Current Corridor Characteristics. MN 62 Corridor Performance
|
|
- Peregrine Andrews
- 5 years ago
- Views:
Transcription
1 Corridor Context The corridor runs 12 miles between I-494 and MN 55 south of Minneapolis. The corridor serves as an important East-West connection for the Metro area. A portion of the corridor has been reconfigured as part of the Crosstown project. City Population Measure Result Infrastructure Preservation Eden Prairie 54,901 60,797 Bridge Edina 47,425 47,941 Minneapolis 382, ,578 Bridge Condition--% Good and satisfactory (by deck area) Minnetonka 51,301 49,734 34,310 35, , ,278 Current Corridor Characteristics MN Corridor Performance Population Trends Statewide Result 95.3% 86.9% 0% 3.2% Ride Quality Good--% of miles 72.9% 70.2% Ride Quality Poor--% of miles 0% 3.7% Bridge Condition--% Poor (by deck area) Highway: MN 2009 AADT: 29,500 93, HCADT: 880 3,250 Number of lanes: 4-6 Key highway connections: I-35W, I494, MN 100, US 169 Public Transit Rail Blue Line (Hiawatha LRT) One Park and Ride lot with a capacity of 400 parking spaces SOO line to Paynesville
2 MN Existing Conditions - Safety Map S Minneapolis 55 Ramsey Co. tu W Hennepin Co. Edina [_ tu 212 Safety Needs [_ Eden Prairie CMSP Problem Locations CMSP Problem Segments Trunk Highways County Highways Class 1 Railroads County Boundaries 100 See District Highway Safety Plan for additional issues and strategies Metro to be Completed May 2012 MN Corridor Safety Performance (MN 55 to I 494) Measure Fatal and Serious Injury Crashes in Corridor Dakota Co. Percent of All Severe Crashes in Corridor Top Four Driver Related Crash Issues Impaired Driver* % Unbelted Driver* % Speed Related % Invalid License % Top Three Infrastructure Related Crash Issues Toward Zero Deaths Efforts County TZD Safe Roads Grant 2012 TZD Enforcement Grant TZD Region Year Established (ATP) County Safety Plan Completion Date Hennepin No Yes Metro, Planned 2012 (ATP 5) Sept Lane Departure Crash % Intersection Crash % Head-on Crash % Fatal and Serious Injury Crashes Corridor Comparison to State Crashes In Corridor Statewide for Trunk Highways 6 2,440 Miles 12 10,980 Fatal and Serious Injury Crashes per Mile E Miles * Crashes may be under reported as this number is according to officer's first impression Note. Data presented include all fatal and serious injury crashes betw een
3 Planned Transit Investments Southdale Transit Center $ 850,000 MN Projects Investment Area Bridge Lighting Signing Project Mill and Overlay Tracy Ave to Penn Ave Redeck Bridges Under Penn and Xerxes Ave Replace lighting Sign Replacement I-494 to TH 55 MN Adjacent Projects Length (Miles) Fiscal Year Investment Area $ 4.5 Million Landscaping N/A 2013 $ 1.6 Million Signing $ 1 Million $ 650,000 : $ 7.8 Million ADA Project Landscaping Various Locations Replace Signing I-94 to I-494 Mill and Overlay I-494 to TH Retrofit Pedestrian Bridge and Noise Walls Length (Miles) Route Fiscal Year 6.2 I-35W $ 1 Million 15.6 US $ 750, US $ 4.8 Million N/A MN $ 1.3 Million $ 7.8 Million North of MN
4 Corridor Performance Based Needs ( ) Bridge Preservation Preservation Culvert Preservation Pipe Replacement Safety Improvements* Mobility 5 Bridges 15 miles of poor pavement 0 7 Poor pipes 0 CMSP Locations 3 CMSP Segments *Assumes completion of STIP projects. *Systematic safety improvements are included as part of most highway projects. Refer to safety map for additional safety information
5 35W/ Crosstown Project Description Reconstruction of 35W/ interchange from 66 th St to 42 nd St in Minneapolis/ High occupancy vehicle lanes *Not all of this total was spent on MN $288 Million* Project Description Bridge Projects Projects Recent Investments ( )* 2010: Replace bridge under Portland Ave 2005: Repair deck on bridges (TH 77 and 28 th Ave) 2009: Bituminous crack seal 2005: Mill and overlay, bus shoulders (Shady Oak Rd to TH 100) 2005: Mill and overlay, bus shoulders (Portland Ave to 43 rd Ave) 2002: Mill and overlay, culvert replacement (TH 100 to I-35W) $ 1.5 Million $ 9 Million Other Infrastructure 2009: Lighting Replacement (TH 212 to Gleason Rd) $ 822,000 *Only includes projects over $500,000. Systematic safety improvements are routinely included as part of most highway projects $ Million
I-394 Corridor Performance
Population Trends Corridor Context The corridor runs from edge of Hennepin County to downtown Minneapolis and serves the cities of Delano, Independence, Medina, and Wayzata. City Population 2000 2010 2,088
More informationUS 10 Corridor Performance
Corridor Context The corridor runs northwest 18 miles from I-35W to the edge of Anoka County. The corridor connects the cities of Ramsey, Anoka,, Mounds View, and Blaine. Current Corridor Characteristics
More informationPopulation Trends. US 12 Corridor Performance
Corridor Context The corridor runs over 81 miles from Willmar to the Twins Cities metropolitan area. It connects the Twin Cities and the cities of Montrose, Howard Lake, Cokato, Dassel, Litchfield, Atwater,
More informationTransportation Improvement Program (TIP) Candidate Project List for Public Review
2011-2014 Transportation Improvement Program (TIP) Candidate List for Public Review Table 1 Annual Listing Of Federal Aid Obligation For Federal Fiscal Year 2010 North Dakota s Number Transit 410083 Transit
More informationSales and Use Transportation Tax Implementation Plan
Sales and Use Transportation Tax Implementation Plan Transportation is more than just a way of getting from here to there. Reliable, safe transportation is necessary for commerce, economic development,
More informationPublic Information Packet FY Fargo-Moorhead Metropolitan Transportation Improvement Program (TIP)
Public Information Packet FY - Fargo-Moorhead Metropolitan Transportation Improvement Program (TIP) Comment Form Annual Element TIP Projects - TIP Projects Year - Metropolitan Transportation Improvement
More informationTransportation accomplishments
1 1 Welcome Transportation accomplishments Federal Funding State Funding Challenges Future Projects 2 Transportation Project: The NDDOT had a record construction season in 2011. Completed $595.6 million
More informationTransitways. Chapter 4
4 Transitways Figure 4-1: Hiawatha LRT Train at the Lake Street/Midtown Station The 23 Transportation Policy Plan identifies a network of transitway corridors to be implemented by 23. Transitways recommended
More informationExtending TRACKS. Preliminary design plan review underway. Public comment and approval process in May & June. Municipal Consent Process
Extending TRACKS Issue 5 Spring 2014 Preliminary design plan review underway Public comment and approval process in May & June Residents and businesses along the Southwest LRT (METRO Green Line Extension)
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationCorridor Sketch Summary
Corridor Sketch Summary SR 241: I-82 Jct (Sunnyside) to SR 24 Jct Corridor Highway No. 241 Mileposts: 7.53 to 25.21 Length: 17.65 miles Corridor Description The seventeen and one-half mile corridor begins
More informationOperating & Maintenance Cost Results Report
Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June
More informationCommittee Report. Transportation Committee. Business Item No
Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope
More informationBackground Information for MPRB Community Advisory Committee for 2010 Southwest Light Rail Transit Project DEIS Comment Letter Section 2
Background Information for MPRB Community Advisory Committee for 2010 Southwest Light Rail Transit Project DEIS Comment Letter Section 2 1 2. SW LRT Corridor Overview Source: http://www.southwesttransitway.org/home.html
More informationWestern ND Meeting. February 19, 2014 Grant Levi, NDDOT Director
Western ND Meeting February 19, 2014 Grant Levi, NDDOT Director 1 Traffic Trends in North Dakota 2 Truck Traffic 2008 3 Truck Traffic 2012 4 Average Daily Traffic 5 ND Vehicle Miles Traveled Statewide
More informationMPO Staff Report Technical Advisory Committee: July 12, 2017
MPO Staff Report Technical Advisory Committee: July 12, 2017 RECOMMENDED ACTION: 2 nd TAC Meeting with Kimley-Horn/WSB in Updating the Street/Highway Element of 2045 Metropolitan Transportation Plan. Matter
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationC LINE: LONG-TERM GLENWOOD REALIGNMENT STUDY
C LINE: LONG-TERM GLENWOOD REALIGNMENT STUDY Comments on this study and the long-term Glenwood realignment recommendation can be submitted to brtprojects@metrotransit.org. Comments can be submitted through
More informationKentucky Highway District 6
Kentucky Highway District 6 ROAD AND BRIDGE CONDITIONS, TRAFFIC SAFETY, TRAVEL TRENDS, AND NEEDS MARCH 2018 PREPARED BY WWW.TRIPNET.ORG Founded in 1971, TRIP of Washington, DC, is a nonprofit organization
More information2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS. Eastside Transportation Partnership September 9, 2016
2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS Eastside Transportation Partnership September 9, 2016 1 2 PSRC 2016 Project Selection Process 2018-2020 Estimated FHWA Funds Available: (Summary)
More informationEXCEPTION TO STANDARDS REPORT
EXCEPTION TO STANDARDS REPORT PROJECT DESCRIPTION AND NEED The project is located in Section 6, Township 23 North, Range 9 East and Section 31 Township 24 North, Range 9 East, in the Town of Stockton,
More informationI-35W Past, Present, and Future: METRO Orange Line
I-35W Past, Present, and Future: METRO Orange Line 2018 State Public Transportation Partnerships Conference Charles Carlson Director, BRT Projects Metro Transit Charles.Carlson@metrotransit.org Metro Transit:
More informationArterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014
Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update
More informationExtending TRACKS. Peer reviews, advanced design next for Southwest LRT
Extending TRACKS Issue 7 Fall 2014 Peer reviews, advanced design next for Southwest LRT A new chapter is beginning for the planned METRO Green Line Extension (Southwest Light Rail Transit Project), following
More informationBi-County Transitway/ Bethesda Station Access Demand Analysis
Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction
More informationEnergy Technical Memorandum
Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter
More informationRecommended Transportation. Capital Improvement Program
Recommended 2018-2022 Transportation Capital Improvement Program 1 Overview 2017 Review 2018-2022 Considerations 2018-2022 Recommended CIP 2 Limited Resources are Directed to the Highest Priority Number
More informationMETRO Orange Line BRT American Boulevard Station Options
METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN
More informationDRAFT Travel Demand Methodology & Forecast
DRAFT Travel Demand Methodology & Forecast February 2016 Revision 4 Southwest LRT Project Technical Report This page intentionally blank. Contents 1. Introduction... 1 2. Methodology... 3 2.1. Model Overview...
More informationDistrict 7 10-Year Capital Highway Investment Plan ( )
District 7 10-Year Capital Highway Investment Plan (2018-2027) Cover Picture DRAFT JUNE 2017 Prepared by Office of Transportation System Management DISTRICT 7 10-YEAR CHIP OVERVIEW District 7 s 10-Year
More informationACTION TRANSMITTAL No
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior
More informationvision42
vision42 www.vision42.org vision42 auto-free light rail boulevard for 42nd Street Roxanne Warren, AIA, Chair George Haikalis, ASCE, Co-Chair Institute for Rational Urban Mobility,Inc. www.vision42.org
More informationSnelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1
Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule
More informationCEDAR AVENUE TRANSITWAY Implementation Plan Update
CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,
More informationBrigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction
Brigham City 1200 West Box Elder Creek Bridge - Widening Project Type Reconstruction 550 North to 650 North $ 1,750,000 $ 1,582,113 To widen an existing bridge on 1200 West over Box Elder Creek that will
More informationBusiness Advisory Committee. July 7, 2015
Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS
More informationAlternatives Analysis Findings Report
6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop
More informationApril 27, FHWA/FTA Approval of an Amendment to the Kansas STIP to include WAMPO s April 14, 2009 TIP Amendment 6
U.S. Department of Transportation Federal Transit Administration Federal Highway Administration 901 Locust Street, Suite 404 6111 SW 29 th Street, Suite 100 Kansas City, MO 64106 Topeka, KS 66614-4271
More informationChapter 7. Transportation Capital Improvement Projects. Chapter 7
Chapter 7 Transportation Capital Improvement Projects Chapter 7 81 Chapter 7 Transportation Capital Improvement Projects Local Transportation Sales Tax Programs For over three decades, Santa Clara County
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationMetropolitan Freeway System 2013 Congestion Report
Metropolitan Freeway System 2013 Congestion Report Metro District Office of Operations and Maintenance Regional Transportation Management Center May 2014 Table of Contents PURPOSE AND NEED... 1 INTRODUCTION...
More informationEUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT
EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING
More informationDevelop ground transportation improvements to make the Airport a multi-modal regional
Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use
More informationCITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE
CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE TUESDAY, DECEMBER 5, 2017 1 DISCUSSION TOPICS Update of Infrastructure Action Plan (IAP) o Sidewalk and Roadway projects
More informationMaryland Gets to Work
I-695/Leeds Avenue Interchange Reconstruction Baltimore County Reconstruction of the I-695/Leeds Avenue interchange including replacing the I-695 Inner Loop bridges over Benson Avenue, Amtrak s Northeast
More informationHighway Safety Update
Highway Safety Update January 26, 2018 Karin Mongeon, Safety Division Bryon Fuchs, Local Government NDDOT Safety Division The Traffic Records Program Collect and analyze crash data to identify traffic
More informationNew Buck O Neil (U. S. 169) Crossing Benefit-Cost Analysis. Kansas City, Missouri
New Buck O Neil (U. S. 169) Crossing Benefit-Cost Analysis Kansas City, Missouri New Buck O Neil (U. S. 169) Crossing Benefit-Cost Analysis prepared for Kansas City, Missouri prepared by Burns & McDonnell
More informationSTH 60 Northern Reliever Route Feasibility Study Report
#233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development
More informationTransportation Committee Revised Project Scope and Cost Estimate. November 23, 2015
Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project
More informationSlow Down! Why speed is important in realizing your Vision Zero goals and how to achieve the speeds you need
Slow Down! Why speed is important in realizing your Vision Zero goals and how to achieve the speeds you need Lake McTighe, METRO Joel McCarroll, ODOT Jenna Marmon, ODOT Matt Ferris-Smith, PBOT Oregon Active
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of April 24, 2004 DATE: April 14, 2004 SUBJECT: Arlington Boulevard (U.S. 50) Bridge Deck Replacement at Washington Boulevard - Overhead Utility
More informationTransportation. Background. Transportation Planning Goals. Level of Service Analysis 5-1
Transportation portion of the city s stormwater utility, and state road and fuel taxes. Background The transportation needs of the City of Lacey and its planning areas are met by a growing multimodal network
More informationIntroduction. Assumptions. Jeff Holstein, P.E., City of Brooklyn Park Steve Wilson, Principal Tim Babich, Associate Krista Anderson, Engineer
SRF No. 10482 To: From: Jeff Holstein, P.E., City of Brooklyn Park Steve Wilson, Principal Tim Babich, Associate Krista Anderson, Engineer Date: May 16, 2018 Subject: City of Brooklyn Park Year 2040 Forecasts
More informationCTA Blue Line Study Area
CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING
More informationPurpose and Need Report
Purpose and Need Report State Highway (SH) 29 From Southwestern Boulevard to SH 95 Williamson County, Texas (CSJ: 0337-02-045) Prepared by Blanton & Associates, Inc. Date: November, 2015 The environmental
More informationUnified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report
Unified Corridor Investment Study DRAFT Step 2 Scenario Analysis Report REVISIONS 1. Table 39: New Public Investments for Operation and Maintenance Costs 2. Appendix A-10: Passenger Rail Service - Operations
More informationOver-Dimensional Vehicle Restriction Study for US 129 in TN
Over-Dimensional Vehicle Restriction Study for US 129 in TN July 30,2015 TDOT Region 1 US 129 Location Map US 129 Topography and Scenery Operational and Safety Study August 2014, US129 Operational and
More informationValley Metro Overview. ITE/IMSA Spring Conference March 6, 2014
Valley Metro Overview ITE/IMSA Spring Conference March 6, 2014 Valley Metro Who Are We? Operate Regional Transit Services Valley Metro and Phoenix are region s primary service providers Light Rail and
More informationHennepin County Transit Oriented Development Program. The Ellipse, St. Louis Park, 2009
Hennepin County Transit Oriented Development Program The Ellipse, St. Louis Park, 2009 What is Transit Oriented Development (TOD)? Development within walking distance of transit Typically ¼ to ½ mile 10
More informationCharlotte-Mecklenburg Region Rapid Transit and Land-Use Integration
Charlotte-Mecklenburg Region Rapid Transit and Land-Use Integration Legislative Committee on Urban Growth and Infrastructure Carolyn Flowers CEO Charlotte Area Transit System March 23, 2010 Charlotte Region
More informationMidtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions
Midtown Corridor Alternatives Analysis Capital Cost Estimation Methodology and Assumptions 1/3/2014 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 Alternatives Overview...
More informationTOWARD SAFE AND RELIABLE ROADWAYS. Jill Ryan, MPH Eagle County Commissioner
TOWARD SAFE AND RELIABLE ROADWAYS Jill Ryan, MPH Eagle County Commissioner Where Does CDOT Money Go? FY2012 (in CDOT millions) Expenditures $1,104,588,163* $684.3 [63%] MAINTAIN What We Have 15% 14% 5%
More informationTransportation Highway Engineering Conference February 24, 2015
Transportation Highway Engineering Conference February 24, 2015 Today s Agenda Move Illinois status Jane Addams Memorial (I-90) Rebuilding and Widening Project Building a 21 st century corridor Incorporating
More informationIMPROVEMENT CONCEPTS
IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic
More informationWAKE TRANSIT PLAN Summer 2018
WAKE TRANSIT PLAN Summer 2018 Planning for growth WAKE COUNTY s population already exceeds ONE MILLION and grows by more than 60 people a day. That s 23,000 people a year or basically another Morrisville.
More informationTrunk Highway 13 Corridor Study Update Existing and No-Build Conditions Technical Memo #2B: Traffic Forecasts and Operations Analysis SEH No.
TECHNICAL MEMORANDUM TO: FROM: Molly McCartney MnDOT Project Manager Haifeng Xiao, PE Tom Sohrweide, PE, PTOE DATE: November 27, 2012 RE: Trunk Highway 13 Corridor Study Update Existing and No-Build Conditions
More informationF:\PROJ\ \dwg\Alt-bridge-alignments.dwg, 17-2, 11/12/ :22:17 PM, saamhu, Acrobat PDFWriter
F:\PROJ\55211014\dwg\Alt-bridge-alignments.dwg, 17-2, 11/12/2002 03:22:17 PM, saamhu, Acrobat PDFWriter MERRIFIELD RIVER CROSSING METHOD OF CHANGE FROM ID# ISSUES MEASUREMENT UNITS VALUE BASE CONDITIONS
More informationRTID Travel Demand Modeling: Assumptions and Method of Analysis
RTID Travel Demand Modeling: Assumptions and Method of Analysis Overall Model and Scenario Assumptions The Puget Sound Regional Council s (PSRC) regional travel demand model was used to forecast travel
More informationIntroduction and Background Study Purpose
Introduction and Background The Brent Spence Bridge on I-71/75 across the Ohio River is arguably the single most important piece of transportation infrastructure the Ohio-Kentucky-Indiana (OKI) region.
More informationState Avenue Corridor Bus Rapid Transit (BRT)
State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!
More informationChapter 7: Travel Demand Analysis. Chapter 8. Plan Scenarios. LaSalle Community Center. Image Credit: Town of LaSalle
Chapter 7: Travel Demand Analysis Chapter 8 Plan Scenarios LaSalle Community Center. Image Credit: Town of LaSalle 164 Chapter 8: Plan Scenarios Moving Ahead for Progress in the 21 st Century Act (MAP
More informationRocky Mount. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation
2020 Transportation Plan Developed by the Transportation Planning Division of the Virginia Department of Transportation in cooperation with the U.S. Department of Transportation, Federal Highway Administration
More informationPopulation Trends. US 71 Corridor Performance
Conex Te corridor rns 121 miles, from Willmar o e Iowa Sae Line. I connecs e ciies of Willmar,, Redwood Falls, Windom and. Crren Caracerisics Hiway: US 2009 AADT: 1,500 11,700 2009 HCADT: 165 1,500 Nmber
More informationSpeed Limit Study: Traffic Engineering Report
Speed Limit Study: Traffic Engineering Report This report documents the engineering and traffic investigation required by Vermont Statutes Annotated Title 23, Chapter 13 1007 for a municipal legislative
More information2016 Congestion Report
2016 Congestion Report Metropolitan Freeway System May 2017 2016 Congestion Report 1 Table of Contents Purpose and Need...3 Introduction...3 Methodology...4 2016 Results...5 Explanation of Percentage Miles
More informationBROWARD BOULEVARD CORRIDOR TRANSIT STUDY
BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,
More informationMass Transit in Charlotte and San Antonio. Keith T. Parker, AICP
Mass Transit in Charlotte and San Antonio Keith T. Parker, AICP President/CEO Presentation Overview Charlotte Agency and Customer Profile San Antonio Agency and Customer Profile Attracting New Customers
More informationFlorida Strategic Highway Safety Planning Florida Strategic Highway Safety Plan (SHSP) Update and Performance Overview
Session 1 Florida Strategic Highway Safety Planning Florida Strategic Highway Safety Plan (SHSP) Update and Performance Overview Joe Santos, PE, FDOT, State Safety Office October, 23, 2013 Florida Statistics
More informationThe Eastern Connector Study November, 2007 planning for the future
The Eastern Connector Study November, 2007 planning for the future In late 2006, Albemarle County and the City of Charlottesville jointly initiated the Eastern Connector Corridor Study. The Project Team
More information4.0 TIER 2 ALTERNATIVES
4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationStreetcar and Light Rail Design Differences. March 2015
Streetcar and Light Rail Design Differences March 2015 How Are Streetcar and Light Rail Different? The design differences between streetcar and light rail are tied to the distinctions in the markets served
More informationUS 81 Bypass of Chickasha Environmental Assessment Public Meeting
US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments
More informationRegional Safety Study
BOONSLICK REGIONAL PLANNING COMMISSION Regional Safety Study PART I: General Crash Data and Trends SPRING 2012 BRPC REGIONAL SAFETY STUDY: PART 1 ~ GENERAL CRASH DATA & TRENDS 1 TABLE OF CONTENTS REPORT
More informationBuilding our future, together. Steering Committee Presentation for the Comprehensive Plan Update April 23, 2013
Building our future, together Steering Committee Presentation for the Comprehensive Plan Update April 23, 2013 Vision In 2030, the City of Tyler will be nationally known for its commitment to community,
More informationSubarea Study. Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project. Final Version 1. Washington County.
Subarea Study Manning Avenue (CSAH 15) Corridor Management and Safety Improvement Project Final Version 1 Washington County June 12, 214 SRF No. 138141 Table of Contents Introduction... 1 Forecast Methodology
More informationWELCOME. Transit Options Amherst - Buffalo Public Workshops
WELCOME Transit Options Amherst - Buffalo Public Workshops Sponsored by Niagara Frontier Transportation Authority Greater Buffalo Niagara Regional Transportation Council Where do you live? Where do you
More informationCTA Blue Line Study Area
1 CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING
More informationOpen House. Highway212. Meetings. Corridor Access Management, Safety & Phasing Plan. 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition
Welcome Meetings 5:30 to 6:30 p.m. - Southwest Corridor Transportation Coalition 6:30 to 8:00 p.m. - Open House Why is Highway 212 Project Important? Important Arterial Route Local Support Highway 212
More informationBalancing the Transportation Needs of a Growing City
Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program
More informationTracking the Blue Line Extension
BROOKLYN PARK CRYSTAL ROBBINSDALE GOLDEN VALLEY MINNEAPOLIS Tracking the Blue Line Extension Issue 4 December 2015 Metropolitan Council approves refined 11-station scope and $1.496 billion cost estimate
More informationRail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005
Rail~Volution 2005 Hal Ryan Johnson, AICP, Bus Rapid Transit Project Manager Utah Transit Authority September 7, 2005 Public Transit District Utah Transit Authority Linear Geographic Area - 130 miles by
More information6.0 TRANSPORTATION EFFECTS
Chapter 6 6.0 TRANSPORTATION EFFECTS This chapter describes the anticipated transportation impacts of the No Build, the Enhanced Bus Alternative, and the Build Alternatives described in Chapter 2. Evaluation
More informationsystem performance I-820 East Loop FM 156 TxDOT is working to expand its busiest metropolitan corridors.
system performance TxDOT is working to expand its busiest metropolitan corridors. Nine of the state s 100 most congested highways are located in Tarrant County. Six of these highways will be expanded and
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationKentucky Highway District 1
Kentucky Highway District 1 ROAD AND BRIDGE CONDITIONS, TRAFFIC SAFETY, TRAVEL TRENDS, AND NEEDS FEBRUARY 2018 PREPARED BY WWW.TRIPNET.ORG Founded in 1971, TRIP of Washington, DC, is a nonprofit organization
More informationCity of Pacific Grove
Regional Study Utilizing Caltrans Intersection Evaluation Section 7: City of Pacific Grove s: FIRST STREET AT CENTRAL AVENUE Transportation Agency for Monterey County Prepared by Transportation Agency
More informationACTION TRANSMITTAL
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: February 12, 2014 TO: FROM: PREPARED BY: SUBJECT: REQUESTED ACTION: RECOMMENDED MOTION: ACTION TRANSMITTAL 2014-14 Transportation
More informationMetropolitan Freeway System 2007 Congestion Report
Metropolitan Freeway System 2007 Congestion Report Minnesota Department of Transportation Office of Traffic, Safety and Operations Freeway Operations Section Regional Transportation Management Center March
More informationARTERIAL BRT OVERVIEW
ARTERIAL BRT OVERVIEW Key Question: Could arterial Bus Rapid Transit (BRT) routes improve near-term mobility in the northwest area until rail can be built? Key Findings: 6 arterial BRT routes have been
More information