To: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resources Planning. From: Sarah Liuba Approved by: /s/
|
|
- Anabel Fields
- 5 years ago
- Views:
Transcription
1 AGENDA ITEM NO.: 4.G. To: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resources Planning From: Sarah Liuba Approved by: /s/ Energy Resources Analyst Nicolas Procos General Manager Subject: Authorize Staff to Sell the Banked Low Carbon Fuel Standard Credits Allocated by the California Air Resources Board to Alameda Municipal Power for 2015 and 2016; and, Delegate to AMP s General Manager, or His Delegate, Authority to Negotiate and Execute Necessary Agreements to Accomplish the Transaction RECOMMENDATION By motion, authorize staff to sell the banked Low Carbon Fuel Standard (LCFS) credits allocated by the California Air Resources Board (CARB) to Alameda Municipal Power (AMP) for 2015 and 2016; and, delegate to AMP s General Manager (GM), or his delegate, authority to negotiate and execute necessary agreements to accomplish the transaction. BACKGROUND California enacted its LCFS program in January 2007 in compliance with AB 32 (the Global Warming Solutions Act of 2006) with the primary objective of reducing carbon intensity (CI) of transportation fuels by 10 percent by In January 2011 under Executive Order S-1-07, CARB became the regulatory body with oversight over the allocation of LCFS program credits and compliance criteria. Under the LCFS program, providers of alternative, low-carbon fuel receive credits that can either be used for compliance reporting of emissions or sold to transportation agencies or related entities of fossil fuel production, generation, or distribution. In 2015, CARB approved AMP s request to join the LCFS program. Due to legal challenges and various procedural issues related to the original program in 2013, CARB re-adopted the LCFS program with improved regulations in September As of January 1, 2016, electric distribution utilities that provide non-metered, residential electric vehicle (EV) charging are eligible for LCFS credits based on the number of registered EVs within their service territory as reported by the Department of Motor Vehicles (DMV). 1 CI refers the amount of life cycle emissions per unit of energy of fuel measured in of grams of carbon dioxide equivalent per megajoule (CO 2 e). Page 1 of 5
2 AGENDA ITEM NO.: 4.G.2 As part of the new requirements, CARB included a containment measure, which imposed a price ceiling of $200 per CI credit. Since 2015, the monthly average price per credit increased from $40 to over $120/credit at the height of the market and currently resides at about $90. Each credit is measured as one metric ton (MT) of CO 2 e for electricity dispensed. Banked Credits On March 15, 2017, AMP received 1,752 LCFS credits based on CARB s calculation for the daily average non-metered EV electricity use per vehicle from 2016 along with usage reporting from AMP s EV charging stations. Adding to the previous year s pool of 736 banked credits, AMP s total generated LCFS credits are 2,488. As of March 5, 2017, CARB s Transfer Activity report listed the average market price ($/MT) at $96.32, with sales ranging from $70- $100 per credit. Based on this information, complete monetization of AMP s credits could yield from $174,00 to $248,000 (less transaction fees and brokerage service fees). The LCFS program is scheduled to continue through Staff forecasts a gradual decline in credit generation as annual compliance goals are met through In lieu of exhausting all of AMP s banked LCFS credits, staff recommends the monetization of 2,450 credits out of the 2,488 current banked credits. AMP is not aware of any program obligations at this time, but will reserve the 33 credits for any CI deficit under the LCFS program. DISCUSSION Assumptions The LCFS credit market indicates price flattening after a high point starting early 2016 and followed by a significant decrease beginning April 2016 through June Revenue projections are based on the forecasted price of $80/MT. The City of Alameda is expected to see an increase of EVs through 2020 providing the ability to generate and sell additional LCFS credits going forward. As CI reduction continues to move towards compliance targets, fewer generated credits will be available to participating entities each year. Analysis Figure 1 below presents the monthly average LCFS credit pricing from January 2013 through February The moving average price indicates that LCFS credit values may stay at about $90 for the subsequent month. (Prior to the re-adoption of the LCFS program, market prices for LCFS credits fluctuated within the $20-$80 range. The visible spike in July 2015 is believed to be correlated with the new regulations.) Staff recommends that LCFS credit sales be made between May 2017 and July Page 2 of 5
3 Figure 1 CARB monthly average of LCFS program credit pricing AGENDA ITEM NO.: 4.G.3 Figure 2 shows a granular depiction of the current credit transfers along with their market pricing from July 2016 to March The overlaid rolling average of the LCFS credit sales illustrates price flattening seen after the last significant descent in pricing noted in Figure 1. Staff is providing this analysis to highlight the volatility of the market and support the expectation that AMP s LCFS credits will sell in the $80-$90 range. Figure 2 LCFS transfer activity from July 2016 March 2017 with $/MT indication 2 Page 3 of 5
4 AGENDA ITEM NO.: 4.G.4 Staff considered these assumptions in planning for the sale/transfer of banked LCFS credits and expects its sale to be priced around the illustrated $80/LCFS credit monthly average. The revenue for 2,450 LCFS credits at this price would be $196,000 (before service fees). Electric Vehicle Count Table 1 depicts that the City of Alameda is expected to see an average of 350 additional EVs each year through Based on this projection, AMP has the potential to generate around 2,100 additional credits throughout This assumes depreciated EV valuation as overall CI of transfer fuels is reduced. The LCFS program regulations and access to credit sales/transfers are anticipated to remain in place even after Market fluctuation is likely to continue during this time. Table 1 Estimated EV count each year through 2025 Fiscal Year Estimated EV Count ,131 1,404 1,704 2,008 2,298 2,605 NEXT STEPS Staff has outlined the current protocol and next steps in executing the sale(s) subject to the authorization to sell from the Public Utilities Board. Sale 1. Staff will develop necessary counterparty forms with the legal team based on industry standard templates created by the Leadership for Energy Automated Processing group. 2. Staff will locate counterparties with emissions reporting and compliance obligations, possibly by utilizing the services of an exchange broker. 3. The GM will authorize entering into agreement(s) with the counterparty/parties. 4. Staff will move forward with the agreement(s) and coordinate the mechanics of the transfer/sale. 5. Use of funds will be determined at a later date with the consideration that under LCFS program guidelines, credit proceeds must benefit current or future EV customers, educate the public on EV benefits, or provide rate options that encourage off-peak charging and minimize grid impacts. FINANCIAL IMPACT There are currently no associated costs with receiving generated LCFS credits from CARB. Brokerage fees may be necessary in facilitating the sale. Monetization of the recommended 2,450 LCFS credits is estimated to produce $196,000 (less service fees). Page 4 of 5
5 AGENDA ITEM NO.: 4.G.5 LINKS TO BOARD POLICY AND OBJECTIVES KRA 1 Goal 1.2 Goal 1.3 KRA 5 Goal 5.1 Customer Programs & Experience Increase Customer Energy Efficiency Provide Programs that Support Green Alameda Energy Resources Develop Alternative Energy Opportunities EXHIBIT None. Page 5 of 5
To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM-Customer Resources. From: Kelly Birdwell Brezovec Approved by: /s/
AGENDA ITEM NO.: 5.A.1 MEETING DATE: 10/16/2017 ADMINISTRATIVE REPORT NO.: 2018-15 To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM-Customer Resources From: Kelly Birdwell Brezovec
More informationTo: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM Customer Resources
AGENDA ITEM NO.: 5.E.1 ADMINISTRATIVE REPORT NO.: 2018-02 To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin AGM Customer Resources From: Kelly Brezovec Approved by: /s/ Utility Energy
More informationYour Fuel Can Pay You: Maximize the Carbon Value of Your Fuel Purchases. Sean H. Turner October 18, 2017
Your Fuel Can Pay You: Maximize the Carbon Value of Your Fuel Purchases Sean H. Turner October 18, 2017 Agenda Traditional Funding Mechanisms vs. Market- Based Incentives for Renewable Fuels and Electric
More informationTo: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin Interim AGM Customer Resources. From: Kelly Birdwell Approved by: /s/
AGENDA ITEM NO.: 5.B.1 MEETING DATE: 10/20/2014 ADMINISTRATIVE REPORT NO.: 2015-18 To: Honorable Public Utilities Board Submitted by: /s/ Rebecca Irwin Interim AGM Customer Resources From: Kelly Birdwell
More informationTo: Honorable Public Utilities Board Submitted by: Senior Energy Resources Analyst Deborah Whiteman Senior Energy Resources Analyst Approved by:
AGENDA ITEM NO.: 5.G.1 MEETING DATE: 07/16/2018 ADMINISTRATIVE REPORT NO.: 2018-73 To: Honorable Public Utilities Board Submitted by: /S/ Vidhi Chawla AGM-Energy Resource Planning From: Alan Hanger Senior
More informationElectric Vehicle Charge Ready Program
Electric Vehicle Charge Ready Program September 20, 2015 1 Agenda About SCE The Charge Ready Initiative Depreciation Proposals of The Charge Ready Initiative Challenges Outcomes September 20, 2015 2 About
More informationTo: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resource Planning. From: Alan Hanger Approved by: /s/
AGENDA ITEM NO.: 4.J.1 To: Honorable Public Utilities Board Submitted by: /s/ Barry Leska AGM Energy Resource Planning From: Alan Hanger Approved by: /s/ Senior Energy Resource Analyst Glenn O. Steiger
More informationDecision on Merced Irrigation District Transition Agreement
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More informationPENINSULA CLEAN ENERGY JPA Board Correspondence
PENINSULA CLEAN ENERGY JPA Board Correspondence DATE: June 22, 2016 BOARD MEETING DATE: June 23, 2016 SPECIAL NOTICE/HEARING: None VOTE REQUIRED: Majority Present TO: FROM: SUBJECT: Honorable Peninsula
More information2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION
2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION L o s A n g e l e s S e p t e m b e r 1 0 th & 11 th 1 General Considerations of Staff Proposal Achieve zero emission
More informationKetchum Energy Advisory Committee Annual Update and Recommendation for Electric Vehicle Charging Station
March 21, 2016 Mayor Jonas and City Councilors City of Ketchum Ketchum, Idaho Mayor Jonas and City Councilors: Ketchum Energy Advisory Committee Annual Update and Recommendation for Electric Vehicle Charging
More informationRNG Production for Vehicle Fuel. April 4, 2018
RNG Production for Vehicle Fuel April 4, 2018 Forward-Looking Statements This presentation contains forward-looking statements within the meaning of Section 27A of the Securities Act of 1933 and Section
More informationMSRC CLEAN TRANSPORTATION FUNDING LOCAL GOVERNMENT PARTNERSHIP
MSRC CLEAN TRANSPORTATION FUNDING LOCAL GOVERNMENT PARTNERSHIP PROGRAM DUE: AUGUST 2, 2018 CITY OF "Agency Name" LOCAL GOVERNMENT PARTNERSHIP PROGRAM PROPOSAL SUBMITTED: "Month XX, 2018" TABLE OF CONTENTS
More informationOverview of California AB32 Regulations
Overview of California AB32 Regulations Business Council for Sustainable Energy Seminar Washington, DC Scott Tomashefsky Northern California Power Agency January 6, 2011 NCPA Overview California Joint
More informationThe Gambia National Forum on
The Gambia National Forum on Renewable Energy Regulation Kairaba Hotel, The Gambia January 31 February 1, 2012 Tariff and Price Regulation of Renewables Deborah Erwin Public Service Commission of Wisconsin
More informationLow Carbon Fuel Standard
Low Carbon Fuel Standard April 26, 2017 Jing Yuan, Ph.D. Fuels Section Transportation Fuels Branch Industrial Strategies Division 1 Outline Program background Demonstration How do I register in the system?
More informationSolano County Transit
AGENDA ITEM: 9 BOARD MEETING DATE: FEBRUARY 18, 2016 Solano County Transit TO: PRESENTER: SUBJECT: ACTION: BOARD OF DIRECTORS ALAN PRICE, PROGRAM ANALYST II REVIEW AND APPROVE IMPLEMENTATION OF THE FUELING
More informationCalifornia Greenhouse Gas Vehicle and Fuel Programs
NCSL Advisory Council on Energy California Greenhouse Gas Vehicle and Fuel Programs Charles M. Shulock California Air Resources Board November 28, 2007 Overview AB 32 basics GHG tailpipe standards Low
More informationCalifornia Environmental Protection Agency. Air Resources Board. Low Carbon Fuel Standard (LCFS) Update 2015 CRC LCA of Transportation Fuels Workshop
California Environmental Protection Agency Air Resources Board Low Carbon Fuel Standard (LCFS) Update 2015 CRC LCA of Transportation Fuels Workshop Anil Prabhu October 27-28, 2015 Overview of Presentation
More informationCreating A Cleaner Energy Future For the Commonwealth. Growing Solar in MA. MMA Annual Meeting. Boston, 1/24/14
MMA Annual Meeting Boston, 1/24/14 Growing Solar in MA Renewable Energy Generation in MA 3,500 GWH 3,000 2,500 2,000 1,500 1,000 Hydro Wind Solar Landfill Gas Biomass Anaerobic Digester 500 0 2003 2004
More informationFrom: Tito R. Nagrampa Jr, P.E. Approved by: /s/ General Manager Juan M. Ulloa, P.E. Engineering Supervisor
AGENDA ITEM NO: 4.I.1 MEETING DATE: 12/10/2012 ADMINISTRATIVE REPORT NO.: 2013-28 To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM Engineering and Operations From: Tito R. Nagrampa
More informationYukon s Independent Power Production Policy
Yukon s Independent Power Production Policy Updated October 2018 BACKGROUND The Government of Yukon (YG) released the Energy Strategy for Yukon in January 2009. The strategy sets out YG s energy priorities,
More informationRecharge Kick-off Meeting Recharge Activity Review Process for
Recharge Kick-off Meeting Debra Fry Executive Director, Operating Budget and Recharge Review Gabriella Hato Manager, Recharge Review Sarah Hislen Analyst, Recharge Review Charet Wynn Analyst, Recharge
More informationENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION
ENERGY STRATEGY FOR YUKON Net Metering Policy DRAFT FOR CONSULTATION February 2011 Page 1 of 4 BACKGROUND The Yukon government released the Energy Strategy for Yukon in January 2009. The Energy Strategy
More informationTo: Honorable Public Utilities Board Submitted by: /s/ Janet Oppio AGM - Energy Resource Planning
AGENDA ITEM NO: 5.E.1 ADMINISTRATIVE REPORT NO. 2013-02 To: Honorable Public Utilities Board Submitted by: /s/ Janet Oppio AGM - Energy Resource Planning From: Alan Hanger Senior Energy Resources Analyst
More informationUrban Construction Initiative Certification Program Update
Urban Construction Initiative Certification Program Update Presentation at the UCI Annual Meeting July 28 th, 2011 Todd Halacy, PE VDOT LAD Phil Pullen, PE City of Virginia Beach The Urban Construction
More informationTERMS AND CONDITIONS
XXV. NET METERING A. Applicability and Availability 1. The terms Net Metering Service, Demand Charge-based Time-of- Use Tariff, Net Metering Customer, Customer, Time-of-Use Customer, Time-of-Use Tier,
More informationENERGY STRATEGY FOR YUKON. Independent Power Production Policy
ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out
More informationMA SREC Update August 21, SRECTrade, Inc.
MA SREC Update August 21, 2014 2014 SRECTrade, Inc. Speakers Steven Eisenberg CEO Alex Sheets Director Environmental Markets Sam Rust Director Business Development Agenda Company Overview Steven Eisenberg
More information24. SOLAR INCENTIVE PROGRAM II
24. SOLAR INCENTIVE PROGRAM II A. General California Senate Bill 1 requires publicly owned utilities that sell electricity at the retail level, to adopt, implement, and fund a solar incentive program for
More informationTaxis and Accessible Services Division Medallion Reform Background May 1, 2018
Introduction: Taxis and Accessible Services Division Medallion Reform Background May 1, 2018 SFMTA s Taxis and Accessible Services Division is responsible for the regulation of the private businesses that
More information216B.164 COGENERATION AND SMALL POWER PRODUCTION.
116C.7792 SOLAR ENERGY INCENTIVE PROGRAM. (a)the utility subject to section 116C.779 shall operate a program to provide solar energy production incentives for solar energy systems of no more than a total
More informationCreating A Greener Energy Future For the Commonwealth. Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics.
Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics December 18, 2012 Outline Learn how the solar PV market has grown in MA since 2007 Understand the policy design of the MA Solar Carve-Out
More information(2) Scope. 220 CMR applies to all Distribution Companies subject to the jurisdiction of the Department.
D.P.U. 11-10-A 220 CMR 18.00: NET METERING Section 18.01: Purpose and Scope 18.02: Definitions 18.03: Net Metering Services 18.04: Calculation of Net Metering Credits 18.05: Allocation of Net Metering
More informationProposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013
Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in 2015 Stakeholder Webconference February 28, 2013 Page 2 Merced Irrigation District (Merced) Background Merced Irrigation
More informationD.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES
220 CMR 18.00: NET METERING Section 18.01: Purpose and Scope 18.02: Definitions 18.03: Net Metering Services 18.04: Calculation of Net Metering Credits 18.05: Allocation of Net Metering Credits 18.06:
More informationAddressing Indirect Land Use Change in the NEMA LCFS
Addressing Indirect Land Use Change in the NEMA LCFS Options for Discussion with Stakeholders September 29, 2010 DRAFT Sept. 29, 2010-2 This presentation presents options for consideration and discussion
More informationCity-wide LED Street Light Conversion Program
City-wide LED Street Light Conversion Program Arts & Innovation Board of Public Utilities July 25, 2016 Project Description Utility 2.0 Multi-phase implementation of city-wide street light conversion program
More informationCRYPTOCURRENCY MORATORIUM SMALL MINER RATE IMPACT. September 4, 2018
CRYPTOCURRENCY MORATORIUM SMALL MINER RATE IMPACT September 4, 2018 TODAY S DISCUSSION Understanding impact Rate considerations for residential connections Next steps Seeking direction and feedback, NO
More informationRIVERSIDE PUBLIC UTILITIES Board Memorandum
RIVERSIDE PUBLIC UTILITIES Board Memorandum BOARD OF PUBLIC UTILITIES DATE: JULY 25, 2016 ITEM NO: 12 SUBJECT: CITY-WIDE STREETLIGHT LIGHT EMITTING DIODE CONVERSION PROGRAM (PHASE ONE - DESIGN) APPROVAL
More informationRECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which:
DATE: July 16,2007 TO: FROM: SUBJECT: CITY COUNCIL CITY MANAGER CONSIDERATION OF ADOPTION OF NEW FEDERAL STANDARDS RELATING TO ELECTRIC UTILITIES UNDER THE PUBLIC UTILITIES REGULATORY POLICIES ACT AND
More informationS T A F F R E P O R T
S T A F F R E P O R T DATE: December 11, 2012 TO: FROM: Honorable Mayor and City Council Superintendent, Brandon Graham SUBJECT: Net Metering Policy Section A 2. b. (Change the maximum installation capacity
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION
More informationTRANSFORMING TRANSPORTATION
TRANSFORMING TRANSPORTATION WITH ELECTRICITY: STATE ACTION MARCH 3, 2014 KRISTY HARTMAN ENERGY POLICY SPECIALIST NCSL NCSL OVERVIEW Bipartisan organization Serves the 7,383 legislators and 30,000+ legislative
More informationBACKGROUND AND ANALYSIS
AGENDA BILL Agenda Item No. 6(B) Date: November 21, 2017 To: From: Subject: El Cerrito City Council Maria Sanders, Operations + Environmental Services Manager Yvetteh Ortiz, Public Works Director/City
More informationDATE: MAY 3, 2007 ENVIRONMENTAL MANAGEMENT DIVISION
DATE: MAY 3, 2007 FROM: ENVIRONMENTAL MANAGEMENT DIVISION SUMMARY: This Board item requests that the Board of Harbor Commissioners approve the allocation and expenditure, from funds previously disbursed
More informationElectric Vehicle Charging Station Installation and Eco-Pass Updates. Report Prepared by: A. Rolston, Parking Operations Coordinator
Report to Council Date: File: 1862-01 To: From: Subject: City Manager D. Duncan, Manager, Parking Services Electric Vehicle Charging Station Installation and Eco-Pass Updates Report Prepared by: A. Rolston,
More informationA Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012
A Guide to the medium General Service Conservation Rate BC Hydro Last Updated: February 24, 2012 Executive summary The way Medium General Service (MGS) accounts pay for electricity is changing. MGS is
More informationUC Santa Cruz TAPS 3-Year Fee & Fare Proposal, through
UC Santa Cruz TAPS 3-Year Fee & Fare Proposal, 2016-17 through 2018-19 Introduction Transportation and Parking Services (TAPS) proposes a three-year series of annual increases to most Parking fees and
More informationPlease visit the stations to provide your input: EV Charging Location Map EV Adoption ZEV Drivers Other Ideas
Welcome! Thank you for joining us. Please visit the stations to provide your input: EV Charging Location Map EV Adoption ZEV Drivers Other Ideas A brief presentation will begin at 6pm. Table activities
More informationElectric Vehicle Basics for Your Business
Welcome to Electric Vehicle Basics for Your Business Electric Vehicle Basics for Your Business What You Need to Know About EVs and Charging September 25, 2013 1 Agenda 7788 Copyright 2012, -800-990- SCE
More informationLANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT
January 1, 2016 CA Public Utilities Commission Energy Division Attention: Tariff Unit 505 Van Ness Avenue, 4thFloor San Francisco, CA 94102-3298 Advice Letter LCE 001-E RE: LANCASTER CHOICE ENERGY S BIENNIAL
More informationCity of Palo Alto (ID # 7128) Finance Committee Staff Report
City of Palo Alto (ID # 7128) Finance Committee Staff Report Report Type: Action Items Meeting Date: 9/20/2016 Council Priority: Environmental Sustainability Summary Title: Approval of Low Carbon Fuel
More informationExecutive Summary of Proposed Class Settlement Program
Executive Summary of Proposed Class Settlement Program TABLE OF CONTENTS Benefits to Owners / Lessees How to Obtain Settlement Benefits Environmental Relief Attorneys Fees Summary Settlement Payments to
More informationTerry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis
Terry Blackwell Page 1 of 5 Education 1977 North Carolina State University BS, Electrical Engineering Power Systems emphasis Professional Qualifications 1977 PE-Professional Engineer Business Experience
More informationRevised Cal. P.U.C. Sheet No E Cancelling Revised Cal. P.U.C. Sheet No E. San Francisco, California
Revised Cal. P.U.C. Sheet No. 42736-E Cancelling Revised Cal. P.U.C. Sheet No. 41884-E ELECTRIC SCHEDULE EL-1 Sheet 1 APPLICABILITY: This schedule is applicable to single-phase and polyphase residential
More informationa) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load
Memorandum To: Municipal Light Advisory Board; Municipal Light Board; file From: Belmont Light Staff Date: June 19, 2014 Re: Solar PV Distributed Generation 1. Background & Summary Belmont Light supports
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM
Date: March 26, 2013 CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM To: From: The Honorable City Council c/o City Clerk, Room 395 Attention: Honorable Mitchell Englander, Chair, Public Safety Committee
More informationZero Emission Bus Impact on Infrastructure
Zero Emission Bus Impact on Infrastructure California Transit Association (CTA) Fall Conference Nov 17, 2016 Russ Garwacki Director, Pricing Design & Research 626.302.6673 Russell.Garwacki@sce.com Barbara
More informationJoint Legislative Program Evaluation Oversight Committee March 14, 2012
Motor Fleet Management Uses Best Practices, but Needs Telematics to Strengthen Accountability A presentation to the Joint Legislative Program Evaluation Oversight Committee Carol Shaw, Principal Program
More informationPublic Meeting Point of Regulation for the Sources of Fuel Combustion Included in the Second Compliance Period in a California Cap-and-Trade Program
Public Meeting Point of Regulation for the Sources of Fuel Combustion Included in the Second Compliance Period in a California Cap-and-Trade Program June 23, 2009 California Air Resources Board California
More informationELECTRIC VEHICLE, PLUG-IN HYBRID ELECTRIC VEHICLE, ELECTRIC VEHICLE SUPPLY EQUIPMENT, AND ELECTRIC BIKE GROUP DISCOUNT PROGRAM
REQUEST FOR INTEREST ELECTRIC VEHICLE, PLUG-IN HYBRID ELECTRIC VEHICLE, ELECTRIC VEHICLE SUPPLY EQUIPMENT, AND ELECTRIC BIKE GROUP DISCOUNT PROGRAM ( Electric Car Discount Program ) SUBMITTAL DUE DATE
More informationHonorable Mayor and Members of the City Council. Parking Policies and Fee Schedule Adjustments for City-Owned Garages
Office of the City Manager To: From: Honorable Mayor and Members of the City Council Christine Daniel, Interim City Manager Submitted by: Andrew Clough, Director, Public Works Subject: Parking Policies
More informationCalifornia Low Carbon Fuel Standard Status Report. John D. Courtis October 17, 2011
California Low Carbon Fuel Standard Status Report John D. Courtis October 17, 2011 Background CA legislature adopts Global Warming Solutions Act (AB 32) in 2006 Board passes LCFS April 2009 Title 17, CCR,
More informationElectric Vehicle Cost- Benefit Analysis. Plug-in Electric Vehicle Cost-Benefit Analysis: Maryland
Electric Vehicle Cost- Benefit Analysis Plug-in Electric Vehicle Cost-Benefit Analysis: Maryland December 2016 Acknowledgements Authors: Prepared By: For Submission to: Dana Lowell, Brian Jones, and David
More informationCriteria. As background, the US Environmental Protection Agency s Green Vehicle Guide states that:
GREEN COMMUNITIES Fuel efficient 4 Vehicles GRANT PROGRAM GUIDANCE Criteria INTRODUCTION Criteria Four of the Green Communities Program states that communities must purchase only fuel-efficient vehicles
More informationv Deborah Flint - Chief ecutive e, ficer
Date 6/30/2017 6/30/2017: 6/26/2017: Approval EY MY By RW AE MT BY...jil 0.'1 1 Los Angeles World Airports REPORT TO THE B A - e OF AIRPORT COMMISSIONERS Meeting Date:, A irdro, /. Approved : aiph -,...
More informationRenewable Fuels: Overview of market developments in the US and a focus on California
Renewable Fuels: Overview of market developments in the US and a focus on California Cynthia Obadia Cynthia Obadia Consulting Renewable fuel s growth driven by incentives from RFS and LCFS RFS - Federal
More informationMOTION NO. M Light Rail Vehicle Oil-less Rotary Scroll Air Compressor Upgrade PROPOSED ACTION
MOTION NO. M2017-152 Light Rail Vehicle Oil-less Rotary Scroll Air Compressor Upgrade MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee PROPOSED ACTION 12/07/2017 Final
More informationCreating A Greener Energy Future For the Commonwealth. Massachusetts RPS Solar Carve-Out: Overview & Program Basics.
Massachusetts RPS Solar Carve-Out: Overview & Program Basics November 2, 2011 Outline Learn how the solar PV market has grown in MA since 2007 Understand the policy design of the MA RPS Solar Carve-Out
More informationFITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM
Sheet 1 FITCHBURG GAS AND ELECTRIC LIGHT COMPANY SCHEDULE NM Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services
More informationElectric Vehicle Cost- Benefit Analysis. Plug-in Electric Vehicle Cost-Benefit Analysis: Connecticut
Electric Vehicle Cost- Benefit Analysis Plug-in Electric Vehicle Cost-Benefit Analysis: Connecticut December 2016 Acknowledgements Authors: Prepared By: For Submission to: Dana Lowell, Brian Jones, and
More informationON-ROAD HEAVY-DUTY TRUCK APPLICATION
CARL MOYER MEMORIAL AIR QUALITY STANDARDS ATTAINMENT PROGRAM ON-ROAD HEAVY-DUTY TRUCK APPLICATION Revised 08/2016 1 of 11 CARL MOYER RURAL ASSISTANCE PROGRAM Instruction Sheet The California Air Pollution
More information2019 NYC Solar Installer Workshop: Solar and Storage. March 18, 2019
2019 NYC Solar Installer Workshop: Solar and Storage March 18, 2019 2 ConEdison Activity Since MW Block Redesign Commercial MW Block Activity 3 15 MW submitted since redesign - 6/17/2018 10 rooftop canopy
More informationSalary Compaction Adjustment Tractor Trailer Driver and Solid Waste Loader Operator Classifications
Office of the City Manager CONSENT CALENDAR September 22, 2009 To: From: Honorable Mayor and Members of the City Council Phil Kamlarz, City Manager Submitted by: David W. Hodgkins, Director of Human Resources
More informationJennifer Szaro Renewables Manager, OUC
Jennifer Szaro Renewables Manager, OUC Bottom Line: They re Coming Cost savings Reduced Tailpipe Emissions Energy independence Economic development and job creation 3 Hybrid Conversions Standard hybrids
More informationFrom: Arthur Canafe, P.E. Approved by: /s/ General Manager
AGENDA ITEM : 3.F.1 MEETING DATE: 05/17/2010 ADMINISTRATIVE REPORT : 2010-64 To: Honorable Public Utilities Board Submitted by: /s/ Robert Streich AGM Engineering and Operations From: Arthur Canafe, P.E.
More informationEITF Issue 15-A, Application of the Normal Purchases and Normal Sales Scope Exception to Certain Electricity Contracts within Nodal Energy Markets
EITF Issue 15-A, Application of the Normal Purchases and Normal Sales Scope Exception to Certain Electricity Contracts within Nodal Energy Markets Education Session January 22, 2014 1 Overview and agenda
More informationFLEET SERVICES OVERVIEW and ACCOMPLISHMENTS Public Works Commission August 10, 2017
FLEET SERVICES OVERVIEW and ACCOMPLISHMENTS Public Works Commission August 10, 2017 DESCRIPTION OF FLEET OPERATION Fleet operations include vehicle and equipment maintenance, procurement and surplus services,
More informationCity of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources
Ordinance No. Exhibit A ----------------------------------------- City of, Kansas Electric Department Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources -------------------------------------
More informationSAN JOAQUIN VALLEY AIR POLLUTION CONTROL DISTRICT AGRICULTURAL PUMP ENGINE COMPONENT
SAN JOAQUIN VALLEY AIR POLLUTION CONTROL DISTRICT HEAVY-DUTY ENGINE PROGRAM AGRICULTURAL PUMP ENGINE COMPONENT ELECTRIC MOTOR NEW PURCHASE OPTION ELIGIBILITY CRITERIA AND APPLICATION GUIDELINES The San
More information2017 Colorado Phase 2 Regulatory Rate Review Frequently asked questions
1 What did Black Hills Energy file? We submitted a Phase 2 Rate Review proposal to the Colorado Public Utilities Commission (PUC) to complete the two-step process of updating electric rates, which were
More informationPortland General Electric Company Eleventh Revision of Sheet No. 7-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No.
Portland General Electric Company Eleventh Revision of Sheet No. 7-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No. 7-1 AVAILABLE In all territory served by the Company. APPLICABLE To Residential
More informationworkplace charging an employer s guide
workplace charging an employer s guide taking responsibility At your business, the efficient use of energy brings benefits such as lower bills, improved comfort levels for your customers and employees,
More informationCarbon Intensity Records under the Renewable and Low Carbon Fuel Requirements Regulation
under the 1 of 9 1. Background The Greenhouse Gas Reduction (Renewable and Low Carbon Fuel Requirements) Act (Act) sets low carbon fuel requirements for Part 3 fuel suppliers. A Part 3 fuel supplier is
More informationRegulatory and Permitting Requirements of Stationary Generators In Delaware
Regulatory and Permitting Requirements of Stationary Generators In Delaware Delaware - DNREC Air Quality Management February 7, 2006 Mark A. Prettyman and Guadalupe J. Reynolds Outline Regulation No. 1144
More informationEmerald People s Utility District RATE SCHEDULES. Rate Schedules Effective April 1, 2018
Emerald People s Utility District RATE SCHEDULES 2018 Rate Schedules Effective April 1, 2018 Connect With Us 33733 Seavey Loop, Eugene, OR 97405 Phone: 541-746-1583 Toll-free: 800-422-4086 Fax: 866-284-7953
More informationSCAQMD s Proposition 1B Goods Movement Emission Reduction Program
SCAQMD s Proposition 1B Goods Movement Emission Reduction Program Webinar Overview Prop 1B Funding Overview Truck Funding Overview Truck Infrastructure Project TRU Funding Overview Application Process
More informationFITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM
Sheet 1 FITCHBURG GAS AND ELECTRIC LIGHT COMPANY SCHEDULE NM Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services
More informationToo Good to Throw Away Implementation Strategy
Too Good to Throw Away Implementation Strategy Council Briefing by Sanitation Services October 4, 2006 Purpose of Briefing Summarize preparations for Too Good To Throw Away recycling services FY07 Recommend
More informationSALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE
SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE Effective: April 2015 Billing Cycle AVAILABILITY: The E-27 Price Plan is subject
More informationProposal Concerning Modifications to LIPA s Tariff for Electric Service
Proposal Concerning Modifications to LIPA s Tariff for Electric Service Requested Action: The Trustees are being requested to approve a resolution adopting modifications to the Long Island Power Authority
More informationORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report
ORANGE COUNTY TRANSPORTATION AUTHORITY Agreement to Purchase Compressed Natural Gas Articulated Staff Report November 8, 2012 To: From: Subject: Transit Committee Will Kempton, Chief Executive Officer
More informationUPPER CUMBERLAND ELECTRIC MEMBERSHIP CORPORATION. RESIDENTIAL RATE--SCHEDULE RS (March 2019) Availability. Character of Service.
UPPER CUMBERLAND ELECTRIC MEMBERSHIP CORPORATION RESIDENTIAL RATE--SCHEDULE RS () Availability This rate shall apply only to electric service to a single-family dwelling (including its appurtenances if
More informationTraffic Signals and Streetlights
Traffic Signals and Streetlights Overview This chapter provides an overview of the electricity usage and resulting CO 2 emissions from the City s traffic signals and streetlights. Data for this chapter
More informationThe oil fields in the NCS are located in the North Sea, Norwegian Sea, and Barents Sea.
A.2 Norway Volumes of Associated Gas Flared on Norwegian Continental Shelf Norway is a major oil producer, and its oil fields are located offshore in the Norwegian Continental Shelf (NCS). 81 In 2002,
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 DIVISION: Transit Services BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Requesting authorization for the SFMTA, through the Director of Transportation,
More informationElectric Vehicle Cost-Benefit Analyses
Electric Vehicle Cost-Benefit Analyses Results of plug-in electric vehicle modeling in eight US states Quick Take M.J. Bradley & Associates (MJB&A) evaluated the costs and States Evaluated benefits of
More informationSDG&E Customer Distributed Generation Programs. Steve Jaffe Senior Market Advisor Customer Innovations Group September 14, 2009
SDG&E Customer Distributed Generation Programs Steve Jaffe Senior Market Advisor Customer Innovations Group September 14, 2009 About SDG&E... A regulated public utility that provides service in San Diego
More information