Initial Field Trials of Distributed Series Reactors and Implications for Future Applications

Similar documents
Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

2015 Grid of the Future Symposium

Electric Power Research Institute, USA 2 ABB, USA

Control of Power Flow in Transmission Lines using Distributed Series Reactors

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Smart Grid 2.0: Moving Beyond Smart Meters

Dynamic Control of Grid Assets

ABB POWER SYSTEMS CONSULTING

EPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Assessing Feeder Hosting Capacity for Distributed Generation Integration

Deploying Smart Wires at the Georgia Power Company (GPC)

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

NRECA Cooperative Research Network. Modern Grid Initiative Southeast Summit August 10, 2006 Nashville, TN

Dynamic Control of Grid Assets

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

100 MW Wind Generation Project

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Transmission s Future Today. High Capacity High Efficiency Low Profile

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Dynamic Line Rating as a Means to Enhance Transmission Grid Resilience

Cost Benefit Analysis of Faster Transmission System Protection Systems

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

GRID INNOVATION CAUCUS CO-CHAIRS

Targeted Application of STATCOM Technology in the Distribution Zone

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

400/230 Volt 60Hz UPS Power

Energy Storage for the Grid

B-4: Reducing Peak Demand through Distributed Grid Edge Control

15 Nelson-Marlborough Regional Plan

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Management of Congestion in the Deregulated Energy Market

C PER. Center for Advanced Power Engineering Research C PER

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Georgia Transmission Corporation Georgia Systems Operations Corporation

15 Nelson-Marlborough Regional Plan

Residential Smart-Grid Distributed Resources

Distributed Energy Resources

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

When Grids Get Smart - ABB s Vision for the Power System of the Future

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Integrated System Models Graph Trace Analysis Distributed Engineering Workstation

Breakout Session 1 Report-out presentations

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

AEP Ohio Distribution Reliability and Technology Programs

Fault management for grid automation Advanced fault location solution

SCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Optimising battery energy storage systems operation

Interconnection System Impact Study Report Request # GI

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Nanophosphate for Grid Storage Applications

STATCOM Application to Address Grid Stability and Reliability: Part II. D.J. SHOUP, N.W. TENZA Mitsubishi Electric Power Products, Inc.

VFT Response to a Breaker Trip and Runback Event

ELG4125: Flexible AC Transmission Systems (FACTS)

The Grid Link Project. Summary of the Report for the Independent Expert Panel

Portland General Electric

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Grid Impact of Electric Vehicles with Secondary Control Reserve Capability

Power System Stability Analysis on System Connected to Wind Power Generation with Solid State Fault Current Limiter

Improving Transmission Asset Utilization Through Advanced Mathematics and Computing

Model-Based Integrated High Penetration Renewables Planning and Control Analysis

Looking Towards the Future: Advantages of 765-kV Transmission Technology

3.0 Radial Distribution Systems

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Decision on Merced Irrigation District Transition Agreement

New Power Flow Controller for Congestion Management and Reliability Improvement in Transmission and Distribution Systems

Source-Side Fuse/Load-Side Recloser Coordination

Powering the most advanced energy storage systems

A low loss mechanical HVDC breaker for HVDC Grid applications THOMAS ERIKSSON, MAGNUS BACKMAN, STEFAN HALÉN ABB AB, CORPORATE RESEARCH SWEDEN

INTRODUCTION TO SMART GRID

Solutions for Smart Transmission Panel Session

CONTROLS UPGRADE CASE STUDY FOR A COAL-FIRED BOILER

In 2007, with oil at $70 per barrel, the U.S. trade deficit in petroleum products was 36% of the total of $819 billion deficit.

Final Written Examination.

OBJECTIVES LCC HVDC SYSTEMS VSC HVDC SYSTEMS COMMON EQUIPMENT DIFFERENT OPTIONS ECONOMIC IMPACTS CONCLUSIONS

Merger of the generator interconnection processes of Valley Electric and the ISO;

RESERVOIR SOLUTIONS. GE Power. Flexible, modular Energy Storage Solutions unlocking value across the electricity network

Control System for a Diesel Generator and UPS

Introducing Nexans Superconducting Fault Current Limiters (SCFCLs)

Transforming the US Electric Grid

Building a Stronger and Smarter Electrical Energy Infrastructure. Smart Grid. A Necessary Component in the Remaking of America

The Status of Energy Storage Renewable Energy Depends on It. Pedro C. Elizondo Flex Energy Orlando, FL July 21, 2016

Impact of Distributed Generation and Storage on Zero Net Energy (ZNE)

Use of Microgrids and DERs for black start and islanding operation

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

2015 WDC Disturbance and Protection Standards Overview

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

Electric Power System Under-Voltage Load Shedding Protection Can Become a Trap

Climate change drivers for a single and smart EU grid

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC)

What is Smart Grid? R.W. Beck Inc.

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Transcription:

21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium Initial Field Trials of Distributed Series Reactors and Implications for Future Applications I. GRANT Tennessee Valley Authority J. SHULTZ Tennessee Valley Authority S. OMRAN Virginia Tech J. COUILLARD Smart Wire Grid Inc. F. KREIKEBAUM Smart Wire Grid Inc. R. BROADWATER Electrical Distribution Design (EDD) SUMMARY Distributed Series Reactors (DSRs) are a low-cost alternative for flow control on an individual phase basis. The devices are clipped onto line conductors, typically at each end of multiple spans, and can be installed or relocated in a very short time. Pilot tests on utility lines have demonstrated that DSRs perform as designed. Depending on the sophistication of the communication and control system, a wide range of operating characteristics may be possible. Studies are identifying advanced applications in future grid operation. KEYWORDS Distributed Series Reactors, FACTS, D-FACTS, Power Flow Control, Line Rating, Line Impedance, Series Reactance isgrant@tva.gov

INTRODUCTION The US grid is frequently described as aging, and many transmission lines have been in operation beyond their 30-50 year design lifetimes, but in reality inspection and maintenance programs ensure that structures, foundations, insulators, conductors, and sag issues are readily detected and repaired or even uprated. However, contingencies which may be caused by widespread severe weather, a desire to expand supply capacity and meet short lead times to encourage new industries, reduced use or retirement of older coal plants, or a need for outages to allow uprating, may challenge the ability of a grid to meet criteria for delivering power during certain windows of time. Alternatives used to respond to these challenges tend to be situation-specific, uneconomic, and a burden for system operators. Flexible alternating current transmission systems (FACTS) are potentially attractive for power flow control, but are rarely used for this purpose due to their cost, centralized nature, and station space requirements, while they represent a cost and location commitment that is better suited to a long term need where often the requirement is for a limited time. Distributed Series Reactors (DSRs) are an alternative approach for flow control that has been developed by a vendor working initially with the Tennessee Valley Authority (TVA) and the California Energy Commission and then advanced further with the additional participation of Southern Company, National Rural Electric Cooperative Association (NRECA), Baltimore Gas and Electric, Department of Energy (DOE), the National Electric Energy Testing Research and Applications Center (NEETRAC) and the DOE Advanced Research Program Agency - Electric (ARPA-E) [1]. DSRs are devices that are clamped to phase conductors and powered by the line current. A magnetic link allows the device to inject inductive reactance to increase line impedance. In a meshed transmission grid, increased impedance in one path results in transfer of power flow to other paths. TECHNOLOGY DEVELOPMENT In 2009, the National Electric Energy Testing Research and Applications Center (NEETRAC) established an initiative to develop and test a prototype DSR, develop a specification for the nextgeneration DSR, develop and test the next-generation DSR, and review the test results. The initiative founding members were TVA, Southern Company, Baltimore Gas and Electric, and NRECA. The DSR, shown in Figure 1, consists of a split transformer hung from the conductor. The conductor forms the primary winding of the transformer. When the secondary winding is shorted, the unit operates in monitoring mode and negligible inductance is coupled in series with the line. When the secondary winding is opened, the magnetizing inductance of the transformer is coupled in series with the line, and the unit operates in injection mode. Figure 1: DSR on a Line Conductor 2

Over the operating range the coupled inductance is more than 50 microhenries (µh), as shown in Table 1. While an individual device has a very small effect on the impedance of a line phase, adding numbers of them can change reactive impedance by several percent. For a 161 kv line, one device per phase per mile provides approximately 2% impedance change. Thus 10 devices per phase per mile change the impedance by 20%. Since the devices are relatively inexpensive and can easily be hung at each end of each conductor span it is practical to consider adding quite large numbers of them, typically one at each end of each span. Model Rated Current (A) Injection Mode Inductance at Rated Current (µh) Table 1: DSR Characteristics Reactance added per DSR* (p.u.) 115 kv 138 kv 161 kv 230 kv 750 750 47 1.34e-4 9.30e-5 6.84e-5 3.35e-5 1000 1000 42 1.20e-4 8.31e-5 6.11e-5 2.99e-5 1500 1500 37 1.05e-4 7.32e-5 5.38e-5 2.64e-5 DSRs can be controlled in several ways. They can be pre-programmed to operate at a given current threshold, managed manually from an operating center in response to system conditions, or controlled automatically for more complex applications. Communications may be simply through one-way power line carrier, or two-way through cell phone circuits. Manual or automatic control is achieved as shown in Figure 2 through real-time communications. A Super DSR manages a set of proximate DSRs and communicates with a DSR System Manager, which interfaces the entire fleet of DSRs with the energy management system (EMS). Figure 2: DSR Communications The central System Manager allows configuring, monitoring and operating the DSRs as well as data archival. A DSR can provide line current, conductor temperature, fault location 3

indication, fault current,, conductor vibration, conductor sag angle, and conductor blowout angle. When the DSR controller detects a fault, it returns the units to monitoring mode in less than 4 milliseconds to ensure that the DSRs do not interfere with existing protection schemes. To date, none of the DSR pilot deployments have required any changes to protection settings. APPLICATIONS Applications include reliability improvement, delaying new line construction, reduction of congestion/redispatch, simplification or removal of operating procedures, maintenance and construction outage support, phase balancing, and improved situational awareness. DSRs can be deployed to simplify or eliminate a remedial action scheme (RAS) or special protection scheme (SPS). In a study for a utility, a specific N-2 asset outage resulted in tripping generation and load with a RAS. Deploying DSRs on a number of transmission lines simplified the RAS and eliminated 1200 megawatts (MW) of generation and load shedding. In another study, DSRs in tandem with conventional system upgrade methods were able to eliminate 1800 MW of generation and load shedding. In a further study DSRs added to six congested lines significantly reduced average electricity cost within an Interconnection. DSRs can dynamically adapt to mitigate congestion over a range of operating conditions. DEPLOYMENTS TO DATE The first pilot test included 100 units installed over 17 spans of a 21 mile 161 kv line owned by the Tennessee Valley Authority. Installations averaged approximately 10 minutes per unit including wire brushing the conductor, installation of protector rods and installation of an associated vibration damper. Figure 3 shows an installation in progress. Figure 3: DSR Installation on TVA 161 kv Line 4

TEST RESULTS The pilot test at TVA demonstrated DSR operations for the first time on an energized line. Due to grid limitations the DSRs could not be exercised through their full range, but all operating functions were successfully demonstrated. System operators checked performance of the units at four stepped set points. TVA also explored phase balancing with the DSRs. One of the phases of the test line tends to run 20-30 A higher than the other two phases, so all DSRs on this particular phase were placed in injection mode, while the other two phases were set to monitor mode. The DSRs caused a 20 A drop on the higher phase and increased current on the other two phases, almost equally balancing the three phases of the line. While it may seem that DSRs are best suited to shorter lines since a small number of devices can achieve a desired percentage impedance change, in fact they are equally suited to lines of any length since the ratio of cost to add DSRs versus original line cost is approximately constant for a given percentage impedance change. The value of a given installation is determined from system studies and will be dependent on the individual relationship of the target line and existing power flows in the grid. Some examples are provided below. ADVANCED DESIGN: CASE FOR UNBALANCED, THREE-PHASE MODELS DSR design involves determining the number and location of DSRs needed to prevent an overload. As part of the ARPA-E project, EDD developed a DSR Design Tool. The tool uses Discrete Ascent Optimal Programming [2], and at each step of the optimization algorithm places DSRs on lines that have the most effect on power flow per DSR. Studies have shown that fewer DSRs placed on a line with no overload can be more effective than DSRs placed on the overloaded lines. DSR design results are very dependent upon the model used to perform the study. That is, a three-phase model of a system with non-transposed lines and unbalanced impedances can give very different results than the single-phase, positive sequence equivalent of a non-transposed line. The IEEE 39-bus standard model was modified to a three-phase model, and then all transmission lines in the standard model were replaced with 345 kv line models that use the unbalanced construction illustrated in Figure 4 [3]. The length of the 345 kv lines used in the Unbalanced, 3-phase model were made proportional to the positive sequence impedances of the lines in the IEEE 39-bus standard model, where a 20 mile line corresponded to the smallest positive sequence impedance in the standard model, and a 100 mile line was used for the largest positive sequence impedance. 5

Figure 4: 345kV line construction used in the Unbalanced, 39-bus, 3-Phase Model A second model used in DSR design studies was then derived from the Unbalanced, 39-bus, 3-phase model by applying symmetrical component transformations to the admittance matrices of the lines. The ratings of corresponding lines in the Unbalanced and Balanced 3- phase models were made the same. Studies to evaluate DSRs for handling load growth were then performed for both models. In the design studies the load from the IEEE 39-bus standard transmission model provided the initial starting load, or 100% loading, and the load was then increased uniformly. Design results for the two 3-phase models are compared in Figure 5. Figure 5 (a) compares the total number of DSRs deployed versus percent loading level. It should be noted that the Balanced model has line overloads starting at 141% loading, and thus DSRs being added to eliminate overloads starting at 141% loading, whereas the Unbalanced model does not see overloads until the 145% loading level is reached. From Figure 5(a), the Balanced, 3-phase model has more DSRs added to correct overload problems. These extra DSRs in the Balanced model design are explained by the comparison in Figure 5 (b), which shows the rate of change of MWs per DSR at each loading level. Starting at the 145% loading level the rate of change of MWs per DSR is larger for the Unbalanced model than the Balanced model. Balanced Unbalanced Balanced Unbalanced Total No. of DSRs Deployed 6000 5000 4000 3000 2000 1000 0 5550 3750 3525 1950 1650 900 675 75 0 0 141% 143% 145% 147% 149% System Loading % Slope (MW/DSR) 40 35 30 25 20 15 10 5 0 141% 143% 145% 147% 149% System Loading (%) (a) (b) Figure 5: Comparison of design results for Balanced and Unbalanced 3-phase models 6

APPLICATIONS TO THE GRID OF THE FUTURE When alternative paths exist in the power system, DSRs can often be controlled to access existing transmission line capacity that cannot be used today due to overloads on other lines, analogous to what automatic control often does in other areas. Automatic control allows us to take an existing plant and increase production at a lower cost than building a bigger plant. Table 2 presents results of a study of the Unbalanced, 39-bus, 3-phase model described above. The study required satisfying a 40% load growth while handling all first contingencies. For certain contingencies DSRs were not effective. In such cases new 345 kv lines were added to the model so that the contingency could be handled. Altogether three new 345kV lines were added in parallel to existing lines, resulting in 95 miles of new transmission lines. Along with the three new lines, 1575 DSRs were also added to the system using the EDD Design Tool to achieve the 40% load growth. The 3 new lines added to the system only allowed for a 25% load growth without contingency problems, and so the DSRs were needed to achieve the 40% load growth where all first contingencies were handled. Table 2: Results for Unbalanced, 3-Phase Model Design to Achieve 40% Load Growth While Handling all First Contingencies Case Max MW Max % Load Increase Loading MWs from Base Base 100% 6309 With 3 Lines Reinforced with Parallel Lines 125% 7886 1577 With 3 Lines Reinforced and 1575 DSRs 140% 8833 2524 Assuming a construction cost for 345kV lines of 1.3M$/mile [4,5,6], the cost per MW increase for the three new lines can be calculated as 78k$/MW, where the three new lines provided for 1577 MW of load growth as shown in Table 2. Using this cost per MW increase as a reference, the worth of each DSR per MW increase is 47k$/MW, i.e. if a DSR costs 47k$, then the per unit MW increase obtained by adding the 3 new lines is the same as that of adding the 1575 DSRs. In applications thus far, DSRs cost significantly less than 47k$. Since lines in the transmission system are often not transposed, DSRs can be used in place of transposition to help balance receiving end voltages. If the sending end voltage of a line is unbalanced then line transposition does not help, but DSRs can still help balance the receiving end voltage. Unbalanced transmission leads to unbalanced voltages delivered to distribution systems. Such unbalanced voltages affect distribution system operations, and can prevent conservation voltage reduction programs from realizing their full potential. Model-based control facilitates maximization of DSR benefits. Under a distributed version of model-base control, each transmission line with DSRs will have a local controller. The local controller will use a model of the three-phase line to make decisions about imbalanced operation of DSRs between phases to balance the line operation. Also a model-based, hierarchical system control can calculate where and how many DSRs to operate to control system flows. During normal system conditions DSRs will be operated to achieve the best economic operation. Lower generation cost that today cannot be accessed by some load areas due to transmission system limits, will be more fully utilized. With contingencies, real-time 7

DSR control can affect flows so overloads are eliminated, even in lines that do not have DSRs. Fully integrating DSRs with EMS allows for coordinated optimization of the power system. For example, the capabilities of the DSRs post-contingency can be used to realize a generation dispatch that would be infeasible if DSRs were responding to local control. The optimality of the dispatch can be further extended by combining DSRs with dynamic line rating. The improved dispatch can be used to achieve lower production costs, higher reliability, or a combination of multiple objectives. An advanced concept yet to be fully modeled is a grid with all lines equipped with DSRs, dynamically optimized in real time through a State Estimator or similar controller. CONCLUSIONS DSRs have been successfully demonstrated as a low-cost method of controlling power flow in a meshed transmission grid. Pilot tests have confirmed ease of application and relocation, hardware reliability, and controllability. Studies of potential applications continue and show that wider scale installations can achieve more sophisticated goals. BIBLIOGRAPHY [1] Deepak Divan et al, "A Distributed Static Series Compensator System for Realizing Active Power Flow Control on Existing Power Lines", IEEE Transactions on Power Delivery, 2007 [2] R. Broadwater, et al, "Minimum Loss Optimization in Distribution Systems: Discrete Ascent Optimal Programming," Electric Power Systems Research Journal, vol. 36, no. 2, pp. 113-121, 1996. [3] EPRI, Transmission Line Reference Book - 345kV and above, Electric Power Research Institute, Third Edition, 1982. [4] "Transmission and Substation Capital Costs," Western Electricity Coordinating Council, Aug.2012. [5] A. Silverstein, "TRANSMISSION101 - Transmission Capital Cost by Voltage," in NCEP Transmission Technologies Workshop, April, 2011. [6] "Generation & Transmission Model, Version2," Western Renewable Energy Zones, June 2009. 8