Elected Officials Briefing North Metro Rail Line Update. November 10, 2016
|
|
- Alexis Jefferson
- 6 years ago
- Views:
Transcription
1 Elected Officials Briefing North Metro Rail Line Update November 10, 2016
2 Dave Genova, RTD General Manager and CEO
3 Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April 22 B Line, July 25 G Line, fall 2016 R Line, winter 2016
4 Ridership Flatiron Flyer Averaging 14,428 passengers per weekday Increase of 45 percent from previous service on the corridor University of Colorado A Line Averaging 18,880 passengers per weekday Averaging 16,151 passengers per Saturday Averaging 10,810 passengers per Sunday and Holidays B Line 1,511 passengers per weekday
5 Henry Stopplecamp, RTD Assistant General Manager, Capital Programs
6 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of bus rapid transit (BRT) 31 new Park-n-Rides; 21,000+ parking spaces Enhanced bus network and transit hubs Redevelopment of Denver Union Station 57 new rail and/or BRT stations Opportunities for Transit-Oriented Communities
7 FasTracks Status West Rail Line (W Line) Open Denver Union Station Open East/Gold/Northwest Rail Lines (EAGLE) Gold (G): 95% complete, testing underway; the University of Colorado A Line and B Line Open I-225 Rail (R) Line 94% complete with integrated testing underway throughout most of the line. U.S. 36 BRT (Flatiron Flyer) BRT in operation; express lanes complete; final construction activities underway North Metro (N) Line Construction continues on the Skyway Bridge; work on all bridges is underway. Drainage work along the alignment is ongoing, and OCS foundations and poles are being set throughout the line. Southeast Rail Soil nail wall and pier construction for the RidgeGate Parkway Station parking garage is underway. Continued abutment work for the RidgeGate and I-25 bridges. Ongoing utility relocations just north of Lincoln Avenue.
8 G Line to Arvada/Wheat Ridge 11.2 miles electric commuter rail 7 stations 25-minute travel time to Ward Road Opens fall 2016
9 G Line Update Denver Transit Partners (DTP), RTD s contractor for the Eagle P3 project, has been working on resolving the issues affecting the University of Colorado A Line s crossings. DTP has been operating trains under a waiver from the Federal Railroad Administration (FRA). The FRA has granted a 90-day extension on their waiver, allowing for continued operation of the University of Colorado A Line and B Line through February 4. RTD will resume testing along the G Line once the FRA approves progress along the University of Colorado A Line. Targeted opening date is fall 2016; RTD will update the public as soon as possible.
10 R Line through Aurora 22 miles of light rail 16 stations 5 new Park-n-Rides Regional connections to the University of Colorado A Line and Southeast Rail Line Scheduled to open by the end of the year
11 Economic Impact FasTracks job impact categories: Direct: Purchasing trains, building stations, and constructing railways. Indirect: Suppliers of goods and services such as train vehicles, steel for rails, and concrete for stations. Induced: Construction workers, engineers and other professionals working on FasTracks who spend their paychecks on consumer goods at local retailers, restaurants, movie theaters and coffee shops.
12 Economic Impact Since Jan. 2005, RTD has injected over $3.5 billion into the local economy Since 2005, FasTracks has created many jobs each year during peak construction: 600 construction jobs during West Rail Line construction 2,500 direct and indirect jobs during Eagle P3 construction Total direct full-time jobs: approx. 15,000 Total indirect and induced jobs: approx. 23,000
13 FasTracks as an Economic Driver Continue to implement more than $5 billion across the region 15,000 full-time jobs created since FasTracks began in 2005 $1 billion of development around Union Station Every $1 invested in transit infrastructure translates into $4 injected in the local economy
14 Ashland Vaughn, RTD North Metro Project Manager
15 North Metro Rail Line 18.5 miles, 13 under construction Electrified commuter rail 8 stations, 6 under construction Frequency 20-minute peak 30-minute off-peak 27 minutes Union Station to Eastlake 124 th Single track with multiple passing tracks Serves Denver, Commerce City, Thornton, Northglenn, Adams County
16 Schedule Construction: Civil & Infrastructure Systems & Stations 2018 Testing & Training 2018 Open to the public
17 Differences between N Line & Eagle Project Lessons learned No quad gates Do not have adjacent freight lines Do not have as complex roadway geometry and associated traffic signals as Eagle Project
18 Design Status Area A-C (DUS throat to York St.) is at IFC Area D (York to 72 nd ) is at IFC Area E (72 nd to 88 th ) is at IFC Area F (88 th -104 th ) is at IFC Area G (104 th to 112 th ) is at IFC Area H (112 th to 124 th ) is at IFC Bridges are all at IFC 48 th / Brighton is at IFC 72 nd and 112 th stations are at 100% 88 th Ave Station is at 100%. 104 th Station with parking garage is at 90% 124 th Station is at IFC
19 Systems Status Signals design is at IFC System-wide electrical design is at IFC Communications design is at IFC Traction Electrification and Overhead Catenary Design is at 100%, IFC (Nov. 2016) Xorail signals/communications detailed design is at preliminary (~90%) and moving toward final design
20 Dave Trent, RRP North Metro Project Director
21 Utility Relocations Utility Relocation activity along the line: Xcel electric relocation at 46th Avenue and National Western Drive Xcel electric relocation at Washington Street Bridge Cable TV at Washington Street Bridge Completed 67% of the 129 total utility conflicts
22 Ductbank Installation
23 OCS Pole Installation
24 Eastlake at 124th Station
25 120th Avenue Bridge
26 Northglenn at 112th Station August 2016 October 2016
27 Grange Hall
28 104th Avenue Bridge August 2016 October 2016
29 88th Avenue Bridge August 2016 October 2016
30 Hoffman and Lower Clear Creek October 2016
31 South Platte 3 Rehabilitation August 2016
32 Commerce City at 72nd Station
33 Skyway Bridge Longest bridge in the state 9,533 feet 63 piers/64 spans 7,626 fasteners, no ballast
34
35 Montclair Drainage August 2016 October 2016
36 Washington Bridge September 2016 October 2016
37 Denargo Bridge August 2016 October 2016
38 Upcoming Construction Ballasted track 112th to 124th Avenues OCS installation between 72nd and 104th Avenue School Tributary drainage pipe Divert South Platte River for pier protection at S. Platte 3 Bridge 70th Avenue Bridge Plinth pour at Skyway National Western Center Station platform walls Pour Denargo Bridge straddle cap
39 Questions? General Questions: Lindsey Smith lindsey.smith@rtd-denver.com Construction Questions: Kathy Berumen kberumen@rrpjv.com Visit the North Metro Rail Line website and sign up for notices at and click on North Metro
Elected Officials Briefing. North Metro Rail Line Update. February 9, 2017
Elected Officials Briefing North Metro Rail Line Update February 9, 2017 Dave Genova, RTD General Manager and CEO Openings 2016-2017 Flatiron Flyer, Jan. 3, 2016 University of Colorado A Line, April 22,
More informationElected Officials Briefing North Metro Rail Line Update. August 11, 2016
Elected Officials Briefing North Metro Rail Line Update August 11, 2016 1 Christina Henderson, Suncor Director of Energy Pipelines U.S. 2 August 11, 2016 RTD Update Christina Henderson Director, Suncor
More informationCommunity Meeting Station Elements
Community Meeting Station Elements North Metro Rail Line September 25, 2014 1 RRP Shawn Plichta Design Build Coordination Manager 2 RTD Jane Donovan Deputy Project Manager 3 The RTD FasTracks Plan 122
More informationDenver Metro Association of Realtors
Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;
More informationNorth Metro Rail Line Elected Officials Briefing. August 10, 2017
North Metro Rail Line Elected Officials Briefing August 10, 2017 Henry Stopplecamp, RTD Assistant General Manager, Capital Programs University of Colo. A Line, B Line & G Line: Update RTD met with Federal
More informationGold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014
Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014 RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;
More information8/18/2014. Peoria Station Meeting. August 14, Project Update. Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager
Peoria Station Meeting August 14, 2014 1 Project Update Tina Jaquez RTD Aurora Line/I-225 Rail Public Information Manager 2 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles
More informationRegional Transportation District. Dave Genova Interim General Manager and CEO August 21, 2015
Regional Transportation District Dave Genova Interim General Manager and CEO August 21, 2015 About RTD Created in 1969 Eight-county service area Service area: 2,340 square miles 2.8 million population
More informationQUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N
QUALITY OF LIFE EXECUTIVE SUMMARY REPORT UN I O N S TAT I O N T R AV E L by TR A I N Published September 2017 2015 PROGRESS MAP This document reports FasTracks progress through 2015 BACKGROUND RTD The
More informationFasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016
July 29, 2013 Welcome to Inside RTD FasTracks a monthly e- update to keep you informed about the progress of the Regional Transportation District's FasTracks program. FasTracks News RTD s Eagle P3 Transit
More informationI-225 Rail Line 2 nd /Abilene Station Design Public Meeting
I-225 Rail Line 2 nd /Abilene Station Design Public Meeting Jan. 29, 2014 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager 2 The RTD FasTracks Plan 122 miles of rail 18
More informationThe Southeast Rail Line extension is officially moving forward
November 2015 Welcome to Inside FasTracks -- your monthly update about FasTracks news, progress and people FasTracks News The Southeast Rail Line extension is officially moving forward Lone Tree Mayor
More informationWelcome to Inside FasTracks - - your monthly update about FasTracks news, progress and people
December 2014 Welcome to Inside FasTracks - - your monthly update about FasTracks news, progress and people FasTracks News I hear the train a- comin RTD s first electric commuter rail cars arrive in Denver
More informationPositive Train Control (PTC)
Positive Train Control (PTC) PTC at a glance FasTracks systems have Positive Train Control (PTC) technology called I-ETMS. This is a complex GPS-and-communications-based system that reduces the risk of
More informationAurora Line/I-225 Rail Project Update Public Meeting. June 4, 2014
Aurora Line/I-225 Rail Project Update Public Meeting June 4, 2014 FasTracks and I-225 Rail Line Update Danielle Smith I-225 Rail Line Design/Build Coordination Manager 2 The RTD FasTracks Plan 122 miles
More informationEagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013
Construction of Peña Bridge - March 2013 South Platte River Bridge Eagle P3 Project Update FasTracks Monitoring Committee Sept. 3, 2013 Today s Agenda Project background Schedule Design Systems Rail cars
More informationI-225 Rail Line. 13 th Avenue Station Information Meeting. July 25, 2013
I-225 Rail Line 13 th Avenue Station Information Meeting July 25, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager 2 The RTD FasTracks Plan 122 miles of rail 18 miles
More informationEast Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015
1 East Rail Line Update RTD FasTracks Citizens Advisory Committee March 18, 2015 Today s Agenda Safety Eagle P3 Project Commuter rail vehicle East Rail Line Economic impacts DBE/SBE/WIN status Progress
More informationB Line Update RTD FasTracks Citizens Advisory Committee Sept. 16, 2015
1 B Line Update RTD FasTracks Citizens Advisory Committee Sept. 16, 2015 Northwest Rail (B) Line 6.2 miles electric commuter rail Downtown to Westminster at the 71 st /Lowell Station 11-minute travel time
More informationRTD Commuter Rail System APTA Rail Conference June 23, 2015
RTD Commuter Rail System APTA Rail Conference June 23, 2015 RTD Eagle & North Metro Commuter Rail System Today s Presentation Eagle Design, Construction, Systems Commuter Rail Vehicles and CRMF/OCC EC
More informationEnergy Technical Memorandum
Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter
More informationI-225 Rail Line Iliff and Florida Stations Information Meeting
I-225 Rail Line Iliff and Florida Stations Information Meeting May 15, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager Chris Hinton I-225 Rail Line Deputy Project
More informationMETRO Light Rail Update
American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations
More informationConstruction Review Council. Sept. 13, 2011
Construction Review Council Sept. 13, 2011 Introduction Rick Clarke, Assistant General Manager, Capital Programs FasTracks Program Update and Schedule Del Walker, Deputy Assistant General Manager, Capital
More informationTrain Cars Are On The Move! Trains are rolling on the Eagle P3 Project.
In This Issue Page 2 Transit-Oriented Development Good for Communities Page 3 Eagle P3 Public Tours are Back! Denver Stands Up for Transportation Page 4 $1.19 Billion: Eagle P3 Project Builds Local Economy
More informationMobility Management: Caltrain
Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review
More informationCREATING CONNECTIONS IN WATERLOO REGION
CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX
More informationHelp shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary
Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County
More informationPomona Rotary December 19, 2017
Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking
More informationI-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager
I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results Public Meeting Wulf Grote, Director Project Development Rick Pilgrim, Project Manager March 4 & 5, 2008 Today s Agenda Overview of Alternatives
More informationCREATING CONNECTIONS IN THE CITY OF WATERLOO
CREATING CONNECTIONS IN THE CITY OF WATERLOO GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX METROLINX PRESENTATION TO
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationUpdate of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI
Update of the Midwest Regional Rail Initiative Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI Key Presentation Take-Aways Status of Midwest Regional Rail Initiative
More informationLeadership NC. November 8, 2018
v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the
More informationCommunity Advisory Committee. October 5, 2015
Community Advisory Committee October 5, 2015 1 Today s Topics Hennepin County Community Works Update Project Ridership Estimates Technical Issue #4:Golden Valley Rd and Plymouth Ave Stations Technical
More informationNew Haven Hartford Springfield Rail
New Haven Hartford Springfield Rail Opportunities for Economic Growth NHHS Rail Conference, October 25, 2011 NHHSrail.com Tom Maziarz, CT DOT, Bureau of Policy & Planning Thomas.Maziarz@ct.gov New Haven
More informationBusiness Advisory Committee. November 3, 2015
Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal
More informationMidtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions
Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions 1/3/2014 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 Alternatives Overview...
More informationCREATING CONNECTIONS IN THE TOWN OF NEWMARKET
CREATING CONNECTIONS IN THE TOWN OF NEWMARKET NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 10, 2017 GRIDLOCK
More informationTRANSFORMING THE WAY OUR REGION MOVES
TRANSFORMING THE WAY OUR REGION MOVES Judy Pfeifer, Chief Communications and Public Affairs Officer Gord Troughton, Director, Corridor Infrastructure Chris Burke, Director, Service Planning GRIDLOCK COSTS
More informationConfederation Line Stage 1 and 2. Our Lady of Fatima Church May 10 th, 2018
Confederation Line Stage 1 and 2 Our Lady of Fatima Church May 10 th, 2018 Agenda Confederation Line Stage 1 Overview project, consortium, vehicles Confederation Line Stage 2 Overview project, benefits
More informationNew Haven-Hartford-Springfield Rail Project Gateway to New England. Program Update March 14, 2011 Revised & Updated March 31, 2011
New Haven-Hartford-Springfield Rail Project Gateway to New England Program Update March 14, 2011 Revised & Updated March 31, 2011 1 New Haven-Hartford-Springfield Rail Corridor Glory Days: 1925-1955 22
More informationDraft Results and Open House
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationDART Priorities Overview
City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee
More informationSidewalk Working Group Update October 22, 2018
Sidewalk Working Group Update October 22, 2018 The Neighborhood Sidewalk Repair Program & The Sidewalk Gap Program Improving Mobility Freedom in Denver Neighborhood Sidewalk Repair Program: Repairing hazardous
More informationSales and Use Transportation Tax Implementation Plan
Sales and Use Transportation Tax Implementation Plan Transportation is more than just a way of getting from here to there. Reliable, safe transportation is necessary for commerce, economic development,
More informationQuarterly Update Meeting
Quarterly Update Meeting December 6, 2011 www.dcstreetcar.com / hotline: (855)413-2954 Agenda I. Welcome II. System Overview III. Project Update IV. Upcoming Meetings V. Stay Connected Provided by DC Streetcar
More informationExpo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015
Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide a final update
More informationBusiness Advisory Committee. July 7, 2015
Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS
More informationPeninsula Corridor Electrification Update Meeting
Peninsula Corridor Electrification Update Meeting Brisbane City Council September 6, 2018 Agenda Caltrain System Overview Project Overview Electric Multiple Unit (EMU) Design Brisbane Construction Activities
More informationNorthwest Rail Environmental Evaluation. Governments Team. September 13, 2007
Northwest Rail Environmental Evaluation Governments Team September 13, 2007 1 Agenda Welcome and introductions Commuter rail technology discussion History Technology review Technology evaluation criteria
More informationCommittee Report. Transportation Committee. Business Item No
Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope
More informationI-405 and SR 522/NE 145th Bus Rapid Transit. Elected Leadership Groups Meeting November 30, 2018
I-405 and SR 522/NE 145th Bus Rapid Transit Elected Leadership Groups Meeting November 30, 2018 Agenda Welcome and Introductions Public Comment BRT Connection in Bothell Common Elements: Bus base, Station
More informationCEDAR AVENUE TRANSITWAY Implementation Plan Update
CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,
More informationWest Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017
West Santa Ana Branch Transit Corridor Informational Briefing Gateway Cities Service Council April 13, 2017 Project Study Area 98 square miles 20 individual cities plus unincorporated LA County 1.2 million
More informationMaryland Gets to Work
I-695/Leeds Avenue Interchange Reconstruction Baltimore County Reconstruction of the I-695/Leeds Avenue interchange including replacing the I-695 Inner Loop bridges over Benson Avenue, Amtrak s Northeast
More informationExpo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011
Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor
More informationConfederation Line West Alignment Improvement. September 21, 2016
Confederation Line West Alignment Improvement September 21, 2016 Agenda Background Lincoln Fields Station and alignment improvement LRT alignment, west of Lincoln Fields to Queensview, including: Pedestrian
More informationGreen Line Long-Term Investments
Enhancements Short-term improvements to keep Austin moving. Investments Long-term projects to support our future. Mobility Hubs MetroRapid MetroRail MetroExpress Connectors Circulators Project Connect
More informationGreen Line opens June 14
Winter 2014 Green Line opens June 14 To-do list for METRO Green Line s grand opening Yours: Study safety tips at www.centralcorridor.org/safety Learn about planned Metro Transit bus service changes on
More informationValley Metro: Past, Present and Future. September 11, 2014
Valley Metro: Past, Present and Future September 11, 2014 Valley Metro Who are We? Two Boards of Directors Regional Public Transportation Authority Fund and operate regional transit services Valley Metro
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationUtility work, road construction substantially done on Fourth Street
November 2010 Fourth Street in downtown is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Utility work, road
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationFINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit
Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper
More informationCREATING CONNECTIONS IN THE CITY OF KITCHENER
CREATING CONNECTIONS IN THE CITY OF KITCHENER GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS KITCHENER CITY COUNCIL SEPTEMBER 25, 2017 CONGESTION
More informationCTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016
CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis
More informationCONFEDERATION LINE EAST SEGMENT
The O-Train Confederation Line project is the first stage in Ottawa s future light rail network. The 12.5 kilometre electric rail system will replace existing diesel powered buses, providing rapid transit
More informationDevelop ground transportation improvements to make the Airport a multi-modal regional
Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use
More informationUPGRADING THE AMTRAK KEYSTONE CORRIDOR
UPGRADING THE AMTRAK KEYSTONE CORRIDOR Mark A. Wurpel Director Project Initiation & Development Amtrak 2005 AREMA Conference & Exposition Chicago, Illinois ABSTRACT: Upgrading the Amtrak Keystone Corridor
More informationUCLA Lake Arrowhead Conference. October 18, 2010
BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1
More informationCREATING CONNECTIONS IN EAST GWILLIMBURY
CREATING CONNECTIONS IN EAST GWILLIMBURY NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 4, 2017 Page 8 of 146 GRIDLOCK
More informationNorthern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019
Northern Indiana Commuter Transportation District VENDOR OPEN HOUSE APRIL 17, 2019 VENDOR OPEN HOUSE AGENDA Welcome and Introductions Safety Briefing NICTD Website and Plan Room Upcoming Projects Disadvantaged
More informationCREATING CONNECTIONS IN RICHMOND HILL
CREATING CONNECTIONS IN RICHMOND HILL Mohamed Alkoka, Director, Corridor Infrastructure Metrolinx Anthony Irving, Manager, Community Relations Metrolinx May 15, 2017 1 GRIDLOCK COSTS OUR ECONONY Residents
More informationExpo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014
Expo Line Project Westside/Central Metro Service Council November 2014 2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily
More informationRail alignment and benefits (rab) study
Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study May 22, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create
More informationBalancing the Transportation Needs of a Growing City
Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program
More informationConfederation Line West Queensway Terrace North. May 27, 2017
Confederation Line West Queensway Terrace North May 27, 2017 Agenda Background Lincoln Fields Station Concept LRT alignment, southwest of Lincoln Fields to Queensway, including: Pedestrian bridge replacement
More informationACT Canada Sustainable Mobility Summit Planning Innovations in Practice Session 6B Tuesday November 23, 2010
ACT Canada Sustainable Mobility Summit Planning Innovations in Practice Session 6B Tuesday November 23, 2010 Presentation Outline Context t of Mississauga i City Centre Implementing Paid Parking and TDM
More informationUCLA Lake Arrowhead Conference. October 18, 2010
BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1
More informationUCLA Lake Arrowhead Conference. October 18, 2010
BART Click to Capacity edit Master Overview title style for UCLA Lake Arrowhead Conference October 18, 2010 0 BART Basics 360,000 daily riders 104 miles 43 stations 1.3 billion annual passenger miles 1
More informationStrategies to keep people and goods moving in and through Seattle
Strategies to keep people and goods moving in and through Seattle SR 99 Closure and the Seattle Squeeze 2018-2024 DON Information Session Department of Transportation Delridge Community Center November
More informationSouthern California - CHSRA
CALIFORNIA HIGH-SPEED RAIL Michael Gillam, Deputy Program Director Southern California - CHSRA CMAA - Construction Management Association of America July 19, 2012 CALIFORNIA S HIGH-SPEED TRAIN SYSTEM Largest
More informationCapital Needs Assessment Riders Advisory Council July2, 2008
Capital Needs Assessment 2011-2020 Riders Advisory Council July2, 2008 1 Outline I. Capital Improvement Plan History II. Capital Improvement Plan Update III. Capital Needs Assessment State of Good Repair
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract
More informationStaff Contact: Carlos de Melo, Community Development Director, (650)
Meeting Date: April 10, 2018 STAFF REPORT Agency: City of Belmont Staff Contact: Carlos de Melo, Community Development Director, (650) 595-7440 cdemelo@belmont.gov Agenda Title: Agenda Action(s): Caltrain
More informationPoint A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017
Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS
More informationBART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010
BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and
More informationBrigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction
Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction 550 North to 650 North $ 1,750,000 $ 1,582,113 To widen an existing bridge on 1200 West over Box Elder Creek that will
More informationThe Denver Model. Miller Hudson
The Denver Model Miller Hudson The Regional Transportation District Created in 1969 Eight county service area 40 municipalities Service area: 2,410 square miles 2.5 million population 15 elected Board
More informationCPG is pleased to report the following accomplishments this quarter:
MEMORANDUM To: From: Metrolinx Board of Directors Matthew Clark Chief Capital Officer (A), Capital Projects Group Date: February 7, 2019 Re: Capital Projects Group Quarterly Report Recommendation That
More informationTransitways. Chapter 4
4 Transitways Figure 4-1: Hiawatha LRT Train at the Lake Street/Midtown Station The 23 Transportation Policy Plan identifies a network of transitway corridors to be implemented by 23. Transitways recommended
More informationChicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015
Chicago to St. Louis High-Speed Rail IDOT District 8 Crossings July 29, 2015 1 History: Chicago-St. Louis Corridor» IDOT has actively developed the Chicago to St. Louis corridor since the mid 1980 s» In
More informationCrenshaw-Prairie Transit Corridor Study Public Meetings
Crenshaw-Prairie Transit Corridor Study Public Meetings Darby Park: Wednesday, February 20, 2008 6:30 8:00 PM US Bank Community Room: Thursday, February 21, 2008 6:30 8:00 PM Nate Holden Performing Arts
More informationPresentation of the Baltimore Metro System
Presentation of the Baltimore Metro System Presenter: Michael S. Davis Deputy Administrator, Transit Operations Division March 2, 2010 Topics Early Planning for Rapid Rail Transit System Overview Section
More information