Decision. On 30 July 2015 the National Energy Regulator of South Africa ( NERSA or the Energy Regulator ) decided as follows:

Size: px
Start display at page:

Download "Decision. On 30 July 2015 the National Energy Regulator of South Africa ( NERSA or the Energy Regulator ) decided as follows:"

Transcription

1 NATIONAL ENERGY REGULATOR OF SOUTH AFRICA Decision On 30 July 2015 the National Energy Regulator of South Africa ( NERSA or the Energy Regulator ) decided as follows: 1. that the piped-gas multi-year transmission tariffs for Sasol Gas (Pty) Ltd are as follows: Table 1: Sasol Gas multi-year transmission tariffs for the period 01 July 2015 to June 2017 Zone 1 July '15-30 June '16 1 July '16-30 June '17 1 Gauteng R6.00/GJ R6.01/GJ 2 Secunda - Middleburg R19.16/GJ R19.43/GJ 3 KwaZulu Natal R6.09/GJ R6.25/GJ 2. that the approved tariff is a maximum tariff exclusive of VAT; 3. that discounts are allowed and must be applied in accordance with the nondiscrimination provisions of section 22 of the Gas Act, 2001 (Act No 48 of 2001); and 4. that the tariffs are applicable for the period from 01 July 2015 to 30 June 2017, but will remain in force until the date the Energy Regulator approves another tariff. The applicant is directed to submit a tariff application four months prior to commencement of that tariff period. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 1

2 Reasons for Decision Contents Decision... 1 Reasons for Decision Applicable law Introduction Sasol Gas Transmission Tariff Application Nersa Assessment Elements Of Allowable Revenue... 8 a. Regulatory Asset Base (RAB)... 9 b. Depreciation (d) and Amortization c. Net working Capital (w) d. Tax (T) e. Expenses (E) f. Decommissioning Provision g. Weighted Average Cost of Capital (WACC) h. Claw-back Transmission Tariff Zones Analysis Of Comments Received...Error! Bookmark not defined. 8. Conclusion Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 2

3 Reasons for Decision 1. APPLICABLE LAW 1.1 The legal basis for the National Energy Regulator of South Africa ( NERSA or the Energy Regulator ) to regulate tariffs of piped-gas is derived from the National Energy Regulator Act, 2004 (Act No. 40 of 2004) ( the National Energy Regulator Act ), read with the Gas Act, 2001 (Act No. 48 of 2001) ( the Gas Act ). 2. INTRODUCTION 2.1 Section 4(h) of the Gas Act provides that the Energy Regulator must monitor and approve and, if necessary, regulate transmission and storage tariffs. In practice, this is interpreted as follows: In monitoring and approval, NERSA will not set tariffs but will review tariffs prepared by licensees or applicants for transmission and storage facilities; NERSA can request licensees or applicants to amend the levels of tariffs or tariff structure or both; and NERSA can approve or decide not to approve a tariff. 2.2 If NERSA decides not to approve the proposed tariff, then section 4(h) of the Gas Act requires the Energy Regulator to regulate the tariff. The process to be followed in regulating the tariff is outlined in the Tariff Guideline. In regulating, NERSA will regulate by determining the tariffs, if necessary, to ensure that NERSA is fulfilling its regulatory duties, inter alia by ensuring tariffs are cost effective and applied in a non-discriminatory manner. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 3

4 2.3 For monitoring purposes, the application for and implementation of a tariff must be provided on an annual basis, although applicants are allowed to apply for approval of tariffs for a period of several years. 2.4 The approved tariff becomes the applicable tariff and discounts are permissible. It must be noted that the discounts should be consistent with the objectives of the Gas Act as well as section 22 of the Gas Act. 2.5 The approved tariff will by virtue of section 22 of the Gas Act also apply to third parties. 3. SASOL GAS TRANSMISSION TARIFF APPLICATION 3.1 Sasol Gas (Pty) Ltd (registration number 1964/006005/06) is wholly owned by Sasol Gas Holdings (Pty) Ltd (registration number 2000/013669/07), a limited liability company incorporated in terms of South African company law. Sasol Gas Holdings (Pty) Ltd is in turn a wholly owned subsidiary of Sasol Limited. 3.2 Sasol Gas is vertically integrated in the gas industry supply chain in South Africa, i.e. it is active in gas transmission, gas distribution and gas trading. Sasol Limited has also secured rights to natural gas from the Republic of Mozambique through a series of agreements with the Mozambican Government. 3.3 Sasol Gas is involved in the transmission, distribution and trading of; piped natural gas from the Mozambican gas fields, as well as piped methane-rich gas produced at Secunda. 3.4 The Sasol Gas pipeline network covers most of the Gauteng Province, as well as parts of the Free State, Mpumalanga and KwaZulu-Natal provinces. The Application 3.5 On 03 March 2015, the Energy Regulator received a transmission tariff application from Sasol Gas. The application is for two years and will be effective for the period 01 July 2015 to 30 June Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 4

5 3.6 It is split into two tariff periods aligned with Sasol Gas financial year. The first tariff period is from 01 July 2015 to 30 June The second tariff period is from 01 July 2016 to 30 June Sasol Gas is applying for a postal pricing tariff approach whereby its transmission infrastructure is divided into three zones, with one tariff applicable to each zone. The Tariff Guidelines allows for this type of a tariff structure. According to section 6 of the Tariff Guidelines, the common approaches to tariff structuring are the Full distance pricing; Entry / exit pricing; and Postal pricing. 3.8 The full distance pricing, is the calculation of tariffs for individual pairs of entry and off-take points. The tariffs will reflect the distance between the off-take point and the point where gas was delivered into the gas pipeline system. A tariff will be calculated for each entry and exit point. The Tariff Guidelines further state that where the system is complex (there are many interconnections) and there is a large number of off take points, full distance pricing may be complicated to develop and impracticable to administer and maintain. 3.9 The simplified version of full distance pricing is the entry/exit pricing. In this pricing, off take points are grouped for each zone. In this method tariffs will be set for the transmission of gas from the point at which it enters the transmission system, the entry point, to the zonal exit points Postal pricing is a system in which each off take point in a particular region is charged a flat rate, irrespective of its capacity, the distance gas is transported or any other characteristic, similar to a postage stamp. This is the methodology that Sasol Gas has opted to use. The method may have the disadvantage of not being able to fully reflect costs associated with gas transportation over specific distances. However it presents a practical solution when compared to the cost reflective tariff pricing that is deemed to be complex and impractical to maintain if there are many (above 20) entry and exit points such as those prevalent in the Sasol Gas case. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 5

6 3.11 The application proposes three transmission zones namely: 1) Zone 1 : Secunda-Gauteng-Sasolburg network natural gas 2) Zone 2: Witbank-Middelburg network methane-rich gas; and 3) Zone 3: KwaZulu-Natal network methane-rich gas The figure below provides an illustration of the zones. Jofane Rumbacaca Temane INHAMBANE Talofo Muabsa Vilanculos Componde GAZA Chigubo Camo-Camo Mabuiapanse Magandene Meginge 1 Babelegi Rosslyn Pretoria Lyttelton Kemptonpark GAUTENG Benoni Randfontein A Springs Lenasia E Nigel Alberton Meyerton Vereeniging 2 MPUMALANGA Nelspruit Middelburg Witbank Carolina Hendrina Breyten Bethal Ermelo Secunda Badplaas Amsterdam B Malelane Barberton SWAZILAND MAGUDE Mahele Panjane MOAMBA Sabie Komatipoort Ressano Garcia Guija Chokwe Motaze MAPUTO C Maputo Sasolburg Standerton Volksrust New Castle 3* 1 Zone1 KWAZULU-NATAL Empangeni Mandini Richardsbay 2 Zone 2 Verulam Phoenix D Avoca Durban 3 Zone 3 * Zone 3: Excludes the Transnet Lily Pipeline 3.13 The tariff per zone is determined by calculating the allowable revenue per zone divided by the budgeted volume commitment for the zone The following table summarises the transmission tariffs Sasol Gas is applying for: Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 6

7 Table 1: Sasol Gas Tariff Application Summary Zone Component 1 July '15-30 June '16 1 July '16-30 June '17 Allowable Revenue (R ) Gauteng Volume (GJ) Tariff Allowable Revenue (R ) Secunda - Middleburg Volume (GJ) Tariff Allowable Revenue (R ) KwaZulu Natal Volume (GJ) Tariff NERSA ASSESSMENT 4.1 According to the Guidelines for Monitoring and Approving transmission and storage tariffs for the Piped-Gas Industry in South Africa (Tariff Guidelines), applicants are required to submit a tariff application based on their respective preferred methodology that may be chosen from the approved menu of tariff methodologies. 4.2 Each tariff application is reviewed using the same methodology chosen and used by the tariff applicant and any other appropriate information or method for assessing the reasonableness of each application by the Energy Regulator. 4.3 Alternative tariff methodologies or variations on the methods listed on the menu may be used by the applicant, provided that such method is proven, tested and verifiable. 4.4 Therefore, to review the application for reasonableness, the Energy Regulator used the Rate of Return ( RoR ) methodology as it was in line with Sasol Gas transmission tariff application. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 7

8 5. ELEMENTS OF ALLOWABLE REVENUE 5.1 The formula for calculating the allowable revenue for the tariff is as follows: AR = (RAB x WACC) + E + T + D ± C Where: AR - Allowable Revenue RAB - Regulatory Asset Base WACC - Weighted Average Cost of Capital E- Expenses T - Taxes D Depreciation & Amortization C Claw back 5.2 The above formula yielded the following results: Table 2: 2015/16 Allowable Revenue Calculation Summary (AR = (RAB*WACC) + E +D +T±C) NERSA Sasol Gas (R) (R) (RAB = v-d +net working capital) a Total Regulatory Asset Base RAB b WACC WACC 000% 000% c Rab x WACC= (a*b) RAB *WACC d Operating Expenses E e Depreciation and Amortization D f Tax T g Clawback C h Allowable Revenue (AR) = (c+d+e+f+g) AR 1,045,271,011 1,136,143,664 Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 8

9 Table 3: 2016/17 Allowable Revenue Calculation Summary (AR = (RAB*WACC) + E +D +T±C) NERSA Sasol Gas (R) (R) (RAB = v-d +net working capital) a Total RAB RAB b WACC WACC 00% 00% c RAB x WACC RAB * WACC d Operating expenses E e Depreciation and Amortization D g Tax T h Clawback C i Total Allowable Revenue (AR) = (c+d+e+f+g) AR 1,093,411,385 1,193,089, The paragraphs below provide an analysis of each component of the allowable revenue formula. a. Regulatory Asset Base (RAB) 5.4 In terms of section of the Tariff Guidelines, the value of the RAB is the inflation-adjusted historical cost or trended original cost ( TOC ) of plant, property and equipment less the accumulated depreciation for the period under consideration plus net working capital. The formula for this is as follows: Regulatory Asset Base = Trended Original Cost of Property, Plant & Equipment (v) - Accumulated Depreciation (d) + Net Working Capital (w) 5.5 Using the above formula, the resultant RAB for transmission as calculated by Sasol Gas is 0000 million for the period 01 July 2015 to 30 June 2016 ( FY16 ) and 0000 million for the period 1 July 2016 to 30 June 2017 ( FY17 ). The increase in the RAB from FY 16 to FY17 is attributable to projected additions during the tariff period. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 9

10 Secunda-Sasolburg pipeline 5.6 As part of the RAB, Sasol Gas included the Secunda to Sasolburg Pipeline ( GNP ). During licensing, the GNP was justified by Sasol Gas, indicating that it was required for new projects that had been initiated by Sasol Limited in the Sasolburg area. Sasol Gas stated that it saw a need to increase the capacity of the natural gas supply from Secunda to Sasolburg by constructing an additional transmission facility between Secunda and Sasolburg. 5.7 In the same licence application, Sasol Gas indicated that the additional natural gas will be used for xxx production by xxxxxxxxx and for power generation by xxxx ddd ddddd. The additional gas demand by bbbbbbbbbbbbbb for nnn production was projected to be 0 Million Gigajoules/annum plus 00 Million Gigajoules/annum to be used for power generation by vvvvvv vvvv vvv. Sasol Gas also indicated that it expects to supply additional 00 million Gigajoules to the Sasolburg customers. In total the additional gas that was expected by building the GNP pipeline was 00 million gigajoules over 10 years from Sasol Gas has further reported that there would have been capacity and pressure challenges if GNP was not commissioned. ArcelorMittal, Sasol Chemical Industries (high pressure customers) and the customers serviced by the distribution networks supplied by the Gauteng Network ( GTN ) would not be able to operate at their contractual capacity. The 140 MW power plant in Sasolburg will not have been built. If gas availability improves, more external customers could be added to GTN and GNP. Sasol Gas added that the GNP is used as back up for the GTN in the sense that every time pressure drops GNP PPS will open to stabilise GTN network to avoid supply interruptions of the customers supplied by the GTN. 5.9 During the public hearing Sasol Gas was requested to provide an explanation on what it is using the GNP for and whether it is connected to external customers. In its responses, Sasol Gas indicated that no external customer is connected directly to the GNP but that it is connected to the GTN by way of a pressure protection station in Sasolburg. Sasol Gas further reported that the capacity of the pipeline is not 00m GJ/ annum as reported in the public hearing but 000m GJ/annum that was submitted to NERSA when the pipeline was licensed. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 10

11 However, Sasol Gas indicated that its current capacity is 00 m GJ/annum and this can be enhanced to 000m GJ/annum at an additional cost of R000 million. Sasol Gas further stated that it is using 00m GJ/annum in the pipeline and that indeed there is uncommitted capacity in the pipeline NERSA noted the reduction in available capacity which is now 00m GJ/annum down from the 00m GJ/annum reported in the public hearing. The available capacity was calculated by simply subtracting the used capacity from the design capacity. The GNP is currently being used for internal customers and no external customers receive gas through this pipeline and yet it is included in the RAB. Sasol Gas argued that the GNP will technically benefit customers located around Sasolburg and Vanderbilpark but did not elaborate nor demonstrate how external customers benefit from the pipeline. No tangible evidence was provided to substantiate the claim. In this regard, the Gas division will conduct further inquiries on the operation of this pipeline to establish the actual volumes transported and to whom as well as the available capacity for third party access 5.11 NERSA conducted a desktop analysis, investigating the impact of excluding the GNP tariff from the total allowable revenue before it is split into zones. Thus NERSA used the total allowable revenue divided by volume to arrive at a figure and this was compared to the effect of excluding the GNP from the RAB. Operating expenses were not included in the calculation. The resultant difference was minimal and the GNP is included in the RAB However, NERSA will conduct an additional inquiry on who uses the GNP, the volumes it is transporting and whether it benefits the GTN network or not. Depending on the result of this inquiry, NERSA may not include the GNP in successive tariff assessments and may claw back the value of the GNP from the RAB. Other RAB 5.13 NERSA conducted a verification of the Sasol Gas asset base during the Regulatory Financial Reports ( RFR ) audit for the financial year ended 30 June As part of the Agreed Upon Audit Procedures, the Auditors were to: Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 11

12 Compare the starting RAB per the RFR to the historical asset base information provided to NERSA by Sasol Gas; Enquire from Sasol Gas whether a roll forward algorithm had been built into the ERP system, which is in accordance with NERSA s approved trending principles; Compare the calculation of the depreciation and amortisation inflation writeup per the RFR to the related NERSA principles in the RRM, and report on any deviations; Inspect that the starting RAB as per the RFR is determined on the historical cost basis or NERSA s approved revaluation values and further confirm that licensee utilises the starting RAB as approved by NERSA; Obtain representation from Sasol Gas confirming if plant held for future use (mothballed plant) existed and if so that they were itemized separately for exclusion from the RAB The audit report confirmed that there were no deviations or material findings Furthermore, NERSA performed a reasonableness check on the submitted RAB and performed a high level calculation based on the average useful life per asset class The resultant RAB for FY16 was R0000 million and 0000 million for FY17. This is 7% higher than the RAB values submitted by Sasol Gas where trending was done per individual asset item in the ERP system In light of the above, NERSA used the RAB values of 0000 million for FY16 and 0000 million for FY17 as applied for by Sasol Gas in its calculation of the allowable revenue. b. Depreciation (d) and Amortization 5.18 Section of the Tariff Guidelines provides that accumulated depreciation (d) is the cumulative depreciation against plant property, vehicles and equipment in service should be calculated on a straight line basis over the economic life of the Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 12

13 asset. This yielded a depreciation and amortisation expense of 0000 million for FY16 and 000 million for FY17. c. Net working Capital (w) 5.19 According to the Tariff Guidelines, net working capital refers to the various regulatory asset-base funding requirements other than utility plant in service. This is determined using the following formula: Net working capital = inventory + receivables + operating cash trade payables The Energy Regulator used the 45-day average working capital figure of 000 million for FY16 and 000 million for FY17, as provided by Sasol Gas and required by the Tariff Guidelines The principles and policies used to derive the elements of working capital was also verified though the FY14 full-year audit to confirm that they complied with the Tariff Guidelines and Regulatory Reporting Manuals (RRM). d. Tax (T) 5.22 Section 4.4 of the Tariff Guidelines provides that the flow-through tax approach is the Energy Regulator s preferred tax methodology. Under this approach, only the current taxes payable are factored into the allowable revenue and recovered during the tariff period under review The Energy Regulator allowed for the flow-through tax payable amount of R000 million for FY16 and 0000 million for FY17 in the allowable revenue calculation. Deferred tax was not taken into consideration since the flow-through tax method does not provide for future income taxes payable outside the tariff period. e. Expenses (E) Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 13

14 5.24 The Energy Regulator is required by section 4.3 of the Tariff Guidelines to assess the operating and maintenance expenses using principles such as whether the expenses were prudently incurred and efficient Sasol Gas applied for operating expenses of R 000 million for FY16 and million for FY17. NERSA used the principles as articulated in the approved Sasol Gas Cost Allocation Manual (CAM2) and Tariff Guidelines to assess each expense item as provided by Sasol Gas. After these prudency checks, NERSA allowed operating expenses of R0000 million for FY16 and 000 million for FY17. NERSA excluded expenses for other community development and penalties as these were viewed not to be efficient Sasol Gas, after the preliminary assessment, agreed with the NERSA assessment and excluded the expenses for community development and penalties from the final allowable revenue that would be used for approving the tariffs. Sasol Gas used the NERSA revised figures of 0000 million for FY16 and 0000 million for FY 17. f. Decommissioning Provision 5.27 NERSA allowed a decommissioning provision of 000 million, included in the expenses figure, in line with section 34 (1) (d) of the Gas Act and Regulation 11 (4) and (5) which require licensees to provide for security in respect of rehabilitation obligations The decommissioning provision is an amount that is collected during the operating period of an asset and it will be used to rehabilitate the land as prescribed in the Gas Act. The decommissioning provision is calculated in a similar manner as straight line depreciation whereby the present value of the decommissioning expense is divided by the remaining useful life of the assets. The remaining useful life used in the calculation is 15 years and this figure is the outcome of a study undertaken to determine the lifespan of the remaining gas reserves. Equal amounts, adjusted for asset additions and retirements is then collected in the tariff. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 14

15 g. Weighted Average Cost of Capital (WACC) 5.29 The Energy Regulator used the following formula in its determination of Sasol Gas WACC: WACC E Dt + E Ke Dt + Dt + E Kd ( real) = * ( real) * ( real) Where: E = equity Dt = debt Ke (real) = real cost of equity derived from the Capital Asset Pricing Model (CAPM) Kd (real) = the post tax real cost of debt Table 4: 2015/16 WACC calculation summary Symbol NERSA Sasol Gas Cost of Equity (Ke=Rf+(MRP*beta)+SSP) a Real Risk free rate (Rf) Rf 3.99% 4.05% b Real Market Risk Premium (MRP) MRP 5.80% 7.65% c Beta β d Small Stock Premium SSP 00% 00% e Real Cost of Equity (Ke) = ((a+(b*c)+d)) Ke 00% 00% Cost of Debt f Nominal Cost of Debt 000% 000% g Corporate tax rate Tax 28.00% 28.00% h Nominal Cost of Debt (Post-tax) 000% 000% i CPI forecast CPI f 000% 000% j Post tax Real cost of debt ((1+h)/(1+i))-1 Kd 000% 000% k Debt percentage 00% 00% l Equity percentage 00% 00% m Weighted Average Cost of Capital(Real) WACC 000% 000% Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 15

16 Table 5: 2016/17 WACC calculation summary Symbol NERSA Sasol Gas Cost of Equity (Ke=Rf+(MRP*beta)+SSP) a Real Risk free rate (Rf) Rf 3.99% 4.05% b Real Market Risk Premium (MRP) MRP 5.80% 7.65% c Beta β d Small Stock Premium SSP 00% 00% e Real Cost of Equity (Ke) = ((a+(b*c)+d)) Ke 00% 00% Cost of Debt f Nominal Cost of Debt 000% 000% g Corporate tax rate Tax 28.00% 28.00% h Nominal Cost of Debt (Post-tax) 000% 000% i CPI forecast CPI f 000% 000% j Post tax Real cost of debt ((1+h)/(1+i))-1 Kd 000% 000% k Debt percentage 00% 00% l Equity percentage 00% 00% m Weighted Average Cost of Capital(Real) WACC 000% 000% 5.30 Sasol Gas current gearing levels are below the xxxxx level required by Tariff Guidelines. Therefore the gearing based on xxxxx debt ratio of 00% was used to calculate the WACC The mark-to-market risk free rate of a selected 5 to 10 year government of South Africa bonds were used for the expected risk free return (Rf) in the estimation of cost of equity. This yielded a real risk free rate of 3.99% The market return (Rm) was calculated using the JSE ALL Share Index, converted from a nominal to real value for the previous 25 years (ended 30 June 2014) as prescribed by the Tariff Guidelines. The average month-to-month CPI over the same period (ended 30 June 2014) was used. This yielded a real market risk premium (MRP) of 5.80% Sasol Gas used 32 years (384 months) from March 1982 to February 2014 to calculate a risk free rate of 4.05% and an MRP 7.65%. As part of the reasons, it stated that ideally the period should not be shorter than the useful life of the pipeline assets. Sasol Gas contends that this would ensure that the return Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 16

17 expectations are commensurate with the investment horizon. A long MRP would also allow for all possible economic situations and scenarios to be captured in the calculation of the MRP estimate. Sasol Gas further stated that this principle is consistent with frequently cited International practice by Ibbotson Associates. Despite these assertions, Sasol Gas used 32 years to estimate the MRP which is a shorter period than the average useful life of its assets of 45 years and stated that data beyond the 32 years was not available The beta (β) was determined by proxy. As a proxy, the average of six gas pipeline companies chosen by the Energy Regulator and listed on stock exchanges must be used as per the Tariff Guidelines. The following US companies were used by the Sasol Gas as proxies: AGL Resources Inc; UGI Corporation; South Jersey Industries; WGL Holdings Inc.; The Laclede Group; and Piedmont Natural Gas Company Inc The beta was calculated using the Hamada methodology. NERSA used the same companies as those selected by Sasol Gas and updated its beta using the AGL Resources financial information However Sasol Gas used the above companies and the below mentioned data to derive a beta of 0.00: weekly returns observations; an estimation window using returns measured over the five-year period. In the previous tariff application, Sasol Gas used a two-year period; and raw equity betas which were not adjusted for proxy companies tax Although the Tariff Guidelines do not specify the data inputs to be used to estimate the beta, it has been NERSA s standard in piped-gas to use: weekly returns observations; Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 17

18 an estimation window using returns measured over the two-year period; and adjusted betas which were adjusted for proxy companies marginal tax in line with the Hamada formula The NERSA approach yielded a beta of In the determination of return on equity (Ke), NERSA allowed a Small Stock Premium (SSP) of 0.00% in line with international standards. The Tariff Guidelines, although they allow for adjustments to the WACC to reflect the real risk of the cost of equity, they do not specify the formula to be used. Therefore, this SSP adjustment is based on a research study conducted by PWC South Africa in 2009/10. The conclusions of the study are in line with valuation methodologies used by leading international valuation experts such as Professor Aswath Damodaran, who recommends that smaller companies should add a premium to their Ke Moreover finance literature clearly establishes that the Ke is the risk adjusted opportunity cost to the investors and not the cost of the specific capital sources employed by investors, meaning that the true cost of capital depends on the use to which the capital is put and not on its source. In a subsidiariy of a group such as Sasol Gas, it is not the parents WACC that determines the subsidiary s cost of equity because the parents WACC is itself a weighted average of equity costs of all subsidiaries. In this regard, Sasol Gas is treated as a small company because according to the RRMs, Sasol Gas is supposed to ring fence and report each regulated activity separately. Therefore, the transmission activity is separated from the trading and distribution activities and there should be no cross subsidisation among the regulated activities A cost of debt (Kd) of 00 % as provided by Sasol Gas was used to calculate the post-tax real cost of debt of 000% for FY16 and 000% for FY It must be noted that the sources of information prescribed by NERSA were used by Sasol Gas as data sources for calculating the WACC. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 18

19 h. Claw-back 5.43 NERSA calculated an under recovery claw back of R00.0 million that will be added to the current allowable revenue, whilst Sasol Gas calculated an under recovery of 000 million. However, after the preliminary assessment was published, Sasol Gas revised their clawback figure and used the NERSA figure of R00.0 million NERSA advocates for the use of the same cost of equity that was used at the application stage. It is NERSA s view that the shareholders view of their cost of investment cannot be clawed back. The cost of debt should be the actual debt used during the period and can be clawed back The other difference in the figures used by Sasol Gas in the 2014 allowable revenue was the decommissioning provision. Sasol Gas used R000 million in FY 2014 but has updated it with the actual figure of R00 million. The difference in the two figures mainly emanated from different useful life s used to calculate the provision. During the application stage for the 2014 decision Sasol Gas used 45 years, being the economic useful life of the assets, instead of 15 years up to 2029, when the gas reserves are expected to be depleted. In addition, a minor cause of the difference in the figures also arose from the fact that there were asset additions in 2014 and these increase the amount needed to decommission the assets Table 6 below provides a summary of NERSA s claw back calculation for the FY14. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 19

20 Table 6: Clawback summary calculation Clawback Calculation Total RAB Estimates used to calculate the FY14 Tariff Audited Actual figures being used for claw back purposes for FY14 Tariff ZONE 1 Clawback per zone ZONE 2 Clawback per zone ZONE 3 Clawback per zone R R R R R WACC Return on assets (RAB*WACC) Operating Costs (E) Depreciation & Amortisation -(D) Taxation Decommissioning Provision Allowable Revenue 936,342, ,150, ,707, ,347,069 98,096,817 Volume used to calculate tariff 169,911, ,509, ,110,797 6,267,246 17,131,599 Audited actuals of estimates - R/GJ Estimates at tariff approval - R/GJ Portion of tariff to be clawed back in R/GJ Actual Volumes sold in the tariff period (26 March June 2014) - GJ Clawback - AR under/ (over) recovered (Actual vol x under recovered tariff) 6. TRANSMISSION TARIFF ZONES 6.1 Sasol Gas transmission tariff is divided into three zones namely: a) Zone 1 : Secunda-Gauteng-Sasolburg network natural gas b) Zone 2: Witbank-Middelburg network methane-rich gas; and c) Zone 3: KwaZulu-Natal network methane-rich gas. 6.2 The tariff per zone is determined by calculating the allowable revenue per zone divided by the budgeted volume commitment for the zone. 6.3 The split of the allowable revenue elements into zones was done as per the approved CAM2 principles. The Tariff Guidelines allows for this type of a tariff structure. 6.4 The application of these principles yielded the following allocation drivers: Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 20

21 Table 7: Allocation Drivers for Allowable Revenue elements ZONE 1 ZONE 2 ZONE 3 COMPONENT RAB % 0% 0% 0% 0% 0% 0% OPEX % 0% 0% 0% 0% 0% 0% VOLUME (MGJ/a) NERSA application of the above approach yielded the following tariffs applicable to each zone: Table 8: Allowable Revenue Calculation per Zone - 01 July 2015 to 30 June 2016 Zone Allowable Revenue (R ) Volume (GJ) Tariff R/GJ 1 826,884, ,512, ,564,080 6,296, ,822,787 18,461, Table 9: Allowable Revenue Calculation per Zone - 01 July 2016 to 30 June 2017 Zone Allowable Revenue (R ) Volume (GJ) Tariff R/GJ 1 865,511, ,628, ,826,190 6,520, ,073,584 19,060, DECISION MAKING PROCESS 7.1 The non-confidential version of the application was published on the Energy Regulator website on 17 April Notices inviting members of the public to comment were published in The Star, Mail and Guardian and the Sunday Times on 24 April At the closing date of receiving written comments of 18 June 2015, only Illovo Sugar had submitted its comment. Below is an analysis of received comments: Comment There is an inconsistency between the asset base reported by Sasol Gas in its application and the total assets reported by Sasol Gas in its annual Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 21

22 financial statements, with the latter being substantially less than the former. Response The assets reported in the Sasol Gas annual financial records are recorded at historical cost whereas the assets used to calculate a return are recorded at inflation adjusted historical cost or trended original cost. The difference is that in the NERSA approach the Regulatory Asset Base is adjusted for inflation. The same inflation indices used to adjust for inflation will be used to adjust the nominal return/ WACC to real The key principle in setting a Regulatory Asset Base is to ensure that the investment in assets receives an appropriate level of return to recoup the investment and a return commensurate with risk. At the same time this requires the WACC to be set at an appropriate level for adequate return on capital. Therefore the adjustment to the assets is matched by the adjustment on WACC to ensure that there is no over recovery of the return on investment. In addition, setting the asset value correctly ensures that the appropriate level of funds is available as the return of capital towards the eventual replacement of the assets. Comment All relevant figures are redacted from the current published application for a transmission tariff for the period 01 July 2015 to 30 June Illovo submits that it s unable to comment on these figures and the onus is on NERSA to correctly evaluate the values provided in the application, particularly those assigned to infrastructure so as to ensure that there are no similar inconsistencies which could potentially result in an inflated tariff being granted. Response The legislation provides that NERSA should treat some information submitted by external parties as confidential provided that the external party has applied for the information to be treated as confidential under the relevant laws of the country. Section 36(1) of PAIA provides that: Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 22

23 Subject to subsection (2), the information officer of a public body must refuse a request for access to a record of a body if the record contains- a) trade secrets of a third party; b) financial, commercial, scientific or technical information, other than trade secrets of a third party, the disclosure of which would be likely to cause harm to the commercial or financial interest of that third party; or c) information supplied in confidence by a third party the disclosure of which could reasonably be expected- d) to put that third party at a disadvantage in contractual or other negotiations; or e) to prejudice that third party in commercial competition Furthermore, in terms of section 29(4) of the Gas Act, no information obtained by the Gas Regulator in terms of the Gas Act which is of a nongeneric, confidential, personal, commercially sensitive or of a proprietary nature may be made public or otherwise disclosed to any person without permission of the person to whom that information relates, except in terms of a high court order. Comment Illovo challenges the use of replacement value of assets when calculating the transmission base. Response NERSA does not use the replacement value of assets to calculate the regulatory asset base of the transmission assets but uses the inflation adjusted historic cost or (trended original cost) of assets. 7.2 Sasol Gas provided oral comments at the public hearing held on 02 July Sasol Gas agreed with the NERSA preliminary assessment of the claw back and the expenses. This had the effect of reducing the tariffs that Sasol Gas applied for. The tables below show the Sasol Gas tariffs before the public hearing and after the public hearing. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 23

24 Table 10: Sasol Gas multi-year transmission tariffs for the period 01 July 2015 to June 2016 Zone Before public hearing After public hearing 1 Gauteng R6.07/GJ R6.00/GJ 2 Secunda - Middleburg R19.40/GJ R19.16/GJ 3 KwaZulu Natal R6.16/GJ R6.09/GJ Table 11: Sasol Gas multi-year transmission tariffs for the period 01 July 2016 to June 2017 Zone Before public hearing After public hearing 1 Gauteng R6.01/GJ R6.01/GJ 2 Secunda - Middleburg R19.45/GJ R19.43/GJ 3 KwaZulu Natal R6.26/GJ R6.25/GJ 8. CONCLUSION 8.1 On the conspectus of the facts and evidence, it is appropriate and in compliance with the requirements of the National Energy Regulator Act, 2004 (Act No. 40 of 2004) to make the decision set out above. Reason for Decision For Sasol Gas Multiyear Transmission Tariff Application For 2015 to 2017 Page 24

TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE

TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE TARIFF DECISION FOR SASOL OIL (PTY) LTD S SECUNDA TO NATREF INTEGRATED (SNI) PIPELINE 10 MAY 2018 Page 1 of 19 TABLE OF CONTENTS Introduction... 6 Applicable Law... 6 The Methodology... 6 Decision-Making

More information

Decision. On 27 August 2015, the National Energy Regulator of South Africa ( NERSA or the Energy Regulator ) approved:

Decision. On 27 August 2015, the National Energy Regulator of South Africa ( NERSA or the Energy Regulator ) approved: NATIONAL ENERGY REGULATOR OF SOUTH AFRICA Decision On 27 August 2015, the National Energy Regulator of South Africa ( NERSA or the Energy Regulator ) approved: 1. A trading margin of R8.69/GJ for the period

More information

DISCUSSION DOCUMENT ON SASOL GAS (PTY) LTD APPLICATION TO APPROVE THE TRADING MARGIN FOR THE PERIOD 2017 TO 2019

DISCUSSION DOCUMENT ON SASOL GAS (PTY) LTD APPLICATION TO APPROVE THE TRADING MARGIN FOR THE PERIOD 2017 TO 2019 ANNEXURE A DISCUSSION DOCUMENT ON SASOL GAS (PTY) LTD APPLICATION TO APPROVE THE TRADING MARGIN FOR THE PERIOD 2017 TO 2019 1. INTRODUCTION 1.1 This discussion document provides background information

More information

THE PRICE CAPPING MECHANISM FOR AVERAGE PIPED-GAS PRICES IN. Decision. On 6 August 2014, the Energy Regulator approved the following:

THE PRICE CAPPING MECHANISM FOR AVERAGE PIPED-GAS PRICES IN. Decision. On 6 August 2014, the Energy Regulator approved the following: ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding THE PRICE CAPPING MECHANISM FOR AVERAGE PIPED-GAS PRICES IN THE PERIOD 01 APRIL 2013 TO 31 MARCH 2014 TO EXTERNAL CUSTOMERS OF SASOL LIMITED Decision

More information

ROMPCO 120 ( GTA1 ) 2013 (2013 Q2)

ROMPCO 120 ( GTA1 ) 2013 (2013 Q2) Consultation Document regarding the change in the RSA Producer Price Index (PPI) base used in the calculation of ROMPCO s tariff for volumes not exceeding 120 million gigajoules per annum ( GTA1 tariff

More information

Application of claw-back

Application of claw-back Application of claw-back A report for Vector Dr. Tom Hird Daniel Young June 2012 Table of Contents 1. Introduction 1 2. How to determine the claw-back amount 2 2.1. Allowance for lower amount of claw-back

More information

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) Presenter: National Treasury 18 November 2015 90 day Action Plan In November 2014, the Ministers

More information

SADC Industrialisation Week Lessons Learned from Mozambique South African Pipeline

SADC Industrialisation Week Lessons Learned from Mozambique South African Pipeline SADC Industrialisation Week Lessons Learned from Mozambique South African Pipeline 1 August 2017 Sasol at a glance Pioneer in the inventive monetisation of hydrocarbons An international integrated chemicals

More information

Market Value Pricing is defined in clause 1.16 of the Agreement as the determination of gas price by comparison with:

Market Value Pricing is defined in clause 1.16 of the Agreement as the determination of gas price by comparison with: NATIONAL ENERGY REGULATOR OF SOUTH AFRICA In the matter regarding Market Value Pricing (MVP) The market value pricing (MVP) principle is prescribed in Schedule One to the Agreement Concerning the Mozambican

More information

Valvoline Fourth-Quarter Fiscal 2016 Earnings Conference Call. November 9, 2016

Valvoline Fourth-Quarter Fiscal 2016 Earnings Conference Call. November 9, 2016 Valvoline Fourth-Quarter Fiscal 2016 Earnings Conference Call November 9, 2016 Forward-Looking Statements This presentation contains forward-looking statements within the meaning of Section 27A of the

More information

2. General Information on Recharge Centers

2. General Information on Recharge Centers Recharge Center Policy & Procedures 1. Introduction and Definition 2. General Information on Recharge Centers 3. Expenditures/Costs 4. Rate Setting 5. Taxes 6. Deficits, Surpluses, and Working Capital

More information

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

Proposal Concerning Modifications to LIPA s Tariff for Electric Service Proposal Concerning Modifications to LIPA s Tariff for Electric Service Requested Action: The Trustees are being requested to approve a resolution adopting modifications to the Long Island Power Authority

More information

SASOL GAS LIMITED PFG INTERCONNECTION LICENCE APPLICATION TO CONSTRUCT A GAS TRANSMISSION FACILITY IN THE EKURHULENI AREA, SPRINGS, GAUTENG

SASOL GAS LIMITED PFG INTERCONNECTION LICENCE APPLICATION TO CONSTRUCT A GAS TRANSMISSION FACILITY IN THE EKURHULENI AREA, SPRINGS, GAUTENG SASOL GAS LIMITED PFG INTERCONNECTION LICENCE APPLICATION TO CONSTRUCT A GAS TRANSMISSION FACILITY IN THE EKURHULENI AREA, SPRINGS, GAUTENG NATIONAL ENERGY REGULATOR APPLICATION FOR LICENCE IN TERMS OF

More information

NERSA CONSULTATION PAPER PROCESS. Moefi Moroeng Specialist: Wholesale Electricity Trading

NERSA CONSULTATION PAPER PROCESS. Moefi Moroeng Specialist: Wholesale Electricity Trading NERSA CONSULTATION PAPER PROCESS Moefi Moroeng Specialist: Wholesale Electricity Trading 1 AGENDA Energy Regulator Overview Regulation of the Electricity Supply Industry Current Structure of the Electricity

More information

For personal use only

For personal use only AER ISSUES NETWORK REVENUES DRAFT DECISIONS FOR ACT AND NSW ENERGY CUSTOMERS The Australian Energy Regulator (AER) has issued draft decisions on the revenue proposals submitted by ACT and NSW distribution

More information

UK Power Networks Use of System Charging Methodology

UK Power Networks Use of System Charging Methodology UK Power Networks Use of System Charging Methodology Effective From: 1 July 2018 Published: 15 June 2018 Contents General Introduction... 3 Who we are 3 Licence Obligations 3 Price Control 3 Connection

More information

Shareholders are referred to the Claw-back Offer Circular dated 13 July 2012 ("the Waiver Circular") detailing:

Shareholders are referred to the Claw-back Offer Circular dated 13 July 2012 (the Waiver Circular) detailing: RARE HOLDINGS LIMITED (Incorporated in the Republic of South Africa) Registration Number: 2002/025247/06 Share Code: RAR ISIN: ZAE000092714 ("the Company" or "RARE") RESULTS OF THE GENERAL MEETING, WAIVER

More information

MARKET VALUE PRICING EXPLANATORY NOTES

MARKET VALUE PRICING EXPLANATORY NOTES MARKET VALUE PRICING EXPLANATORY NOTES 1. INTRODUCTION 1.1 The Market Value Pricing (MVP) principle is prescribed in Schedule One to the Agreement Concerning the Mozambican Gas Pipeline between the Government

More information

TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT 14 TH MARCH 2008 TABLE OF CONTENTS Page 1 Introduction... 2 2 Charging Methodology Objectives... 4 3 Connection Charging Methodology... 5 4 Connection

More information

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By ABN 70 250 995 390 180 Thomas Street, Sydney PO Box A1000 Sydney South NSW 1235 Australia T (02) 9284 3000 F (02) 9284 3456 18/10/2018 Mr Peter Adams General Manager, Wholesale Markets Australian Energy

More information

This Distribution Charter explains how PLS distributes collective licensing

This Distribution Charter explains how PLS distributes collective licensing Distribution Charter 1 This Distribution Charter explains how PLS distributes collective licensing revenues. 1. Introduction 1.1 Collective licensing for published materials was introduced in the UK in

More information

Analysis of Operating Results and Financial Status

Analysis of Operating Results and Financial Status 29 Analysis of Operating Results and Financial Status 1. Analysis of Operating Results of EGAT and Its Subsidiaries Operating results of EGAT and its subsidiaries including associated company and joint

More information

Grindrod Investments Proprietary Limited (Incorporated in the Republic of South Africa) (Registration number 1957/003944/07) ( Grindrod Investments )

Grindrod Investments Proprietary Limited (Incorporated in the Republic of South Africa) (Registration number 1957/003944/07) ( Grindrod Investments ) Remgro Limited (Incorporated in the Republic of South Africa) (Registration number 1968/006415/06) Share code: REM ISIN: ZAE000026480 acting through its wholly-owned subsidiary Industrial Partnership Investments

More information

New Brunswick transitional rules for HST increase

New Brunswick transitional rules for HST increase New Brunswick transitional rules for HST increase April 2016 The 2016-17 New Brunswick budget announced an increase in the HST rate from 13% to 15%, effective July 1, 2016. Transitional rules have recently

More information

1QFY2018 Financial Results. Quarter Ended 30 June 2017

1QFY2018 Financial Results. Quarter Ended 30 June 2017 1QFY2018 Financial Results Quarter Ended 30 June 2017 Disclaimer This presentation is not and does not constitute an offer, invitation, solicitation or recommendation to subscribe for, or purchase, any

More information

Lazydays Holdings, Inc. Reports Second Quarter 2018 Financial Results

Lazydays Holdings, Inc. Reports Second Quarter 2018 Financial Results News Contact: +1 (813) 204-4099 investors@lazydays.com Lazydays Holdings, Inc. Reports Second Quarter 2018 Financial Results Tampa, FL (August 9, 2018) Lazydays Holdings, Inc. ( Lazydays )(NasdaqCM: LAZY)

More information

Every Disclosure Document issued by a Franchisor Member pursuant to the Code shall comply with the following requirements: -

Every Disclosure Document issued by a Franchisor Member pursuant to the Code shall comply with the following requirements: - C:\Users\Vera\Documents\Documents\FASA\DisclosureDocument\DISCLOSURE DOCUMENT REQUIREMENTS updated13aug 2011DRAFT.doc 29 August 2011 FRANCHISE ASSOCIATION OF SOUTH AFRICA DISCLOSURE DOCUMENT REQUIREMENTS

More information

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) APPLICATION BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Application of Great Oaks Water Company (U-162-W for an Order establishing its authorized cost of capital for the period from July 1, 2019

More information

Strong performance by the Bolloré Group s operating activities in 2018 Mr Cyrille Bolloré unanimously appointed Chairman and Chief Executive Officer

Strong performance by the Bolloré Group s operating activities in 2018 Mr Cyrille Bolloré unanimously appointed Chairman and Chief Executive Officer PRESS RELEASE 2018 results (1) March 14, 2019 Strong performance by the Bolloré Group s operating activities in 2018 Mr Cyrille Bolloré unanimously appointed Chairman and Chief Executive Officer Revenue:

More information

Consolidated Edison Company of New York, Inc.

Consolidated Edison Company of New York, Inc. PSC NO: 11 Electricity Leaf: 1 Initial Superseding Economic Development Delivery Service No. 2 Consolidated Edison Company of New York, Inc. Schedule For Economic Development Delivery Service Subsequent

More information

SASOL GAS LIMITED SPRING LIGHTS GAS, NCS RESINS LICENCE APPLICATION TO CONSTRUCT A GAS DISTRIBUTION FACILITY IN THE PROSPECTON AREA, KZN

SASOL GAS LIMITED SPRING LIGHTS GAS, NCS RESINS LICENCE APPLICATION TO CONSTRUCT A GAS DISTRIBUTION FACILITY IN THE PROSPECTON AREA, KZN SASOL GAS LIMITED SPRING LIGHTS GAS, NCS RESINS LICENCE APPLICATION TO CONSTRUCT A GAS DISTRIBUTION FACILITY IN THE PROSPECTON AREA, KZN NATIONAL ENERGY REGULATOR APPLICATION FOR LICENCE IN TERMS OF SECTION

More information

Explanatory Notes to aid completion of Disclosure Document Template

Explanatory Notes to aid completion of Disclosure Document Template Explanatory Notes to aid completion of Disclosure Document Template These explanatory notes have been prepared to assist Franchisors in completing the disclosure document template, and to ensure the disclosure

More information

Derivative Valuation and GASB 53 Compliance Report For the Period Ending September 30, 2015

Derivative Valuation and GASB 53 Compliance Report For the Period Ending September 30, 2015 Derivative Valuation and GASB 53 Compliance Report For the Period Ending September 30, 2015 Prepared On Behalf Of Broward County, Florida October 9, 2015 BLX Group LLC 777 S. Figueroa Street, Suite 3200

More information

Comhairle Cathrach Chorcaí Cork City Council

Comhairle Cathrach Chorcaí Cork City Council Transportation Division City Hall Cork Response to the Consultation Paper on the ESBN Electric Vehicle Pilot & Associated Assets Reference CER/16/286 Introduction welcomes the opportunity to respond to

More information

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS

Maharashtra Electricity Regulatory Commission (Renewable Purchase Obligation, Its. Regulations, 2016 STATEMENT OF REASONS MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400 005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@mercindia.org.in Website: www.mercindia.org.in

More information

MYPD3 tariff restructuring plan use-of-system charges. Brochure

MYPD3 tariff restructuring plan use-of-system charges. Brochure MYPD3 tariff restructuring plan use-of-system charges Brochure November 2012 Use-of-system charges for MYPD3 Page 1 PART 1: ESKOM REVENUE REQUIREMENT Introduction The current Multi-Year Price Determination

More information

TRANSMISSION LICENCE NO. 1 OF 2011 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA

TRANSMISSION LICENCE NO. 1 OF 2011 LICENCE FOR TRANSMISSION OF ELECTRICITY IN THE STATE OF MAHARASHTRA MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th floor, Cuffe Parade, Mumbai - 400 005. Tel. No. 022 22163964/65/69 Fax 022 22163976 E-mail mercindia@mercindia.org.in

More information

10 Sasol Khanyisa Public (RF) Limited Group Annual Report SASOL SOUTH AFRICA Fact Book

10 Sasol Khanyisa Public (RF) Limited Group Annual Report SASOL SOUTH AFRICA Fact Book 10 Public (RF) Limited Group Annual Report 2018 SASOL SOUTH AFRICA Fact Book CONTENTS Sasol South Africa At a Glance 12 Full Year 2018 Highlights 12 Did you Know? 13 Operating Structure and the Products

More information

PUBLIC Law, Chapter 539 LD 1535, item 1, 124th Maine State Legislature An Act To Create a Smart Grid Policy in the State

PUBLIC Law, Chapter 539 LD 1535, item 1, 124th Maine State Legislature An Act To Create a Smart Grid Policy in the State PLEASE NOTE: Legislative Information cannot perform research, provide legal advice, or interpret Maine law. For legal assistance, please contact a qualified attorney. Emergency preamble. Whereas, acts

More information

Factbook. Tokyo Electric Power Company Holdings, Inc. August Tokyo Electric Power Company Holdings, Inc. All Rights Reserved.

Factbook. Tokyo Electric Power Company Holdings, Inc. August Tokyo Electric Power Company Holdings, Inc. All Rights Reserved. Factbook Tokyo Electric Power Company Holdings, Inc. August 2018 (Note) Please note that the following to be an accurate and complete translation of the original Japanese version prepared for the convenience

More information

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS. 25.211. Interconnection of On-Site Distributed Generation (DG). (a) (b) (c) Application. Unless the context indicates otherwise, this section and 25.212 of this title (relating to Technical Requirements

More information

Licence Application Decision

Licence Application Decision Licence Application Amendment to Licence Application # 199-13 Applicant Whistler Resort Cabs Ltd. Trade Name (s) Resort Cabs Principals PARHAR, Salindar Singh PARMAR, Navdeep Singh Address 225 2063 Lake

More information

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators

Wheeling charges, Banking charges & Cross Subsidy Surcharge for Solar Power Generators KARNATAKA ELECTRICITY REGULATORY COMMISSION No.9/2, 6 th & 7 th Floor, Mahalaxmi Chambers, M.G.Road, Bangalore-560 001 Present: Shri M.R. Sreenivasa Murthy Chairman Shri H. D. Arun Kumar Shri D.B. Manival

More information

Part 3 Tax Planning for Property Developers. TST Consultants Sdn Bhd 1

Part 3 Tax Planning for Property Developers. TST Consultants Sdn Bhd 1 Part 3 Tax Planning for Property Developers TST Consultants Sdn Bhd 1 Tax Planning for Property Developer A. Purchase the land or Purchase the share? (Beware the capital reserve and deferred Tax) B. Disposal

More information

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)* Australian Capital Territory Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)* Disallowable instrument DI2016 189 made under the Utilities Technical Regulation

More information

SONI LTD TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT

SONI LTD TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT SONI LTD TRANSMISSION CONNECTION CHARGING METHODOLOGY STATEMENT 14 TH MARCH 2008 TABLE OF CONTENTS Page 1 Introduction...1 2 Charging Methodology Objectives...3 3 Connection Charging Methodology...4 4

More information

according to Annex 30A of the Regulation no. 1/2006 with subsequent amendments regarding the issuers and securities operations

according to Annex 30A of the Regulation no. 1/2006 with subsequent amendments regarding the issuers and securities operations Quarterly Report on March 31 st, 2016 according to Annex 30A of the Regulation no. 1/2006 with subsequent amendments regarding the issuers and securities operations Date of report: March 31 st, 2016 Company's

More information

PRO-FORMA FIGURES OF THE A2A GROUP

PRO-FORMA FIGURES OF THE A2A GROUP PRO-FORMA FIGURES OF THE A2A GROUP restated at December 31, 2007 published on March 25, 2009 Contents 3 0.1 Summary of pro-forma figures restated at December 31, 2007 7 0.2 Presentation of the pro-forma

More information

PIVE 1 PIVE 2 PIVE 3 PIVE 4 PIVE 5 PIVE 6 PIVE 7 PIVE

PIVE 1 PIVE 2 PIVE 3 PIVE 4 PIVE 5 PIVE 6 PIVE 7 PIVE Title of the measure: SPA51-PIVE Efficient-Vehicle Incentive Programme General description PIVE Programme was approved in Cabinet Meeting of 27 September 2012 with an initial budget allocation of 75 million,

More information

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM

FITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM Sheet 1 FITCHBURG GAS AND ELECTRIC LIGHT COMPANY SCHEDULE NM Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services

More information

Consolidated Financial Results for 1Q FY2016 July 29, 2016 Fuji Electric Co., Ltd.

Consolidated Financial Results for 1Q FY2016 July 29, 2016 Fuji Electric Co., Ltd. Consolidated Financial Results for 1Q FY2016 July 29, 2016 Fuji Electric Co., Ltd. 2016Fuji Electric Co., Ltd. All rights reserved. 1 Summary of Consolidated Financial Results for 1Q FY2016 (YoY Comparison)

More information

Merger of the generator interconnection processes of Valley Electric and the ISO;

Merger of the generator interconnection processes of Valley Electric and the ISO; California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric

More information

Electric Vehicle Charge Ready Program

Electric Vehicle Charge Ready Program Electric Vehicle Charge Ready Program September 20, 2015 1 Agenda About SCE The Charge Ready Initiative Depreciation Proposals of The Charge Ready Initiative Challenges Outcomes September 20, 2015 2 About

More information

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE September 7, 2016 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT ON COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE PURPOSE To update Council on Kamloops

More information

May 2017 Pei Sue Ong, Capital Accounting Advice Manager Pacific Gas and Electric Company

May 2017 Pei Sue Ong, Capital Accounting Advice Manager Pacific Gas and Electric Company Accounting for New Technologies Storage Batteries May 2017 Pei Sue Ong, Capital Accounting Advice Manager Pacific Gas and Electric Company 1 Agenda 1. Storage Battery Technologies 2. PG&E Owned Storage

More information

Cosmo Oil Co., Ltd. Presentation on Results for First Quarter of Fiscal 2012 August 2, 2012 Director: Satoshi Miyamoto

Cosmo Oil Co., Ltd. Presentation on Results for First Quarter of Fiscal 2012 August 2, 2012 Director: Satoshi Miyamoto Cosmo Oil Co., Ltd. Presentation on Results for First Quarter of Fiscal 2012 August 2, 2012 Director: Satoshi Miyamoto Copyright 2012 COSMO OIL CO.,LTD. All Rights Reserved. Key Points of Financial Results

More information

Smart metering Estonian case study

Smart metering Estonian case study Smart metering Estonian case study Dr. Märt Ots Estonian Competition Authority www. erranet.org Estonia north-eastern part of Europe 2 General information about Estonia Small country: area: 45 227 sq km;

More information

COMPETITION TRIBUNAL OF SOUTH AFRICA ROADSPAN HOLDINGS (PTY) LTD

COMPETITION TRIBUNAL OF SOUTH AFRICA ROADSPAN HOLDINGS (PTY) LTD COMPETITION TRIBUNAL OF SOUTH AFRICA In the matter between: Case No: 79/LM/Nov09 WBHO CONSTRUCTION (PTY) LTD Acquiring Firm And ROADSPAN HOLDINGS (PTY) LTD Target Firm Panel : Norman Manoim (Presiding

More information

FREE SHARE ALLOCATION LETTER

FREE SHARE ALLOCATION LETTER {SEQUENCE} {FULLNAME} {ADDRESS_1} {ADDRESS_2} {ADDRESS_3} {ADDRESS_4} {ADDRESS_5} {POSTCODE} FREE SHARE ALLOCATION LETTER FREE SHARE ALLOCATION LETTER SASOL KHANYISA FREE SHARE ALLOCATION On 16 April 2018,

More information

Statement of Expected Price Trends

Statement of Expected Price Trends 2012-13 2016-17 June 2016 TasNetworks Pty Ltd PO Box 606 Moonah TAS 7009 ABN 24 167 357 299 Enquiries regarding this document should be addressed to: TasNetworks Revenue and Pricing Regulation Team Leader

More information

Financial Data Supplement Q4 2017

Financial Data Supplement Q4 2017 Bank Financial Data Supplement Q4 2017 2 February 2018 Due to rounding, numbers presented throughout this document may not sum precisely to the totals we provide and percentages may not precisely reflect

More information

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SOUTHERN ELECTRIC POWER DISTRIBUTION PLC EMBEDDED DISTRIBUTION NETWORKS

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SOUTHERN ELECTRIC POWER DISTRIBUTION PLC EMBEDDED DISTRIBUTION NETWORKS STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SOUTHERN ELECTRIC POWER DISTRIBUTION PLC EMBEDDED DISTRIBUTION NETWORKS Effective from 1 st April 2013 The methodology set out in this statement was approved

More information

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which:

RECOMMENDATION: It is recommended that the City Council, following a public hearing, adopt the attached resolution which: DATE: July 16,2007 TO: FROM: SUBJECT: CITY COUNCIL CITY MANAGER CONSIDERATION OF ADOPTION OF NEW FEDERAL STANDARDS RELATING TO ELECTRIC UTILITIES UNDER THE PUBLIC UTILITIES REGULATORY POLICIES ACT AND

More information

COMMISSION OF THE EUROPEAN COMMUNITIES

COMMISSION OF THE EUROPEAN COMMUNITIES COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, 17.11.1997 PUBLIC VERSION MERGER PROCEDURE ARTICLE 6(1)(b) DECISION To the notifying parties: Dear Sirs, Subject: Case No IV/M.1015 - Cummins/Wärtsilä Notification

More information

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min Gas Advisory Board Draft Agenda Meeting No. 1 Location: Parmelia Hilton, Swan B Room 14 Mill Street, Perth WA 6000 Date: 20 December 2011 Time: 11:15am 12:15pm Item Subject Responsible Time 1. WELCOME

More information

CPP FINANCIAL MODEL Powerco CPP proposal. 12 June 2017

CPP FINANCIAL MODEL Powerco CPP proposal. 12 June 2017 CPP FINANCIAL MODEL Powerco CPP proposal 12 June 2017 Model notes Table of contents Module Worksheet Purpose Cover Model notes Error checks master Summarises all of the error checks that are contained

More information

UMW HOLDINGS BERHAD ( P)

UMW HOLDINGS BERHAD ( P) EXECUTION OF A SHARE PURCHASE AGREEMENT BETWEEN UMW RIG ASSET (L) LTD AND S.D. STANDARD DRILLING PLC IN RESPECT OF THE ACQUISITION OF THE ENTIRE ISSUED AND PAID-UP CAPITAL IN OFFSHORE DRILLER 4 LTD 1.

More information

I remind you that our presentation is available on our website. We can start from the first 2 slides that show Piaggio Group First

I remind you that our presentation is available on our website. We can start from the first 2 slides that show Piaggio Group First CONFERENCE CALL 2009 1 st HALF RESULTS Good afternoon and welcome to everybody. I remind you that our presentation is available on our website. We can start from the first 2 slides that show Piaggio Group

More information

Months Investor Presentation

Months Investor Presentation 2018 9 Months Investor Presentation 25.10.2018 Disclaimer Ereğli Demir Çelik Fabrikaları T.A.Ş. (Erdemir) may, when necessary, make written or verbal announcements about forward-looking information, expectations,

More information

Annual KRTA Report for the Year 2016

Annual KRTA Report for the Year 2016 Annual KRTA Report for the Year 2016 Tracy Golden, CPE, CPA Chief Financial Officer Board Meeting August 21, 2017 Key Ratio Trend Analysis Provided by CFC each year Numbers come from annual CFC Form 7

More information

Financial Summary for 2Q-FY2017 And Projections for FY2017

Financial Summary for 2Q-FY2017 And Projections for FY2017 Financial Summary for 2Q-FY2017 And Projections for FY2017 1 INDEX 01 Financial Summary for 2Q-FY2017 02 Performance Forecast for FY2017 03 Topics 2 01 Financial Summary for 2Q-FY2017 3 01 Financial Summary

More information

1160 Halston Avenue, Kamloops BC V2B 7L3 SANDHU, Jagwinder Singh

1160 Halston Avenue, Kamloops BC V2B 7L3 SANDHU, Jagwinder Singh Application Decision Application: Applicant: Trade Names: Address: Principals: Special Authorization: Summary: AV75 11 Kami Cabs Ltd. Kami Cabs 1160 Halston Avenue, Kamloops BC V2B 7L3 KANG, Harman Singh

More information

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SCOTTISH HYDRO ELECTRIC POWER DISTRIBUTION PLC DISTRIBUTION SYSTEM

STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SCOTTISH HYDRO ELECTRIC POWER DISTRIBUTION PLC DISTRIBUTION SYSTEM STATEMENT OF CHARGING METHODOLOGY FOR USE OF THE SCOTTISH HYDRO ELECTRIC POWER DISTRIBUTION PLC DISTRIBUTION SYSTEM Effective from 1 st April 2013 The methodology set out in this statement was approved

More information

BlueScope Steel Limited Consolidated Financial Headlines

BlueScope Steel Limited Consolidated Financial Headlines BlueScope Steel Limited Consolidated Financial Headlines 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2013 2013 2014 2014 2014 2015 2015 2015 2016 2016 2016 2017 2017 2017 2018 2018 2018 Total

More information

Rhode Island Division of Public Utilities and Carriers & Office of Energy Resources. Power Sector Transformation

Rhode Island Division of Public Utilities and Carriers & Office of Energy Resources. Power Sector Transformation 1 Rhode Island Division of Public Utilities and Carriers & Office of Energy Resources Power Sector Transformation Notice of Inquiry into the Electric Utility Business Model and Request for Stakeholder

More information

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque Energy Regulation : Australian Experience Engr.Khondkar Abdus Saleque 14/11/2014 Australian Energy Regulator Australia is a federal Country with Six Sates and two territories Victoria, NSW, Queensland,

More information

Licence Application Decision

Licence Application Decision Licence Application Decision Limousine Additional Vehicles Application # AV167-15 Applicant Luxury Life Limousine Inc. Trade Name (s) Luxury Life Limousine Principals JHOOTY, Vikrambir JHOOTY, Jasbir Singh

More information

Lazydays Holdings, Inc. Reports Third Quarter 2018 Financial Results

Lazydays Holdings, Inc. Reports Third Quarter 2018 Financial Results News Contact: +1 (813) 204-4099 investors@lazydays.com Lazydays Holdings, Inc. Reports Third Quarter 2018 Financial Results Tampa, FL (November 8, 2018) Lazydays Holdings, Inc. ( Lazydays ) (NasdaqCM:

More information

SASOL KHANYISA. Information Booklet

SASOL KHANYISA. Information Booklet Information Booklet 1 Sasol Khanyisa 2018 CONTENTS 5 WELCOME 6 UNDERSTANDING SHARES 8 YOUR INVESTMENT 11 HOW DO YOU TRADE YOUR SOLBE1 SHARES? 13 15 WHAT HAPPENS IF YOU DIE? MANAGING YOUR INVESTMENT Sasol

More information

SASOL KHANYISA QUESTIONS AND ANSWERS

SASOL KHANYISA QUESTIONS AND ANSWERS SASOL KHANYISA QUESTIONS AND ANSWERS 1 Sasol Khanyisa Frequently Asked Questions 1. How is the Sasol Khanyisa transaction structured and what is the B-BBEE ownership percentage? 2. Who will take part in

More information

Sasol South Africa (Pty) Ltd Directors' report The directors have pleasure in presenting their report for the year ended 30 June 2016. Nature of business The main business of the company is focused on

More information

Submission on the Electricity ( Disconnections and Low Fixed Charges) Amendment Bill

Submission on the Electricity ( Disconnections and Low Fixed Charges) Amendment Bill Submission on the Electricity ( Disconnections and Low Fixed Charges) Amendment Bill Submission : TrustPower supports the Amendments relating to Disconnections. TrustPower does not support the Amendments

More information

Maritime Electric C A N A D A PROVINCE OF PRINCE EDWARD ISLAND BEFORE THE ISLAND REGULATORY AND APPEALS COMMISSION

Maritime Electric C A N A D A PROVINCE OF PRINCE EDWARD ISLAND BEFORE THE ISLAND REGULATORY AND APPEALS COMMISSION Maritime Electric C A N A D A PROVINCE OF PRINCE EDWARD ISLAND BEFORE THE ISLAND REGULATORY AND APPEALS COMMISSION IN THE MATTER of Section 20 of the Electric Power Act (R.S.P.E.I. 1988, Cap. E- 4) and

More information

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017) NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. (0) 0 0 IN THE MATTER OF the Electrical Power Control Act,, SNL, Chapter E-. (the EPCA ) and the Public

More information

ASIAN DEVELOPMENT FUND (ADF) ADF XI REPLENISHMENT MEETING 7 9 March 2012 Manila, Philippines. Post-Conflict Assistance to Afghanistan

ASIAN DEVELOPMENT FUND (ADF) ADF XI REPLENISHMENT MEETING 7 9 March 2012 Manila, Philippines. Post-Conflict Assistance to Afghanistan ASIAN DEVELOPMENT FUND (ADF) ADF XI REPLENISHMENT MEETING 7 9 March 2012 Manila, Philippines Post-Conflict Assistance to Afghanistan February 2012 ABBREVIATIONS ADB Asian Development Bank ADF Asian Development

More information

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and

Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section and Application for Commission Approval to Construct a Generating Station Pursuant to Public Utilities Article Section 7-207.1 and 7-207.2 APPLICABILITY The Public Service Commission of Maryland ( Commission

More information

PEC is continuously experiencing growth in its service territory. Weather and member growth are primary drivers for increased kwh sales.

PEC is continuously experiencing growth in its service territory. Weather and member growth are primary drivers for increased kwh sales. Year System Value Median NBR Rank Median NBR Rank Median NBR Rank Median NBR Rank Median NBR Rank Comment BASE GROUP (RATIOS 1-5) RATIO 1 --- AVERAGE TOTAL CONSUMERS SERVED 2010 234,676 13,250 815 1 19,413

More information

Future Funding The sustainability of current transport revenue tools model and report November 2014

Future Funding The sustainability of current transport revenue tools model and report November 2014 Future Funding The sustainability of current transport revenue tools model and report November 214 Ensuring our transport system helps New Zealand thrive Future Funding: The sustainability of current transport

More information

Direct Energy Regulated Services

Direct Energy Regulated Services Decision 23986-D01-2018 Application for True-Up of the 2017 and 2018 Interim Rates for the Default Rate Tariff and the Regulated Rate Tariff December 4, 2018 Alberta Utilities Commission Decision 23986-D01-2018

More information

216B.164 COGENERATION AND SMALL POWER PRODUCTION.

216B.164 COGENERATION AND SMALL POWER PRODUCTION. 116C.7792 SOLAR ENERGY INCENTIVE PROGRAM. (a)the utility subject to section 116C.779 shall operate a program to provide solar energy production incentives for solar energy systems of no more than a total

More information

AMAG posts record shipments in 2013; dividend recommendation of 0.60 EUR per share unchanged on last year

AMAG posts record shipments in 2013; dividend recommendation of 0.60 EUR per share unchanged on last year Ranshofen, 28 February 2014 AMAG posts record shipments in 2013; dividend recommendation of 0.60 EUR per share unchanged on last year Shipments at an all-time high of 351,700 tonnes (t) in 2013, compared

More information

RATE 765 RENEWABLE FEED-IN TARIFF

RATE 765 RENEWABLE FEED-IN TARIFF NORTHERN INDIANA PUBLIC SERVICE COMPANY Original Sheet No. 104 TO WHOM AVAILABLE Sheet No. 1 of 12 This Rate Schedule is a voluntary offer available to any Customer that operates within the Company s service

More information

CASE No. 35 of In the matter of

CASE No. 35 of In the matter of Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005 Tel. 022 22163964/65/69 Fax 22163976 Email: mercindia@merc.gov.in Website:

More information

Transportation Charging Statement

Transportation Charging Statement Transportation Charging Statement Revision One Effective: 29 th June 2012 Transportation Charges for Natural Gas Distribution Networks BK-REL-IG-0020 GPL Transportation Charges Statement Rev 01 Page 1

More information

FISCAL YEAR ENDED MARCH 2011 FINANCIAL RESULTS

FISCAL YEAR ENDED MARCH 2011 FINANCIAL RESULTS FISCAL YEAR ENDED MARCH 211 FINANCIAL RESULTS Mazda Motor Corporation April 28, 211 Mazda MINAGI 1 PRESENTATION OUTLINE Highlights Fiscal Year Ended March 211 Results In Summary Question & Answer Session

More information

POLICY NUMBER: SUPERSEDES: C462A. Planning and Development Department DATE: Business Revitalization Zone Establishment and Operation

POLICY NUMBER: SUPERSEDES: C462A. Planning and Development Department DATE: Business Revitalization Zone Establishment and Operation CITY POLICY POLICY NUMBER: C462B REFERENCE: C462A City Council 1996 05 07 C462 City Council 1992 07 14 ADOPTED BY: City Council SUPERSEDES: C462A PREPARED BY: Planning and Development Department DATE:

More information

KBA Kraftfahrt-Bundesamt

KBA Kraftfahrt-Bundesamt Kraftfahrt-Bundesamt (Federal Motor Transport Authority) Your central provider of services and information concerning vehicles and their users Vehicle Technology - Information Sheet on Approvals for New

More information

SASOL INZALO AND SASOL KHANYISA FREQUENTLY ASKED QUESTIONS

SASOL INZALO AND SASOL KHANYISA FREQUENTLY ASKED QUESTIONS SASOL INZALO AND SASOL KHANYISA FREQUENTLY ASKED QUESTIONS 15 November 2017 1 SASOL INZALO AND SASOL KHANYISA QUESTIONS AND ANSWERS TABLE OF CONTENTS Top 10 Sasol Inzalo Questions 6 1. How has Sasol Inzalo

More information

MONRO MUFFLER BRAKE, INC. PROVIDES FOURTH QUARTER AND FISCAL 2017 FINANCIAL RESULTS

MONRO MUFFLER BRAKE, INC. PROVIDES FOURTH QUARTER AND FISCAL 2017 FINANCIAL RESULTS CONTACT: John Van Heel Chief Executive Officer (585) 647-6400 Robert Gross Executive Chairman (585) 647-6400 FOR IMMEDIATE RELEASE Brian D Ambrosia Senior Vice President Finance Chief Financial Officer

More information

best to you all Gail Carbiener Page 1 of 5

best to you all Gail Carbiener Page 1 of 5 Please accept this attachment as my up dated response to the B2H DEIS. If this is not acceptable, please let me know. Nice meeting last Monday in Boardman. 300316 best to you all Gail Carbiener 2 Page

More information