MBTA Key Bus Route. Community Meeting Route 1 - Boston
|
|
- Luke Fox
- 5 years ago
- Views:
Transcription
1 MBTA Key Bus Route Improvement Program Community Meeting Route 1 - Boston United South End Settlement Agenda Welcome and introductions Safety briefing/accommodations Key Bus Route Program overview Existing conditions Recommendations Next Steps Discussion 2 1
2 Introduction Enhancements to 15 Key Bus Routes Funded by $10 million ARRA grant 3 Implementation Process Coordination with municipalities Development of initial concepts Community meetings Incorporation of public comments Refinement of concepts and final community buy-in Final design and construction 4 2
3 Project Schedule Bus Route 1 Develop Concept Jan/ Feb Apr Jun 2012 Mar Finalize Plan Engineering Implementation Public Process 5 1/19 1/20 2/2 3/8 6/13 6/14 Key Bus Route Goals Reliability less bus bunching Faster service fewer delays, less stops, shorter trip times Improved accessibility p Passenger amenities for seniors and persons with disabilities shelters, benches, signage, trash receptacles 6 3
4 Key Bus Routes 7 Typical Conditions Bus stop too short Signage issues Poorly located boarding area 8 Bus stops too close 4
5 Improved Accessibility Legal Mandate All bus doors must open at curb Deter cars from parking in stops Providing accessible curb access requires longer bus stops Bus Stops must meet Current Guidelines for 40 buses 9 9 Farside 60ft Nearside 80ft Required Bus Stop Lengths 10 Midblock (or after left hand turn) 100ft 5
6 Reliability Issues Bus bunching Overcrowding On-time performance 11 Preferred Bus Stop Locations Sufficient length to allow buses to pull to the curb Clear boarding/alighting area Not blocking crosswalks or driveways Considerate of adjacent traffic Appropriate distance between stops 12 6
7 Factors for Improving Stop Locations Ridership customer boardings and alightings Proximity to schools, medical centers etc Distance to adjacent stops Reducing traffic congestion Parking impacts Potential to add amenities shelters, benches etc. 13 Bus Stop Spacing Ideal spacing is 4-7 stops per mile (every 750-1,320 ft) (4-6 minutes walking distance) Route 1 has stops as close as 260 ft
8 Bus Stop Consolidation Benefits Shortens bus trip times Improves service reliability Minimizes stop & go experience Provides additional parking spaces Ability to provide better stop amenities 15 Traffic Signal Improvements Provide advance green time for buses Reduce overall congestion Requires coordination with roadway authority 16 8
9 Improved Amenities Trash receptacles Shelters 17 Benches Pavement markings Improving Customer Information 18 9
10 Route 1: Overview Harvard Square to Dudley Station Via Mass Ave, Central Sq. Cambridge, and South End Harvard University, MIT, Boston Medical Center, Symphony Hall 5 miles long Run time varies by time of day (20-39 min.) Connects to: Red, Green, Orange & Silver Lines 30+ bus routes, including: KBR 15, 23, 28,39, 57, 66, 71, 73, Route 1: Overview MBTA s 4 th busiest route Over 12,300 avg. daily boardings Peak Hour Headways Every 7-9 minutes On-time performance 65% weekdays Source:MBTA s 2008 Biennial Service Plan 69 stops 35 inbound (to Dudley) 34 outbound (to Harvard) 20 10
11 Proposed Recommendations (updated) 21 30% Design Plans 22 11
12 Farside 60ft Nearside 80ft Required Bus Stop Lengths 23 Midblock (or after left hand turn) 100ft Boston Improvements 24 12
13 Dudley Square Area 25 Melnea Harrison Ave Relocate IB stop farside, install concrete landing pad Proposed 26 13
14 Melnea Harrison Ave Relocate IB stop farside, install concrete landing pad. 27 Albany Melnea Cass Blvd IB Relocate stop to farside of Randall St. Investigate signal improvements and pavement markings. Proposed
15 Albany Melnea Cass Blvd IB Relocate stop to farside of Randall St. Investigate signal improvements and pavement markings. 29 Albany Street Consider outbound via Hampden St 30 15
16 Albany Northampton St Remove stops to improve bus stop spacing and due to low ridership Mass Ave Reconstruction Area St Botolph St to Albany St 32 16
17 Mass Harrison & Albany Maintain both stops, despite close proximity. Add amenities. 33 Mass Harrison Ave IB/OB Add pavement markings, and shorten OB stop
18 Mass Washington St OB Add pavement markings and amenities Mass Shawmut Ave Remove IB and OB stops to provide better bus stop spacing
19 Mass Columbus Ave Proposal to remove IB and OB stops is withdrawn. Add OB pavement markings Mass Mass Ave Station Pavement markings/crossing improvements. 38 June Leading 13, 2011 the Nation in Transportation Excellence 19
20 Mass Christian Science OB Consolidate Westland Ave with Clearway St. Construct landing area and add shelter and pavement markings. 90 Proposed Mass Christian Science OB Consolidate Westland Ave with Clearway St. Construct landing area and add shelter and pavement markings
21 Mass Christian Science IB Consolidate Christian Science Center with Westland Ave. Add shelter, trash receptacle and pavement markings. 81 Proposed Mass Christian Science IB Consolidate Christian Science Center with Westland Ave. Add shelter, trash receptacle and pavement markings
22 Mass Belvidere St Remove stop to provide better bus stop spacing and improve pedestrian and vehicle flow Mass Boylston Street Investigate shared bus/right turn lane Outbound Inbound 44 June Leading 13, 2011 the Nation in Transportation Excellence 22
23 Mass Hynes/Newbury St Repair sidewalk; consider adding bus lane Mass Hynes/Newbury St Relocate OB stop closer to Green Line Station. Add pavement markings, bus lane, and bus advance signal. 93 Proposed 46 23
24 Mass Hynes/Newbury St Relocate OB stop closer to Green Line Station. Add bus lane and TSP. 47 Mass Comm Ave Remove inbound/outbound stops and relocate shelters Leading the Nation in Transportation 94 Excellence 24
25 Mass Beacon Street Retain stops. Investigate shelter at OB stop Summary of Preliminary Recommendations Add benches, trash receptacles, pavement markings, shelters Stops lengthened for accessibility Stops relocated Stops Consolidated Current Stop Plan 36 IB/33 OB Proposed Stop Plan 28 IB/26 OB Investigating traffic signal improvements Sidewalk Improvements 50 25
26 Summary of Preliminary Recommendations IB OB Total Total existingstops Existing stops lengthened Existing stops relocated Proposed stops Proposed shelters Proposed benches Proposed trash receptacles Parking added Parking removed Project Schedule Bus Route 1 Develop Concept Jan/ Feb Apr Jun 2012 Mar Finalize Plan Engineering Implementation Public Process 52 1/19 1/20 2/2 3/8 6/13 6/14 26
27 Public Outreach
28 Comments and Next Steps Project Updates at Mail to Operations and Service Development, 45 High St, Boston, MA to Comments due by June 30, 2011 Next community meeting Route 1: June 14 Cambridge Senior Center Route 57: June 22 Boston Route 66: June 23 Mission Hill Discussion 55 Discussion We want to hear from you! 56 28
MBTA Key Bus Route Improvement Program. Community Meeting Route 66 Allston/Brighton
MBTA Key Bus Route Improvement Program Community Meeting Route 66 Allston/Brighton January 19, 2011 Honan-Allston Library 300 North Harvard Street Agenda Welcome and introductions Safety briefing/accommodations
More informationMBTA Key Bus Route Improvement Program. Community Meeting Route 57 - Boston. January 31, 2011 Boston Arts Academy, 174 Ipswich St.
MBTA Key Bus Route Improvement Program Community Meeting Route 57 - Boston January 31, 2011 Boston Arts Academy, 174 Ipswich St., Boston Agenda Welcome and introductions Safety briefing/accommodations
More informationMBTA Key Bus Route Improvement Program. Community Meeting Routes 15, 22, & 28. June 28, 2012 Dudley Library
MBTA Key Bus Route Improvement Program Community Meeting Routes 15, 22, & 28 June 28, 2012 Dudley Library Agenda Welcome and introductions Safety briefing/accommodations Key Bus Route Program overview
More informationKEY BUS ROUTE IMPROVEMENT PROJECT ROUTE 23 AGENDA
KEY BUS ROUTE IMPROVEMENT PROJECT ROUTE 23 December 9, 2009 Codman Tech 450 Washington Street AGENDA Introduction Key Bus Routes Program Route 23 Challenges Proposed Improvement Plan Next Steps Question
More informationIMPROVEMENT CONCEPTS
IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic
More informationHDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009
HDR Engineering HART North / South BRT Corridor PD&E Tampa Bay Applications Group Meeting May 14, 2009 1 Agenda Update on Project Development and Environment (PD&E) Study Project Overview System Branding
More informationGreater Cleveland Regional Transit Authority. Bus Stop Design Guidelines
Greater Cleveland Regional Transit Authority Bus Stop Design Guidelines Contents Purpose... I Bus Stop Design & Location... 1 Bus Stop Planning... 1 Bus Stop Safety & Consolidation... 1 As Needed Basis...
More informationI-405 and SR 522/NE 145th Bus Rapid Transit. Elected Leadership Groups Meeting November 30, 2018
I-405 and SR 522/NE 145th Bus Rapid Transit Elected Leadership Groups Meeting November 30, 2018 Agenda Welcome and Introductions Public Comment BRT Connection in Bothell Common Elements: Bus base, Station
More informationMetro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner
Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning
More informationNortheast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study
Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for
More informationVan Ness Transit Corridor Improvement Project. Engineering, Maintenance and Safety Committee March 25, 2015
Van Ness Transit Corridor Improvement Project Engineering, Maintenance and Safety Committee March 25, 2015 Project Need 16,000 daily passenger boardings within the project corridor Average bus speed 8
More informationArterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014
Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update
More informationSan Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors
Transportation Committee November 17, 2016 Agenda Item No. 5, Update on the San Rafael Transit Center Relocation San Rafael Transit Center Relocation Study Update 11/17/16 Golden Gate Bridge, Highway &
More informationDraft Station Plan. Tuesday, November 17th
Draft Station Plan Comments on this draft plan can be submitted to brtprojects@metrotransit.org. The public is also invited to attend upcoming open houses to provide input and learn more about the C Line
More informationState Avenue Corridor Bus Rapid Transit (BRT)
State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!
More informationBUS STOP DESIGN & PLANNING GUIDE
BUS STOP DESIGN & PLANNING GUIDE Prepared by the Operations and Planning Departments 2011 PURPOSE OF GUIDE The design of passenger waiting areas plays a significant role in a person s decision of whether
More informationBackground Information about the Metrobus 29 Lines Study
Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and
More informationCTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016
CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationChicago Transit Authority Service Standards and Policies
Chicago Transit Authority Service Standards and Policies Overview and Objectives The Chicago Transit Authority (CTA) has revised its Service Standards and Policies in accordance with Federal Transit Administration
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationDraft Results and Open House
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi
More informationSound Transit Operations July 2016 Service Performance Report. Ridership
Ridership Total Boardings by Mode Mode Jul-15 Jul-16 % YTD-15 YTD-16 % ST Express 1,618,779 1,545,852-4.5% 10,803,486 10,774,063-0.3% Sounder 333,000 323,233-2.9% 2,176,914 2,423,058 11.3% Tacoma Link
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More information2.0 Development Driveways. Movin Out June 2017
Movin Out June 2017 1.0 Introduction The proposed Movin Out development is a mixed use development in the northeast quadrant of the intersection of West Broadway and Fayette Avenue in the City of Madison.
More informationDevelop ground transportation improvements to make the Airport a multi-modal regional
Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use
More informationHelp shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary
Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County
More informationD Line Station Plan: Table of Contents
Final Station Plan This document identifies D Line station locations for approval by the Metropolitan Council in summer 2018. It is a final revision of the D Line Station Plan previously published for
More informationPedestrians, Cars, Buses and Trains? Considerations for Rapid Transit Service at Western University
Pedestrians, Cars, Buses and Trains? Considerations for Rapid Transit Service at Western University Shift: The City of London s Rapid Transit Proposal Shift: The City of London s Rapid Transit Proposal
More informationCITY COUNCIL STUDY SESSION UPDATE ON SMART. January 19, 2017 CITY OF SAN RAFAEL
CITY COUNCIL STUDY SESSION UPDATE ON SMART January 19, 2017 CITY OF SAN RAFAEL SONOMA MARIN AREA RAIL TRANSIT UPDATE OUTLINE BACKGROUND INITIAL OPERATION SYSTEM (IOS1) CIVIC CENTER AREA LARKSPUR EXTENSION
More informationSTH 60 Northern Reliever Route Feasibility Study Report
#233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development
More informationMETRO Orange Line BRT American Boulevard Station Options
METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN
More informationVIRGINIA RAILWAY EXPRESS MANASSAS PARK STATION PARKING EXPANSION. Site Evaluation & Recommendation. October 18, 2016
MANASSAS PARK STATION PARKING EXPANSION Site Evaluation & Recommendation October 18, 2016 1 INFORMATION ITEM Project Overview Parking Demand Site Evaluation VRE Recommended Preferred Alternative Next Steps
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationKing County Metro. Columbia Street Transit Priority Improvements Alternative Analysis. Downtown Southend Transit Study. May 2014.
King County Metro Columbia Street Transit Priority Improvements Alternative Analysis Downtown Southend Transit Study May 2014 Parametrix Table of Contents Introduction... 1 Methodology... 1 Study Area...
More informationAddress Land Use Approximate GSF
M E M O R A N D U M To: Kara Brewton, From: Nelson\Nygaard Date: March 26, 2014 Subject: Brookline Place Shared Parking Analysis- Final Memo This memorandum presents a comparative analysis of expected
More informationNew McNicoll Bus Garage Public Open House
New McNicoll Bus Garage Public Open House Kennedy Public School 1 The Need for a New Bus Garage Riders Increased ridership means Buses Need for new buses Garage And a new buses facility Problems Garages
More informationEssex Junction Train Station Access and Scoping Study Presentation of Transportation Alternatives
Essex Junction Train Station Access and Scoping Study Presentation of Transportation Alternatives Village of Essex Junction Chittenden County Regional Planning Commission RSG, Inc. Scott & Partners Architectural
More informationUpdate on Bus Stop Enhancements
Customer Service and Operations Committee Board Information Item III-A February 2, 2012 Update on Bus Stop Enhancements Page 3 of 15 Washington Metropolitan Area Transit Authority Board Action/Information
More informationMannheim/Higgins. Lee/Touhy. Municipal. Alternate 1), Village of Rosemont (Eastbound. Major Considerations:
Mannheim/Higgins Municipality: Municipality: City of Village Des Plaines of Skokie (Eastbound Alternate 1), Village of Rosemont (Eastbound Alternate Major 2 and Considerations: Westbound Alternate 1),
More informationMOBILITY AND ACCESSIBILITY IN OUR COMMUNITY
MOBILITY AND ACCESSIBILITY IN OUR COMMUNITY MOBILITY AND ACCESSIBILITY BACKGROUND Mobility and Accessibility Working Committee Broad representation Transit, Transportation, Planning and Development, Facility
More informationSnelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1
Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule
More informationANDERSON PROPERTY SITE ANALYSIS
ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion
More informationBus Stop Optimization Study
Bus Stop Optimization Study Executive Summary February 2015 Prepared by: Passero Associates 242 West Main Street, Suite 100 Rochester, NY 14614 Office: 585 325 1000 Fax: 585 325 1691 In association with:
More informationDowntown Transit Connector. Making Transit Work for Rhode Island
Downtown Transit Connector Making Transit Work for Rhode Island 3.17.17 Project Evolution Transit 2020 (Stakeholders identify need for better transit) Providence Core Connector Study (Streetcar project
More informationVIRGINIA RAILWAY EXPRESS MANASSAS PARK STATION PARKING EXPANSION. Public Meeting June 20, 2017
MANASSAS PARK STATION PARKING EXPANSION Public Meeting June 20, 2017 1 AGENDA Project Status Schematic Design Circulation Traffic Analysis Proposed Garage Location Next Steps Cost Estimate 2 PROJECT PHASES
More informationWhere will. BRT run? BRT will serve 20 stations along the line, connecting to bus routes and serving major destinations. How often will service run?
Where will 32 65 87 223 Rosedale Transit Center 225 227 264 801 ROSEVILLE 65 Snelling & County Road B BRT run? Snelling & Roselawn FALCON HEIGHTS BRT will serve 20 stations along the line, connecting to
More informationConnect. Thrive. Develop. KC Streetcar Riverfront Extension & Multi-Modal Feasibility Study
Connect. Thrive. Develop. Why go to the Riverfront? KC Streetcar is a proven catalyst for development & connecting people to Downtown. < $2 billion in adjacent development: new businesses, hotels, apartments
More informationCentral Park Drives Traffic Management Overview
Central Park Drives Traffic Management Overview Spring 2015 New York City Department of Transportation Existing Traffic Management From Labor Day thru Last Day of NYC Public School: 8-10 AM weekdays (Southbound)
More informationWhat IS BRT, Really? Not BRT and RNY
What IS BRT, Really? 2007 Winter TexITE Meeting Presented by Jeff Arndt, TTI Not BRT and RNY 1 What is Bus Rapid Transit? A flexible, rubber-tired from of rapid transit that combines stations, vehicles,
More informationBROWARD BOULEVARD CORRIDOR TRANSIT STUDY
BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,
More informationA Transit Plan for the Future. Draft Network Plan
A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year
More informationUS 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017
US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master
More informationRecommended Station Plan
Recommended Station Plan Comments on this recommended D Line Station Plan can be submitted to dline@metrotransit.org through June 8, 2018. This document identifies D Line station locations recommended
More information1. INTRODUCTION 2. PROJECT DESCRIPTION CUBES SELF-STORAGE MILL CREEK TRIP GENERATION COMPARISON
CUBES SELF-STORAGE MILL CREEK TRIP GENERATION COMPARISON 1. INTRODUCTION This report summarizes traffic impacts of the proposed CUBES Self-Storage Mill Creek project in comparison to the traffic currently
More informationCommunity Open Houses November 29 December 7, 2017
Community Open Houses November 29 December 7, 2017 1 Community Open House Agenda 6:00 PM Open House 6:30-7:30 PM Presentation and Q&A 7:30-8:00 PM Open House Resumes after the presentation and Q&A Thank
More informationGODURHAM PROGRESS REPORT
GODURHAM PROGRESS REPORT OVERVIEW OPERATIONS & PERFORMANCE With the service enhancements, total revenue hours increased In 2016, GoDurham connected 5.9 million passengers to jobs, education and health
More informationKendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study
Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What
More informationEast Bay Bus Rapid Transit Project. Downtown Oakland to San Leandro International Blvd to East 14 th St
East Bay Bus Rapid Transit Project 1 AC Transit at a Glance EAST BAY AREA S LARGEST PUBLIC TRANSIT PROVIDER RIDERSHIP Daily (weekday) 178,851* Annual 54,987,132 Paratransit (daily) 1,994 ** * Includes
More informationDetailed Definition of Alternatives
West Broadway Transit Study Detailed Definition of Alternatives 9/4/2015 DRAFT Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 2040 No-Build Alternative... 1 Build Alternatives...
More informationRestoration of Historic Streetcar Services in Downtown Los Angeles
Restoration of Historic Streetcar Services in Downtown Los Angeles Alternatives Analysis Community Update Meeting August 2, 2011 Introduction Key players Local lead agency: Metro Federal lead agency: Federal
More informationTroost Corridor Transit Study
Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit
More informationFederal Way Link Extension
Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate
More informationRecommended C Line Station Plan
Recommended C Line Station Plan Comments on this recommended C Line Station Plan can be submitted to brtprojects@metrotransit.org through March 11, 2016. This document identifies C Line station locations
More informationLAX Specific Plan Amendment Study. CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006
LAX Specific Plan Amendment Study CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006 Agenda Background on public planning process Regional planning update LAWA progress on settlement commitments
More informationFirst of four service increases delivered in April 2015
CAC Update AGENDA» Recent service improvements» Upcoming service improvements» Transit and pedestrian safety corridor improvement projects slated for legislation» Outreach look ahead First of four service
More informationI-26 Fixed Guideway Alternatives Analysis
I-26 Fixed Guideway Alternatives Analysis Public Meetings: North Charleston, January 25, 2016 Charleston: January 26, 2016 Summerville: January 28, 2016 Agenda I. Project Update II. III. IV. Screen Two
More informationFixing the Line s Canarsie Tunnel. Manhattan CB6 11/5/2018
Fixing the Line s Canarsie Tunnel Manhattan CB6 11/5/2018 Interborough Bus Service 80+ buses in the peak hour in the peak direction over the Williamsburg Bridge Projected to carry 17% of riders 1 Bus Priority
More informationSouth Lexington Transportation Study Lexington, Massachusetts
South Lexington Transportation Study Lexington, Massachusetts Preliminary Findings and Options for Consideration Businesses Meeting 10/10/13 Town of Lexington Engineering and Planning Departments Meeting
More informationCROSSING RAIL PROJECT (P4) RAIL
GRAND CROSSING RAIL PROJECT (P4) Community Advisory Group October 10, 2012 1:30 pm Grand Crossing Park Field House 7655 S. Ingleside Avenue, Chicago GRAND CROSSING RAIL PROJECT (P4) Community Advisory
More informationScoreCard Jun 2014 [May 14 Data] Ridership
+ ScoreCard Jun 214 [May 14 Data] Ridership Average Weekday Ridership May 14: 1.36M Up 2.% from May 213 Year-to-Year Change: May 13 to Present -.6% -1.% -2.3% -1.7%.4% 4.9% -.2% -.3% -3.8%.8%.7% 3.1% 2.%
More informationTransportation Sustainability Program
Transportation Sustainability Program Photo: Sergio Ruiz San Francisco 2016 Roads and public transit nearing capacity Increase in cycling and walking despite less than ideal conditions 2 San Francisco
More informationAppendix "A" Transit Bus Stop Accessibility Criteria & Guidelines
Appendix "A" Transit Bus Stop Accessibility Criteria & Guidelines Public Works Department, Transportation Division January 2014 Transit Bus Stop Accessibility Criteria & Guidelines These criteria and guidelines
More informationTPA Steering Committee for Tri-Rail Extension to Northern Palm Beach County. February 26, 2018
TPA Steering Committee for Tri-Rail Extension to Northern Palm Beach County February 26, 2018 Agenda Review Committee Purpose Review Project Map Discuss Service Alternatives Capital Costs (Stations, Track,
More informationService Quality: Higher Ridership: Very Affordable: Image:
Over the past decade, much attention has been placed on the development of Bus Rapid Transit (BRT) systems. These systems provide rail-like service, but with buses, and are typically less expensive to
More informationProject Status Update January 2017
Project Status Update January 2017 1 What is the Purple Line? A new 16 mile east-west light rail line Operates mostly on the surface with 21 stations Connects New Carrollton in Prince George s County and
More informationTable Station Elements
The overall layout of the station in the Preferred Alternative (Modified Alternative 2) is described in Table 7.5-1. Table 7.5-1 Station Elements Ground Level Mezzanine Level Platform Level Existing/Upgraded
More informationThe Latest on Joint Development Policy Guidance
Panelists The Latest on Joint Development Policy Guidance Moderator: Jonathan Davis Deputy General Manager and Chief Financial Officer Massachusetts Bay Transportation Authority James Blakesley, Attorney-Advisor,
More informationMBTA DEPARTMENT OF SYSTEM-WIDE ACCESSIBILITY FIXED ROUTE REPORT December, 2011
MBTA DEPARTMENT OF SYSTEM-WIDE ACCESSIBILITY FIXED ROUTE REPORT December, 2011 Accessibility Improvements at the 10 Park Plaza Bus Stop At the request of AACT, MBTA Operations is pursuing ways to improve
More informationWorkshop Agenda. Bransford Roundabout. Bedford Intersection/Roundabout. Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion
Workshop Agenda Bransford Roundabout Bedford Intersection/Roundabout Section 3 Revisions (Left turn lanes) Roadway Section/Curb Type Discussion Project Phasing Summary of Recommendation Purpose: Provide
More informationSPACE COAST AREA TRANSIT BUS STOP ACCESSIBILITY STUDY. Final Report
SPACE COAST AREA TRANSIT BUS STOP ACCESSIBILITY STUDY Final Report November 28, 2018 (This page intentionally left blank) Space Coast TPO Final Report Bus Stop Accessibility Study TABLE OF CONTENTS Inventory
More informationMTA New York City Transit Service Guidelines Manual
MTA New York City Transit Service Guidelines Manual Thomas F. Prendergast, President Robert Bergen, Executive Vice President Division of Operations Planning Peter G. Cafiero, Chief August 2010 Table of
More informationDevelopment and Overview of the NY 5 Bus Rapid Transit Corridor. New York State MPO Conference June 5, 2009
Development and Overview of the NY 5 Bus Rapid Transit Corridor New York State MPO Conference June 5, 2009 Bus Rapid Transit (BRT) n Enhancement of ordinary bus route to offer high quality transit at low
More informationNEWCASTLE MIDDLE SCHOOL Traffic Impact Analysis
Gibson Traffic Consultants 2802 Wetmore Avenue Suite 220 Everett, WA 98201 425.339.8266 NEWCASTLE MIDDLE SCHOOL Traffic Impact Analysis Prepared for: Renton School District Jurisdiction: City of Newcastle
More informationCEDAR AVENUE TRANSITWAY Implementation Plan Update
CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,
More informationMississauga Bus Rapid Transit Preliminary Design Project
Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.
More informationCentral Loop Bus Rapid Transit
Central Loop Bus Rapid Transit Transportation Goals of the Chicago Central Area ACTION Plan, page 2-6 Central Area Plan Improve Transit in Central Area Improve Pedestrian Environment Manage Traffic Circulation
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More information48 th and Chicago D Line Stop - September 13 th, 2018 Open House Materials
48 th and Chicago D Line Stop - September 13 th, 2018 Open House Materials Page 1: Table of Contents Page 2-3: Metro Transit Postcard: sent to station area Page 4-10: E-Newsletters Page 11-16: Meeting
More informationRailyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY
Railyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY RAB Citizen Working Group Meeting, August 1 st 2016 CITIZEN WORKING GROUP (CWG)
More informationMetro Transit Arterial Transitway Corridors Study
Metro Transit Arterial Transitway Corridors Study Technical Memorandum #3 Corridor Mode Development 2/1/2012 Prepared by the SRF Consulting Group Team Table of Contents Introduction... 1 Concept Plans...
More informationTreasure Island Toll Policy, Affordability and Transit Pass Programs. TIMMA Board Meeting December 11, 2018
Treasure Island Toll Policy, Affordability and Transit Pass Programs TIMMA Board Meeting December 11, 2018 Avoiding Island Gridlock 2 Island Mobility Goals Incentivize transit, walking, and biking Discourage
More informationTRAIN, BUS & TRANSIT
TRAIN, BUS & TRANSIT Input Metra 1 Metra does not want to add parking because of space; maxed out on number of cars per train. Developments on Rt. 59 will affect. 2 Should do studies regarding what the
More informationEast San Fernando Valley Transit Corridor. Information Session, October 10, 2017
East San Fernando Valley Transit Corridor Information Session, October 10, 2017 1 Welcome and Meeting Purpose Introductions Metro Transit Corridors Planning Metro Real Estate Metro Community Relations
More informationBOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY. Consent Workshop [ ]
- _j POSTPONED FROM THE JANUARY 14 BCC MEETING Agenda Item #5,::.. I BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY Meeting Date: February 4, 2014 [ ] [ ] Department: Submitted By: Engineering & Public
More information1 On Time Performance
MEMORANDUM: US 29 Travel Time & OTP To: From: Joana Conklin, Montgomery County DOT James A. Bunch, SWAI Subject: US 29 Travel Time and On Time Performance Analysis Date: This memorandum documents the US
More informationPulse Overview. Future Pulse Lines
Pulse Overview Pace s new rapid transit network, Pulse, will provide enhanced express bus service to commuters using the latest technology and streamlined route design. Pulse is designed to provide fast,
More informationEast San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013
East San Fernando Valley Transit Corridor TAC Briefing December 4, 2013 Overview Measure R Project Long Range Transportation Plan Reserves $170.1 Million 2018 Revenue Operations Date Coordination with
More informationThe Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix
The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis High Speed Intercity Passenger Rail Technical Appendix Prepared by HDR August 5, 2010 The Boston South Station HSIPR Expansion Project
More informationVIADUCT LOCATION STUDY. October 19, 2009
VIADUCT LOCATION STUDY October 19, 2009 Background Information Traffic Study Alternative Evaluation Public Involvement Preferred Concept Next Steps Evaluate alternatives for the location of a viaduct to
More information