ClariMax Inclined Plate Clarifier. Installation, Operation & Maintenance Manual

Size: px
Start display at page:

Download "ClariMax Inclined Plate Clarifier. Installation, Operation & Maintenance Manual"

Transcription

1 THE ART & SCIENCE OF WASTEWATER TREATMENT ClariMax Inclined Plate Clarifier Installation, Operation & Maintenance Manual

2 TABLE OF CONTENTS 1.1. WARRANTY INSPECTION STORAGE ADDITIONAL INFORMATION 3 2. INSTALLATION TOOLS REQUIRED FOR INSTALLATION LIFTING THE UNIT ANCHORING AND LEVELING OF EQUIPMENT PLUMBING CONNECTIONS 5 3. SLUDGE AUGER Sludge Auger INSTALLATION 6 4. Plate Pack INSTALLATION Partition Wall INSTALLATION Effluent Trough INSTALLATION Effluent Trough ADJUSTMENT ELECTRICAL CONNECTIONS MECHANICAL PRINCIPAL OF OPERATION SLUDGE REMOVAL EFFLUENT QUALITY MAINTENANCE COATING MAINTENANCE RECOMMENDED PERIODIC MAINTENANCE TABLE 16 2

3 PREFACE The information found in this manual is based on years of experience with the installation, operation and maintenance of this type of equipment, however it is intended only as a guide. The methods that are available to you may require other, more appropriate procedures for the proper installation of this equipment. Proper care and safety should always be paramount. Use only qualified technicians and procedures in compliance with local building codes WARRANTY warrants its equipment to be free from defects in materials and workmanship for a period of one year from startup or 16 months from shipment, whichever occurs first. All component manufacturer s warranty will supersede this warranty and shall take precedence. HYDRO-FLO TECHNOLOGIES, INC. will not accept any back charges for warranty work, changing, adjusting, servicing or any other work that has not received advanced written authorization. HYDRO-FLO TECHNOLOGIES, INC. will grant authorization for the changing, adjusting or servicing of this equipment only in the interest of warranty repair, or to correct any deficiency discovered. Such work will only be considered upon written agreement from to do so INSPECTION Thoroughly inspect all equipment upon arrival. If any items are missing or damaged, note this on the shipping papers and contact your transportation company representative and HYDRO-FLO TECHNOLOGIES, Inc. immediately. Touch up all coatings damaged during shipment immediately. See the specification information for this particular piece of equipment for proper procedures for coatings touchups STORAGE If you are not ready to install the equipment upon arrival, store it in an area away from traffic. The ground should be level and free of any sharp objects that might damage the structure or coatings. Store the equipment with all factory packing intact as much as possible until ready for installation. Store the equipment out of the elements, preferably indoors. If this is not possible, make sure the equipment does not fill with water and debris. Verify that ancillary components (accessories, pumps, instruments) were not shipped inside the unit prior to outdoor storage. If components were shipped inside of the unit, insure that they are stored in a manner that is appropriate with their respective I, O & M manuals. For outdoor storage, we recommend you cover the equipment with a tarp! Store any pumps and other accessory items in a similar fashion ADDITIONAL INFORMATION For additional information that may be required for this installation or for answers to any questions you might have, contact: 3

4 Hydro-Flo Technologies Commerce DR. St Charles, IL Tel: (630) Fax: (630) INSTALLATION CAUTION! Prior to off-loading and installation of equipment, study the general arrangement drawing(s) and make yourself familiar with all aspects of the installation, operation and maintenance of this equipment TOOLS REQUIRED FOR INSTALLATION Crane for offloading and placing Masonry drill with masonry bit set for the installation of the equipment anchors (if applicable). Standard socket set, wrench set and miscellaneous drift pins for the installation and adjustment of the effluent weir. Carpenter's level for leveling width of unit. Machinery shims and grout for leveling the unit 2.2. LIFTING THE UNIT Warning: Unit must be empty (no water) when lifted! All units are designed to be lifted vertically and moved into place. Always lift the unit with a spreader bar to prevent damage to the float skimmer system. Attach lifting cables directly to all lifting eyes on the unit. Check load balance and readjust if required ANCHORING AND LEVELING OF EQUIPMENT For the Clarifier to operate correctly the unit must be level. Steps for anchoring and leveling of the equipment are as follows: Make sure that the ground is free of any sharp objects that might damage the coating. Set the tank in position on a level floor or pad. If the floor or pad is not level, use a good quality machinery grout to level the unit after drilling and installing the anchor bolts. Follow the grout manufacturer s instructions for shimming and grouting when leveling the unit. Mark the anchor bolt locations. 4

5 Move the equipment aside and drill holes for the anchors of your choice. Install the anchor bolts per the manufacturer's recommendations. We recommend using, as a minimum, 3/4" diameter x 4" - 6" long embedment type anchor bolts. Check local codes for seismic or other anchoring requirements. *HYDRO-FLO TECHNOLOGIES does not supply the anchor bolts. Note: If grouting is required, the height the anchor bolts extends above the surface must be increased to compensate for the thickness of the grout layer. Set the unit back in place. Level the unit from side to side by placing a good quality level on top of the fixed effluent weir wall. Level the unit from influent end to effluent end by using the clear tubing filled with water. Level the unit so that the water in the clear tubing on both ends is at the top of the flange radius. Check level at several points on each end. Securely tighten anchor bolt nuts PLUMBING CONNECTIONS The plumbing connections typically required for the installation of a Clarifier unit include but are not limited to: influent, effluent, sludge draw off and effluent chamber drain. Please refer to the instructions below and your project specific drawings for details. When making plumbing connections to the unit, the plumbing must be properly supported to carry the weight of the plumbing when full of water. Damage caused to this equipment by improperly supported plumbing will void the warranty. Connections do not have to be made in the order listed below. Review your situation and make the plumbing connections in the most logical order for your installation. The fittings on the unit are not designed to support a load due to connecting piping. When making connections to the unit, do not use the unit as a pipe support. All plumbing connections should be properly supported so as not to add stress to the unit s fittings. HYDRO-FLO TECHNOLOGIES, INC. cannot honor a warranty for tank failure due to improperly supported piping or incorrect installation CONNECT THE EFFLUENT PLUMBING The effluent plumbing must be the same size or larger than the nozzle size on the equipment. Do not reduce the size of the effluent piping as this might cause hydraulic overloading of the equipment. Also, try to run the discharge piping as short a distance as possible, through as few changes of direction as possible and at a pitch of not less than 1/16" per foot CONNECT THE INFLUENT PLUMBING The influent plumbing must be the same size as the nozzle size on the equipment for a minimum of 20 pipe diameters. Do not reduce the size of the influent piping as this might cause inappropriate velocities before it enters the unit. Also, try to run the inlet piping as 5

6 short a distance as possible, through as few changes of direction as possible and at a pitch of not less that 1/16" per foot CONNECT THE SLUDGE DRAW-OFF PLUMBING Connect a valve to the sludge draw-off flange and run a short length of pipe to a place where the sludge can be periodically decanted. When selecting a valve make sure that it is suitable for use with the type of sludge collected in your unit. Plumb up all sludge draw off nozzles for best evacuation of accumulated sludge. This includes the fittings on both sides of the sludge hopper. 3. SLUDGE AUGER If the unit comes equipped with a sludge auger/thickener device it will be powered by an electric motor connected to a gearbox for speed reduction to the auger shaft. The gearbox is maintenance free and may be mounted in any position. The auger shaft enters the tank directly adjacent the auger drive motor. The shaft incorporates a stuffing box type seal with a compression gasket and two mounting studs with gland seal nuts. The stuffing box seal will wear over time and begin to drip excessive water. The stuffing box seal will require tightening of the gland seal nuts to reduce leaking. When you tighten the gland seal nuts you must tighten them no more than ½ turn each and check for leaking while the shaft is turning. Never tighten more than ½ turn without checking for leaking Sludge Auger INSTALLATION The sludge auger /thickener rotates on 3 types of shafts, bearing assemblies. First is the end shaft assembly. It consists of the following components... Next is the intermediate shaft assembly. It consists of the following components... 6

7 Last is the driven shaft assembly. It consists of the following components... When assembling the auger, follow these basic guidelines... Always use anti-seize on all hardware. Assemble the auger starting with the end shaft followed by the intermediate shafts and finishing with the driven shaft. DO NOT assemble the thickener paddles until all the shafts and auger tubes are in place. DO NOT install the auger drive until the entire auger is assembled and checked for clearance. 7

8 Adjust the center bearing hanging rods so that all the shafts evenly spaced from the clarifier floor and the assembly runs in as straight a line as possible (from the end shaft to the driven shaft) When installing the paddles, adjust them so that there is 1/4" minimum clearance from the end of the paddle to the closest tank wall. 8

9 After the paddles are installed, they can be set in place with 1/8" diameter set pins or they can tacked in place with small spot welds. While not necessary, pinning the flights in place will prevent them from shifting. Pilot holes have been located in each flight for the location of dowel pins. Also, tacking the flights in place with small tack welds will also prevent them from shifting, but tacking the flights in place will make auger maintenance / flight replacement a bit more difficult. Below is an exploded view of a typical auger assembly. 9

10 4. PLATE PACK INSTALLATION Installing the plate packs is the most critical and time consuming aspect of the clarifier assembly. Care must be taken that each plate or plate pack is installed properly and that no gaps are allowed to develop during the installation. When assembling the clarifier plate pack, follow these basic guidelines... Start media installation at the influent end of the clarifier. Install the two EXTERIOR rows first. Install the two INTERIOR rows last. Check the angle of EACH plate as they are installed to make sure that they match the angle of the influent and effluent clarifier support walls. Any accumulated misalignment will have a negative effect on the overall installation. Take your time. Install one plate at a time. Check the angle. Contact Hydro-Flo immediately if you have any questions or concerns during the media installation. 5. PARTITION WALL INSTALLATION There are two partition walls that need to be installed after the media pack installation is completed. All of the panels are identical except for the 4 located on each end of the clarifier. 10

11 When assembling the partition walls, follow these basic guidelines... All of the central partition plates are identical and can be installed on either side of the clarifier. Install all the identical central partition plates first. Each plate will hang from a single hole located in each truss section. LOOSLY hang all sections in place. DO NOT tighten ANY of the bolts of the assembly until all sections of the partition walls are located in position. The bent flanges and threaded studs will always face toward the INSIDE of the clarifier. Install the 4 end sections. Install the central pack "T" baffles (these will be the items facing the center of the clarifier). All of these items will be identical except for the ones located at the far ends of the partition walls. Position them over the studs and loosely thread the nuts and washers over the studs. Install the exterior pack "T" baffles (these will be the items facing the exterior of the clarifier). All of these items will be identical except for the ones located at the far ends of the partition walls. Set them in position and loosely install the nuts, bolts and washers. 11

12 6. EFFLUENT TROUGH INSTALLATION There are two major components in the trough assembly. First are the individual trough sections and second are the trough mating channel. All of the mating channels are identical. The troughs themselves come in three different configurations. The influent end trough has one end sealed off and will be located at the clarifiers influent end. the discharge troughs are identical to the intermediate troughs except in overall length and are located at the effluent end of the clarifier. The intermediate troughs are all identical and are located in between the influent end trough and the discharge troughs. When assembling the effluent weir troughs, follow these basic guidelines... Pre-Assemble all of the trough adjustment studs to the clarifier mating channels Start at the EFFLUENT end of the clarifier. Set each trough section in position and loosely bolt a trough mating channel to each end. Install the trough leveling studs (4 at each mating trough). Install the intermediate troughs one at a time. Bolt them to the mating channels. Bolt the adjustment studs to the clarifier truss. Install the end troughs. Snug all the mating channel bolts (tight enough to pull the troughs together but not so tight that they restrict movement). DO NOT tighten them down until the troughs are basically leveled. 12

13 6.1. Effluent Trough ADJUSTMENT Each unit is supplied with multiple, adjustable, effluent collection troughs. The troughs and media packs may or may not be shipped installed depending on clarifier size etc. Generally speaking, if the clarifier must be shipped laying down due to size, then the plate packs are likely not installed and will be required to be installed in the field. Also, the clarifier internals may not be installed if there is a chance of damaging the internals during shipment. In addition, other items that may have to be removed for shipping will be required to be re-installed in the field.. Field adjustment of the effluent troughs after clarifier installation will be required in order to level troughs to ensure the water spilling in the troughs is even and consistent to ensure proper flow across all the plate packs. NOTE: Please read and understand the entire instruction before performing this task. This is an important requirement for proper clarifier operation. SAFETY FIRST! Never perform any work or make any adjustments to ANY mechanical or electrical system without first disconnecting and locking out power to the unit or serious injury can result. Tools needed: A 4 foot bubble level and a set of wrenches and a set of socket wrenches Step 1. Remove clarifier lid(s) if supplied. Step 2. The leveling of the effluent troughs is ESSENTIAL to good clarifier performance and should not be overlooked nor taken lightly. Leveling of the effluent troughs achieves totally even distribution of water and floc thru the clarifier which is needed to take advantage of the entire plate settling system and ensure proper clarifier performance. Step 3. Set the four foot level on the width of the clarifier near the troughs to determine the high side (if any). We ll select the high side as the starting point and adjust the other troughs up to it. Typically there is one trough per side, separated in the middle of the clarifier by the influent trough. All of the troughs will need to be perfectly level to one another as explained further on. Step 4. Use the four foot level on the selected highest trough to level the length of the trough. The trough is leveled by adjusting the threaded rod bolts to achieve long elevation and side to side elevation. Use the two foot level to level the troughs side to side. There are threaded rods at the end of each individual trough section. These rods are used to adjust level along the length and from side to side. Step 5. Use the two foot level to level from the first leveled trough to the adjacent trough. Step 6. Now level the length and side to side of this trough. Step 7. Double check that these first two troughs (or single trough in small clarifiers) are perfectly level to one another before proceeding to the other troughs. Step 8. All the troughs pierce the effluent chamber wall and stick out into the effluent chamber approximately 6. This is where we get to match level between the two plate chambers that are separated by the center influent trough. Use the four foot level to match the elevation of the effluent end of a previously leveled trough to it s adjacent trough in the adjacent plate chamber. 13

14 Step 9. Now carefully and precisely level the length of this trough using the effluent end of the trough as the start point. Be sure to level side to side as well. Step 10. Repeat steps 5, 6, and 7 until all troughs are perfectly level to one another. Double check the level between all trough ends in the effluent chamber to be sure they are all perfectly matched level to one another. Step 11. As you fill the clarifier for the first time you can watch the water spill into the troughs thru their entry weir holes. All of the "V" notch weirs should spill water into the troughs at very nearly the same moment, within 1-2 seconds from one another. Additionally, the cascade of water spilling into the troughs over the "V" notch weirs should appear about the same size (approximately 10-15% variance) with no one being much larger or smaller than the other. If the cascade size varies beyond 10-15% from one another it indicates a different flow rate thru that weir hole and therefore potentially uneven flow distribution. 7. ELECTRICAL CONNECTIONS SAFETY FIRST! Never perform any work or make any adjustments to ANY mechanical or electrical system without first disconnecting and locking out power to the unit or serious injury can result. Refer to project specific electrical drawing for all required field connections. 8. MECHANICAL SAFETY FIRST! Never perform any work or make any adjustments to ANY mechanical or electrical system without first disconnecting and locking out power to the unit or serious injury can result. Prior to sustained operation, bump all motors to ensure proper rotation. The unit may be equipped with a mechanical sludge auger/thickener. These units will be equipped with a gearbox for speed reduction. The standard gear reducers are maintenance free and may be installed in any position. 9. PRINCIPAL OF OPERATION Clarifier systems remove settlable solids and floc. They utilize inclined plate media packs in order to greatly increase the amount of projected surface settling area available in a smaller than normal footprint. The solids removal efficiency of the clarifier is directly related to the amount of projected surface area offered for a given flow rate and translates to an Hydraulic Loading Ratio (HLR) ratio of GPM/ft 2. A typical overflow ratio range is 0.25 gpm/ft 2.to 0.50 gpm/ft SLUDGE REMOVAL Please consult your local city and state regulatory agency regarding specific requirements on the proper disposal of the sludge generated in your process. If you need help with the disposal or treatment of the collected sludge, please contact your local HYDRO-FLO TECHNOLOGIES representative. 14

15 Sludge removal is very important to the proper operation of your Clarifier. Draw off the settled sludge regularly. Do not allow it to accumulate excessively or operational malfunctions can result. If sludge accumulates to an excessive level, the sludge level will rise to a point where it will contact and interfere with the operation of the media packs and floc or solids may be washed out of the clarifier. Any settled sludge should be drawn off periodically according to the accumulation rate. We recommend sludge be drawn off using a timer controlled sludge pump operating at 1-3% of the clarifier flow rate for 30 seconds every 15 minutes and adjust from there to match the accumulation rate. This will prevent any major sludge and effluent performance related problems. If your system was supplied with a bottom sludge auger/thickener it should be allowed to operate continuously as it will assist in preventing the sludge from naturally compacting in the sludge chamber EFFLUENT QUALITY Regularly check the effluent quality of your unit. If you notice any loss in effluent quality, take steps to correct the situation immediately. Some areas to check if your effluent quality has deteriorated are: Have you exceeded the unit s maximum rated flow? Have the influent characteristics changed due to some process change upstream? Are you chemically treating before the unit and if so have these chemicals changed? Are the chemicals being used for treatment completely mixed and are they fresh? Has the sludge collected to the point where it has begun to interfere with the media packs? Have you introduced anything new or foreign into the waste stream? 10. MAINTENANCE COATING MAINTENANCE Touch up all damaged coatings immediately prior to putting the clarifier into service. Regularly inspect the coatings ANNUALLY for damage or degradation and repair immediately to prevent severe damage. Drain the clarifier completely, wash out any accumulated sludge and inspect the coatings from the top to the bottom sludge chamber. CAUTION: Observe proper confined space entry procedures for internal inspections. Pay particular attention to coating condition at the weld seams, and any corners. See the specification information for this particular piece of equipment for proper procedures for coatings touchups for the coatings applied to this equipment. Pay particular attention to coatings condition and perform touchups after installation of any accessory equipment such as mixers, electrical, and media plate packs. Coatings used can vary depending on project requirements. 15

16 See Project Specific Drawings and Data for coatings used for your project RECOMMENDED PERIODIC MAINTENANCE TABLE MAINTENANCE TASK Check chemical supplies (if used) and replenish as needed. Remove accumulated sludge from the sludge collection chamber. Check for proper operation of the sludge auger/thickener (if supplied). Check auger drive shaft seal. Tighten enough to eliminate excessive leaking. Drain unit and inspect interior coatings. Touch up as necessary. RECOMMENDED MAINTENANCE SCHEDULE AS REQUIRED Daily if possible. AS REQUIRED Daily if possible. AS REQUIRED Daily if possible. AS REQUIRED Weekly if possible. Annually 16

Installation, Operation & Maintenance Manual. TotlSep (TS) Series. FRP Oil/Water Separator

Installation, Operation & Maintenance Manual. TotlSep (TS) Series. FRP Oil/Water Separator THE ART & SCIENCE OF WASTEWATER TREATMENT Installation, Operation & Maintenance Manual TotlSep (TS) Series FRP Oil/Water Separator Revised 09/2015 TABLE OF CONTENTS 1.0 PREFACE... 3 1.1 BACK CHARGE POLICY...

More information

INSTALLATION AND OPERATING INSTRUCTIONS FOR CONCRETE VAULT TYPE UNITS

INSTALLATION AND OPERATING INSTRUCTIONS FOR CONCRETE VAULT TYPE UNITS INSTALLATION AND OPERATING INSTRUCTIONS FOR CONCRETE VAULT TYPE UNITS CONTENTS Introduction Safety Operating Principle System Installation Initial Startup System Operations Troubleshooting Maintenance

More information

SaniTEE Wastewater Screens Installation & Service Manual FOR USE WITH SNT416, SNT418, SNT818, SNT 838, SNT1618, and SNT1638

SaniTEE Wastewater Screens Installation & Service Manual FOR USE WITH SNT416, SNT418, SNT818, SNT 838, SNT1618, and SNT1638 SaniTEE Wastewater Screens Installation & Service Manual FOR USE WITH SNT416, SNT418, SNT818, SNT 838, SNT1618, and SNT1638 SaniTEE Manual Bio-Microbics, Inc. Revised December 2009. SaniTEE is a registered

More information

Removal and Installation Guidelines

Removal and Installation Guidelines Removal and Installation Guidelines For: Drive Unit Removal and Re-installation WesTech Contact: Phone: (801) 265-1000 3665 S. West Temple Salt Lake City, UT 84115 Walkway Removal All sketches are for

More information

BOILER FEED SYSTEM OPERATION AND MAINTENANCE MANUAL

BOILER FEED SYSTEM OPERATION AND MAINTENANCE MANUAL BOILER FEED SYSTEM OPERATION AND MAINTENANCE MANUAL IMPORTANT These instructions are intended as a guide for the Installing Contractor and as a reference for the Operator, Owner and Serviceman. RETAIN

More information

GT-200 GATE VALVES PN16, Screwed end

GT-200 GATE VALVES PN16, Screwed end Document No. : MD-QO-04-281 Date : 2009/07 /17 Version : 1.0 GT-200 GATE VALVES PN16, Screwed end USER MANUAL Modentic Industrial Corporation 14F-1,No.57Taya Rd.,Taichung,Taiwan,R.O.C. Email:modentic@ms9.hinet.net

More information

WSB clean: Installation Manual

WSB clean: Installation Manual WSB clean: Installation Manual Models: WSB 400 WSB 1250 WSB 500 WSB 1500 WSB 600 WSB 1600 WSB 750 WSB 1800 WSB 1000 TABLE OF CONTENTS 1 INTRODUCTION...3 2 SAFETY INFORMATION...3 3 WSB CLEAN SYSTEM OPERATION...4

More information

I-234. Victaulic Styles 234/234S Restrained, Flexible Single-Gasket Couplings WARNING IMPORTANT INFORMATION ITEMS PROVIDED WITH SHIPMENT:

I-234. Victaulic Styles 234/234S Restrained, Flexible Single-Gasket Couplings WARNING IMPORTANT INFORMATION ITEMS PROVIDED WITH SHIPMENT: WARNING Read and understand all instructions before attempting to install any Victaulic piping products. Depressurize and drain the piping system before attempting to install, remove, or adjust any Victaulic

More information

Product Manual PS3900 / PS4600 / PS7000 / PS15000 / BF1600 / BF1900 / BF2600 / BF

Product Manual PS3900 / PS4600 / PS7000 / PS15000 / BF1600 / BF1900 / BF2600 / BF WG Product Manual PS3900 / PS4600 / PS7000 / PS15000 / BF1600 / BF1900 / BF2600 / BF3800 1.330.274.8317 www.atlanticwatergardens.com Table of Contents Pond Volume... 2 Surface Area... 3 Streambed Construction...

More information

Model AM2 M40 Panel Installation, Operation, and Maintenance Manual

Model AM2 M40 Panel Installation, Operation, and Maintenance Manual Model AM2 M40 Panel Installation, Operation, and Maintenance Manual RECEIVING AND INSPECTION Upon receiving unit, check for any interior and exterior damage, and if found, report it immediately to the

More information

MASTER COALESCER JR & PORTABLE MASTER COALESCER JR AIR PUMP MODEL INSTALLATION MANUAL

MASTER COALESCER JR & PORTABLE MASTER COALESCER JR AIR PUMP MODEL INSTALLATION MANUAL MASTER COALESCER JR & PORTABLE MASTER COALESCER JR AIR PUMP MODEL INSTALLATION MANUAL INSTALLATION: CHOOSING THE LOCATION: Locate the coalescer as near to the intended point of use as possible. Avoid high

More information

REMOVING THRUST ASSEMBLY IN 90AD EXTRUDER

REMOVING THRUST ASSEMBLY IN 90AD EXTRUDER TSB DSD 0001 TECHNICAL SERVICE BULLETIN REMOVING THRUST ASSEMBLY IN 90AD EXTRUDER 1-800- 278-3353 www.jcsteele.com 2018 J.C. Steele & Sons, Inc. SAFETY J.C. Steele and Sons equipment is designed to process

More information

SIDNEY MANUFACTURING

SIDNEY MANUFACTURING SIDNEY MANUFACTURING SIDE WALL RETURNTM DRAG CONVEYOR INSTALLATION INSTRUCTIONS NOTICE BEFORE ANY MAINTENANCE OR SERVICE IS PERFORMED ON THIS DRAG CONVEYOR, IT MUST BE LOCKED OUT IN ACCORDANCE WITH CURRENT

More information

CompoSeal butterfly valves, wafer style Installation & Maintenance Instructions

CompoSeal butterfly valves, wafer style Installation & Maintenance Instructions Please read these instructions carefully This symbol indicates important messages and safety instructions. Intended valve use The valve is intended to be used only in applications within the pressure/temperature

More information

Installation & Operation Manual

Installation & Operation Manual Installation & Operation Manual Thank you for purchasing our AS4795.1 Butterfly Valve. Before installing or operating, please carefully read this manual to know thoroughly how to install or operate. The

More information

Self Cleaning Hood System Installation, Operation, and Maintenance Manual

Self Cleaning Hood System Installation, Operation, and Maintenance Manual Self Cleaning Hood System Installation, Operation, and Maintenance Manual RECEIVING AND INSPECTION Upon receiving unit, check for any interior and exterior damage, and if found, report it immediately to

More information

Butterfly Valve Type 57P

Butterfly Valve Type 57P Butterfly Valve Type 57P Contents Lever Type: 50-200 mm (2-8 ) Body Material: CPVC Gear Type: 50-200mm (2-8 ) Body Material: CPVC (1) Be sure to read the following warranty clauses of our product 1 (2)

More information

INSTALLATION - MAINTENANCE MANUAL Severe Service Series M4 Ball Valve

INSTALLATION - MAINTENANCE MANUAL Severe Service Series M4 Ball Valve INSTALLATION - MAINTENANCE MANUAL Severe Service Series M4 Ball Valve Date: May 2016/ Page 2 of 12 Table of Contents 1. Safety Information - Definition of Terms..........................2 2. Bill of Materials....................................

More information

KESSEL-Grease Separator Under sink

KESSEL-Grease Separator Under sink INSTRUCTIONS FOR INSTALLATION, OPERATION AND MAINTENANCE KESSEL-Grease Separator Under sink Order Number 93025.00/US Product advantages Compact structure fully adjustable inlet 290 to 420 260 350 release

More information

Crispin Valves Operating Guide. Crispin

Crispin Valves Operating Guide. Crispin Crispin Valves Operating Guide Crispin Since 1905 Crispin Multiplex Manufacturing Co. 600 Fowler Avenue Berwick, PA 18603 1-800-AIR-VALV T: (570) 752-4524 F: (570) 752-4962 www.crispinvalve.com sales@crispinvalve.com

More information

Installation, Operation, and Maintenance Manual

Installation, Operation, and Maintenance Manual Intelligent Flow Measurement Your Sole Source for Badger Differential Producers Worldwide 6 Blackstone Valley Place, Lincoln RI 02865-1162 Ph: 401 334 1170 Fx: 401 334 1173 Em: solutions@wyattflow. Installation,

More information

Hampton Roads Planning District Commission

Hampton Roads Planning District Commission Hampton Roads Planning District Commission OBJECTIVE To help Grease Haulers comply with the Regional Consent Order and ensure proper maintenance of grease control devices. BACKGROUND In 2007, Special Orders

More information

Principals of Operation... 1 Rotary Vane Priming Pump VPE and VPES... 2 Rotary Vane Priming Pump VPO and VPOS Priming Valve...

Principals of Operation... 1 Rotary Vane Priming Pump VPE and VPES... 2 Rotary Vane Priming Pump VPO and VPOS Priming Valve... Priming Systems Installation Priming Systems Operation & Maintenance Form No. F 1031 Section 2312 Issue Date 10/07/94 Rev. Date 02/27/06 Table of Contents Illustrations Principals of Operation...........................

More information

Operation and Maintenance

Operation and Maintenance E-Z Set Company requires regular inspection and maintenance of the E-Z Treat Re- Circulating Sand/Media Filter, as a condition of purchase and ongoing operation compliance. The mandatory service contract

More information

Geared Drives 200Z PSRU Zero Offset Gearbox with Centrifugal Clutch Assembly

Geared Drives 200Z PSRU Zero Offset Gearbox with Centrifugal Clutch Assembly Instructions for Removing and replacing Gen X Gearbox with Geared Drives 200Z Prior to your gear box arriving: Using a strap or chain and an engine hoist to hold your engine up in the mount, remove your

More information

I-231.T2S1/CLAD. Victaulic Style 231 Non-Restrained, Flexible Expansion Coupling with Cladding on Expansion Side of Pipe WARNING IMPORTANT INFORMATION

I-231.T2S1/CLAD. Victaulic Style 231 Non-Restrained, Flexible Expansion Coupling with Cladding on Expansion Side of Pipe WARNING IMPORTANT INFORMATION WARNING Read and understand all instructions before attempting to install any Victaulic piping products. Depressurize and drain the piping system before attempting to install, remove, or adjust any Victaulic

More information

Installation Instructions

Installation Instructions E/One Sewers TM Installation Instructions for Flexible Hose & Horizontal Slideface Read all instructions before proceeding with installation. 1 AMGP INSTALLATION LAYOUT SHEET 3 After Market Grinder Pump

More information

Stormwater Treatment System

Stormwater Treatment System The Up-Flo Filter Stormwater Treatment System Table of Contents 3 Up-Flo Filter - Overview - General Product Description - Typical Configurations - Maintenance Services 4 Operation - Introduction - Pollutant

More information

Single and Bi-Parting Manual Sliding Doors. Installation. R-PLUS Cold Storage Doors

Single and Bi-Parting Manual Sliding Doors. Installation. R-PLUS Cold Storage Doors Single and Bi-Parting Manual Sliding Doors Installation Door Leaf J-Box Door Heater J-Box Door Header Adjusting Rod Door Hanger Assembly Track Roller Door Track SJO Cable Trailing Edge Door Snubber Neoprene

More information

I-232.T3S2 Victaulic Style 232 Restrained, Flexible High-Pressure Coupling

I-232.T3S2 Victaulic Style 232 Restrained, Flexible High-Pressure Coupling WARNING Read and understand all instructions before attempting to install any Victaulic piping products. Depressurize and drain the piping system before attempting to install, remove, or adjust any Victaulic

More information

ABCD BFDC BEDA AB CDEFCC

ABCD BFDC BEDA AB CDEFCC ABCD BFDC BEDA AB CDEFCC ABCD BFDC BEDA AB CDEFCC AFC Oil/ Water Separator Specifications and Operation & Maintenance Schedule 1) Model of AFC Oil/ Water Separator: a)

More information

IMPORTANT INSTRUCTIONS FOR OPERATION & MAINTENANCE OF

IMPORTANT INSTRUCTIONS FOR OPERATION & MAINTENANCE OF IMPORTANT INSTRUCTIONS FOR OPERATION & MAINTENANCE OF CONVEYORS EASIKIT 300 EASIKIT 450 EASIKIT 600, 900, 1200 & 1500 The manufacturer does not accept responsibility for any loss, damage to other equipment,

More information

NECO Pumping Systems

NECO Pumping Systems INSTALLATION OPERATION & MAINTENANCE INSTRUCTIONS For Your NECO Pumping Systems PACKAGED CIRCULATING SYSTEM THIS COMPLETELY ASSEMBLED, TESTED, PACKAGED CIRCULATING SYSTEM IS OF THE HIGHEST QUALITY AND

More information

Orifice Flange Union Assembly and Orifice Run Installation and Operation Manual

Orifice Flange Union Assembly and Orifice Run Installation and Operation Manual Orifice Flange Union Assembly and Orifice Run Installation and Operation Manual 354-EN Please read and save these instructions. Installation Procedures Orifice Flange Union Assembly Installing Orifice

More information

OWS OPERATIONS & MAINTENANCE

OWS OPERATIONS & MAINTENANCE SUPPLEMENTAL INSTRUCTIONS 1. INTRODUCTION 1.1. Containment Solutions manufactures Oil/Water Separator (OWS) tanks with internal coalescing plates. These units are available in single or double-wall model

More information

Impeller Replacement

Impeller Replacement Impeller Replacement Threaded Shaft Frame Mount H 806 Clockwise Rotation Volute shown. 1149 0794 1 Unfasten hardware holding volute to bracket. Remove volute to expose impeller. Peel off old volute gasket

More information

Typical Machine Tool Coolant Purification Unit Installation and Operating Manual Note: MSR provides a custom manual for every application

Typical Machine Tool Coolant Purification Unit Installation and Operating Manual Note: MSR provides a custom manual for every application Typical Machine Tool Coolant Purification Unit Installation and Operating Manual Note: MSR provides a custom manual for every application Mohr Separations Research Model MSR-33 S Separator Customer: Background

More information

Series Base mounted pump. Installation and operating instructions

Series Base mounted pump. Installation and operating instructions Series 4030 Installation and File No: 40.80 Date: june 25, 2015 Supersedes: 40.80 Date: october 10, 2009 contents General 4 Inspection 4 Installation - Series 4030 base mounted Pump 4 1.0 Location 4 2.0

More information

A+ Battery Backup Power Supply For use with Hydromatic model B-A1/BV-A1

A+ Battery Backup Power Supply For use with Hydromatic model B-A1/BV-A1 Unit Installation and Service Manual A+ Battery Backup Power Supply For use with Hydromatic model B-A1/BV-A1 NOTE! To the installer: Please make sure you provide this manual to the owner of the pumping

More information

Val-Matic 1-4 Combination Air Valve (Single Housing Type)

Val-Matic 1-4 Combination Air Valve (Single Housing Type) Manual No. ARCO-OM1-3 Val-Matic 1-4 Combination Air Valve (Single Housing Type) Operation, Maintenance and Installation Manual INTRODUCTION... 1 RECEIVING AND STORAGE... 1 DESCRIPTION OF OPERATION... 1

More information

M14 AUTOMOTIVE SPARK PLUGS AND WIRES CONVERSION KIT INSTALLATION INSTRUCTIONS

M14 AUTOMOTIVE SPARK PLUGS AND WIRES CONVERSION KIT INSTALLATION INSTRUCTIONS M14 AUTOMOTIVE SPARK PLUGS AND WIRES CONVERSION KIT INSTALLATION INSTRUCTIONS (It is highly recommended you read the instructions completely before beginning) 1. Be sure the magneto switches are turned

More information

Instruction Manual. SHPE1500 Salt Dogg Spreader Hopper Poly Electrical 1.5 cubic yards

Instruction Manual. SHPE1500 Salt Dogg Spreader Hopper Poly Electrical 1.5 cubic yards 9049 Tyler Blvd. Mentor, Ohio 44060 Phone (440) 974-8888 Fax (440) 974-0165 Toll-Free Fax 800-841-8003 buyersproducts.com SHPE1500 Salt Dogg Spreader Hopper Poly Electrical 1.5 cubic yards Instruction

More information

Installation and Operating Procedures

Installation and Operating Procedures Installation and Operating Procedures Manual Grease Interceptors 60100H SERIES 60210A SERIES Josam Company 525 W.U.S. Hwy 20 Michigan City, IN 46360 1-800-365-6726 www.josam.com REV A 04/15/11 WARNING:

More information

Jeep JL 3.5 Spring Lift

Jeep JL 3.5 Spring Lift 1 Jeep JL 3.5 Spring Lift www.teraflex.com Important Notes: Prior to beginning this install, or any installation, read the instructions thoroughly to familiarize yourself with the required steps. Evaluate

More information

INSTALLATION TROUBLESHOOTING SUPPLEMENT

INSTALLATION TROUBLESHOOTING SUPPLEMENT TITAN Fuel Tanks INSTALLATION TROUBLESHOOTING SUPPLEMENT For Midship Replacement Fuel Tanks AND Utility Tanks This supplement is intended to provide additional information for installers to aid in simple

More information

WARNING!!! READ AND UNDERSTAND ALL INSTRUCTIONS BEFORE PROCEEDING. MAKE SURE THAT YOU HAVE ALL TOOLS AND PARTS BEFORE BEGINNING THE INSTALLATION.

WARNING!!! READ AND UNDERSTAND ALL INSTRUCTIONS BEFORE PROCEEDING. MAKE SURE THAT YOU HAVE ALL TOOLS AND PARTS BEFORE BEGINNING THE INSTALLATION. INSTALLATION INSTRUCTIONS FOR 2007-2015 JEEP JK 3 SUSPENSION LIFT SYSTEM PART NUMBER 587 WARNING!!! READ AND UNDERSTAND ALL INSTRUCTIONS BEFORE PROCEEDING. MAKE SURE THAT YOU HAVE ALL TOOLS AND PARTS BEFORE

More information

Section 10 Chapter 17

Section 10 Chapter 17 Section 10 Chapter 17 24 Valve, 8.3 Liter Engine Air Intake System Note: All coding used in the 8.3 Liter and 9 Liter engine manuals are Cummins engine codes. These engine codes have no meaning to New

More information

RollSeal 1733 County Road 68 Bremen, Alabama Part No Rev Owner s Manual RS-Divider Curtain

RollSeal 1733 County Road 68 Bremen, Alabama Part No Rev Owner s Manual RS-Divider Curtain 1. 2. 7 3. 4. RollSeal 1733 County Road 68 Bremen, Alabama 35033 256-287-7000 Part No 4801-5176 Rev 12-11-17 Owner s Manual RS-Divider Curtain Table of Contents 1 Warnings (Avertissements)... 3 2 Limited

More information

MODEL NUMBER: MEDIUM DUTY ONBOARD AIR SYSTEM

MODEL NUMBER: MEDIUM DUTY ONBOARD AIR SYSTEM MODEL NUMBER: 10003 MEDIUM DUTY ONBOARD AIR SYSTEM IMPORTANT: It is essential that you and any other operator of this product read and understand the contents of this manual before installing and using

More information

Manufacturer Kakogawa, Japan DC5S

Manufacturer Kakogawa, Japan DC5S ISO 9001/ ISO 14001 Manufacturer Kakogawa, Japan is approved by LRQA LTD. to ISO 9001/14001 Cyclone Separator Trap DC5S Copyright 2015 by TLV Co., Ltd. All rights reserved 1 Contents Introduction... 1

More information

Albany RR1000. Mechanical Installation Manual. PN: 6410T0029 Version - Rev: 04/23/2014. ASSA ABLOY Entrance Systems

Albany RR1000. Mechanical Installation Manual. PN: 6410T0029 Version - Rev: 04/23/2014. ASSA ABLOY Entrance Systems PN: 6410T0029 Version - Rev: 04/23/2014 Mechanical Installation Manual Albany RR1000 ASSA ABLOY Entrance Systems High Performance Door Solutions Tel: (770) 338-5000 975A Old Norcross Road Fax: (770) 388-5024

More information

TECHNICAL ASSISTANCE TOLL FREE TELEPHONE NUMBER TECHNICAL ASSISTANCE FAX:

TECHNICAL ASSISTANCE TOLL FREE TELEPHONE NUMBER TECHNICAL ASSISTANCE FAX: ACORN SAFETY P.O. BOX 3527 CITY OF INDUSTRY, CA 91744-0527 UNITED STATES OF AMERICA WWW.ACORNSAFETY.COM INSTALLATION, OPERATION AND MAINTENANCE INSTRUCTIONS DECK MOUNTED EYE/FACEWASH Model S0730 / S0740

More information

When installing the screwed end, socket weld & flanged end valves the following respective procedures shall be followed for better performance.

When installing the screwed end, socket weld & flanged end valves the following respective procedures shall be followed for better performance. 1. Storage LARSEN & TOUBRO LIMITED Page 1 of 5 1.1. All valves are to be stored in fully open position, in order to protect the sphere surface and soft valve seats. 1.2. Before shipping, the inlet and

More information

PRODUCT OPERATING MANUAL

PRODUCT OPERATING MANUAL PRODUCT OPERATING MANUAL PANBLAST TM PROFLO ABRASIVE RECYCLING SYSTEM Manual Number: ZVP PC 0035 01 SECTION 1. GENERAL INFORMATION 2. ASSEMBLY INSTRUCTIONS 3. OPERATING INSTRUCTIONS 4. MAINTENANCE 5. TROUBLE

More information

( Versions Available)

( Versions Available) STYLE 494 ELECTRIC LADDER PIPE INSTALLATION, OPERATING AND MAINTENANCE INSTRUCTIONS ( Versions Available) The following is intended to provide the basic instructions for installation, operating and maintenance

More information

E-Z Treat Installation Guidelines

E-Z Treat Installation Guidelines E-Z Treat Installation Guidelines E-Z Treat Company or its representative will conduct on-site training with each installer before they are certified to install E-Z Treat systems. The training will include

More information

Installation - Tank & Aerator

Installation - Tank & Aerator Installation - Tank & Aerator 1500 SERIES MEDIA PLANTS & ALL OTHER MODELS NSF LISTED & 1500 S SERIES PLANTS These instructions apply to J-1500 Series and 1500 S Series plants. Each series has a 500, 750,

More information

Installation, Operation and Maintenance Manual

Installation, Operation and Maintenance Manual Document 483509 VCD, FBH & FBV Models Vertical and Horizontal Mount Installation, Operation and Maintenance Manual Please read and save these instructions for future reference. Read carefully before attempting

More information

TJ SPEED BUMPS Part # Part #

TJ SPEED BUMPS Part # Part # PRODUCT INSTALLATION GUIDE THIS KIT IS DESIGNED TO WORK ON A TJ WITH 4+ OF LIFT Important Notes: TJ SPEED BUMPS Part # 1958700 Part # 1958720 Prior to beginning this or any installation read these instructions

More information

HENNIG, INC N. ALPINE ROAD MACHESNEY PARK, IL (815) (PH.) (815) (FAX)

HENNIG, INC N. ALPINE ROAD MACHESNEY PARK, IL (815) (PH.) (815) (FAX) HENNIG, INC. 9900 N. ALPINE ROAD MACHESNEY PARK, IL 61115 (815)-636-9900 (PH.) (815)-636-1988 (FAX) WWW.HENNIG-INC.COM MANUAL REVISION DATE: 07/27/2016-1 - HENNIG CHIP CONVEYOR The Hennig Chip Conveyor

More information

Banks Monster Exhaust System

Banks Monster Exhaust System Banks Monster Exhaust System 2007-2008 Chevy/GMC 1500 Silverado 4.8L, 5.3L, 6.0L V-8 Gas, New Body Style THIS MANUAL IS FOR USE WITH MONSTER EXHAUST SYSTEMS 48344, 48345 Gale Banks Engineering 546 Duggan

More information

Service Manual Air Plus Second Stage

Service Manual Air Plus Second Stage Service Manual Air Plus Second Stage Includes XS Series Second Stage Copyright 2002, Cressi-sub Revised 3/2002 2 Air Plus Second Stage Service Manual Contents BEFORE STARTING... 3 DISASSEMBLY... 3 PARTS

More information

SUPERIOR PERFORMANCE

SUPERIOR PERFORMANCE REVERSE PULSE DUST COLLECTORS OPERATION & MAINTENANCE MANUAL M600-2C, M900-2C & M1200-2C SUPERIOR PERFORMANCE And Quality In Blast Cleaning Equipment! WARNING Read Manual Failure to read, understand &

More information

AWWA C504. Double Eccentric AWWA C504

AWWA C504. Double Eccentric AWWA C504 AWWA C504 Double Eccentric AWWA C504 Series 3900F - Flanged with Handwheel or Lever Handle Series 3900MJ - Mechanical Joint with Handwheel or Lever Handle 0418 0318 MODEL 3975F - Butterfly Valve with Manual

More information

Instruction Manual. SaltDogg Spreader Hopper Poly Electrical 0.65 cubic yards. Table of Contents. General Information. Vehicle Requirements: WARNING

Instruction Manual. SaltDogg Spreader Hopper Poly Electrical 0.65 cubic yards. Table of Contents. General Information. Vehicle Requirements: WARNING SaltDogg Spreader Hopper Poly Electrical 0.5 cubic yards Instruction Manual Table of Contents General Information... Warranty Information... Safety Precautions... Installation Instructions... -3 Spreader

More information

Installation, Operation and Maintenance Manual

Installation, Operation and Maintenance Manual Installation, Operation and Maintenance Manual for the MOGAS Improved RSVP Metal Seated Ball Valve How to Install the valve properly Stress relieve welds according to ASME B31.1 ASME 1500 CLASS Maintain

More information

GARDEN HOSE UTILITY PUMP

GARDEN HOSE UTILITY PUMP GARDEN HOSE UTILITY PUMP MODEL #HPP360, HPP12V, 473707 MODEL #HPP360, 473707 MODEL #HPP12V ATTACH YOUR RECEIPT HERE Purchase Date SAFETY INFORMATION Please read and understand this entire manual before

More information

DODGE OFF ROAD T-STYLE STEERING KIT INSTALLATION INSTRUCTIONS

DODGE OFF ROAD T-STYLE STEERING KIT INSTALLATION INSTRUCTIONS Dodge Off Road, LLC Specializing in Dodge Ram Solid-Axle 4x4 Suspension and Steering for Off Road Applications 855.9009.DOR sales@dodgeoffroad.com dodgeoffroad.com DODGE OFF ROAD T-STYLE STEERING KIT INSTALLATION

More information

Operating and Installation Instructions

Operating and Installation Instructions Model Number 20902 Fabricator's Power Module Kit - Aluminum Operating and Installation Instructions CAUTION! This product is to be installed only by persons knowledgeable in the repair and modification

More information

2" - 24" OS Series Butterfly Valves. Operation and Maintenance Manual. Job Name: Contractor: Date:

2 - 24 OS Series Butterfly Valves. Operation and Maintenance Manual. Job Name: Contractor: Date: s Operation and Maintenance Manual Job Name: Contractor: Date: Document #: IOM Revision Date: 10/2/2016 SAFETY MESSAGES All safety messages in the instructions are flagged with an exclamation symbol and

More information

JK HD Skid Plate for Rear Falcon Shocks

JK HD Skid Plate for Rear Falcon Shocks 1 JK HD Skid Plate for Rear Falcon Shocks Kit # 36-07-01-300 Tools needed: Important Notes: Prior to beginning this or any installation read these instructions to familiarize yourself with the required

More information

TECHNICAL ASSISTANCE TOLL FREE TELEPHONE NUMBER TECHNICAL ASSISTANCE FAX:

TECHNICAL ASSISTANCE TOLL FREE TELEPHONE NUMBER TECHNICAL ASSISTANCE FAX: ACORN SAFETY P.O. BOX 3527 CITY OF INDUSTRY, CA 91744-0527 UNITED STATES OF AMERICA WWW.ACORNSAFETY.COM INSTALLATION, OPERATION AND MAINTENANCE INSTRUCTIONS PEDESTAL EYE/FACEWASH Models S0310 / S0320 /

More information

September Leopold Sludge Collection Equipment

September Leopold Sludge Collection Equipment September 2012 Leopold Sludge Collection Equipment Clari-Trac -2 (CT2 ) Submerged Sludge Collector Arrangement differential head to sludge disposal Graphic on Front of Brochure Illustrates the Principle

More information

Tuned Length Headers. Special Tools Required: Install Time: Difficulty: Follow these instructions carefully to ensure correct fitment and operation.

Tuned Length Headers. Special Tools Required: Install Time: Difficulty: Follow these instructions carefully to ensure correct fitment and operation. Special Tools Required: welder / saws all Install Time: Approximately 4 Hours Difficulty: 4 out of 5 Follow these instructions carefully to ensure correct fitment and operation. STEP 1 Disconnect the negative

More information

Kits 75559, & Universal Air Spring-Over-Strut

Kits 75559, & Universal Air Spring-Over-Strut Kits 75559, 75561 & 75562 Universal Air Spring-Over-Strut MN-723 (061901) ECR 8657 NOTE: THIS KIT IS SOLD WITHOUT A WARRANTY. INSTALLATION GUIDE For maximum effectiveness and safety, please read these

More information

AQUATOR Commercial Oil Water Separator Operating, Installation & Maintenance Manual

AQUATOR Commercial Oil Water Separator Operating, Installation & Maintenance Manual AQUATOR Commercial Oil Water Separator Operating, Installation & Maintenance Manual For Single-Wall and Double-Wall Fibreglass Underground Storage Tanks This Aquator Commercial Oil Water Separator (OWS)

More information

Owner smanual. Banks Monster Exhaust System Toyota FJ Cruiser. with Installation Instructions

Owner smanual. Banks Monster Exhaust System Toyota FJ Cruiser. with Installation Instructions with Installation Instructions Owner smanual Banks Monster Exhaust System 2007-2009 Toyota FJ Cruiser THIS MANUAL IS FOR USE WITH MONSTER EXHAUST SYSTEMS 48141, 48142 Gale Banks Engineering 546 Duggan

More information

READ AND SAVE THESE INSTRUCTIONS. High Velocity Restaurant-Duty Utility Set Belt Driven for Roof Mounting

READ AND SAVE THESE INSTRUCTIONS. High Velocity Restaurant-Duty Utility Set Belt Driven for Roof Mounting READ AND SAVE THESE INSTRUCTIONS INSTALLATION, OPERATING INSTRUCTIONS & PARTS MANUAL High Velocity Restaurant-Duty Utility Set Belt Driven for Roof Mounting Electrical wiring and connections should be

More information

TECHNICAL ASSISTANCE TOLL FREE TELEPHONE NUMBER TECHNICAL ASSISTANCE FAX:

TECHNICAL ASSISTANCE TOLL FREE TELEPHONE NUMBER TECHNICAL ASSISTANCE FAX: ACORN SAFETY P.O. BOX 3527 CITY OF INDUSTRY, CA 91744-0527 UNITED STATES OF AMERICA WWW.ACORNSAFETY.COM INSTALLATION, OPERATION AND MAINTENANCE INSTRUCTIONS COMPACT RECESSED EYEWASH/FACEWASH MODELS S0560

More information

Installation Instructions

Installation Instructions 9049 Tyler Blvd. Mentor, Ohio 44060 Phone (440) 974-8888 Fax (440) 974-0165 Toll-Free Fax 800-841-8003 saltdogg.com Installation Instructions Salt Dogg Spreader Hopper Poly Electrical 2.0 cubic yards Serial

More information

CHEVROLET TAHOE/DENALI/AVALANCHE/YUKON/ SILVERADO/SIERRA 2007+

CHEVROLET TAHOE/DENALI/AVALANCHE/YUKON/ SILVERADO/SIERRA 2007+ CHEVROLET TAHOE/DENALI/AVALANCHE/YUKON/ SILVERADO/SIERRA 2007+ INSTALLATION INTRODUCTION 1. REMOVING THE FENDER AND DOORS FROM THE A-PILLAR AND DISCONNECTING THE WIRE HARNESS @ THE DOOR JAM 2. REMOVING

More information

MACH 1 TSQV SEVERE SERVICE PLUG VALVES

MACH 1 TSQV SEVERE SERVICE PLUG VALVES MACH 1 TSQV SEVERE SERVICE PLUG VALVES FOREWORD The Flowserve Corporation has established this Installation, Operating and Maintenance Manual to facilitate field installation, operation and repair of Triple

More information

Please visit for the latest version of these installation instructions.

Please visit   for the latest version of these installation instructions. Please visit www.blueox.com for the latest version of these installation instructions. BX2338 2012-17 Hyundai Accent GLS/SE (Includes Foglights) Attachment Tab Height: 14 Serial Number Attachment Tab Width:

More information

Instruction Manual for HSPA Take-Up Units

Instruction Manual for HSPA Take-Up Units Installation Instruction Manual for HSPA Take-Up Units Warning: To ensure the drive is not unexpectedly started, turn off and lockout the power source before proceeding. Failure to observe these precautions

More information

TECHNICAL ASSISTANCE TOLL FREE TELEPHONE NUMBER TECHNICAL ASSISTANCE FAX:

TECHNICAL ASSISTANCE TOLL FREE TELEPHONE NUMBER TECHNICAL ASSISTANCE FAX: ACORN SAFETY P.O. BOX CITY OF INDUSTRY, CA -0 UNITED STATES OF AMERICA WWW.ACORNSAFETY.COM INSTALLATION, OPERATION AND MAINTENANCE INSTRUCTIONS EYEWASH / FACEWASH Models S00 / S00 / S00 / S00-CS-SSE /

More information

Sediment strainer (Type Y)

Sediment strainer (Type Y) Installation,Operation and Maintenance Manual Serial No. H-V034-E-9 Sediment strainer (Type Y) Contents (1) Be sure to read the following warranty clauses of our product 1 User s Manual (2) General operating

More information

FTFR Maintenance and Parts Manual SQ-1 FLOOR TRUSS FINISH ROLLER. Operators Manual

FTFR Maintenance and Parts Manual SQ-1 FLOOR TRUSS FINISH ROLLER. Operators Manual FTFR Maintenance and Parts Manual SQ-1 FLOOR TRUSS FINISH ROLLER Operators Manual FOREWORD This manual explains the proper maintenance of Square 1 Design Floor Truss Finish Roller as well as the daily

More information

CSO/STORMWATER MANAGEMENT. HYDROVEX CCV Check Valve

CSO/STORMWATER MANAGEMENT. HYDROVEX CCV Check Valve CSO/STORMWATER MANAGEMENT HYDROVEX CCV Check Valve HYDROVEX CCV CIRCULAR CHECK VALVE APPLICATION The HYDROVEX CCV Check Valve is designed for use in water and sewage. It has no reinforcement and is especially

More information

CT SEPARATOR SYSTEM OPERATION & MAINTENANCE MANUAL

CT SEPARATOR SYSTEM OPERATION & MAINTENANCE MANUAL CT SEPARATOR SYSTEM OPERATION & MAINTENANCE MANUAL PLEASE RECORD THE FOLLOWING DATA (Information is located on the product label or packing slip) Model Number: Date Code: Installation Date: Installation

More information

DC Series Installation Manual (# )

DC Series Installation Manual (# ) DC Series Installation Manual (# 101630) Page 1 of 33 In this booklet you will find: TOWER INSTALLATION... 3 U-Bolt Style mount... 4 Side Frame Style mount... 4 PIVOT INSTALLATION... 5 External Pivot Installation:

More information

5000/6000 SERIES BALL VALVES INSTALLATION - MAINTENANCE MANUAL

5000/6000 SERIES BALL VALVES INSTALLATION - MAINTENANCE MANUAL Date: August 2011 / Page 1 of 6 5000/6000 SERIES BALL VALVES INSTALLATION - MAINTENANCE MANUAL DESIGN The design features three piece construction and a free floating ball allowing ease of maintenance

More information

SERIES PC INSTRUCTION AND OPERATION MANUAL

SERIES PC INSTRUCTION AND OPERATION MANUAL MEGGA SERIES PC INSTRUCTION AND OPERATION MANUAL Models PCT and PCF Close-coupled and frame-mounted single-stage horizontal end-suction pumps. WARNING: Read this manual before installing or operating this

More information

Installation Manual. stairlift. A 4724 Neukirchen/W, Salling 8 Tel: 07278/ , Fax: 07278/ Mobil: 0664/

Installation Manual. stairlift. A 4724 Neukirchen/W, Salling 8 Tel: 07278/ , Fax: 07278/ Mobil: 0664/ Installation Manual Ω MEGA stairlift A 4724 Neukirchen/W, Salling 8 Tel: 07278/3514-15, Fax: 07278/3514-12 Email: office.lehner@gmx.at Mobil: 0664/1612980 CONTENTS OBSERVE THE FOLLOWING POINTS BEFORE INSTALLATION!...

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS INSTALLATION INSTRUCTIONS REAR DISC BRAKE CONVERSION KIT A126-1 1973-87 CHEVROLET 1/2 TON 2WD Thank you for choosing STAINLESS STEEL BRAKES CORPORATION for your braking needs. Pleases take the time to

More information

Butterfly Valve Type 58 (PDCPD)

Butterfly Valve Type 58 (PDCPD) Serial No. H-V074-E Butterfly Valve Type 58 (PDCPD) 700mm (28 ) User s Manual Contents (1) Be sure to read the following warranty clauses of our product 1 (2) General operating instructions 2 (3) General

More information

JK HD Skid Plate for Rear Falcon Shocks

JK HD Skid Plate for Rear Falcon Shocks 1 JK HD Skid Plate for Rear Falcon Shocks Kit # 36-07-01-300 Important Notes: Prior to beginning this or any installation read these instructions to familiarize yourself with the required steps and evaluate

More information

Installation Guide for the JK Wrangler 4-Inch Suspension System with FlexArms

Installation Guide for the JK Wrangler 4-Inch Suspension System with FlexArms INSTALLATION GUIDE Installation Guide for the JK Wrangler 4-Inch Suspension System with FlexArms TeraFlex, Inc. Tera5680 Manufacturing, Inc. W Dannon Way 5251 South Commerce West Jordan, UT 84081 Dr. Phone/801.288.2585

More information

Air Trap TATSU2. Copyright 2013 by TLV CO., LTD. All rights reserved ISO 9001/ ISO M-02 (TATSU2) 7 August 2013.

Air Trap TATSU2. Copyright 2013 by TLV CO., LTD. All rights reserved ISO 9001/ ISO M-02 (TATSU2) 7 August 2013. 172-65177M-02 (TATSU2) 7 August 2013 ISO 9001/ ISO 14001 Manufacturer Kakogawa, Japan is approved by LRQA LTD. to ISO 9001/14001 Air Trap TATSU2 Copyright 2013 by TLV CO., LTD. All rights reserved 1 Contents

More information

Tillotson Tc3A Carburator

Tillotson Tc3A Carburator Tillotson Tc3A Carburator 176 FUEL SYSTEMS - 5B-11 CENTER BOWL TYPE CARBURETOR Removal 1. Remove front cowl cover and wrap-around cowl. 2. Remove swivel link from lower carburetor. (Figure 2) 3. Loosen

More information

MS2200, MS2500, and MS3000 Suspension Installation Manual ON/OFF HIGHWAY SUSPENSION SYSTEM

MS2200, MS2500, and MS3000 Suspension Installation Manual ON/OFF HIGHWAY SUSPENSION SYSTEM MS22, MS25, and MS3 Suspension Installation Manual ON/OFF HIGHWAY SUSPENSION SYSTEM 972.547.62 8.445.736 FAX: 972.542.97 725 E. UNIVERSITY ST. McKINNEY, TEXAS 7569 www.watsonsuspensions.com Watson & Chalin

More information