1 Work Zone Safety Mike Marr Industrial Safety Consultant Ohio Bureau of Workers Compensation Division of Safety & Hygiene 1
2 Agenda Manuals/Codes/Statistics Setup & Removal of Work Zones Devices and Locations Duration of Work Maintenance of the Work Zone Flagging Procedures Questions 2
3 You Never Know!
4 MILES PER HOUR & STOP TIME 30 MPH = 44 Feet per Second 50 MPH = 73 Feet per Second 60 MPH = 88 Feet per Second 70 MPH = 103 Feet per Second 100 MPH = 146 Feet per Second
5 PERCEPTION / REACTION TIME Mental Process 1. Sensation something in the road! 2. Perception/recognition recognize, identify! 3. Situational awareness speed, time to impact, consequence, escape route! 4. Response selection decide what to do! Elapsed time; 1.5 to >2.5 seconds
6 PERCEPTION / REACTION TIME Average Movement Time Foot to brake 0.2 second Device Response Time Braking begins 0.1 second Total elapsed time (best case) before vehicle begins slowing seconds
7 PERCEPTION / REACTION 55 mph (80.67 ft/s) + Stopping Distance Time before braking begins 1.8 sec. ( ) x ft/s = Distance Traveled ft. + Stopping ft. TOTAL DISTANCE TRAVELED ft
8 PERCEPTION-REACTION TIME Industry Standard 2.5 seconds Older Driver - > 2.5 ~ 3.0 seconds Unexpected Event = > 2 to 3 times
9 Manuals ODOT FHWA OHIO OSHA ODOT - Part 6, MUTCD - MUTCD - Subpart G - Plans 9
10 PERRP: PERRP s Mission: The role and mission of PERRP is to ensure public employees in Ohio have safe and healthy working conditions. Public employers must furnish to each public employee a workplace free from recognized hazards that are causing or are likely to cause death or serious physical harm. This fundamental requirement is the foundation of the Public Employment Risk Reduction Act (the Act) which is also referred to as House Bill (HB) 308 and was enacted
11 Primary Reasons for Enforcing the Improve worker safety Work zones are one of the primary locations of public employee fatalities Minimize delay for motorists Manual FHWA
12 Part 6 Organization Section 6A General Information Section 6B Fundamental Principals Section 6C TTC* Elements Section 6D Pedestrian and Worker Safety Section 6E Flagger Control Section 6F TTC Zone Devices Section 6G TTC Zone Activities Section 6H Typical Applications Section 6I Incident Management FHWA
13 Four Little Words Should (Voluntary) Shall (Mandatory) Must (Mandatory) May (Voluntary) If a standard has a mandatory (shall or must) provision, then there are no options. If a standard has a voluntary provision (should or may) then the employer must consider those provisions to be minimum expectations, however, they can modify them to fit their circumstances.
14 Ohio Fatalities in Motor Vehicle Traffic Crashes and Work Zones Highway Crashes WZ Crashes Total , , , , , , , , , , Not available 186 people died in vehicle crashes in Ohio work zones in the eleven-year period from 2002 to 2012 (the most recent information available).
15 Importance of Protection Effective Temporary Traffic Control" saves lives Worker fatalities in Ohio workzones Worker fatalities nationally in workzones Source: workzonesafety.org
16 According to ODOT (2003 to 2012): 7 ODOT employees have been killed in construction zones in Ohio in the last decade from 2003 to ,945 vehicle crashes occurred in Ohio work zones in that same 10-year period 20,590 vehicle crashes occurred in Ohio work zones when workers were present 19,988 of the total vehicle crashes were rear end collisions The top three causes of work zone crashes are: Following too closely Failure to control Improper lane changes Excessive speed has directly resulted in more than 1,500 work zone crashes since 2003 Across the nation, you are more likely to be injured or killed in a work zone on a dry and sunny August afternoon than any other time of year
17 What Is a Temporary Traffic Control Zone? A TTC zone may include: o Work zone o Roadway incident o Special event FHWA FHWA
18 Parts of a Traffic Control Zone 1. Advance Warning Area 2. Transition Area 3. Buffer Area 4. Work Area 5. Termination Area 18
19 Parts of a Traffic Control Zone 19
20 20 Advance Warning Area
21 Regulatory Signs
22 Warning Signs 22
23 Advance Warning Area Advance Warning Signs Warning Information Communication Regulatory 23
24 Advance Warning Area Sign Spacing Chart 24 Low Speed < 45 M.P.H. High Speed > 45 M.P.H
25 Portable Changeable Message Signs
26 Advance Warning Area Changeable Message Signs 26
27 Transition Area Drums & Cones 36 lit/reflective drums 28 & 42 reflective cones. 27
28 Drums and Cones Standard requires uniformity for color of all drums If drums, cones, or tubular markers are used to channelize pedestrians, they shall be located such that there are no gaps between the bases of the devices, in order to create a continuous bottom. The height of each individual drum, cone, or tubular marker shall be no less than (36 in) to be detectable to users of long lanes.
29 Cones Cones shall be: Predominantly orange Made of a material that can be struck without causing damage to the impacting vehicle. For daytime and low speed roadways, cones shall be not less than 18 in in height. When cones are used on freeways and other high-speed highways or at night on all highways, or when more conspicuous guidance is needed, cones shall be a minimum of (28 in) in height. For nighttime use, cones shall be retro-reflectorized or equipped with lighting devices for maximum visibility.
30 30 Device Spacing Chart
31 Transition Area Flashing Arrow Panels Strongly recommend solid panels, not sequential. 31
32 Arrow Boards 48 x x x 48 - Type A -45 MPH & below -Type B -45 MPH & below -Type C -45 MPH & above NEVER use an arrow board in a two lane, one way closure use a Flagger! 32
33 Buffer Space 33 Buffer Space (Longitudinal) Speed (mph) Length (feet)
34 34 Work Zone Examples:
35 Example of 25 MPH Traffic Control Zone -Signs 100 apart -Transition cones minimum -Cone spacing 20 along taper and 25 after taper -Buffer space 55
36 Example of 35 MPH Traffic Control Zone -Signs 100 apart -Transition cones minimum -Cone spacing 20 along taper and 35 after taper -Buffer space 120
37 Example of 45 MPH Traffic Control Zone -Signs 350 apart -Transition cones minimum -Cone spacing 40 along taper and 45 after taper -Buffer space 220
38 Termination Area Optional but strongly recommended. Well worth the short additional time that it takes to install. Why wouldn t you get your crews into this simple, wise habit? 38
39 Work Zone Safety Single Lane Closure How to install and remove a single lane closure On a four lane road way. 39
40 Work Zone Safety Single Lane Closure 40 Work Area
41 Work Zone Safety Single Lane Closure 41
42 Work Zone Safety Single Lane Closure 42 Advance Warning signs
43 Work Zone Safety Single Lane Closure 43 Advance Warning Signs
44 Work Zone Safety Single Lane Closure 44 Arrow Board and Taper
45 Work Zone Safety Single Lane Closure 45 Complete
46 Work Zone Safety Single Lane Closure Removal Removal of the lane closure Is done in the exact opposite order 46
47 Work Zone Safety Single Lane Closure 47 Arrow Board and Taper
48 Work Zone Safety Single Lane Closure 48 Advance Warning Signs
49 Work Zone Safety Single Lane Closure 49 Work Area
50 Work Zone Safety Single Lane Closure 50 Freeway Setup
51 Lane Shift 51
52 Devices Type III Barricades Portable Gates 52
53 Devices Additional Traffic Control Devices Plastic Fence Caution Tape Safety Vest Hard Hats Temporary Pavement Tape Stop and Slow Paddles 53
54 Duration Of Work Long-term Intermediate-term Short-term Mobile 54
55 Duration of Work Short Term: 0 15 minutes. Truck emergency flashers and beacon lights minutes. Truck emergency flashers, beacon lights, correct size and amount of cones placed around work zone and a minimum of one correctly placed advanced warning sign. Correct arrow board strongly recommended - consider the location, crew/public safety, traffic volume, liability etc. 55
56 Duration of Work Intermediate Term: 60 minutes 3 days Truck emergency flashers, beacon lights, correct size and amount of cones placed around the work zone and all correctly placed advanced warning signs on all affected streets. Correct arrow board as required. 56
57 Duration of Work Long Term: Beyond 3 days. Permanently mounted, correct advanced warning signs on all affected streets. Truck emergency flashers, beacon lights, correct size and amount of cones placed around the work zone. Correct arrow board as required. 57
58 WORK DURATION Five Categories: Long-Term Stationary Intermediate-term Stationary Short-term Stationary Short Duration > 3 days > 12 hrs to 3 days includes overnight 1 hr to 12 hrs < 1 hr Mobile moves intermittently with stop times < 15 minutes or moves continuously
59 Mobile Work Often involve frequent short stops for activities Such as litter cleanup, pothole patching, or utility operations, and are similar to short-duration operations NCOSHA
60 60 They Do Help!
61 Mobile Work o TTC zones may include: Warning signs, high-intensity rotating, flashing, oscillating, or strobe lights on a vehicle, flags, and/or channelizing devices Flaggers A shadow vehicle equipped with an arrow panel or a sign following the work vehicle Appropriately colored and marked vehicles with signs, flags, high-intensity rotating, flashing, oscillating, or strobe lights, truck-mounted attenuators, and arrow panels or portable changeable message signs may follow a train of moving work vehicles
62 Work Zone Safety Maintenance of a Work Zone Cover or remove signs when not in use! Clean all traffic control equipment. Drive the zone after set up and through out the day - consider who may be coming through your set up at any time! Recognizing problems: skid marks, auto parts, damaged traffic control devices. 62 Always use Common Sense and Good Judgment!
63 Worker Safety Consideration - Training All workers should be trained on: Working safely adjacent to vehicular traffic Work zone traffic control techniques Device Usage Safety devices Traffic control devices Placement of traffic control devices Relevant OSHA Regulation 29 CFR , Safety Training and Education
64 Flagger Apparel
65 Section 6E.02 High-Visibility Safety Apparel o Apparel background (outer) material color shall be either fluorescent orange-red, or fluorescent yellow-green as defined in the standard. o The retro-reflective material shall be either orange, yellow, white, silver, yellow-green, or a fluorescent version of these colors. ATSSA for US DOT 65 FHA grant DTFH61-06-G-00004
66 Conspicuity Class 2 Conspicuity level for use in occupational activities where risk levels exceeding those in Class 1, such as where: 1. Greater visibility is desired during inclement weather conditions; 2. Complex backgrounds are present; 3. Employees are performing tasks which divert attention from approaching vehicle traffic 4. Vehicle or moving equipment speeds exceed 25 mph; or 5. Work activities take place in or near vehicle traffic. 66
67 Conspicuity Class 3 where risks exceed those in Class 2 1. Workers exposed to traffic > 50 mph; 2. Pedestrian worker & vehicle operator with task loads placing themselves in danger; 3. The wearer must be conspicuous through range of motion at a minimum distance of 1280 feet & be identifiable as a person.
68 Flagging Mandatory 18 x 18 minimum Stop/Slow Paddle with a minimum 7 handle. 68
69 Flagger Standard: A flagger shall be a person who provides temporary traffic control. For daytime work, the flagger's vest, shirt, or jacket shall be either orange, yellow, yellow-green, or a fluorescent version of these colors. For nighttime work, similar outside garments shall be retro-reflective. Flagger stations shall be located far enough in advance of the work space so that approaching road users will have sufficient distance to stop before entering the work space. Flags are only for emergency use.
70 Flagger Paddles The STOP/SLOW paddle shall have an octagonal shape on a rigid handle. STOP/SLOW paddles shall be at least 18 wide with letters at least 6 high and should be fabricated from light semi-rigid material. Background of the STOP face shall be red with white letters and border. The Background of the SLOW face shall be orange with black letters and border. When used at night, the STOP/SLOW paddle shall be retro-reflectorized.
71 Flagger Procedures The following methods of signaling with paddles shall be used: To stop road users, the flagger shall face road users and aim the STOP paddle face toward road users in a stationary position with the arm extended horizontally away from the body. To direct stopped road users to proceed, the flagger shall face road users with the SLOW paddle face aimed toward road users in a stationary position with the arm extended horizontally away from the body. To alert or slow traffic, the flagger shall face road users with the SLOW paddle face aimed toward road users in a stationary position with the arm extended horizontally away from the body.
72 Pedestrians Public safety. You & the crew s safety. Liability issues! Correctly close sidewalks when needed. 72
73 Work Zone Safety Record Keeping Detailed Accident Reports Pictures Sketches Any witness information and specific contacts 73
74 74
75 75
76 76
77 77
78 78
79 Summary Effective Temporary Traffic Control serves to: Warn Inform Guide Regulate 79
80 Work Zone Safety Questions? 80
South Carolina. It s serious. Deadly serious.
South Carolina It s serious. Deadly serious. Work Zone Safety Guidelines for the South Carolina Department of Transportation, Municipalities, Counties, Utilities, and Contractors 2013 1 Table of Contents
More informationWork Zone Safety Best Practices Traffic Engineering & Safety Conference October 18, Dean Mentjes Federal Highway Administration
Work Zone Safety Best Practices Traffic Engineering & Safety Conference October 18, 2017 Dean Mentjes Federal Highway Administration Juan Pava Illinois Department of Transportation 1 Setting the Stage:
More informationWork Zone Safety. Guidelines for Temporary Traffic Control
Work Zone Safety Guidelines for Temporary Traffic Control Revised April 2015 1 Table of Contents Introduction 3 Traffic Control Devices 4 Signs 4 Channelizing Devices 7 Lighting Devices 11 Component Parts
More informationSection 6H.01 Typical Applications
December 27, 2010 Draft Page 6H-1 Section 6H.01 Typical Applications Support: 01 Whenever the acronym TTC is used in this Chapter, it refers to temporary traffic control. 02 The needs and control of all
More information2013 Changes to the 2011 MMUTCD, Part 6 September 2013
2013 Changes to the 2011 MMUTCD, Part 6 September 2013 The requirements for drum spacing in Sections 6C.07 (Page 557 (MI)) and 6F.63 (Page 604 (MI)) have been revised to more closely match the pavement
More informationTemporary Traffic Control Plans
Temporary Traffic Control Plans US Department of Transportation Federal Highway Administration (FHWA) MUTCD 2009 EDITION Adopted by WSDOT December 19, 2011 with modifications per WAC 468-95. 2-1 Standard
More informationSECTION 12 - CONSTRUCTION AREA TRAFFIC CONTROL TABLE OF CONTENTS
SECTION 12 - CONSTRUCTION AREA TRAFFIC CONTROL TABLE OF CONTENTS Section Page 12-1 GENERAL...12.1 12-2 FLAGGING...12.1 12-2.01 Flaggers...12.1 12-2.02 Flagging Costs...12.1 12-3 TRAFFIC-HANDLING EQUIPMENT
More informationREVIEW OF THE DRAFT 2011 VA WORK AREA PROTECTION MANUAL. December 14, 2010 David Rush VDOT WZS Program Manager
REVIEW OF THE DRAFT 2011 VA WORK AREA PROTECTION MANUAL December 14, 2010 David Rush VDOT WZS Program Manager Manual on Uniform Traffic Control Devices (MUTCD) Released in December 2009 States have until
More informationTRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM
VIRGINIA DEPARTMENT OF TRANSPORTATION TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Portable Temporary Rumble Strips (PTRS) SPECIFIC SUBJECT: Guidelines for the
More informationREVIEW OF SIGNIFICANT CHANGES IN THE 2011 VIRGINIA WORK AREA PROTECTION MANUAL. VDOT Traffic Engineering Division Oc7, 2011 Presentation
REVIEW OF SIGNIFICANT CHANGES IN THE 2011 VIRGINIA WORK AREA PROTECTION MANUAL VDOT Traffic Engineering Division Oc7, 2011 Presentation VA Supplement to the MUTCD VDOT developed Supplements which consist
More informationWork Zone Worker Protection
Work Zone Worker Protection Field Guide Developed by American Traffic Safety Services Association 15 Riverside Parkway, Suite 100 Fredericksburg, VA 22406 (800) 272-8772 Web Address: www.atssa.com E-mail:
More informationTRAFFIC CONTROL PLAN ONE-LANE TWO-WAY TRAFFIC CONTROL TCP(1-2)-12 ONE LANE TWO-WAY CONTROL WITH YIELD SIGNS ONE LANE TWO-WAY CONTROL WITH FLAGGERS
DISCLAIMER: The use of this standard is governed by the "Texas Engineering Practice Act". No warranty of any kind is made by TxDOT for any purpose whatsoever. TxDOT assumes no responsibility for the conver-
More informationSN01 STANDARD NOTES CITY OF SAMMAMISH 2018 FLASHING YELLOW ARROW SIGNALS PROJECT NO. DATE BY APPR REVISION COSA0023 KING COUNTY WASHINGTON
STANDARD NOTES SN01 2 OF 8 ROADWAY PLAN PL01 3 OF 8 ROADWAY PLAN PL02 4 OF 8 LANE 10 105 150 205 270 450 500 550 11 12 SHOULDER 115 125 MINIMUM LANE CLOSURE TAPER LENGTH = L 165 225 295 180 245 320 5 25
More informationAnticipated Changes Based on 2009 Federal MUTCD
Anticipated Changes Based on 2009 Federal MUTCD Section 1A.13 Meanings of text headings (Standard, d Guidance, Option, Support) relocated and clarified Standard d statements shall hll not be modified difid
More informationAct 229 Evaluation Report
R22-1 W21-19 W21-20 Act 229 Evaluation Report Prepared for Prepared by Table of Contents 1. Documentation Page 3 2. Executive Summary 4 2.1. Purpose 4 2.2. Evaluation Results 4 3. Background 4 4. Approach
More informationNight Work Specification
Night Work Specification 1.0 Hours of Work The contractor is advised that most work for this contract will be carried out during night time hours. For the purposes of this contract night is defined as
More informationSN01 STANDARD NOTES CITY OF SAMMAMISH 2018 INTERSECTION IMPROVEMENTS PROJECT NO. DATE BY APPR REVISION COSA0023 KING COUNTY WASHINGTON
STANDARD NOTES SN01 2 OF 17 STANDARD NOTES SN02 3 OF 17 SITE PREP & T.E.S.C. NOTES GENERAL NOTES SITE PREP & T.E.S.C. PLAN SP01 4 OF 17 SITE PREP & T.E.S.C. NOTES GENERAL NOTES SITE PREP & T.E.S.C. PLAN
More informationREVISION VIRGINIA WORK AREA PROTECTION MANUAL. Effective April 1, 2015 for State Forces & Effective starting on the July 2015 Advertisement
REVISION 1 2011 VIRGINIA WORK AREA PROTECTION MANUAL Effective April 1, 2015 for State Forces & Effective starting on the July 2015 Advertisement VA Supplements to the MUTCD Revisions to VDOT developed
More informationLaDOTD s s New Traffic Control Details
LaDOTD s s New Traffic Control Details Louisiana Pavement Conference Baton Rouge, Louisiana October 7, 2004 Charles Adams, P.E., PTOE Objectives Traffic Background Information What Drove the Department
More informationSCDOT TRAFFIC SIGNAL SPECIAL PROVISIONS TRAFFIC CONTROL FOR TRAFFIC SIGNAL PROJECTS MAINTENANCE OF TRAFFIC
SCDOT TRAFFIC SIGNAL SPECIAL PROVISIONS TRAFFIC CONTROL FOR TRAFFIC SIGNAL PROJECTS MAINTENANCE OF TRAFFIC TRAFFIC CONTROL: The Contractor shall execute the item of Traffic Control as required by the Standard
More informationLouisiana s s Work Zone Task Force Work Zone Improvements
Louisiana s s Work Zone Task Force Work Zone Improvements Louisiana Asphalt Technology Conference Shreveport, Louisiana February 24, 2005 Charles Adams, P.E., PTOE Why Improve Work Zones? Number of Work
More information60 70 Guidelines. Managing Speeds. Work Zones
50 40 30 60 70 Guidelines on Managing Speeds in Work Zones 50 40 30 60 70 This document summarizes available guidance on setting speed limits and managing speeds in work zones. The Manual on Uniform Traffic
More informationMoving Operations. Introduction by. National Traffic Management & Work Zone Safety Conference March 2009
Driver Behavior Around Moving Operations Introduction by Mli Melisa D. Fil Finley, PE P.E. National Traffic Management & Work Zone Safety Conference March 2009 Mobile Operation Intrusions New York State
More informationAGC/MoDOT Annual COOP Meeting. Safety/Traffic Division & Specialty Contractors/Suppliers Breakout Session. December 5, 2018
AGC/MoDOT Annual COOP Meeting Safety/Traffic Division & Specialty Contractors/Suppliers Breakout Session December 5, 2018 District Work Zone Review St. Louis June 11-14, 2018 Central July 16-18, 2018 Northeast
More informationSTATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS
STATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS SUB TOTAL SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT
More informationDiagram 1 - Shoulder Assistance
Diagram - Shoulder Assistance Approx. skip (40 ). Notify K. C. Scout. Turn on the emergency directional flashers and top rear facing strobe lights. 3. Pull to the shoulder and stop approximately 40 feet
More informationA Literature Review of Roadway Safety for Firefighters
A Literature Review of Roadway Safety for Firefighters Mark J. Correira Mukilteo, Washington An applied research project submitted to the University of Cincinnati as part of the Firefighter Safety and
More informationExhibit H: Typical Traffic Control Plans. North Metro Natural Gas Pipeline Project Routing Study
Exhibit H: Typical Traffic Control Plans North Metro Natural Gas Pipeline Project Routing Study North Metro Natural Gas Pipeline Project Routing Study This page intentionally left blank. Contractor: CAMPOS
More information2014 Fall Asphalt Conference October 7, 2014 Richmond, VA Review of Virginia s 2013 Work Zone Crash Statistics
2014 Fall Asphalt Conference October 7, 2014 Richmond, VA Review of Virginia s 2013 Work Zone Crash Statistics David Rush WZ Safety Program Manager Traffic Engineering Division Review of Virginia s 2013
More informationLesson 5 4-Hour Version Slide: 4H-90
Lesson 5 4-Hour Version Slide: 4H-90 Lesson Objectives 4-Hour Version Slide: 4H-91 Lesson Objective: 5.1 4-Hour Version Slide: 4H-92 Making responder vehicles more visible improves safety by reducing the
More informationWork Zone Safety & New Interstate Resurfacing Provision
2017 CAPA Presentation Work Zone Safety & New Interstate Resurfacing Provision Steve Kite, PE State Work Zone Engineer Work Zone Safety Data In 2016, Approximately 600 construction projects across NC (not
More informationTRAFFIC CONTROL PLAN FOR SURVEYING OPERATIONS END ROAD WORK END ROAD WORK * ** END ROAD WORK END ROAD WORK. TCP (S-1a) TCP (S-1b)
kind is made by TxDOT for any purpose whatsoever. TxDOT assumes no responsibility for the conversion of this standard to other formats or for incorrect results or damages resulting from its use. 3 for
More informationHandbook for Temporary Traffic Control - Construction, Maintenance, and Utility Operations
Purdue University Purdue e-pubs Indiana Local Technical ssistance Program (LTP) Publications Indiana Local Technical ssistance Program (LTP) 7-2004 Handbook for Temporary Traffic Control - Construction,
More informationSTATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 808 DIGITAL SPEED LIMIT (DSL) SIGN ASSEMBLY.
808.01 Description 808.02 Materials 808.03 Design Speed 808.04 Construction 808.05 Method of Measurement 808.06 Basis of Payment STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 808
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007
07-08001 Sheet 1 of 2 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007 SECTION 805 WORK ZONE TRAFFIC CONTROL AND SAFETY TYPICAL TRAFFIC CONTROL, 2-LANE
More informationProcedure Effective date Rescinds Vehicle Placement In or Near Moving Traffic 17 November January 2005
Procedure Effective date Rescinds Vehicle Placement In or Near Moving Traffic 17 November 2008 1 January 2005 Reference Norwich Township Fire Department SOG #30 Page 1 of 6 Purpose: The purpose of this
More informationLee County DOT Traffic Section Design Standard for Sign Installation
Lee County DOT Traffic Section Design Standard for Sign Installation Traffic Section Table Of Contents Section Title 1. Sign Panel Material 2. Sign Shape 3. Posts 4. Fasteners 5. Retro reflectivity and
More informationDESIGNATED CONSTRUCTION ZONE SPEED FINES DOUBLE. Manitoba Infrastructure and Transportation. Infrastructure and Transportation. Traffic Engineering
CONSTRUCTION DESIGNATED ZONE SPEED FINES DOUBLE Manitoba Infrastructure and Transportation Work Zone Traffic Control Manual Provincial Roads and Provincial Trunk Highways Infrastructure and Transportation
More informationPURPOSE POLICY. Page 1 of 6 / S.O.G Highway Operations Pascal Arnes Chief of Fire
DECATUR TOWNSHIP FIRE DEPARTMENT STANDARD OPERATING GUIDELINE TITLE: HIGHWAY OPERATIONS SECTION: SAFETY NUMBER: 6.01 EFFECTIVE: JULY 1, 2014 THIS GUIDELINE SUPERSEDES ALL PREVIOUS GENERAL ORDERS, POLICIES,
More informationWork Zone Safety Initiatives and Research Efforts. Irene Soria Safety Evaluation Engineer Illinois Department of Transportation Safety Engineering
Work Zone Safety Initiatives and Research Efforts Irene Soria Safety Evaluation Engineer Illinois Department of Transportation Safety Engineering TES Conference - October 17 th, 2012 Outline Work Zone
More informationCreated by: St. Louis County
Created by: Victor Lund, PE Traffic Engineer St. Louis County Ken Johnson, PE, PTOE State WZ, etc. MnDOT Why do workers want speed limits? How effective are speed limits in work zones? New legislation
More informationIn Recognition of National Work Zone Safety Awareness Week April 11-15, 2016 Presentation Provided by Alabama Struck By Alliance
TOOL BOX SAFETY TALK In Recognition of National Work Zone Safety Awareness Week April 11-15, 2016 Presentation Provided by Alabama Struck By Alliance 1 GOALS To prevent highway construction and utility
More informationLCDOT DETOUR PROCEDURES. and GUIDELINES
LCDOT DETOUR PROCEDURES and GUIDELINES LCDOT Traffic Department (847) 377-7400 Rev 2/3/2017 ADVANCE ROAD CLOSED SIGNS (W20-3) These signs shall be a 48" x 48" Black Legend on Fluorscent Orange Sheeting.
More informationUnit 1 - Driving, Mobility and Laws. Chapter 1 - Driving and Mobility
The outline listed below is meant to be used as a reference for the placement of The Driving Zone 2 DVD clips into Responsible Driving text book where they may provide benefit and talking points for the
More informationBrownwood Portable Traffic Signals and AFADs Evaluation. Carl Johnson, P.E., TxDOT Brownwood District Melisa Finley, P.E., TTI
Brownwood Portable Traffic Signals and AFADs Evaluation Carl Johnson, P.E., TxDOT Brownwood District Melisa Finley, P.E., TTI Using Portable Traffic Signals (PTS) in Maintenance Operations: Brownwood District
More informationExcerpts from the Motor Vehicle Act and Motor Vehicle Act Regulation, Province of British Columbia
Excerpts from the Motor Vehicle Act and Motor Vehicle Act Regulation, Province of British Columbia Extracted May 20, 2015 for the purposes of Traffic Control Person Training WARNING These excerpts are
More informationImplementation of Automatic Flagger Assistance Devices (AFADs) for Minnesota Department of Transportation Flagger Operations
Implementation of Automatic Flagger Assistance Devices (AFADs) for Minnesota Department of Transportation Flagger Operations Edward F. Terhaar, Principal Investigator Wenck Associates, Inc. December 2014
More informationAPPENDIX A State Requirements
APPENDIX A State Requirements Note: This list was compiled as a service only and is not intended as a legal representation of a state s specifications, standards or guidelines. Please contact the state
More informationThe final test of a person's defensive driving ability is whether or not he or she can avoid hazardous situations and prevent accident..
It is important that all drivers know the rules of the road, as contained in California Driver Handbook and the Vehicle Code. However, knowing the rules does not necessarily make one a safe driver. Safe
More informationWork Zone Changes Since We Last Met 2016 Louisiana Transportation Conference. Barry L. Lacy, P.E. Work Zone/Claims/Audit Engineer
Work Zone Changes Since We Last Met 2016 Louisiana Transportation Conference Barry L. Lacy, P.E. Work Zone/Claims/Audit Engineer Louisiana State Motto Why is Work Zone Safety Important? US Work Zone Fatalities
More informationWork Zone Safety Intrusion Mitigation
Work Zone Safety Intrusion Mitigation Advanced Warning and Risk Evasion Lee Cole VP EHS CRH Americas Materials Lee.Cole@na.crh.com Curt Davison Director of AWARE (407) 353-1140 cbdavison@oldcastlematerials.com
More informationTTI TRAFFIC SAFETY CONFERENCE. John A. Barton, P.E.
TTI TRAFFIC SAFETY CONFERENCE John A. Barton, P.E. Introduction TxDOT Mission Work with others to provide safe and reliable transportation solutions for Texas. 2 Mission Zero Is a Journey toward: Zero
More informationVirginia Department of Education
Virginia Department of Education Module Three Transparencies Basic Maneuvering Tasks: Low Risk Environment Topic 1 -- Basic Maneuvers Topic 2 -- Vision and Perception Topic 3 -- Controlling Risk Using
More informationSEGMENT SIXTEEN - Other Risks and Hazards
SEGMENT SIXTEEN - Other Risks and Hazards After studying this segment you should have a greater understanding of other risks and hazards that are less common in the Seafood Industry such as working from
More informationPurdue Road School West Lafayette IN
Purdue Road School West Lafayette IN Plastic Safety Systems, Inc. Tim Cox National Sales Manager Kenny Kolberg Roadway Safety Consultant Indiana Work Zone Facts Source: IN DOT In 2013, 13 fatalities in
More informationDEFENSIVE DRIVING COMMUNITY SERVICES FOR THE DEVELOPMENTALLY DISABLED
DEFENSIVE DRIVING COMMUNITY SERVICES FOR THE DEVELOPMENTALLY DISABLED WHAT DOES IT MEAN TO DRIVE DEFENSIVELY? Defensive driving is a technique you can apply while operating your own or an agency vehicle,
More informationGARDEN STATE. 1 Active Work Zone When Flashing 36x36 W Advisory Speed 10 18x18 W Advisory Speed 15 18x18 W
ROAD SIGNS, SIGN POSTS AND TRAFFIC CONTROL ITEMS - BID TABULATION IFB #15-012 (All Bids) Garden State Highway Products Contact: Joe McCracken 1740 E. Oak Road Vineland, NJ 08361 Phone: 856-692-7572 Fax:
More informationDefensive Driving Policy
Date: 01 January 2015 To: All Chieftain Contract Services LLC Employees From: Scott Wiegers, Director of Safety, Chieftain Contract Services LLC Re: Defensive Driving Policy Defensive Driving Policy Chieftain
More informationFlagger Workbook VERSION 01-15
AMERICAN TRAFFIC SAFETY SERVICES ASSOCIATION Flagger Workbook VERSION 01-15 Endorsed by AASHTO In Cooperation with FHWA AMERICAN TRAFFIC SAFETY SERVICES ASSOCIATION ATSSA s Online Flagger Certification
More informationHighway Construction Worker Dies When Struck By Semi-Tractor Trailer Incident Number: 03KY030
Highway Construction Worker Dies When Struck By Semi-Tractor Trailer Incident Number: 03KY030 Kentucky Fatality Assessment and Control Evaluation Program Kentucky Injury Prevention and Research Center
More informationDEPARTMENTAL MATERIAL SPECIFICATIONS TRAFFIC CONTROL PLAN TYPICAL DETAILS WZ(TD)-13 BARRIER DELINEATION WITH MODULAR GLARE SCREENS
Concrete Barrier NOTES: 1. Length of Safety Glare Fence will be specified elsewhere in the plans. 2. The cumulative nominal length of the modular units shall equal the length of the individual sections
More information3. What is the most important aspect of social skills as a driver?
Student LESSON 1 Page 1 YOUR DRIVING TASK 1. What skills does driving require? Social Skills: You must interact successfully with other people. All drivers bring their own problems and skill levels to
More informationSafeZone Sign Stands. Stand Features
SafeZone Sign Stands Stand Features Crash Designed Break-Away Base Quick Release System for all modular attachments and accessories Pull Pin/Kick Release for easy deployment of legs Independently adjustable
More informationWorksite Safety Update Promoting safety in road construction
Worksite Safety Update Promoting safety in road construction No 116 February 2012 In this Edition: Temporary Safety Barrier Developments Page 1 Internal Traffic Control Plans for Improved Site Safety Page
More informationSIGNING UPDATES MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD), 2009 EDITION. CLIFF REUER SDLTAP WESTERN SATELLITE (c)
SIGNING UPDATES MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD), 2009 EDITION CLIFF REUER SDLTAP WESTERN SATELLITE 605-773-5108 605-209-8932 (c) MUTCD 2009 EDITION MUTCD http://mutcd.fhwa.dot.gov/ Purchase
More informationDefensive Driving. BLR Business & Legal Resources 1406
Defensive Driving Session Objectives You will be able to: Identify driving hazards Understand defensive driving techniques Use defensive driving techniques to prevent accidents and injuries on the road
More informationMobile Barrier Trailer
Mobile Barrier Trailer Protecting our employees History Born out of the need to protect employees working on highways (June 2004) 4 years of research and development Manufacture and deployment of the Mobile
More informationHeavy Vehicle Visibility
Heavy Vehicle Visibility Industry Technical Council Advisory Procedure Printed by 3M Traffic Safety Systems in the interest of improving truck safety, through greater visibility Disclaimers This Code of
More informationPedestrian Safety In Forklift Operations: An Introduction
Pedestrian Safety In Forklift Operations: An Introduction Welcome Cisco-Eagle is a national and international material handling systems integration company with customers in all 50 states and over 70 nations.
More informationTHE FUTURE OF SAFETY IS HERE
THE FUTURE OF SAFETY IS HERE TOYOTA S ADVANCED ACTIVE SAFETY PACKAGES: TSS-C AND TSS-P Crash protection starts with crash prevention. Collisions that result in injury may be caused by the delay in a driver
More informationOccupational Driving Safety Programs: The Driver
Occupational Driving Safety Programs: The Driver Karen Puckett Director, Workplace Safety Texas Department of Insurance, Division of Workers Compensation (DWC) 1 Driving in Texas No deathless days in 2014
More informationCLAY COUNTY MISSOURI HIGHWAYS AND TRANSPORTATION COMMISSION PLANS FOR PROPOSED STATE HIGHWAY NOT TO SCALE LENGTH OF PROJECT
DI E INDE OF SHEETS TYPICAL SECTIONS (TS) ( SHEET)--- QUANTITIES (QU) (7 SHEETS)--------- 3 PLAN-PROFILE (PP)------------------ REFERENCE POINTS (RP)-------------- COORDINATE POINTS (CP)------------- CULVERT
More informationRoadside Responder is Struck by a Box Truck and Dies Incident Number: 11KY006
Roadside Responder is Struck by a Box Truck and Dies Incident Number: 11KY006 Photograph of location where roadside responder was struck by box truck. Kentucky Fatality Assessment and Control Evaluation
More informationTITLE 16. TRANSPORTATION CHAPTER 27. TRAFFIC REGULATIONS AND TRAFFIC CONTROL DEVICES
NOTE: This is a courtesy copy of this rule. The official version can be found in the New Jersey Administrative Code. Should there be any discrepancies between this text and the official version, the official
More informationPERFORMANCE ACTIVITY 603 SIGNS
PERFORMANCE ACTIVITY 603 SIGNS WORK DESCRIPTION 3 WORK DESCRIPTION 4 WORK DESCRIPTION 6 New Install Maintenance / Replace Temporary 603 SIGNS ACTIVITY DESCRIPTION Install new signs and maintain and replace
More informationTEST SUMMARY AND FRAMEWORK TEST SUMMARY
Washington Educator Skills Tests Endorsements (WEST E ) TEST SUMMARY AND FRAMEWORK TEST SUMMARY TRAFFIC SAFETY Copyright 2014 by the Washington Professional Educator Standards Board 1 Washington Educator
More informationQuestions and Answers from March 1 st, 2016 Roadbuilders Introduction Webinar
Questions and Answers from March 1 st, 2016 Roadbuilders Introduction Webinar No. Question Answer 1 Is it mandatory to have an Engineer sign off on all TMP's containing a lane closure even in a 50 or 60
More information2003 EDITION. Illinois Supplement to the National Manual on Uniform Traffic Control Devices. Division of Highways
2003 EDITION Illinois Supplement to the National Manual on Uniform Traffic Control Devices Division of Highways ILLINOIS SUPPLEMENT TO THE NATIONAL MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES INTRODUCTION
More informationSupport: The Crossbuck (R15-1) sign assigns right-of-way to rail traffic at a highway-rail grade crossing.
TECHNICAL COMMITTEE: Railroad and Light Rail Transit Technical Committee DATE OF ACTION: June 25, 2004 TOPIC: Crossbuck with Yield or Stop Signs and Advance Signs. STATUS: Accepted by the National Committee
More informationAFFECTED SECTIONS OF MUTCD: Section 2C.36 Advance Traffic Control Signs Table 2C-4. Guidelines for Advance Placement of Warning Signs
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 RWSTC June 2012 RW # 3 TOPIC: Advance Traffic Control Signs TECHNICAL COMMITTEE: Regulatory &
More informationSlow Down! Why speed is important in realizing your Vision Zero goals and how to achieve the speeds you need
Slow Down! Why speed is important in realizing your Vision Zero goals and how to achieve the speeds you need Lake McTighe, METRO Joel McCarroll, ODOT Jenna Marmon, ODOT Matt Ferris-Smith, PBOT Oregon Active
More informationCollect and analyze data on motorcycle crashes, injuries, and fatalities;
November 2006 Highway Safety Program Guideline No. 3 Motorcycle Safety Each State, in cooperation with its political subdivisions and tribal governments and other parties as appropriate, should develop
More informationNight Driving. Monthly Training Topic NV Transport Inc. Safety & Loss Prevention
Night Driving Monthly Training Topic NV Transport Inc. Safety & Loss Prevention Introduction Night driving is difficult for many people. Driving in the dark is much different from driving during the daylight
More informationWork Zone Traffic Control Inspection Ratings Report 2005
Work Zone Traffic Control Report 25 Maryland Department of Transportation State Highway Administration Work Zone Traffic Control Report 25 State Maintained Highway System - IS, US, MD Prepared By Traffic
More informationOutsource Practices & Policies OPP
Outsource Practices & Policies OPP 0900-300.2 SAFE OPERATION OF VEHICLES Introduction The purpose of this practice is to provide procedures for all employees of Outsource who drive on company business
More informationDefensive Driving Training
Defensive Driving Training Department of Administrative Services Loss Control Services Why is this training presentation needed? Because people like this are taking their Driver s Test. Customer was on
More informationMAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT MAPLE STREET UNDERPASS BRIDGE (MM 106.0)
MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT 2016.04 MAPLE STREET UNDERPASS BRIDGE (MM 106.0) Make the following changes to the bid documents: In the Contract Documents, Part 2 Special Provisions,
More informationINCIDENT COMMAND PONCHOS: LHV-5ANSI-IC or HV-5ANSI-IC ANSI CLASS 2
LHV-5ANSI (Available in Lime or Orange) Visi-Cool ANSI Mesh 2" 3M silver reflective stripes PROTECTION ANSI-107-1999 COMPLIANT LH V-4ANSI-PC (Lime o nly) Fluorescent Lime/Yellow with 3 pkts Imported LH
More informationOhio Department of Transportation. Special Hauling Permits Section West Broad St. Columbus, Ohio Third Floor Mailstop #5140
Ohio Department of Transportation Special Hauling Permits Section 1980 West Broad St. Columbus, Ohio 43223 Third Floor Mailstop #5140 1 When is a Permit Needed? Whenever a vehicle/load are to move on the
More informationObjectives. Understand defensive driving techniques. Increase awareness of safe driving behaviors
Defensive Driving Objectives Understand defensive driving techniques Increase awareness of safe driving behaviors Provide insight into identifying and anticipating hazards encountered while driving Why
More informationpanelsizes:min.:30x30,std.:36x36,exp.:36x36,fwy.:48x48 levels:gscolorfill GSBWFILL GSOUTLINE chevronshoulderradius: constructpanels: pan
panelsizes:min.:30x30,std.:36x36,exp.:36x36,fwy.:48x48 levels:gscolorfill GSBWFILL GSOUTLINE chevronshoulderradius:12.000 constructpanels:36 24 18 panelborderradius:12.000 chevrontipradius:12.000 panelstyle:warning.ssi
More informationDRIVER EDUCATION FORUM 5/10/2007 SFC. T. ARCARO
DRIVER EDUCATION FORUM 5/10/2007 SFC. T. ARCARO CRASHES Motor vehicle crashes are the leading cause of death for people ages 16 through 24 years old. The fatality rate for young drivers 16 through 19 years
More informationINDEX. Long Sleeve T-Shirt One pocket with harness tape configuration. Hooded Sweatshirt Zipper front closurre with 2 pockets
#2013-9/15 INDEX Class 2 FR Vests... 3 Lightweight and affordable, Class 2 vests conform to ASTM F1506 and are available in 3 styles: Standard Traditional vest layout with harness tape configuration and
More informationTwo-Lane, Two-Way Roads
Two-Lane, Two-Way Roads road consisting of two opposing lanes of undivided traffic. Two-Lane Two-Way *Drawings Not To Scale mndot.gov/fieldmanual Field Manual January 08 Intermediate Volume Up to 00 DT
More informationTemporary Traffic Control Manual
Temporary Traffic Control Manual For Street Construction and Maintenance Operations in the City of Appleton Prepared by the City of Appleton Department of Public Works Engineering Division Traffic Section
More informationWork Zone Traffic Control
Work Zone Traffic Control AGC/ Annual Meeting Bob Pappe, PE, PLS Traffic-Roadway Engineer Oregon Department of Transportation Chapter 1: TCP Design Introduction 1 Work Zone Traffic Control Update from
More informationIn the Interest of Safety
Operation Lifesaver Presents: In the Interest of Safety Andy Blenko 1 It Happens Every Day. 2 United States Highway Rail Crossing Incidents 2500 2280 2096 2000 1500 2013 2014 1000 Ohio Ranking No. 8 of
More informationSafety... Sometimes it can t be dependent on reflectivity alone. ATSSA s Proud Recipient
Safety... Sometimes it can t be dependent on reflectivity alone. ATSSA s Proud Recipient The Problem Traffic Control professionals have long recognized that certain sign situations are more critically
More informationMaine Turnpike Authority
Company Name Total Bid Amount CPM Constructors - Freeport, ME $1,309,765.25 Scott Construction Corporation - Portland, ME $1,528,840.00 Wyman & Simpson Inc. - Richmond, ME $1,674,845.00 Page 1 of 10 CPM
More informationPage 1 of KA
Page 1 of 10 5 Contact the Area Engineer at 620-384-7821 for RAP sample location. Page 2 of 10 SS-1HP or approved alternate shall be used for Tack. Page 3 of 10 Ú City limit or Urban boundary No Centerline
More information