Ravenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4, Ravenswood Avenue Railroad Crossing Project

Size: px
Start display at page:

Download "Ravenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4, Ravenswood Avenue Railroad Crossing Project"

Transcription

1 Ravenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4,

2 Presentation Outline Project Background Review Current Alternatives City Council Requests Council Direction Requested Next Steps 2

3 Council Feedback Requested Third track location Station configuration Hybrid alternative to move forward 3

4 Station Configuration Existing station platform Proposed platform additional width OCS Pole Height ~ 30 ft Caltrain Station Looking North North of Ravenswood 4

5 Project Background Previous Studies Feasibility Study, 2003 and 2004 Basic assumptions Expand 2 to 4 tracks Study 4 alternative methods At-grade at Atherton & Palo Alto boundaries Evaluate all 4 Menlo Park crossings Options considered Trench alternative elevate roads, lower tracks Overpass alternative elevate roads, tracks remain Underpass alternative lower roads, tracks remain Split alternative lower roads, elevate tracks 5

6 Trench Alternative Issues Requires roadway raising Deep trench, high fences Depressed station platforms High cost Utility relocations High construction impacts 6

7 7

8 Overpass Alternative San Antonio Road, Mountain View Issues Requires 30 ft bridge Overpass length: 1,100 ft Requires raising El Camino Real Major visual impacts Largest footprint 8

9 9

10 Underpass Alternative Jefferson Avenue, Redwood City Issues Retaining walls Limits access to adjacent properties Side street connectivity 10

11 11

12 Split (Hybrid) Alternative Holly Street, San Carlos Issues Long embankments Raised tracks Improved connectivity Reduced impact to adjacent properties 12

13 13

14 Feasibility Study General Findings Trench Alternative Partial trench due to City limits requires difficult road connections Construction required along entire length of tracks Overpass Alternative Largest footprint, major visual impacts Least desirable of all alternatives studied Underpass Alternative Road connection changes Long approaches required to meet elevations Split (Hybrid) Alternative Maintains road connections Requires raised track embankment 14

15 Viaduct Option 2003 study found viaduct option infeasible Constraints - City limits - Crossover tracks - Station area - Caltrain design criteria Hybrid grade separations needed Undesirable by community 15

16 Viaduct Option Atherton Caltrain Station Platform Atherton Channel Viaduct Encinal Ave Glenwood Ave Alternative A Existing Elevation Oak Grove Ave Menlo Park Caltrain Station Platform Ravenswood Ave Alternative B Alternative C Crossover Tracks San Francisquito Creek 16

17 Following Studies Coordination with adjacent cities Caltrain Modernization Updated HSR/Blended System Rail Subcommittee and City Council meetings, Spring 2015 Rail Policy & Position Statement Direction for current study 17

18 Scoping Current Study Project Study Report (PSR) Measure A grant funding Alternatives evaluation Basic assumptions Maintain 2 tracks and allow for possible 3 rd track in future Study 2 alternative types: Underpass and Hybrid At-grade at Atherton & Palo Alto boundaries Prioritize Ravenswood Avenue crossing 18

19 Current Alternatives 19

20 Alternative A 3D Animation East to West See project web page for link to video. 20

21 Alternative A 3D Animation Flyover See project web page for link to video. 21

22 Railroad Profiles Alt C Max Fill = 10 ft Alt B Max Fill = 14 ft 750 ft South of Ravenswood Alt C Max Fill = 10 ft Alt B Max Fill = 17 ft Encinal Ave Alt C Max Fill = 5 ft Glenwood Ave Alt C Max Fill = 10 ft Alt B Max Fill = 6 ft Oak Grove Ave Ravenswood Ave Alternative B Alternative C San Francisquito Creek Alternative A Caltrain Station Platform 22

23 Alternative B Photo Simulation of Ravenswood, Looking East from El Camino 23

24 Alternative B Oak Grove Ave Maximum Excavation = 15 ft Fill at Oak Grove = 6 ft 24

25 Alternative C Photo Simulation of Ravenswood, Looking East from El Camino 25

26 Alternative C Glenwood Ave and Oak Grove Ave Fill at Glenwood = 5 ft Fill at Oak Grove = 10 ft 26

27 Alternatives Comparison Color coded rating system Ratings based on qualitative assessment and quantitative assessment Greatest Improvement Significant Improvement Some Improvement Some Impact Significant Impact Greatest Impact 27

28 Alterna8ves Alternatives Matrix A B C Reduced Potential Rail/Vehicle Conflict East/West Connectivity Improvement Ped/Bike Access Horn Noise Alma St/Ravenswood Ave Connectivity Potential Visual Impacts Property/Driveway Impacts Disruption During Construction Impact Order of Magnitude Cost Traffic Operations 28

29 City Council Requests Legal counsel regarding passing track requirement Assess impacts of third track location Perform direct outreach to Felton Gables and Linfield Oaks residents Construction cost estimates 29

30 City Council Requests Legal counsel regarding passing track requirement Assess impacts of third track location Perform direct outreach to Felton Gables and Linfield Oaks residents Construction cost estimates 30

31 Passing Track Grant requirement Consistent with the Measure A funding requirements, at least one alternative would be developed to allow for the addition of a third passing track through Menlo Park, which is currently an alternative for the Caltrain/HSR blended system. Legal counsel - At least through project study area Caltrain s interpretation - Currently proposed Caltrain/HSR blended system Middle 3 Track option, continuous from San Mateo to south Palo Alto 31

32 Passing Track 32

33 City Council Requests Legal counsel regarding passing track requirement Assess impacts of third track location Perform direct outreach to Felton Gables and Linfield Oaks residents Construction cost estimates 33

34 Third Track Two Potential Locations for a Third Track: - Option 1: In the center of the two main tracks (Outboard platforms at the station) - Option 2: On the outside of the main tracks (Center platform at the station) Opportunities and constraints for each option 34

35 Station Platform & Third Track Options Outboard Platform Third Track in Center 35

36 Station Platform & Third Track Options Center Platform Passing Track on the Outside 36

37 Cross Sections 37

38 Cross Section (North of Encinal Ave) 38

39 Cross Section (North of Encinal Ave) 39

40 Cross Section (North of Glenwood Ave) 40

41 Cross Section (North of Glenwood Ave) 41

42 Cross Section (South of Glenwood Ave) 42

43 Cross Section (South of Glenwood Ave) 43

44 City Council Requests Third Passing Track Questions Legal counsel regarding passing track requirement Assess impacts of third track location Perform direct outreach to Felton Gables and Linfield Oaks residents Construction cost estimates 44

45 City Council Requests Legal counsel regarding passing track requirement Assess impacts of third track location Perform direct outreach to Felton Gables and Linfield Oaks residents Construction cost estimates 45

46 Community Engagement to Date Community Meetings May 2, 2016 October 4, 2016 June 7, 2017 (Upcoming) Commission Meetings Parks & Recreation Commission May 25, 2016 Library Commission June 13, 2016 Transportation Commission November 9, 2016 Bicycle Commission November 14, 2016 Planning Commission December 5, 2016 City Council Meetings February 7, 2017 Rail Public Informational Meeting -March 20,

47 Community Outreach Project web page: City Council Digest s City Newsflash s Social media Flyers and posters Chamber of Commerce Local news media Postcards Electronic sign 47

48 City Council Requests Legal counsel regarding passing track requirement Assess impacts of third track location Perform direct outreach to Felton Gables and Linfield Oaks residents Construction cost estimates 48

49 Preliminary Construction Cost Estimates Alternative Alternative A: Underpass, 1 grade separation Alternative B: Hybrid, 2 grade separations Alternative C: Hybrid, 3 grade separations Preliminary Construction Cost Estimate $ million $ million $ million Planning level estimates For relative cost differential purposes Not yet reviewed by Caltrain engineering staff Will be revised as project moves forward 49

50 Next Steps Community Meeting #3, June 7, Arrillaga Recreation Center Stakeholders meetings, Summer 2017 Commission meetings, Fall 2017 City Council, Fall

51 Council Feedback Requested Third track location Station configuration Hybrid alternative to move forward 51

52 Thank You For More Information: Visit Us at: Us at: 52

SAN FRANCISCO TO SAN JOSE PROJECT SECTION

SAN FRANCISCO TO SAN JOSE PROJECT SECTION SAN FRANCISCO TO SAN JOSE PROJECT SECTION Local Policy Maker Group Thursday, February 23, 2017 San Carlos, California INTRODUCTIONS 1 CALIFORNIA HIGH-SPEED RAIL PROGRAM UPDATE Jeff Morales, CEO HIGH-SPEED

More information

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE

SAN FRANCISCO TO SAN JOSE PROJECT UPDATE SAN FRANCISCO TO SAN JOSE PROJECT UPDATE San Francisco County Transportation Authority Tuesday, April 25, 2017 Ben Tripousis, Northern California Regional Director HIGH-SPEED RAIL: Connecting California

More information

Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae

Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae Dominic Spaethling Regional Program Manager Bethany Williams Public Involvement Manager, HNTB April

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

San Francisco to San Jose Preliminary Alternatives Analysis

San Francisco to San Jose Preliminary Alternatives Analysis San Francisco to San Jose High-Speed Train Project EIR/EIS San Francisco to San Jose Preliminary Alternatives Analysis April 15, 2010 Page 1 Largest Public Transportation Project in U.S. History 800 miles

More information

Community Advisory Committee. October 5, 2015

Community Advisory Committee. October 5, 2015 Community Advisory Committee October 5, 2015 1 Today s Topics Hennepin County Community Works Update Project Ridership Estimates Technical Issue #4:Golden Valley Rd and Plymouth Ave Stations Technical

More information

Caltrain Business Plan

Caltrain Business Plan Caltrain Business Plan FEBRUARY 2019 LPMG February 28, 2019 Caltrain Business Plan Project Update 2 3 What is the Caltrain Business Plan? What Why Addresses the future potential of the railroad over the

More information

Agenda. Open House Presentation Question and Answer Break Out Groups Report Out & Close

Agenda. Open House Presentation Question and Answer Break Out Groups Report Out & Close Agenda Open House Presentation Question and Answer Break Out Groups Report Out & Close Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Sunnyvale Dominic Spaethling

More information

Electric Multiple Unit Procurement Update

Electric Multiple Unit Procurement Update Electric Multiple Unit Procurement Update Public Meetings September 2014 Caltrain Today 2 1 Key Facts Diesel commuter rail system SF to SJ area 77 mile corridor, 32 stations 92 trains / weekday Ridership:

More information

What is the Peninsula Corridor Electrification Project (PCEP)?

What is the Peninsula Corridor Electrification Project (PCEP)? What is the Peninsula Corridor Electrification Project (PCEP)? Project Purpose and Need Improve Train Performance Increase Service and Ridership Increase Revenue and Reduce Cost Reduce Environmental Impacts

More information

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015 Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract

More information

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup

Exhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting

More information

Business Advisory Committee. November 3, 2015

Business Advisory Committee. November 3, 2015 Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal

More information

Mobility Management: Caltrain

Mobility Management: Caltrain Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review

More information

VIADUCT LOCATION STUDY. October 19, 2009

VIADUCT LOCATION STUDY. October 19, 2009 VIADUCT LOCATION STUDY October 19, 2009 Background Information Traffic Study Alternative Evaluation Public Involvement Preferred Concept Next Steps Evaluate alternatives for the location of a viaduct to

More information

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors Transportation Committee November 17, 2016 Agenda Item No. 5, Update on the San Rafael Transit Center Relocation San Rafael Transit Center Relocation Study Update 11/17/16 Golden Gate Bridge, Highway &

More information

Information Meeting Transfer Station Options. September 30, 2014

Information Meeting Transfer Station Options. September 30, 2014 Information Meeting Transfer Station Options September 30, 2014 Outline of Presentation Why we are looking at changes Background on current Transfer Station Options that were considered need, function

More information

CalMod Local Policy Maker Group (LPMG) Agenda

CalMod Local Policy Maker Group (LPMG) Agenda CalMod Local Policy Maker Group (LPMG) Thursday, September 25, 2014 6:00 PM 7:30 PM SamTrans Offices Bacciocco Auditorium 2 nd Floor 1250 San Carlos Ave., San Carlos Agenda 1. JPB Staff Report 2. Information/Discussion

More information

Welcome. Green Line in Your Community

Welcome. Green Line in Your Community Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay

More information

Key Project Elements Status Report

Key Project Elements Status Report Los Angeles County Metropolitan Transportation Authority Key Project Elements Status Report presented to the Corridor Advisory Committee August 18, 2016 Background Motion 22.1 elements are grouped into

More information

Caltrain Business Plan. Project Update July 2018 through January 2019

Caltrain Business Plan. Project Update July 2018 through January 2019 Caltrain Business Plan JANUARY 2019 Project Update July 2018 through January 2019 2 Business Plan Overview Business Plan Overview A Vision for Growth Crafting Scenarios Looking Beyond the Tracks Outreach

More information

Harlem Avenue between 63 rd and 65 th

Harlem Avenue between 63 rd and 65 th Harlem Avenue between 63 rd and 65 th Public Meeting #2 March 13, 2018 Summit Park District Welcome to the second Public Meeting for the preliminary engineering and environmental studies of Illinois 43

More information

Policy Advisory Committee Meeting November 13, 2013

Policy Advisory Committee Meeting November 13, 2013 Midtown Corridor Alternatives ti Analysis Policy Advisory Committee Meeting November 13, 2013 Today s Agenda Introductions Follow up from September meeting Alternatives review Process update Key evaluation

More information

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

SH 249 IN GRIMES COUNTY. Open House April 3, 2014 SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss

More information

FROM: CITY MANAGER DEPARTMENT: PLANNING & COMMUNITY ENVIRONMENT

FROM: CITY MANAGER DEPARTMENT: PLANNING & COMMUNITY ENVIRONMENT TO: HONORABLE CITY COUNCIL FROM: CITY MANAGER DEPARTMENT: PLANNING & COMMUNITY ENVIRONMENT DATE: AUGUST 9, 2004 CMR: 380:04 SUBJECT: ZONING ORDINANCE UPDATE ADOPTION OF A NEW AUTOMOBILE DEALERSHIP (AD)

More information

Downtown Parking/Wayfinding Study. Review of Recommendations to City Council: January 16, 2018

Downtown Parking/Wayfinding Study. Review of Recommendations to City Council: January 16, 2018 Downtown Parking/Wayfinding Study Review of Recommendations to City Council: January 16, 2018 Tonight s Focus Objectives & Timeline Recap Study Findings Present Staff Recommendations 2018 Action items

More information

SAN FRANCISCO TO SAN JOSE PROJECT SECTION. City of Brisbane Baylands Public Hearing June 7, 2017

SAN FRANCISCO TO SAN JOSE PROJECT SECTION. City of Brisbane Baylands Public Hearing June 7, 2017 SAN FRANCISCO TO SAN JOSE PROJECT SECTION City of Brisbane Baylands Public Hearing June 7, 2017 CALIFORNIA HIGH-SPEED RAIL PROGRAM OVERVIEW 2 HIGH-SPEED RAIL: Connecting California 3 HIGH-SPEED RAIL: It

More information

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,

Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present

More information

METRO Light Rail Update

METRO Light Rail Update American Society of Highway Engineers METRO Light Rail Update Brian Buchanan Director, Design and Construction October 13, 2009 1 High Capacity Transit System 2 20-Mile Light Rail Line 3 Operations Operations

More information

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation

More information

Harlem Avenue between 63 rd and 65 th

Harlem Avenue between 63 rd and 65 th Harlem Avenue between 63 rd and 65 th Community Advisory Group Meeting #3 December 1, 2017 Bedford Park Public Library 1 Meeting Agenda 1. Welcome/Introductions (3 mins) 2. Project Overview and Re-Cap

More information

CalMod Local Policy Maker Group (LPMG) Agenda

CalMod Local Policy Maker Group (LPMG) Agenda CalMod Local Policy Maker Group (LPMG) Thursday, March 27, 2014 6:00 PM 7:30 PM SamTrans Offices Bacciocco Auditorium 2 nd Floor 1250 San Carlos Ave., San Carlos Agenda 1. JPB Staff Report 2. Information/Discussion

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

Federal Way Link Extension

Federal Way Link Extension Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate

More information

Rail alignment and benefits (rab) study

Rail alignment and benefits (rab) study Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study May 22, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

City of San Juan Capistrano Agenda Report

City of San Juan Capistrano Agenda Report 12/16/214 82 City of San Juan Capistrano Agenda Report TO: FROM: DATE: SUBJECT: Karen P. Brust, City Manag4(?1-- Keith Van Der Maaten, P.E., Public Works and Utilities Directo Prepared by: George Alvarez,

More information

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West

More information

Peninsula Corridor Electrification Project Cost / Schedule Update

Peninsula Corridor Electrification Project Cost / Schedule Update Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system

More information

February 2012 Caltrain Annual Passenger Counts Key Findings

February 2012 Caltrain Annual Passenger Counts Key Findings February 2012 Caltrain Annual Passenger Counts Key Findings Key Findings February 2012 Caltrain Annual Passenger Counts The 2012 annual Caltrain passenger counts, which were conducted in February 2012,

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

Confederation Line West Alignment Improvement. September 21, 2016

Confederation Line West Alignment Improvement. September 21, 2016 Confederation Line West Alignment Improvement September 21, 2016 Agenda Background Lincoln Fields Station and alignment improvement LRT alignment, west of Lincoln Fields to Queensview, including: Pedestrian

More information

Confederation Line West Queensway Terrace North. May 27, 2017

Confederation Line West Queensway Terrace North. May 27, 2017 Confederation Line West Queensway Terrace North May 27, 2017 Agenda Background Lincoln Fields Station Concept LRT alignment, southwest of Lincoln Fields to Queensway, including: Pedestrian bridge replacement

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

This Evening s Agenda. Open House 7:00 7:30 Presentation 7:30 8:00 Community Feedback8:00 9:00 Adjourn

This Evening s Agenda. Open House 7:00 7:30 Presentation 7:30 8:00 Community Feedback8:00 9:00 Adjourn This Evening s Agenda Open House 7:00 7:30 Presentation 7:30 8:00 Community Feedback8:00 9:00 Adjourn Preliminary Station Footprint Potential Mid-Peninsula High Speed Train Station Palo Alto Dominic Spaethling,

More information

CREATING CONNECTIONS IN THE TOWN OF NEWMARKET

CREATING CONNECTIONS IN THE TOWN OF NEWMARKET CREATING CONNECTIONS IN THE TOWN OF NEWMARKET NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 10, 2017 GRIDLOCK

More information

Electric Multiple Unit Procurement Update

Electric Multiple Unit Procurement Update Electric Multiple Unit Procurement Update Board of Directors August 7, 2014 Context* * The proposed project is not yet approved pending environmental clearance. 2 1 Status April 2014 - JPB update on EMU

More information

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018 NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3

More information

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014 Expo Line Project Westside/Central Metro Service Council November 2014 2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting

More information

Table of Contents. Attachment 1 Caltrain Service History Attachment 2 Tables and Graphs Caltrain Annual Passenger Counts 1 of 12 Final

Table of Contents. Attachment 1 Caltrain Service History Attachment 2 Tables and Graphs Caltrain Annual Passenger Counts 1 of 12 Final February 2013 Caltrain Annual Passenger Counts Key Finding gs Table of Contents Methodology and Background... 2 Recent Service Changes... 2 Weekday Ridership... 2 Stations... 4 Baby Bullet Stations...

More information

Item No. 10 Town of Atherton

Item No. 10 Town of Atherton Item No. 10 Town of Atherton CITY COUNCIL STAFF REPORT REGULAR AGENDA TO: FROM: HONORABLE MAYOR AND CITY COUNCIL GEORGE RODERICKS, CITY MANAGER MICHAEL KASHIWAGI COMMUNITY SERVICES DIRECTOR DATE: DECEMBER

More information

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

Green Line LRT: Beltline Segment Update April 19, 2017

Green Line LRT: Beltline Segment Update April 19, 2017 Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street

More information

Public Information Centre

Public Information Centre Junction Street Wastewater Pumping Station & Forcemain Schedule B Municipal Class Environmental Assessment Study Public Information Centre June 28, 2017. 6:00 to 8:00 pm. The Burlington Performing Arts

More information

Key Findings. February 2009 Caltrain Annual Passenger Counts

Key Findings. February 2009 Caltrain Annual Passenger Counts Key Findings February 2009 Caltrain Annual Passenger Counts The 2009 annual Caltrain passenger counts, which were conducted starting in late-january and were complete by mid-february, followed the same

More information

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Green Line LRT: Beltline Recommendation Frequently Asked Questions Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria

More information

E) That the General Manager be authorized to execute and deliver such documentation on behalf of the Park Board.

E) That the General Manager be authorized to execute and deliver such documentation on behalf of the Park Board. Date: May 30, 2012 TO: Board Members Vancouver Park Board FROM: General Manager Parks and Recreation SUBJECT: Electric Vehicle Charging Stations and Cellular Infrastructure in English Bay Parks RECOMMENDATION

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

The Eastern Connector Study November, 2007 planning for the future

The Eastern Connector Study November, 2007 planning for the future The Eastern Connector Study November, 2007 planning for the future In late 2006, Albemarle County and the City of Charlottesville jointly initiated the Eastern Connector Corridor Study. The Project Team

More information

February 2011 Caltrain Annual Passenger Counts Key Findings

February 2011 Caltrain Annual Passenger Counts Key Findings February 2011 Caltrain Annual Passenger Counts Key Findings Key Findings February 2011 Caltrain Annual Passenger Counts The 2011 annual Caltrain passenger counts, which were conducted in February 2011,

More information

CREATING CONNECTIONS IN EAST GWILLIMBURY

CREATING CONNECTIONS IN EAST GWILLIMBURY CREATING CONNECTIONS IN EAST GWILLIMBURY NICK SPENSIERI, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX APRIL 4, 2017 Page 8 of 146 GRIDLOCK

More information

On June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue.

On June 11, 2012, the Park Board approved the installation of three electric vehicle charging stations along Beach Avenue. January 8, 2017 TO: Park Board Chair and Commissioners FROM: General Manager Vancouver Board of Parks and Recreation SUBJECT: Electric Vehicle Charging Stations New Park Board Locations RECOMMENDATION

More information

CITY COUNCIL STUDY SESSION UPDATE ON SMART. January 19, 2017 CITY OF SAN RAFAEL

CITY COUNCIL STUDY SESSION UPDATE ON SMART. January 19, 2017 CITY OF SAN RAFAEL CITY COUNCIL STUDY SESSION UPDATE ON SMART January 19, 2017 CITY OF SAN RAFAEL SONOMA MARIN AREA RAIL TRANSIT UPDATE OUTLINE BACKGROUND INITIAL OPERATION SYSTEM (IOS1) CIVIC CENTER AREA LARKSPUR EXTENSION

More information

RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION

RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION REFRIGERATION UNITS AND MAINTENANCE SHOPS. CHAPTER FIVE railyards

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q2 Quarterly Update #13 October 1 December 31, 2017 JPB Board Meeting February 1, 2018 Agenda Item # 8b Electrification - Infrastructure Progression of

More information

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 EAST-WEST CORRIDOR Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 Presentation Agenda Project Overview / Purpose and Need Highway Component Transit Component

More information

Rail alignment and benefits (rab) study

Rail alignment and benefits (rab) study Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study June 5, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

Staff Contact: Carlos de Melo, Community Development Director, (650)

Staff Contact: Carlos de Melo, Community Development Director, (650) Meeting Date: April 10, 2018 STAFF REPORT Agency: City of Belmont Staff Contact: Carlos de Melo, Community Development Director, (650) 595-7440 cdemelo@belmont.gov Agenda Title: Agenda Action(s): Caltrain

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

Powering Sydney s Future

Powering Sydney s Future Powering Sydney s Future Frequently Asked Questions December 2017 Project background Q: Why is this project needed? A: Inner Sydney is one of the most critical parts of the NSW electricity network. However,

More information

Metro Green Line to LAX Alternatives Analysis. March 2012

Metro Green Line to LAX Alternatives Analysis. March 2012 Metro Green Line to LAX Alternatives Analysis 1 2 The Crenshaw/LAX Project Foundation for Metro Green Line to LAX 8.5 mile extension Metro Exposition Line (Crenshaw Exposition) to Metro Green Line (Aviation/LAX

More information

Railyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY

Railyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY Railyard Alternatives & I-280 Boulevard Feasibility Study 1 RAILYARD ALTERNATIVES & I-280 BOULEVARD (RAB) FEASIBILITY STUDY RAB Citizen Working Group Meeting, August 1 st 2016 CITIZEN WORKING GROUP (CWG)

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

APPENDIX E: BIBLIOGRAPHY

APPENDIX E: BIBLIOGRAPHY Caltrain Electrification Program EA/EIR APPENDIX E: BIBLIOGRAPHY Technical Reports The following technical reports, listed alphabetically by report title, document the studies conducted for this EA/EIR.

More information

NEW YORK CITY CARSHARE PILOT

NEW YORK CITY CARSHARE PILOT NEW YORK CITY CARSHARE PILOT Community Board Briefing February 2018 1 Concept and Context 1 nyc.gov/dot 2 CHALLENGE OF CONTINUED GROWTH The City must use its streets as efficiently as possible to move

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway

More information

VAN NESS AVENUE BUS RAPID TRANSIT

VAN NESS AVENUE BUS RAPID TRANSIT VAN NESS AVENUE BUS RAPID TRANSIT Commission of the Environment Policy Committee May 22, 2014 Peter Gabancho Project Manager III Capital Programs & Construction SFMTA 1 Conceptual Visual Simulation Center-Running

More information

Rolling Road (Route 638) Widening Project

Rolling Road (Route 638) Widening Project Rolling Road (Route 638) Widening Project From: 0.369 Mile North of Fairfax County Parkway (Route 286) To: Old Keene Mill Road (Route 644) State Project No. 0638-029-156, P104, R204, C504; UPC 5559 Public

More information

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan Utility Undergrounding Strategies & Laguna Canyon Road Master Plan January 17, 2017 City Council Meeting 2 Agenda Progress since March 2016 Status of undergrounding and road widening between El Toro Rd.

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT

CITY OF VANCOUVER ADMINISTRATIVE REPORT CITY OF VANCOUVER A19 ADMINISTRATIVE REPORT Report Date: July 10, 2007 Author: Chris Darwent Phone No.: 604.873.7358 RTS No.: 6866 VanRIMS No.: 13-1400-20 Meeting Date: July 24, 2007 TO: FROM: SUBJECT:

More information

25 th AVENUE GRADE SEPARATION and RAIL REALIGNMENT PROJECT

25 th AVENUE GRADE SEPARATION and RAIL REALIGNMENT PROJECT 25 th AVENUE GRADE SEPARATION and RAIL REALIGNMENT PROJECT Application to the San Mateo County Transportation Authority for funding under the Measure A Grade Separation Program Submitted September 13,

More information

2017 MAX Program. Red & Blue Line Platform Extension. John Rhone Vice President, Capital Design & Construction June 22, 2017

2017 MAX Program. Red & Blue Line Platform Extension. John Rhone Vice President, Capital Design & Construction June 22, 2017 2017 MAX Program Red & Blue Line Platform Extension John Rhone Vice President, Capital Design & Construction June 22, 2017 Project Goals and Objectives Increase capacity: Move more passengers by 2021 with

More information

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010

BART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010 BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and

More information

CROSSING RAIL PROJECT (P4) RAIL

CROSSING RAIL PROJECT (P4) RAIL GRAND CROSSING RAIL PROJECT (P4) Community Advisory Group October 10, 2012 1:30 pm Grand Crossing Park Field House 7655 S. Ingleside Avenue, Chicago GRAND CROSSING RAIL PROJECT (P4) Community Advisory

More information

Mississauga Bus Rapid Transit Preliminary Design Project

Mississauga Bus Rapid Transit Preliminary Design Project Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.

More information

Cotton Belt Corridor. Area Focus Group (AFG) Richardson/Plano April 27, John Hoppie, Capital Planning

Cotton Belt Corridor. Area Focus Group (AFG) Richardson/Plano April 27, John Hoppie, Capital Planning Cotton Belt Corridor Area Focus Group (AFG) Richardson/Plano April 27, 2017 John Hoppie, Capital Planning 0 Agenda Introductions Area Focus Group (AFG) Purpose Project Background Project Scope Richardson/Plano

More information

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council:

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council: Corporate NO: R279 Report COUNCIL DATE: DECEMBER 18, 2006 REGULAR COUNCIL TO: Mayor & Council DATE: December 15, 2006 FROM: General Manager, Engineering FILE: 8710-20 (Heritage) SUBJECT: Update on Community

More information

FY 2017 Proposed Work Session Follow-Up. April 4, 2016

FY 2017 Proposed Work Session Follow-Up. April 4, 2016 Subject: DES Update on Parking Meter Tour FY 2017 Proposed Work Session Follow-Up April 4, 2016 The following information is provided in response to a request made by Mr. Vihstadt via email on March 7,

More information

Tempe Streetcar. March 2, 2016

Tempe Streetcar. March 2, 2016 Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use

More information

Proposed Revised Network Presented 10/17/2017. Kitsap Transit Board Workshop October 17, 2017

Proposed Revised Network Presented 10/17/2017. Kitsap Transit Board Workshop October 17, 2017 Kitsap Transit Board Workshop October 17, 2017 Agenda Revised Route Network: What We Heard Service Options Phase 2 Public Outreach Wrap Up and Next Steps TRANSFORM Comprehensive TRANSIT: Route Let s Analysis

More information

Balancing the Transportation Needs of a Growing City

Balancing the Transportation Needs of a Growing City Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina Public Meeting & Open House July 23, 2013 Project Roadway Limits From: FM 1957 To: FM 471 MAP OR PHOTO Counties Bexar & Medina 1 I. Project History II. III. IV. Project Overview Project Alternatives Response

More information