East Link Extension. September 16, Bel-Red Conclusion to Final Design Open House Public Involvement Summary

Similar documents
East Link Extension. March 25, Downtown Bellevue Segment 60% Design Open House Public Involvement Summary

East Link light rail: Bel-Red/Overlake Open House Summary

East Link Extension. February 25, East Main Station Segment 60% Design Open House Public Involvement Summary

East Link Extension. July 8, Mercer Island Final Design Open House Public Involvement Summary

Public Involvement Summary

Federal Way Link Extension

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

FasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Exposition Light Rail Transit Project

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Rail alignment and benefits (rab) study

Green Line LRT: Beltline Segment Update April 19, 2017

TRAIN, BUS & TRANSIT

Project Status Update January 2017

Troost Corridor Transit Study

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Tempe Streetcar. March 2, 2016

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project

Harlem Avenue between 63 rd and 65 th

Organization. SDOT Date and Commute Seattle. Dave Sowers, Deputy Program Administrator

Waco Rapid Transit Corridor (RTC) Feasibility Study

WAKE TRANSIT PLAN Summer 2018

2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS. Eastside Transportation Partnership September 9, 2016

Attachment D Environmental Justice and Outreach

What We Heard Report - Metro Line NW LRT

Appendix C: Comments

Welcome. Green Line in Your Community

Strategies to keep people and goods moving in and through Seattle

Fresno County. Sustainable Communities Strategy (SCS) Public Workshop

3.1 Introduction Transportation Elements and Study Area Meeting the Need for the Project

FREQUENTLY ASKED QUESTIONS

Background Information about the Metrobus 29 Lines Study

Stadium Expansion Parking Plan and Transportation Management Program

SUMMARY OF COMMENTS AT PUBLIC OPEN HOUSES SCOPING OF ALTERNATIVES GATEWAY CORRIDOR ALTERNATIVES ANALYSIS

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

SUPPORTING TOD IN METRO CHICAGO

1 Downtown LRT Connector: Draft Concept

Welcome! Think carpool, then think bigger! Questions? Contact our Vanpool team!

Dallas Area Rapid Transit (DART) Cotton Belt Regional Rail Project

EAST LINK PROJECT. Environmental Scoping Information Report. Seattle to Bellevue to Redmond. September 2006

The Capital Grid Project:

appendix 4: Parking Management Study, Phase II

THE MARKET TALKS. October a monthly report on single family residential real estate activity windermeremercerisland.

Northeast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study

6/11/2018. June 7, Item #1 CITIZENS PARTICIPATION

Executive Summary October 2013

Best Route. Best Care. The Milwaukee Regional Medical Center s Alternative Transportation Program

Presentation Overview. Stop, Station, and Terminal Capacity

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

Kendall Drive Premium Transit PD&E Study

Mobility Corridor Updates. Transit & Active Transportation Projects

West Broadway Reconstruction/LRT Design. March 19, 2015

2018 Long Range Development Plan Update Community Advisory Group- February 21, 2018

Westside Issues Major generators: employment centers, retail, residential, recreational, UCLA, LAX Rising jobs-housing imbalance Transportation improv

Electric Multiple Unit Procurement Update

Rail alignment and benefits (rab) study

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Newmarket GO Station Mobility Hub Study. Open House #1 MAY 18, 2017

Transportation Sustainability Program

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min.

6.1 Performance in Meeting Project Goals and Objectives

QUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study

5. OPPORTUNITIES AND NEXT STEPS

Point A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017

Proposed Revised Network Presented 10/17/2017. Kitsap Transit Board Workshop October 17, 2017

Dallas CBD Second Light Rail Alignment (D2)

Draft Results and Open House

Electric Multiple Unit Procurement Update

The TDM Plan for Fort Washington Office Park NOVEMBER 1 6, 2017 FORT WASHINGTON OFFICE PARK STAKEHOLDERS

2 EXISTING ROUTE STRUCTURE AND SERVICE LEVELS

Mobility Corridor Updates. Transit & Active Transportation Projects

CTA Blue Line Study Area

East Bay Bus Rapid Transit Project. Downtown Oakland to San Leandro International Blvd to East 14 th St

MARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018

Denver Car Share Program 2017 Program Summary

BROCHURE AND APPLICATION FORM

Help shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary

10/4/2016. October 6, Item #1 CITIZENS PARTICIPATION

Click to edit Master title style

Community Advisory Committee. October 5, 2015

Downtown Parking/Wayfinding Study. Review of Recommendations to City Council: January 16, 2018

TRANSPORTATION REVIEW

Pomona Rotary December 19, 2017

Michigan Avenue Corridor Study. Joint Policy / Technical Committee Meeting Wednesday, June 8, 2016

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017

Restoration of Historic Streetcar Services in Downtown Los Angeles

METRO Orange Line BRT American Boulevard Station Options

We Want Your Input! Review the design alternatives and tell us what s important to you in the design of these areas of the approved BRT Network:

Streamlining the District s Nightlife Curbside Access. Managing High-Demand Curbside Passenger Loading Zones

Draft Results and Recommendations

WELCOME. What are we doing here tonight? What can you expect? How can you participate?

Business Advisory Committee. November 3, 2015

NEW YORK CITY CARSHARE PILOT

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

A Transit Plan for the Future. Draft Network Plan

Transcription:

East Link Extension September 16, 2014 Bel-Red Conclusion to Final Design Open House Public Involvement Summary

Table of contents 1 Background 2 Overview 2 Notification 3 Open House Overview 4 Comment Summary 5 Permanent Station Naming Comment Summary 6 Next Steps 6 Stay Involved Sound Transit East Link

Background East Link Extension is a key element of the regional mass transit system approved by voters in 2008. This 14-mile light rail line will benefit local communities and support regional growth with fast, frequent and reliable light rail service, connecting the Eastside s biggest population and employment centers to Seattle. The project builds on the Link light rail system running between Sea-Tac Airport and downtown Seattle and the University Link and S. 200th Link Extensions that are scheduled to open in 2016. East Link is part of the new light rail extensions being built north, south and east from Seattle. When East Link opens around 2023, 10 stations, serving Seattle, Mercer Island, Bellevue, South Bellevue and Overlake in Redmond will become a part of a regional light rail system stretching more than 50 miles. By 2030, about 50,000 riders will use East Link every day. Final design has been a collaborative effort between Sound Transit and project stakeholders including: The community, including impacted property owners City of Bellevue City of Bellevue Light Rail Permitting Citizens Advisory Committee Other jurisdictional authorities, such as, Washington State Department of Transportation, emergency service providers, King County, and transit providers. During final design, project architects and engineers define the light rail system, determining the technical specifications for the stations and track. To keep stakeholders informed and empowered to provide input throughout this project phase, Sound Transit hosted three public meetings, multiple briefings with nearby businesses and property owners, and additional in-person and electronic outreach. The East Link Extension project team actively sought public feedback at key design milestones. Public input was shared with the project team and considered with attention to feasibility, design guidelines and jurisdictional requirements. The Bel-Red Segment final design is the result of ongoing community conversations and stakeholder input since the segment final design kickoff in March 2013. Visit the East Link document archive for a summary of outreach at each final design milestone: soundtransit.org/ projects-and-plans/east-link-extension/east-link-extensiondocument-archive. Bel-Red conclusion to final design open house summary 1

Overview Notification On Sept. 16, 2014, Sound Transit hosted an open house to share the East Link Extension completed final design plans for the Bel-Red Segment, including the 130th station. The meeting provided an opportunity for community members to view design plans, meet and talk with the project team in-person, provide input on the station name for the 130th station, and learn about how to stay involved as the project moves towards early construction in 2015. The open house was held at the Highland Park Community Center in Bel-Red, Bellevue from 5 to 7 p.m. The open house was widely publicized through the following channels: Display advertisements in the Bellevue Reporter, Korea Daily, La Raza, Phuong Dong Times, Russian World, Seattle Chinese News, Seattle Chinese Post, Seattle Transit Blog and The Facts Postcards mailed to over 17,000 residents and businesses Press release to local papers and blogs Email notification to approximately 6,000 subscribers of the East Link Extension listserv Announcements on the Sound Transit project web page Announcement on the Sound Transit Facebook page Announcement through Sound Transit s Twitter feed Flyers distributed to businesses situated near the future 130th station and along the Bel-Red segment alignment 130th Station Located between 130th and 132nd avenues NE at NE 16th St., this at-grade station includes a park-and-ride lot with capacity for approximately 300 vehicles. JOIN US! SEPT. 16 Bel-Red Segment East Link light rail open house Your participation helped complete the 130th station design join Sound Transit at the Sept. 16 open house to see how it looks. Attend to learn more about: 130th station final design Station artist Patrick Marold Learn about: Urban design and landscaping Early construction work coming in 2015 and 2016 Please join us: Tuesday, Sept. 16, 2014 5-7 p.m. (presentation begins at 5:30 p.m.) Highland Community Center 14224 Bel-Red Road, Bellevue, 98007 Learn more and submit comments online at soundtransit.org/eastlink or contact Sound Transit at 206-398-LINK, eastlink@soundtransit.org. To request information in alternative formats or accommodations for persons with disabilities, call 1-800-201-4900/ TTY Relay: 711 or email accessibility@soundtransit.org. Station design Planning for construction SUBSCRIBE TO PROJECT AND CONSTRUCTION-RELATED UPDATES: soundtransit.org/subscribe 2 Sound Transit East Link Extension

Open house overview Approximately 65 people attended the open house to learn about final design plans for the Bel-Red segment. Attendees were greeted by project staff, asked to sign in and provided with a Community Guide to Final Design, Community Guide to Construction, segment fact sheet and comment forms. Display boards and roll plots featured information about East Link, the light rail construction process and updated design plans for the Bel-Red segment, including the 130th station. An overview presentation was held at 5:30 p.m. Project staff were available throughout the meeting to answer questions and explain design details to the public. All meeting materials and electronic versions of the comment forms were made available on the East Link project website following the open house. Bel-Red conclusion to final design open house summary 3

Comment summary Sound Transit accepted public comments in person at the open house, and by mail, email and electronically on the East Link website. The following section is a summary of comments received at the open house, during pre-open house outreach and through the online comment form between Sept. 16 and Sept. 30, 2014. Bel-Red segment design General comments on the Bel-Red segment and light rail alignment: Change the line routing to run more/less north from the 120th Ave station to the south side of SR 520, then parallel SR 520 to the Overlake Village station.eliminate the 130th Ave. station; it is too close to the 120th Ave station and is not needed. Comments on station design, features and amenities: 130th station needs lots of benches and covered areas for older riders to be protected in the winter. Interest in hiring local artists to develop station artwork. Interest in safety at and around the station: Will there be any surveillance cameras on the platform? Interest in parking amenities around the station: Eliminate the park and ride facility on 130th Avenue; relocate it to the 120th Ave station. Parking lot needs to have covered walkways and benches for older and special needs riders. *The plans suggests 130th Station is a walking station. This station is located in a minimally developed residential area and a low density business area no information as to how parking requirements are determined for the station. Interest in the start of construction and construction impacts: **[Concern about how] businesses will be affected by disruptions. Will there be construction at night? I am worried about link rail creating traffic backups. Interest in pedestrian and bicycle amenities: I question why the bike cage is on the 132nd side, when 130th is the spot with the actual connection to the SR 520 trail, as well as the road with bike lanes. There should at least be racks on both sides. I would like to see a bigger picture consideration of pedestrian and bicycle and bus access to the stations. A quarter of a mile out doesn t reflect users. * Summarized comment * * Comment received verbally 4 Sound Transit East Link Extension

Tell us about yourself! How do you plan to use East Link? Do you live or work near a station? Yes - 5 Do you intend to use light rail for daily commuting, special events, or both? Daily commuting - 2 How often do you anticipate using the station? More than two times a week - 2 Special events - 3 Both - n/a 2-3 times a week - n/a 2-5 times a week - n/a 2-3 times a year - 1 Zero - 1 How do you plan on accessing the station? Walk - n/a Drive - 2 Bus - n/a Bike - 2 Passenger drop off - n/a No plans - 1 Bel-Red conclusion to final design open house summary 5

Permanent station naming comment summary A separate comment form was provided to gather input on permanent station names for the 130th station. Sound Transit requested that station names reflect the neighborhood environment, avoid commercial references, comply with ADA guidelines, and follow Sound Transit Board policy requirements for station naming. Following the meeting, an online survey was posted to the project website. A total of 15 responses were submitted. What is your preference for the 130th station name? Comments received about permanent station names: Bel-Red Station - 9 If a 130th St. station is built in Seattle (which I strongly advocate), I suggest it be named after the 130th Station - 4 more established neighborhood there, and this be called the 130th Ave- the only neighborhood names here would be too confusing, as they d equally to Goff Creek Station - 2 124th Ave station. Bel-Red Station would be the most sensible choice, but I think naming it something else would serve two purposes: 1) lessen the confusion of using Bel-Red as shorthand for Bel-Red Road and Bel- Red Station, and 2) Give a new name to an area that is intended to be completely transformed from an existing warehouse district to a new mixed use area. need new image 130th station mid-platform looking west 6 Sound Transit East Link Extension

Next steps Early construction work in Bel-Red anticipated in 2015 and 2016 What will happen? Utility infrastructure owners will relocate outside the Sound Transit work zone. Duration: Intermittent work occurring over a 2-year window. Typical impacts: Temporary utility service disruptions Traffic circulation and access impacts Blocked off work areas Trucks hauling materials Noise, vibration, dust and debris Changes to mail, transit operations and other services Storage of work materials and equipment Keeping you informed: Sound Transit will hold community meetings and briefings during construction to keep the public informed. Sound Transit will keep you informed early and often throughout construction. Sound Transit will notify neighboring residents and businesses in advance of upcoming work. Subscribe to the East Link email listserv (listed below) to stay engaged and receive project and construction-specific updates. Stay tuned for an opportunity to learn about construction before it begins, anticipated in the second half of 2015. Stay involved Visit the project website for the latest news: soundtransit.org/eastlink Request a briefing for yourself or your organization: Contact Sound Transit Community Outreach staff at eastlink@soundtransit.org or 206-398-LINK Subscribe to the construction notification listserv: soundtransit.org/subscribe-to-alerts Bel-Red conclusion to final design open house summary 7