Power System Fundamentals

Size: px
Start display at page:

Download "Power System Fundamentals"

Transcription

1 Power System Fundamentals Horace Horton Senior Market Trainer, Market Training, NYISO New York Market Orientation Course (NYMOC) June 5-8, 2018 Rensselaer, NY 12144

2 Session Objectives At the end of this session attendees will be able to Understand the Fundamentals of the New York Control Area (NYCA) Power System Identify the Physical Components of the New York Control Area (NYCA) Power System Explain the Purpose behind Operational Ancillary Services 2

3 Basic Fundamentals. 3

4 NYCA Power System Basic Fundamentals Bulk Power vs. Retail Load Distribution NYCA Zones Neighboring Control Areas Common Terms 4

5 Bulk Power vs. Load Distribution Bulk Power Transmission NYISO is responsible for controlling the transmission of power across the high-voltage transmission network, which is maintained by the Transmission Owners Distribution System Transmission Owners are responsible for distributing power across the lower voltage transmission network to consumers Management of Retail Load Consumption Load Serving Entities buy power at the wholesale level to sell to consumers at the retail level 5

6 Bulk Power vs. Distribution vs. Retail Load GENERATE Diverse Set of Generators Produce Energy ENERGY PRODUCTION AND DELIVERY TRANSFORM Transformers Step-Up Voltage for Transmission TRANSMIT High Voltage Transmission Lines Transmit Power TRANSFORM Transformers Step-Down Voltage for Distribution DISTRIBUTE Local Utility Supplies Power Via Distribution System CUSTOMERS Power Used for Homes, Business, and Industry Step-Up Step-Down Energy Suppliers Bulk Power System - Grid Distribution System Wholesale Energy Market - NYISO Retail - Customers Retail Load 6

7 New York Control Area Load Zones Upstate Zones A - E A B C E F D A B C D E F G H I J K WEST GENESE CENTRL NORTH MHK VL CAPITL HUD VL MILLWD DUNWOD N.Y.C. LONGIL B Downstate Zones F - K J I G H K 7

8 New York Control Area Load Zones A B C D E F G H I J K Marcy WEST GENESE CENTRL NORTH MHK VL CAPITL HUD VL MILLWD DUNWOD N.Y.C. LONGIL 8

9 Neighboring Control Areas IESO HQ D ISO-NE A B E F C B PJM I G H J K 9

10 Basic Fundamentals Common Terms Load (Demand) Total electric power consumed by all users connected to the distribution network of a system, and also the power used to compensate for losses in all parts of the network. Generation Equipment that converts energy sources, e.g. mechanical, solar, etc. into electrical energy for consumption by the load. Transmission Bulk transfer of electrical energy from the generating power plants to electrical substations located near load (demand) centers. 10

11 Basic Fundamentals Common Terms Bus A conductor or group of conductors that serve as a common connection point for two or more electric circuits. Contingency A circumstance that is possible but cannot be predicted with certainty. Constraint A limitation to the system that prevents optimal transfer of power from generation to load. Contingency Circuit Breaker Tripping 11

12 Basic Fundamentals Common Terms Watt Unit of power that measures the rate of energy transfer. Megawatt Equal to 1 million watts. Generation is produced/sustained on this scale. Megawatt-Hour 1 million watts consumed over 1 hour = 1 MWHr ½ million watts over 2 hours = 1 MWHr Voltage The force that moves electricity. 100 Watts 10, W Lightbulbs = 1MW 10, W Lightbulbs energized for 1 hour would consume 1 MWHr 12

13 Basic Fundamentals Common Terms New York Control Area (NYCA) The area in which the NYISO, among other things, balances load and generation, which includes the entire state of New York. Rest of State (ROS) For purposes of the Capacity Market, all areas of the New York control area excluding Load Zones G (Hudson Valley), H (Millwood), I (Dunwoodie), J (NY City), and K (Long Island). Interface Group of transmission lines that define an internal or external boundary. 13

14 Physical Components of the NYCA Power System. 14

15 Physical Components of NYCA Power System Load Generation GENERATION TRANSMISSION Transmission LOAD 15

16 Load Power Consumed off of NYCA Grid GENERATION TRANSMISSION LOAD LOAD 16

17 2017 NYCA Load Profile Seasonal and Hourly Low Points Morning Pickup Peak Summer Peak Fall & Winter 17

18 NYCA Load Profile Historical Record Peak Days 35,000 Record Summer Peak 33,956 MW ,000 25,000 Record Winter Peak 25,738 MW ,000 15, _July_ _Jan_7 10,000 5,

19 NYCA Load by Zone July 19, 2017 Total = 29,664 MWs Zones A I = 14,472 MWs Zones J-K = 15,192 MWs (NYC & LI) IMPORTANT FACT Nearly 51% of electric load was located in NYC & LI B 1,798 MW A 2,435 MW C 2,557 MW E 1,147 MW J 10,240 MW F 2,024 MW G 2,061 MW D 512 MW H 603 MW I 1,335 MW K 4,952 MW 19

20 Let s Review Load NYISO Control Area load profiles reflect which of the following: a. Zone J&K load total nearly equal to the Rest of State total b. Peak usage is always between 1200 and 1400 c. Less load in the summer than winter d. All of the above 20

21 Generation. 21

22 Generation Electrical energy for load consumption GENERATION TRANSMISSION LOAD 22

23 NYS Major Generation MW Values from 2017 Summer Capability ST. LAWRENCE 856 MW Wind Farms 1740 MW Somerset 686 MW NIAGARA MW 9 MILE MW 9 MILE MW FITZPATRICK 838 MW OSWEGO 1639 MW BLENHEIM-GILBOA 1170 MW BETHLEHEM 760 MW GINNA 580 MW = COAL = NUCLEAR = OIL/GAS = HYDRO = PUMP STORAGE = COMBINED CYCLE = WIND FARMS SITHE INDEPENDENCE 949 MW BOWLINE 1125 MW RAVENSWOOD 2190 MW ASTORIA EAST 1126 MW ASTORIA -760 MW ARTHUR KILL MW NYPA ASTORIA 467 MW ATHENS 981 MW ROSETON 1189 MW INDIAN PT MW INDIAN PT MW NORTHPORT 1574 MW 23

24 Capacity vs. Energy Two very different commodities! Capacity measured in MW Refers to the electric power output for which a generating system, plant, or unit is rated Energy measured in MWh Is the amount of energy produced (from capacity) over time 24

25 Generating Capacity vs. Energy New York Statewide Generating Capacity by Fuel Source: 2017 * New York Statewide Energy Production by Fuel Source: 2017 *If Nuclear ran at full capacity for a year: 5375 MW x 24 hrs x 365 days = 47,085 GWh Produced Source: 2017 and 2018 Power Trends Report New York Independent System Operator 25

26 NYCA Load vs. Generation LOAD 7/19/17 HB18 (Top Number) GEN CAPACITY Summer 17 (Bottom Number) A 2,435 MW 3,965 MW B 1,798 MW 768 MW C 2,557 MW 6,636 MW 51% of NYCA load was in Zones J and K (NYC and LI) 62% of NYCA Generation Capacity was in Zones A - I E 1,147 MW 1,037 MW I 1,335 MW 0 MW J 10,240 MW 9,612 MW F 2,024 MW 4,411 MW G 2,061 MW 3,004 MW D 512 MW 1,927 MW A B C D E F G H I J K H 603 MW 2,092 MW WEST GENESE CENTRL NORTH MHK VL CAPITL HUD VL MILLWD DUNWOD N.Y.C. LONGIL K 4952 MW 5,325 MW 26

27 Let s Review Generation Fossil Fuels are used by less than 25% of the Generation Capacity in the NYCA: a. True b. False 27

28 Let s Review Generation Which best describes the Concentration of Generation and Demand in the NYCA: Option Zones A - I Zones J and K (NYC/LI) a. 62% Gen 51% Load b. 70% Load 30% Gen c. 30% Load 70% Gen d. 63% Gen 37% Load 28

29 Transmission. 29

30 Transmission Bulk transfer of electrical energy GENERATION TRANSMISSION LOAD 30

31 NYCA TRANSMISSION OWNERS NEW YORK POWER AUTHORITY Transmission Lines Throughout State ROCHESTER GAS AND ELECTRIC CORPORATION NIAGARA MOHAWK POWER CORPORATION - NATIONAL GRID NEW YORK STATE ELECTRIC AND GAS CORPORATION ORANGE AND ROCKLAND UTILITIES, INC. CONSOLIDATED EDISON CO OF NEW YORK, INC. CENTRAL HUDSON GAS AND ELECTRIC CORPORATION LONG ISLAND POWER AUTHORITY 31

32 NYCA Transmission System 765/500 kv Transmission 32

33 NYCA Transmission System 345 kv Transmission 33

34 NYCA Transmission System 230 kv Transmission 34

35 DC/VFT Transmission Cross Sound DC Cable (ISO-NE) Hudson Transmission Project (PJM) Linden VFT (PJM) Neptune DC Cable (PJM) 35

36 NYCA Transmission System Bulk Transmission Note: There are some 115 and 138 kv facilities considered part of the Bulk Power System 36

37 Transmission Interfaces Definition of Interface A defined set of transmission facilities that separate Load Zones and that separate the NYCA from the adjacent Control Areas Internal Interface Obey transfer limitations across the internal interface to deliver generation to load within NYCA External Interface Obey transfer limitations across the external interface to import or export scheduled power transactions between RTO/ISOs 37

38 Load Zone Interfaces Moses South Multiple transmission lines make up the interface between the load zones Interface limits can create constraints on the flow of power between zones Some interfaces are more impacting on the flow of power A B West Central Dysinger East B C Volney East E Millwood South Dunwoodie South F G D H I J K Total East Central East UPNY SENY UPNY Con Ed Con Ed-LIPA 38

39 New York State Transmission System Internal Interfaces * * Not all NYCA internal interfaces are shown 39

40 Example Interface Definitions * Interface DYSINGER EAST Name of Line/Equipment Line ID Somerset Rochester (Station 80) SR1 39 Niagara Rochester NR2 Lockport N. Akron 108 Lockport Oakfield 112 Lockport Sweden Lockport Shelby 113 Lockport Telegraph 107 Lockport Telegraph 114 Stolle Road High Sheldon 67 Andover Palmiter Interface Central East Name of Line/Equipment Line ID Edic New Scotland 14 Marcy New Scotland 18 Porter Rotterdam 30 Porter Rotterdam 31 East Springfield Inghams Inghams PAR Inghams Bus Tie Plattsburg-Sand Bar PAR R81 PV-20 * As found in the NYISO Operating Study Summer 2017, Appendix E Interface Definitions 40

41 Interface Transfer Limits Transfer limits create constraints on the flow of energy Types of Transfer Limits Thermal Limits Summer and Winter Ratings Voltage Collapse Limits Varies on equipment in-service Stability Limits Varies on lines in-service or load on selected lines Total Transfer Capability = Min(Thermal Limit, Voltage Collapse Limit, Stability Limit) Real time transfer limits vary with system conditions and are posted at the 5 minute level, both positive and negative limits. 41

42 Interface Congestion Congestion creates constraints on the transmission system 42

43 Example of Interface Flows Central East Interface at Limit 43

44 Let s Review Transmission The majority of the bulk power transmission in NYS is at what level? a. 115 kv b. 230 kv c. 345 kv d. 765 kv 44

45 Let s Review Transmission Which definition best describes a transmission interface? a. A piece of equipment that connects a clutch and transmission b. A defined set of transmission facilities that separate zones and that separate the NYCA from adjacent Control Areas c. A standard used for connecting computers d. 765 kv 45

46 Operational Ancillary Services. 46

47 Operational Ancillary Services Purpose Behind Voltage Support Regulation & Frequency Control Operating Reserves Black Start Service 47

48 Voltage Support Voltage Support is needed to: Transfer power from the generation to the load Prevent equipment damage from high voltages Prevent voltage collapse during high load periods Water Pressure Analogy No Pressure No Flow 48

49 Operational Ancillary Services Voltage and Reactive Power VAR = Volt-Amperes Reactive = Reactive Power Reactive Power supports the Voltage that must be controlled within limits for System Reliability Too few VARs, Voltage goes Down Too many VARs, Voltage goes Up Not load but cannot move WATTs without VARs Wheelbarrow analogy Reactive Power lifting the wheelbarrow handles Real power move the load by pushing the wheelbarrow 49

50 Operational Ancillary Services System Voltage Control Voltage Control is a Continuous Process System Voltage Control provided by the Voltage Support Service is an Optional program in which Generators can participate Generator monitors local voltage Must utilize Automatic Voltage Regulator (AVR) Transmission Owners (TO) are responsible for Local Control within their Network 50

51 Non-Generator Voltage Support - Examples Legend: 765 kv 500 kv 345 kv 230 kv 115 kv (Reactive Support) Moses- SC St. Lawrence Dennison Colton Whiteh Blissville Adirondack Cap all Oswego Hoosick Bennington Complex Somerset StatCom Cap Beck Rotterdam Marcy Niagara Sta.80 Pannell Cap Cap Rx New Robinson Rd. Clay Edic Porter Scotland Cap Huntley Cap Lafayette Gilboa Alps Stolle Rd. Richfield Inghams Leeds Gardenville Meyer Springs Cap Cap Cap SVC SVC Dunkirk Andover Palmiter Cap Watercure Fraser Hillside Oakdale Coopers Cap Corners Pleasant Valley Cap Roseton Homer City SC = Synchronous Condenser Rock Buchanan Tavern Cap Millwood SVC = Static VAR Compensator Ramapo Cap Sprainbrook = Shunt Capacitor Bank(s) W49St/Rainey Dunwoodie Rx = Shunt Reactors Shore Rd. Rx Farragut E.Garden City StatCom = Static Compensator (FACTS) Goethals Saunders Cap Massena Rx Chateauguay Willis Plattsburgh Sandbar 51

52 Let s Review Voltage Support A Generator s Voltage Regulators may be used to: a. Decrease power on the system b. Increase loads on the system c. Support voltage on the system d. None of the above 52

53 Operational Ancillary Services Regulation and Frequency Control Areas are Controlled by Functional Entities defined by NERC as Balancing Authorities (BA) The NYISO is a Balancing Authority 53

54 Operational Ancillary Services Control Area Operation Criteria is set forth to instantaneously Balance Load and Generation throughout the Eastern interconnection In order to sustain a 60 Hz Frequency Load Generation 54

55 Operational Ancillary Services System Frequency Changes Load Increases without Generation Increase L F Generation Increases without Load Increase G F 55

56 Operational Ancillary Services Frequency Control 17,000 MW 17,000 MW 60 MPH 56

57 Operational Ancillary Services Frequency Control Effect of Increasing Load 17,000 MW 17,200 MW Hz 17,000 MW MPH 57

58 Operational Ancillary Services Frequency Control Generation needs to be increased to maintain Load-Gen Balance and to maintain frequency at 60 Hz. 17,200 MW 17,200 MW 58

59 Operational Ancillary Services Area Control Error (ACE) ACE is an error signaled created when the Actual Net Interchange and Desired Net Interchange (scheduled) are different 0 The ACE formula also uses the system frequency to ensure the Balancing Authority is contributing to frequency regulation of the interconnection A negative ACE means that the control area is under generating A positive ACE means that the control area is over generating The ACE signal is used to move the regulating units up or down A reserve pick-up may be used to return to schedule if the Area Control Error (ACE) exceeds ( )100 MW 59

60 Operational Ancillary Services Automatic Generation Control (AGC) Compensates for Over or Under Generation NYISO measurements are gathered every 6 Seconds Automatic control provided by Regulating units (Regulation Service) Regulating units are dispatched every 6 Seconds based on ACE 60

61 Operational Ancillary Services System Frequency Impacts Industrial & Commercial Equipment Operating at 60 Hz will be impacted Industrial Motors, Refrigerators, Laundry Machines, Clocks, etc. Generator s Rotational Speed is tied to the Frequency of the System Cascading effect to Generation Load continually increasing, Generation trips off-line 61

62 Let s Review Regulation Regulation Service provides the following: a. Regulates Installed Capacity to ensure Blackouts do not occur b. Regulates System Loads to maintain System Frequency c. Regulates Generation Output to maintain System Frequency d. None of the above 62

63 Operational Ancillary Services NYCA Black Start Service Generators capable of starting without an outside Electric Supply, following a System-Wide blackout 9 Nov July August

64 Black Start - Priorities in Restoration Energizing the backbone transmission path of the NYS Power System. Synchronizing the NYS Power System with the interconnection. Restoring off-site power supplies to nuclear power plants. The next priority shall be load restoration. If there is limited energy available within the NYCA, preference shall be given to generating station startup, followed by the restoration of the high-density load portions of the system. 64

65 Operational Ancillary Services Operating Reserves Backup Generation in the event of a System Contingency NYSRC Total Operating Reserve Requirement: Must Procure to 1.5 x times the Largest Single Contingency (in MW) Largest Single Contingency is 1310 MWs NYISO Procures 2 x Largest Single Contingency 2 x 1310 = 2,620 MWs of Total Reserves each Market Day Regional/Locational Requirements Time/Product Type Requirements 65

66 Operational Ancillary Services Largest Single Contingency Q: What is the largest single generation contingency for this system? A: MW Q: According to NYISO s Reserves scheduling process, how much in Operating Reserves would be scheduled in this example? A: MW 100 MW B 200 MW C 40 MW D off line A 66

67 Example: Small Reserve Pickup New reserve units would need to be selected to maintain Operating Reserves. 301 Lightning strikes the 92 line Substation A Substation B 91 Substation C The reserves being held in NYC & LI would be asked to start generating. 67

68 Let s Review Operating Reserves Identify the NYISO Reserve Requirement for a largest single contingency of 1000 MWs: a. 500 MWs b. 750 MWs c MWs d MWs 68

69 Putting it all Together The following is an Exercise in Maintaining Reliable Operations of a Simplified NYCA Power System It Highlights: The Principles Driving Generation Dispatch Three Factors Affecting Transmission System Limitations The Criteria for a Reliable Operating Scenario The Impact of Contingencies 69

70 Power System Analysis Secure for System Contingencies Forced Generator Outage Forced Line Outage Secure for System Constraints Obey Transmission Limitations Thermal Limitations Voltage Limitations Stability Limitations Obey Generator Limitations Ramp Rates, Upper Operating Limits, Emergency Operating Limits 70

71 Contingency Example Lightning Strikes Sub Station 71

72 Simple Power System Analysis Office Load Generator 2 Max Gen = 500 MW Line D Limit = 400 MW Line A Limit = 175 MW Generator 1 Max Gen = 400 MW Line C Limit = 300 MW Line B Limit = 200 MW Assume No Losses House Load 72

73 Generation Load Balance Office Load = 150 MW Generator 2 Max Gen = 500 MW Gen Output = 0 MW Line D Limit = 400 MW Flow = 50 MW Line A Limit = 175 MW Flow = 100 MW Generator 1 Max Gen = 400 MW Gen Output = 150 MW Assume No Losses Line C Limit = 300 MW Flow = 50 MW Line B Limit = 200 MW Flow = 50 MW House Load = 0 MW Generator 1 More economical to run 73

74 74

75 75

76 76

77 77

78 Let s Review Power System Analysis Which of the following could affect flows on a NYCA interface line: a. Dispatch of a Generator in the Area b. Generator Outage c. Line Forced out of Service d. All of the above 78

79 Summary Power Systems Fundamentals NYISO Responsible for NYCA Bulk Power Operations Three Primary Components to Power System Load, Generation, & Transmission Operational Ancillary Services in place to meet the following System Requirements: Maintaining power transfer capability of the transmission system (Voltage Support) Maintaining balance between Generation and Load (Regulation and Frequency Support) Securing System for Contingencies & Constraints (Reserves) System Restoration (Black Start Service) 79

Power Systems Fundamentals

Power Systems Fundamentals Power Systems Fundamentals Yachi Lin Senior Manager, Transmission Planning New York Independent System Operator Market Overview Course September 20, 2017 Rensselaer, NY 2017 New York Independent System

More information

SUMMARY OF NYISO INTERFACE LIMITS AND OPERATING STUDIES

SUMMARY OF NYISO INTERFACE LIMITS AND OPERATING STUDIES Summary of NYISO Interface Limits and Operating Studies SUMMARY OF NYISO INTERFACE LIMITS AND OPERATING STUDIES Summary of NYISO Interface Limits and Operating Studies SUMMARY OF NYISO INTERFACE LIMITS

More information

EXCEPTIONS TO NYSRC RELIABILITY RULES

EXCEPTIONS TO NYSRC RELIABILITY RULES 1 NYPA Run Back of EXCEPTIONS RELIABILITY RULES REVISION 1 MAY 11, 2010 Post Contingency Flow on Marcy-New Scotland The post-contingency flow on the Marcy-New Scotland 18 line is allowed to exceed its

More information

Hurricane Sandy. Preparations, Response & Recovery. Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012

Hurricane Sandy. Preparations, Response & Recovery. Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012 Hurricane Sandy Preparations, Response & Recovery Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012 Topics Storm Preparation Sequence of Events Infrastructure Status Operations

More information

The New York State Bulk Power Transmission Facilities

The New York State Bulk Power Transmission Facilities 7040 CHATEAUGUAY 765 MASSENA 765 BK 1 MARCY 765 MARCY 345 BK 2 MARCY 765 MARCY 345 MSU1 MASSENA 765 MARCY 765 BK 1 MASSENA 765 MASSENA A 230 BK 2 MASSENA 765 MASSENA B 230 5018 BRANCHBURG 500 RAMAPO 500

More information

EXCEPTIONS TO RELIABILITY RULES REVISION 4 MAY 8, 2015

EXCEPTIONS TO RELIABILITY RULES REVISION 4 MAY 8, 2015 1 NYPA Run Back of EXCEPTIONS RELIABILITY RULES REVISION 4 MAY 8, 2015 Post Contingency Flow on Marcy-New Scotland The post-contingency flow on the Marcy-New Scotland 18 line is allowed to exceed its LTE

More information

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018 1 NYPA Run Back of EXCEPTIONS RELIABILITY RULES Revision 11 February 9, 2018 Post Contingency Flow on Marcy-New Scotland The post-contingency flow on the Marcy-New Scotland 18 line is allowed to exceed

More information

EXCEPTIONS TO RELIABILITY RULES Revision 10 August 11, 2017

EXCEPTIONS TO RELIABILITY RULES Revision 10 August 11, 2017 1 NYPA Run Back of EXCEPTIONS RELIABILITY RULES Revision 10 August 11, 2017 Post Contingency Flow on Marcy-New Scotland The post-contingency flow on the Marcy-New Scotland 18 line is allowed to exceed

More information

2016 Load & Capacity Data Report

2016 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System 2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System A Draft Report by the New York Independent System Operator October 24, 2017 - DRAFT DRAFT PURPOSES ONLY NYISO

More information

2013 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Year 2018) DRAFT REPORT

2013 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Year 2018) DRAFT REPORT 2013 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Year 2018) DRAFT REPORT March 20, 2014 Caution and Disclaimer The contents of these materials are

More information

Ancillary Services. Horace Horton Senior Market Trainer, Market Training, NYISO. New York Market Orientation Course (NYMOC)

Ancillary Services. Horace Horton Senior Market Trainer, Market Training, NYISO. New York Market Orientation Course (NYMOC) Ancillary Services Horace Horton Senior Market Trainer, Market Training, NYISO New York Market Orientation Course (NYMOC) June 5-8, 2018 Rensselaer, NY 12144 1 Ancillary Services SESSION OBJECTIVES: attendees

More information

NYISO: Dynamic Line Rating in Real Time Markets

NYISO: Dynamic Line Rating in Real Time Markets NYISO: Dynamic Line Rating in Real Time Marets Muhammad Marwali Manager - Energy Marets roducts, Maret Structures New Yor Independent System Operator ECC Worshop Bedford Springs, A June 4, 2013 resentation

More information

2014 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Years 2015, 2019, 2024)

2014 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Years 2015, 2019, 2024) 2014 Intermediate Area Transmission Review Of the New York State Bulk Power Transmission System (Study Years 2015, 2019, 2024) DRAFT REPORT February 26, 2015 Caution and Disclaimer The contents of these

More information

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

NYISO OPERATING STUDY WINTER Prepared by Transmission Studies Staff New York Independent System Operator, Inc.

NYISO OPERATING STUDY WINTER Prepared by Transmission Studies Staff New York Independent System Operator, Inc. Prepared by Transmission Studies Staff New York Independent System Operator, Inc. Approved by the NYISO Operating Committee December 18, 2008 Caution and Disclaimer The contents of these materials are

More information

Western NY Public Policy Transmission Report

Western NY Public Policy Transmission Report Western NY Public Policy Transmission Report Dawei Fan Supervisor, Public Policy and Interregional Planning ESPWG/TPAS July 20, 2017, KCC Agenda Public Policy Transmission Planning Process Western NY Public

More information

Ancillary Services. Horace Horton. Market Overview Course. Senior Market Trainer, Market Training, NYISO. March 8, Rensselaer, NY 12144

Ancillary Services. Horace Horton. Market Overview Course. Senior Market Trainer, Market Training, NYISO. March 8, Rensselaer, NY 12144 Ancillary Services Horace Horton Senior Market Trainer, Market Training, NYISO Market Overview Course March 8, 2018 Rensselaer, NY 12144 1 Ancillary Services Objectives At the end of this session attendees

More information

NYISO OPERATING STUDY SUMMER Prepared by Operations Engineering Staff New York Independent System Operator, Inc.

NYISO OPERATING STUDY SUMMER Prepared by Operations Engineering Staff New York Independent System Operator, Inc. Prepared by Operations Engineering Staff New York Independent System Operator, Inc. Approved by NYISO Operating Committee June 20, 2013 Caution and Disclaimer The contents of these materials are for informational

More information

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any Draft Version 1 Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation,

More information

NYISO Operating Study Winter A report from the New York Independent System Operator

NYISO Operating Study Winter A report from the New York Independent System Operator NYISO Operating Study Winter 2016-17 A report from the New York Independent System Operator December 15, 2016 Executive Summary This study is conducted as a seasonal review of the projected thermal transfer

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Monthly Report May 2016

Monthly Report May 2016 Monthly Report May 2016 TABLE OF CONTENTS Operations Performance Metrics Report Market Operation s Report Daily Loads Regulatory Filings May 2016 Operations Performance Metrics Monthly Report May 2016

More information

Monthly Report November 2016

Monthly Report November 2016 Monthly Report November 2016 TABLE OF CONTENTS Operations Performance Metrics Report Market Operation s Report Daily Loads Regulatory Filings November 2016 Operations Performance Metrics Monthly Report

More information

Monthly Report December 2017

Monthly Report December 2017 Monthly Report December 2017 Table of Contents Operations Performance Metrics Report Market Operation s Report Daily Loads Regulatory Filings Operations Performance Metrics Monthly Report December 2017

More information

Western NY Public Policy Transmission Planning Report

Western NY Public Policy Transmission Planning Report Western NY Public Policy Transmission Planning Report Dawei Fan Supervisor, Public Policy and Interregional Planning Business Issues Committee September 12, 2017 Operating Committee September 15, 2017

More information

An Empirical Assessment of the Success of Financial Rights Auctions in PJM and New York

An Empirical Assessment of the Success of Financial Rights Auctions in PJM and New York An Empirical Assessment of the Success of Financial Rights Auctions in PJM and New York Prepared by Susan L. Pope EUCI Electric Power Market Performance Conference September 20, 2001 1 TOPICS Financial

More information

NYISO Operating Study Summer 2018

NYISO Operating Study Summer 2018 NYISO Operating Study Summer 2018 A Report by the New York Independent System Operator June 2018 NYISO Operating Study Summer 2018 1 Table of Contents EXECUTIVE SUMMARY... 4 INTRODUCTION... 5 PURPOSE...

More information

2013 CARIS Phase 1 Report

2013 CARIS Phase 1 Report 2013 CARIS Phase 1 Report Timothy Duffy Manager, Economic Planning New York Independent System Operator Business Issues Committee September 18, 2013 KCC 2013 New York Independent System Operator, Inc.

More information

NYISO Operating Study Summer 2017

NYISO Operating Study Summer 2017 NYISO Operating Study Summer 2017 A Report by the New York Independent System Operator June 2017 Table of Contents EXECUTIVE SUMMARY... 4 INTRODUCTION... 5 PURPOSE... 5 SYSTEM OPERATING LIMIT (SOL) METHODOLOGY...

More information

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Local Transmission Plan. October 11, 2013 Revised August 25, 2014 Local Transmission Plan October 11, 2013 Revised August 25, 2014 2 Central Hudson s System Zone G: Majority of Central Hudson s load Zone E: One small distribution substation Interconnections with Consolidated

More information

2015 Preliminary Weather Normalized MW and 2016 ICAP Forecast (V3)

2015 Preliminary Weather Normalized MW and 2016 ICAP Forecast (V3) 2015 Preliminary Weather Normalized MW and 2016 ICAP Forecast (V3) Arthur Maniaci Supervisor, Load Forecasting & Energy Efficiency New York Independent System Operator Load Forecasting Task Force December

More information

Effects of Smart Grid Technology on the Bulk Power System

Effects of Smart Grid Technology on the Bulk Power System Effects of Smart Grid Technology on the Bulk Power System Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Union College 2013 Environmental Science, Policy & Engineering

More information

ELECTRIC TRANSMISSION 101: Operational Characteristics. Wayne Galli, Ph.D., P.E. Executive Vice President Clean Line Energy Partners LLC

ELECTRIC TRANSMISSION 101: Operational Characteristics. Wayne Galli, Ph.D., P.E. Executive Vice President Clean Line Energy Partners LLC ELECTRIC TRANSMISSION 101: Operational Characteristics Wayne Galli, Ph.D., P.E. Executive Vice President Clean Line Energy Partners LLC Objectives Primary objective is to understand how the power system*

More information

COST ALLOCATION OF NEW INTERCONNECTION FACILITIES TO THE NEW YORK STATE TRANSMISSION SYSTEM

COST ALLOCATION OF NEW INTERCONNECTION FACILITIES TO THE NEW YORK STATE TRANSMISSION SYSTEM New York Independent System Operator COST ALLOCATION OF NEW INTERCONNECTION FACILITIES TO THE NEW YORK STATE TRANSMISSION SYSTEM FOR THE CLASS YEAR 2001 ANNUAL TRANSMISSION BASELINE ASSESSMENT AND ANNUAL

More information

Benefits of Reducing Electric System Losses

Benefits of Reducing Electric System Losses Benefits of Reducing Electric System Losses Dr. Henry Chao Vice President System Resource Planning John Adams Principal Electric System Planner April 9, 2009 Caution and Disclaimer The contents of these

More information

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA Submission of Indicated New York Transmission Owners For Authority to Construct and Operate Electric Transmission Facilities in Multiple Counties in New York Case 13-M-0457 Edic to New Scotland 345 kv

More information

GridView An Analytic Tool for. ABB Inc. Electric Systems Consulting. Market Simulation & Asset Performance Evaluations. ABB Inc.

GridView An Analytic Tool for. ABB Inc. Electric Systems Consulting. Market Simulation & Asset Performance Evaluations. ABB Inc. ABB Inc. Electric Systems Consulting GridView An Analytic Tool for Market Simulation & Asset Performance Evaluations Outline What is GridView about? GridView Capabilities and Functional Highlights Demonstration

More information

Wholesale Electric Market Economics

Wholesale Electric Market Economics Wholesale Electric Market Economics Sponsored by the Institute for Policy Integrity 15 June 2011 Presented by Doug Hurley and Paul Peterson New England Markets and Relative Size All other ancillary services

More information

Overview of ISO New England and the New England Wholesale Power Markets

Overview of ISO New England and the New England Wholesale Power Markets Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England

More information

The Long-Range Transmission Plan

The Long-Range Transmission Plan The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning

More information

National Grid s 2017 Local Transmission Plan

National Grid s 2017 Local Transmission Plan National Grid s 2017 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY 1.0 PURPOSE... 2 2.0 MINIMUM OIL BURNING/AUTOMATIC FUEL SWAPPING CAPABILITY NOTIFICATIONS... 3 3.0 MINIMUM OIL BURNING/AUTOMATIC FUEL SWAPPING CAPABILITY CRITERIA... 5 4.0 MINIMUM OIL BURNING/AUTOMATIC

More information

Essential Reliability Services Engineering the Changing Grid

Essential Reliability Services Engineering the Changing Grid Essential Reliability Services Engineering the Changing Grid Robert W. Cummings Senior Director Engineering and Reliability Initiatives i-pcgrid March 39, 2016 Change is Coming Characteristics and behavior

More information

Dynamic Control of Grid Assets

Dynamic Control of Grid Assets Dynamic Control of Grid Assets Panel on Power Electronics in the Smart Grid Prof Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent Power Infrastructure Consortium School

More information

National Grid s 2018 Local Transmission Plan

National Grid s 2018 Local Transmission Plan National Grid s 2018 Local Transmission Plan Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

2018 Load & Capacity Data Report

2018 Load & Capacity Data Report Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any kind, including without limitation, accuracy, completeness

More information

Key to Status Fields in the Project List

Key to Status Fields in the Project List Key to Fields in the Project List Load Growth Interconnection Economic Reliability Concept Proposed Planned Under Construction In Cancelled N/A Backstop Too early TO Update Base case Increasing load served

More information

Local Transmission Plan. Rev. 1: April 2018

Local Transmission Plan. Rev. 1: April 2018 Local Transmission Plan Rev. 1: April 2018 1 Central Hudson s Service Territory Own & Operate approximately 610 miles of 69 kv, 115 kv & 345 kv transmission lines and three 345 kv substations 2 Central

More information

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS 2/27/2018 ELECTRIC TRANSMISSION PLANNING Table of Contents Table of Contents... 2 Executive

More information

Illinois State Report

Illinois State Report July 2016 Illinois State Report Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast Gas Pipeline Information 2 Executive Summary (July 2016) Existing Capacity:

More information

2019 Preliminary ICAP Forecast

2019 Preliminary ICAP Forecast 2019 Preliminary ICAP Forecast Arthur Maniaci Supervisor, Load Forecasting & Analysis Load Forecasting Task Force December 11, 2018 Rensselaer, NY COPYRIGHT NYISO 2018. ALL RIGHTS RESERVED Consolidated

More information

NYISO Dynamic Disturbance Recorder Location Study

NYISO Dynamic Disturbance Recorder Location Study NYISO Dynamic Disturbance Recrder Lcatin Study A reprt frm the New Yrk Independent System Operatr Date Cautin and Disclaimer The cntents f these materials are fr infrmatin purpses and are prvided as is

More information

Benefits of Electric Power Transmission Ties and Interconnected System Operation

Benefits of Electric Power Transmission Ties and Interconnected System Operation Benefits of Electric Power Transmission Ties and Interconnected System Operation Joint Stakeholder Meeting April 2, 2018 2018 1 Introduction There are many mutual benefits of synchronous transmission ties

More information

New Jersey State Report

New Jersey State Report New Jersey State Report July 2017 Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions

More information

NYISO Market Initiatives

NYISO Market Initiatives NYISO Market Initiatives Robb Pike Director Market Design New York Independent System Operator Ventyx Market Leadership Council Santa Clara, CA April 23, 2012 Topics Roles of the NYISO Smart Grid Integrating

More information

15 Nelson-Marlborough Regional Plan

15 Nelson-Marlborough Regional Plan 15 Nelson-Marlborough Regional Plan 15.1 Regional overview 15.2 Nelson-Marlborough transmission system 15.3 Nelson-Marlborough demand 15.4 Nelson-Marlborough generation 15.5 Nelson-Marlborough significant

More information

Georgia Transmission Corporation Georgia Systems Operations Corporation

Georgia Transmission Corporation Georgia Systems Operations Corporation Georgia Transmission Corporation Georgia Systems Operations Corporation Reactive Power Requirements for Generating Facilities Interconnecting to the Georgia Integrated Transmission System with Georgia

More information

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012 ERCOT Overview Paul Wattles Senior Analyst, Market Design & Development Solar Energy Industries Association History of Electric Reliability Council of Texas, Inc. 1941 Utilities band together to aid war

More information

Dynamic Control of Grid Assets

Dynamic Control of Grid Assets Dynamic Control of Grid Assets ISGT Panel on Power Electronics in the Smart Grid Prof Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent Power Infrastructure Consortium School

More information

Good afternoon Chairman Maziarz and Members of the Senate. Standing Committee on Energy and Telecommunications. We welcome this

Good afternoon Chairman Maziarz and Members of the Senate. Standing Committee on Energy and Telecommunications. We welcome this Welcome and Introductions Good afternoon Chairman Maziarz and Members of the Senate Standing Committee on Energy and Telecommunications. We welcome this opportunity to address the impact that closing the

More information

POWER SYSTEM OPERATION AND CONTROL YAHIA BAGHZOUZ UNIVERSITY OF NEVADA, LAS VEGAS

POWER SYSTEM OPERATION AND CONTROL YAHIA BAGHZOUZ UNIVERSITY OF NEVADA, LAS VEGAS POWER SYSTEM OPERATION AND CONTROL YAHIA BAGHZOUZ UNIVERSITY OF NEVADA, LAS VEGAS OVERVIEW Interconnected systems Generator scheduling/dispatching Load-generation balancing Area Control Error (ACE) Load

More information

Distributed Energy Resources

Distributed Energy Resources Distributed Energy Resources WECC Data Subcommittee Rich Hydzik, Avista (ERSWG/DER Subgroup Lead) June 29, 2018 Why Are We Concerned About DER? Concern about changing generation fleet Large coal fired

More information

Ancillary Services & Essential Reliability Services

Ancillary Services & Essential Reliability Services Ancillary Services & Essential Reliability Services EGR 325 April 19, 2018 1 Basic Products & Ancillary Services Energy consumed by load Capacity to ensure reliability Power quality Other services? o (To

More information

Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc

Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc Con Edison s Infrastructure Delivers Energy To New York City And Westchester 3.3 million electric customers 1.1 million gas customers

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

The Status of Energy Storage Renewable Energy Depends on It. Pedro C. Elizondo Flex Energy Orlando, FL July 21, 2016

The Status of Energy Storage Renewable Energy Depends on It. Pedro C. Elizondo Flex Energy Orlando, FL July 21, 2016 The Status of Energy Storage Renewable Energy Depends on It Pedro C. Elizondo Flex Energy Orlando, FL July 21, 2016 Energy Storage Systems Current operating mode of electrical networks Electricity must

More information

Power Grid & Blackouts. Prof. Ramzy R. Obaid

Power Grid & Blackouts. Prof. Ramzy R. Obaid Power Grid & Blackouts Prof. Ramzy R. Obaid With many thanks and appreciation to Professor Mohamed A. El Sharkawi Power System The electric power systems in the North America and Europe are probably the

More information

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017 Sheffield-Highgate Export Interface SHEI VSPC Quarterly Meeting October 18, 2017 Northern Vermont Export Study Update VELCO is providing information to enable evaluation of potential solutions Incremental

More information

GRID INNOVATION CAUCUS CO-CHAIRS

GRID INNOVATION CAUCUS CO-CHAIRS February 16, 2017 GRID INNOVATION CAUCUS CO-CHAIRS REP. JERRY NCNERNEY (D-CA) REP. BOB LATTA (R-OH) 2 WIRES UNIVERSITY Transmission 101: The Fundamentals Of High Voltage Transmission February 16, 2017

More information

PSNH INTERCONNECTION REQUEST

PSNH INTERCONNECTION REQUEST PSNH INTERCONNECTION REQUEST Send the completed Interconnection Request and required attachments to: Public Service of New Hampshire Attn: Michael Motta, Senior Engineer Supplemental Energy Sources P.

More information

The Role of Electricity Storage on the Grid each location requires different requirements

The Role of Electricity Storage on the Grid each location requires different requirements Functional Requirements for Energy on the Utility Grid EPRI Renewable Council Meeting Bill Steeley Senior Project Manager Dan Rastler Program Manager April 5-6, 2011 The Role of Electricity on the Grid

More information

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid India need regulations for energy storage to implement grid ancillary services

More information

2018 Final ICAP Forecast

2018 Final ICAP Forecast 2018 Final ICAP Forecast Arthur Maniaci Supervisor, Load Forecasting & Energy Efficiency Load Forecasting Task Force December 19, 2017 DRAFT FOR DISCUSSION PURPOSES ONLY COPYRIGHT NYISO 2017. ALL RIGHTS

More information

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross Briefing for the Kansas Legislature March 6, 2013 Paul Suskie & Mike Ross psuskie@spp.org mross@spp.org 501.614.3200 Presentation overview Who we are What we do How we benefit the consumer Industry dynamics

More information

IEEE SESSION COMPUTER AIDED SMART POWER GRID

IEEE SESSION COMPUTER AIDED SMART POWER GRID IEEE SESSION COMPUTER AIDED SMART POWER GRID GEN_1 t.giras@ieee.org GEN_2 LOAD_1 LOAD_2 1 HIGH SMART GRID LEVEL LOW SMART POWER GRID TECHNOLOGY HISTORY MIT NETWORK ANALYZER 1940 ANALOG DISPATCH ACE SCADA

More information

Electric Power Transmission: Research Needs to Sustain a Critical National Infrastructure

Electric Power Transmission: Research Needs to Sustain a Critical National Infrastructure Electric Power Transmission: Research Needs to Sustain a Critical National Infrastructure Robert J. Thomas Cornell University Energy Council s 2003 Federal Energy and Environmental Matters Conference March

More information

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool WIRES University Overview of ISO/RTOs Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool 1 OUR MISSION Helping our members work together to keep the lights on

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Transmission Planning using Production Cost Simulation & Power Flow Analysis

Transmission Planning using Production Cost Simulation & Power Flow Analysis ABB Transmission Planning using Production Cost Simulation & Power Flow Analysis Jinxiang Zhu, Ph.D. Senior Principal, ABB Power Consulting ABB Group January 16, 2018 Slide 1 Power System Studies TECHNICAL

More information

Knickerbocker to Pleasant Valley 345 kv Transmission Line Project (KB-PV)

Knickerbocker to Pleasant Valley 345 kv Transmission Line Project (KB-PV) Knickerbocker to Pleasant Valley 345 kv Transmission Line Project () NYISO Filing Note: This page intentionally left blank KNICKERBOCKER TO PLEASANT VALLEY 345 KV TRANSMISSION LINE PROJECT () TABLE OF

More information

VFT Response to a Breaker Trip and Runback Event

VFT Response to a Breaker Trip and Runback Event 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2014 Grid of the Future Symposium VFT Response to a Breaker Trip and Runback Event P.E. MARKEN GE Digital Energy Indiana,

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER 1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com Hawai'i Electric Light System Overview

More information

NYCA LOLE Violations (Methods D and E )

NYCA LOLE Violations (Methods D and E ) Proposals for Cost Allocation of Regulated Reliability Solutions Associated with NYCA LOLE Violations (Methods D and E ) Presented by Jerry Ancona National Grid For Discussion by NYISO Electric System

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment For NPCC Governmental / Regulatory Affairs Advisory Group May 21 st, 2009 ON IT Executive Summary Engineers from Con

More information

Transmission Congestion Contract Settlements

Transmission Congestion Contract Settlements Transmission Congestion Contract Settlements Gina E. Craan Manager, Market Training New York Independent System Operator Accounting & Billing Workshop October 18 20, 2016 Latham, New York 2016 New York

More information

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID. A GUIDE TO TRANSPOWER 2009 TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID. Contents 01 Introduction 02 System Operator 24/7

More information

Electric Transmission 101 or Everything You Wanted to Know About the Grid But Were Afraid to Ask. Gerald Deaver Manager Regional Transmission Policy

Electric Transmission 101 or Everything You Wanted to Know About the Grid But Were Afraid to Ask. Gerald Deaver Manager Regional Transmission Policy Electric Transmission 101 or Everything You Wanted to Know About the Grid But Were Afraid to Ask Gerald Deaver Manager Regional Transmission Policy Some Xcel Energy Statistics Transmission Business 19,000

More information

Running the Electric Power Grid

Running the Electric Power Grid Running the Electric Power Grid Your electricity needs never stop, and neither do we. We keep power flowing across New England. Inside Our Control Room Before electricity is delivered to your street, it

More information

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation Intentionally left blank F1 Description and Functional Specifications of Proposed

More information

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM 1 1 The Latest in the MIT Future of Studies Recognizing the growing importance of energy issues and MIT s role as an honest broker, MIT faculty have undertaken a series of in-depth multidisciplinary studies.

More information

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK Grid Operations and the Increasing Challenges of Balancing Renewable Energy JANUARY 18 ALBUQUERQUE QUALITY NETWORK JANUARY 18, 2018 AGENDA Overview and History of PNM Grid Operation Challenges Generation

More information

DER101: Distributed Energy Resources basics. May 4, 2017

DER101: Distributed Energy Resources basics. May 4, 2017 DER101: Distributed Energy Resources basics May 4, 2017 Agenda Introduction Definitions Abbreviations Types Why it is important Common Misconceptions DER System Basics References, Codes and Standards Interconnection

More information

SYSTEM OPERATOR. Ancillary Services Technical Requirements for 2018/ /23 REFERENCE NO. :

SYSTEM OPERATOR. Ancillary Services Technical Requirements for 2018/ /23 REFERENCE NO. : SYSTEM OPERATOR REFERENCE NO. : 342-466 PAGE 2 OF 25 TABLE OF CONTENTS 1. INTRODUCTION... 5 2. METHODOLOGY... 5 3. RESERVES... 6 3.1 INTRODUCTION... 6 3.2 INSTANTANEOUS RESERVE... 6 3.2.1 Description...

More information

Electric Transportation and Energy Storage

Electric Transportation and Energy Storage Electric Transportation and Energy Storage Eladio M. Knipping, Ph.D. Senior Technical Manager, Environment April 24, 2009 Fate of U.S. Electricity Production Generation Transmission Distribution Residence/

More information

Demand Response - An End-to-End Approach from Markets to Consumers

Demand Response - An End-to-End Approach from Markets to Consumers Demand Response - An End-to-End Approach from Markets to Consumers Rana Mukerji Senior Vice President Market Structures New York Independent System Operator EPRI PDU Sector Council Meeting Boston, MA September

More information

APPENDIX E: Project Need and Description

APPENDIX E: Project Need and Description APPENDIX E: Project Need and California ISO/MID E-1 Intentionally left blank California ISO/MID E-2 Tyler 60 kv Shunt Capacitor Installation of a 2x10 MVAR capacitor bank at Tyler 60 kv bus Objectives

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems Ben Huckaba, P.E. President & Principal Engineer 317-273-9841 benh@alphaeng.us Indiana University Bloomington,

More information