Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

Size: px
Start display at page:

Download "Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group"

Transcription

1 Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

2 Table of Contents 1. Introduction Purpose Customer Eligibility Obtain Required Documentation from EPE Website New Mexico Customers Texas Customers Application Process New Mexico Renewable Energy Interconnection Process Flow New Mexico Application Process Texas Renewable Energy Interconnection Process Flow Texas Application Process Technical Requirements Sample One-Line Diagram Checklists New Mexico Checklist Texas Checklist EPE Field Inspection System Expansion Expansion Application Process Renewable Energy System Ownership Change Ownership Change Application Process Downloading Required Documentation from EPE Website Appendix A: Sample Forms 11. Appendix B: Simplified Interconnections Terms and Conditions 12. Appendix C: Safety Recommendations (Please make sure Blue Books Standards are followed) 13. Appendix D: Type of Service Voltages 14. Appendix E: Technical Requirements for Interconnections and Parallel Operation of Qualifying Facilities 10 kw or Less

3 1. Introduction El Paso Electric (EPE) is committed to providing its customers with reliable and high quality electric power; as part of this commitment, EPE is supporting and promoting the development of renewable energy projects in its service territory. EPE actively seeks to further develop renewable energy programs and partnerships that will help increase the electric generation from renewable energy projects. Conveniently, the fast development of technology has made the use of natural resources accessible for the production of electrical power at a lower price than it was a decade ago. The EPE Renewable Energy Interconnection program enables EPE s customers that have a renewable system installed at their residence or business to interconnect with EPE s grid. The installation and interconnection of a renewable system to EPE s grid will not only reduce the customer s kwh consumption from EPE, but will also help the environment to be less impacted by electric generation using non-renewable resources. 2. Purpose The purpose of this manual is to provide EPE s customers with the necessary information to successfully complete the Interconnection Packet for a renewable system. This packet must be processed prior to any system interconnection to EPE s grid. This manual includes the required forms and completion guidelines for an accurate inclusion of all pertinent information in the Interconnection packet. Additionally, this manual includes a brief description of the procedure that the Interconnection Application Packet follows in order to be processed by EPE, as well as the roles and responsibilities of the customer and EPE. 3. Customer Eligibility 3.1 Obtain Required Documentation from EPE Website Customers may find all necessary forms and additional information by visiting EPE s website. Please click on the following link to be directed to EPE s website: Note: Section 9 Downloading Required Documents from EPE Website provides additional guidelines for obtaining these documents. 3.2 New Mexico Customers All EPE New Mexico customers are eligible to interconnect their renewable energy system to EPE s grid as long as the EPE established requirements for interconnection are met. The customer is 1 P a g e

4 required to submit an Interconnection Packet to EPE which consists of the following documents that must be accurately completed (Customers may download the forms at the website address listed below): TWO originals of the Simplified Interconnection Application Forms completely and accurately filled out; /Simplified_Interconnection_Application-Form_40.pdf A one-line diagram (please include the side and top view) that includes the location of the meters and the A/C Disconnect and all necessary technical data; Line_Diagram_2011.pdf ONE $50 checks, one for the Simplified Interconnection Applications processing fee (please make checks payable to EPE); ONE original NM Renewable Energy Facility Ownership Status form, completely and accurately filled out wable_energy_facility_ownership_status.pdf ONE W-9 Form accurately filled out and signed by the customer applying for interconnection; and, ONE Form 35 Notice of Self Certification Technical Specifications or Technical Data Sheets. The documents previously mentioned must be included in order to process the Interconnection Packet. The customer may submit the Interconnection Application forms with original electronic signature but please note that no copies will be accepted. Additional and optional documents include: An Authorization Agreement for Direct Deposit Form; Note: Customer applying for interconnection must be one of the EPE s account owner of record. 2 P a g e

5 eement_for_direct_deposits_customers.pdf For more information on the Purchase Power Service Rate, please refer to Rate 16 on EPE s website or follow the link below: For more information on the Small Renewables Energy Certificate Purchase, please refer to Rate 33 on EPE s website or follow the link below: The Interconnection Packet and/or related documentation must be mailed to: 3.3 Texas Customers Renewables Development El Paso Electric (loc. 131) P.O Box 982 El Paso, Texas All EPE Texas customers are eligible to interconnect their renewable energy system to EPE s grid as long as the EPE established requirements for interconnection are met. The customer is required to submit an Interconnection Packet to EPE that consists of the following documents accurately completed: TWO originals of the Interconnection and Parallel Operation of Distributed Generation with the Utility System Applications; ction Parallel_Operation_of_DG_.pdf A one-line diagram (side view and top view too) that includes the location of the meters and the A/C Disconnect and all necessary technical data; and, Line_Diagram_2011.pdf Technical Specifications or Technical Data Sheets. The documents previously mentioned must be included in order to process the Interconnection Packet. Please note that customer may submit the Interconnection Application forms with original electronic signature but no copies will be accepted. ONE W-9 Form accurately filled out and signed by the customer applying for interconnection; 3 P a g e

6 ONE Interconnection Application Fee as Applicable please refer to page one of the Interconnection Application for details; Metering Option Selection Form: nrollment_form.pdf Rate Selection Form for Residential Customers: m_-_residential.pdf or Rate Selection Form for Non-Residential Customers: m_-_non-residential.pdf Additional and optional documents include: ONE original TX Renewable Energy Facility Ownership Status form, completely and accurately filled out; _Energy_Facility_Ownership_Status.TX.pdf ONE Renewable Energy Credit Microgenerator Listing Form Credit_Microgenerator_Listing_Form.pdf REC Management Agreement Required by PUCT Subst Rule q (2) Agreement_Required_by_PUCT_Subst_Rule_25_173_q_2.pdf For more information on the Purchase Power Service Rate, please refer to Rate 48 on EPE s website or follow the link below: Firm_Purchased_Power pdf The Interconnection Packet and/or related documentation must be mailed to: El Paso Electric P.O Box 982 El Paso, Texas Attention: Renewables Development (loc.131) 4 P a g e

7 4. Application Process 4.1 New Mexico Renewable Energy Interconnection Process Flow 5 P a g e

8 4.2 New Mexico Application Process: Step 1: Step 2: Step 3: Step 4: Step 5: Step 6: Step 7: Customer completes Interconnection Packet and mails it to EPE Renewables Development Department. EPE Renewables Development reviews Interconnection Packet for completion and accuracy of forms. EPE Renewables Development initiates the process of the Interconnection application by reviewing the information provided for interconnection (e.g. name, address, account number, technical information, etc.) One-line diagram is submitted for review and technical approval by EPE Meter Test and EPE Engineering Departments. Please refer to Section 5. Technical Requirements for more information. If one-line diagram is not approved, EPE Renewables Development notifies the customer and informs customer of necessary changes. The customer must submit a revised oneline diagram for new review and technical approval. EPE Renewables Development informs the customer of technical review approval. The customer initiates the construction of the renewable energy system. Note: Communication is via by submitting an inquiry through smallrenewables@epelectric.com or by contacting EPE Renewables Development at , ext or ext Upon completion of system construction, the customer obtains the electrical release from the corresponding City/County and requests an EPE field inspection by contacting EPE Renewables Development at smallrenewables@epelectric.com. Please refer to Section 6.3 EPE Field Inspection to review the field inspection request checklist. An EPE Meter Test inspector visits the system site and performs the field inspection. If field inspection is not approved, EPE Renewables Development notifies the customer and 6 P a g e

9 informs necessary changes to be performed. The customer requests a new field inspection upon integration of changes. Step 8: Step 9: EPE Renewables Development informs the customer of field inspection approval and informs EPE internal groups for rate assignment and meter order to be issued. EPE internal groups perform their tasks and the EPE Meter Test inspector installs the new meters. NET and REC meters are installed. Step 10: The renewable energy system goes on-line. Step 11: One executed contract is mailed back to the customer and the other one is filed for EPE records. 7 P a g e

10 4.3 Texas Renewable Energy Interconnection Process Flow 8 P a g e

11 4.4 Texas Application Process: Step 1: Step 2: Step 3: Step 4: Step 5: Step 6: Step 7: Customer completes Interconnection Packet and mails it to EPE Renewables Development Department. EPE Renewables Development reviews Interconnection Packet for completion and accuracy of forms. EPE Renewables Development initiates the process of the Interconnection application by reviewing the information provided for interconnection (e.g. name, address, account number, technical information, etc.) One-line diagram is submitted for review and technical approval by EPE Meter Test and EPE Engineering Departments. Please refer to Section 5. Technical Requirements for more information. If one-line diagram is not approved, EPE Renewables Development notifies the customer and informs of necessary changes. The customer must submit a revised one-line diagram for new review and technical approval. EPE Renewables Development informs the customer of technical review approval. The customer initiates the construction of the renewable energy system. Note: Communication is via by submitting an inquiry to smallrenewables@epelectric.com or by the customer contacting Renewables Development at ext.4465 or ext Upon completion of construction of the system, the customer obtains the electrical release from the corresponding City/County and requests an EPE field inspection by contacting Renewables Development at smallrenewables@epelectric.com. Please refer to Section 6.3 EPE Field Inspection to review the field inspection request checklist. An EPE Meter Test inspector visits the system site and performs the field inspection. If field inspection is not approved, EPE Renewables Development notifies the customer and informs necessary changes to be performed. The customer requests a new field inspection upon integration of changes. 9 P a g e

12 Step 8: Step 9: EPE Renewables Development informs the customer of field inspection approval and informs EPE internal groups for rate assignment and meter order to be issued. EPE internal groups perform their tasks and the EPE Meter Test inspector installs the new meters. NET and REC meters are installed. Step 10: One executed contract is mailed back to the customer and the other one is filed for EPE s records. 10 P a g e

13 5. Technical Requirements The one-line diagram must include the following: Site Plan: The Customer must provide details on equipment capacity, type and location. Information must be clearly identified and marked to avoid confusions and delay in the technical review step. All specifications provided in the sample one-line diagram are reviewed and must be satisfied prior to technical review approval. For more information on the specifications, please follow the sample one-line diagram link provided previously in Section 3.1/3.2/3.3 or visit Appendix A. The one-line diagram must comply with the DSO 1875 standard. Please see Section 5.1 Sample One-Line Diagram. Note: Prior standards will not be accepted by EPE. Inverter information: All inverters must comply with UL1741 and must be equipped with protective devices to prevent connection or parallel operation of the generating equipment unless EPE s service voltage and frequency are within standard operating ranges. The delivery service phase must be clearly specified in the one-line diagram and in the Interconnection Application. Inverter s manufacturer and model, specific power and voltage ratings must be identified. A/C Disconnect information: A visible A/C Disconnect must be installed to allow manual interruption of electrical service from the main service panel. It must be accessible to EPE s Meter Test employees, and must be equipped with protective devices to prevent connection to a de-energized circuit. The location of the A/C Disconnect must be between the REC meter and the main service panel according to the one-line diagram requirements. Breaker information: The one-line diagram must depict the breaker rating. The breaker rating specified on the one line must match the breaker size installed at the premise. Wire Size Wire sizing must be provided for the wires used from the disconnect to the REC Meter and from the REC to the main service. Storage System information (if applicable): If installing a storage system, the one-line must also depict the following: The energy storage type: (e.g. battery) If Battery: Battery Chemistry (e.g. Lead Acid, Li-Ion, NiCa) Max Storage Capacity (kw) Energy Capacity (kwh) Energy Storage System Voltage: (V) 11 P a g e

14 Energy Storage Maximum Discharge Capacity: Rated maximum current at rated voltage (A) Energy Storage Nominal Discharge Capacity: Rated current at rated voltage (A) Specify intended use for mode of operation (Backup power, power quality, other) If installing a separate inverter for the storage system, please provide the following information on the one-line diagram: o Inverter Manufacturer o Inverter Model o Inverter certification o Rated output power (Watts) o Maximum apparent AC output power (VA) o Rated Output Voltage (V) o Inverter Short Circuit Capacity (Amps or per unit), if available o Provide Manufacturer specifications sheet o Provide transfer switch specs 12 P a g e

15 5.1 Sample One-Line Diagram 13 P a g e

16 14 P a g e

17 Examples of existing one-line diagrams/systems: Contractor to attach tag stating Net Metering Site Label for REC Meter Label for Disconnect One-Line Diagram located beside REC Meter 15 P a g e

18 One-Line Diagram located on REC Meter Address Contractor to attach tag stating Net Metering Site NOTE 1: Main Service Disconnect located inside Main Service Panel Voltage Rating 16 P a g e

19 17 P a g e

20 6. Checklists The customer may use these checklists as a tool to verify that the interconnection packet is complete. Note: The checklist does not have to be included in the interconnection packet. Its purpose is for customer reference only. 6.1 New Mexico Checklist Required Forms (New Mexico) Check Two (2) Simplified Interconnection Application Forms (Original Signature Required) One-Line Diagram, Side and Top View Diagrams One (1)- $50 check for Interconnection Application One (1)-NM Renewable Energy Facility Ownership Status form Form 35 Notice of Self Certification W-9 Form Technical Specifications or Technical Data Sheets Authorization Agreement for Direct Deposit Form (optional) 18 P a g e

21 6.2 Texas Checklist Required Forms (Texas) Check Two (2) Interconnection Applications Forms (Original Signature Required) One-Line Diagram, Side and Top View Diagrams Technical Specifications or Technical Data Sheets W-9 Form Metering Option Selection Form Rate Selection Form for Residential or Non-Residential customers One (1)-TX (Optional) Renewable Energy Facility Ownership Status form Renewable Energy Credit Microgenerator Listing Form (Optional) REC Management Agreement Required by PUCT Subst Rule q 2 (Optional) Additional Information: 19 P a g e

22 Customer must sign in the customer section on each page of the interconnection applications that requires it. Please note that electronic signatures are now being accepted. If the system facility is different than the mailing address, the customer must include and indicate the mailing address where EPE should mail the executed application. The customer applying for the interconnection must be the EPE s service account owner or must be included in the application. The EPE account number must pertain to the location where the system is installed. For the system address, the customer must ensure that all paperwork with the City/County matches the address provided for the interconnection point. The customer must clearly specify the system s source type (e.g. solar, wind, etc.) The customer must include information relating to the power, voltage rating, and number of phases in the application spaces where they are required and in the one-line diagram. It is preferable if the kw capacity output of the system to be installed is provided in terms of AC. All information provided must be consistent in all applications. The customer must provide a valid address where applications status notifications will be received. If the application does not have a designated area for this information to be included, please make a note next to the customer s name/contractor. In order to avoid delays in the interconnection application process, the customer should verify that all the requirements described herein have been satisfied. Usage of the checklist provided as a tool in Section 6 is recommended. 20 P a g e

23 6.3 EPE Field Inspection The customer may use these checklists as a tool to verify that the system is ready for an EPE field inspection Residential System Checklist Yes Completed Requirements Notes No Utility Revenue Meter must be within 5 feet from the Main Service Disconnect. Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No No No No No No No No No No REC Meter must also be within 5 feet from the Main Service Disconnect. The Qualifying Facility AC energy source must have a visible, lockable disconnect within 5 feet of Main Service Disconnect. The Qualifying Facility AC Energy Source Disconnect must be placed between the Renewable Energy Meter and Utility Meter. A One-Line Electrical Diagram of the facility must be permanently posted on site next to the REC Meter. The One-Line Diagram must be weather proof (i.e. a placard, or inside a PVC pipe that is no less than 1.5 inch in diameter). Placards must be permanently placed on service indicating this is an Interconnection Site, REC Meter, A/C Disconnect. (3 placards) The system that is built must match the One-Line Diagram that is sent in with the Interconnection Application Package. The voltage that is listed on the One-Line Diagram must match the voltage of the system. Any revisions or additions must be pre-approved before implementation. If existing service is upgraded, changed or modified it must be brought up to current EPE standards and current local and state codes. 21 P a g e

24 6.3.2 Commercial System Checklist Yes Completed Requirements Notes No Utility Revenue Meter must be within 5 feet from the Main Service Disconnect. Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes No No No No No No No No No No The Qualifying Facility AC energy source must have a visible, lockable disconnect within 5 feet of Main Service Disconnect. The Qualifying Facility AC Energy Source Disconnect must be placed between the Renewable Energy Meter and Utility Meter. A One-Line Electrical Diagram of the facility must be permanently posted on site next to the REC Meter. The One-Line Diagram must be weather proof (i.e. a placard, or inside a PVC pipe that is no less than 1.5 inches in diameter). Placards must be permanently placed on service indicating this is an Interconnection Site, REC Meter, A/C Disconnect. (3 placards) The system that is built must match the One-Line Diagram that is sent in with the Interconnection Application Package. The voltage that is listed on the One-Line Diagram must match the voltage of the system. Any revisions or additions must be pre-approved before implementation. If existing service is upgraded, change or modified it must be brought up to current EPE standards and current local and state codes. Utility Revenue Meter must be within 5 feet from the Main Service Disconnect. 22 P a g e

25 7. System Expansion A customer with an existing interconnected renewable energy system that would like to include additional panels and therefore increase the system capacity must follow the system expansion process. Note: When considering expanding an existing system please note that the documentation specified below is only applicable to systems that expand within the limits of small size systems ( 10kW); if the existing system is expanded beyond the 10kW limit, it becomes a medium size system and different guidelines apply (the customer will have to submit a medium size application package to EPE). To increase size of renewable energy system for a total system capacity of less than 10kW, customers must provide the following documentation to EPE prior to the expansion of the system: TWO original Simplified Expansion Applications accurately and completely filled out. The one-line diagram with all the specifications mentioned in this manual and specifying how many panels will be added to the system and the total capacity of the new system. For New Mexico Customers only: a $50 check application processing fee must be attached to the Interconnection Application (Please make check payable to El Paso Electric Co). 7.1 Expansion Application Process Step 1: Step 2: The customer completes the Expansion Interconnection Packet that includes two original Simplified Expansion Applications, the one-line diagram, and a $50 check(nm customers only). The customer mails the Expansion Interconnection Packet to EPE: Step 3: El Paso Electric P.O Box 982 El Paso, Texas Attention: Renewables Development (loc.131) Renewables Development reviews the applications for completeness and accuracy and submits the one-line diagram for technical review to Engineering and Meter Test Departments. If the one-line diagram is rejected, Renewables Development informs the customer of disapproval and informs needed changes for the one-line diagram. The customer submits a revised one-line diagram for new technical revision. Note: Please review Section 5. Technical Requirements for more information on the oneline diagram. 23 P a g e

26 Step 4: Step 5: Renewables Development informs the customer of technical review approval. Renewables Development informs internal EPE groups of system expansion. Step 6: Customer completes construction of expansion and notifies Renewables Development. Step 7: Upon completion of system expansion, the customer requests an EPE field inspection by sending an to Step 8: EPE meter test performs field inspection. Step 9: The system goes on-line. Step 10: EPE mails to the customer the executed interconnection contract. Note: In order to avoid delays in the expansion application process, please take the time to verify all the requirements described herein have been satisfied. 8. Renewable Energy System Ownership Change A customer with an existing interconnected renewable energy system that will like to transfer the system ownership must follow the Renewable Energy system ownership change process. To change the ownership of an existing interconnected renewable energy system, the New Mexico customers must provide the following documentation to EPE: One Renewable Energy Credit (REC) Application accurately and completely filled out; and Note: Please write OWNERSHIP CHANGE on top of the Interconnection Application. One $50 check processing fee must be attached to the Renewable Energy System Ownership Change Application (Please make check payable to EPE). One W9 form accurately filled out and signed by the customer is required. Note: Before submitting the ownership change application, the customer must verify the EPE account for the system location is under the customer s name. To change the ownership of an existing interconnected renewable energy system, the Texas customers must send an notification to smallrenewables@epelectric.com for EPE to update its solar system interconnection records and call our customer service center in Texas at to update name on the electric account. 24 P a g e

27 8.1 Ownership Change Application Process Step1: Step 2: The customer prepares the Ownership Change Interconnection packet that includes one original Renewable Energy Credit Application, W9 form and a $50 check. The customer mails the Ownership Change Interconnection packet to EPE: El Paso Electric P.O Box 982 El Paso, Texas Attention: Renewables Development (loc.131) Step 3: Step 4: Renewables Development reviews the accuracy and completeness of the forms and forwards it to EPE s internal groups. Renewables Development informs EPE internal groups of ownership change. Note: In order to avoid delays in the ownership change application process, please take the time to verify all the requirements described herein have been satisfied. 25 P a g e

28 9. Downloading Required Documentation from EPE Website Customers may find all application forms referred to in this manual by visiting EPE s website. The instructions on how to download all the forms are presented below: 1. Go to the EPE website: 2. Click on the Residential Services tab on the top of the page. 3. Select the appropriate State of service: 4. Click on the Renewable Energy blue tab: 5. Click on the Renewable Energy Interconnection orange tab located on the left column. 26 P a g e

29 6. Select the appropriate link: a. Interconnection of facilities less than 10kW for NM; or, b. Interconnection of facilities less than 20kW for TX. 7. Print and complete the appropriate forms and submit the Interconnection Packet to EPE. 27 P a g e

30 28 P a g e

31 10. Appendix A: Sample Forms for New Mexico Sample Simplified Interconnection Application for New Mexico 29 P a g e

32 Sample Simplified Interconnection Application for New Mexico 30 P a g e

33 Sample New Mexico Renewable Energy Facility Ownership Status 31 P a g e

34 Sample W-9 for New Mexico 32 P a g e

35 Direct Deposit Sample Form for New Mexico 33 P a g e

36 Sample Forms for Texas Sample Interconnection Agreement for Texas 34 P a g e

37 Sample Interconnection Agrement for Texas 35 P a g e

38 Sample Interconnection Agrement for Texas 36 P a g e

39 Sample Interconnection Agrement for Texas 37 P a g e

40 Sample Interconnection Agreement for Texas 38 P a g e

41 Sample Interconnection Agreement for Texas 39 P a g e

42 Sample Interconnection Agreement for Texas 40 P a g e

43 Sample Interconnection Agreement for Texas 41 P a g e

44 Sample Interconnection Agreement for Texas 42 P a g e

45 Sample Interconnection Agreement for Texas 43 P a g e

46 Sample Interconnection Application for Texas 44 P a g e

47 Sample Interconnection Application for Texas 45 P a g e

48 Sample Texas Renewable Energy Facility Owhership Status 46 P a g e

49 11. Appendix B: Simplified Interconnections Terms and Conditions Appendix B 47 P a g e

50 Appendix B 48 P a g e

51 12. Appendix C : Safety Recommendations Appendix C 49 P a g e

52 Appendix C 50 P a g e

53 Appendix C 51 P a g e

54 Appendix C 52 P a g e

55 Appendix C 53 P a g e

56 Appendix C 54 P a g e

57 13. Appendix D: Type of Service Voltages Appendix D 55 P a g e

58 Appendix D 56 P a g e

59 Appendix D 57 P a g e

60 Appendix D 58 P a g e

61 14. Appendix E: Technical Requirements for Interconnections and Parallel Operation of Qualifying Facilities 10 kw or Less Appendix E 59 P a g e

62 Appendix E 60 P a g e

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group

Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Renewable Energy Interconnection Manual for Small Size Systems ( 10kW in NM 20kW in TX) Renewables and Emergent Technologies Group Table of Contents 1. Introduction... 1 2. Purpose... 1 3. Customer Eligibility...

More information

Municipality Generator Interconnection Application Single Meter Application Part I

Municipality Generator Interconnection Application Single Meter Application Part I Municipality Generator Interconnection Application Single Meter Application Part I New Application Revised Application A single customer interconnecting to a single meter at a single premise makes a new

More information

Eligible Renewable Generation (ERG) Application INSTRUCTIONS

Eligible Renewable Generation (ERG) Application INSTRUCTIONS INSTRUCTIONS THIS DOCUMENT CONTAINS: ERG Application INSTRUCTIONS ERG Application INFORMATION ERG Application FORM ERG Application CHECKLIST Please read the INSTRUCTIONS and INFORMATION before completing

More information

Net Metering Service. Customer Information Package

Net Metering Service. Customer Information Package Net Metering Service Customer Information Package March 20, 2017 Net Metering - The means of measuring the difference between the electricity supplied by an electric utility and the electricity generated

More information

NET METERING APPLICATION

NET METERING APPLICATION NET METERING APPLICATION This form must be filled out completely and submitted to the City of Geneva Electric Division before a customer s renewable energy facility can be interconnected with City s distribution

More information

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application

More information

Instructions for Completing Oncor s Interconnection Application For Solar PV Projects

Instructions for Completing Oncor s Interconnection Application For Solar PV Projects Instructions for Completing Oncor s Interconnection Application For Solar PV Projects Program Year 2009 Take a Load Off, Texas SM is provided by Oncor Electric Delivery LLC as part of the company s commitment

More information

RENEWABLE ENERGY PROGRAM Step 1, Section 1 ENROLLMENT FORM FOR LEASED RESIDENTIAL AND SMALL COMMERCIAL PHOTOVOLTAIC AND WIND TURBINE SYSTEMS

RENEWABLE ENERGY PROGRAM Step 1, Section 1 ENROLLMENT FORM FOR LEASED RESIDENTIAL AND SMALL COMMERCIAL PHOTOVOLTAIC AND WIND TURBINE SYSTEMS RENEWABLE ENERGY PROGRAM Step 1, Section 1 ENROLLMENT FORM FOR LEASED RESIDENTIAL AND SMALL COMMERCIAL PHOTOVOLTAIC AND WIND TURBINE SYSTEMS For residential and commercial systems, the combined generation

More information

Duke Energy Carolinas North Carolina Interconnection Request Checklist

Duke Energy Carolinas North Carolina Interconnection Request Checklist Duke Energy Carolinas North Carolina Interconnection Request Checklist The North Carolina Utilities Commission issued North Carolina Interconnection Procedures, Forms, And Agreements For State-Jurisdictional

More information

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program As part of our commitment to support renewable energy, Kissimmee Utility Authority

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS XXV. NET METERING A. Applicability and Availability 1. The terms Net Metering Service, Demand Charge-based Time-of- Use Tariff, Net Metering Customer, Customer, Time-of-Use Customer, Time-of-Use Tier,

More information

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power

40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power 40kW (and under) Solar/Inverter Installations Generation Interconnection Application to Minnesota Power WHO SHOULD FILE THIS APPLICATION: Anyone expressing interest to install generation which will interconnect

More information

THE EMPIRE DISTRICT ELECTRIC COMPANY P.S.C. Mo. No. 5 Sec. 4 1st Revised Sheet No. 23

THE EMPIRE DISTRICT ELECTRIC COMPANY P.S.C. Mo. No. 5 Sec. 4 1st Revised Sheet No. 23 P.S.C. Mo. No. 5 Sec. 4 1st Revised Sheet No. 23 Canceling P.S.C. Mo. No. 5 Sec. 4 Original Sheet No. 23 PURPOSE: The purpose of this Rider SR is to implement the solar rebate established through 393.1030

More information

Application for Interconnection and Net Metering Revision: 1 Revised: November 7, 2017

Application for Interconnection and Net Metering Revision: 1 Revised: November 7, 2017 Net Metering Revision: 1 Revised: November 7, 2017 Net Metering Page 1 of 5 1 Net Metering This Application and Agreement is considered complete when it provides all applicable and correct information

More information

Renewable energy & your co-op Installation procedures & guidelines for Farmers EC members YOU RE IN POWER.

Renewable energy & your co-op Installation procedures & guidelines for Farmers EC members YOU RE IN POWER. DISTRIBUTED GENERATION Renewable energy & your co-op Installation procedures & guidelines for Farmers EC members IPORTANT: Before construction and build of your distributed generation system, read this

More information

Columbia Water & Light Interconnection & Net Metering Agreement Electrical Facility

Columbia Water & Light Interconnection & Net Metering Agreement Electrical Facility Processed Date Columbia Water & Light Interconnection & Net Metering Agreement Electrical Facility Customer s Printed Name Installation Street Address Account Number Please note: Columbia Water & Light

More information

Louisiana Net Metering Service. Customer Information Package

Louisiana Net Metering Service. Customer Information Package Louisiana Net Metering Service Customer Information Package August 1, 2013 Net Metering - The means of measuring the difference between the electricity supplied by an electric utility and the electricity

More information

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities New Ulm Public Utilities Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities INDEX Document Review and History... 2 Definitions... 3 Overview... 3 Application

More information

Oncor Application for Interconnection of Distributed Generation

Oncor Application for Interconnection of Distributed Generation Oncor Application for Interconnection of Distributed Generation Certified Systems (12/7/2017) What is a certified system? A certified system is one that meets the requirements of UL-1741 Utility Interactive

More information

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620 Policy Bulletin No. 25 Net Metering Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620 Interconnection Standards For Residential Net Energy Metering With Electric

More information

HydroGenerations PROGRAM HANDBOOK

HydroGenerations PROGRAM HANDBOOK HydroGenerations PROGRAM HANDBOOK TABLE OF CONTENTS Please ensure you are reading the most recent version of this handbook by visiting the NV Energy website, www.nvenergy.com/hydro. Contents HydroGenerations

More information

NET METER REQUEST FORM

NET METER REQUEST FORM Form No. 3651 02/17 NET METER REQUEST FORM In order to receive a Net Meter, please provide the information requested below, sign and return only this coversheet by mail to the address below. NorthWestern

More information

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Consumer Guidelines for Electric Power Generator Installation and Interconnection Consumer Guidelines for Electric Power Generator Installation and Interconnection Habersham EMC seeks to provide its members and patrons with the best electric service possible, and at the lowest cost

More information

WOLFEBORO MUNICIPAL ELECTRIC DEPARTMENT NET METERING PILOT PROGRAM. Customer-Owned Renewable Energy Generation Resources (25 Kilowatts or Less)

WOLFEBORO MUNICIPAL ELECTRIC DEPARTMENT NET METERING PILOT PROGRAM. Customer-Owned Renewable Energy Generation Resources (25 Kilowatts or Less) WOLFEBORO MUNICIPAL ELECTRIC DEPARTMENT NET METERING PILOT PROGRAM Customer-Owned Renewable Energy Generation Resources (25 Kilowatts or Less) Issued and Effective: April 3, 2008 Agreement Between And

More information

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase PAGE 1 OF 7 USE: Requirements and guidelines for interconnection of single phase customer owned, (DR) Distributed Resource generation source, to NIPSCO s electric system, configured for. LATEST REVISION:

More information

Net Metering & Compensation Seminar

Net Metering & Compensation Seminar Net Metering & Compensation Seminar November 2, 2017 Eversource Energy Hadley, MA Changes Are Here Market Net Metering Credit was introduced: 60% Market equal to 60% of distribution, transition, transmission

More information

Electrical District No. 3 SOLAR Q & A

Electrical District No. 3 SOLAR Q & A D3 Electrical District No. 3 SOLAR Q & A What are some things I should consider before going solar? Leasing verses owning: Know the Pros and Cons of each, as well as the Short-term and Long-Term effects

More information

ELECTRICAL DISTRICT # 2

ELECTRICAL DISTRICT # 2 ELECTRICAL DISTRICT # 2 SOLAR ELECTRICAL APPLICATION AND AGREEMENT INSTRUCTIONS This is the application for residential or commercial solar installations. Complete the form and include a quote and full

More information

Rider : NET METERING SERVICE AND ELECTRICAL SYSTEM INTEGRATION

Rider : NET METERING SERVICE AND ELECTRICAL SYSTEM INTEGRATION SAMPLE ORDINANCE 3/5/2012 Rider : NET METERING SERVICE AND ELECTRICAL SYSTEM INTEGRATION Section 1: Applicable Service Territory Net metering and electrical system interconnection is available on a first-come,

More information

SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board

SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board SOUTH HADLEY ELECTRIC LIGHT DEPARTMENT Net Metering Policy As Amended 03/23/16 By the South Hadley Municipal Light Board Policy Description: In an effort to ensure fair treatment of all of its customers,

More information

Solar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota

Solar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota P a g e 1 Solar*Rewards Community Engineering Frequently Asked Questions For Garden Operators Minnesota The purpose of this document is to provide Garden Operators further documentation of engineering

More information

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _ Application for Operation of & Net Metering for Member-Owned Generation -------------- OWNER/APPLICANT INFORMATION Name: Mailing Address: City: County: State: Zip Code: _ Phone Number: Email Address:.Representative:

More information

MISSOURI SERVICE AREA

MISSOURI SERVICE AREA MO.P.S.C. SCHEDULE NO. 6 4th Revised SHEET NO. 88 CANCELLING MO.P.S.C. SCHEDULE NO. 6 3rd Revised SHEET NO. 88 PURPOSE SOLAR REBATE The purpose of this Rider SR is to implement the solar rebate established

More information

Louisville Gas and Electric Company

Louisville Gas and Electric Company P.S.C. Electric No. 11, Original Sheet No. 57 APPLICABLE In all territory served. AVAILABILITY OF SERVICE Available to any customer-generator who owns and operates a generating facility located on Customer

More information

TILLAMOOK PEOPLE S UTILITY DISTRICT

TILLAMOOK PEOPLE S UTILITY DISTRICT TILLAMOOK PEOPLE S UTILITY DISTRICT DISTRIBUTION INTERCONNECTION PROCEDURE Inverter Based Generators 25 kw and Smaller This document contains the interconnection requirements for inverter based generators,

More information

Solar*Rewards Frequently asked questions system size and customer usage

Solar*Rewards Frequently asked questions system size and customer usage Solar*Rewards 1. Will a PV system work with my home? 2. Am I eligible to participate in the Solar*Rewards program? 3. What size system should I get? 4. Can a customer at a service location apply for the

More information

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

Northeastern Rural Electric Membership Corporation Columbia City, Indiana Page 1 of 5 SCHEDULE ADG - 1 AGGREGATED DISTRIBUTED GENERATION SERVICE I. AVAILABILITY This Aggregated Distributed Generation Schedule is available to any member in good standing of Northeastern REMC (Northeastern),

More information

Contents. Solar Select TM Frequently Asked Questions

Contents. Solar Select TM Frequently Asked Questions Solar Select TM Frequently Asked Questions Contents Program Overview and How Solar Select Works... 1 Participation Requirements... 3 Cost and Payment... 4 Solar Production... 5 Development, Equipment,

More information

JEA Distributed Generation Policy Effective April 1, 2018

JEA Distributed Generation Policy Effective April 1, 2018 Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The

More information

ADOPT INTERCONNECTION AGREEMENT FORMS FOR CUSTOMERS INSTALLING GENERATION EQUIPMENT PURSUANT TO REGULATION 23.

ADOPT INTERCONNECTION AGREEMENT FORMS FOR CUSTOMERS INSTALLING GENERATION EQUIPMENT PURSUANT TO REGULATION 23. TO: Honorable Mayor and City Council THROUGH: Municipal Services Committee (May 10, 2016) FROM: SUBJECT: Water and Power Department ADOPT INTERCONNECTION AGREEMENT FORMS FOR CUSTOMERS INSTALLING GENERATION

More information

To complete the process for a net metering interconnection, please follow the steps below:

To complete the process for a net metering interconnection, please follow the steps below: We appreciate your interest in Pacific Power s net metering program. Before purchasing any net metering equipment, we recommend you review the requirements for interconnecting a net metering system to

More information

Umatilla Electric Cooperative Net Metering Rules

Umatilla Electric Cooperative Net Metering Rules Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through

More information

New Hampshire Electric Cooperative (NHEC) Introduction to Net Metering

New Hampshire Electric Cooperative (NHEC) Introduction to Net Metering New Hampshire Electric Cooperative (NHEC) Introduction to Net Metering NHEC supports the development of member-sited renewable energy generation and storage facilities (referred to herein as an interconnection

More information

To complete the process for a net metering interconnection, please follow the steps below:

To complete the process for a net metering interconnection, please follow the steps below: We appreciate your interest in Rocky Mountain Power s net metering program. Before purchasing any net metering equipment, we recommend you review the requirements for interconnecting a net metering system

More information

KANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No.

KANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. 39 PURPOSE: The purpose of the Solar Subscription Pilot Rider (Program) is to provide a limited number of

More information

INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS

INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS INTERCONNECTION RULES AND REGULATIONS FOR NET ENERGY METERING SYTEMS TABLE OF CONTENTS Purpose and Scope...2 Authority...2 Applicability... 2 Intent.. 2 Maximum Connected Generation Allowed. 2 Definitions.

More information

Net +Plus Connection Code

Net +Plus Connection Code Net +Plus Connection Code LANKA ELECTRICITY COMPANY (PRIVATE) LIMITED 1.0 BACKGROUND The existing Net Metering Concept launched in the year 2010 noticed an exponential growth in the recent year and at

More information

Definitions. Scope. Customer Generation Interconnection Requirements

Definitions. Scope. Customer Generation Interconnection Requirements Updated 02/1 Page 1 Scope The purpose of this document is to describe Idaho Power s requirements for the installation and testing of Customer Generation acilities that are interconnected with Idaho Power

More information

NEW HAMPSHIRE ELECTRIC COOPERATIVE S (NHEC) ABOVE THE CAP NET METERING INTERCONNECTION APPLICATION INFORMATION

NEW HAMPSHIRE ELECTRIC COOPERATIVE S (NHEC) ABOVE THE CAP NET METERING INTERCONNECTION APPLICATION INFORMATION NEW HAMPSHIRE ELECTRIC COOPERATIVE S (NHEC) ABOVE THE CAP NET METERING INTERCONNECTION APPLICATION INFORMATION Dear NHEC Member: Thank you for inquiring about New Hampshire Electric Cooperative s Net Metering

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

City of Banning Electric Utility - Residential Self Generating Facility Program (Photovoltaic Systems <48kW)

City of Banning Electric Utility - Residential Self Generating Facility Program (Photovoltaic Systems <48kW) City of Banning Electric Utility - Residential Self Generating Facility Program (Photovoltaic Systems

More information

Noble County Rural Electric Membership Corporation

Noble County Rural Electric Membership Corporation Albion, Indiana Page 1 of 5 SCHEDULE NB-1 RESIDENTIAL NET BILLING I. AVAILABILITY This Net Billing Rate is available to any residential member in good standing of Noble REMC (Noble) who owns and operates

More information

2018 Solar Installer Training. March 2018

2018 Solar Installer Training. March 2018 2018 Solar Installer Training March 2018 Welcome to the 2018 Solar Installer Training Goal: To provide installers and developers with the information necessary to complete Xcel Energy s solar applications

More information

REVISED 8/1/2018 SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & WGC INTERCONNECTION AGREEMENT

REVISED 8/1/2018 SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & WGC INTERCONNECTION AGREEMENT REVISED 8/1/2018 SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & WGC INTERCONNECTION AGREEMENT INTRODUCTION Lathrop Irrigation District has created a policy to allow safe connection

More information

2012 INSTALLERS MEETING UES INSTALLER S MEETING

2012 INSTALLERS MEETING UES INSTALLER S MEETING 2012 INSTALLERS MEETING UES INSTALLER S MEETING Agenda Welcome & Introductions 2011 Overview Policies and Procedures 2012 Program Overview Program Incentives Questions & Answers UES Conservation and Renewable

More information

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING Third Revised Sheet 55a Cancels Second Revised Sheet 55a A. ELIGIBLE CUSTOMER-GENERATOR RULE NO. 17 NET ENERGY METERING Net energy metering is available to eligible customer-generators, defined as, permanent

More information

CHOCTAWHATCHEE ELECTRIC COOPERATIVE, INC RESIDENTIAL SERVICE--NET METERING RIDER

CHOCTAWHATCHEE ELECTRIC COOPERATIVE, INC RESIDENTIAL SERVICE--NET METERING RIDER RS-N SECOND REVISED SHEET NO. 8.2.1 CANCELLING FIRST SHEET NO. 8.2.1 NAME OF UTILITY CHOCTAWHATCHEE ELECTRIC COOPERATIVE, INC RESIDENTIAL SERVICE--NET METERING RIDER DEFINITION Net Metering means calculating

More information

SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & INTERCONNECTION AGREEMENT

SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & INTERCONNECTION AGREEMENT SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & INTERCONNECTION AGREEMENT INTERCONNECTION AGREEMENT FOR SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION THIS AGREEMENT MUST ACCOMPANY

More information

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM Sheet 1 FITCHBURG GAS AND ELECTRIC LIGHT COMPANY SCHEDULE NM Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services

More information

THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY

THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY THE CONNECTICUT LIGHT AND POWER COMPANY dba EVERSOURCE ENERGY AND THE UNITED ILLUMINATING COMPANY Virtual Net Metering Application Effective November 18, 2016 This application form addresses virtual net

More information

Bulletin Interconnection of electric power production sources Rules 2-010, , , , , , and

Bulletin Interconnection of electric power production sources Rules 2-010, , , , , , and Bulletin 84-1-11 Interconnection of electric power production sources Rules 2-010, 64-078, 64-110, 84-004, 84-008, 84-018, 84-022 and 84-030 Scope Issued May 2018 Supersedes Bulletin 84-1-10 1) Requirements

More information

2018 Solar Home & Solar Share Home Program Manual

2018 Solar Home & Solar Share Home Program Manual 2018 2018 Solar Home & Solar Share Home Program Manual Version 02022018 This Program Manual is intended to serve as a reference for Santee Cooper s residential Customers that are interested in learning

More information

Guidelines for Inverter-Based Micro-Generating Facility (10 kw and Smaller)

Guidelines for Inverter-Based Micro-Generating Facility (10 kw and Smaller) Guidelines for Inverter-Based Micro-Generating Facility (10 kw and Smaller) Cover: Photos courtesy of Balance Solutions for Today Inc OVERVIEW Today many home, farm and small business owners are considering

More information

New Hampshire Electric Cooperative s (NHEC) Above the Cap Interconnection (Net Metering) Application Instructions

New Hampshire Electric Cooperative s (NHEC) Above the Cap Interconnection (Net Metering) Application Instructions Dear NHEC Member: New Hampshire Electric Cooperative s (NHEC) Above the Cap Interconnection (Net Metering) Application Instructions Thank you for inquiring about New Hampshire Electric Cooperative s Interconnection

More information

Lassen MUD PV BUYDOWN PROGRAM Photovoltaic Systems Guidelines

Lassen MUD PV BUYDOWN PROGRAM Photovoltaic Systems Guidelines Lassen MUD PV BUYDOWN PROGRAM Photovoltaic Systems Guidelines Lassen Municipal Utility District (LMUD) is committed to promoting and supporting renewable technologies and is offering its customers rebates

More information

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES Last Revised Date: October 15, 2015 Contents Chapter 1 - Purpose and Scope 2 Chapter 2 - Application of Rules 2 Chapter 3 - Definitions

More information

3. Customer shall provide space for metering equipment and meter base as per Springville City Power requirements.

3. Customer shall provide space for metering equipment and meter base as per Springville City Power requirements. A. General This Customer-Owned Generation Standards for Customer-Owned Grid Connected Electric Generating Systems sets forth the requirements and conditions for interconnected non-utility-owned electric

More information

London Hydro Connection Checklist

London Hydro Connection Checklist London Hydro Connection Checklist Applicants should be aware not to incur expenses prior to London Hydro approving the connection of the facility to the grid. Payment of Connection Fee: $1000 plus HST

More information

December 13, This document was filed with the Board of Public Utilities on December 13, It is awaiting final approval by BPU staff.

December 13, This document was filed with the Board of Public Utilities on December 13, It is awaiting final approval by BPU staff. JERSEY CENTRAL POWER & LIGHT UNIFORM TECHNICAL AND PROCEDURAL INTERCONNECTION REQUIREMENTS FOR NET METERING FACILITIES FOR INVERTER BASED WIND AND PHOTOVOLTAIC SYSTEMS OF 100 kw OR SMALLER for Atlantic

More information

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Outlined below are the engineering documents and their associated minimum detail requirements for a Distributed Energy Resource (DER)

More information

MENARD ELECTRIC COOPERATIVE POLICY MANUAL. SECTION IV Operating Rules for Cooperative Members

MENARD ELECTRIC COOPERATIVE POLICY MANUAL. SECTION IV Operating Rules for Cooperative Members 49.1 INTERCONNECTION OF AND SERVICE TO QUALIFYING FACILITIES UNDER Objective To provide for the interconnection of and service to a Qualifying Facility in keeping with the provisions of the Public Utility

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

32 IAEI NEWS March. April

32 IAEI NEWS March. April 32 IAEI NEWS March. April 2013 www.iaei.org PV Perspectives by John Wiles perspectives on pv Batteries in PV Systems Electrical power outages are becoming more common in recent times with man-made and

More information

EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 26A

EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 26A EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 26A SUBJECT: Interconnection of and Service to Qualifying Facilities under Public Utility Regulatory Policies Act (PURPA) OBJECTIVE: To provide, through

More information

ENGINEERING SPECIFICATION

ENGINEERING SPECIFICATION December 206 ENGINEERING SPECIFICATION No. of 6 DATE: 2-9-6 CATEGORY SUBJECT TABLE OF CONTENTS. Overview... 2 2. General Requirements for Service... 3 3. Definitions... 3 4. Abbreviations... 5 5. References

More information

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1. Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.3, 5/16/18 1.0 Scope This document is currently limited in scope to inverter interfaced PV installations

More information

RULES ENABLING THE NET- METERING PROGRAM FOR RENEWABLE ENERGY

RULES ENABLING THE NET- METERING PROGRAM FOR RENEWABLE ENERGY RULES ENABLING THE NET- METERING PROGRAM FOR RENEWABLE ENERGY Outline 1. Introduction 2. Legal Basis 3. Scope, Applicability & Qualification 4. Interconnection Set-Up 5. Pricing Methodology 6. Net-Metering

More information

White River Electric Association, Inc. Net Metering Information & Service Requirements

White River Electric Association, Inc. Net Metering Information & Service Requirements White River Electric Association, Inc. Net Metering Information & Service Requirements What is Net Metering? Net Metering is an electric policy and service for consumers who own and utilize renewable energy

More information

Document Requirements for Engineering Review PV Systems v1.0 6/9/2017

Document Requirements for Engineering Review PV Systems v1.0 6/9/2017 Document Requirements for Engineering Review PV Systems v1.0 6/9/2017 Outlined below are the documents and associated minimum details required for Engineering Review of Distributed Energy Resources Interconnection

More information

Your Friendly and Caring Member Cooperative. Consumer Guidelines for Electric Power Generator Installation and Interconnection

Your Friendly and Caring Member Cooperative. Consumer Guidelines for Electric Power Generator Installation and Interconnection Your Friendly and Caring Member Cooperative Consumer Guidelines for Electric Power Generator Installation and Interconnection Your electric cooperative seeks to provide its members and patrons with the

More information

RIDER NM NET METERING

RIDER NM NET METERING d/b/a Ameren Illinois 5 th Revised Sheet No. 24 Electric Service Schedule Ill. C. C. No. 1 (Canceling 4 th Revised Sheet No. 24) PURPOSE * The purpose of this tariff is to establish an offering of net

More information

REVISION NO.: 7 EFFECTIVE: 07/07/16

REVISION NO.: 7 EFFECTIVE: 07/07/16 SOLAR PROGRAM INTERCONNECTION PROCESS OVERVIEW FOR RESIDENTIAL AND SMALL GENERAL SERVICE REVISION NO.: 7 EFFECTIVE: 07/07/16 Required Steps for ED3 s Solar Program Interconnection Process for Residential

More information

REBATE APPLICATION. 1. Rebate Applicant Information. 2. Dealer Information OKLAHOMA NATURAL GAS COMPRESSED NATURAL GAS (CNG)

REBATE APPLICATION. 1. Rebate Applicant Information. 2. Dealer Information OKLAHOMA NATURAL GAS COMPRESSED NATURAL GAS (CNG) OKLAHOMA NATURAL GAS COMPRESSED NATURAL GAS (CNG) REBATE APPLICATION 1. Rebate Applicant Information Application is required for each requested rebate: Applicant Name: (as it appears on account, if Oklahoma

More information

Application for Service Residential Subdivision / Development

Application for Service Residential Subdivision / Development Application for Service Residential Subdivision / Development Please complete this application and submit the completed form and attachments to PG&E Application for Service at P.O. Box 24047 Fresno CA

More information

NYS Commercial Solar Interconnection Workshop & Roundtable. Thomas V. Higgins Lead Technical Support Consultant - 9/29/2016

NYS Commercial Solar Interconnection Workshop & Roundtable. Thomas V. Higgins Lead Technical Support Consultant - 9/29/2016 NYS Commercial Solar Interconnection Workshop & Roundtable Thomas V. Higgins Lead Technical Support Consultant - 9/29/2016 NYSIR what is it? The NYSIR is the New York State Standardized Interconnection

More information

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System This document is intended to be a general overview of PG&E s current technical

More information

REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDING 50 kw

REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDING 50 kw REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDG 50 kw FOREWARD Requirements for Parallel Operations for Customers with Generation Not Exceeding 50 kw is intended to be used

More information

WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM

WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM A. Application. The following tariff shall apply to members who: (1) take service under a rate within this electric service

More information

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5 Columbia City, Indiana Page 1 of 5 SCHEDULE DG-2 LARGE POWER DISTRIBUTED GENERATION I. AVAILABILITY This Distributed Generation Rate is available to any member in good standing of Northeastern REMC (Northeastern)

More information

Montana-Dakota Utilities Co. A Division of MDU Resources Group, Inc. 400 N 4 th Street Bismarck, ND 58501

Montana-Dakota Utilities Co. A Division of MDU Resources Group, Inc. 400 N 4 th Street Bismarck, ND 58501 Original Sheet No. 72 Page 1 of 7 AVAILABILITY: Available to any customer that owns and operates a solar, wind or hydroelectric generating facility with a capacity of not more than 25 Kw that is located

More information

Michigan Renewable Energy Case Study

Michigan Renewable Energy Case Study Michigan Renewable Energy Case Study NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION TBILISI, GEORGIA JANUARY 27-31, 2014 GREG R. WHITE, COMMISSIONER

More information

Interconnection Process Simplification Webinar

Interconnection Process Simplification Webinar Please stay tuned for the 1 Interconnection Process Simplification Webinar We will be starting momentarily last updated 3.4.13 2 Agenda Overview of PG&E s NEM Program What you need to know about NEM interconnections

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System Adopted Based on State and Tariff Interconnection Rules Applicable to Northern States Power,

More information

Solar Net Metering and Billing FAQ

Solar Net Metering and Billing FAQ Information Title Solar Net Metering Sheet and Billing FAQ If you ve recently had your solar meters installed or purchased a home with existing solar, you likely have questions. We want to help so we ve

More information

WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM

WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM WASHINGTON ELECTRIC COOPERATIVE, INC. NET METERING TARIFF POLICY BULLETIN NO. 38 NM A. Application. The following tariff shall apply to members who: (1) take service under a rate within this electric service

More information

5. NOTE: ALL VENDORS PAID IN FULL BY 12/30/18 WILL BE INCLUDED ON THE VENDORS LIST AT OUR GUEST SERVICES BOOTHS LOCATED THROUGHOUT THE FAIRGROUNDS.

5. NOTE: ALL VENDORS PAID IN FULL BY 12/30/18 WILL BE INCLUDED ON THE VENDORS LIST AT OUR GUEST SERVICES BOOTHS LOCATED THROUGHOUT THE FAIRGROUNDS. FLORIDA STATE FAIR - FEBRUARY 7-18, 2019 OUTDOOR SPACE COMMERCIAL EXHIBITORS APPLICATION MUST BE RETURNED BY AUGUST 31, 2018 Please return application to Jody Holcomb P.O. Box 11766, Tampa, Florida, 33680

More information

STATE CORPORATION COMMISSION DIVISION OF PUBLIC UTILITY REGULATION. May 22, 2018

STATE CORPORATION COMMISSION DIVISION OF PUBLIC UTILITY REGULATION. May 22, 2018 William F. Stephens Director (804) 371-9611 FAX (804)371-9350 PO Box 1197 Richmond, Virginia 23218-1197 DIVISION OF May 22, 2018 Mr. Eric M. Page Ecker Seamans Cherin & Mellott, LLC 919 East Main Street

More information

Electric Vehicle Charging Station Incentives PROGRAM HANDBOOK

Electric Vehicle Charging Station Incentives PROGRAM HANDBOOK Electric Vehicle Charging Station Incentives PROGRAM HANDBOOK 1 1 TABLE OF CONTENTS Please ensure you are reading the most recent version of this handbook by visiting the NV Energy website https://www.nvenergy.com/cleanenergy/electric-vehicles

More information

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources

City of, Kansas Electric Department. Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources Ordinance No. Exhibit A ----------------------------------------- City of, Kansas Electric Department Net Metering Policy & Procedures for Customer-Owned Renewable Energy Resources -------------------------------------

More information