Rocky Mountain Power Five Year Study Findings & Kick Off Meeting
|
|
- Alexina Washington
- 5 years ago
- Views:
Transcription
1 2000 PACIFICORP PAGE 1 Attachment K Rocky Mountain Power Five Year Study Findings & Kick Off Meeting Thursday, June 9 th 2016
2 2000 PACIFICORP PAGE 2 Rocky Mountain Power Area Transmission Planning Manager: Ken Shortt Area Transmission Engineering: Mark Adams Talmage Daley Jeremy Viula Nathan Wilson Nicole DeGiulio Carlton Jones Scott Murdock Sachith Abayakoon
3 2000 PACIFICORP PAGE 3 Study Areas for 2016 Findings Reports Honeyville/Malad Montpelier Utah Valley, Utah Kickoff Studies Smithfield/Preston & Sigurd, Utah Price, Utah Southern Wyoming &Vernal, Utah Scott Murdock Carlton Jones Nicole DeGiulio Carlton Jones Nicole DeGiulio Scott Murdock
4 2000 PACIFICORP PAGE 4 HONEYVILLE/MALAD STUDY FINDINGS AREA ENGINEER ~ MARK ADAMS Completed by Scott Murdock
5 2000 PACIFICORP PAGE 5 Honeyville/Malad Study Area Area boundaries: North: Malad City East: Cache National Forest West: West side Great Salt Lake South: Brigham City Ben Lomond is outside of the area, but a main source
6 2000 PACIFICORP PAGE 6 Study Service Area Urban & agricultural areas: Service to portions of Box Elder & Cache counties in Utah & Oneida county in Idaho Larger communities served are: Tremonton, Malad City & Brigham City Largest population center is Brigham City
7 2000 PACIFICORP PAGE 7 Honeyville/Malad Study Info One municipality in the study area Four transmission substations at 138 kv 16 distribution substations 11 transmission customers Transmission voltages: 138, 69 & 46 kv Distribution voltages: & 4.16 kv
8 2000 PACIFICORP PAGE 8 MALAD AREA OF SERVICE: Mainly agricultural Service to Oneida & Box Elder counties Communities: o o o Snowville Malad City Holbrook Voltages: 138 kv, 69 & kv Substations: o o o one transmission three distribution one customer owned
9 2000 PACIFICORP PAGE 9 WHEELON/CUTLER AREA OF SERVICE: Mainly agricultural & industrial Service to portions of Oneida, Box Elder & Cache counties in Utah Communities: o Fielding, Plymouth, Newton, Wheelon, Riverside, Collinston, Garland, Bothwell, Thatcher, Deweyville, Elwood, & Tremonton Voltages: 138, 46 & kv Substations: o one transmission o eight distribution o three customer owned
10 2000 PACIFICORP PAGE 10 HONEYVILLE AREA SUBSTATIONS Mainly agricultural Service to Box Elder county Communities: o o o Honeyville Corrine Bear River Voltages: 138, 46 & kv Substations: o o o one transmission six distribution two customer owned
11 2000 PACIFICORP PAGE 11 LAMPO AREA LOADS All industrial loads Service in Box Elder county Voltages: 138 & 46 kv Substations: o o one transmission three customer owned
12 2000 PACIFICORP PAGE 12 Total Area Load Growth Base System Loads o o Growth o Summer 2015: 276 MVA (76% industrial) Winter : 220 MVA Summer: 1.1% (includes industrial) o Winter: 1.0% Projected System Loads o o Summer 2020: 310 MVA (includes industrial) Winter : 254 MVA
13 2000 PACIFICORP PAGE 13 Area Generation MW hydro units, 37.5 MW, owned by PacifiCorp. Average combined daily output is 16 MW. Several small third party river hydro s east of Brigham City near Mantua.
14 2000 PACIFICORP PAGE 14 Area Distribution Capacity The area is sectionalized into four operating areas: Malad-19.2 MVA Honeyville-35 MVA, Transmission substations: Cutler-56 MVA Lampo-75 MVA Distribution substations: (4) kv transformers MVA (1) kv transformer 14.0 MVA (2) kv transformers 13.4 MVA (15) kv transformers 65.0 MVA Total Distribution capacity is 205 MVA* *rounded up
15 Malad Bank #2 Increase Capacity 2000 PACIFICORP PAGE 15
16 2000 PACIFICORP PAGE 16 Move existing tap (3) to tap (4) in order to boost the voltage at Bear River & Blue Creek. e A load transfer on the distribution system is also required from Bush to Gold Rush; which will be done under the direction of field engineering.
17 Substation equipment bus fault-duty is within guidelines PACIFICORP PAGE 17
18 During peak summer loading most any of the N-1 conditions may require load shedding PACIFICORP PAGE 18
19 2000 PACIFICORP PAGE 19 Construction Schedule Summary Construction Schedule Summary 2016 CONSTRUCTION Set voltage recording meters at Blue Creek to verify high side voltage. Verify the jumpers on the Bear River tap line are equal to or greater than the line capacity. O/M O/M Subtotal $ CONSTRUCTION Malad Bank #2 Increase Capacity. $1,960,000 Subtotal $1,960, CONSTRUCTION No construction proposed for this year CONSTRUCTION Change No-Load Taps at Honeyville, move load from Bush to Gold Rush. N/A Subtotal $0 O/M Subtotal $ CONSTRUCTION No construction proposed for this year. Subtotal $0 Grand Total $1,960,000
20 2000 PACIFICORP PAGE 20 Honeyville/Malad Study Any questions or comments?
21 2000 PACIFICORP PAGE 21 MONTPELIER STUDY FINDINGS AREA ENGINEER - MARK ADAMS Completed by Carlton Jones
22 2000 PACIFICORP PAGE 22 Montpelier Study Area Ovid & Montpelier in north 69 kv loop around Mud Lake Intersection of three state borders Naughton in south 46 kv system from Sage
23 2000 PACIFICORP PAGE 23 Montpelier Study Info Five residential load centers: Montpelier, Cokeville, Garden City, St. Charles, & Bear River Remaining substations are agricultural Four transmission substations: Ovid, Sage, Naughton* & Oneida* Transmission Voltages:138, 69, & 46 kv Distribution Voltages: 12.47, 7.2, & 2.4 kv No appreciable generation Substation equipment bus fault duty: within guidelines No transmission capacitors *Naughton & Oneida are outside this study, but are sources for the area.
24 2000 PACIFICORP PAGE kv System Ovid kv to Naughton kv Ovid kv Serves Rich, Montpelier & Bear Lake areas Substations: o three transmission o eleven distribution Sage kv Naughton kv
25 2000 PACIFICORP PAGE kv System North & south from Sage service to Cokeville, Randolph, Woodruff Can be backfed by installing kv mobile at Railroad Substations: o One transmission o Five distribution
26 2000 PACIFICORP PAGE 26 Load & Growth Base System Loads o o Summer 2016: 33.4 MVA Winter : 23.8 MVA Growth o Summer: 2.3% o Winter: 1.2% Projected System Loads o o Summer 2020: 38.2 MVA Winter : 25.3 MVA Distribution Capacity: 65 MVA (Summer)
27 2000 PACIFICORP PAGE 27 N-0 System Improvements ( ) The Garden City area is prone to low voltages. Switching Lifton s feed to the Ovid-Naughton 69 kv line solves the low voltage problem. A tap change at Sage reduces the likelihood of low voltages on the Sage 46 kv system that may be increased by the above Lifton change. Regulators at St. Charles are undersized. They need to be replaced with kva units.
28 2000 PACIFICORP PAGE 28 N-1 System Improvements Outages involving Naughton & Ovid sources are difficult to mitigate & may require dropping load. The line between Ovid & Sage can only be opened with circuit breakers. Installing two loop-opening switches, i.e. with bottles, one on either side of Indian Creek tap will help reduce switching outages. Note: Unplanned transmission outages are uncommon in the area.
29 2000 PACIFICORP PAGE 29 Construction Schedule Summary Construction Schedule Summary 2016 Construction Move Lifton's source to Ovid-Sage line. Change Sage O&M no-load tap to #3 from #1 prior to transfer St. Charles ~ Increase capacity: Replace existing $ 260,000 regulators with 250 kva units 2017 Construction New 69kV LO/LD switch between Lifton & Indian Creek $ 62, Construction No work required 2019 Construction No work required 2020 Construction No work required Total: $ 322,000
30 2000 PACIFICORP PAGE 30 Montpelier Study Any questions or comments?
31 2000 PACIFICORP PAGE 31 Utah Valley Study Prepared by: Nicole DeGiulio Area Planner: Nathan Wilson
32 2000 PACIFICORP PAGE 32 System Overview 1 3 Primary Sources kv lines from Salt Lake Valley 2. Spanish Fork kv 3. Lake Side Generation 4. Payson Generation (UAMPS) 4 2
33 2000 PACIFICORP PAGE 33 Load Growth Base System Loads o Summer 2015: 1011 MW (Industrial 47%) o Winter : 617 MW Growth: o Average Summer Percentage 3.2% o Average Winter Percentage 3.6% Projected System Loads o o Summer 2020: 1232 MW Winter : 816 MW Distribution capacity 681 MVA
34 2000 PACIFICORP PAGE 34 N-0 Conditions Vineyard Upgrade, 2017 Vineyard XFMR at 112% (22.4 MVA Rating) This is an approved project Convert substation to 138kV & Install a 30 MVA LTC transformer at Vineyard substation. Estimated cost: $7.6 Million
35 2000 PACIFICORP PAGE 35 N-0 Conditions Pelican Point Low Voltage, 2018 Pelican Point has low voltage This is an approved project. Move Pelican Point on to distribution circuit, Saratoga 17 Estimated cost: $675k
36 2000 PACIFICORP PAGE 36 N-0 Conditions Willow Ridge Transformer, 2018 Willow Ridge XFMR at 104% (14 MVA Rating) This is an approved project. Increase Capacity ~ Install a 22.4 MVA transformer with LTC Estimated cost: $750k
37 2000 PACIFICORP PAGE 37 N-0 Conditions Benjamin Transformer, 2019 Benjamin 2.5 MVA XFMR at 109% This is an approved project. Install a 3.75 MVA transformer. The existing single phase regulators will also need to changed to match the new transformer rating. Estimated cost: $500k
38 2000 PACIFICORP PAGE 38 N-0 Conditions Mapleton Transformer, MVA transformer at 106% This is an approved project. Install a 22.4 MVA transformer with LTC. Estimated cost: $1.4m
39 2000 PACIFICORP PAGE 39 N-0 Conditions Lehi Carter Conversion, 2019 Accommodate a Lehi City Carter substation conversion to 138 kv. It is required to rebuild 2.1 miles of 46 kv line to 138 kv, from Carter to Bull River, tying into the existing 138 kv system. This is an approved project. Use 1272 ACSR conductor. Estimated cost: $1.7m
40 2000 PACIFICORP PAGE 40 N-0 Conditions American Fork Transformer, 2020 Existing transformer has a 28.3 MVA rating loaded to 106% Install a second 30 MVA transformer with LTC. Estimated cost: $5.8m
41 2000 PACIFICORP PAGE 41 Total Construction Costs Construction Item 2017 CONSTRUCTION Cost Vineyard ~ Increase capacity $7.6m Subtotal $7.6m 2018 CONSTRUCTION Pelican Point ~ Remove substation & move load to distribution $675k Willow Ridge ~ Increase capacity. Install a kv transformer $750k Subtotal $1.425m 2019 CONSTRUCTION Benjamin ~ Increase capacity. Install a kv transformer $500k Mapleton ~ Increase capacity. Install a kv transformer $1.4m Lehi #3 ~ Convert to 138 kv & rebuild 46 kv line $1.7m Subtotal $3.6m 2020 CONSTRUCTION American Fork ~ Increase capacity. Install a second kv transformer $5.8m Subtotal $5.8m TOTAL COST $18.425m
42 Any questions or comments? 2000 PACIFICORP PAGE 42
43 2000 PACIFICORP PAGE 43 Study Areas for 2016 Kickoff Studies Smithfield/Preston & Sigurd, Utah Carlton Jones Price, Utah Nicole DeGiulio Southern Wyoming & Vernal, Utah Scott Murdock
44 2000 PACIFICORP PAGE 44 Carlton Jones/Mark Adams SMITHFIELD/PRESTON AREA STUDY
45 2000 PACIFICORP PAGE 45 Smithfield/Preston Study Service Area Downey in the North Dividing line to the East is the Cache Nation Forest Wheelon & Treasureton are the main sources for the area
46 2000 PACIFICORP PAGE 46 Smithfield/Preston Study Service Area Transmission Voltages are 230,138, & 46 kv Transmission substations: o Treasureton o Oneida o Franklin o Green Canyon kv kv (generation) kv kv o Smithfield kv Thirteen distribution substations, & 25 kv Municipalities: Logan City & Hyrum City Four transmission customers Area generation < 50 MW of natural gas & hydro
47 2000 PACIFICORP PAGE 47 Smithfield/Preston Study Any questions or comments?
48 2000 PACIFICORP PAGE 48 Carlton Jones/Nathan Wilson SIGURD UTAH AREA STUDY
49 2000 PACIFICORP PAGE 49 Sigurd Utah Study Includes portions of Sanpete, Sevier, Beaver, Garfield, Piute & Millard counties Some of the larger cities served include Gunnison, Beaver, Richfield, Panguitch, & Milford
50 2000 PACIFICORP PAGE 50 Sigurd Utah Study There are approximately 32 substations in the area Transmission voltages served are 230, 138, 69 & 46 kv Other entities within the area include Garkane Energy & Beaver City Municipal Electric
51 2000 PACIFICORP PAGE 51 Sigurd Utah Study Generation in the area is Blundell Geothermal Plant & Upper Beaver Hydro Plant.
52 2000 PACIFICORP PAGE 52 Sigurd Utah Study Any questions or comments?
53 2000 PACIFICORP PAGE 53 Nicole DeGiulio/Nathan Wilson PRICE AREA STUDY
54 2000 PACIFICORP PAGE 54 Price Study Soldier Summit in the north Emery city in southwest Green River in southeast I-70 defines the southern boundary
55 2000 PACIFICORP PAGE 55 Price Study Info Covers 5,200 square miles in Emery, Carbon & surrounding counties Two municipalities: Price city & Helper city Main source for the area is three local generation plants Approximately 60 substations, 31 are customer owned Transmission voltages 46, 69, 138 & 345 kv Study will concentrate mainly on the 138 kv system & below
56 2000 PACIFICORP PAGE 56 Price Study Any questions or comments?
57 2000 PACIFICORP PAGE 57 Scott Murdock/Talmage Daley SOUTHERN WYOMING STUDY
58 2000 PACIFICORP PAGE 58 Southern Wyoming Study The southern Wyoming study serves portions of Sweetwater, Carbon, & Albany counties. Major cities served include: Green River, Rock Springs, Sinclair & Laramie.
59 2000 PACIFICORP PAGE 59 Southern Wyoming Study Covers approximately 14,000 square miles of area There are approximately 32 substations in the area Transmission voltages: 345, 230, 115 & 57 kv Majority of investigative work will be 230 kv & below Area has several municipalities including WAPA & AMOCCO
60 2000 PACIFICORP PAGE 60 Southern Wyoming Study Main sources of generation are Flaming Gorge Dam in Utah, Jim Bridger thermal plant & Foote Creek Rim wind plant in Wyoming.
61 2000 PACIFICORP PAGE 61 Southern Wyoming Study Any Questions or Comments?
62 2000 PACIFICORP PAGE 62 Scott Murdock/Nathan Wilson VERNAL UTAH AREA STUDY
63 2000 PACIFICORP PAGE 63 Vernal Study Town of Hanna in west Town of Vernal in east Bonanza Power Plant (Deseret) It is approximately 53 miles northwest of Helper, Utah
64 2000 PACIFICORP PAGE 64 Vernal Study Info About 1,700 sq miles of territory located in Duchesne & Uintah counties Major communities served are Vernal & Maeser There are 11 substations, four are customer owned Transmission voltages include 345,138, & 69 kv
65 2000 PACIFICORP PAGE 65 Vernal Area Generation Generation from Flaming Gorge also contributes to the area Bonanza, owned by Deseret Generation & Transmission (DG&T), is the only generation within the study area
66 2000 PACIFICORP PAGE 66 Vernal Study Any Questions or Comments?
Rocky Mountain Power Five Year Study Findings & Kick Off Meeting
2000 PACIFICORP PAGE 1 Attachment K Rocky Mountain Power Five Year Study Findings & Kick Off Meeting Thursday, December 8 2016 2000 PACIFICORP PAGE 2 Study Areas for 2016 Findings Reports Southeast, Utah
More informationSalt Lake County Electrical Plan Task Force October Douglas N. Bennion, P.E. Vice President Rocky Mountain Power
Salt Lake County Electrical Plan Task Force October 2009 Douglas N. Bennion, P.E. Vice President Rocky Mountain Power 1 Rocky Mountain Power s Bright History In 1881, Salt Lake City became the fifth city
More informationQ0044 interconnection at
Generation Interconnection Feasibility Study Report for Q0044 interconnection at Utah County Utah on PacifiCorp s Transmission System (138 kv Transmission System) September 15, 2004 Page 1 1.0 Description
More informationTransmission Planning Attachment K Public Input Meeting
Transmission Planning Attachment K Public Input Meeting FERC 890 6 th Quarter Meeting May 25, 2011 Agenda Mountain Time Topic Presenter 1:00 1:15 Greetings and Introduction Dennis Desmarais 1:15 1:30 Attachment
More informationPHONE # FAX # BOX ELDER COUNTY P F P F P F CACHE COUNTY
1 1 REHABILITATION ACILITIES Mission at Bear River Rehab Ctr 460 W 600 N, Tremonton 84337 Pioneer Care Ctr 815 S 200 W, Brigham City 84302 Willow Glen Health Rehab 775 N 200 E, Brigham City 84302 Rocky
More informationGateway South Transmission Project
Phase 1 Comprehensive Progress Report Volume 1 - Technical Report Report Prepared by PacifiCorp Transmission Planning Department November 21, 2008 WECC1-V4 Phase 1 Comprehensive Progress Report Executive
More informationAttached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.
March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating
More informationTHE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive
More informationAppendix D Black Hills Project Summary
Page 1 of 28 Appendix D Black Hills Project Summary Table of Contents Black Hills Project Summary... D-1 Boone-Nyberg 115 kv Project... D-3 Rattlesnake Butte 115 kv Substation Terminal... D-6 Fountain
More informationTEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY
TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY 2011-2020 P+ PowerPlus Engineering A Department of STAR Energy Services, LLC TEN YEAR PLANNING GUIDE 2011-2020 SHASTA LAKE ELECTRIC UTILITY CITY OF
More informationNorth Oregon Coast Area Study. Adam Lint
North Oregon Coast Area Study Adam Lint PAGE 2 North Oregon Coast System Overview - Clatsop Study Covers: Transmission Switching Stations (Clatsop District): Astoria Lewis and Clark 115 kv Distribution
More informationOuter Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)
Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co) Participants: Great River Energy Xcel Energy Inc. Executive Summary This study is done to address various load serving
More information100 MW Wind Generation Project
A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility
More informationLocal Transmission Plan. October 11, 2013 Revised August 25, 2014
Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated
More informationWyoming Energy Projects
Wyoming Energy Projects Wyoming Infrastructure Authority Spring Conference March 28-29, 2019 PacifiCorp Overview Two divisions Rocky Mountain Power and Pacific Power 5600 Employees 1.9 million electricity
More informationDunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study
` Dunvegan Hydroelectric Project For Glacier Power Limited Preliminary Interconnection Study Prepared by Pung Toy, P. Eng. and Ata Rehman, P. Eng. September 24, 2004 Table of Contents Table of Contents...
More informationLarge Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project
Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives Addendum San Juan Major Project Tri-State Generation and Transmission Association Power System Planning December, 2008
More informationConsulting Agreement Study. Completed for Transmission Customer
Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...
More informationBusiness Park North Muskegon County, MI
Business Park North Muskegon County, MI OVERVIEW January 1, 2017 CONTACT US Scott Corrin, Economic Development Manager 517-374-2248 scott.corrin@cmsenergy.com Consumers Energy Business Center 800-805-0490
More informationSouth Dakota 890 Study
South Dakota 890 Study September 16, 2011 South Dakota 890 Study Presentation of 890 Study results from 2011 Includes WAPA suggested system improvements and timelines Stakeholder Feedback Questions? 2
More informationFalcon-Midway 115 kv Line Uprate Project Report
Falcon-Midway 115 kv Line Uprate Project Report 12/1/2008 1 Background The function of this project is to uprate the 26.7 miles of Tri-State s 115 kv line between Midway and Falcon substations from 50
More informationAppendix B. Summary of Changes to the Year Assessment
Appendix B Summary of Changes to the 2003 10- Assessment For the below tables, the following color-coding scheme was utilized for indicating what type of change has been made to the 10- Assessment from
More informationElbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI
Executive Summary Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI-2003-2 Xcel Energy Transmission Planning January 2004 This Interconnection Feasibility
More informationWest Station-West Cañon 115 kv Transmission Project
West Station-West Cañon 115 kv Transmission Project Project Sponsor: Additional Project Participants: Project Description: Black Hills Colorado Electric New 115 kv line from West Station to West Cañon
More informationDate: March 15, Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, Utah
TRANSMISSION PLANNING Craig Quist Director of Area/Transmission Planning East PacifiCorp 1407 West North Temple, Suite 275 Salt Lake City, Utah 84116 (801)220-4264 PH (801)220-2842 FAX Date: March 15,
More informationIllinois State Report
July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:
More informationCraig Quist Craig Quist
TRANSMISSION PLANNING Craig Quist, Manager Transmission Development & Planning PacifiCorp 1407 West North Temple, Suite 275 Salt Lake City, Utah 84140 801-220-4264 FAX 801-220-2842 craig.quist@pacificorp.com
More informationReasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders
Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders Reasonableness Test: Salisbury Substation 11kV Feeders DISCLAIMER The purpose of this document is to inform customers, Interested Parties,
More informationMuskegon Waste Water Treatment Site Muskegon County, MI
Muskegon Waste Water Treatment Site Muskegon County, MI OVERVIEW January 1, 2017 CONTACT US Scott Corrin, Economic Development Manager 517-374-2248 scott.corrin@cmsenergy.com Consumers Energy Business
More informationTwin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN
Twin Cities Minnesota Zone Meeting Xcel Energy May 11, 2005 Bloomington, MN Overview of Presentation Xcel Energy Projects: Aldrich to St Louis Park 115 kv line Eden Prairie to Edina 115 kv line Eden Prairie
More informationProcess Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment.
Process Timeline Legend Problem Area that have been resolved Recurring Areas from previous System Assessment New Areas Area Bubbles Flows Modeled for One-Year Heavy Winter Peak Conditions Base Case Conditions
More informationBlack Hills Project Summary
2016 Rule 3627 Report Black Hills Project Summary Page 1 of 38 Black Hills Project Summary Colorado PUC E-Filings System D 1 2016 Rule 3627 Report Black Hills Project Summary Page 2 of 38 Category Transmission
More informationTransmission Planning. WECC 2014 Progress Report. March 14, 2014
Transmission Planning WECC 2014 Progress Report March 14, 2014 Report Prepared By: Dennis Stevens -TPP (360) 619-6821 BPA TS TPP 2014-022 Page 1 Table of Contents 1 Introduction... 1 2 Planned Transmission
More informationWestern Area Power Administration
2014/15 Integrated System (IS) 890 Local Planning Stakeholder Meeting #2 Western Area Power Administration Upper Great Plains Region Transmission Planning Stakeholder Meeting Wednesday, December 10 th,
More informationAlberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation
Decision 21781-D01-2016 Alberta Electric System Operator Needs Identification Document Application Facility Applications September 7, 2016 Alberta Utilities Commission Decision 21781-D01-2016: Alberta
More informationMILLIGAN SOLAR PROJECT
February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission
More informationWheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation
Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation 1. Description In the 2013-2014 Transmission Planning Cycle, the ISO approved the construction
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationFirst Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012
First Energy Generator Deactivation Request - January 2012 Deactivation Study Results and Required Upgrades April 25, 2012 General PJM received a notice on January 26, 2012 from FirstEnergy of its intent
More information2013 ANNUAL PROGRESS REPORT
March 1, 2013 Mr. David Franklin, Chairman WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768-2560 Mr. Enoch Davies WECC Technical Staff 155 North 400 West,
More informationEntergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects
Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects Entergy Transmission Planning Summit New Orleans, LA July 14, 2005 1 2004-06 EGSI-TX Transmission Western Region Reliability
More informationTransmission Planning Report
Transmission Planning Report Board of Directors Meeting December 15, 2010 1 Overview Study Team Reports Puget Sound Area Study Team Northern Mid-Columbia Study Team Cross Cascades Study Team Centralia
More information2013 ANNUAL PROGRESS REPORT
Bonneville Power Administration 2013 ANNUAL PROGRESS REPORT Report Prepared By: Dennis Stevens Bonneville Power Administration Transmission Planning TPP/OPP-3 (360) 619-6821 BPA TS TPP 2013-018 Page 1
More informationCUSTOMER/ TWIN ARROWS PROJECT
A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset
More informationSoutheastern Region Transmission Planning. 10 Year Transmission Expansion Plan
10 Year Transmission Expansion Plan Disclaimer The projects described in this presentation represent the current ten (10) year expansion plan. The expansion plan is periodically reviewed and may be revised
More informationSystem Impact Study Report
Report For: NTE Carolinas II, LLC ( Customer ) Queue #: 42432-01 Service Location: Rockingham County, NC Total Output: 477 MW (summer) / 540 MW (winter) Commercial Operation Date: 12/1/2020 42432-01 SIS
More informationSub Regional RTEP Committee - Southern. August 19, 2011
Sub Regional RTEP Committee - Southern August 19, 2011 2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator
More informationWestern Area Power Administration Rocky Mountain Region (LAPT) Network Integrated Transmission Service. Designated Network Resources
Customer Name Basin Electric Cheyenne Power and Light City of Fort Morgan & Estimated Maximum Resource MW Point of Receipt Delivering Party & Voltage Antelope Valley 2 Yellowtail Basin Electric 115 kv
More informationATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M
of Need In-service Cost Alternatives Service Projects in PG&E Service Territory Mare Island - Ignacio 115 kv NERC Category 2010 Reconductor the limiting 19 $19M Connect Highway May 2012 Line re-rates and
More informationStatus of PNM s Completed Transmission Construction Projects 11/30/2017
Status of s Completed Transmission Construction Projects Second Tah Ta Hey 115/345 kv Transformer Yah Ta Hey Switching Station On January 9, 2015, filed with the NMPRC under NMPRC Rule 440 information
More informationInterconnection System Impact Study Report Request # GI
Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010
More informationCustomer Charge or Minimum Bill. Total Average Annual Bill (9 Dth) Total Volumetric Rate*
Residential Gas Rates for Wyoming Regulated Utilities Gas Rates are in effect as of: 11/03/17 Estimates of Seasonal Bills (illustrational purposes only) Customer Charge or Minimum Bill Total Volumetric
More informationSub-Regional RTEP Committee PJM South
Sub-Regional RTEP Committee PJM South SRRTEP - South December 1, 2016 www.pjm.com PJM Baseline Project B2185 Update Problem: NERC Category B Violation (DVP Analysis) The 2017 summer base case indicates
More informationTransmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona
Transmission Planning & Engineering P.O. Box 53933 MS 3259 Phoenix, Arizona 85072-3933 March 9, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff
More informationReliability Analysis Update
Reliability Analysis Update Transmission Expansion Advisory Committee October 11, 2018 Proposal Window Exclusion Definitions The following definitions explain the basis for excluding flowgates and/or projects
More informationTransmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting
Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting BHE Wyoming Q4 Stakeholder Meeting November 17, 2016 @ 1:00PM MT Black Hills Energy Service Center 409 Deadwood Avenue, Rapid
More informationNew Jersey State Report
New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions
More informationUpdated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers
Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers Puget Sound Area Study Team Bonneville Power Administration, Puget Sound Energy, Seattle City Light,
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Memorandum To: ISO Operations (MRTU) Committee From: Armando J. Perez, Director of Grid Planning cc: ISO Board of Governors ISO Officers Date: April 29, 2005 Re:
More informationROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP
ROCKY MOUNTAIN POWER A DIVISION OF PACIFICORP January 29, 2014 201 South Main, Suite 2300 Salt Lake City, Utah 84111 VIA ELECTROl.fiC FILI1VG AND OVERNIGHT DELIVERY Wyoming Public Service Commission 2515
More informationService Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #
Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists
More informationThis are the pictures from the Stockholders Report
Utah Securities Corporation Utah Light and Traction Company Financial and Physical Data As of March 31, 1915 This are the pictures from the Stockholders Report Page 32 Electrically Operated Hydraulic Dredge
More informationBC Hydro System 2011 Annual Progress Report
March 1, 2011 Mr. Kyle R. Kohne, Chairman WECC Technical Studies Subcommittee Bonneville Power Administration P.O. Box 491 MS, TPP-OPP-3 Vancouver, WA 98666 Mr. Kent Bolton WECC Technical Staff 155 North
More informationProposed New Construction for
Tri-State Generation and Transmission Association, Inc. Colorado PUC E-Filings System Proposed New Construction for 2016 2019 Colorado PUC Rule 3206 Application April 28, 2016 TABLE OF CONTENTS A) Projects
More informationMountainland Association of Governments SPRINGVILLE-SPANISH FORK AREA TRANSPORTATION STUDY APRIL 2012
Mountainland Association of Governments SPRINGVILLE-SPANISH FORK AREA TRANSPORTATION STUDY APRIL 2012 PLANNING FOR OUR FUTURE Planners with the Mountainland Association of Governments (MAG) have evaluated
More informationInterconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado
Executive Summary Interconnection Feasibility Study Report Request # GI-2016-6 Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado Public Service Company of Colorado Transmission
More informationTri-State December 2013 Board Meeting
1 For more information Tri-State webpage: www.tristategt.org click Operations then Transmission Planning (http://www.tristategt.org/transmissionplanning/puc3627_trans missionprojects.cfm) Email: (transmissionplanning@tristategt.org)
More informationRocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH
Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No. 17-035-40 Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER Exhibit Accompanying Supplemental Direct
More informationPublic Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran
System Impact Study_50 MVA Load Interconnnection Request Near Collbran.doc Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran PSCo Transmission
More informationNew 115 kv Disconnect Switches at Bloomsburg MTS
115 kv Line tap from C9 to Bloomsburg MTS & New Bus Tie Switch CAA ID Number: 2007-EX353 Final Draft ASSESSMENT SUMMARY 1. GENERAL DESCRIPTION Norfolk TS and Bloomsburg MTS are supplied by a single 115
More informationFeasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation
Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT
More informationPJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008
PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral
More informationTABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:
TransWest Express Transmission Project TABLE OF CONTENTS 7.0 DESIGN OPTIONS... 7-1 7.1 OVERVIEW OF DESIGN OPTIONS... 7-1 7.2 DESIGN OPTIONS PURPOSE AND NEED AND DESIGN CHARACTERISTICS... 7-4 7.2.1 Design
More informationMarch 7, Subject: Southern California Edison 2011 Annual Progress Report
March 7, 2011 Mr. Kyle Kohne Mr. Kent Bolton Chair, WECC Technical Studies Subcommittee WECC Technical Staff Bonneville Power Administration University of Utah Research Park P.O. Box 61409 615 Arapeen
More informationPacific Gas and Electric Company s Revised 2016 Annual Progress
March 06, 2016 Mr. Philip Augustin Chair, WECC Technical Studies Subcommittee Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Report Pacific Gas and Electric
More informationFeasibility Study Report
Report For: Orion Renewable Resources LLC ( Customer ) Queue #: Service Location: Rockingham County, NC Total Output Requested By Customer: 100 MW Commercial Operation Date Requested By Customer: 11/1/2019
More informationSPP Notification to Construct
February 19, 2014 SPP Notification to Construct Mr. Mo Awad Westar Energy, Inc. P.O. Box 889 Topeka, KS 66601 RE: Notification to Construct Approved Reliability Network Upgrades Dear Mr. Awad, Pursuant
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives
More informationPJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study
PJM Generator Interconnection R81 Emilie (Fords Mill) 100.9 MW Impact Study Re-Study August 2008 DMS # 498781 General Queue R81 Emilie (Fords Mills) is a Fairless Energy, LLC request to obtain an additional
More information2013 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting
2013 SERTP Welcome SERTP 2013 3 rd Quarter Meeting 2 nd RPSG Meeting 1 2013 SERTP The SERTP process is a transmission planning process. Please contact the respective transmission provider for questions
More informationSub Regional RTEP Committee South
Sub Regional RTEP Committee South December 18, 2017 Baseline Reliability and Supplemental Projects Second Review 2 Date Project Last Presented: 10/30/2017 SRRTEP Problem Statement: DOM End of Life Criteria
More informationMTEP13 SPM #2- Central Region. March 25, 2013
MTEP13 SPM #2- Central Region Ameren Missouri March 25, 2013 Ameren Missouri Project Review Central Region: Ameren Missouri Ameren Missouri has a total of 10 project proposals that are recommended for
More informationPJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:
PJM SRTEP Meeting 2-13-2018 Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge: The problem statement states two 138kV CB s will be installed at Ambler Ridge, however the potential solution
More informationSupplemental Report on the NCTPC Collaborative Transmission Plan
Supplemental Report on the NCTPC 2007-2017 Collaborative Transmission Plan May 16, 2008 1 Table of Contents I. Executive Summary...1 II. Richmond-Fort Bragg Woodruff Street 230 kv Line...2 II.A. Need for
More informationTransWest Express Project
TransWest Express Project Phase One--Feasibility Study Final Study Report November 2006 A subsidiary of Pinnacle West Capital Corporation Executive Summary On October 21, 2005 Arizona Public Service Company
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 28 Blythewood 115 kv Switching Station: Construct 03087A Construct Blythewood Switching Station with four 115 kv line terminals, with plans to expand to 230 kv at a future date. Fold in the
More informationPG&E s 2012 Request Window Proposals
1 PG&E s 2012 Request Window Proposals Central Valley Patrick Tan Transmission System Planning PG&E September 27, 2012 Transmission Projects Overview 2 Projects Seeking CAISO Approval Pease 115/60 kv Transformer
More informationPacific Gas and Electric Company s 2013 Annual Progress Report
March 14, 2013 Mr. David Franklin Chair, WECC Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 Mr. Enoch Davies WECC Technical Staff 155 North 400 West Salt Lake
More informationGeneration Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.
Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project April 23, 2003 Introduction Eurus originally requested an interconnection
More informationDFO STATEMENT OF NEED REPORT
APPENDIX E DFO STATEMENT OF NEED REPORT Table of Contents 1.0 Executive Summary... 1 2.0 Description of the Area... 2 2.1 Geographic Study Area... 2 2.2 2016 System Configuration... 2 3.0 Area Loading
More informationAPPENDIX E: Project Need and Description
APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Lakeville 115 kv Bus Upgrade Installation of a sectionalizing breaker to be installed on 115 kv bus section
More informationSub Regional RTEP Committee Mid-Atlantic
Sub Regional RTEP Committee Mid-Atlantic March 23, 2018 First Review Baseline Reliability and Supplemental Projects 2 AEC Transmission Zone: Supplemental Project 69/12kV Wenonah Substation Retire/Bypass
More information15 Nelson-Marlborough Regional Plan
15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant
More informationTransmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation
Transmission Improvements Plan for 575 MW Network Service Request CC 7 Generation Facility (OASIS # 143556) Georgia Transmission Corporation November 11, 2010 CC7 TIP 11-11-2010 (2).docx PROBLEM STATEMENT
More informationMarch 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1
Energy Division P.O. Box 937 333 E. Barioni Blvd. Imperial, CA 92251 www.iid.com March 18, 2014 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Senior Power System Consultant Avista System
More informationPJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G
PJM Sub Regional RTEP Committee Mid-Atlantic January 22, 2016 Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G PSE&G System Characteristics New Jersey utility characterized by densely populated
More informationSouth Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget
Project 1 of 34 Aiken Trans - Aiken Hampton 115 kv Line: Upgrade 1272A Upgrade the 115 kv line between Aiken and Aiken Hampton substations from 336 ACSR to 1272 ACSR. Total line length approximately 3.7
More informationPacific Gas and Electric Company s Revised 2015 Annual Progress
March 02, 2015 Mr. Tracy Rolstad Chair, WECC Technical Studies Subcommittee Avista PO Box 3727 MSC-16 1411 East Mission Ave Spokane, WA 99220-3727 Mr. Enoch Davies WECC Technical Staff 155 North 400 West
More informationTransmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015
No. Comment Submitted ISO Response Date Q&A Posted 1 Will the ISO consider proposals that are not within the impedance range specified? Yes. However, the benefits estimated and studies performed by the
More informationHeader. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8
Header Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations RT 007-11 Balhannah and Uraidla - Final Draft Page 1 of 8 DISCLAIMER The purpose of this document is to inform customers,
More information