STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 808 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY.

Size: px
Start display at page:

Download "STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 808 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY."

Transcription

1 Description Materials Design Speed Construction Method of Measurement Basis of Payment STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 808 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY January 29, Description. This work consists of furnishing, coordinating, installing, maintaining, operating, tracking, monitoring and subsequently removing a digital speed limit (DSL) sign assembly as well as providing the related Work Zone Speed Zone (WZSZ) Tracking Report Materials. Furnish materials conforming to: Digital Speed Limit (DSL) Sign Assembly Design Speed. Due to the variable nature of Work Zone Speed Zones (WZSZs) the contractor shall consider the multiple speed limits affecting the work zone at any given time and ensure the Temporary Traffic Control Devices (TTCDs) are initially set up in a manner such that they always meet the minimum requirements for device spacing, taper rates, clear zones, buffer spaces, etc. regardless of the speed limit displayed on the DSL Sign Assembly. On the initial approaches to the work zone, the design speed for the placement of TTCDs (e.g. drums, cones, portable barrier, etc.) shall remain at the original posted speed limit. For locations within the work limits where the TTCD will only be in place when workers are present (and all TTCD will be cleared from the roadway when workers are not present [display of original posted speed limit on the DSL Sign Assemblies]), the design speed used to determine the design of TTC and related devices (device spacing, taper rates, etc) shall be based upon the speed limit in effect at the time the TTCD are in place and workers are present. For locations within the work limits where any TTCD will remain in place when workers are not present (display of original posted speed limit or warranted speed limit reduction for when workers are not present on the DSL Sign Assemblies), then the design speed used for the design of TTC and related devices shall be based upon the more conservative speed limit for each individual parameter (e.g., original posted speed limit or warranted speed limit reduction for when workers are not present for tapers, buffers, clear zone, etc., and the warranted reduced speed limit for when workers are present for device spacing, etc.) Construction. Furnish, coordinate, install, maintain, operate, track, monitor and subsequently remove Digital Speed Limit (DSL) Sign Assemblies, and related supplemental 1

2 signage, per plan notes, Standard Construction Drawing (SCD) MT , Ohio Manual on Uniform Traffic Control Devices (OMUTCD) and in accordance with the following requirements: Notify the Engineer in writing 7 calendar days in advance of implementation of an approved WZSZ. Do not implement a WZSZ until a Work Zone Speed Limit Revision Form has been completed and approved by the Department and returned to the Contractor. Prior to first activation of the DSL Sign Assembly(ies), make arrangements with an authorized service agent to assure prompt service in the event of failure. All DSL Sign Assemblies shall be delivered, relocated and removed from the project with deactivated Speed Limit Sign Beacons and the digital speed limit display blanked out. Exact placement of DSL Sign Assemblies will be as directed by the Engineer. Each time a DSL Sign Assembly is installed or relocated, fine tune the positioning of the assembly with oncoming traffic using the sight tube. Once the DSL Sign Assemblies are in position, display the original speed limit. Erect the supplemental signage (W3-H5b signs and R2-1 signs indicating the resumption of the legal speed limit at the end of the WZSZ) and cover or remove the existing speed limit signage per SCD MT The Speed Limit Sign Beacons shall be in the alternating flashing mode (Activated) only when workers are present within the warranted work zone condition. Flash the Speed Limit Sign Beacons at a rate of not less than 50 or more than 60 times per minute. All other times, the Speed Limit Sign Beacons shall not be flashing (Deactivated). At all times, the digital display legend(s) on the DSL Sign Assembly(ies) shall show the appropriate numeric speed limit in accordance with the Warranted Work Zone Speed Limits for Work Zones on High-Speed ( 55 mph) Multi-Lane Highways table in the Work Zone Speed Zones (WZSZ) plan note. The digital display legends and Speed Limit Sign Beacons on the DSL Sign Assemblies shall not be automatically changed/activated/deactivated using a pre-programmed schedule. Activate the Speed Limit Sign Beacons no earlier than 30 minutes before workers arrive in the warranted work zone condition and deactivate no later than 30 minutes after workers depart the warranted work zone condition. Change the digital display legend on the DSL Sign Assembly to the warranted speed limit no earlier than 30 minutes before workers arrive and no later than 30 minutes after workers depart from a warranted work zone condition. Secure/Lock the power supply and hand control enclosure so that unauthorized users cannot tamper with the power supply and hand controls. Maintain the DSL Sign Assemblies, supplemental signage and existing speed limit signage in good working order in accordance with the provisions of C&MS Verify the installed DSL Sign Assemblies are functional and are in good working order on a daily/nightly basis. Reposition the DSL Sign Assemblies using the sight tube for any assemblies out of alignment. 2

3 Except as noted below, after the work that warranted the WZSZ reduction is complete, deactivate the Speed Limit Sign Beacons, blank out the digital display legend, and remove the DSL Sign Assemblies, supplemental signage and restore the original speed limit signing. DSL Sign Assemblies may be left in place during times when the conditions do not warrant a WZSZ reduction, provided that the digital display legend on the DSL Sign Assembly shows the original posted speed limit and the Speed Limit Sign Beacons are deactivated. DSL Sign Assemblies may be left in this condition for up to 14 days, but no longer than until the end of the sign month. Any WZSZ left in place in accordance with this provision must remain as a complete WZSZ and all documentation, maintenance, etc. requirements remain in effect until the WZSZ is removed. By the end of the 14 days or the end of the sign month (whichever occurs first), deactivate the Speed Limit Sign Beacons, blank out the digital display legend, and remove the DSL Sign Assemblies, supplemental signage and restore the original speed limit signing. Relocation of DSL Sign Assemblies to new location(s) within the project limits shall occur between conditions that warrant a WZSZ. The original speed limit signing shall be restored, DSL Sign Assembly Speed Limit Sign Beacons shall be deactivated and the digital display legend shall be blanked out during relocation. Once the DSL Sign Assembly(ies) have been relocated, proceed with positioning and installation as described in prior paragraphs. Limit the active portion of the WZSZ to only the active portion of the project and the work that warrants the WZSZ reduction. A WZSZ in one direction does not automatically constitute a WZSZ in the opposite direction. Manage, coordinate and sign multiple WZSZs spaced less than 1 mile from one another, in the same direction of traffic flow, as a single WZSZ (within the same project and/or between adjacent projects). From the time of initial installation through the final removal, all activations and deactivations of the Speed Limit Sign Beacons, as well as all changes in the speed limit on the digital display legends of each DSL Sign Assembly, shall be logged at the time of occurrence using the Work Zone Speed Zone (WZSZ) Tracking Report (Traffic Engineering Manual Form ). The upto-date WZSZ Tracking Report shall be furnished to the Engineer beginning 7 calendar days after initial installation of the first DSL Sign Assembly and weekly (every 7 calendar days) thereafter until all activations/deactivations/changes for all DSL Sign Assemblies have been submitted (through the time of final removal of all DSL Sign Assemblies). At any time, all or part of the WZSZ Tracking Report may be requested by the Engineer or local law enforcement. Upon request, provide the information to the Engineer within 1 business day. Notify the Engineer upon final removal of the DSL Sign Assemblies. Do not use speed feedback signing within the work zone project limits. DSL Sign Assemblies are not queue detection warning systems and shall not be used in such a manner Method of Measurement. Measurement will begin when each unit initially begins active service and will continue until the Engineer determines the DSL is no longer needed, temporarily or permanently. 3

4 Quantities are measured by the maximum number of DSL Sign Assemblies necessary and in place at any one time during each individual sign month of use. Each DSL Sign Assembly shall be paid for only once, per sign month, regardless of how many times it is moved/replaced, activated/deactivated or how many times the digital display legend on the sign legend is changed. Payment shall be in full sign months. Individual sign month quantities shall not be increased solely based on use of the option to leave a WZSZ in place up to 14 days, but no longer than until to the end of the sign month, during times when conditions do not warrant a WZSZ reduction. A Sign Month will be deducted if the contractor removes the DSL from the project without the Engineer s determination that it is no longer, temporarily or permanently, needed for the project. Any failure shall not result in one or more DSL Sign Assemblies or supplemental signs being out of service for more than 12 hours, including weekends. During the failure time period the speed limit at the subject location(s) must continue to be appropriately controlled and must display the appropriate speed limit to the roadway users at any given time, using static R2-1 speed limit signage. Failure to comply may result in an order to stop work and to restore the original speed limit and/or in the Engineer directing the contractor to take appropriate action to safely control the regulatory speed limit. The entire cost to control the regulatory speed limit during the failure time period and beyond, if applicable, shall be at no cost to the Department. Functional DSL Sign Assembly(ies) displaying an incorrect legend on the digital display(s) shall not be considered a failure and shall instead be considered to be a disincentive violation or noncompliance occurrence depending on the value being shown (if showing a speed limit lower than warranted then a disincentive shall be applied; if showing a speed limit higher than warranted the DSL Sign Assemby(ies) will be found to be in non-compliance and a sign month deduction shall apply, per Assembly) Basis of Payment. Bid price to furnish, coordinate, install, maintain, operate, track, monitor, subsequently remove DSL Sign Assembly(ies) and provide the WZSZ Tracking Report shall be on a sign month basis. A sign month, for WZSZ purposes, shall be a 30-day period that starts on the initial day of each DSL Sign Assembly activation. Included in the bid item price shall be the coordination of the WZSZ with ODOT, applicable law enforcement agency(ies) and any adjacent projects/wzsz. The expense of covering or removal, and subsequent restoration of existing Speed Limit or Minimum Speed Limit signs, including any necessary supports, shall be included in the pay item for the Digital Speed Limit (DSL) Sign Assembly. All installations, relocations and removals, of supplemental signs, including signs and necessary supports, shall be included in the pay item for Digital Speed Limit (DSL) Sign Assembly. Except as described below for a disincentive, the Engineer may remove payment for DSL Sign Assemblies if one or more DSL Sign Assemblies and/or supplemental signage are found to be in non-compliance with this Supplemental Specification (including, but not limited to: failure to submit the completed WZSZ Tracking Report within the established time frame, failure to implement a warranted work zone speed limit reduction on the digital display legend during applicable conditions, or failure to activate or deactivate the Speed Limit Sign Beacons during applicable conditions). Payment shall be removed in full sign months. Failure to return to compliance within 12 hours may result in an order to stop work and to restore the original speed 4

5 limit and/or in the Engineer directing the contractor to take appropriate action to safely control the regulatory speed limit, at no cost to the Department. A disincentive shall be deducted as per the following calculation (per occurrence, per direction of traffic) if one or more DSL Sign Assemblies are found to be in violation by operating without warrant and approval and/or negatively impacting traffic (e.g., reductions without an approved Work Zone Speed Limit Revision Form, slowing traffic when and/or where not permitted, etc.) Disincentive Per Hour in Violation = (Units x Rate) + $600 Units = Total Number of DSL Sign Assemblies in Violation Rate = Rate per Table 1 TABLE 1* Rate (Cost per Hour) AADT 0-50K >50K-75K >75K-100K 100K % Trucks 5 MPH Reductions 70 to 65 mph $155 $195 $235 $295 $310 $390 $390 $ to 60 mph $180 $230 $270 $340 $365 $455 $455 $ to 55 mph $215 $270 $320 $405 $430 $540 $535 $ to 50 mph $255 $325 $385 $485 $515 $645 $645 $ MPH Reductions 70 to 60 mph $335 $425 $505 $635 $675 $845 $845 $1, to 55 mph $395 $495 $595 $745 $790 $995 $990 $1, to 50 mph $470 $590 $710 $885 $945 $1,185 $1,180 $1, to 45 mph $570 $715 $860 $1,075 $1,145 $1,435 $1,430 $1, MPH Reductions 70 to 55 mph $550 $690 $825 $1,035 $1,105 $1,385 $1,380 $1, to 50 mph $655 $820 $980 $1,230 $1,305 $1,640 $1,635 $2, to 45 mph $785 $985 $1,180 $1,480 $1,575 $1,970 $1,965 $2,465 *For speed limit reduction combinations not listed in Table 1, contact the Office of Roadway Engineering for the applicable rate. A spreadsheet ( DSL and Temporary Flatsheet Speed Limit Sign Disincentive Calculator ) to assist in calculating the total disincentive costs can be found on the Office of Construction Administration s website. No additional compensation shall be provided beyond the sign month bid item price. The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 614E18700 Sign Mnth Digital Speed Limit (DSL) Sign Assembly 5

6 Designer Note: Use only in accordance with the Traffic Engineering Manual (TEM) Part 6, Section for situations that meet the criteria for using Work Zone Speed Zones (WZSZ; freeway/expressway/multi-lane highways with original pre-construction speed limits of 55 mph or higher where the work zone condition is at least a 0.5 mile in length as defined by TEM Part 12 Section , with an expected work duration of at least three hours AND where the work zone impacts the travel lanes or shoulder (i.e., lane closure(s), lane shift(s), crossover, contraflow, shoulder closure(s)). Information regarding the use of traditional flatsheet signing for WZSZs can be found in TEM Parts 6 (Section ) and 12. A WZSZ shall not be used for Moving/Mobile activities, as defined by the OMUTCD. Speed feedback signing shall not be used within the work zone project limits. WZSZ DSL Sign Assemblies are regulatory devices; speed feedback signing are not regulatory. Use of both signs throughout the same work zone may lead to driver confusion or may negatively impact the compliance of the regulatory signage. When a WZSZ using DSL Sign Assemblies is required Plan Note (TEM Section ), Supplemental Specification 808 and Standard Construction Drawing MT shall be included in the plans. Change Order Note: Include the following requirements when writing a change order to add Supplemental Specification 808 for the use of Work Zone Speed Zones (WZSZ) using Digital Speed Limit (DSL) Sign Assemblies. The language does not need added to change orders adjusting quantities only on locations/areas already covered by an existing approved Work Zone Speed Limit Revision Form along with applicable notes, supplemental specifications and standard construction drawing. Notify the Engineer in writing 14 calendar days in advance of conditions that meet the qualifications for use of Work Zone Speed Zones (WZSZs) using Digital Speed Limit (DSL) Sign Assemblies as outlined the Work Zone Speed Zones Plan Note. Provide: a description of the work (including location of workers), limits of the work (including facility type and original posted speed limit value), duration of the work, type and duration of temporary traffic control devices that will be used, and any additional pertinent information as requested by the Engineer. Do not implement a WZSZ until a Work Zone Speed Limit Revision Form has been completed and approved by the Department and returned to the Contractor. When a WZSZ using DSL Sign Assemblies is required Plan Note (TEM Section ), Supplemental Specification 808 and Standard Construction Drawing MT shall be included in the plans. 6

1200 ZONES AND STUDIES Traffic Engineering Manual

1200 ZONES AND STUDIES Traffic Engineering Manual TABLE OF CONTENTS Part 12 - ZONES AND TRAFFIC ENGINEERING STUDIES 1200 GENERAL... 12-5 1201 TRAFFIC CONTROL ZONES... 12-5 1202 SCHOOL ZONES... 12-5 1203 SPEED ZONES... 12-5 1203-1 General... 12-5 1203-2

More information

SECTION 12 - CONSTRUCTION AREA TRAFFIC CONTROL TABLE OF CONTENTS

SECTION 12 - CONSTRUCTION AREA TRAFFIC CONTROL TABLE OF CONTENTS SECTION 12 - CONSTRUCTION AREA TRAFFIC CONTROL TABLE OF CONTENTS Section Page 12-1 GENERAL...12.1 12-2 FLAGGING...12.1 12-2.01 Flaggers...12.1 12-2.02 Flagging Costs...12.1 12-3 TRAFFIC-HANDLING EQUIPMENT

More information

Work Zone Safety & New Interstate Resurfacing Provision

Work Zone Safety & New Interstate Resurfacing Provision 2017 CAPA Presentation Work Zone Safety & New Interstate Resurfacing Provision Steve Kite, PE State Work Zone Engineer Work Zone Safety Data In 2016, Approximately 600 construction projects across NC (not

More information

Created by: St. Louis County

Created by: St. Louis County Created by: Victor Lund, PE Traffic Engineer St. Louis County Ken Johnson, PE, PTOE State WZ, etc. MnDOT Why do workers want speed limits? How effective are speed limits in work zones? New legislation

More information

801-R-xxx LAW ENFORCEMENT OFFICER FOR WORK ZONE SAFETY. (Adopted xx-xx-17)

801-R-xxx LAW ENFORCEMENT OFFICER FOR WORK ZONE SAFETY. (Adopted xx-xx-17) 801-R-xxx LAW ENFORCEMENT OFFICER FOR WORK ZONE SAFETY (Adopted xx-xx-17) Description This work shall consist of providing a Law Enforcement Officer, LEO, to assist with the safe, efficient, orderly movement

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 961 PORTABLE TRAFFIC SIGNALS OCTOBER 17, 2008

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 961 PORTABLE TRAFFIC SIGNALS OCTOBER 17, 2008 961.01 Description 961.02 Prequalification 961.03 Requirements STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 961 PORTABLE TRAFFIC SIGNALS OCTOBER 17, 2008 961.01 Description. This

More information

Colorado Revised Statutes Automated vehicle identification systems

Colorado Revised Statutes Automated vehicle identification systems Colorado Revised Statutes 42-4-110.5. Automated vehicle identification systems (1) The general assembly hereby finds and declares that the enforcement of traffic laws through the use of automated vehicle

More information

PN /21/ SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS

PN /21/ SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS PN 420-10/21/2016 - SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS DESCRIPTION: The surface tolerance specification requirements are modified as follows for all pavements of constant width with at least

More information

Section 6H.01 Typical Applications

Section 6H.01 Typical Applications December 27, 2010 Draft Page 6H-1 Section 6H.01 Typical Applications Support: 01 Whenever the acronym TTC is used in this Chapter, it refers to temporary traffic control. 02 The needs and control of all

More information

Applicable California Vehicle Code Sections, 2015 Edition

Applicable California Vehicle Code Sections, 2015 Edition Applicable California Vehicle Code Sections, 2015 Edition Speed limits in California are governed by the California Vehicle Code (CVC), Sections 22348 through 22413; also, pertinent sections are found

More information

Table Standardized Naming Convention for ERD Files

Table Standardized Naming Convention for ERD Files S-1 (2399) PAVEMENT SURFACE SMOOTHNESS (2013 version) DO NOT REMOVE THIS. IT NEEDS TO STAY IN FOR THE CONTRACTORS. Always use with SP2005-111 (CONCRETE PAVING MIX SPECIFICATIONS PAVEMENT) and SP2005-140

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT MAPLE STREET UNDERPASS BRIDGE (MM 106.0)

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT MAPLE STREET UNDERPASS BRIDGE (MM 106.0) MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT 2016.04 MAPLE STREET UNDERPASS BRIDGE (MM 106.0) Make the following changes to the bid documents: In the Contract Documents, Part 2 Special Provisions,

More information

Louisiana s s Work Zone Task Force Work Zone Improvements

Louisiana s s Work Zone Task Force Work Zone Improvements Louisiana s s Work Zone Task Force Work Zone Improvements Louisiana Asphalt Technology Conference Shreveport, Louisiana February 24, 2005 Charles Adams, P.E., PTOE Why Improve Work Zones? Number of Work

More information

TRAFFIC REGULATION APPROVAL PROCESS

TRAFFIC REGULATION APPROVAL PROCESS Approved: Effective: August 22, 2017 Review: June 21, 2017 Office: Traffic Engineering and Operations Topic No.: 750-010-011-e Department of Transportation PURPOSE TRAFFIC REGULATION APPROVAL PROCESS To

More information

LaDOTD s s New Traffic Control Details

LaDOTD s s New Traffic Control Details LaDOTD s s New Traffic Control Details Louisiana Pavement Conference Baton Rouge, Louisiana October 7, 2004 Charles Adams, P.E., PTOE Objectives Traffic Background Information What Drove the Department

More information

Work Zone Safety. Mike Marr Industrial Safety Consultant Ohio Bureau of Workers Compensation Division of Safety & Hygiene

Work Zone Safety. Mike Marr Industrial Safety Consultant Ohio Bureau of Workers Compensation Division of Safety & Hygiene Work Zone Safety Mike Marr Industrial Safety Consultant Ohio Bureau of Workers Compensation Division of Safety & Hygiene 1 Agenda Manuals/Codes/Statistics Setup & Removal of Work Zones Devices and Locations

More information

POLICY FOR THE ESTABLISHMENT AND POSTING OF SPEED LIMITS ON COUNTY AND TOWNSHIP HIGHWAYS WITHIN MCHENRY COUNTY, ILLINOIS

POLICY FOR THE ESTABLISHMENT AND POSTING OF SPEED LIMITS ON COUNTY AND TOWNSHIP HIGHWAYS WITHIN MCHENRY COUNTY, ILLINOIS POLICY FOR THE ESTABLISHMENT AND POSTING OF SPEED LIMITS ON COUNTY AND TOWNSHIP HIGHWAYS WITHIN MCHENRY COUNTY, ILLINOIS MCHENRY COUNTY DIVISION OF TRANSPORTATION 16111 NELSON ROAD WOODSTOCK, IL 60098

More information

DESCRIPTION This work consists of measuring the smoothness of the final concrete or bituminous surface.

DESCRIPTION This work consists of measuring the smoothness of the final concrete or bituminous surface. 2399 PAVEMENT SURFACE SMOOTHNESS 2399.1 DESCRIPTION This work consists of measuring the smoothness of the final concrete or bituminous surface. A Definitions The Department defines Smoothness as the Mean

More information

Act 229 Evaluation Report

Act 229 Evaluation Report R22-1 W21-19 W21-20 Act 229 Evaluation Report Prepared for Prepared by Table of Contents 1. Documentation Page 3 2. Executive Summary 4 2.1. Purpose 4 2.2. Evaluation Results 4 3. Background 4 4. Approach

More information

Diagram 1 - Shoulder Assistance

Diagram 1 - Shoulder Assistance Diagram - Shoulder Assistance Approx. skip (40 ). Notify K. C. Scout. Turn on the emergency directional flashers and top rear facing strobe lights. 3. Pull to the shoulder and stop approximately 40 feet

More information

Traffic Regulations Guidelines

Traffic Regulations Guidelines Traffic Regulations Guidelines PREPARED BY TRAFFIC AND SAFETY June, 2012 Providing the highest quality transportation services for economic benefit and improved quality of life. MDOT Traffic and Safety

More information

60 70 Guidelines. Managing Speeds. Work Zones

60 70 Guidelines. Managing Speeds. Work Zones 50 40 30 60 70 Guidelines on Managing Speeds in Work Zones 50 40 30 60 70 This document summarizes available guidance on setting speed limits and managing speeds in work zones. The Manual on Uniform Traffic

More information

Night Work Specification

Night Work Specification Night Work Specification 1.0 Hours of Work The contractor is advised that most work for this contract will be carried out during night time hours. For the purposes of this contract night is defined as

More information

SN01 STANDARD NOTES CITY OF SAMMAMISH 2018 FLASHING YELLOW ARROW SIGNALS PROJECT NO. DATE BY APPR REVISION COSA0023 KING COUNTY WASHINGTON

SN01 STANDARD NOTES CITY OF SAMMAMISH 2018 FLASHING YELLOW ARROW SIGNALS PROJECT NO. DATE BY APPR REVISION COSA0023 KING COUNTY WASHINGTON STANDARD NOTES SN01 2 OF 8 ROADWAY PLAN PL01 3 OF 8 ROADWAY PLAN PL02 4 OF 8 LANE 10 105 150 205 270 450 500 550 11 12 SHOULDER 115 125 MINIMUM LANE CLOSURE TAPER LENGTH = L 165 225 295 180 245 320 5 25

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007 07-08001 Sheet 1 of 2 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007 SECTION 805 WORK ZONE TRAFFIC CONTROL AND SAFETY TYPICAL TRAFFIC CONTROL, 2-LANE

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA)

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA) MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA) CFS:TEH 1 of 10 APPR:KPK:JFS:07-07-16 FHWA:APPR:07-15-16 a. Description. This

More information

CAR 10-1 TRAFFIC CALMING CAR 10-1 OPR: Engineering 06/06

CAR 10-1 TRAFFIC CALMING CAR 10-1 OPR: Engineering 06/06 CAR 10-1 TRAFFIC CALMING CAR 10-1 OPR: Engineering 06/06 Purpose Section I Policy II I. Purpose The purpose of this Ordinance is to outline the City s response to the traffic complaints arising as a result

More information

ALLEGAN COUNTY ROAD COMMISSION. Adopted by the Board of County Road Commissioners, December 28, Sign Policy

ALLEGAN COUNTY ROAD COMMISSION. Adopted by the Board of County Road Commissioners, December 28, Sign Policy ALLEGAN COUNTY ROAD COMMISSION Adopted by the Board of County Road Commissioners, December 28, 2016 Sign Policy Common/Policies/Sign Policy 2016 TABLE OF CONTENTS Page I. Purpose and Background.................................

More information

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001 Revised April 5, 2005 Revised January 27, 2006 Prepared by: Steve Collin, Engineer 2.5 Revised by Douglas

More information

REVIEW OF THE DRAFT 2011 VA WORK AREA PROTECTION MANUAL. December 14, 2010 David Rush VDOT WZS Program Manager

REVIEW OF THE DRAFT 2011 VA WORK AREA PROTECTION MANUAL. December 14, 2010 David Rush VDOT WZS Program Manager REVIEW OF THE DRAFT 2011 VA WORK AREA PROTECTION MANUAL December 14, 2010 David Rush VDOT WZS Program Manager Manual on Uniform Traffic Control Devices (MUTCD) Released in December 2009 States have until

More information

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Portable Temporary Rumble Strips (PTRS) SPECIFIC SUBJECT: Guidelines for the

More information

CONTENTS I. INTRODUCTION... 2 II. SPEED HUMP INSTALLATION POLICY... 3 III. SPEED HUMP INSTALLATION PROCEDURE... 7 APPENDIX A... 9 APPENDIX B...

CONTENTS I. INTRODUCTION... 2 II. SPEED HUMP INSTALLATION POLICY... 3 III. SPEED HUMP INSTALLATION PROCEDURE... 7 APPENDIX A... 9 APPENDIX B... Speed Hump Program CONTENTS I. INTRODUCTION... 2 II. SPEED HUMP INSTALLATION POLICY... 3 1. GENERAL... 3 2. ELIGIBILITY REQUIREMENTS... 3 A. PETITION... 3 B. OPERATIONAL AND GEOMETRIC CHARACTERISTICS OF

More information

THE CORPORATION OF THE TOWNSHIP OF MIDDLESEX CENTRE BY-LAW NUMBER

THE CORPORATION OF THE TOWNSHIP OF MIDDLESEX CENTRE BY-LAW NUMBER THE CORPORATION OF THE TOWNSHIP OF MIDDLESEX CENTRE BY-LAW NUMBER 2006-052 BEING A BY-LAW TO REGULATE AND CONTROL PARKING WITHIN THE TOWNSHIP OF MIDDLESEX CENTRE WHEREAS the Municipal Act authorizes local

More information

DESIGNATED CONSTRUCTION ZONE SPEED FINES DOUBLE. Manitoba Infrastructure and Transportation. Infrastructure and Transportation. Traffic Engineering

DESIGNATED CONSTRUCTION ZONE SPEED FINES DOUBLE. Manitoba Infrastructure and Transportation. Infrastructure and Transportation. Traffic Engineering CONSTRUCTION DESIGNATED ZONE SPEED FINES DOUBLE Manitoba Infrastructure and Transportation Work Zone Traffic Control Manual Provincial Roads and Provincial Trunk Highways Infrastructure and Transportation

More information

PN 420-7/18/ SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS

PN 420-7/18/ SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS PN 420-7/18/2014 - SURFACE SMOOTHNESS REQUIREMENTS FOR PAVEMENTS DESCRIPTION: The surface tolerance specification requirements are modified as follows for all mainline lanes and collector-distributor road

More information

NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 DATED 5/03/2013

NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 DATED 5/03/2013 NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 DATED 5/03/2013 Control 6237-93-001 Project RMC - 623793001 Highway US0075 County DALLAS Ladies/Gentlemen: Attached please find an addendum on the above captioned

More information

TRAFFIC DEPARTMENT 404 EAST WASHINGTON BROWNSVILLE, TEXAS City of Brownsville Speed Hump Installation Policy

TRAFFIC DEPARTMENT 404 EAST WASHINGTON BROWNSVILLE, TEXAS City of Brownsville Speed Hump Installation Policy A. GENERAL Speed humps are an effective and appropriate device for safely reducing vehicle speeds on certain types of streets when installed accordance with the provisions of this policy. In order for

More information

PERFORMANCE ACTIVITY 603 SIGNS

PERFORMANCE ACTIVITY 603 SIGNS PERFORMANCE ACTIVITY 603 SIGNS WORK DESCRIPTION 3 WORK DESCRIPTION 4 WORK DESCRIPTION 6 New Install Maintenance / Replace Temporary 603 SIGNS ACTIVITY DESCRIPTION Install new signs and maintain and replace

More information

SECTIO N 610 PAVEMENT SMO O THNESS

SECTIO N 610 PAVEMENT SMO O THNESS SECTIO N 610 PAVEMENT SMO O THNESS 610.1 Description. This work shall consist of measuring the smoothness of the final pavement surface. Smoothness shall be measured using the International Roughness Index

More information

1400 MISCELLANEOUS Traffic Engineering Manual

1400 MISCELLANEOUS Traffic Engineering Manual TABLE OF CONTENTS Part 14 - MISCELLANEOUS 1400 GENERAL... 14-3 1415 RUMBLE STRIPS (INCLUDING STRIPES) IN THE ROADWAY... 14-4 1415-1 General... 14-4 1415-2 Transverse Rumble Strips... 14-4 1415-2.1 General...

More information

INDUSTRIAL HAUL AGREEMENT

INDUSTRIAL HAUL AGREEMENT INDUSTRIAL HAUL AGREEMENT PUBLIC WORKS MEMORANDUM OF AGREEMENT entered into this day of, A.D., 20(yr). BETWEEN: PARKLAND COUNTY a County incorporated under the laws of the Province of Alberta, (hereinafter

More information

DIVISION 311 MISCELLANEOUS ELECTRICAL RULES

DIVISION 311 MISCELLANEOUS ELECTRICAL RULES DIVISION 311 MISCELLANEOUS ELECTRICAL RULES 918-311-0000 Design, Planning and Lay Out of Electrical Installations by Supervising Electricians A licensed supervising electrician may design, plan and lay

More information

SN01 STANDARD NOTES CITY OF SAMMAMISH 2018 INTERSECTION IMPROVEMENTS PROJECT NO. DATE BY APPR REVISION COSA0023 KING COUNTY WASHINGTON

SN01 STANDARD NOTES CITY OF SAMMAMISH 2018 INTERSECTION IMPROVEMENTS PROJECT NO. DATE BY APPR REVISION COSA0023 KING COUNTY WASHINGTON STANDARD NOTES SN01 2 OF 17 STANDARD NOTES SN02 3 OF 17 SITE PREP & T.E.S.C. NOTES GENERAL NOTES SITE PREP & T.E.S.C. PLAN SP01 4 OF 17 SITE PREP & T.E.S.C. NOTES GENERAL NOTES SITE PREP & T.E.S.C. PLAN

More information

PERMIT FOR INSTALLATION ON COUNTY RIGHTS-OF-WAY: ACCESS DRIVEWAYS RESIDENTIAL

PERMIT FOR INSTALLATION ON COUNTY RIGHTS-OF-WAY: ACCESS DRIVEWAYS RESIDENTIAL PERMIT FOR INSTALLATION ON COUNTY RIGHTS-OF-WAY: ACCESS DRIVEWAYS RESIDENTIAL Submit To Martin County Judge s Office P.O. Box 1330 Stanton Texas 79782-1330 mhernandez@co.martin.tx.us APPLICATION: Permittee

More information

Questions and Answers from March 1 st, 2016 Roadbuilders Introduction Webinar

Questions and Answers from March 1 st, 2016 Roadbuilders Introduction Webinar Questions and Answers from March 1 st, 2016 Roadbuilders Introduction Webinar No. Question Answer 1 Is it mandatory to have an Engineer sign off on all TMP's containing a lane closure even in a 50 or 60

More information

SAN JOAQUIN VALLEY AIR POLLUTION CONTROL DISTRICT

SAN JOAQUIN VALLEY AIR POLLUTION CONTROL DISTRICT SAN JOAQUIN VALLEY AIR POLLUTION CONTROL DISTRICT DATE: 3/1/10, updated 5/5/10 TO: Interested Parties SUBJECT: Frequently asked questions regarding compliance with Rule 4320, Advanced Emission Reduction

More information

ADOPTED REGULATION OF THE STATE SEALER OF WEIGHTS AND MEASURES. LCB File No. R Effective December 14, 1998

ADOPTED REGULATION OF THE STATE SEALER OF WEIGHTS AND MEASURES. LCB File No. R Effective December 14, 1998 ADOPTED REGULATION OF THE STATE SEALER OF WEIGHTS AND MEASURES LCB File No. R146-98 Effective December 14, 1998 EXPLANATION Matter in italics is new; matter in brackets [ ] is material to be omitted. AUTHORITY:

More information

STATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS

STATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS STATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS SUB TOTAL SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT

More information

CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS TRAFFIC CONTROL STANDARDS

CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS TRAFFIC CONTROL STANDARDS CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS TRAFFIC CONTROL STANDARDS Supplement to O.D.O.T. TRAFFIC ENGINEERING MANUAL November 26, 2013 Revisions to the June 22, 2011 edition are noted by a vertical line

More information

TITLE 16. TRANSPORTATION CHAPTER 27. TRAFFIC REGULATIONS AND TRAFFIC CONTROL DEVICES

TITLE 16. TRANSPORTATION CHAPTER 27. TRAFFIC REGULATIONS AND TRAFFIC CONTROL DEVICES NOTE: This is a courtesy copy of this rule. The official version can be found in the New Jersey Administrative Code. Should there be any discrepancies between this text and the official version, the official

More information

SERIES INSTALLATION & WARRANTY GUIDE SUREGUIDE RETURN ROLLER

SERIES INSTALLATION & WARRANTY GUIDE SUREGUIDE RETURN ROLLER SERIES INSTALLATION & WARRANTY GUIDE SUREGUIDE RETURN ROLLER Installation Instructions Once a problem area has been identified, it is important to adhere to the safety regulations regarding setup, maintenance

More information

CATEGORY 500 PAVING SECTION 535 PAVEMENT SURFACE PROFILE

CATEGORY 500 PAVING SECTION 535 PAVEMENT SURFACE PROFILE CATEGORY 500 PAVING 1 of 9 SECTION 535.01 DESCRIPTION. This work shall consist of measuring the roughness of the final surface of hot mix asphalt (HMA) or portland cement concrete (PCC) pavements. The

More information

TITLE: Vehicle Parking and Traffic Regulations and Procedures

TITLE: Vehicle Parking and Traffic Regulations and Procedures TITLE: Vehicle Parking and Traffic Regulations and Procedures EFFECTIVE DATE: August 29, 2016 1. REGULATIONS 1.1 General Regulations 1.1.1 All vehicle operators are required to comply with all Parking

More information

Chapter 17 TRAFFIC AND VEHICLES. Adoption of Uniform Rules of the Road. Temporary Traffic Regulations.

Chapter 17 TRAFFIC AND VEHICLES. Adoption of Uniform Rules of the Road. Temporary Traffic Regulations. Chapter 17 TRAFFIC AND VEHICLES Article I. Article II. Article III. In General. Section 17.1 Adoption of Uniform Rules of the Road. Section 17.2 Temporary Traffic Regulations. Section 17.3 Traffic Speed,

More information

Ohio Department of Transportation. Special Hauling Permits Section West Broad St. Columbus, Ohio Third Floor Mailstop #5140

Ohio Department of Transportation. Special Hauling Permits Section West Broad St. Columbus, Ohio Third Floor Mailstop #5140 Ohio Department of Transportation Special Hauling Permits Section 1980 West Broad St. Columbus, Ohio 43223 Third Floor Mailstop #5140 1 When is a Permit Needed? Whenever a vehicle/load are to move on the

More information

ORDINANCE NO

ORDINANCE NO ORDINANCE NO. 16-938 AN ORDINANCE OF THE CITY OF LA PUENTE, CALIFORNIA ADDING CHAPTER 3.76 (SHOPPING CART REGULATIONS) TO TITLE 3 (PUBLIC SAFETY AND MORALS) OF THE LA PUENTE MUNICIPAL CODE WHEREAS, shopping

More information

Access Management Standards

Access Management Standards Access Management Standards This section replaces Access Control Standards on Page number 300-4 of the Engineering Standards passed February 11, 2002 and is an abridged version of the Access Management

More information

City of Sacramento Parking Services Division Temporary Tow Away No Parking Posting Guidelines

City of Sacramento Parking Services Division Temporary Tow Away No Parking Posting Guidelines City of Sacramento Parking Services Division Temporary Tow Away No Parking Posting Guidelines Posting Tow Away No Parking Signs/Barricades once Permit is Approved Once the Meter and Parking Space Reservation

More information

WHEREAS, Fees for parking meters, devices or timed parking systems have been historically approved by the City using the Ordinance process; and

WHEREAS, Fees for parking meters, devices or timed parking systems have been historically approved by the City using the Ordinance process; and 1 1 1 0 1 0 1 0 1 ORDINANCE NO. AN ORDINANCE OF THE CITY OF COCOA BEACH, FLORIDA, AMENDING THE CODE OF ORDINANCES, CHAPTER, TRAFFIC, AMENDING ARTICLE II PARKING METERS, BY DELETING REFERENCE TO: - THE

More information

Procedure Effective date Rescinds Vehicle Placement In or Near Moving Traffic 17 November January 2005

Procedure Effective date Rescinds Vehicle Placement In or Near Moving Traffic 17 November January 2005 Procedure Effective date Rescinds Vehicle Placement In or Near Moving Traffic 17 November 2008 1 January 2005 Reference Norwich Township Fire Department SOG #30 Page 1 of 6 Purpose: The purpose of this

More information

Anticipated Changes Based on 2009 Federal MUTCD

Anticipated Changes Based on 2009 Federal MUTCD Anticipated Changes Based on 2009 Federal MUTCD Section 1A.13 Meanings of text headings (Standard, d Guidance, Option, Support) relocated and clarified Standard d statements shall hll not be modified difid

More information

Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE

Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE Heber Light & Power Electric Service Rule No. 14 NET METERING SERVICE 1. Overview The Company offers Residential and Small General Service Customers net metering service that allows the Customer to use

More information

2013 Changes to the 2011 MMUTCD, Part 6 September 2013

2013 Changes to the 2011 MMUTCD, Part 6 September 2013 2013 Changes to the 2011 MMUTCD, Part 6 September 2013 The requirements for drum spacing in Sections 6C.07 (Page 557 (MI)) and 6F.63 (Page 604 (MI)) have been revised to more closely match the pavement

More information

SCDOT TRAFFIC SIGNAL SPECIAL PROVISIONS TRAFFIC CONTROL FOR TRAFFIC SIGNAL PROJECTS MAINTENANCE OF TRAFFIC

SCDOT TRAFFIC SIGNAL SPECIAL PROVISIONS TRAFFIC CONTROL FOR TRAFFIC SIGNAL PROJECTS MAINTENANCE OF TRAFFIC SCDOT TRAFFIC SIGNAL SPECIAL PROVISIONS TRAFFIC CONTROL FOR TRAFFIC SIGNAL PROJECTS MAINTENANCE OF TRAFFIC TRAFFIC CONTROL: The Contractor shall execute the item of Traffic Control as required by the Standard

More information

Town of Springdale Wrecker and Towing Services Agreement

Town of Springdale Wrecker and Towing Services Agreement Company Name: Vehicle Storage Location: Note: Storage location must be within 10 miles of Springdale town limits Town of Springdale Wrecker and Towing Services Agreement The undersigned towing and wrecker

More information

South Carolina. It s serious. Deadly serious.

South Carolina. It s serious. Deadly serious. South Carolina It s serious. Deadly serious. Work Zone Safety Guidelines for the South Carolina Department of Transportation, Municipalities, Counties, Utilities, and Contractors 2013 1 Table of Contents

More information

LCDOT DETOUR PROCEDURES. and GUIDELINES

LCDOT DETOUR PROCEDURES. and GUIDELINES LCDOT DETOUR PROCEDURES and GUIDELINES LCDOT Traffic Department (847) 377-7400 Rev 2/3/2017 ADVANCE ROAD CLOSED SIGNS (W20-3) These signs shall be a 48" x 48" Black Legend on Fluorscent Orange Sheeting.

More information

800 Access Control, R/W Use Permits and Drive Design

800 Access Control, R/W Use Permits and Drive Design Table of Contents 801 Access Control... 8-1 801.1 Access Control Directives... 8-1 801.2 Access Control Policies... 8-1 801.2.1 Interstate Limited Access... 8-1 801.2.2 Limited Access... 8-1 801.2.3 Controlled

More information

traversing them. Speed dips may be installed in lieu of speed humps where the 85 th percentile speed on a street is at least 36 mph.

traversing them. Speed dips may be installed in lieu of speed humps where the 85 th percentile speed on a street is at least 36 mph. County of San Mateo Department of Public Works Residential Speed Control Device Program PURPOSE The purpose of the Residential Speed Control Devices 1 Program is to provide a consistent, fair and cost-effective

More information

MISSOURI HIGHWAYS AND TRANSPORTATION PLANS FOR PROPOSED STATE HIGHWAY DESIGN DESIGNATION INDEX OF SHEETS LENGTH OF PROJECT SHEET NUMBER

MISSOURI HIGHWAYS AND TRANSPORTATION PLANS FOR PROPOSED STATE HIGHWAY DESIGN DESIGNATION INDEX OF SHEETS LENGTH OF PROJECT SHEET NUMBER DESIGN DESIGNATION A.A.D.T - XXXX = XXXX V = XX M.P.H PLANS FOR PROPOSED HIGHWAY INDEX OF SHEETS SHEET DESCRIPTION NUMBER TITLE SHEET ----------------------- 1 TYPICAL SECTIONS (TS) (1 SHEET)-- QUANTITIES

More information

SIDEWALK CAFE AND PARKING PATIO GUIDELINES

SIDEWALK CAFE AND PARKING PATIO GUIDELINES SIDEWALK CAFE AND PARKING PATIO GUIDELINES The following guidelines establish requirements for the licensing and operation of Sidewalk Cafes and Parking Patios located on City of Saskatoon right-of-way

More information

TRAFFIC ENGINEERING DIVISION

TRAFFIC ENGINEERING DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION MEMORANDUM GENERAL SUBJECT: Traffic Signs SPECIFIC SUBJECT: Speed Limit and Fine Signs in Work Zones DIRECTED TO: District Administrators

More information

CHAPTER 69 PARKING REGULATIONS

CHAPTER 69 PARKING REGULATIONS CHAPTER 69 PARKING REGULATIONS 69.01 Parking Limited or Controlled 69.07 Persons With Disabilities Parking 69.02 Park Adjacent to Curb 69.08 Truck Parking Limited 69.03 Park Adjacent to Curb One-way Street

More information

Work Zone Worker Protection

Work Zone Worker Protection Work Zone Worker Protection Field Guide Developed by American Traffic Safety Services Association 15 Riverside Parkway, Suite 100 Fredericksburg, VA 22406 (800) 272-8772 Web Address: www.atssa.com E-mail:

More information

Policy: Traffic and Parking Regulations

Policy: Traffic and Parking Regulations St. Mary s University Policy: Traffic and Parking Regulations Approver(s): Executive Council Authorizes release: Vice President, Administration and Finance Responsible office: University Police Department

More information

1

1 1 2 3 4 5 6 7 8 9 10 11 12 Breakdown of License Changes Definitions First Draft ROW License Changes in Revised Draft Explanation of Change Dockless sharing Shared active transportation vehicle NACTO recommendation

More information

TRAFFIC CONTROL REGULATIONS

TRAFFIC CONTROL REGULATIONS TRAFFIC CONTROL REGULATIONS Town of Southampton Applies to: Vehicles and Traffic in the Town of Southampton Select Board Original Adoption: November 2, 2017 Amended on: -- Last Reviewed by Select Board:

More information

Special Specification 7010 Debris Removal and Disposal

Special Specification 7010 Debris Removal and Disposal Special Specification 7010 Debris Removal and Disposal 1. DESCRIPTION Provide emergency removal and disposal of debris from the highway right of way which is created by a hurricane or other type of natural

More information

Work Zone Safety Initiatives and Research Efforts. Irene Soria Safety Evaluation Engineer Illinois Department of Transportation Safety Engineering

Work Zone Safety Initiatives and Research Efforts. Irene Soria Safety Evaluation Engineer Illinois Department of Transportation Safety Engineering Work Zone Safety Initiatives and Research Efforts Irene Soria Safety Evaluation Engineer Illinois Department of Transportation Safety Engineering TES Conference - October 17 th, 2012 Outline Work Zone

More information

NCUTCD Proposal for Changes to the Manual on Uniform Traffic Control Devices

NCUTCD Proposal for Changes to the Manual on Uniform Traffic Control Devices 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 TECHNICAL COMMITTEE: ITEM NUMBER: TOPIC: ORIGIN OF REQUEST: AFFECTED SECTIONS OF MUTCD: NCUTCD Proposal for Changes

More information

Vista Municipal Code

Vista Municipal Code Section 16.57.050 Private streets prohibited in certain zones. No lots zoned for multi-family, commercial, or industrial uses may be created using private street easements for access, except as provided

More information

PARKING AND TRAFFIC REGULATIONS

PARKING AND TRAFFIC REGULATIONS PARKING AND TRAFFIC REGULATIONS 2016-2017 Jersey Village High School 7600 Solomon Houston, Texas 77040 713-896-3400 CONTENTS Introduction Page 1 Guidelines Pages 2-7 1. Who must purchase a parking sticker?...2.............

More information

52.1 SNOW REMOVAL AND ICE CONTROL (TRUCK)

52.1 SNOW REMOVAL AND ICE CONTROL (TRUCK) 52.1 SNOW REMOVAL AND ICE CONTROL (TRUCK) 52.1.1 GENERAL The Work consists of loading trucks, snowplowing and the application of sand, salt or a sand and salt mixture to roadway surfaces. 52.1.2 MATERIALS

More information

SECTION ONE: ADMINISTRATION AUTHORITY PARKING REGULATIONS DISABLED PARKING PARKING CITATION AUTHORITY...

SECTION ONE: ADMINISTRATION AUTHORITY PARKING REGULATIONS DISABLED PARKING PARKING CITATION AUTHORITY... SECTION ONE: ADMINISTRATION... 3 100 AUTHORITY... 3 101 -... 3 102 - DISABLED PARKING... 3 103 - PARKING CITATION AUTHORITY... 3 120 CALIFORNIA VEHICLE CODE... 3 121 - APPLICATION... 3 122 - WORDS and

More information

Professionalism, Respect, Integrity, Dedication and Excellence

Professionalism, Respect, Integrity, Dedication and Excellence Professionalism, Respect, Integrity, Dedication and Excellence COLLEGE OF SOUTHERN NEVADA DEPARTMENT OF PUBLIC SAFETY - CAMPUS VEHICULAR AND PEDESTRIAN TRAFFIC REGULATION INSTRUCTION NO: LOCAL OPERATION

More information

Transporation Policies and Procedures CO 400.7:

Transporation Policies and Procedures CO 400.7: Transporation Policies and Procedures CO 400.7: Purpose To provide a framework of Transportation policies and procedures that can be implemented at Morehouse College under the direction of the Physical

More information

panelsizes:min.:30x30,std.:36x36,exp.:36x36,fwy.:48x48 levels:gscolorfill GSBWFILL GSOUTLINE chevronshoulderradius: constructpanels: pan

panelsizes:min.:30x30,std.:36x36,exp.:36x36,fwy.:48x48 levels:gscolorfill GSBWFILL GSOUTLINE chevronshoulderradius: constructpanels: pan panelsizes:min.:30x30,std.:36x36,exp.:36x36,fwy.:48x48 levels:gscolorfill GSBWFILL GSOUTLINE chevronshoulderradius:12.000 constructpanels:36 24 18 panelborderradius:12.000 chevrontipradius:12.000 panelstyle:warning.ssi

More information

AFFECTED SECTIONS OF MUTCD: Section 2C.36 Advance Traffic Control Signs Table 2C-4. Guidelines for Advance Placement of Warning Signs

AFFECTED SECTIONS OF MUTCD: Section 2C.36 Advance Traffic Control Signs Table 2C-4. Guidelines for Advance Placement of Warning Signs 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 RWSTC June 2012 RW # 3 TOPIC: Advance Traffic Control Signs TECHNICAL COMMITTEE: Regulatory &

More information

ORDINANCE NO. AN ORDINANCE TO AMEND TITLE 11 VEHICLES AND TRAFFIC, CHAPTER PARKING METERS, OF THE CODE OF ORDINANCES, CITY OF MEMPHIS

ORDINANCE NO. AN ORDINANCE TO AMEND TITLE 11 VEHICLES AND TRAFFIC, CHAPTER PARKING METERS, OF THE CODE OF ORDINANCES, CITY OF MEMPHIS ORDINANCE NO. AN ORDINANCE TO AMEND TITLE 11 VEHICLES AND TRAFFIC, CHAPTER 11 44 PARKING METERS, OF THE CODE OF ORDINANCES, CITY OF MEMPHIS WHEREAS, the City of Memphis has identified a need to provide

More information

To facilitate the extension of departmental services through third party testing organizations as provided for by CRS (b)

To facilitate the extension of departmental services through third party testing organizations as provided for by CRS (b) DEPARTMENT OF REVENUE Division of Motor Vehicles MOTORCYCLE RULES AND REGULATIONS FOR ALMOST ORGANIZATIONS 1 CCR 204-20 [Editor s Notes follow the text of the rules at the end of this CCR Document.] A.

More information

Evaluation of Request to Establish 15 MPH Speed Limits on Streets around Schools

Evaluation of Request to Establish 15 MPH Speed Limits on Streets around Schools Office of the City Manager To: From: Honorable Mayor and Members of the City Council Phil Kamlarz, City Manager Submitted by: Claudette Ford, Director, Public Works Subject: Evaluation of Request to Establish

More information

CLAY COUNTY MISSOURI HIGHWAYS AND TRANSPORTATION COMMISSION PLANS FOR PROPOSED STATE HIGHWAY NOT TO SCALE LENGTH OF PROJECT

CLAY COUNTY MISSOURI HIGHWAYS AND TRANSPORTATION COMMISSION PLANS FOR PROPOSED STATE HIGHWAY NOT TO SCALE LENGTH OF PROJECT DI E INDE OF SHEETS TYPICAL SECTIONS (TS) ( SHEET)--- QUANTITIES (QU) (7 SHEETS)--------- 3 PLAN-PROFILE (PP)------------------ REFERENCE POINTS (RP)-------------- COORDINATE POINTS (CP)------------- CULVERT

More information

PURPOSE POLICY. Page 1 of 6 / S.O.G Highway Operations Pascal Arnes Chief of Fire

PURPOSE POLICY. Page 1 of 6 / S.O.G Highway Operations Pascal Arnes Chief of Fire DECATUR TOWNSHIP FIRE DEPARTMENT STANDARD OPERATING GUIDELINE TITLE: HIGHWAY OPERATIONS SECTION: SAFETY NUMBER: 6.01 EFFECTIVE: JULY 1, 2014 THIS GUIDELINE SUPERSEDES ALL PREVIOUS GENERAL ORDERS, POLICIES,

More information

EXHIBIT A EAST VALLEY WATER DISTRICT SCHEDULE OF WATER AND WASTEWATER RATES AND CHARGES

EXHIBIT A EAST VALLEY WATER DISTRICT SCHEDULE OF WATER AND WASTEWATER RATES AND CHARGES EXHIBIT A EAST VALLEY WATER DISTRICT SCHEDULE OF WATER AND WASTEWATER RATES AND CHARGES UPDATED MAY 24, 2017 Table of Contents Section 1: Water Service Charges... 2 Monthly Water System Charge... 2 Commodity

More information

TITLE VII: TRAFFIC CODE 70. GENERAL PROVISIONS 71. PARKING, STOPPING, AND STANDING 72. TRAFFIC SCHEDULES

TITLE VII: TRAFFIC CODE 70. GENERAL PROVISIONS 71. PARKING, STOPPING, AND STANDING 72. TRAFFIC SCHEDULES TITLE VII: TRAFFIC CODE Chapter 70. GENERAL PROVISIONS 71. PARKING, STOPPING, AND STANDING 72. TRAFFIC SCHEDULES 1 2 Harrodsburg - Traffic Code CHAPTER 70: GENERAL PROVISIONS Section 70.01 Designation

More information

ORDINANCE NO

ORDINANCE NO ORDINANCE NO. 13 2012 AN ORDINANCE OF THE CITY OF ELIZABETHTOWN, KENTUCKY AMENDING SECTION 72: PARKING REGULATIONS OF THE ELIZABETHTOWN CODE OF ORDINANCES BE IT ORDAINED by the City Council of the City

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (IRI ACCEPTANCE CRITERIA)

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (IRI ACCEPTANCE CRITERIA) MICHIGAN DEPARTMENT OF TRANSPORTATION 03SP502(P) SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (IRI ACCEPTANCE CRITERIA) C&T:TEH 1 of 8 C&T:APPR:JFS:MJE:01-28-08 FHWA:APPR:02-01-08 a. Description. Provide

More information

Greater Cleveland Regional Transit Authority. Bus Stop Design Guidelines

Greater Cleveland Regional Transit Authority. Bus Stop Design Guidelines Greater Cleveland Regional Transit Authority Bus Stop Design Guidelines Contents Purpose... I Bus Stop Design & Location... 1 Bus Stop Planning... 1 Bus Stop Safety & Consolidation... 1 As Needed Basis...

More information

Regulation ECE Related Entries:

Regulation ECE Related Entries: Regulation ECE Related Entries: Responsible Office: ECE Associate Superintendent for Operations ECE-R: Traffic and Parking Procedures Las Cruces Public Schools TRAFFIC AND PARKING PROCEDURES I. PURPOSE

More information

Los Angeles County Metropolitan Transportation Authority Permit Parking Terms and Conditions

Los Angeles County Metropolitan Transportation Authority Permit Parking Terms and Conditions Los Angeles County Metropolitan Transportation Authority Permit Parking Terms and Conditions The following Terms and Conditions ( Agreement ) govern your account with Metro, which account may be administered

More information