Cranes and Derricks. Objectives. Construction Safety Lecture 18
|
|
- Alberta Booth
- 5 years ago
- Views:
Transcription
1 North Carolina State University Department of Civil, Construction, and Environmental Engineering Construction Safety Lecture 18 North Carolina State University Cranes and Derricks Subpart N Cranes and Derricks 29 CFR Objectives This presentation will address: OSHA s minimum requirements for cranes in construction. Setup, operation, and inspection of cranes. Hazard identification. Abatement methods. 1
2 General Requirements (a)(1) Employer must comply with manufacturer s specifications and limitation applicable to operation of cranes. General Requirements (a)(1) Attachments used with cranes must not exceed the capacity, rating, or scope recommended by the manufacturer. General Requirements (a)(2) Rated load capacities must be conspicuously posted on all equipment and visible to the operator at his control station. 2
3 General Requirements (a)(5) Competent person must inspect machinery and equipment prior to use. Deficiencies must be repaired or defective parts replaced before use. General Requirements (a)(6) Thorough annual inspection of hoisting machinery must be made by competent person, or US DOL recognized accredited agency. 3
4 General Requirements (a)(6) Record of dates and results of inspection must be maintained. General Requirements (a)(7) Wire rope taken out of service when: Running ropes 6 randomly broken wires in one lay or 3 broken wires in one strand in one lay. Wear, kinking, crushing, bird caging, heat damage. Standing ropes 2 broken wires in one lay or 1 broken wire at an end connection. General Requirements (a)(8) Moving parts or equipment must be guarded if exposed parts can be contacted by employees. 4
5 General Requirements (a)(9) Accessible areas within the swing radius of the rotating superstructure must be barricaded. Prevent employee from being struck or crushed by the crane. 5
6 General Requirements (a)(12) Windows in cabs must be safety glass or equivalent. No visible distortion that will interfere with safe operation of the machine. General Requirements (a)(13)(i) A ladder or steps must be provided to give access to a cab roof where necessary for rigging or service requirements. 6
7 General Requirements (a)(13)(ii) Guardrails, handholds, and steps must be provided on cranes for easy access to the cab. Must conform to ANSI B General Requirements (a)(14)(i) Fire extinguisher of 5BC rating, or higher, must be available at operator station or cab of equipment. General Requirements (a)(14)(ii) All fuels must be transported, stored, and handled in accordance with Subpart F [Fire Protection and Prevention] of this part. 7
8 General Requirements (a)(15) Precautions must be taken to prevent equipment from physical contact with electrical distribution and transmission lines. General Requirements (a)(15) Clearance between lines and any part of crane or load: 10 ft. 50 kv. Or less. 10 ft in. for each 1 kv. over 50 kv. Person designated to observed clearances where necessary. General Requirements (a)(15) In transit with no load and boom lowered, clearance must be a minimum of: 4 ft. less than 50 kv. 10 ft. over 50 kv. and up to 345 kv. 16 ft. voltages up to and including 750 kv. 8
9 General Requirements (a)(16) No modification or additions which affect the capacity or safe operation of the equipment must be made without the manufacturer s written approval. 9
10 General Requirements (a)(19) Employees must be kept clear of loads to be lifted and of suspended loads. Crawler, Locomotive, and Truck Cranes (b)(1) Jibs must have positive stops to prevent movement of more than 5 deg. above the straight line of the jib and boom. Cable type belly slings do not constitute compliance with rule. Jib Stops Belly Slings 10
11 Crawler, Locomotive, and Truck Cranes (b)(2) Crawler, truck and locomotive cranes must meet the requirements for design, inspection, construction, testing, maintenance and operation as outlined in ANSI B
12 Crawler, Locomotive, and Truck Cranes (b)(2) Controls used during normal crane operating cycle must be located within easy reach of operator. Functions of controls must be clearly identified. 12
13 Crawler, Locomotive, and Truck Cranes (b)(2) Cranes must not be loaded beyond the rated capacity of its existing configuration. Crawler, Locomotive, and Truck Cranes (b)(2) Employees must not be allowed to ride on the hook or load. Crawler, Locomotive, and Truck Cranes (b)(2) Operator must not leave his position at the controls while the load is suspended. 13
14 Crawler, Locomotive, and Truck Cranes (b)(2) When the load being handled require the use of outriggers the outriggers must be fully extended and set to remove weight from wheels. Except for locomotive cranes. Crawler, Locomotive, and Truck Cranes (b)(2) Outriggers must be used when load being handled at particular radius exceeds rated load without outriggers as given by manufacturer. Crawler, Locomotive, and Truck Cranes (b)(2) Outrigger floats must be attached to the outriggers. When required blocking under outrigger floats. 14
15 15
16 Crawler, Locomotive, and Truck Cranes (b)(2) Good housekeeping is required in the cab of cranes. Clothing, tools, and other articles must be stored so as not to interfere with access or operation. Hammerhead Tower Cranes Hammerhead Tower Cranes (c)(1) Adequate clearance must be maintained between moving and rotating structures of the crane and fixed objects. 16
17 Hammerhead Tower Cranes (c)(2) Employees performing duties on horizontal booms must be protected against falling by guardrails or personal fall arrest system. Hammerhead Tower Cranes (c)(5) All hammerhead tower cranes must meet the requirements prescribed by the manufacturer: Design Construction Installation Testing Maintenance Inspection Operation Overhead and Gantry Cranes (d) Rated load marked on each side of the crane. Bridge trucks equipped with rail sweeps. Audible warning signal for crane equipped with traveling mechanism. Meet the requirements of ANSI B Design, construction, installation, testing, maintenance, inspection, and operation. 17
18 Derricks (e) Must meet the requirements of ANSI B , Safety Code for Derricks. Design, construction, installation, testing, maintenance, inspection, and operation. Floating Cranes and Derricks (f)(1)(i) The rated load of a mobile crane, mounted on a barge, must not exceed the original capacity specified by manufacturer. 18
19 Floating Cranes and Derricks (f)(1)(i) & (ii) Load rating chart provided and located where easily visible to operator. When load rating reduced for list of barge new load rating chart must be provided. Floating Cranes and Derricks (f)(1)(iv) Mobile cranes on barges must be positively secured. Note: letter of interpretation [1/27/94] registered professional engineer certifies movement of crane will not compromise stability of barge. 19
20 Floating Cranes and Derricks (f)(2)(i),(ii),(iii) Permanently mounted crane on barge capacity and limitations based on competent design criteria. Load rating chart visible to operator. Meet requirements of manufacturer. Crane or Derrick Suspended Personnel Platforms (g)(1)(i) Standard applies to design, construction, testing, use and maintenance of personnel platform. Applies to hoisting of platforms on load lines of cranes or derricks. 20
21 Crane or Derrick Suspended Personnel Platforms (g)(3)(i)(D) Crane must be uniformly level within one percent of level grade and located on firm footing. Outriggers must be fully deployed following manufacturer s recommendation. Crane or Derrick Suspended Personnel Platforms (g)(3)(ii)(A) Cranes and derricks with variable angle booms must be equipped with a boom angle indicator visible to operator. Crane or Derrick Suspended Personnel Platforms (g)(3)(ii)(c) Crane or derrick must be equipped with an anti-twoblocking device. 21
22 Crane or Derrick Suspended Personnel Platforms (g)(4)(i)(A) Designed by a qualified engineer or person competent in structural design. Trial lift with the platform unoccupied. Visual inspection conducted by competent person. Crane or Derrick Suspended Personnel Platforms (g)(4)(iv)(B) Hooks on overhaul ball, lower load blocks, or other attachments must be type that can be closed and locked. Two instances: Personnel platforms. [ (g)(4)(iv)(B)] Steel erection/working under the load. [ (d)(2)(ii)] 22
23 Crane or Derrick Suspended Personnel Platforms (g)(6)(vii) & (viii) Except over water, employees inside platform must use a body belt/harness system. Attached to lower load block or structural member of the platform. No lifts made on crane s other loadlines while personnel suspended on a platform. Retractable reels Any Crane Questions??? 23
24 Thank You NC-LABOR 24
LIFTING/MOBILE EQUIPMENT CRANES AND DERRICKS. Steingass Mechanical Contracting, Inc. 754 Progress Drive Medina, Ohio (330)
LIFTING/MOBILE EQUIPMENT CRANES AND DERRICKS Steingass Mechanical Contracting, Inc. 754 Progress Drive Medina, Ohio 44256 (330) 725-6090 CRANES AND DERRICKS INTRODUCTION The Occupational Safety and Health
More information1 Clearheart Construction Co., Inc. Mobile Crane - Onshore MOBILE CRANES Cranes and derricks
Mobile Crane - Onshore MOBILE CRANES Cranes and derricks. - 1926.550 Cranes, like all pieces of heavy equipment, if not properly operated, inspected and maintained have a potential for causing major bodily
More informationCranes. OSHA Office of Training & Education 1
Cranes OSHA Office of Training & Education 1 Major Causes of Crane Accidents Contact with power lines Overturns Falls Mechanical failures OSHA Office of Training & Education 2 How Do Accidents Occur? Instability
More informationIn This Document MODULE DESCRIPTION This module provides information on the safety concerns and
Crane Safety Fact Sheet In This Document MODULE DESCRIPTION This module provides information on the safety concerns and Introduction necessary precautions you will need to be aware of when working Crane
More informationOVERHEAD & GANTRY CRANE / RIGGING
Overhead & Gantry Crane / Rigging OVERHEAD & GANTRY CRANE / RIGGING Overhead and gantry cranes - 1910.179 Crawler locomotive and truck cranes. - 1910.180 Slings. 1910.184 Cranes, like all pieces of heavy
More informationNote: under no circumstances will a carbon tetrachloride extinguisher be used.
Clearheart Construction Co., Inc. Mobile Crane / Overhead & Gantry Crane / Rigging CRANES & RIGGING Overhead and gantry cranes - 1910.179 Crawler locomotive and truck cranes 1910.180 Cranes and derricks.
More informationGreat Western Painting Crane Operator - Offshore CRANE OPERATOR - OFFSHORE
Crane Operator - Offshore CRANE OPERATOR - OFFSHORE Cranes, like all pieces of heavy equipment, if not properly operated, inspected and maintained have a potential for causing major bodily injury or property
More informationMaterial Handling - Cranes, Hoists, Slings, Chain Falls, and Ratchet Hoists
Material Handling - Cranes, Hoists, Slings, Chain Falls, and Ratchet Hoists University Facilities Internal Procedure: July 1, 2013 Effective date: July 1, 2013 Last Modified: April 2013 Approved by: Bob
More informationHealth & Safety Policy and Procedures Manual SECTION 22 CRANE SUSPENDED PERSONNEL PLATFORMS
SECTION 22 CRANE SUSPENDED PERSONNEL PLATFORMS 1. Scope: This policy and procedure applies to the design, construction testing, use, and maintenance or personnel platforms and hosting of personnel platforms
More informationCrane & Derrick Operation Procedures for Construction
Safety & Health Program Crane & Derrick Operation Procedures for Construction 10627 Midwest Industrial Boulevard, St. Louis, MO Phone: 314-785-6425 Fax: 314-785-6426 The written Crane & Derrick Operation
More informationCRANE & HOIST SAFETY PROGRAM
CRANE & HOIST SAFETY PROGRAM 1.0 PURPOSE The purpose of the Crane and Hoist Safety Program is to: 1.1 Ensure a safe work environment for employees who operate, maintain, or work around cranes and hoists
More informationLiftcrane Boom Capacities 2250 SERIES 3
Liftcrane Capacities 2250 SERIES 3 No. 44 With Long Reach Top LIFTING CAPACITIES: Lifting capacities for various boom lengths and operating radii are for freely suspended loads and do not exceed 75% of
More informationMOBILE CRANES AND HOIST
MOBILE CRANES AND HOIST Applicable OSHA Standards: 29 CFR 1926.251, 1926.1400 PURPOSE SCOPE To provide a guideline for the safe operation, use and inspection of mobile cranes and hoist. This program applies
More informationMOBILE CRANES ONSHORE PROGRAM
Page: Page 1 of 10 Purpose Overhead cranes, hoists, and rigging equipment are used by SHECO Services employees for lifting and moving materials. In order to maintain a safe workplace for its employees,
More informationRigging - Offshore OFFSHORE CRANES API RP 2D Operation and Maintenance of Offshore Cranes
Clearheart Construction Co., Inc. Rigging - Offshore OFFSHORE CRANES API RP 2D Operation and Maintenance of Offshore Cranes Cranes, like all pieces of heavy equipment, if not properly operated, inspected
More informationChicago Crane Operator Examination Study Guide
Chicago Crane Operator Examination Study Guide This candidate guide should help you prepare for the Chicago Crane Operators licensure examinations. Part I contains general information about testing procedures.
More informationDEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR'S OFFICE GENERAL INDUSTRY SAFETY STANDARDS
DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR'S OFFICE GENERAL INDUSTRY SAFETY STANDARDS (By authority conferred on the general industry safety standards commission by sections 16 and 21 of Act
More informationChapter 22 Mobile Cranes
Chapter 22 Mobile Cranes Chapter 22 Mobile Cranes Purpose Overhead cranes, hoists, and rigging equipment are used by Hayward Electric employees for lifting and moving materials. In order to maintain a
More informationSHOP RIGGING & OVERHEAD HOIST SAFETY PROGRAM
Purpose & Scope CLIMATE ENGINEERS, INC. (CE) is dedicated to the protection of our employees from occupational injuries and illnesses. The purpose of this program is to provide procedures to be followed
More informationUNIVERSITY OF TOLEDO
UNIVERSITY OF TOLEDO SUBJECT: CRANE AND HOIST SAFETY PROGRAM Procedure No: S-08-024 PROCEDURE STATEMENT All crane and hoists operated on UT campuses must be adequately maintained and inspected as prescribed
More informationESSENTIAL SAFETY RESOURCES
ESSENTIAL SAFETY RESOURCES GS-3027 MOBILE CRANE / OVERHEAD AND GANTRY CRANE / RIGGING Originator: Safety Advisor s Signature: Type Name Approval: HSE Manager s Signature: Type Name Approval: Operations
More informationLiftcrane Boom Capacities 999 SERIES 2. Manitowoc Cranes, Inc.
Liftcrane Capacities No. 82 or 22EL LIFTING CAPACITIES: Lifting capacities for various boom lengths and operating radii are for freely suspended loads and do not exceed 75% of a static tipping load. Capacities
More informationOSHA PART 1: PREPARING FOR THE SESSION. 1. Training Booklet. 2. Why This Session Is Important. 3. Purpose and Objectives of the Session
Crane, Derrick, and ling afety 5145A OHA A R N I G N I PAR 1: PRPARING FOR H ION 1. raining Booklet here is no training booklet that goes along with this ession. rainers should review other written material
More informationCrane & Hoist Safety Guidelines
Purpose Crane & Hoist Safety Guidelines Many types of cranes, hoists, and rigging devices are used at [COMPANY] for lifting and moving materials. [COMPANY]'s policy is to maintain a safe workplace for
More informationPAGE 1 OF 5 HEALTH, SAFETY & ENVIRONMENTAL MANUAL PROCEDURE: S360 Overhead Cranes & Lifts Procedure REV 4.0 8/14/2012
PAGE 1 OF 5 PURPOSE: OVERHEAD CRANES AND LIFTS PROCEDURE The purpose of this procedure is to define the safety and training requirements for use of overhead cranes and lifts. Procedure: Definitions Designated
More informationMoving materials: Crane and hoist safety
Introduction... 1 Overhead and gantry cranes... 1 Introduction... 1 Crane components... 2 Markings and warnings 3 Loading components... 3 Load handling... 4 Crane inspections... 5 Frequent inspections...
More informationNewport News Shipbuilding Contractor Environmental, Health and Safety Resource Manual Cranes
Newport News Shipbuilding Contractor Environmental, Health and Safety Resource Manual Cranes Newport News Shipbuilding Page 1 CRANES 1. Hazard and Reference The use of cranes at NNS presents a serious
More informationMOBILE CRANE/OVERHEAD & GANTRY CRANE/RIGGING
Doc : SOP-44 Preparation: Safety Mgr Authority: CEO Issuing Dept: Safety Page: Page 1 of 12 Purpose Overhead cranes, hoists, and rigging equipment are used by RELIANT HOLDINGS LTD AND ITS AFFILIATES employees
More information2.0 Reference: 4.0 Applicability: TRF WORKS. 5.0 Responsibility :Contractors, Drivers of the equipment, shift Supervisor/Officers. 6.
Original Issue Date: Date of Revision : Page 1 follwed by 19 1.0 Purpose: To provide guidelines for safe handling of materials manually or by using moving machinery like Fork Lifts Trucks, Trailer EOT,
More informationChicago Crane Operators Examination Study Guide
Chicago Crane Operators Examination Study Guide Cranes and hoisting equipment with a rated capacity of 2,000 pounds or more require a licensed operator for use in the City of Chicago. This study guide
More informationSAFETY GUIDANCE MATERIAL
SAFETY GUIDANCE MATERIAL SAFETY OPERATIONS GUIDANCE MONDAY MARCH 23, 2015 This safety resource was written for the scrap industry by the scrap industry and was developed to assist you in making your scrap
More informationWOC LP. Manual. Standards WOC HSE. WO Executive. Section L003 - Lifting Operations DOCUMENT NO: WOC-HSE-ST & EP Department
/31... ' \.4., _ 4. if IL C WOC LP & EP Department WOC HSE Standards Manual DOCUMENT NO: WOC-HSE-ST-0001 Section L003 - Lifting Operations REV ISSUE PREPARED BY REVIEWED BY APPROVED BY ISSUE DATE * NaviA,&...)
More informationBUCKET TRUCK SAFETY EQUIPMENT
BUCKET TRUCK SAFETY EQUIPMENT Phone Number 800.222.4664 General Safety Guidelines - Safe Use of Bucket Trucks, Aerial Lifts) (Per OSHA Standard 1910.67, 1926.453) Definitions: An aerial device, by definition,
More informationTitle: Crane Operation Effective Date: 12/3/2014 Control Number: THG_0033 Revision Number: 2 Date: 10/22/2015 Annual Review Completed: 5/13/2015
Title: Crane Operation Effective Date: 12/3/2014 Control Number: THG_0033 Revision Number: 2 Date: 10/22/2015 Annual Review Completed: 5/13/2015 Crane Operations CONTENTS 1. PURPOSE 2. SCOPE 3. RESPONSIBILITIES
More informationLIFTING CHARTS - Conventional Truck Cranes AMERICAN MODEL TON CAPACITY
LIFTING CHARTS - Conventional Truck Cranes AMERICAN MODEL - 125 TON CAPACITY 1 LIFT RATINGS With Tubular Hammerhead and "K-F-L-M" Counterweight (34,000 lbs.) Min 11 82.8-91090 250000 250000 47 10 12 81.3-87730
More informationDEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY AND HEALTH STANDARD. Filed with the secretary of state on
DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY AND HEALTH STANDARD Filed with the secretary of state on These rules take effect immediately upon filing with the secretary
More informationCranes and Crane Operators and Construction Work
Cranes and Crane Operators and Construction Work Larry Markee, Crane Technical Specialist Department Of Labor and Industries Division of Occupational Safety and Health November 16, 2006 Objectives Review
More informationLIFTING CHARTS - Crawler Cranes AMERICAN MODEL TON CAPACITY
LIFTING CHARTS - Crawler Cranes AMERICAN MODEL 7260-100 TON CAPACITY 7260 1 LIFT RATINGS with Tubular Chord Hammerhead and "S-S" Counterweight (49,700 lbs.) (15,150 kg.) () From 11 82.8 200000 46 8 12
More informationTitle: Crane Operation Effective Date: 12/3/2014 Control Number: THG_0033 Revision Number: 2 Date: 10/22/2015 Annual Review Completed: 5/13/2015
Title: Crane Operation Effective Date: 12/3/2014 Control Number: THG_0033 Revision Number: 2 Date: 10/22/2015 Annual Review Completed: 5/13/2015 Crane Operations CONTENTS 1. PURPOSE 2. SCOPE 3. RESPONSIBILITIES
More informationSeries 1300 Hydraulic Crane 30 Ton Load Ratings
Series 13 Hydraulic Crane Ton Load Ratings! DANGER AN UNTRAINED OPERATOR SUBJECTS HIMSELF AND OTHERS TO DEATH OR SERIOUS INJURY YOU MUST NOT OPERATE THIS CRANE UNLESS You have been trained in the safe
More informationLIFTING CHARTS - Crawler Cranes AMERICAN MODEL TON CAPACITY
LIFTING CHARTS - Crawler Cranes AMERICAN MODEL 9310-225 TON CAPACITY 9310 1 LIFT RATINGS With Tubular and "S-S" Counterweight (135,000 Lbs.) 17 81.4-450,000 76 12 20 78.9-336,000 75 9 25 74.7 195,030 230,290
More informationSeries 1400 Hydraulic Crane 33 Ton Load Ratings
Series 1 Hydraulic Crane 33 Ton Load Ratings! DANGER AN UNTRAINED OPERATOR SUBJECTS HIMSELF AND OTHERS TO DEATH OR SERIOUS INJURY YOU MUST NOT OPERATE THIS CRANE UNLESS You have been trained in the safe
More informationSeries 1400A Hydraulic Crane 33 Ton
Series 1A Hydraulic Crane 33 Ton Load Ratings DANGER AN UNTRAINED OPERATOR SUBJECTS HIMSELF AND OTHERS TO DEATH OR SERIOUS INJURY YOU MUST NOT OPERATE THIS CRANE UNLESS You have been trained in the safe
More informationHEALTH AND SAFETY MANUAL
HEALTH AND SAFETY MANUAL Title: Crane & Hoist Safety - Onshore/Offshore Approved by: Greg Savoy Rev. 12/27/11 1 Purpose/Scope: Overhead cranes, hoists, and rigging equipment are used by Company employees
More information29 CFR Ch. XVII ( Edition)
1910.180 in paragraphs (c)(1) (ii) and (iii) of this section. Type of crane mounting Maximum load ratings (percent of tipping loads) Locomotive, without outriggers: Booms 60 feet or less... 1 85 Booms
More informationSTANDARDS PRESENTATION Attachment No. 1 TO Page 1 of 6 CALIFORNIA OCCUPATIONAL SAFETY AND HEALTH STANDARDS BOARD
TO Page 1 of 6 TITLE 8: Division 1, Chapter 4, Subchapter 4. Construction Safety Orders Article 12. Pile Driving and Pile Extraction [Notes in italics are editorial notes and generally refer to A10.19
More informationCrane Safety Resource Guide P AGE 1
Crane Safety Resource Guide P AGE 1 As a Home Builder, we do not self-perform any work. This section is a resource guide only and is not intended to put any requirements on the company. All subcontractors,
More information4600 SERIES 3 RINGER SERIES 2. Manitowoc Cranes, Inc. Manitowoc, Wisconsin U.S.A.
Liftcrane Capacities No. 35 thru 1 Degree Static Machine LIFTING CAPACITIES: Lifting capacities are for a RINGER when operating on a barge. Machine shall be positively secured to prevent shifting. Lifting
More informationCRANE, HOIST AND SLING SAFETY PROGRAM
CRANE, HOIST AND SLING SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR 1910.179 and 184 ANSI - B30.2 and 30.9 Crane Manufacturers Association of America 61 BASIS: The Occupational Safety and Health Administration
More informationSeries 1300A Hydraulic Crane 30 Ton Load Ratings
Series 13A Hydraulic Crane 3 Ton Load Ratings DANGER AN UNTRAINED OPERATOR SUBJECTS HIMSELF AND OTHERS TO DEATH OR SERIOUS INJURY YOU MUST NOT OPERATE THIS CRANE UNLESS You have been trained in the safe
More information40' ' POWERED BOOM: MODE 1 40' - 126' POWERED BOOM: MODE 2
Range Diagram and Lifting Capacity Cranes 100 TON LIFTING CAPACITY 40' - 97.3' POWERED BOOM: MODE 1 40' - 126' POWERED BOOM: MODE 2 CRANE WORKING CONDITIONS DIMENSIONS ARE FOR LARGEST FACTORY FUR- NISHED
More informationPURPOSE... 1 II. SCOPE... 2 III. REFERENCES... 2 IV. RESPONSIBILITIES...
Reed College 3203 Southeast Woodstock Blvd. Portland Oregon 97202-8199 Crane Safety Policy Effective Date: Revision Dates: February 9, 2011, June 25, 2012, July 2016 Review Dates: I. PURPOSE... 1 II. SCOPE...
More informationPRESENTER'S GUIDE "CRANE SAFETY" Part of the "SAFETY MEETING KIT" Series Quality Safety and Health Products, for Today...
PRESENTER'S GUIDE "CRANE SAFETY" Part of the "SAFETY MEETING KIT" Series Quality Safety and Health Products, for Today...and Tomorrow OUTLINE OF MAJOR PROGRAM POINTS OUTLINE OF MAJOR PROGRAM POINTS The
More informationLoad Rating Charts C-Series Cranes 3001
Load Rating Charts C-Series Cranes 3001 7600016-001 July 2003 Capacities: Capacities Overloading this crane or failing to comply with operating conditions and restrictions given on Capacity Chart can
More informationHealth, Safety, Security and Environment
Document owner and change code Document Owner Aaron Perronne Title HSSE Manager Mark X Change Code Description X N/A First Issue A Typographical/Grammatical correction; formatting change; text clarification-no
More informationOccupational Safety and Health Admin., Labor
Occupational Safety and Health Admin., Labor 1910.180 561 (ii) Before starting to hoist the following conditions shall be noted: (a) Hoist rope shall not be kinked. (b) Multiple part lines shall not be
More informationRyko Solutions, Inc. Crane and Jib Safety Program
Ryko Solutions, Inc. Crane and Jib Safety Program CONTENTS PURPOSE...3 POLICY...3 SCOPE...3 RESPONSIBILITIES...3 FITNESS FOR DUTY...4 INSPECTIONS...4 FREQUENT INSPECTION...4 PERIODIC INSPECTIONS...5 RATED
More informationCRANE TESTING REQUIREMENTS FOR PERFORMANCE TESTS
APPENDIX I CRANE TESTING REQUIREMENTS FOR PERFORMANCE TESTS 1. PERFORMANCE TESTING. a. Performance testing includes both operational performance testing and load performance testing. The following tables
More informationWashington State s New Construction Crane Rule (Phase 1)
Washington State s New Construction Crane Rule (Phase 1) The New Construction Crane Rule The rule is divided into two parts; The first part deals with Crane Certification and Crane Certifiers; Also included
More informationBritish Columbia - Colombie-Britannique. Aerial Lift - Appareil de Levage
British Columbia - Colombie-Britannique Aerial Lift - Appareil de Levage This material has been extracted from the Acts and Regulations of the Province to help students understand the subject. It is not
More informationLIFTING CHARTS - Crawler Cranes AMERICAN MODEL TON CAPACITY
LIFTING CHARTS - Crawler Cranes AMERICAN MODEL 7250-60 TON CAPACITY 7250 1 LIFT RATINGS With Tubular Hammerhead and "K-F-L-M" Counterweight (34,000 Lbs.) 11 82.8-120000 46 6 12 81.3-120000 46 6 15 77.0-106950
More informationLiftcrane Boom Capacities Boom No. 58 HL 332,000 lb Crane Counterweight 120,000 lb Carbody Counterweight 360 Degree Rating SERIES 3
ANSI B30.5 Liftcrane Boom Capacities Boom No. 332,000 lb Crane Counterweight 120,000 lb Carbody Counterweight 360 Degree Rating 16000 SERIES 3 LIFTING CAPACITIES: Lifting capacities for various boom lengths
More informationCRANES & MOBILE LIFTING EQUIPMENT COMPANY POLICY AND PROCEDURE
COMPANY POLICY AND PROCEDURE This Company s policy on lifting equipment is adopted from the OSHA Standards for Cranes and Derricks. The following procedures and practices will be enforced at the workplace
More informationPROCEDURE. Operative Date: 22/12/2016 Department: HSEC. Revision: Author: D Steel CONTENTS
Title: Cranes - Inspection and Maintenance PROCEDURE Procedure No: P314.422 Issue: 1 Revision: 0 Operative Date: 22/12/2016 Department: HSEC Sect./Classification: Safety / Gear & Equipment Author: D Steel
More informationSECTION 14: AERIAL LIFT PROGRAM
SECTION 14: AERIAL LIFT PROGRAM Fisher Auto Parts is committed to promoting a safe and healthy environment for all employees and customers. Protection from accidental loss of any resources, especially
More informationMobile and Locomotive Cranes
ASME B30.5-2014 (Revision of ASME B30.5-2011) Mobile and Locomotive Cranes Safety Standard for Cableways, Cranes, Derricks, Hoists, Hooks, Jacks, and Slings AN AMERICAN NATIONAL STANDARD ASME B30.5-2014
More informationT 775. truck crane 75 ton capacity. range diagram & lifting capacities. Range Diagram (40' - 126' boom)
T 7 truck crane ton capacity range diagram & lifting capacities DEFLECTIONS NOT SHOWN 6' - 9" 4' - 8" DIMENSIONS ARE FOR LARGEST FACTORY FURNISHED HOOK BLOCK AND HOOK & BALL, WITH ANTI-TWO BLOCK ACTIVATED
More informationHeavy Equipment & Rigging Specialist Training
Heavy Equipment & Rigging Specialist Training Module 3 Unit 1: Crane Load Chart Basics 23Mar08 1 Unit Objective After completion of this unit, you will be able to deploy a mobile crane safely and efficiently
More informationCranes. Range Diagram and Lifting Capacity RT TON LIFTING CAPACITY RANGE DIAGRAM 33' - 110' BOOM
Range Diagram and Lifting Capacity Cranes 55 TON LIFTING CAPACITY RANGE DIAGRAM 33' - 110' BOOM Dimensions are for largest factory furnished hook block and hook & ball, with anti-two block activated COUNTER
More informationRange Diagram and Lifting Capacity T Cranes. View thousands of Crane Specifications on FreeCraneSpecs.com RANGE DIAGRAM BOOM
Range Diagram and Lifting Capacity Cranes RANGE DIAGRAM 30-94 BOOM Dimensions are for largest factory furnished hook block and hook & ball, with anti-two block activated COUNTER WEIGHT BOOM LENGTH UPPERSTRUCTURE
More informationABSTRACT. Federal Program Change, Notice of Intent and Equivalency Required. See Section VI. National, Regional, and Area Offices.
DIRECTIVE NUMBER: CPL 02-01-056 EFFECTIVE DATE: 07/17/2014 SUBJECT: Inspection Procedures for Accessing Communication Towers by Hoist ABSTRACT Purpose: Scope: References: Cancellations: State Plan Impact:
More informationRange Diagram and Lifting Capacity T Cranes RANGE DIAGRAM BOOM
Range Diagram and Lifting Capacity T340-1 Cranes RANGE DIAGRAM 30-94 BOOM Dimensions are for largest factory furnished hook block and hook & ball, with anti-two block activated COUNTER WEIGHT BOOM LENGTH
More informationGUIDANCE IN-SERVICE INSPECTION PROCEDURES
GUIDANCE IN-SERVICE INSPECTION PROCEDURES Number: MLCC 03 Prepared by: MACHINERY LIFTS AND CRANE COMMITTEE Status: Issue 07 Date: 23/06/15 Reference: Health, Safety and Welfare at Work (General Application)
More informationCranes. Range Diagram and Lifting Capacity RT TON LIFTING CAPACITY RANGE DIAGRAM 40' - 126'
Range Diagram and Lifting Capacity Cranes 80 TON LIFTING CAPACITY RANGE DIAGRAM 40' - 126' BOOM Dimensions are for largest factory furnished hook block and hook & ball, with anti-two block activated COUNTER
More information"CRANE SAFETY IN CONSTRUCTION ENVIRONMENTS"
PRESENTER'S GUIDE "CRANE SAFETY IN CONSTRUCTION ENVIRONMENTS" Part of the "CONSTRUCTION SAFETY KIT" Series Quality Safety and Health Products, for Today...and Tomorrow OUTLINE OF MAJOR PROGRAM POINTS OUTLINE
More informationThe Sanford Underground Research Facility Revised: (07/31/2018) CRANES AND HOISTS Supersedes: (03/23/11)
ENVIRONMENT, HEALTH, AND SAFETY CRANES AND HOISTS Document- 73405 Version 3 Date 07/31/2018 i Version Control Responsible Person Document Control Number Document Version Publication Date Description of
More informationRT555 TEREX. rough terrain crane 55 ton capacity. range diagram & lifting capacities. Range Diagram ( boom) HOOK BLOCK WEIGHTS
TEREX RT5 rough terrain crane ton capacity range diagram & lifting capacities DIMENSIONS ARE FOR LARGEST FACTORY FURNISHED HOOK BLOCK AND HOOK & BALL, WITH ANTI-TWO BLOCK ACTIVATED Range Diagram (33-1
More informationSAFETY DIRECTIVE. 2.0 DEPARTMENTS AFFECTED This directive applies to all departments and employees of the Town of Marana.
SAFETY DIRECTIVE Title: Cranes and Rigging Issuing Department: Town Manager s Safety Office Effective Date: September 1, 2014 Approved: Gilbert Davidson, Town Manager Type of Action: New 1.0 PURPOSE This
More information36CSR27 TITLE 36 LEGISLATIVE RULE BOARD OF COAL MINE HEALTH AND SAFETY SERIES 27 RULES AND REGULATIONS GOVERNING SURFACE AREAS
TITLE 36 LEGISLATIVE RULE BOARD OF COAL MINE HEALTH AND SAFETY SERIES 27 RULES AND REGULATIONS GOVERNING SURFACE AREAS 36-27-1. General. 1.1. Scope. -- Rules and Regulations Governing Surface Areas. 1.2.
More informationLifting Capacities Telescopic Boom All Terrain Crane ATC ton (118 metric ton) Link Belt
Lifting Capacities Telescopic Boom All Terrain Crane ATC 3130 130 ton (118 metric ton) Boom and fly capacities for this machine are listed by the following sections: Fully Extended Outriggers Working Range
More informationCranes. Range Diagram and Lifting Capacity RT345-1XL 45 TON LIFTING CAPACITY RANGE DIAGRAM 33.75' - 105' BOOM
Range Diagram and Lifting Capacity RT345-1XL Cranes 45 TON LIFTING CAPACITY RANGE DIAGRAM 33.75' - 105' BOOM DIMENSIONS ARE FOR LARGEST FACTORY FURNISHED HOOK BLOCK AND HOOK & BALL, WITH ANTI-TWO BLOCK
More informationArab Academy for Science, Technology & Maritime Transport Colleague of Engineering & Technology Construction & Building Engineering
Arab Academy for Science, Technology & Maritime Transport Colleague of Engineering & Technology Construction & Building Engineering CB 523 Methods and Equipment for Construction 1 Lecture 8&9: Cranes Instructor:
More informationRange Diagram and Lifting Capacity RT230. Cranes 30 TON LIFTING CAPACITY RANGE DIAGRAM 30' - 94' BOOM REDUCTION IN MAIN BOOM CAPACITY
Range Diagram and Lifting Capacity Cranes 30 TON LIFTING CAPACITY RANGE DIAGRAM 30' - 94' BOOM Dimensions are for largest factory furnished hook block and hook & ball, with anti-two block activated COUNTER
More informationRange Diagram and Lifting Capacity RT665. Cranes 65 TON LIFTING CAPACITY RANGE DIAGRAM 36' - 111' BOOM REDUCTION IN MAIN BOOM CAPACITY
Range Diagram and Lifting Capacity Cranes 65 TON LIFTING CAPACITY RANGE DIAGRAM 36' - 111' BOOM DIMENSIONS ARE FOR LARGEST FACTORY FURNISHED HOOK BLOCK AND HOOK & BALL, WITH ANTI-TWO BLOCK ACTIVATED COUNTER
More informationFor Review Only No Copying No Saving No Lending No Posting Online
The following copyrighted samples are provided as a service for your review only. Copying, saving, lending, posting online or any general use of these files other than for the purpose provided is unlawful
More informationStatus: Issue 08 Date: 18/10/17 Reference: Lifting Operations and Lifting Equipment Regulations 1998 Regulation 9
GUIDANCE IN-SERVICE INSPECTION PROCEDURES Number: MLCC 03 Prepared by: MACHINERY LIFTS AND CRANE COMMITTEE Status: Issue 08 Date: 18/10/17 Reference: Lifting Operations and Lifting Equipment Regulations
More informationCrane and Hoist Safety Program
2017 Crane and Hoist Safety Program Occupational Health, Safety and Injury Prevention 11/28/2017 Subject Matter Expert Lyndsey Beaudin Leb255@cornell.edu 607-255-0205 CONTENTS 1.0 INTRODUCTION... 3 2.0
More informationLOAD CHARTS TMS9000E 85% STABILITY SERIAL NUMBER
LOAD CHARTS TMS9000E 85% STABILITY SERIAL NUMBER TMS9000E - S/N 1 TMS9000E - S/N 2 CONTENTS GENERAL NOTES...11 WEIGHT REDUCTIONS AND WARNING NOTES... 12 COUNTERWEIGHT CONFIGURATIONS... 13-15 LIFTING AREA
More informationELECTRICAL SAFETY-RELATED WORK PRACTICES
ELECTRICAL SAFETY-RELATED WORK PRACTICES This checklist is provided to assist organizations in reviewing compliance with OSHA Standard 29 CFR 1910.331 through 1010.335. Refer to the complete Standard for
More informationRELIANT HOLDINGS LTD AND ITS AFFILIATES Safety Management System. Preparation: Safety Mgr Authority: CEO Issuing Dept: Safety Page: Page 1 of 5
Preparation: Safety Mgr Authority: CEO Issuing Dept: Safety Page: Page 1 of 5 Purpose This program is written to be in compliance with local regulatory requirements and provide directives to managers,
More informationInspection Report: BOOM TRUCK-ANNUAL. Equipment Identification and Specifications
Inspection Report: OHA/ANI/AME tandards: OHA 1926.1400, 1910.180,1926.601 AME B30.5,B30.10 Date Inspected: 07/25/2016 Operation Hours: 11,121. Operation Miles: 107,160. Inspector: teve Marquis Equipment
More informationDGMS (Tech.) Circular No. 10 Dated Dhanbad the 19 th July, Safe use of mobile Cranes Code of practice
DGMS (Tech.) Circular No. 10 Dated Dhanbad the 19 th July, 2002. To Owner, Agent and Manager of all Mines. Safe use of mobile Cranes Code of practice A large numbers of mobile cranes are being used for
More informationGuidelines for Safety Training of Overhead Crane Operators and Supervisors
Guidelines for Safety Training of Overhead Crane Operators and Supervisors Purpose These guidelines present minimum recommended safety requirements for ensuring the safe and efficient operation of overhead
More informationWORKERS COMPENSATION (OCCUPATIONAL HEALTH AND SAFETY) AMENDMENT ACT, 1998
British Columbia - Colombie-Britannique Ladder Safety - Sécurité des échelles This material has been extracted from the Acts and Regulations of the Province to help students understand the subject. It
More informationWork Experience Form Mobile Crane Operator
2013 - National Occupational Analysis (NOA) Work Experience Form Mobile Crane Operator 1-877-978-7233 www.manitoba.ca/tradecareers Personal Information (please print) Legal First Name Middle Initial Legal
More informationSeries I300 Hydraulic Crane
Series 3 Hydraulic Crane 3 Ton Load Ratings AN UNTRANED OPERATOR SUBJECTS HMSELF AND OTHERS TO DEATH OR SEROUS NJURY YOU MUST NOT OPERATE THS CRANE UNLESS You have been trained in the safe operation of
More informationThe following material is Government of Prince Edward Island. Cap. O-1.01 Occupational Health and Safety Act PART 33
Prince Edward Island - Île-du-Prince-Édouard Lift Truck / Forklift This material has been extracted from the Acts and Regulations of the Province of Prince Edward Island to aid students in understanding
More informationWORKING WITH CRANES SAFELY
ERI Safety Videos Videos for Safety Meetings 2948 WORKING WITH CRANES SAFELY Leader s Guide Marcom Group Ltd. INTRODUCTION TO THE PROGRAM Structure and Organization Information in this program is presented
More informationChemical Hazards, Biological Hazards, and Harmful Substances
TM 67 Provisions of the Alberta Occupational Health and Safety Code and The Alberta Occupational Health and Safety Regulation Equipment REGULATION 12.2 If a worker is required under the Act to use or wear
More informationTo learn more about this model, call or visit giuffre.com today! GIUFFRE.COM
TC300 SERIES TELESCOPIC CRANE 2 CONTENTS //////////////////////////////////////////////////////////////////////////////////////// Crane Features...4 Chassis Data... 5 Outrigger Extension... 6 Sub Frame...6
More information