simulation model. In Section III, the results are presented and the conclusions are presented in Section IV. METHODOLOGY The study consists of two parts, one part covering the measurement of the charging and the resulting impact on the connected distribution system and one part covering the possibilities to reduce the impact by using ESS and DR. The flowchart of the study approach is presented in Figure 1. The grid impact was assessed by simulations in an optimal power flow based model using General Algebraic Modeling System (GAMS) [8]. The model includes a module that optimally schedules customers flexible loads which is utilized in the case with DR. The model is further described in [9]. To enable the possibility to include an ESS, the model was extended with an energy storage module considering the state of charge of the batteries. CIRED 2017 1/5

To analyze the grid impact of one charge station and the possible benefits of utilizing active strategies, the objective function of the model was set to minimize the grid losses. In addition, the model could be used in order to find the maximum charge power that could be extracted at different locations. Collect data Measurement route 55 of 6 seconds [10]. The measurements were used to evaluate the impacts on the distribution system and to analyze alternatives to reduce the impacts. Grid data One of the fast charging stations is located at the Johanneberg Campus of Chalmers University Technology. Scenario Reference case Demand response Energy storage Set charge point = 1 Optimization Results Run OPF (max. charge power min. grid losses) Daily losses Charge point =CP max End CASE SET-UP AND DATA YES Charge point +1 This section presents the data and assumption used in the study. Electric bus data and measurement The electric bus line investigated in this study was put in operation in 2016 connecting the two campuses of Chalmers University of Technology. The route is approximately 10 km long and takes about 25 minutes and there is one departure every 10 minutes. It is operated by three fully electrical buses and 7 hybrid electric buses, all developed by Volvo buses [7]. The charging is conducted at each end stop with a charge power of up to 300 kw. The charge station is provided by Siemens and is based on conductive power transfer through a pantograph-system. Electrically, the charge stations are connected to the 10 kv distribution system through an existing 10/0.4 kv transformer by two parallel 240 mm 2 cables. The measurements were conducted during November 2016 January 2017 using a measurement system that measured the energy consumption with a time resolution NO Maximum available capacity Figure 1 Flow chart of the proposed approach Figure 2 One-line diagram of the distribution system in the Campus Johanneberg of Chalmers University of Technology The area consists mostly of office buildings, lecture halls and laboratory facilities. Figure 2 presents a one-line diagram of the 10 kv distribution system. The system is designed as a meshed distribution system but is normally operated radially. The charge station is located at bus 28. To assess the worst case condition the simulations were conducted for the day with highest demand. For investigating the possible impacts of fast charging in other areas and to assess the potential to reduce the impacts by using DR or ESS, a residential area in Gothenburg was chosen. The grid consists of 26 10/0.4 kv transformers connected through 3 main feeders. A detailed description of the grid can be obtained in [11]. As for the campus area, the charge impact was assessed for the peak day of the area. For the case with DR, only electric heating was considered as schedulable and the temperature variations were limited to ±1.5 ºC. The responsive customers were assumed to be 10 % and evenly distributed within the grid. For the case with ESS at the charge location the charge/discharge profile was decided by the optimization model with the objective set to minimize the losses in the system. Simulations were conducted with a usable capacity of the ESS of 5% of the charge station capacity and with a limit on the charge rate at 5C (of the usable capacity). Energy storage system The possible impact of the ESS will mainly depend on the size of the storage and the charge time in relation to the CIRED 2017 2/5

23:59 01:42 03:27 05:07 06:54 08:40 10:23 12:09 13:51 15:29 17:10 18:51 20:34 22:16 Power [kw] 24 th International Conference on Electricity Distribution Glasgow, 12-15 June 2017 time between the buses. For a single charge point, the power drawn from the grid could be calculated from Eq.1, P Grid = { P Ch E ESS E bus T C if E ESS < E bus (1 T C ) if E ESS > E bus (1 T C ) Where, P Ch is the charge power, E ESS is the usable capacity of the storage, E bus is the energy required by the bus, T C is the charge time and is the time between the buses. As can be derived from Eq. (1), for large ESS or for charge stations with a low utilization, i.e. long time between the buses or short charging times, the potential reduction to the grid is limited by the energy required by the bus and the time between the buses, e.g. the average power demand. For smaller ESS, the possibility to shift large amount of energy is limited, or if the charge station has a high utilization the average charge power is high, hence the possible load reduction is limited by the storage size and the charge time. RESULTS AND DISCUSSIONS This section presents the results from the study. Energy measurement Figure 3 and 4 present the charge power during one day in January and for two charge cycles. As can be seen, the charge power varies between about 100-240 kw, where the hybrid buses are being charged with 100 kw and the fully electric buses with 240 kw. One of the reasons for this could be due to that the battery in the hybrid bus is designed for lower current levels and charging with higher power would reduce the lifetime of the battery. The charge time for the electric bus is approximately 2 minutes while it varies for the hybrid bus but is generally around 3 minutes. 250 200 (1) Power [kw] 250 200 150 100 50 0 07:21:00 07:22:43 07:24:13 07:25:42 07:27:17 07:29:10 07:30:58 Time 07:32:51 07:34:26 07:36:03 07:37:33 07:39:45 Figure 4 Load profile for two charge cycles 9th January 2017 Figure 5 Reduction in power drawn from the grid with 300 kw charger for different utilization factors and energy storage sizes Energy storage system Figure 5 presents the grid power drawn from a 300 kw charge station with different storage sizes for four different utilization factors of the charger, for the case with an energy consumption of 15 kwh between the charge stations. As can be seen, even with a small ESS, the power could be reduced substantially. However, it is important to remember that although the energy content is low the actual size may be limited by the charge-rate of the ESS if e.g. batteries are used. Similarly, due to the high number of cycles it could be beneficial to limit the depth of the charge cycles to prolong the life of the ESS. Chalmers campus The simulations from the Chalmers Grid and the real bus charging station shows that the impact on the distribution 150 100 50 0 Time Figure 3 Load profile from one of the bus charging station in Gothenburg 9 th January 2017 Figure 6 Load profile Chalmers grid including bus charging based on measurement CIRED 2017 3/5

Figure 7 Available charge capacity in the residential area without any strategy (blue) and with ESS (green) and DR (yellow) system is limited and the peak demand increase by only about 1%, as can be seen in Figure 6. Similarly, the voltage levels remain within limits and the changes in voltage due to the bus charging is minor. The lowest voltage level reaches 0.98 pu. Regarding the losses, there is a negligible impact on the losses due to the charging, this is mainly due to the small increase of the system load and due to that the distribution system is strong and only covers a small geographical area, i.e. the lengths of the feeders are short. Residential area For the simulations of the residential area, the measured charge profile from the electric bus has been used to assess the potential impacts on the distribution system. To find the maximum available capacity in the grid, simulations were conducted with the objective function being maximizing the charge power. The location of the charge station was varied to assess the impact at the different nodes in the distribution system. As for the case with the real charger at Chalmers campus, a dedicated transformer for the charge station were considered in the simulations. Figure 7 presents the available capacity at the different buses in one of the feeders in the distribution system for the cases with/without active strategies, i.e. ESS and DR. As can be seen the available capacity increases with both strategies although the difference is limited for the size of ESS and responsive customers assumed (12.5 kwh and 10% responsive customers). The capacity increases with about 65 kw for the ESS, which is lower compared to what could be calculated from Eq. (1), The reason for this is due to the discharge rate was limited to 5C (of the usable capacity). With DR the capacity is slightly higher compared to the case with ESS. However, since the ESS is connected to the same node as the charge station the influence on the peak demand in that nod would be higher for the case with ESS compared to DR. It should be noted that the capacity is enough for at least two charge stations in any node without require reinforcements in the distribution system. However, the DSO in Gothenburg design their system according to the N-1 criterion to maintain a high reliability. In the simulated area, this redundancy is not available for the simulated day and the charging of electric buses would reduce the possibility further. The limiting factor was found to be the current limitation in the feeder cable, hence the peak capacity is almost constant for the different nodes. As a consequence the location of the charge station would not affect the result significantly for the studied feeder and almost 800 kw charge power could be distributed anywhere within the system. For feeders/systems with large voltage variations the location/distribution of the charge stations within the grid could have a larger effect on the capacity. Regarding the losses, the charge station has a limited influence on the total losses in the distribution system for the simulated day, about 13 kwh increase. However, this is based on the measured charge profile, e.g. including plug-in hybrid electric buses, for a line with solely electric buses the impact would increase. With the assumed size of the ESS the losses will stay in the same range while they will be slightly reduced for the case of DR, about 12 kwh reduction compared to the case without DR. The reason for the higher loss reduction for the case with DR is due to that more energy is shifted in time compared to the case with ESS and that it is more distributed in the system. The reduction in losses does not solely justify the investment cost associated with the ESS or DR strategies. On the other hand, there could be alternative gains that make the investment more lucrative, such as for areas with large number of solar photovoltaics (PVs) or to enable the possibility to connect the charger to the 400V grid. It could also have an economic incentive for the owner of the charge station by reducing the connection fee and demand charges. However, due to the large fluctuation in the charge power, the hourly average demand is relative low. Since the demand charges generally are based on the hourly average demand the incentive for the owner of the charge station to invest in e.g. ESS is limited under current market structure. Another alternative to reduce the impacts of bus charging could be to use reactive power compensation. However, this alternative has not been investigated in this paper. Interested readers are referred to [12] for more detailed treatment of this topic CONCLUSIONS This paper presents measurements from a fast charging station for electric buses in Gothenburg, Sweden and an investigation on the grid impacts caused by the fast electric bus charger. Alternatives for reducing the grid impact have also been investigated, including energy storage at the charge point and demand response of the customers CIRED 2017 4/5

connected to the distribution system. It has been found that in the area where the charger has been connected (i.e., at the Chalmers University campus), the impact is limited, mainly due to the fact that the grid is strong grid and has short cable lengths. For a weaker residential distribution system, the additional load due to bus charging could be handled without any overloaded components or voltage issues for charge power up to 800 kw. With an increased charge power or more electric bus routes, the impact may not be negligible. By installing an energy storage or using demand response, the possible hosting capacity for bus charging could increase but the possible impact is affected by the frequency of the buses on the bus line. Acknowledgments The authors is grateful for the financial support from Energiforsk/ELEKTRA and the Swedish energy agency. Furthermore, Göteborg Energi and Akademiska Hus is gratefully acknowledged for supporting the project with data. REFERENCES [1] M. Mahmoud, R. Garnett, M. Ferguson, and P. Kanaroglou, Electric buses: A review of alternative powertrains, Renew. Sustain. Energy Rev., vol. 62, pp. 673 684, Sep. 2016. [2] O. Olsson, A. Grauers, and S. Pettersson, Method to analyze cost effectiveness of different electric bus systems, presented at the EVS29 Symposium, Montréal, Québec, Canada, 2016. [3] M. Mohamed, H. Farag, N. El-Taweel, and M. Ferguson, Simulation of electric buses on a full transit network: Operational feasibility and grid impact analysis, Electr. Power Syst. Res., vol. 142, pp. 163 175, Jan. 2017. [4] H. Ding, Z. Hu, and Y. Song, Value of the energy storage system in an electric bus fast charging station, Appl. Energy, vol. 157, pp. 630 639, Nov. 2015. [5] M. Rogge, S. Wollny, and D. U. Sauer, Fast Charging Battery Buses for the Electrification of Urban Public Transport A Feasibility Study Focusing on Charging Infrastructure and Energy Storage Requirements, Energies, vol. 8, no. 5, pp. 4587 4606, May 2015. [6] L. Lindgren, Full electrification of Lund city bus traffic - A simulation study, vol. 7255, 2015. [7] ElectriCity, ElectriCity. [Online]. Available: http://www.goteborgelectricity.se/. [Accessed: 15- Jan-2017]. [8] R. E. Rosenthal, GAMS A User s Guide. Washington, DC, USA: GAMS Development Corporation. [9] D. Steen, L. A. Tuan, and O. Carlson, Effects of Network Tariffs on Residential Distribution Systems and Price-Responsive Customers Under Hourly Electricity Pricing, IEEE Trans. Smart Grid, vol. 7, no. 2, pp. 617 626, Mar. 2016. [10] Eliq - A digital energy advisor for your home, Eliq. [Online]. Available: http://eliq.io/. [Accessed: 15- Jan-2017]. [11] D. Steen, L. A. Tuan, O. Carlson, and L. Bertling, Assessment of Electric Vehicle Charging Scenarios Based on Demographical Data, IEEE Trans. Smart Grid, vol. 3, no. 3, pp. 1457 1468, Sep. 2012. [12] D. Steen, T. Le, and O. Carlson, Fast Charging of Electric Buses in Distribution Systems, presented at the Power-Tech, Manchester, 2017. CIRED 2017 5/5