TRANSMISSION SYSTEM PLANNING UNDER UNCERTAINTY OF SUPPLY AND DEMAND IN INDIAN CONTEXT. I S Jha Y K Sehgal* Subir Sen

Size: px
Start display at page:

Download "TRANSMISSION SYSTEM PLANNING UNDER UNCERTAINTY OF SUPPLY AND DEMAND IN INDIAN CONTEXT. I S Jha Y K Sehgal* Subir Sen"

Transcription

1 21, rue d Artois, F PARIS C1-114 CIGRE 2012 http : // TRANSMISSION SYSTEM PLANNING UNDER UNCERTAINTY OF SUPPLY AND DEMAND IN INDIAN CONTEXT I S Jha Y K Sehgal* Subir Sen Power Grid Corporation of India Ltd Gurgaon, INDIA SUMMARY Electricity demand in Indian Power System is expected to be more than 200GW in next 5-6 years for which more than 75GW capacity additions has been envisaged during 12 th Plan( ). Additionally, more than 30GW has been envisaged to be added through grid interactive renewable energy resources which includes about 19GW through wind and 10GW through solar energy. Both Govt/Public and private sectors are participating in big way in all segments of electricity supply chain i.e., generation, transmission and distribution. The Electricity Act, 2003 enabled setting up of IPPs(private generation project) along with open access. In this direction, large capacity addition has been envisaged through IPPs at various complexes in the State of Orissa, Jharkhand, Chhattisgarh, Tamil Nadu etc. without firm beneficiaries/commissioning schedule. Such uncertainties along with right of way (RoW) pose challenges to the transmission planner for development of transmission system. A new concept for transmission system planning under uncertainty of supply and demand levels for transfer of power to target destinations/direction is presented. The challenges for development of transmission system under such uncertainties as well as implementation mechanism along with recovery of investment are deliberated. Emerging technology integration in the development of transmission system in modular way is also highlighted. A case study with specific reference to development of high capacity transmission corridors for various IPPs in Chhattisgarh, M.P in Western region and Jharkhand, Orissa in Eastern Region is also presented. KEYWORDS Beneficiary, Investment, Planning, Technology, Transmission, Schedule, Uncertainty 1

2 1. INTRODUCTION Power system in India is growing at an accelerated pace. Electricity demand is expected to be increased to more than 200GW in next 5-6 years for which over 75GW capacity additions has been envisaged during 12 th Plan. Additionally, about 31GW has been envisaged to be added through harnessing grid interactive renewable energy resources which includes about 19 GW through wind and 10 GW through Solar energy. Currently, the sector is passing through an evolutionary phase and numerous radical changes are taking place in the structural, institutional and operational arrangements. Both Govt/Public and private sectors are participating in large scale in all facets of electricity supply chain i.e., generation, transmission and distribution. This has resulted into paradigm shift in the way with which the power sector is being viewed. Further, the consumer today is looking for Secure, reliable and quality power at affordable price. The Electricity Act, 2003 has created new paradigm for the development of power sector in our country. It has created a new competitive framework for the development of the Power Sector with focus on the consumer and safeguarding his interest through Independent Regulatory Commissions. The Act enables delicensing of generation, transmission as license activity, trading as distinct activity, non discriminatory Open Access in transmission, no more fixed formulae (unlike earlier fixed formula) for allocation of power to the regional constituents rather they are to be determined based on Competitively bid generation tariff, consumers can procure power from different sources through competitive bidding process etc. As a result, large capacity addition of the order of 180 GW has been envisaged under Govt. and private sector in next 5-6 years without identifying actual destination points i.e, beneficiaries of most of the generation projects. Mostly projects are proposed to be located at pocketed pit-head/resource areas with each location having capacity in the range of 5-10 GW. This necessitates transfer of bulk power to the far-off load centers through long distance transmission system. Various factors like identification of system strengthening in the absence of firm beneficiaries, conservation of eco-sensitive Right-of-Way(ROW), protection of flora & fauna, flexibility to enhance corridor capacity, recovery of investment etc. are posing major challenges towards planning and development of suitable transmission system. In this paper, major considerations for transmission system planning under uncertainties for transfer of power from various generation projects to target destinations are presented. Various issues that need to be addressed towards development high capacity transmission system, comprising ±800kV, 6000MW HVDC and 400kV/765kV AC system with provision to upgrade to 1200kV at a later date, taking into account other factors are also highlighted. Emerging technology integration in the development of transmission system in modular way is also highlighted. A case study in this regard is also presented. 2. OVERVIEW OF INDIAN POWER SYSTEM Indian Power System is demarcated into five(5) electrical regions viz, Northern, Eastern, Western, Southern and North-eastern Regions as shown at Fig.1 below: NR Fig.1: Regional boundary of Indian Power System WR ER NER LAKSHADWEEP SR ANDAMAN & NICOBAR 2

3 Present Installed capacity of Indian Power System is about 186 GW and the peak power demand is about 127 GW. The trunk transmission system in all the regions is dominated by 400kV level networks. The grid comprises about 4500 ckt. kms 765kV lines, 106,000 ckt. km of 400kV lines. In addition, four(4) HVDC bipoles (8000MW), seven(7) HVDC back-to-back (3000MW) links are under operation. Today, as a part of National Grid, central grid comprises of Northern, Western, Eastern & North-eastern regions are operated as a single grid of more than 137 GW and Southern grid of about 49 GW capacity is interconnected through a number of HVDC systems. However, to cater the imbalance between demand and supply in the region, National Grid of 23,800MW capacity through inter-regional links were established for exchange of power between regions. A view of the present National Grid showing inter-regional lines is depicted at Fig. 2. Fig. 2 : Existing Inter-regional links of National Grid As per the Integrated Energy Policy: Report of the expert committee by Planning Commission, it is estimated that by 2027, demand would be about 522GW (considering 9% GDP growth rate) for which total installed capacity of about 685GW is envisaged. Growth pattern of capacity requirement by the end of each five(5) years by 2027 is given at Fig GW Fig. 3: Growth pattern of capacity requirement by

4 In order to enhance the capacity of inter-regional links to enable transfer of power across regions in long-term, National Grid capacity is being enhanced to more than 65,000 MW by A view of National Grid by 2017 is shown at Fig-4 NR KURUSHETRA JAIPUR FATEHPUR GORAKHPUR AGRA AURAIYA BALIA KANKROLI ORAI MUZAFFARPUR RAPP PATNA BIRPARA BARH KOTA RIHAND TILAIYA SILIGURI B'SHARIFF SAHU PURI GAYA MALANPUR MALDA SASARAM GWALIOR V'CHAL ZERDA J'PUR POOL ER DEHRI NAGDA KORBA CHAMPA D'GARH BUDHIPADAR UJJAIN WR POOLING JHARSAGUDA SIPAT RANCHI RAIPUR ROURKELA WR TALCHER BALIMELA CHANDRAPUR NER SALAKATI BONGAIGAON L. SUBANSIRI SHOLAPUR KOLHAPUR PONDA GAZUWAKA RAICHUR NARENDRA BELGAUM U.SILERU NAGJHARI SR KOLAR LEGEND POWERGRID LINES EXISTING UNDER CONST./ PLANNED 765 KV LINES 400 KV LINES 220/132 KV LINES HVDC B/B HVDC BIPOLE Fig. 4: A view of National Grid by CONCERNS IN TRANSMISSION SYSTEM DEVELOPMENT Pocketed generation resources and wide spread load centers across the country coupled with right-ofway problems necessitates development of high capacity transmission corridors. However, major concerns towards planning of such corridors are : Long-term planning keeping a horizon of years Right-of-Way(ROW) and protection of flora and fauna Flexibility to enhance the transfer capacity in view of uncertainty of generation projects, implementation in different phases Optimisation of transmission cost and losses Non-discriminatory Open Access To fulfill above requirements, need of the hour is to introduce emerging technologies into the transmission system. In this direction, many new technologies have already implemented/undertaken. Some of them are: 765kV System with double circuit configuration as high power intensity corridor ±800kV 6000MW long distance HVDC system Multi ckt towers to avoid deforestation and protection of wild life Multi-conductor Bundle line to increase power intensity Compact Tower /Pole Tower to reduce Right-of-Way in urban area High Temp endurance conductor line for increased loading Fixed and Thyristor Controlled Series Capacitor (TCSC) to enhance transmission capability Gas Insulated substation (GIS) to optimise space for substation Substation automation & remote operation to reduce land requirement 4

5 In addition, 1200kV AC technology is being developed as next higher AC voltage in the country, which is the highest AC voltage level in the world. Development of this technology would go a long way for strengthening of National Grid capacity to take care of long-term power transfer requirement of the country. In order to develop this 1200kV AC technology indigenously, a unique effort has been made, which is first time in India Power Sector, through an open collaborative effort between POWERGRID and manufacturers to establish a 1200kV UHVAC Test Station at Bina. This endeavor shall benefit Indian Power sector and manufacturers as availability of 1200KV class equipment within country will not only enable optimisation of transmission cost, but also help in making ease in execution and O&M phase. One 1200kV single circuit transmission line with octa-bundled configuration of about 400km long is under implementation which shall be initially to be operated at 400kV quad-bundled double circuit line. In this direction, POWERGRID along with 34 manufacturers is establishing a 1200kV UHVAC Test Station at Bina. It contains two nos. 1200kV bays comprising 1200kV class equipment like Instrument transformers, Circuit Breakers and surge arresters and two nos. of 1000MVA transformer bank each comprising three(3) single phase 400kV/1200kV, 333 MVA auto transformers. In addition to the above substation equipment, two(2) nos. 1200kV AC test lines about one(1) km. long [one single circuit(s/c) and one double circuit(d/c)] each will also be constructed and charged through these two 1200kV bays to study their performance by conducting measurements of various line parameters. In the existing 400kV system through a Loop-in loop-out (LILO) arrangement, power flow through 1200kV test station shall be established. Schematic of 1200kV National Test Station is presented at Fig kV line 400kV line Satna line 400kV Bina Bus 1200kV line 1200/400kV Transformer 1200/400kV Transformer To 400kV Satna line Fig. 5: Schematic of 1200kV Test Station arrangement Nominal voltage considered as 1150kV with maximum level at 1200kV, LIWL of equipment considered as 2400kVp and SIWL as 1800kVp. Multi Column Surge Arresters have been developed to achieve lower ratio of Lightning and Switching Impulse voltage. The test station is expected to be charged in the first quarter of UNCERTAINTIES IN TRANSMISSION SYSTEM PLANNING In the current electricity supply regime, various uncertainties are associated with transmission system development process. Some of the key uncertainties pushing a paradigm shift in transmission system planning are : Uncertainties in development of generation project time frame No firm beneficiaries at the development stage of the project due to introduction of power purchase through tariff based competitive bidding process Recovery of investment towards transmission development 5

6 4.1 Uncertainties in development of generation project A large number of generation projects are proposed mainly in Orissa, Jharkhand, Chhattisgarh, M.P by private developers in 12 th Plan. All the developers have applied for long-term access for transfer of power from the projects. Past experience reveals that most of the time there is a big gap in planned and actual generation addition, which hampered the optimal utilization of overall planned transmission system as well as impacted in system operation. On the contrary, to address the RoW issue, it is necessary to develop high capacity transmission corridors from resource areas (generation complexes) to the load centers keeping in view long-term perspective. Proposed approach: It is important that most of the projects in the particular generation complex must get materialized as per the schedule to ensure optimal utilization of transmission infrastructure. For this, an integrated resource planning approach is required so that a particular complex gets materialized first. Further, as the generation projects are developed in phases, flexibility in upgradation of transmission corridor matching with its phase-wise development through integration of new technologies may be adopted to take care of uncertainty and optimize investment. This shall also facilitate smooth operation of system in terms of maintaining grid parameters, stability etc. 4.2 Uncertainties in identification of beneficiaries Earlier the projects were planned as a regional generation projects (Inter-State Generation System), in which all the constituents of a particular region were the beneficiaries or at least beneficiaries were known upfront. Accordingly the transmission system was planned based on the requirement of power transfer to the known destinations. However, to promote competition in the electricity supply industry, Govt. of India has issued guidelines for determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees. Due to introduction of such tariff based competitive bidding under Case-I/Case-II guidelines, generation developers don t have conformity from the beneficiary till they win the bid from distribution licensees. Therefore, at the time of long-term access application, no firm beneficiaries are identified. Therefore, in this scenario, generation developers are not able to commit upfront about the beneficiaries along with their allocation for the purpose of planning optimal transmission system. Further, development of number of Merchant Power Plant(MPP) have been envisaged and in such cases also by its nature there is no firm beneficiaries. In such scenario, it has become difficult to plan the transmission system in the absence of information about the beneficiaries and quantum of drawl by each of them. Proposed approach: National Electricity Plan envisaged future demand supply scenario of various regions and Electric Power Survey report provides demand projection of different States. Further, based on the capacity addition programme in the State, future surplus-deficit situation may be estimated. Accordingly, developers may inform the target beneficiary(ies)/regions for power transfer from the respective projects while evolving transmission system fitting into overall transmission plan. In the long-term access regulation of Central Electricity Regulatory Commission(CERC) such provision of indicating target region has been kept now. 4.3 Recovery of investment for Transmission system Uncertainties in generation project schedule and firm beneficiaries, project development in a few complexes, development of high capacity transmission corridors to take care of right-of-way issue etc, has resulted into complexity in recovery of investment in transmission corridors. In case only few generation projects materializes, the cost of transmission for the corridor would be high. On the other hand, as mentioned earlier, generation developers are also not sure about the firm beneficiary and therefore, may be reluctant to share of transmission charges for a particular transmission corridor. This has made the overall transmission system planning and development further difficult. 6

7 Proposed approach: In order to rationalize the transmission charges of various corridors to take care of uncertainties and recovery of investment, it is proposed that transmission system of various private generation projects/mpps may be planned and segregated into two parts: Part-A: Portion of transmission system between generation project and grid interconnection point/pooling station (Inter-state Transmission System) as dedicated transmission system of specific project. Further, being dedicated element, same may be built, owned, operated and maintained by the respective developer/tariff based bidding route and cost to be borne by the particular generation developer. Part-B: Portion of transmission corridor beyond the grid interconnection point/pooling station may be developed as a common purpose system to be utilized by other projects also and same to be treated as part of common system strengthening. Transmission charges are to be pooled with the Regional Transmission system and considered in the Point of Connection(PoC) charges comprising of point of injection and drawal charges. Regulatory approval may be obtained to include the asset in the common pool. However, to ensure timely development of common purpose transmission corridor(s) in an environmental friendly manner, it is proposed that respective generation developers may share the transmission charges to provide comfort for the investment to the transmission developers. The generation developers in turn may make back-to-back arrangement with the procurers/beneficiaries for transmission charges recovery. 5.0 CASE STUDY As discussed above, capacity addition of about 75GW in 12 th Plan (Central sector-24%; State sector- 18% and Private-58%) has been envisaged which includes proposed IPP generation projects mainly in Orissa, Jharkhand, Chhattisgarh, Madhya Pradesh etc. with capacity about 40,000 MW. In most of the cases, firm beneficiaries of the IPPs are not known and only target beneficiaries or destination of power transfer requirement is available. This has cropped up plethora of uncertainties and challenges to the transmission planning and development process. Absence of information about beneficiaries from such large sized projects of Private /Merchant developer as well as firm schedule of generation projects would need to make some assumption regarding destination of power transfer to plan the high capacity transmission system. As per National Electricity Plan/18 th Electric Power Survey report, scenario emerged that power would primarily need to be transferred to deficit regions like Northern/Western region. However considering the severe Right-of-way constraints in States like Chhattisgarh which has about 50% dense forest/reserve areas and of the similar order in the States of Jharkhand and Orissa as well as bulk quantum of power transfer requirement from the generation complexes in these states, it is required to develop high intensity transmission corridors(mw/m ROW) with voltage level 800kV/1200kV. A comparison of power intensity at different transmission voltage level is given at Table-1: Table-1: Power Intensity(MW/m) at different transmission voltage level 400kV 765kV ±800kV HVDC 1200kV ROW(m) Capacity(MW) MW/m It is seen that power intensity(mw/m ROW) of 765kV transmission corridor is about 3 times higher than 400kV level. Further, intensity of ±800kV 6000MW HVDC/1200kV corridor is about 5 times higher than 400kV and almost double than 765kV corridors. A comparison for requirement of number of transmission corridors at different voltage level for transfer of about say 8,000MW power satisfying n-1 redundancy criteria is presented in Table-2 7

8 Table-2: Transmission Corridor Requirement Voltage level No. of Transmission Corridors Approx. min Right-of- Way required(m) 400kV AC D/c kV AC S/c kV AC D/c kV AC ±800kV 6000MW HVDC It is observed that for transfer of about 8,000MW at 765kV level, there is a requirement of at least 4 nos. transmission corridors (S/c) which requires about 250 meter Right-of- way. Keeping this in view, it is the need of the hour to adopt higher voltage level as well as high intensity corridors such as ±800kV, 6000MW HVDC system, 765kV double circuit(d/c), 1200 kv AC(initially may be operated at lower voltage level when power transfer requirement is less) etc. so as to utilize Right-of-way in an optimal manner. As per the information, complex wise proposed capacity addition in the Orissa, Jharkhand, Chhattisgarh, Madhya Pradesh by is shown in Table-3. Table-3: Complex wise capacity addition envisaged State/Complex Capacity(MW) Orissa 10,000 Jharkhand/West Bengal 4,500 Madhya Pradesh 4,500 Chhattisgarh i) Raigarh 11,000 ii) Champa 10,000 Power from the above generation complexes is envisaged to be transferred to different target beneficiaries in Western/Northern Region. Keeping this in view a composite but flexible transmission system was evolved based on the load flow studies. In the studies, entire transmission network of Eastern, North-eastern, Western, Northern grids corresponding to 12 th plan time frame was simulated and complex wise corridors are discussed as below. 5.1 Raigarh Complex In order to facilitate transfer of power from generation projects in Raigarh complex, Chhattisgarh in Western Region, development of a 400/765kV Pooling station near Raigarh is proposed so that power of all the upcoming IPP projects in this complex can be lifted at the pooling stations. For onward dispersal of power, this Pooling Station is proposed to be connected with another pooling station near Raipur. Considering serious ROW constraint beyond Raigarh/Raipur and quantum of power transfer, it was proposed to interconnect Raigarh and Raipur through high capacity 765kV D/c lines. In addition, keeping in view serious ROW constraint and quantum of power transfer beyond Raipur, it was proposed to develop a parallel 765kV D/c high capacity transmission corridor through Raipur- Wardha-Aurangabad in parallel with Wardha Aurangabad 1200kV corridor(initially to be operated at 400kV level). This 765kV D/c corridor is the first of its kind in Indian Power System. 5.2 Champa Complex Similarly for transfer of power from Champa complex in Chhattisgarh, it was proposed to develop a 765/400kV Pooling Station and ±800kV HVDC terminal near Champa to interconnect the nearby IPP projects. Considering the quantum of power transfer requirement and ROW issues, a hybrid high capacity AC & HVDC system is considered. High capacity AC corridor emanating from Champa Pooling Station i.e, Central Part of Chhattisgarh and terminating in Western Part of Maharashtra. This pooling station is also proposed to be interconnected with Raigarh Poooling station thorugh 765kV link for mutual support in power evacuation. Further, in view of the bulk power transfer requirement 8

9 towards Northern region(nr) beneficiaries, a ±800kV, 6000MW HVDC bipole upto Kurushetra in NR is proposed. A schematic of the different high capacity transmission corridors in Western Region is shown at Fig. 6 Fig. 6: Schematic of High capacity transmission corridor in WR for IPPs in Chhattiagarh/M.P 5.3 Orissa/Jharkhand Complex As indicated by the generation developers, the major portion of power from various generation projects of Orissa/Jharkhand would have to be exported to power deficit regions like NR & WR. For evacuation and transfer of power from projects in Orissa/Jharkhand to NR/WR, there was a need to evolve a composite high capacity transmission scheme in view of the Right-of-way problem, wherein different generation projects coming up in different time-frame could be integrated. In order to pool power from various generation projects in Orissa, two(2) nos. of 765/400kV pooling substations have been planned at Angul and Jharsuguda. The pooling stations would be interconnected in ring form with 765kV lines. For transfer of power from Angul/Jharsuguda to WR/NR, a high capacity 765kV AC D/c corridor has been planned to NR via WR and ER. The corridor emanates from Jharsuguda in ER, reaches upto Bhiwani in the western part of NR via important substations like Dharamjaygarh(WR), Jabalpur(WR), Bina(WR), Gwalior(WR) and Jaipur(NR). The corridor also reaches to Indore, northern part of WR via Bhopal(WR) and Jabalpur(WR). In the process three(3) nos. of new 765/400kV substations would be created at Dharamjayagarh, Jabalpur and Bhopal. Dharamjayagarh would be an important power hub where power could be pooled from generation projects of Orissa as well as Jharkhand/Bihar in ER for onward transfer to Western part of WR as well as to NR. Jabalpur 765/400KV substation would be an important take off point for diversion of power to WR through Jabalpur-Bhopal-Indore route and to NR via Jabalpur-Bina-Gwalior(WR)-Jaipur(NR)-Bhiwani route. The corridor in the central part of NR extended at Kanpur/Lucknow, central/northern part of NR via ER. A schematic of the High Capacity Transmission Corridor for IPP projects in Orissa is depicted at Fig. 7. 9

10 Fig. 7: Schematic of High capacity transmission corridor for IPPs in Orissa/Jharkhand 6. RECOVERY OF INVESTMENT Towards recovery of investment in high capacity transmission corridor, it was decided that immediate evacuation system i.e. dedicated transmission system between generation project and Pooling Station/grid connection point for different generation projects shall be developed by the respective generation developers. However, the common transmission corridor to facilitate power transfer to target beneficiaries would be developed as Inter-State Transmission System in phases matching with the commissioning schedule of generation developers. Further, as the transmission corridors were identified based on the target beneficiaries/allocation, hence, developers agreed to share the transmission charges for particular corridor in proportion to their transfer requirement for smooth development of system. Central Transmission Utility(POWERGRID) was also accorded regulatory approval from CERC to undertake implementation of above high capacity transmission corridors keeping in view the progress of he generation projects. 7. CONCLUSION Tremendous growth of Indian Power sector in all fronts viz. generation, transmission and distribution is taking place. National Grid capacity is being enhanced from present level of 23,800 MW to more than 65,000 MW by 2017 which shall be further increased progressively. Large capacity addition was envisaged through IPPs/MPPs mainly confined in Orissa, Jharkhand, West Bengal in Eastern Region, Chhattisgarh and M.P in Western Region. However, various uncertainties are associated with above IPPs specially no information about firm beneficiaries, commissioning schedule of projects, recovery of investment in transmission etc. This made the transmission system planning and development a challenge. Development of high capacity transmission corridors comprising HVDC and AC system interconnecting various generation projects through suitable pooling station to major load centres in power deficit Western/Northern Region based on target beneficiaries were proposed. Further, to rationalize transmission charges, proposed transmission system was divided into generation specificdedicated system to be developed by the respective developer(s) and common purpose system as a system strengthening project in which transmission charges also to be shared by the generation developers corresponding to their capacity for smooth development of system. 10

11 ACKNOWLEDGMENT Authors are thankful to the management of POWERGRID for granting permission to present the paper. Views expressed in the paper are of authors only and need not necessarily be that of management. BIBLIOGRAPHY [1] Key inputs for accelerated development of Indian Power Sector for 12 th Plan & beyond, CEA Base paper, 2009 [2] Integrated Energy Policy-Report of the Expert committee, GoI, 2006 [3] Central Electricity Authority(CEA) Website: 11

Overview of Indian Power Sector. February 29, 2008

Overview of Indian Power Sector. February 29, 2008 Overview of Indian Power Sector February 29, 2008 Evolutionary Phase of Power Sector Radical changes in structural, institutional and operational arrangements. Supply of electricity is moving away from

More information

Transmission System Planning under Uncertainty in Indian Context

Transmission System Planning under Uncertainty in Indian Context Transmission System Planning under Uncertainty in Indian Context R.N. Nayak, Y.K. Sehgal and Subir Sen Abstract Indian power sector is passing through an evolutionary phase and radical changes are taking

More information

HVDC Systems in India

HVDC Systems in India HVDC Systems in India Outline Introduction HVDC Systems presently in operation Main Data/Salient Features Upcoming Projects Future Challenges Transmission Network - Present 765kV/400kV lines: about 1,03,000

More information

Future Power Supply Scenario

Future Power Supply Scenario Indian Power Scenario At a glance Surplus Regions 30,860 MW 2300 2300 16,000 32,700 MW 30,500 MW Deficit Regions Installed Capacity : 1,18,000 MW Peak Demand : 87,000 MW Peak Availability : 77,000 MW Energy

More information

Report. the feasibility of

Report. the feasibility of Report on the feasibility of Additional Interconnection between India and Bangladesh Joint Technical Team (JTT) of India and Bangladesh July 2016 Contents 1.0 Background 1 2.0 Additional power export to

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 TRANSMISSION SECTOR GROWTH HIGHLIGHTS Source - POWERLINE Transmission line length

More information

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region 1.0 Applications for Connectivity and Long Term (Open) Access. Applications for grant of Connectivity

More information

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1 TRANSMISSION CAPACITY ADDITION PROGRAMME DURING 2006-07 Sl. No. Contents Page No. 1 Introduction 1 2 Chapter 1 Transmission Capacity Additions During 2005-06 of 10 th plan period 3 Chapter 2 Construction

More information

HIGH CAPACITY POWER TRANSMISSION CORRIDOR

HIGH CAPACITY POWER TRANSMISSION CORRIDOR HIGH CAPACITY POWER TRANSMISSION CORRIDOR - PROJECT INCEPTION REPORT Power Grid Corporation of India Ltd. Gurgaon BACKGROUND 1. Pursuant to the introduction of Long Term Open Access (LTOA) in the inter-state

More information

PRAGATI ENGINEERING COLLEGE

PRAGATI ENGINEERING COLLEGE Report on Industrial Visit to Power Grid 765/400 KV (GIS) Sub-Station No. of days of Visit : Two days Date(s) of Visit : 19 th September, 2017& 7 th October, 2017 Faculty In-charges : 4 Members 1. Mr.S.Ashokreddy,

More information

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority ,.,.;i')!i,:;;',;~~~. 'ffrff mm I Government of India ~ ~.I Ministry of Power 4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority III ~~~~~~I"1",~~1 ;J' :. r System Planning & Project Appraisal Division

More information

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden Conference-1 Latest Technologies in T & D, Renewable Energy Integration, Smart Grid, Energy Efficiency, Communication Next Generation of UHVDC System R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC

More information

Indian Power System Framework

Indian Power System Framework R P SASMAL 1 ST JUNE 2016 Indian Power System Framework Electricity - A Concurrent Subject Both Central & State Govt. are responsible for overall development of Power Sector Generators Central Level Central

More information

Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region

Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region a) Power Supply to M/s Noida Power Company Limited (NPCIL) NPCL has applied to CTU for connectivity for

More information

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in Website: www.mercindia.org.in

More information

HVDC Multi-Terminal Interconnections a viable and optimal solution for India

HVDC Multi-Terminal Interconnections a viable and optimal solution for India Presented at Cigré 2000 Conference, Paris, France, Aug/Sept 2000 HVDC Multi-Terminal Interconnections a viable and optimal solution for India K.M.Saxena Dr. Channakeshava Mata Prasad* Dr.R.P.Bhatele Dr.

More information

Smart Grid Initiatives in EHV Transmission in Indian Power Sector

Smart Grid Initiatives in EHV Transmission in Indian Power Sector Smart Grid Initiatives in EHV Transmission in Indian Power Sector Presentation by N. S. Sodha General Manager (Incharge) Load Despatch & Communication Department 1 Presentation Flow EHV Transmission in

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007 KERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION No.1/1/KSERC-2006/ Dated, Thiruvananthapuram 6 th August,2007 KSERC (Supply of Power from Captive Generating Plants to Distribution Licensees)

More information

1. Confirmation of the minutes of 19th meeting of the Standing Committee on Transmission system Planning held on at Amritsar, Punjab.

1. Confirmation of the minutes of 19th meeting of the Standing Committee on Transmission system Planning held on at Amritsar, Punjab. Agenda note for 20 th Standing Committee Meeting for planning of transmission system of Northern Region 1. Confirmation of the minutes of 19th meeting of the Standing Committee on Transmission system Planning

More information

Bangladesh s Power Sector : At a Glance

Bangladesh s Power Sector : At a Glance Bangladesh s Power Sector : At a Glance December, 2014 Installed Capacity (MW) : 10,709 De-rated Capacity (MW) : 10,130 Maximum Generation (MW) : 7,418 Total Consumers (in Million) : 15.4 Transmission

More information

SOLAR PV INTEGRATION: ISSUES & CHALLENGES with NET METERING

SOLAR PV INTEGRATION: ISSUES & CHALLENGES with NET METERING SOLAR PV INTEGRATION: ISSUES & CHALLENGES with NET METERING A.K. Bohra Chief Executive Officer NESCO, WESCO & SOUTHCO Central Service Office, Bhubaneswar DISTRIBUTED RENEWABLE ENERGY GENERATION With the

More information

ABB Next Level Big shift in power attractive opportunities

ABB Next Level Big shift in power attractive opportunities Bernhard Jucker and Claudio Facchin, Capital Markets Day, London, ABB Next Level Big shift in power attractive opportunities Slide 1 Agenda Profitably growing ABB s power business Shifting the center of

More information

Draft National Electricity Plan

Draft National Electricity Plan Draft National Electricity Plan (Volume - II) Transmission [In fulfilment of CEA s obligation under section 3(4) of the Electricity Act 2003] Government of India Ministry of Power Central Electricity Authority

More information

SOLAR PLANT PERFORMANCE IN INDIA

SOLAR PLANT PERFORMANCE IN INDIA Now Available SOLAR PLANT PERFORMANCE IN INDIA 2017-18 Report (PDF) Data-set (Excel) India Infrastructure Research SOLAR PLANT PERFORMANCE IN INDIA 2017-18 Table of Contents 1. Solar Power Sector Overview

More information

Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India

Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India Infrastructure Revitalization in India Power System Operation Corporation (POSOCO) New Delhi, India 26th March 2014 Infrastructure Revitalization in India 1 Outline Indian Power System Indian Grid - WAMS

More information

Minutes of 6 th Joint Co-ordination Meeting of IPPs granted LTA in ER held on at CC, POWERGRID

Minutes of 6 th Joint Co-ordination Meeting of IPPs granted LTA in ER held on at CC, POWERGRID Minutes of 6 th Joint Co-ordination Meeting of IPPs granted LTA in ER held on 26.0.20 at CC, POWERGRID. The 6 th meeting of the Joint Co-ordination Committee of IPPs in ER was held at POWERGRID Office,

More information

Agenda Note for Standing Committee Meeting of Power System Planning in ER

Agenda Note for Standing Committee Meeting of Power System Planning in ER Agenda Note for Standing Committee Meeting of Power System Planning in ER 1.0 Confirmation of the minutes of the meeting held at NRPC, New Delhi on 28.12.2010. Minutes of the Standing Committee Meeting

More information

Agenda Note for 28 th meeting of the Standing Committee on Power System Planning of Northern Region

Agenda Note for 28 th meeting of the Standing Committee on Power System Planning of Northern Region Agenda Note for 28 th meeting of the Standing Committee on Power System Planning of Northern Region 1. Confirmation of minutes of 27th meeting held on 30.5.2009 1.1 Minutes of 27 th meeting was circulated

More information

2015 Grid of the Future Symposium

2015 Grid of the Future Symposium 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http ://www.cigre.org 2015 Grid of the Future Symposium Flexibility in Wind Power Interconnection Utilizing Scalable Power Flow Control P. JENNINGS,

More information

The Electric Power System

The Electric Power System The Electric Power System INDIA Indian Power System 1 2 Basic facts Area:3.288 million km² Population:1.25 Billion Electricity consumers: 216 Million- (31.3.2013) Number of TSOs: 14- (31.3.2013) Numbe

More information

Power Sector Trends: Focus on States

Power Sector Trends: Focus on States Power Sector Trends: Focus on States Japan-India Climate Policy Research Workshop December 2017 Dr. Kartikeya Singh Deputy Director and Fellow Wadhwani Chair in U.S.-India Policy Studies CSIS ksingh@csis.org

More information

Transmission Line Survey

Transmission Line Survey Transmission Line Survey Name of the Project Owner / Client Scope of Work Type of Survey Instrument & Software tools used Schedule Time of Completio n Year of Completion Letter of Award for "Rate Contract"

More information

SAIREC Panel Discussion

SAIREC Panel Discussion Text SAIREC Panel Discussion Cape Town 04-Oct-2015 Unlocking Grid Capacity for the Energy Mix Proposed in the IRP Cape Town International Convention Centre Sunday, 04 October 2015, 11:30 for 13:00 Highlights

More information

(i) Establishment of 400kV Pooling Station at Fatehgarh (with a provision to upgrade at 765kV level)

(i) Establishment of 400kV Pooling Station at Fatehgarh (with a provision to upgrade at 765kV level) Annex-I Corrigendum to Minutes of the 36 th meeting of the Empowered Committee on Transmission held on 26 th July, 2016 at 3:30 PM at Conference Room of CEA, 2 nd Floor, Sewa Bhawan, R.K. Puram, New Delhi

More information

Electricity industry structure and capacity growth trends

Electricity industry structure and capacity growth trends Electricity industry structure and capacity growth trends Restructuring since 1997 has resulted in the separation of electricity generation from transmission and distribution. However, the sector continues

More information

Agenda Note for Long Term Open Access Applications of New Generation in Southern Region

Agenda Note for Long Term Open Access Applications of New Generation in Southern Region Agenda Note for Long Term Open Access Applications of New Generation in Southern Region EXECUTIVE SUMMARY 1. Long Term Open Access Applications POWERGRID has received following Long Term Open Access applications

More information

-As per List enclosed- 27 th meeting of the Standing Committee on Power System Planning of

-As per List enclosed- 27 th meeting of the Standing Committee on Power System Planning of स खय /No. 1/9/08-SP&PA/ भ रत सरक र/Government of India क य वध त धकरनण/Central Electricity Authority णल आय जन एव पर य जन म य कनण भ ग/SP&PA Division आर क प रम/R.K. Puram नई द ल /New Delhi -110606 [आई आई.एस

More information

Thereafter, the agenda items were taken up.

Thereafter, the agenda items were taken up. The Summary record of the 21 st meeting of Standing Committee held at NRPC Conference Room, Katwaria Sarai, Delhi on 03 rd November 2006. (1) List of the participants is annexed. CE SP&PA, CEA welcomed

More information

Analysis of Indian electricity distribution systems for integration of high shares of rooftop PV By Joerg Gaebler, IGEN Solar, GIZ India

Analysis of Indian electricity distribution systems for integration of high shares of rooftop PV By Joerg Gaebler, IGEN Solar, GIZ India Analysis of Indian electricity distribution systems for integration of high shares of rooftop PV By Joerg Gaebler, IGEN Solar, GIZ India Seite 1 Key technical question: How much distributed PV can be integrated

More information

Renewable Energy Integration: Wind, Solar and Energy Storage

Renewable Energy Integration: Wind, Solar and Energy Storage Renewable Energy Integration: Wind, Solar and Energy Storage ReGen Powertech Archit Khemka Technology Overview: Wind Solar Hybrid with Energy Storage Concepts Co-located System Two largely independent

More information

STATUS OF CROSS BORDER TRADE AND ENERGY MARKET NEPAL-INDIA EXCHANGE

STATUS OF CROSS BORDER TRADE AND ENERGY MARKET NEPAL-INDIA EXCHANGE STATUS OF CROSS BORDER TRADE AND ENERGY MARKET NEPAL-INDIA EXCHANGE South Asia Regional Workshop on Policies and Regulations to Increase Cross Border Energy Trade ( February 15-17,2012; New Delhi) RAM

More information

Frequently Asked Questions for Grid Connected Solar Rooftop Systems

Frequently Asked Questions for Grid Connected Solar Rooftop Systems Frequently Asked Questions for Grid Connected Solar Rooftop Systems 1. What is a Solar Rooftop System? In a solar rooftop system, the solar panels are installed in the roof of any residential, commercial,

More information

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, 2015- DRAFT 1. PREAMBLE 1.1 To harness the potential of renewable energy resources in the state, Government of Madhya Pradesh

More information

The SAARC Power Grid Nepal s Perspective

The SAARC Power Grid Nepal s Perspective The SAARC Power Grid Nepal s Perspective Anil Rajbhandary Director, Power Trade Department, NEA Medium Term Vision for Energy Connectivity in the SAARC Region 10 March, 2015; Islamabad Energy Resources

More information

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016 The role of Transmission System Operator in Belgium and in Europe Vlerick Alumni Event 26 January 2016 Agenda Introduction Infrastructure management Controlling the system Developing the EU Market 1/25/2016

More information

Enhancement of Power Transfer Capability of Existing 400kV Transmission Lines

Enhancement of Power Transfer Capability of Existing 400kV Transmission Lines 558 NATIONAL POWER SYSTEMS CONFERENCE, NPSC 22 Enhancement of Power Transfer Capability of Existing 4kV Transmission Lines Rajiv Gandhi, Anish Anand, Y. K. Sehgal, M. Krishnakumar and Anand Mohan Abstract--The

More information

An Overview to HVDC links in India

An Overview to HVDC links in India I J C International Journal of lectrical, lectronics ISSN No. (Online) : 77-66 and Computer ngineering (1): 94-98(013) An Overview to HVDC links in India Prof. Kusum Tharani, Aahuti Gupta and Apoorva Gupta

More information

9 ;J;;fzr;:;/=a ~ Central Electricity Authority ~ ~ ~ ~ ~ ~ 0TI g Western Regional Power Committee ISO:

9 ;J;;fzr;:;/=a ~ Central Electricity Authority ~ ~ ~ ~ ~ ~ 0TI g Western Regional Power Committee ISO: 'fff«fmq)f{ 9 ;J;;fzr;:;/=a 0TI g 9001-2008 0flllI -3, Iff;r, 0imt ( ), - 400 093 F-3, MIDe Area, Andheri (East), Mumbai - 400 093 Phone: 022-28221636; 28221681; 28220194-6; Fax: 022-28370193 Ref: no:

More information

RPO-REC Framework: Emerging Challenges and way forward. Background Presentation

RPO-REC Framework: Emerging Challenges and way forward. Background Presentation RPO-REC Framework: Emerging Challenges and way forward Background Presentation Ashwin Gambhir, Vishal Toro, Vijaypal Singh Prayas (Energy Group), Pune 10 th June, 2013, IHC, New Delhi Prayas Energy Group,

More information

Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner

Sub : In the matter of determination of Parallel Operation Charges. MPERC, Bhopal - Petitioner MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION, BHOPAL Sub : In the matter of determination of Parallel Operation Charges. Suo-Motu Petition No. 73/2012 ORDER (Date of order 31 st December, 2012) MPERC,

More information

Following are the growth rates of each sub segment of the auto sector over the last 5 years:

Following are the growth rates of each sub segment of the auto sector over the last 5 years: Sector Auto Components Industry Project Title Tyres Manufacturing Plant Project Description The Auto sector contributes 4.2% to India s GDP. The Indian automobile industry stood at 11 million vehicles

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Grid Stability Analysis for High Penetration Solar Photovoltaics

Grid Stability Analysis for High Penetration Solar Photovoltaics Grid Stability Analysis for High Penetration Solar Photovoltaics Ajit Kumar K Asst. Manager Solar Business Unit Larsen & Toubro Construction, Chennai Co Authors Dr. M. P. Selvan Asst. Professor Department

More information

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna 800 021 ------------------------------------------------------------------------------------------------------------- ROOFTOP

More information

The Grid Link Project. Summary of the Report for the Independent Expert Panel

The Grid Link Project. Summary of the Report for the Independent Expert Panel The Grid Link Project Summary of the Report for the Independent Expert Panel Who are EirGrid - and what do we do? EirGrid is responsible for a safe, secure and reliable supply of electricity: now and in

More information

Protective firing in LCC HVDC: Purposes and present principles. Settings and behaviour. V. F. LESCALE* P. KARLSSON

Protective firing in LCC HVDC: Purposes and present principles. Settings and behaviour. V. F. LESCALE* P. KARLSSON 21, rue d Artois, F-75008 PARIS B4-70 CIGRE 2016 http : //www.cigre.org Protective firing in LCC HVDC: Purposes and present principles. Settings and behaviour. V. F. LESCALE* P. KARLSSON VILES Consulting

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Innovative technologies ready for the Supergrid

Innovative technologies ready for the Supergrid Innovative technologies ready for the Supergrid The Roadmap to the Supergrid Technologies EEF lunchtime discussion Feb 6, 2013 in Strasbourg Presented by Dr. Magnus Callavik, ABB (Convenor of WG 2 - Technology)

More information

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2013 Grid of the Future Symposium Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate

More information

FAX : Member Secretary Southern Regional Power Committee 29, Race Course Cross Road Bangalore FAX :

FAX : Member Secretary Southern Regional Power Committee 29, Race Course Cross Road Bangalore FAX : Distribution List : 1. Shri Ravinder Member (Power Systems) Central Electricity Authority Sewa Bhawan, R K Puram New Delhi-110 066 FAX : 011-26102045 3. CEO POSOCO B-9, Qutab Institutional Area Katwaria

More information

Utility Operator Model

Utility Operator Model Mini-Grid Policy Toolkit- Case Study Country: KENYA Project: Rural electrification with governmentrun mini-grids Utility Operator Model Project Summary Site map of Kenyan mini-grid locations (red dots)

More information

Guidelines for Solar Grid Power Projects

Guidelines for Solar Grid Power Projects Guidelines for Solar Grid Power Projects NTPC Ltd. NTPC Vidyut Vyapar Nigam Ltd. AGENDA 1 2 3 NTPC / NVVN at a glance Broad Guidelines for Selection of Solar Power Developers Elements of PPA NTPC Limited

More information

Minutes of the 37 th Meeting of Standing Committee on Power System Planning in Western Region held on at Mumbai

Minutes of the 37 th Meeting of Standing Committee on Power System Planning in Western Region held on at Mumbai 545-558 Minutes of the 37 th Meeting of Standing Committee on Power System Planning in Western Region held on 5-09-2014 at Mumbai 1.0 The 37 th meeting of the Standing Committee on Power System Planning

More information

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM 1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.

More information

Policy & Regulatory Issues : Solar & Wind. Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014

Policy & Regulatory Issues : Solar & Wind. Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014 Policy & Regulatory Issues : Solar & Wind Shri Rajinder Kumar Kaura CMD, Bergen Group India 21 st August 2014 About Us Vision To develop a solution with low cost, high technology power generation & fulfill

More information

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION REGISTERED NO. PT.-40 The B Bihar Gazett te EXTRA ORDINARY PUBLISHED BY AUTHORITY 16 AASHAADHA, 1937(S) (NO.PATNA 737) PATNA, TUESDAY, 7 TH JULY 2015 BIHAR ELECTRICITY REGULATORY COMMISSION NOTIFICATION

More information

Before the. Case No. 106 of 2009

Before the. Case No. 106 of 2009 Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in

More information

Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh

Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh mohammad_alauddin4124@yahoo.com December 19, 2013 Total area

More information

Power Distribution Tariffs in India 2016 Discom Wise & Consumer Wise Comprehensive Track

Power Distribution Tariffs in India 2016 Discom Wise & Consumer Wise Comprehensive Track Power Distribution Tariffs in India 2016 Discom Wise & Consumer Wise Comprehensive Track E-REP Fact Factor Series March 2016 INR/Month INR/Month Power Distribution Tariffs in India 2016 2 CERC Final tariff

More information

160 MW Solar-Wind Hybrid project with BESS at Ramgiri, Andhra Pradesh

160 MW Solar-Wind Hybrid project with BESS at Ramgiri, Andhra Pradesh Presentation on 160 MW Solar-Wind Hybrid project with BESS at Ramgiri, Andhra Pradesh by Solar Energy Corporation of India Ltd. Feb 3, 2019 2 February 2019 Solar Energy Corporation of India Ltd 1 Indian

More information

Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05.

Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05. Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05. 1. List of the participants is enclosed at Annex - I. Member (PS) CEA welcomed

More information

MANHARI SOLAR. (Your own renewable energy management experts)

MANHARI SOLAR. (Your own renewable energy management experts) MANHARI SOLAR (Your own renewable energy management experts) 100% Accelerated Depreciation Assured Returns (15-40% IRR) Quick Payback Period No Recurring Cost Absolutely No Pollution Reduced Carbon Footprint

More information

Raising the bar. UHV switchgear and components

Raising the bar. UHV switchgear and components Raising the bar UHV switchgear and components Walter Holaus, Michael Lane, Richard Thomas The reliable supply of electrical energy is a backbone of the modern economy. Its ability to operate safely and

More information

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2

More information

SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION

SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION SMART DIGITAL GRIDS: AT THE HEART OF THE ENERGY TRANSITION SMART DIGITAL GRIDS For many years the European Union has been committed to the reduction of carbon dioxide emissions and the increase of the

More information

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION Summary Abhay Kumar Mata Prasad R C Maheshwari Asea Brown Boveri Ltd. 4th Floor, 71 Nehru Place, New Delhi

More information

In-House Paper on the implementation of Single Part Tariff in Power Distribution

In-House Paper on the implementation of Single Part Tariff in Power Distribution December 9, 2016 In-House Paper on the implementation of Single Part Tariff in Power Distribution Background: Tariff Introduction: Tariff is the price Structure at which electricity is sold to the consumers.

More information

~ ~ ~1~ctJ'{UI. 2 ~ ~, 9 ct>1~4i<'1ct> ~ (~~~I~~), ~, ~ 1iif, ~ ~\j\)~q~'1 ~ ct>1~~~, ~-8, ~-24, ~ ~ ~ ~ ~.

~ ~ ~1~ctJ'{UI. 2 ~ ~, 9 ct>1~4i<'1ct> ~ (~~~I~~), ~, ~ 1iif, ~ ~\j\)~q~'1 ~ ct>1~~~, ~-8, ~-24, ~ ~ ~ ~ ~. .,.. -- ~~ ~ ~ ~1~ctJ'{UI ~ ~ ~ 4~~1\J1"11 ~iifi"f ~ "flqr oqq;f,,{i~~wi~,{~, "fi ~ 110066 "(p"'~. : 26/10/2011-~. m. ti. 1!./~& ~.s-;j ~: 20.01.2011 1 ~ ~~), 8 I ~~~~, ~3TftfItffi ~), ~ ~ ~, ~ ~ ct>ix41~~11

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

northeast group, llc India Smart Grid: Market Forecast ( ) January group.com

northeast group, llc India Smart Grid: Market Forecast ( ) January group.com northeast group, llc India Smart Grid: Market Forecast (2015 2025) January 2015 www.northeast- group.com India Smart Grid: Market Forecast (2015 2025) In many ways, India represents the best smart grid

More information

Case No. 109 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

Case No. 109 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd. Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Michigan Thumb Loop Transmission Line Project

Michigan Thumb Loop Transmission Line Project Michigan Thumb Loop Transmission Line Project ITC Holdings Corp. Simon Whitelocke VP., Regulatory and External Affairs October 30, 2013 What is Transmission? The electric transmission system is the network

More information

Nepal Power Investment Summit Transmission Line Projects

Nepal Power Investment Summit Transmission Line Projects Nepal Power Investment Summit 2016 Transmission Line Projects Presented By: Mr. Kanhaiya Kumar Manandhar Deputy Managing Director Transmission Directorate Nepal Electricity Authority SYSTEM AT A GLANCE

More information

Fuel Cells and Hydrogen 2 Joint Undertaking (FCH 2 JU) Frequently Asked Questions

Fuel Cells and Hydrogen 2 Joint Undertaking (FCH 2 JU) Frequently Asked Questions Fuel Cells and Hydrogen 2 Joint Undertaking (FCH 2 JU) Frequently Asked Questions Background information: The Fuel Cells and Hydrogen Joint Undertaking was established in 2008-2013, as the first publicprivate

More information

Case No. 163 of In the matter of

Case No. 163 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

DG system integration in distribution networks. The transition from passive to active grids

DG system integration in distribution networks. The transition from passive to active grids DG system integration in distribution networks The transition from passive to active grids Agenda IEA ENARD Annex II Trends and drivers Targets for future electricity networks The current status of distribution

More information

EUCL AMI Project Experience Share

EUCL AMI Project Experience Share EUCL AMI Project Experience Share James Musoni--Project Manager of Revenue Protection Program(RPP) EUCL COMPANY S STRUCTURE 2 General power system planning Energy infrastructure projects development Electricity

More information

STATE LOAD DISPATCH CENTRES (SLDC)

STATE LOAD DISPATCH CENTRES (SLDC) ACTIVITIES OF SLDC STATE LOAD DISPATCH CENTRES (SLDC) **The State Load Despatch Centre:- As per section 33 of Electricity Act - 2003 (Central Act 36 of 2003), SLDC performs powers as defined below:- SLDC

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

Nordic co-operation when meeting System challenges

Nordic co-operation when meeting System challenges Nordic co-operation when meeting System challenges Evolving the market conference Ulla Sandborgh CEO Agenda > System challenges > System development plan > Strategies > Grid development > Tariff development

More information

Intra-State Availability Based Tariff (ABT)

Intra-State Availability Based Tariff (ABT) Intra-State Availability Based Tariff (ABT) What is ABT? 1. In Year 2000, the CERC revised the tariff structures of inter- state generators from drawal-based tariffs to ABT to discipline grid operations.

More information

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES 1 PRESENTATION OUTLINE Generation System Demand Outlook Existing Generation Resources Transmission System National Interconnected

More information

best to you all Gail Carbiener Page 1 of 5

best to you all Gail Carbiener Page 1 of 5 Please accept this attachment as my up dated response to the B2H DEIS. If this is not acceptable, please let me know. Nice meeting last Monday in Boardman. 300316 best to you all Gail Carbiener 2 Page

More information

Estimating the cost of electrification technology options to aid electricity access scale up: The case of Ghana

Estimating the cost of electrification technology options to aid electricity access scale up: The case of Ghana The African Electrification Initiative Practitioner Workshop, Dakar, Senegal November 14 th 16 th, 2011 Estimating the cost of electrification technology options to aid electricity access scale up: The

More information

Battery Energy Storage System Pilot Project, Puducherry Power Grid Corporation of India Limited. Manish Kumar Tiwari

Battery Energy Storage System Pilot Project, Puducherry Power Grid Corporation of India Limited. Manish Kumar Tiwari Battery Energy Storage System Pilot Project, Puducherry Power Grid Corporation of India Limited Manish Kumar Tiwari POWERGRID An Overview CENTRAL TRANSMISSION UTILITY A NAVARATNA COMAPANY CPSU CONSISTENTLY

More information

Presentation of the European Electricity Grid Initiative

Presentation of the European Electricity Grid Initiative Presentation of the European Electricity Grid Initiative Contractors Meeting Brussels 25th September 2009 1 Outline Electricity Network Scenario European Electricity Grids Initiative DSOs Smart Grids Model

More information

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat Galapagos San Cristobal Wind Project VOLT/VAR Optimization Report Prepared by the General Secretariat May 2015 Foreword The GSEP 2.4 MW Wind Park and its Hybrid control system was commissioned in October

More information

GRID-INTERACTIVE SPV ROOFTOP PLANTS: AN OPTION FOR INDIA GROWING ENERGY DEMAND

GRID-INTERACTIVE SPV ROOFTOP PLANTS: AN OPTION FOR INDIA GROWING ENERGY DEMAND GRID-INTERACTIVE SPV ROOFTOP PLANTS: AN OPTION FOR INDIA GROWING ENERGY DEMAND Prashant Kumar Tayal 1, NeeruGoyal 2, Rajveer Singh 3, Prashant Vats 4 1,4 Faculty, Department of Electrical Engineering,

More information

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out

More information