Agenda for discussions in the 39 th meeting of the STU Coordination Committee to be held under the chairmanship of ProSecretary (MPP& Power)

Size: px
Start display at page:

Download "Agenda for discussions in the 39 th meeting of the STU Coordination Committee to be held under the chairmanship of ProSecretary (MPP& Power)"

Transcription

1 Agenda for discussions in the 39 th meeting of the STU Coordination Committee to be held under the chairmanship of ProSecretary (MPP& Power) 1. Evacuation arrangement for Beaskund HEP (9 MW) & other SHPs in Palchan valley:- a) 33/220 kv MVA sub station in the yard of Allain Dhuangan HEP (Revised Time Line ): In its 38 th meeting held on , Committee was apprised that Project Authorities of Allain Dhuangan HEP had stopped the construction activities on which had not only led to further delay in commissioning of the sub station but had also resulted in loss to the Contractor for mobilization of the equipment. Committee directed that all the pending issues with ADHPL be sorted out and under no circumstances work should be held up. HPPTCLmay update the Committee. b) 33 kv DIC Palchan-Prini line: Forest Case: In the last meeting of Committee held on , it was apprised that: FCA case is under process and will be resubmitted to forest Department in December, 2014 in conformity with guide lines issued on HPPTCLmay update the Committee.. 2. Construction of 4 Nos. Transmission Projects to be built by HPPTCLwith Financial assistance by ADB (Tranche-I): - Progress review of 4 Nos. Transmission Projects being built by HPPTCLwith financial assistance by ADS: 1

2 i) 22/66/220 kv. (22/66 kv. 2x10 MVA+66/220 kv MVA) Pooling station at Bhoktoo +LlLO of one circuit of 220 kv Kashang- Bhaba Line- 22/66 kv portion- Revised time line In its 38 th meeting of the Committee, it was apprised that there is slippage in commissioning of 22/66 kv portion and the revised target for commissioning of 66/22 kv portion is HPPTCLmay update the Committee. 66/220 kv portion- Revised Time Line Director (Technical), HPSEBL had informed that there are capacity constraints in their 66 kv Nathpa-Ghanvi-I-Kotla SIC line and under the present loading conditions, only 3 MW additional power can be evacuated. In order to evacuate power of other projects through HPSEBL system till regular arrangements are commissioned by HPPTCL, 66 kv Nathpa-Ghanvi-I- Kotla line along with 66/220 kv transformer at Kotla shall require augmentation and, for terminating one circuit of 220 kv Kashang-Bhaba line (charged at 66 kv) at Nathpa, 66 kv bay shall have to be installed. Cost of these works shall have to be shared by the IPPs. Committee had directed HPSEBL to immediately call a meeting of all the IPPs and devise a mechanism for sharing of cost and early completion of interim arrangements.. HPSEBLmay update the Committee. 2

3 ii) 220/400 kv, 315 MVA P.S near Pragati Nagar+ LlLO of both circuits of 400 kv Ihakri- Abdullapur DIC Line.- COD-30 th June, :- In its 38 th meeting of the Committee held on 19.1l.2014, progress of this ongoing work was reported as under: The work of retaining wall is in progress (7 mtr. Raft concreting completed). Matter regarding approach road to site through Pvt. Land has been finalized. Owner expects quip pro quid and wants the release of his power connection for allowing access. HPSEBL assured to extend help for early release of power connection HPPTCLand HPSEBLmay update the Committee. iii) 220 kv D/C High Capacity Line from Hatkoti to 220/400 kv P.S near Pragati Nagar.-COD- 30 th June, :- In the last meeting of Committee held on 19.1l.2014, it was apprised that: FCA case for diversion of forest land for Stage-I submitted to MOEF, New Delhi has been returned for revision in conformity with fresh guide lines issued on Case is being revised and shall be resubmitted by Committee constituted for acquisition of private locations. HPPTCLmay update the Committee. 3

4 iv) 66/220 kv, 2x80/100 MVA+220/400 kv, 2x315 MVA P.S at Wangtoo+ LlLO of both circuits of 220 kv and 400 kv Lines COD- 220 kv portion - 31st October, 2015 and 400 kv portion-30 th April, 2016:-. In the last meeting of Committee held on , it was apprised that: Revenue Department to transfer the land to Power Deptt. and there after it shall be transferred to HPPTCL. Schedule shall be reworked after take over of the land. HPPTCLmay update the Committee. 3. Construction of 33/220 kv GIS Sub Station at Phojal in Naggar Valley in Distt. Kullu (Revised Time Line ) In the 38 th meeting of the Committee held on , it was apprised that: a: Control Room Building 220 kv and 33 kv C & R panels erected. Testing of internal wiring completed. Sub station Automation system panels and FOTE Panel erected. b: 220 kv GIS Building Erection of 220 kv GIS completed. Sub station assembly completed. Minor defects detected shall be rectified in a week. c: HT cables for 4 Nos. 33 kv line bays, 3 transformers & 1 station transformer have been laid & power cabling work between 220 kv GIS.and C & R panels completed. d: Transformer Erection: All the three units of power transformers erected. Erection work of 4th (spare) unit is also completed except damaged material, which is yet to be received. Neutral formation work is in progress. 4

5 Committee was apprised that interim arrangement for evacuation of power of Baragaon HEP (24 MW) i.e. LlLO of 33 kv Naggar- Bajaura line is under implementation by the Developer of Baragaon HEP with costs to be reimbursed by HPSEBL. The work is in progress and shall be completed in 10 days..hpptcland HPSEBLmay update the Committee. LlLO of 220 kv Prini- Nalagarh Line (Revised Time Line ): In its 38 th meeting of the Committee held on , it was reported that: a: Work on laying of foundations stc protection work has been completed on 23 locations and 2 No. legs of 24thtower location (total locations 24 Nos). is in progress on 6 locations. 14 towers have been erected and work is in progress on erection of 3 more towers. Sagging work of Km out of total 6.8 Km completed. b: Tower material of 5 No. towers (3 rd lot) received on HPPTCLmay update the committee. 4. Valley wise transmission Plan for Palampur Zone, Satluj Basin (up to Wangtoo) and Ravi basin (Chamba & Gharola Zones) Committee shall be apprised on the following: i) Short term arrangements for evacuation of Small Hydel power in Palampur Zone: Activity wise progress review of following works was reported as under: 33 kv Baner- Darang- Kangra line.- 5

6 The loan against scheme has been sanctioned by Mis REC Ltd during Feb, The FRA case under process Revised Time Line kv Maranda- Nagrota-Kangra line.- Loan sanctioned by Mis REC on the FRA case under process. Revised Time Line kv Baner-Sidhpur & Kangra Loan sanctioned by Mis REC Ltd. During pt week of March, Tender opened on The work is also included in KfW loan. Time line for execution kv Baijnath-Bassi line Loan sanctioned by Mis REC and under process. i) Tenders for the line portion between Baijnath to Chauntra have been invited and being processed by CE(OP) North. ii) CE(OP) CZ, Mandi has executed the work under their jurisdiction i.e. Bassi to Chauntra. Time line for Commissioning falling ii) Evacuation arrangements for Small HEPs in Satluj Basin (up to Wangtoo) In the 38 th meeting of the Committee, that: it was apprised a: 66/22 kv sub-station work at Ani (Nagan) has. been completed b: LlLO of 66 kv Gumma-Kumarsain line: work awarded on Turnkey basis to Mis M.G. Engg. works, New Delhi. 6

7 Land acquired for all 30 Nos. towers. Out of 30 Nos Towers Excavation works of 28 Nos. towers completed. Stubbing for 22 Nos. towers is completed. iii) The Tower material for 18 Nos. towers has been received at site till now. Erection and 6 Nos Towers completed. Revised time line HPSEBLmay update the Committee. Evacuation arrangements for Small HEPs in Ravi Basin (Chamba & Gharola Zones) In the 38 th meeting of the Committee held on , progress of following works was reported as under: i} 33 kv DIC line between Holi & Gharola: The Tender again invited for execution of the work for construction of 33KV Holi to Gharola. Time line s. ii} 33 kv DIC line between Gharola and Bharmour: The work line has been awarded 85% work has been completed. Time line by CE (OP) North and HPSEBLmay update the Committee. iii} 33/220 kv GIS sub station at Karian: The substation work completed and 33 kv portion of the sub station commissioned on

8 iv) 220 kv SIC line on D/C towers between Karian and 400/220 kv Chamera P.S of PGCIL. 7 No. out of 18 nos. wrongly casted stubs have been recasted and 3 new stubs casted. 4 nos. already erected. Erection work at tower location 10 & 12 is in progress. HPPTCL may update the Committee. 5. Construction of 220 kv Kashang- Bhaba D/C Line (Revised Time Line ): In the 38 th meeting of the Committee held on , progress of completion reported as under: of 220 kv Kashang-Bhaba line was De-stringing work in progress at tower No Earth cutting work at tower No is in progress. Re-stubbing of Leg D at tower No. 83 completed. 85% earth cutting work at tower No completed. Purchase order for additional material required has been placed on Material likely to be received by Tree cutting work shall be completed by Financial concurrence obtained by circulation in BOD of HPSEBLand Administrative last week of November, 2014 Approval shall be issued by the HPPTCLand HPSEBLmay update the Committee. 6. Progress review of Transmission Projects planned to be built with ADB Loan -Tranche-II:. In 38 th meeting of the Committee held on , status/proqress of various transmission projects covered in Tranche-II of ADB Loan was given as under: 8

9 a) 66 kv GIS Switching station at Urni (Revised Time Line- January, 2016) : Mobilization advance released on Site handed over to the Contractor on Initial activities i.e. survey work, preliminary engineering design and drawing activities initiated by the firm. b) 66 kv Urni- Wangtoo DIC Line (Time Line- April, 2015): FBER sent to ADB for approval on FCA case submitted to MOEF for Stage-I clearance has been returned for revision of ROW in accordance with fresh guide lines issued on c) 33/220 kv, 50/63 MVA GIS sub-station at Lahal (Time Line-August, 2015) Work awarded on d) 220 kv Lahal- Budhil SIC Line (Time Line-August, 2015). FBERsent to ADB for approval on Case is being pursued with MOEFfor transfer of land. e) 132/220 kv, 2x100 MVA GIS sub-station at Sunda (Time Line-October, 2015) Tender opened on TBER under process. f) 220 kv Sunda - Hatkoti DIC Line (Time Line-October, 2015). Forest case returned by Forest. Deptt. Is being revised. FBER sent to ADB for approval on g) 220 kv Switching Station at Hatkoti (Time Line-October, 2015). Site under finalization. 9

10 h) 33/132 kv, 2x25/31.5 MVA GIS sub-station at Chambi (Shahpur) with LlLO of 132 kv Dehra- Kangra SIC Line (Time Line-February, 2016). Tender opened on TBER under process. Site to be finalized by i) 33/132 kv, 2x25/31.5 MVA GIS sub-station at Barsaini (Time Line-March, 2016). Land Acquisition: Site has been finalized and the same shall be purchased after approval of BOD. j) 132 kv D/C Line from Barsaini to 132/220 kv Charor Substation (Time Line- April, 2016). FCA case returned by Forest Deptt. is being revised and shall be resubmitted by FBER sent to ADB for approval on k) 132/220 kv, 126 MVS GIS sub-station at Charor (Time Line-May, 2016). NIT floated on and bid is due for opening on I) 220 kv Charor- Banala D/C Line (Time Line-April, 2016). Forest Case. FCA case with Nodal Officer Shimla. Observations raised by Nodal officer have been attended to and case resubmitted to Nodal officer. FBER sent to ADB for approval on m) 33/132 kv, 31.5 MVA GIS sub-station at Pandoh with LlLO of 132 kv Bajaura- Kangoo line (Time Line- Feb, 2016) TBER under process. Meeting with BBMB authorities fixed in December, 2014 for transfer of site. HPPTCL may update the Committee on the progress of above works. 10

11 7. Construction of IPPs'/HPPCLlines by HPPTCL In 38 th meeting of the Committee held on , progress of following lines under implementation by HPPTCLwas reported as under: a) 132 kv D/C line from Tangnu Romai (44 MW) HEP to 132/220 kv planned sub station of HPPTCLat Sunda. Forest case returned by Forest Deptt. is being revised. Funds for construction of the line approved under Green Energy Corridor scheme of Gol b) 220 kv Snail (Sawra Kuddu HEP)- Hatkoti D/C line The FCA case returned by forest Deptt. is being revised. HPPTCLmay update the Committee on the progress of above works. 8. Transmission System for supplying construction power and evacuation of power from Chhoo (3.5 MW) and Tindi (4.4 MW -proposed to be revised to 5 MW): In its 38 th meeting held on , HPSEBL apprised the Committee that: a meeting was held with the developer to suggest way forward for construction of high voltage evacuation line in the hostile terrain but the matter is still under consideration due to lack of expertise of construction of lines in the hostile terrain. Representative of MIS L & T Power requested for early finalization of evacuation arrangement as TEe for his 11

12 project is held up for want of confirmed evacuation arrangement. Committee directed HPSEBL to resolve all the pending issues at the earliest. HPSEBLmay apprise the Committee. 9. Grant of Connectivity at Sub stations under implementation by HPPTCL: In its 38 th meeting held on , HPSEBL informed that that as per HPERCRegulations, DISCOM is not required to apply for connectivity to HPPTCL. However, they are ready to pay the cost for 33 kv bays kept for them at Phojal, Karian and Bhoktoo and also pay 0 & M charges. However, HPPTCL apprised that, in case, bays kept at HPPTCL are used by HPSEBL for injection purpose, status of HPSEBL shall be treated as that of IPPs who have to apply for connectivity as per the Procedure. Committee directed HPPTCL & HPSEBL to revisit the issue of connectivity and apprise it in its next meeting. HPSEBLand HPPTCLmay update the Committee. 10. Evacuation of Toss (10 MW), Jirah (4 MW) and Chakshi (2 MW) SHEPs through 132 kv Malana-I- Bajaura D/C line of MIS MPCL: In its last meeting, HPSEBLapprised the Committee that: The details submitted by MIS MPCL are being scrutinized. The firm has been requested to depute their representative for clarifying the claim deposited by them. MIS MPCL has submitted revised calculation on in line with Hon'ble Supreme Court orders in 12

13 Civil Appeal No. 1795/2013. Wheeling charges for Toss HEP amounting to ~ 2,71,55,805/- case are under process for funding the wheeling charges. HPSEBLmay update the Committee. 11. Evacuation arrangement for Rukti-II HEP(5 MW) In the last meeting of Committee, HPSEBL informed that there are certain issues to be discussed with developers of Shaung & Brua HEPs before proposal to evacuate Rukti-II HEP (5 MW) in joint mode with these projects up to 66 kv switching station under construction by HPPTCL at Urni is firmed up. HPSEBLmay update the Committee. 12. Four laning of Kiratpur to Ner Chowk Section of NH-21 from to Km in the state of Punjab and Himachal Pradesh. Shifting of Transmission Tower constructed by AD Hydro Power Ltd. Near village Jadol thereof In its last meeting, Committee was apprised that in pursuance of meeting taken by Pro Secretary (Power) on , M/S ADHPL have submitted the cost estimate for shifting of tower of 220 kv line which is being evaluated by 'HPPTCLfor prudency checks. It was agreed that: 1. HPPTCLshall vet and send the cost estimate to NHAI with in a week time. 2. NHAI shall deposit the money with ADHPL with in 15 days after receipt of the vetted cost estimate.: 3. M/S ADHPL shall shift the tower with in 6 months after deposit of the cost by NHAI 13

received 1. Shyang (3 MW)- Completed 2. Tangling (5 MW)- Completed 3. Shaung (interim) (3 MW)--completed 4 Brua (Interim) (9 MW) - Completed

received 1. Shyang (3 MW)- Completed 2. Tangling (5 MW)- Completed 3. Shaung (interim) (3 MW)--completed 4 Brua (Interim) (9 MW) - Completed Agenda for discussions in the 44 th meeting of the STU Coordination Committee to be held under the chairmanship of Addl. Chief Secretary (MPP & Power) Sr. No. A 1.2. Progress Review of Transmission Projects

More information

Determination of Average Pooled Purchase Cost for FY

Determination of Average Pooled Purchase Cost for FY BEFORE THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA Determination of Average Pooled Purchase Cost for FY 2014-15 Submitted to Himachal Pradesh State Electricity Regulatory Commission

More information

Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05.

Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05. Minutes of the 19 th meeting of the Standing committee on transmission system of Northern Region held at Amritsar on 01/10/05. 1. List of the participants is enclosed at Annex - I. Member (PS) CEA welcomed

More information

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE

JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE JAMMU AND KASHMIR STATE POWER DEVELOPMENT CORPORATION LIMITED PUBLIC NOTICE Objections/ comments invited from various stakeholders on ARR filing and Tariff Petition of Hydro Electric Stations, Gas Turbine

More information

Guidelines for Solar Grid Power Projects

Guidelines for Solar Grid Power Projects Guidelines for Solar Grid Power Projects NTPC Ltd. NTPC Vidyut Vyapar Nigam Ltd. AGENDA 1 2 3 NTPC / NVVN at a glance Broad Guidelines for Selection of Solar Power Developers Elements of PPA NTPC Limited

More information

PCDO. Jan Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project

PCDO. Jan Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project PCDO Jan-2018 Launched portion of Viaduct Deck Structure from S-180 (KATRA- BANIHAL SECTION) Udhampur-Srinagar-Baramulla Rail Link Project Northern Railway vuqjkx dqekj lpku vkbzvkj,lb Anurag Kumar Sachan

More information

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010 FINAL FACILITY STUDY 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1 September 10, 2010 I. Introduction This is a revised facility study performed for Transmission Queue Request 2009

More information

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1

TRANSMISSION CAPACITY ADDITION PROGRAMME DURING No. 1 Introduction 1 TRANSMISSION CAPACITY ADDITION PROGRAMME DURING 2006-07 Sl. No. Contents Page No. 1 Introduction 1 2 Chapter 1 Transmission Capacity Additions During 2005-06 of 10 th plan period 3 Chapter 2 Construction

More information

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW) Monthly Progress Report Prepared by : Sano Milti Khola Hydropower Limited www.smi.com.np smi.investment.limited@gmail.com Date : June,

More information

Engineers Ireland Site Visit 23 rd March 2010

Engineers Ireland Site Visit 23 rd March 2010 Whitegate Independent Power Plant CER Site Visit 24 th October 2008 CER Site Visit 24 th October 2008nt Engineers Ireland Site Visit 23 rd March 2010 Agenda Presentation of project and progress to date.

More information

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region

Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region Agenda for Connectivity and Long Term (Open) Access of IPP Generation Projects in Odisha of Eastern Region 1.0 Applications for Connectivity and Long Term (Open) Access. Applications for grant of Connectivity

More information

Transmission System Bottlenecks & Planning for Mumbai Metropolitan Region

Transmission System Bottlenecks & Planning for Mumbai Metropolitan Region Transmission System Bottlenecks & Planning for Mumbai Metropolitan Region TRANSMISSION GROUP MERC 5 th August 2011 2 Actual Flows for Mumbai Peak FY12 ( 3209 MW) Tie Line Flows (Amp & MW) during Mumbai

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

Electric Vehicles and the Environment (EVE IWG)

Electric Vehicles and the Environment (EVE IWG) Submitted by the EVE informal working group Electric Vehicles and the Environment () 1 Informal document GRPE-78-30-Rev.1 78 th GRPE, 10-11 January 2018 Agenda item 9 REPORT TO GRPE 78 TH SESSION Original

More information

(i) Establishment of 400kV Pooling Station at Fatehgarh (with a provision to upgrade at 765kV level)

(i) Establishment of 400kV Pooling Station at Fatehgarh (with a provision to upgrade at 765kV level) Annex-I Corrigendum to Minutes of the 36 th meeting of the Empowered Committee on Transmission held on 26 th July, 2016 at 3:30 PM at Conference Room of CEA, 2 nd Floor, Sewa Bhawan, R.K. Puram, New Delhi

More information

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012

CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 CONFERENCE ON TRANSMISSION & DISTRIBUTON MR N C VENUGOPAL TRANSMISSION SECTOR GROWTH & CHALLENGES. DATE 2 ND NOVEMBER 2012 TRANSMISSION SECTOR GROWTH HIGHLIGHTS Source - POWERLINE Transmission line length

More information

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of November 18, 2017

ARLINGTON COUNTY, VIRGINIA. County Board Agenda Item Meeting of November 18, 2017 ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of November 18, 2017 DATE: November 7, 2017 SUBJECT: Six-Month Extension of car2go Demonstration Study Agreement C. M. RECOMMENDATIONS: 1. Authorize

More information

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min Gas Advisory Board Draft Agenda Meeting No. 1 Location: Parmelia Hilton, Swan B Room 14 Mill Street, Perth WA 6000 Date: 20 December 2011 Time: 11:15am 12:15pm Item Subject Responsible Time 1. WELCOME

More information

Procurement Plan. Eskom Holdings SOC Limited. Eskom Investment Support Project

Procurement Plan. Eskom Holdings SOC Limited. Eskom Investment Support Project Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized General. Project information Country: Borrower: Loan number: Project Implementation Agency

More information

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:

More information

Metal Bulletin Conference

Metal Bulletin Conference Sakura Ferroalloys Project Metal Bulletin Conference Singapore, 01 st April 2015 P R E S E N T E D BY: T I A A N VA N A S W EG E N D I R E C TO R A S S M A N G C H A I R M A N S A KU R A F E R R OALLOY

More information

Transit Project Delivery Status Report. Significant Issues

Transit Project Delivery Status Report. Significant Issues Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda

More information

Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region

Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region Additional Agenda for 31 st Standing Committee Meeting of Power System Planning for Northern Region a) Power Supply to M/s Noida Power Company Limited (NPCIL) NPCL has applied to CTU for connectivity for

More information

MINUTES OF THE 47 th SLCF MEETING HELD ON

MINUTES OF THE 47 th SLCF MEETING HELD ON MINUTES OF THE 47 th SLCF MEETING HELD ON 23.11.2016 Shri. Rafikul Islam, Chief Engineer (SLDC), WBSETCL & Chairperson, SLCF welcomed all the participant members to the 47 th SLCF meeting.. ITEM-1: CONFIRMATION

More information

Need Assessment Document (NAD) DDUGJY

Need Assessment Document (NAD) DDUGJY Need Assessment Document (NAD) DDUGJY Index SNo. Details Page No. 1.0 General Instruction 3 2.0 Objectives of DDUGJY 5 3.0 Scope of works 7 4.0 General information of project area 10 5.0 Details of existing

More information

:Tamil Nadu Generation and Distribution Corporation Limited: Delegation of powers of sanction to officers (TNEB Volume-II) - revised Communicated Reg

:Tamil Nadu Generation and Distribution Corporation Limited: Delegation of powers of sanction to officers (TNEB Volume-II) - revised Communicated Reg :Tamil Nadu Generation and Distribution Corporation Limited: Delegation of powers of sanction to officers (TNEB Volume-II) - revised Communicated Reg Technical Branch (Per) TANGEDCO Proceedings. (FB) No.

More information

DETAILED NOTICE INVITING TENDER WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED. (A Govt of West Bengal Enterprise)

DETAILED NOTICE INVITING TENDER WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED. (A Govt of West Bengal Enterprise) DETAILED NOTICE INVITING TENDER WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED (A Govt of West Bengal Enterprise) CHIEF ENGINEER (PROCUREMENT), VIDYUT BHAVAN NOTICE INVITING TENDERS For CONSTRUCTION

More information

Government of India Central Electricity Authority SP&PA Division R.K. Puram, New Delhi

Government of India Central Electricity Authority SP&PA Division R.K. Puram, New Delhi Government of India Central Electricity Authority SP&PA Division R.K. Puram, New Delhi -110066 F.No. 1/9/SP&PA-12/ Dated: 20/1/12 -As per list enclosed- Sub: The 30 th meeting of the Standing Committee

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the Southern Arizona Economic Development Group September 12, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT SEPTEMBER 12, 2017 0 SouthWestern

More information

GOVERNMENT OF ANDHRA PRADESH ABSTRACT

GOVERNMENT OF ANDHRA PRADESH ABSTRACT 1 GOVERNMENT OF ANDHRA PRADESH ABSTRACT PUBLIC SERVICES Employees Welfare Scheme Andhra Pradesh State Employees Group Insurance Scheme 1984 Revised Rate of Interest on accumulated Savings Fund Communication

More information

HVDC Systems in India

HVDC Systems in India HVDC Systems in India Outline Introduction HVDC Systems presently in operation Main Data/Salient Features Upcoming Projects Future Challenges Transmission Network - Present 765kV/400kV lines: about 1,03,000

More information

Umatilla Electric Cooperative Net Metering Rules

Umatilla Electric Cooperative Net Metering Rules Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through

More information

ACTION: ESTABLISH LIFE-OF-PROJECT BUDGET FOR UP TO 100 NEW COMPO BUSES

ACTION: ESTABLISH LIFE-OF-PROJECT BUDGET FOR UP TO 100 NEW COMPO BUSES QD Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net oplo OPERATIONS COMMITTEE June 16, 2011 SUBJECT: PURCHASE REPLACEMENT

More information

THE PUBLIC UTILITIES BOARD ACT April 22, Graham F. J. Lane, C.A., Chairman Monica Girouard, C.G.A., Member Mario J. Santos, B.A., LL.B.

THE PUBLIC UTILITIES BOARD ACT April 22, Graham F. J. Lane, C.A., Chairman Monica Girouard, C.G.A., Member Mario J. Santos, B.A., LL.B. MANITOBA THE PUBLIC UTILITIES BOARD ACT April 22, 2005 Before: Graham F. J. Lane, C.A., Chairman Monica Girouard, C.G.A., Member Mario J. Santos, B.A., LL.B., Member AN APPLICATION BY CENTRA GAS MANITOBA

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Agenda of 11 th System Studies Meeting in NER

Agenda of 11 th System Studies Meeting in NER Agenda of 11 th System Studies Meeting in NER Date: 16.12.2015. Venue: Hotel Nandan, Guwahati 1. Review of SPS I, II, III & SPS IV related to Palatana GBPP, OTPC after commissioning of Palatana Module

More information

Ocala Airport Advisory Board Agenda Thursday, July 26, 2018

Ocala Airport Advisory Board Agenda Thursday, July 26, 2018 Ocala Airport Advisory Board Agenda Thursday, July 26, 2018 Meeting Information Contact Haydee Sosa Admin Specialist 3 (352) 629-8377 Location Sheltair Aviation 1200 SW 60th Avenue Ocala, Florida 34474

More information

Supplemental Report on the NCTPC Collaborative Transmission Plan

Supplemental Report on the NCTPC Collaborative Transmission Plan Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for

More information

Regular Meeting PULASKI COUNTY Mon. August 18, 2003 PUBLIC SERVICE AUTHORITY FOLLOW-UP ITEM. 1. Citizen Comments

Regular Meeting PULASKI COUNTY Mon. August 18, 2003 PUBLIC SERVICE AUTHORITY FOLLOW-UP ITEM. 1. Citizen Comments AGENDA Regular Meeting PULASKI COUNTY Mon. August 18, 2003 PUBLIC SERVICE AUTHORITY 9:00 a.m. FOLLOW-UP ITEM 1. Citizen Comments 2. Reports from the County Administrator & Staff: a. Collection Staff Activity:

More information

Implementation Status & Results Bosnia and Herzegovina ROAD INFRASTRUCTURE AND SAFETY PROJECT (P100792)

Implementation Status & Results Bosnia and Herzegovina ROAD INFRASTRUCTURE AND SAFETY PROJECT (P100792) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Bosnia and Herzegovina ROAD INFRASTRUCTURE AND SAFETY PROJECT (P100792) Operation Name: ROAD INFRASTRUCTURE

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY WORKSHOP AGENDA

COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY WORKSHOP AGENDA COMMITTEE FOR TRANSPORTATION MOBILITY & ACCESSIBILITY Wednesday, February 1, 2017 10:00 AM PLEASE NOTE MEETING DATE VTA Conference Room B-106 3331 North First Street San Jose, CA WORKSHOP AGENDA COMMITTEE

More information

DRAFT Subject to modifications

DRAFT Subject to modifications TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The

More information

Western Alberta Transmission Line (WATL) HVDC Project

Western Alberta Transmission Line (WATL) HVDC Project Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink Attachment

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract

More information

RFP Corrigendum No. 01

RFP Corrigendum No. 01 RFP Corrigendum 01 The RFP document for selection of Transmission Service provider for the Package- 1 against tender specification ESD-765/4 has been modified to the extent below: S. Clause / Page 1. Definition

More information

congestion management program

congestion management program congestion management program 2550 Rail Vehicle Program March 2012 11-0319tr 2010 lacmta Q U A R T E R LY P R O J E C T S TAT U S R E P O R T 255O RAIL VEHICLE PROGRAM QUARTERLY PROJECT STATUS REPORT THE

More information

LATEST DEVELOPMENTS IN NEPAL POWER SECTOR INCLUDING THE STATUS OF D-M 400 KV CBTL

LATEST DEVELOPMENTS IN NEPAL POWER SECTOR INCLUDING THE STATUS OF D-M 400 KV CBTL Third Meeting of Taskforce 2, February 25-26, 2015; Colombo, Sri Lanka LATEST DEVELOPMENTS IN NEPAL POWER SECTOR INCLUDING THE STATUS OF D-M 400 KV CBTL Surendra Rajbhandari Chief, Project Management Directorate,

More information

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority Washington Metropolitan Area Transit Authority BUS PROCUREMENT PROGRAM REPROGRAMMING OF FUNDING P D E C PLANNING DEVELOPMENT ENGINEERING CONSTRUCTION Presented to the Board of Directors: Budget Committee

More information

Reliability Analysis Update

Reliability Analysis Update Reliability Analysis Update Transmission Expansion Advisory Committee February 8, 2018 2018 RTEP Analysis Update 2 PSE&G Transmission Zone Transmission Service Update 3 Linden VFT Previous agreements:

More information

Annex_Tumkur In-principle(Phase-I) 1)Minutes of the meeting held on )In-principle Approval_Tumkur Phase-I

Annex_Tumkur In-principle(Phase-I) 1)Minutes of the meeting held on )In-principle Approval_Tumkur Phase-I Annex_Tumkur In-principle(Phase-I) 1)Minutes of the meeting held on 16-12-2015 2)In-principle Approval_Tumkur Phase-I Government of India Ministry of Power Central Electricity Authority PSP & PA- I Division

More information

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Please Refer to Attached Sample Form

Please Refer to Attached Sample Form Pacific Gas and Electric Company San Francisco, California U 39 Revised Cal. P.U.C. Sheet No. 32105-E Cancelling Revised Cal. P.U.C. Sheet No. 28313-E Electric Sample Form No. 62-0686 Application for Service

More information

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS 1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS The Transit Committee recommends the adoption of the recommendations contained in the

More information

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST Cleco Power LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST OASIS 71956063 0 Rev Issue Date Description of Revision Table of Contents 1. Purpose...3 2. System Impact Study Conclusions...3 2.1 The Pineville

More information

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5 ALANNA GILLIS ACTING COMMISSION SECRETARY Commission.Secretary@bcuc.com web site: http://www.bcuc.com SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, BC CANADA V6Z 2N3 TELEPHONE: (604) 660 4700 BC TOLL

More information

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document Decision 2013-127 Alberta Electric System Operator Saleski Transmission Project Needs Identification Document ATCO Electric Ltd. Saleski 901S Substation and 144-kV Transmission Line 7L142 Facility Application

More information

Taxis and Accessible Services Division Medallion Reform Background May 1, 2018

Taxis and Accessible Services Division Medallion Reform Background May 1, 2018 Introduction: Taxis and Accessible Services Division Medallion Reform Background May 1, 2018 SFMTA s Taxis and Accessible Services Division is responsible for the regulation of the private businesses that

More information

Seabrook Substation Reliability Improvement Project

Seabrook Substation Reliability Improvement Project New England Division Seabrook Substation Reliability Improvement Project 1. Project Summary Description Seabrook Substation is critical to ISO-New England as a Pool Transmission Facility, to grid availability

More information

/ I S S : / S T S I

/ I S S : / S T S I Agenda Electrical Transformers (Quality Control) Order Obtaining BIS Licence Requirements of Guidelines / IS 1180-1: 1: 2014 / STI Concerns in Getting BIS Licence Experience with BEE Regulations Recommendations

More information

SWANTOWN MARINA MARINE FUELING FACILITY. Ed Galligan Executive Director

SWANTOWN MARINA MARINE FUELING FACILITY. Ed Galligan Executive Director SWANTOWN MARINA MARINE FUELING FACILITY Ed Galligan Executive Director Agenda of Events Welcome & History Fueling Facility Design Overview Fuel Consumption Survey & Updated Financial Evaluations Facility

More information

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007

KERALA STATE ELECTRICITY REGULATORY COMMISSION. NOTIFICATION Dated, Thiruvananthapuram 6 th August,2007 KERALA STATE ELECTRICITY REGULATORY COMMISSION NOTIFICATION No.1/1/KSERC-2006/ Dated, Thiruvananthapuram 6 th August,2007 KSERC (Supply of Power from Captive Generating Plants to Distribution Licensees)

More information

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION

ENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION ENERGY STRATEGY FOR YUKON Net Metering Policy DRAFT FOR CONSULTATION February 2011 Page 1 of 4 BACKGROUND The Yukon government released the Energy Strategy for Yukon in January 2009. The Energy Strategy

More information

Metropolitan Domestic Water Improvement District Board of Directors Meeting. August 8, July 2011 Report

Metropolitan Domestic Water Improvement District Board of Directors Meeting. August 8, July 2011 Report Metropolitan Domestic Water Improvement District Synopsis The purpose of this agenda item is to provide the Board with an update of the District s activities for the past month. This is not an action item,

More information

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012 POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 PREPARED BY: Electricity System Operations Planning and Performance DATE: 5 June 2012 FINAL

More information

Doran Street and Broadway/Brazil Grade Separation Project

Doran Street and Broadway/Brazil Grade Separation Project Doran Street and Broadway/Brazil Grade Separation Project Public Outreach Meeting October 4, 2017 Agenda Introductions Project Overview Grade Separation Alternative Traffic Report Update Interim Condition

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,

More information

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES: TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design

More information

City of Grand Island Tuesday, October 23, 2012 Council Session

City of Grand Island Tuesday, October 23, 2012 Council Session City of Grand Island Tuesday, October 23, 2012 Council Session Item G5 #2012-308 - Approving Bid Award - Substation Transformer Testing Services Staff Contact: Tim Luchsinger, Jason Eley Grand Island Council

More information

STAFF REPORT ACTION REQUIRED

STAFF REPORT ACTION REQUIRED STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This

More information

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan XXXXX Kokish River Hydroelectric Project Interconnection Facilities Study and Project Plan March 16, 2011 British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority 2010. All

More information

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000.

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000. Date: April 11, 2012 To: From: Board of Directors Neil McFarlane Subject: RESOLUTION 12-04-30 OF THE TRI-COUNTY METROPOLITAN TRANSPORTATION DISTRICT OF OREGON (TRIMET) AUTHORIZING A CONTRACT WITH SIEMENS

More information

GC108: EU Code: Emergency & Restoration: Black start testing requirement

GC108: EU Code: Emergency & Restoration: Black start testing requirement Stage 01: Modification Proposal Grid Code GC108: EU Code: Emergency & Restoration: Black start testing requirement Purpose of Modification: This modification seeks to align the GB Grid Code with the European

More information

From: Arthur Canafe, P.E. Approved by: /s/ General Manager

From: Arthur Canafe, P.E. Approved by: /s/ General Manager AGENDA ITEM : 3.F.1 MEETING DATE: 05/17/2010 ADMINISTRATIVE REPORT : 2010-64 To: Honorable Public Utilities Board Submitted by: /s/ Robert Streich AGM Engineering and Operations From: Arthur Canafe, P.E.

More information

ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE

ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE ROLLOVER RIGHTS OF LONG TERM FIRM TRANSMISSION SERVICE In this Section: Overview Evaluation of Initial Requests Rollover Request Competing Request Competing Examples 1.0 OVERVIEW Pursuant to Section 2.2

More information

One City, One System: Integrating Public Urban Transportation in Coimbra

One City, One System: Integrating Public Urban Transportation in Coimbra One City, One System: Integrating Public Urban Transportation in Coimbra CIVITAS MODERN Study Tour Luis Santos, SMTUC Luis da Vinha, Municipality of Coimbra 8-9 November 2012 Coimbra Situation before CIVITAS

More information

From: Tito R. Nagrampa Jr, P.E. Approved by: /s/ General Manager Juan M. Ulloa, P.E. Engineering Supervisor

From: Tito R. Nagrampa Jr, P.E. Approved by: /s/ General Manager Juan M. Ulloa, P.E. Engineering Supervisor AGENDA ITEM NO: 4.I.1 MEETING DATE: 12/10/2012 ADMINISTRATIVE REPORT NO.: 2013-28 To: Honorable Public Utilities Board Submitted by: /s/ Douglas Draeger AGM Engineering and Operations From: Tito R. Nagrampa

More information

Rolling Road (Route 638) Widening Project

Rolling Road (Route 638) Widening Project Rolling Road (Route 638) Widening Project From: 0.369 Mile North of Fairfax County Parkway (Route 286) To: Old Keene Mill Road (Route 644) State Project No. 0638-029-156, P104, R204, C504; UPC 5559 Public

More information

Peninsula Corridor Electrification Project Cost / Schedule Update

Peninsula Corridor Electrification Project Cost / Schedule Update Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system

More information

9LQL-rn; PREFACE. Shimla

9LQL-rn; PREFACE. Shimla PREFACE It is a matter of satisfaction that First Annual Administrative Report of Himachal Pradesh State ~Iectricity Board limited is being published for the year ending 31 st March, 2011. HPSEB was established

More information

7 The revised IS 8034:2002 and revised STI be implemented w.e.f. 1 Feb 2005.

7 The revised IS 8034:2002 and revised STI be implemented w.e.f. 1 Feb 2005. BUREAU OF INDIAN STANDARDS (CENTRAL MARKS DEPARTMENT-III) Our Ref: CMD-III/16:8034 25 Oct 2004 Subject: Implementation of revised IS 8034:2002 Submersible Pump Sets and revised STI (Doc:STI/8034/5 ) IS

More information

Request for Proposal for Trolley Security Services

Request for Proposal for Trolley Security Services Request for Proposal for Trolley Security Services April 6, 2018 Trolley Security Support Services The Loop Trolley Company The Loop Trolley Company (LTC) is requesting proposals for armed on-board security

More information

OTS Technical Advisory Committee Meeting

OTS Technical Advisory Committee Meeting OTS Technical Advisory Committee Meeting March 21st 2012 For Audio Dial 416-343-2285 or 1-877-969-8433 PIN# 4467765 Agenda 1) Diversion Rates 2) Tire Collection Update 3) Tire Transportation and Delivery

More information

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting

More information

Appendix 6.7 January 23, 2015 SURPLUS ENERGY PROGRAM PROPOSED TERMS AND CONDITIONS

Appendix 6.7 January 23, 2015 SURPLUS ENERGY PROGRAM PROPOSED TERMS AND CONDITIONS Appendix 6.7 SUR ENERGY PROGRAM PROPOSED TERMS AND CONDITIONS SUR ENERGY PROGRAM INDUSTRIAL LOAD - OPTION 1 TABLE OF CONTENTS Page No. Eligibility...1 Reference Demand...1 Billing...2 Interruptions...3

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

BC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014

BC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014 T BC Hydro OATT - Balancing Area Transmission Service Workshop January 20, 2014 1 AGENDA Topic Time Speaker Welcome and Introduction 09:00 09:15 Gord Doyle Background 09:15 10:00 Martin Huang Enforcement

More information

City Transfer Stations: Loading Services and Fees

City Transfer Stations: Loading Services and Fees STAFF REPORT ACTION REQUIRED City Transfer Stations: Loading Services and Fees Date: March 24, 2009 To: From: Wards: Reference Number: Public Works and Infrastructure Committee General Manager, Solid Waste

More information

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016 Decision 21481-D01-2016 October 18, 2016 Alberta Utilities Commission Decision 21481-D01-2016 Proceeding 21481 Application 21481-A001 October 18, 2016 Published by the: Alberta Utilities Commission Fifth

More information

Item No Halifax Regional Council June 21, 2016

Item No Halifax Regional Council June 21, 2016 P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. 14.2.2 Halifax Regional Council June 21, 2016 TO: Mayor Savage and Members of Halifax Regional Council SUBMITTED BY: Councillor Tim Outhit, Chair,

More information

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED SARDAR PATEL VIDYUT BHAVAN RACE COURSE, VADODARA TENDER FOR

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED SARDAR PATEL VIDYUT BHAVAN RACE COURSE, VADODARA TENDER FOR GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED SARDAR PATEL VIDYUT BHAVAN RACE COURSE, VADODARA - 390 007 TENDER FOR Design,Engineering, manufacturing, supply, erection, testing & commissioning of 66

More information

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT CITY OF ELK GROVE CITY COUNCIL STAFF REPORT AGENDA ITEM NO. 10.2 AGENDA TITLE: Receive Update on Citywide Light Emitting Diode (LED) Streetlight Conversion and Provide Guidance on Next Steps MEETING DATE:

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility

More information

Implementation Status & Results Ukraine Power Transmission Project in Support of the Energy Sector Reform & Development Program (P096207)

Implementation Status & Results Ukraine Power Transmission Project in Support of the Energy Sector Reform & Development Program (P096207) Public Disclosure Authorized Public Disclosure Authorized The World Bank Implementation Status & Results Ukraine Power Transmission Project in Support of the Energy Sector Reform & Development Program

More information

Alert: Electromobility infrastructure

Alert: Electromobility infrastructure Alert: Electromobility infrastructure 6 February 2018 The development of electromobility infrastructure in Poland The Act on Electromobility and Alternative Fuels ( Act ) was passed by the Sejm and Senate

More information

YUKON DEVELOPMENT CORPORATION

YUKON DEVELOPMENT CORPORATION YUKON DEVELOPMENT CORPORATION 2 http://www.ydc.yk.ca YUKON DEVELOPMENT CORPORATION ANNUAL REPORT 2016 TABLE OF CONTENTS Message from the Chair...4 Message from the President and Chief Executive Office...

More information

First NEP Implementation Workshop, Thingaha Hotel, NayPyiTaw Myanmar.

First NEP Implementation Workshop, Thingaha Hotel, NayPyiTaw Myanmar. First NEP Implementation Workshop, Thingaha Hotel, NayPyiTaw Myanmar. October 21, 2015 1 Institutional Framework for National Electrification Plan and Project Strategic Direction and Guidance National

More information

Transmission Line Survey

Transmission Line Survey Transmission Line Survey Name of the Project Owner / Client Scope of Work Type of Survey Instrument & Software tools used Schedule Time of Completio n Year of Completion Letter of Award for "Rate Contract"

More information

SunZia Southwest Transmission Project

SunZia Southwest Transmission Project SunZia Southwest Transmission Project SunZia Project Update for the 9 th Annual Transmission Summit West October 13, 2017 SUNZIA SOUTHWEST TRANSMISSION PROJECT OCTOBER 13, 2017 0 SouthWestern Power Group

More information