Approved Contractor Construction e-guide Residential Commercial

Size: px
Start display at page:

Download "Approved Contractor Construction e-guide Residential Commercial"

Transcription

1 Approved Contractor Construction e-guide Residential Commercial Clark Public Utilities PO Box 8900 Vancouver, WA 98668

2 (PAGE 2) TABLE OF CONTENTS PAGE Trenching 3 Wire 8 Single-Phase Transformer Set 13 Secondary Pedestal 36 Lighting 42 Metering 45 Three-Phase Transformer Set 55 Padmount Transformers 60 Single-Phase J-Box 62 Three-Phase J-Box 64

3 (PAGE 3)

4 (PAGE 4)

5 (PAGE 5)

6 (PAGE 6)

7 (PAGE 7)

8 (PAGE 8)

9 (PAGE 9)

10 (PAGE 10)

11 (PAGE 11)

12 (PAGE 12)

13 (PAGE 13)

14 (PAGE 14)

15 (PAGE 15)

16 (PAGE 16)

17 (PAGE 17)

18 (PAGE 18)

19 (PAGE 19)

20 (PAGE 20)

21 (PAGE 21)

22 (PAGE 22)

23 (PAGE 23)

24 (PAGE 24)

25 (PAGE 25)

26 (PAGE 26)

27 (PAGE 27)

28 (PAGE 28)

29 (PAGE 29)

30 (PAGE 30) Clark Public Utilities Commercial Electric Service Handbook Transformer location and access Underground electrical facilities must be readily accessible by the utility during construction and for future operation and maintenance. The area around padmounted electrical equipment must provide a clear and level working space and remain free from obstructions such as landscaping, poles, retaining walls, structures, fences, etc. All transformers and padmounted equipment are to be located: Within 10 feet of a drivable surface but not closer than 5 feet (Figure 3). With the front of the equipment (door and lock side) facing toward the drivable surface. With the transformer pad parallel to the edge of the drivable surface. Allowing 10 feet of clearance in front and 3 feet from the back and sides of the equipment (Figure 3). At least 2 feet from a sidewalk for pedestrian safety. Figure 3 Commercial padmounted transformer location and access VIEW FROM ABOVE 3 ft. minimum of clear working space from back and sides 2 ft. minimum of clear working space from a sidewalk to front of transformer pad sidewalk transformer door and lock edge of transformer pad 5 ft. minimum to 10 ft. maximum of clear working space from drivable surface to front of transformer pad curb position transformer with door and lock facing the drivable surface drivable surface Chapter 3: Commercial Underground Services / January

31 (PAGE 31) Clark Public Utilities Commercial Electric Service Handbook Transformer safety clearances Clearances from padmounted transformers to structures are measured from the nearest metal portion of the transformer to the structure or any overhang. The clearance from a building is 10 feet if the building has combustible walls, and 3 feet if the building has non-combustible walls as shown in Figure 4. Table 4 provides additional safety clearances that apply to any oil-filled electrical equipment. Figure 4 Commercial padmounted transformer minimum safety clearances non-combustible structure and roof combustible structure and roof 3 ft. min. transformer 10 ft. minimum 3 ft. 10 ft. transformer operable window or other opening 10 ft. door or other opening 10 ft. 10 ft. fire escape fuel dispensing facilities 20 ft. 15 ft. gas meter 6 ft. hydrant transformer 10 ft. fuel storage 18 Chapter 3: Commercial Underground Services / January 2011

32 (PAGE 32) Clark Public Utilities Commercial Electric Service Handbook If the distance between the corner posts exceeds 5 feet, a removable center post is required (Figure 5). If a removable center post is installed, the threaded joint requires treatment with an anti-seizing agent. Paint exposed section of post traffic yellow. Figure 5 Guard post (bollard) installation for commercial transformers FRONT VIEW do not fill center post with concrete domed concrete 3 ft. minimum coupling FINAL GRADE 2 ft. concrete fill 4 in. galvanized/steel pipe, concrete filled removable center post, as required 4 in. galvanized/steel pipe, concrete filled VIEW FROM ABOVE edge of transformer pad edge of transformer commercial transformer 18 in. minimum on 45 door and lock removable center post, as required NOTE: Additional guard posts may be required at back and sides of transformer. 20 Chapter 3: Commercial Underground Services / January 2011

33 (PAGE 33)

34 (PAGE 34)

35 (PAGE 35)

36 (PAGE 36)

37 (PAGE 37)

38 (PAGE 38)

39 (PAGE 39)

40 (PAGE 40) Clark Public Utilities Residential Electric Service Handbook Figure 7 Typical secondary trenches to underground utility sources secondary trench to padmount transformer #### FRONT OF TRANSFORMER transformer number transformer lock NOTE: Clark Public Utilities personnel will route wire into energized facilities. leave 8 ft. tail of triplex wire at transformer use the utility provided white paint mark to position trench (or use transformer lock if mark is not shown) 2 ft. secondary trench to secondary pedestal view from side 2 ft. to 2-1/2 ft. open NOTE: Clark Public Utilities personnel will route wire into energized facilities. 8 ft. of makeup wire 18 in. minimum cover to top of conduit view from back 24 in. trench depth 2 ft. bushing required, do not permanently attach to conduit 6 in. conduit aimed at center of pedestal (leave 2 feet between end of conduit and pedestal) Chapter 3: Underground Secondary Services / February

41 CHAPTER3 Clark Public Utilities Residential Electric Service Handbook (PAGE 41) Underground Secondary Services Preparing for the installation Typically, an extension of secondary 120/240 volt electrical service is all that is required if less than 200 feet of secondary voltage wire is needed to connect the meter socket to a transformer. For homes with large motor loads such as multiple heat pumps or dryers, air conditioning units, etc., this distance may be less. All single-family residences not located within 200 feet of existing primary require an underground primary line extension to place a transformer closer to the structure. See Chapter 4, Primary Line Extensions, for more information on this type of installation. The following checklist will assist in preparing a project for the installation of secondary underground electric service. After these items have been completed, Clark Public Utilities will connect the service and set the meter (Figure 4). Figure 4 Typical underground secondary service meter base (ground per NEC) secondary pedestal dig out and expose back of pedestal 2 ft. to 2-1/2 ft. open conduit aimed at center of pedestal 8 ft. of makeup wire 6 ft. maximum 5 ft. preferred 5 ft. minimum 2 in. schedule 80 PVC service entrance equipment 18 in. minimum icover to top iof conduit 24 in. trench depth bushing required, do not permanently attach to conduit 6 in. 3 in. schedule 40 PVC 3 in. to 2 in. schedule 40 reducer 24 in. radius, 2 in. schedule 40, 90 degree elbow Chapter 3: Underground Secondary Services / February

42 (PAGE 42)

43 (PAGE 43)

44 (PAGE 44)

45 Meter Department Pre-Made Wire Bundles All are solid copper wire (PAGE 45) 1 Potentials #14 gauge Black, Green, White Currents #12 gauge Blue, Yellow, Brown 3 Potentials #14 gauge Black, Green, White, Orange Currents #12 gauge Blue, Yellow, Brown, Red Note: Maximum distance for #12 current wire is 35 feet one way to meet burden of 0.2 on rating factor 4 C.T. s. For C.T. conduit run over 35 feet use #10 current wire to a maximum of 60 feet for a burden of 0.2. If a longer conduit run than 60 feet is unavoidable see meter department for C.T. and burden chart s and C.T. sizing. DISTANCE CHART CT TO METER DISTANCE TOTAL W IRE DISTANCE SOLID STATE METER ADD ELECTRICAL MECHANICAL <MISC> <TEST SW> #12 OHM PER 10' 35' 50' 70' 70' 100' 140' ' 200' ' 250' ' 300' ' 120' #10 OHM PER 10' 75' 80' 100' 150' 160' 200' ' 400'

46 (PAGE 46)

47 (PAGE 47)

48 Clark Public Utilities Metering Requirements Commercial Applications (PAGE 48) Source Voltage Ampacity Reference Circle AW Part Number 120 Volts 1 2 Wire 120/240Volt 1 3Wire 120/240Volt Amps 324N, 1 3Wire 324NF 120/240Volt Over Wire Amps 240/480Volt 1 3Wire 240/480Volt Over Wire Amps 120/208Volt 3Wire Network 120/208Volt Over 200 3Wire Network Amps 240Volt 3 3Wire Delta 120/208Volt 3 4Wire Wye 120/208Volt Over Wire Wye Amps 240/120Volt 3 4Wire Delta 240/120Volt Over Wire Delta Amps 277/480Volt 3 4Wire Wye 277/480Volt Over Wire Wye Amps 480Volt 3 3Wire Delta 480Volt 3 3Wire Delta Meter Diagram Numbers Circle AW part numbers are for cross reference only. All Commercial current transformer cabinets shall have hinged doors. CURRENT TRANSFORMER CABINET DIMENSIONS, Number of Terminals CT MOUNTING BASE Amperes Dimensions Circle AW or Equivalent 200 Amps- 400 Amps 1 24 X 30 X HAL (LUG LUG) 401 Amps- 800 Amps 1 30 X 36 X HEL (LUG LUG) 200 Amps- 400 Amps 3 30 X 36 X HAL or 6067-HAL 401 Amps- 800 Amps 3 36 X 48 X HEL or 6067-HEEL See EUSERC Spec 328B & 329B Over 800 Amps Switchgear Required Maximum wire size 600 MCM per lug or parallel per EUSERC SPEC. & UL label Rev 4: Changed blocks with a *. Bypass Provision Required Amps U121314* MD01 4 Yes No Amps U264 MD02 4 Yes No MD03 4 Yes No MD10 MD11 6 No Yes Amps 124TB MD02 4 Yes No MD05 Dmd MD10 6 No Yes MD Amps 125TB MD04 5 Yes No MD12 8 No Yes Amps 125TB MD06 5 Yes No Amps 127TB MD07 7 Yes No MD13 13 No Yes Amps 127TB MD08 7 Yes No MD14 13 No Yes Amps 127TB MD07 7 Yes No MD13 13 No Yes Amps 125TB MD06 5 Yes No Over 200 Amps MD12 8 No Yes Test Switch Required

49 Source Voltage Ampacity Reference Circle AW Part Number 120 Volts 1 2 Wire 120/240Volt 1 3Wire 120/240Volt 1 3Wire Amps 324N, 120/240Volt 1 3Wire Clark Public Utilities Metering Requirements Residential Applications Meter Diagram Numbers Number of Terminals Bypass Provision Required Amps 011 MD01 4 No No Amps 204, U204 MD02 4 No No Over 400 Amps 324NF UO11, 011, 925 or 926 MD03 4 Yes No MD09 MD11A 5 or 6 No No Test Switch Required (PAGE 49) Circle AW part numbers are for cross reference only. CURRENT TRANSFORMER CABINET DIMENSIONS, CT MOUNTING BASE Amperes Dimensions Circle AW or Equivalent 200 Amps- 400 Amps 1 Window 24 h X 32 w X 9 d PED *401 Amps- 800 Amps 1 Buss Mt. 24 h X 30 w X 11 d hinged door 6019-HAL (LUG LUG) 200 Amps- 400 Amps 3 Window 30 h X 36 w X 11 d PED *401 Amps- 800 Amps 3 Buss Mt. 36 h X 48 w X 11 d hinged door 6019-HEL (LUG-LUG) * Optional Notes: 1. CT Metering for Amp panels required pre-approval from Clark Public Utilities 2. All CT cans shall be mounted outside. Rev 2: Add optional CT cabinet dimensions and notes.

50 (PAGE 50) Clark Public Utilities Commercial Electric Service Handbook Figure 8 Typical amp single-phase current transformer (CT) metering 30 in. wide conduit 35 ft. maximum permanent load and line identifying labels corresponding to appropriate connections Load Test Switch 36 in. tall Line 1 in. electrical conduit ground per NEC 6 ft. maximum 5 ft. preferred 5 ft. minimum hinged door required, hinges on opposite side of CT enclosure from meter socket ground per NEC 18 in. minimum 11 in. deep FINAL GRADE CT mounting base Installation requirements for current transformer mounting bases are as follows (Figure 9): Mounting base is rated for a minimum of 50k amps fault current. Line and load side terminations require two bolts per connector and two bolts on the neutral bus. The customer furnishes all lugs and terminates both load and line side conductors to the bus. A 4-wire delta service requires orange marking of the high leg. Switchboard metering Switchboard metering is required for three-phase services over 800 amps. At the customer s option, this type of metering may be installed for services sized 201 to 800 amps. The customer-installed equipment must be EUSERC-approved. Chapter 4: Commercial Metering / January

51 (PAGE 51) Clark Public Utilities Commercial Electric Service Handbook Figure 9 Commercial three-phase CT mounting base 5 in. minimum two CT mounting bolts, 6 places typical 1-3/8 in. 7/8 in machine screw and washer drilled and tapped into bus N 1-1/2 in. 8-1/8 in. 1-3/8 in. CT CT CT 3/4 in. 7 in. minimum 7 in. minimum bus marking CT typical 3 locations insulating support 1/4 in. 3-5/16 in. insulating barrier NOTE: For additional information see EUSERC drawing 329B. All customer-installed switchboards require a: Current transformer (CT) mounting base. Service section. Set of bus bars/links. Panel(s). Meter base with provisions for a test switch. Means for locking the meter enclosure with independent 24-hour access to utility personnel. Concrete mounting pad. Case ground as required per the NEC. NOTE: Customers requiring more than 480 volts of service will have primary metering. Ownership and maintenance agreements for primary metered services will be mutually agreed upon with Clark Public Utilities. 34 Chapter 4: Commercial Metering / January 2011

52 (PAGE 52) Clark Public Utilities Commercial Electric Service Handbook Multiple metered services Commercial tenant spaces Non-residential multiple meter installations such as ganged, modular and switchboard metering have the following requirements: Spacing to socket centers a minimum of 3 feet and a maximum of 6 feet above the finished grade or the floor of an approved equipment room (factory-built meter packs require meters installed at least 3 feet above the ground). Meter packs with more than six meters require a main disconnect per the NEC (Figure 10). All self-contained meter bases require a safety socket or a manual link bypass. Each metered service is permanently labeled. (See Multiple meter labeling section for additional information.) Panel covers must be secured prior to connection of the service. Figure 10 Multiple meter socket detail meter and corresponding disconnect labeled with unit number using minimum 1/2 in. letters 7-1/2 in. min. hard plastic, metal or phenolic block labels with raised or engraved letters disconnect required if more than six meters Main disconnect /2 in. min. address label with minimum 1 in. letters 123 Clark St Bldg B service entrance floor or finished grade 3 ft. min. 6 ft. max. HOUSE building meter labeled HOUSE with minimum 1/2 in. letters 6 ft. maximum 5 ft. preferred 5 ft. minimum NOTE: See page 31 for meter base bypass requirements. Chapter 4: Commercial Metering / January

53 (PAGE 53)

54 (PAGE 54)

55 (PAGE 55)

56 (PAGE 56)

57 (PAGE 57)

58 (PAGE 58)

59 (PAGE 59)

60 (PAGE 60)

61 (PAGE 61)

62 (PAGE 62)

63 (PAGE 63)

64 (PAGE 64)

65 (PAGE 65)

66 (PAGE 66)

Clark Public Utilities Commercial Electric Service Handbook. This page left blank intentionally.

Clark Public Utilities Commercial Electric Service Handbook. This page left blank intentionally. This page left blank intentionally. 38 Chapter 4: Commercial Metering / January 2011 APPENDIX Glossary Approval Acceptable to the authority having jurisdiction. Associated equipment As related to metering

More information

10 Commercial, Industrial, Agricultural Services

10 Commercial, Industrial, Agricultural Services 10 Commercial, Industrial, Agricultural Services This section describes the Power Company requirements for commercial, industrial, and agricultural services. This section covers single phase and three

More information

Commercial Electric Service Handbook

Commercial Electric Service Handbook Commercial Electric Service Handbook January 2011 CONTACTS Clark Public Utilities: Website........................................... www.clarkpublicutilities.com Construction Services department (To initiate

More information

9. Non-Residential Services (Commercial, Industrial, and Agricultural)

9. Non-Residential Services (Commercial, Industrial, and Agricultural) Section 9 2016 Electric Service Requirements, 3rd Edition Section 9 Non-Residential Services Directory Page 9.1 General Requirements 68 9.2 Direct-Connect Metering, Single Installations 69 9.3 Direct-Connect

More information

COMMERCIAL QUICK REFERENCE

COMMERCIAL QUICK REFERENCE COMMERCIAL QUICK REFERENCE PROVO CITY POWER STANDARDS ELECTRICAL ENGINEERING UPDATED: 2016 SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTIFICATION. 18" MIN. OF TAIL. (NEUTRAL CONDUCTOR MUST BE WHITE OR

More information

Metering and Service Installation:

Metering and Service Installation: Table of Contents 1. Metering Installation Requirements, General... 1 2. Type of Service... 2 3. Definitions... 2 4. Who Provides Metering Equipment?... 2 5. Establishment of Service... 2 6. Meter Access...

More information

D9-3. No. WIRING DIAGRAM CONNECTIONS FOR UNDERGROUND SELF CONTAINED METERS JRH JED krich95 LINE LINE ABCN SOURCE SOURCE GROUND GROUND STUD STUD SOURCE

D9-3. No. WIRING DIAGRAM CONNECTIONS FOR UNDERGROUND SELF CONTAINED METERS JRH JED krich95 LINE LINE ABCN SOURCE SOURCE GROUND GROUND STUD STUD SOURCE SOURCE 20V 240V STUD (PER NEC) A customer supplied and installed teaser wire is required from the neutral lug to a 5th terminal mounted on the left side of the meter block between the line and load terminals.

More information

PUBLIC UTILITY DISTRICT NO. 1 OF LEWIS COUNTY METERING SPECIFICATIONS

PUBLIC UTILITY DISTRICT NO. 1 OF LEWIS COUNTY METERING SPECIFICATIONS PUBLIC UTILITY DISTRICT NO. 1 OF LEWIS COUNTY METERING SPECIFICATIONS 1. General Metering Requirements a. Interpretation The District s metering requirements shall not be interpreted to conflict with the

More information

AMENDMENT ELECTRIC SERVICE MANUAL 2014

AMENDMENT ELECTRIC SERVICE MANUAL 2014 AMENDMENT (Pages 20,43,50,72,74,,76,78,83,86,99) ELECTRIC SERVICE MANUAL 2014 Effective April 1, 2015 18-7 6.0 SERVICE AND SERVICE ENTRANCES (General), Continued Conductor Sizing It is recommended that

More information

Customer Requirements Meter Socket Configurations

Customer Requirements Meter Socket Configurations Application Information on meter socket configurations available from Tacoma Power. For enclosed meter pedestals, see standard C-MR-0020 Customer Requirements, Enclosed Meter Pedestal. General Requirements

More information

NEW SERVICE HANDBOOK COMMERCIAL & IRRIGATION SUPPLEMENT

NEW SERVICE HANDBOOK COMMERCIAL & IRRIGATION SUPPLEMENT NEW SERVICE HANDBOOK COMMERCIAL & IRRIGATION SUPPLEMENT Meter Installations There are three basic ways to measure electricity consumption: Small and medium services are metered directly using direct connect

More information

Pentahead bolts See note 2. Conduit run as specified. Company facility. Refer to drawing SS8.6-2 or SS8.6-3 STANDARD SERVICE INSTALLATION

Pentahead bolts See note 2. Conduit run as specified. Company facility. Refer to drawing SS8.6-2 or SS8.6-3 STANDARD SERVICE INSTALLATION PULL BOX F SECONDARY SYSTEM Typical grade Pentahead bolts See note 2 Conduit run as specified Plastic or fiberglass for grass areas or Polymer concrete for light duty areas (see notes 2, 3, & 4) Company

More information

Associated equipment As related to metering equipment: such as the current transformers, CT wiring and test switches.

Associated equipment As related to metering equipment: such as the current transformers, CT wiring and test switches. APPENDIX Glossary Approval Acceptable to the authority having jurisdiction. Assessor s Parcel Number (APN) Identifying number assigned by the county assessor s office to each taxable building lot in the

More information

RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS SECTION VI RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS

RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS SECTION VI RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS SECTION VI SERVICE REQUIREMENTS This section discusses the requirements for establishing electric service to new residential subdivisions in Palo Alto. Subdivisions are normally constructed on dedicated

More information

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS Prepared by: ABB1 AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS 05619 Asset Type: Electric Metering Function: Design and Construction Issued by: Lisseth Villareal (LDV2) Date: 07-31-15 Rev. #10: This

More information

Engineering Service Specifications. Commercial Single-Phase Current Transformer Metering Schemes

Engineering Service Specifications. Commercial Single-Phase Current Transformer Metering Schemes Engineering Service Specifications Commercial Single-Phase Current Transformer Metering Schemes Specifications for Commercial Underground Current Transformer Metering Requirements for a Single-Phase Customer

More information

SINGLE PHASE WIRING SPECIFICATIONS

SINGLE PHASE WIRING SPECIFICATIONS SINGLE PHASE WIRING SPECIFICATIONS 1-866-MEC-ELEC (1-866-632-3532) Office Locations: Hondo Office 237 Hwy 173 N Hondo, TX 78661-0370 Fax 830.426.3335 Dilley Office 1718 W. FM 117 Dilley, TX 78017 Fax 830.965.1425

More information

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION Roseville Electric SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION REVISED 04/25/18 Specifications for Residential Construction Revision List REVISION Date Page No. Description 03/20/00 6.1-6.2 Added Armorcast

More information

Meter Standards COMMERCIAL. Metering Guidelines for Electric Service. March 28, 2014

Meter Standards COMMERCIAL. Metering Guidelines for Electric Service. March 28, 2014 Meter Standards COMMERCIAL Metering Guidelines for Electric Service March 28, 2014 13315 Goodnough Drive NW Gig Harbor WA 98332-8640 Phone (253) 857-1547 Fax (253) 857-1557 www.penlight.org Commercial

More information

SECTION 500 METERING AND ASSOCIATED EQUIPMENT

SECTION 500 METERING AND ASSOCIATED EQUIPMENT SECTION 500 METERING AND ASSOCIATED EQUIPMENT 500.0 General Meter sockets shall be provided, installed and maintained by Customer. When the ratings of meter sockets are exceeded, transockets shall be used.

More information

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION Roseville Electric SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION REVISED 10/03/17 Specifications for Residential Construction Revision List REVISION Date Page No. Description 8/18/09 T.O.C., 8.1-8.1.5 &

More information

THREE PHASE WIRING SPECIFICATIONS

THREE PHASE WIRING SPECIFICATIONS THREE PHASE WIRING SPECIFICATIONS 1-866-MEC-ELEC (1-866-632-3532) Office Locations: Hondo Office 237 Hwy 173 N Hondo, TX 78661-0370 Fax 830.426.3335 Dilley Office 1718 W. FM 117 Dilley, TX 78017 Fax 830.965.1425

More information

7 Single Family Service

7 Single Family Service 7 Single Family Service 7. General The location of the service entrance on the Customer s premises is an important consideration. For clearance and location information see section 5 (Clearances). Consult

More information

UNDERGROUND SERVICE. Items to consider. There will be charges from ComEd if you convert from overhead to underground service.

UNDERGROUND SERVICE. Items to consider. There will be charges from ComEd if you convert from overhead to underground service. UNDERGROUND SERVCE tems to consider f your trenching route has to be dug by hand, or if a cable must be installed under a paved surface, additional charges apply. f your service cable has to be moved later

More information

Meter Installation. -and- Padmount Transformer Guide

Meter Installation. -and- Padmount Transformer Guide Meter Installation -and- Padmount Transformer Guide Feb. 2016 METERING REQUIREMENTS The following information shall be used as a guide for installing metering equipment. A self-contained meter has all

More information

Table of Contents. Electrical Service Requirements. 1. General Requirements

Table of Contents. Electrical Service Requirements. 1. General Requirements Table of Contents 1. General Requirements 1.1 General Definition.................................................... 1 1 1.2 Booklet Purpose and Organization....................................... 1-1

More information

UNDERGROUND SERVICES - SECONDARY

UNDERGROUND SERVICES - SECONDARY UNDERGROUND SERVICES - SECONDARY Contents - Underground Services... U-1 General Requirements for Underground Service...U-2 Names of Parts for Underground Service... U-3 Service Termination in a Service

More information

Electric & Gas Service Requirements (Greenbook) Overview

Electric & Gas Service Requirements (Greenbook) Overview INTRODUCTION The Greenbook contents and standard documents are updated regularly to provide users with the most current information possible. In conjunction with this effort, the 2016 Greenbook was reviewed

More information

PEU reserves the right to determine all meter locations. Only authorized PEU personnel will determine this location.

PEU reserves the right to determine all meter locations. Only authorized PEU personnel will determine this location. I N T R O D U C T I O N - M-1 RIGHTS: PEU reserves the right to determine all meter locations. Only authorized PEU personnel will determine this location. NOTIFICATION: Customers planning to install or

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION Installing new electric service is a joint project between the customer and the power company. The power company is responsible for bringing power to the site, for installing the

More information

Section 6 Electric Metering: Residential

Section 6 Electric Metering: Residential Section 6 Electric Metering: Residential 6.1. Scope This section provides specific information for residential metering that is not covered by the basic requirements in Section 5, Electric Metering: General.

More information

34.00 METERING GENERAL LABELING MULTIPLE METER ENCLOSURES ON A SINGLE PREMISE

34.00 METERING GENERAL LABELING MULTIPLE METER ENCLOSURES ON A SINGLE PREMISE 4. METERING GENERAL LABELING MULTIPLE METER ENCLOSURES ON A SINGLE PREMISE 4.-4 4. SELF-CONTAINED METERING, SINGE-PHASE INSTALLATION DETAILS /4 VOLT SINGLE-PHASE UNDERGROUND RESIDENTIAL SERVICE AND METER

More information

Customer Requirements Downtown Secondary Network Service

Customer Requirements Downtown Secondary Network Service Application This standard describes the limitations and requirements for receiving service from the Tacoma Power secondary network system within the City of Tacoma downtown core area. In This Standard

More information

RESIDENTIAL. Metering Guidelines for Electric Service. Meter Standards. October 25, 2017

RESIDENTIAL. Metering Guidelines for Electric Service. Meter Standards. October 25, 2017 Meter Standards RESIDENTIAL Metering Guidelines for Electric Service October 25, 2017 13315 Goodnough Drive NW Gig Harbor WA 98332-8640 Phone (253) 857-1547 Fax (253) 857-1557 www.penlight.org Residential

More information

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016

ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016 DISTRIBUTED GENERATION CHAPTER 5 500. SCOPE This chapter includes distributed or customer-owned generation connected in parallel and operating with Alliant Energy s electric distribution system. For all

More information

Electric Service Requirements & Guidelines

Electric Service Requirements & Guidelines Electric Service Requirements & Guidelines Montana Service Area September 2011 NORTHWESTERN ENERGY Montana Service Area ELECTRIC SERVICE REQUIREMENTS AND GUIDELINES CONTENTS I. GENERAL INFORMATION 1.01

More information

Parkland Light & Water Co. ELECTRIC SERVICE REQUEST AND METER STANDARDS

Parkland Light & Water Co. ELECTRIC SERVICE REQUEST AND METER STANDARDS Parkland Light & Water Co. ELECTRIC SERVICE REQUEST AND METER STANDARDS Revised: January, 2017 Contents SERVICE REQUEST FORMS RECEIPT OF ELECTRIC SERVICE REQUEST AND METER STANDARDS ELECTRIC SERVICE REQUEST

More information

STOUGHTON UTILITIES ELECTRIC SERVICE RULES AND INFORMATION

STOUGHTON UTILITIES ELECTRIC SERVICE RULES AND INFORMATION CHAPTER 1 - GENERAL INFORMATION 100. Purpose 101. Codes and rules 102. Continuity of service 103. Frequency, Voltage, and Amperage Limitations 104. High voltages 105. Unusual capacity requirements 106.

More information

7. Residential Single-Family and Duplex Buildings (Dwellings)

7. Residential Single-Family and Duplex Buildings (Dwellings) Sin g le -F a mily a n d Du p le x Bu ild in g s 2016 Electric Service Requirements, 2 nd Edition Section 7 Section 7 Residential Single-Family and Duplex Buildings (Dwellings) Directory Page 7.1 General

More information

CT Metering. CT Metering. Meter Mounting Equipment

CT Metering. CT Metering. Meter Mounting Equipment Single Meter Sockets, Without Bypass - CT Rated.................................. 67-68 Single Meter Sockets, CT Rated With Test Switch Bypass Provision............. 69-70 Meter Socket / Enclosure Combination

More information

Indianapolis Power & Light Company

Indianapolis Power & Light Company Indianapolis Power & Light Company Electric Service and Meter Manual The Electric Service & Meter Manual is not copyrighted and permission is hereby given to reproduce this document. However, the Indianapolis

More information

Approved Meter Sockets and Cabinets

Approved Meter Sockets and Cabinets Single Unit Residential Guide 1 PHASE, 120/240 VOLT SERVICES SERVICE CAPACITY OWNED METERING (Metering sockets and cabinets are supplied by Customer). Outdoor meter mounting height is 1730 mm ( 5 8 ) to

More information

Service Requirements

Service Requirements Service Requirements General Contact Idaho Power before beginning work on any new service. All meter installations must meet current electrical code requirements and display the proper electrical permit.

More information

Installing or Rebuilding Your Electric Service

Installing or Rebuilding Your Electric Service Installing or Rebuilding Your Electric Service 2 3 Contents Policies for New and Rebuilt Electric Service 2-4 Paperwork and fees...2 Five-year policy...3 Proposed route location and conditions...3 Construction

More information

OREGON TRAIL ELECTRIC CO-OP ELECTRIC SERVICE REQUIREMENTS & GUIDELINES

OREGON TRAIL ELECTRIC CO-OP ELECTRIC SERVICE REQUIREMENTS & GUIDELINES 10/12/2016 ARTICLE OREGON TRAIL ELECTRIC CO-OP ELECTRIC SERVICE REQUIREMENTS & GUIDELINES TABLE OF CONTENTS LOCATION OF OTEC OFFICES... IV OTEC SERVICE AREA... V SECTION I GENERAL INFORMATION 1.1 PURPOSE...

More information

10. METERING General Requirements

10. METERING General Requirements 10. METERING 10.1 General Requirements A. The Company will not supply service to a Customer whose wiring is designed for resale of electricity through submetering except for recreational campgrounds, marinas,

More information

SOUTHWEST LOUISIANA ELECTRIC MEMBERSHIP COORPORATION COMMERCIAL SERVICE REQUIREMENTS

SOUTHWEST LOUISIANA ELECTRIC MEMBERSHIP COORPORATION COMMERCIAL SERVICE REQUIREMENTS SOUTHWEST LOUISIANA ELECTRIC MEMBERSHIP COORPORATION COMMERCIAL SERVICE REQUIREMENTS November 17, 2016 Engineering Service Specifications Table of Contents Commercial Service Requirements SLEMCO Commercial

More information

RESIDENTIAL UNDERGROUND AND OVERHEAD SERVICE REQUIREMENTS SECTION II RESIDENTIAL UNDERGROUND AND OVERHEAD SERVICE REQUIREMENTS

RESIDENTIAL UNDERGROUND AND OVERHEAD SERVICE REQUIREMENTS SECTION II RESIDENTIAL UNDERGROUND AND OVERHEAD SERVICE REQUIREMENTS SECTION II This section discusses the City of Palo Alto's requirements for establishing electric service to new or upgraded residential installations. The same requirements apply to both underground and

More information

For Conduit Inspections

For Conduit Inspections Underground Conduit Standards - Table of Content 5/8/2017 Section S22 Underground Conduit Standard Index: Description: 00 Table of Content 01 General Notes 02 Definition of Terms 03 Primary Riser Conduit

More information

PERMANENT RESIDENTIAL UNDERGROUND SERVICE

PERMANENT RESIDENTIAL UNDERGROUND SERVICE CITY OF RICHLAND ENERGY SERVICES DEPARTMENT 505 Swift Boulevard, MS-21 Richland, WA 99352 Telephone (509) 942-7403 Fax (509) 942-7405 PERMANENT RESIDENTIAL UNDERGROUND SERVICE A. INTRODUCTION This guide

More information

320A Single Phase URD Meter Loop Installations

320A Single Phase URD Meter Loop Installations 320A Single Phase URD Meter Loop Installations Location: The meter loop shall be mounted on the side of the pedestal facing the consumer's lot. (The side being one of the four flat surfaces of the pedestal

More information

Service Requirements

Service Requirements Service Requirements General Contact Idaho Power before beginning work on any new service. All meter installations must meet current electrical code requirements and display the proper electrical permit.

More information

SALEM CITY POWER ELECTRICAL REQUIREMENTS & STANDARDS MANUAL

SALEM CITY POWER ELECTRICAL REQUIREMENTS & STANDARDS MANUAL SALEM CITY POWER DEPARTMENT TABLE OF CONTENTS Section 1 General Requirements Purpose...1.1 Codes and Ordinances...1.1 Changes or Conflicts in Requirements and Guidelines...1.1 Application for Service...1.2

More information

ELECTRICAL METERING RESIDENTIAL

ELECTRICAL METERING RESIDENTIAL ELECTRICAL METERING RESIDENTIAL 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 UNDERGROUND FED METER SOCKET (226-320 AMPS) 5.0 METER SOCKET (0-320 AMPS, 120/208V) 6.0 UNDERGROUND SERVICE W/CURRENT

More information

SECTION VII METERING INSTALLATIONS

SECTION VII METERING INSTALLATIONS SECTION VII METERING INSTALLATIONS 1. GENERAL Outdoor metering is required for all new service installations to one, two, and three family detached, semi-detached and row houses. 2. COMPANY FURNISHES AND

More information

New Service. From... BARRON. Spooner Office: P.O. Box 261 Spooner, WI Barron Office: P.O. Box 40 Barron, WI

New Service. From... BARRON. Spooner Office: P.O. Box 261 Spooner, WI Barron Office: P.O. Box 40 Barron, WI New Service Guidelines and Diagrams From... BARRON www.barronelectric.com email: janderson@barronelectric.com Barron Office: P.O. Box 40 Barron, WI 54812-0040 Spooner Office: P.O. Box 261 Spooner, WI 54801-0261

More information

GENERAL INFORMATION 1.01 PURPOSE

GENERAL INFORMATION 1.01 PURPOSE GENERAL INFORMATION 1.01 PURPOSE The purpose of this manual is to supply essential information to customers, employees, architects, engineers, contractors, and others concerned with electrical installations

More information

METERING REQUIREMENTS

METERING REQUIREMENTS METERING REQUIREMENTS KUA will not accept a non-securable service trough entrance. That is, all enclosed conductors prior to the meter (line side) will be securable by and accessible to KUA personnel only.

More information

OVERHEAD SERVICE. Items to consider

OVERHEAD SERVICE. Items to consider OVERHEAD SERVICE Items to consider The maximum length of the service wire from the ComEd pole to the point of attachment on your residence is 150 feet, if practical. Your service wire installation must

More information

Electric Service Requirements

Electric Service Requirements Electric Service Requirements Section V Commercial Industrial July 2007 ENGINEERING SPECIFICATION 620 S Street, P.O. Box 5830, Sacramento, CA 95852-830 The Power To Do More ṢM SM A registered service mark

More information

ELECTRIC SERVICE RULES UTILITY/CATV SERVICES Issued Jan 2016

ELECTRIC SERVICE RULES UTILITY/CATV SERVICES Issued Jan 2016 UTILITY/CATV SERVICES CHAPTER 9 900. GENERAL A. Alliant Energy receives many requests for electric service from other utilities; telephone, telecommunications companies, cable television, the Department

More information

ELECTRIC SERVICE MANUAL

ELECTRIC SERVICE MANUAL ELECTRIC SERVICE MANUAL Issued: November 2018 For the most current version of the Jo-Carroll Energy electric service manual please visit www.jocarroll.com TABLE OF CONTENTS Chapter 1. General Information...1

More information

WPS SERVICE MANUAL. Section 7 Clearances. 7-1 Basic Electric Clearances - Services Miscellaneous Clearances Antenna Clearances...

WPS SERVICE MANUAL. Section 7 Clearances. 7-1 Basic Electric Clearances - Services Miscellaneous Clearances Antenna Clearances... Revised 03/2016 Section 7 CLEARANCES Page 1 of 9 Section 7 Clearances 7-1 Basic Electric Clearances - Services... 2 7-2 Miscellaneous Clearances... 7 7-3 Antenna Clearances... 9 Revised 03/2016 Section

More information

TABLE OF CONTENTS. Important Notices Underground Plant Protection Information. Commercial/Industrial Information Sheet

TABLE OF CONTENTS. Important Notices Underground Plant Protection Information. Commercial/Industrial Information Sheet DRAWING NUMBER INTRODUCTORY INFORMATION Important Notices Underground Plant Protection Information Code Clearances Commercial/Industrial Information Sheet Work Management Customer Projects Engineering

More information

Revised: April 2018 ¹ SERVICE TO WIRELESS DEVICE ANTENNA ATTACHMENTS ON CUSTOMER SERVICE POLES (SHEET 1) CUSTOMER: 1. An overcurrent protective device including a disconnect switch shall

More information

SECTION 300 OVERHEAD SERVICE

SECTION 300 OVERHEAD SERVICE SECTION 300 OVERHEAD SERVICE 300.01 General Company provides, installs, and maintains service drop to point of delivery approved by Company. Customer provides point of attachment which is acceptable to

More information

NEW SERVICE HANDBOOK

NEW SERVICE HANDBOOK NEW SERVICE HANDBOOK LOCATING UNDERGROUND UTILITIES CHECK SHEET cut here Will you be working within ten feet of any overhead power lines? Yes No Type of work Work being done for County Nearest City Address

More information

Electric Service Standards

Electric Service Standards VI - 1 of 17 VI. METERING EQUIPMENT A. Equipment Furnished and Installed by FPL FPL provides and installs, at its expense, adequate metering instruments to measure the electric service used by the Customer.

More information

KIUC Service Installation Manual

KIUC Service Installation Manual KIUC Service Installation Manual Second Edition (November 2016) This manual provides the general requirements for electric service and metering for Kauaʻi Island Utility Cooperative ("KIUC") and is meant

More information

SECTION LOW VOLTAGE DISTRIBUTION EQUIPMENT

SECTION LOW VOLTAGE DISTRIBUTION EQUIPMENT SECTION 16400 LOW VOLTAGE DISTRIBUTION EQUIPMENT A. General 1. The University does not accept Series-Rated equipment for power distribution switchboards, distribution panels and branch circuit panelboards.

More information

CONTENTS BY CHAPTER. Chapter 2: COMPANY EQUIPMENT ON CUSTOMER PREMISES

CONTENTS BY CHAPTER. Chapter 2: COMPANY EQUIPMENT ON CUSTOMER PREMISES CONTENTS BY CHAPTER Chapter 1: GENERAL INFORMATION Chapter 2: COMPANY EQUIPMENT ON CUSTOMER PREMISES Chapter 3: SERVICE ENTRANCES Chapter 4: METERING INSTALLATION Chapter 5: CUSTOMER-INSTALLED SERVICE

More information

RESIDENTIAL NEW CONSTRUCTION PACKET CITY OF VERO BEACH UTILITIES. Important Notice to Builders/Contractors/Developers From Electrical Engineering

RESIDENTIAL NEW CONSTRUCTION PACKET CITY OF VERO BEACH UTILITIES. Important Notice to Builders/Contractors/Developers From Electrical Engineering 1036 20 TH ST. PO BOX 1389 VERO BEACH, FLORIDA 32961-1389 TELEPHONE: (772) 978-5100 FAX: (772) 978-5125 Important Notice to Builders/Contractors/Developers From Electrical Engineering You must contact

More information

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST Use & Identification of Grounded and Grounding Conductors YES NO N/A Grounded conductors are identifiable and distinguishable from all other conductors.

More information

SAFETY SOCKET BOX. Note 8 3" MIN. 3" Max. (200 A)

SAFETY SOCKET BOX. Note 8 3 MIN. 3 Max. (200 A) .&. SAFETY SOCKET BOX USE: 1 12/24V 1A & 2A 4 Terminal EUSERC Dwg. No's 34 & 35 (With Factory Installed Test-Bypass Facilities) Refer to SR-452 for the complete Front View Lower-Panel Removed Note 3 3"

More information

Electric Service Requirements

Electric Service Requirements Electric Service Requirements for Residential & Commercial Service Committed to safely and economically provide reliable energy and other services which bring value to its membership. ELECTRIC SERVICE

More information

Customer Guide to Electric Service Requirements

Customer Guide to Electric Service Requirements Customer Guide to Electric Service Requirements Tillamook People s Utility District Power Services Group 1115 Pacific Avenue Tillamook, Oregon 97141 OFFICE: 503.815.8629 FAX: 503.815.8648 TOLL FREE: 800.422.2535

More information

SERVICE REQUIREMENTS COMMERCIAL & INDUSTRIAL CUSTOMERS

SERVICE REQUIREMENTS COMMERCIAL & INDUSTRIAL CUSTOMERS ENERGY SERVICES ENGINEERING 840 Northgate Drive Telephone (509) 942-7403 Fax (509) 942-7405 P.O. Box 190 Richland, WA 99352 www.ci.richland.wa.us SERVICE REQUIREMENTS COMMERCIAL & INDUSTRIAL CUSTOMERS

More information

TEMPORARY SERVICE TABLE OF CONTENTS PUD SERVICE TERRITORY AND CONTACTS CHAPTER ONE - INTRODUCTION CHAPTER TWO - TEMPORARY OVERHEAD SERVICE

TEMPORARY SERVICE TABLE OF CONTENTS PUD SERVICE TERRITORY AND CONTACTS CHAPTER ONE - INTRODUCTION CHAPTER TWO - TEMPORARY OVERHEAD SERVICE Electrical Service Requirements TEMPORARY SERVICE TABLE OF CONTENTS PUD SERVICE TERRITORY AND CONTACTS CHAPTER ONE - INTRODUCTION Inspections and codes Underground Utility locates Meter socket requirements

More information

Generator Fire Safety: Generator assemblies should be located outside the building.

Generator Fire Safety: Generator assemblies should be located outside the building. SECTION 33 70 00 - ELECTRICAL DISTRIBUTION PACKAGED GENERATOR ASSEMBLIES Generator Fire Safety: Generator assemblies should be located outside the building. All fuel piping from the outside of the building

More information

Service Entrance Methods

Service Entrance Methods Service Section Typical switchboards consist of a service section, also referred to as the main section, and one or more distribution sections. The service section can be fed directly from the utility

More information

Portland General Electric. Electric Service Requirements 2018

Portland General Electric. Electric Service Requirements 2018 Portland General Electric 2018 January 2018 Copyright 2018 by Portland General Electric. All rights reserved. No part of this publication may be reproduced without the written permission of Portland General

More information

INTERMOUNTAIN RURAL ELECTRIC ASSOCIATION. Builder/Developer Information

INTERMOUNTAIN RURAL ELECTRIC ASSOCIATION. Builder/Developer Information INTERMOUNTAIN RURAL ELECTRIC ASSOCIATION Builder/Developer Information Revised October 2015 WELCOME TO INTERMOUNTAIN RURAL ELECTRIC ASSOCIATION We understand that obtaining electrical facilities is only

More information

CABINET - CURRENT TRANSFORMER Indoor - Outdoor 240 Volts Amperes Maximum

CABINET - CURRENT TRANSFORMER Indoor - Outdoor 240 Volts Amperes Maximum PAGE 1 OF 5 USE: 1. For commercial and industrial installations purchased and installed by the Customer. 2. For use on the following services: 1 phase 3 wire 240 volts, 3 phase 3 wire 240 volts, 3 phase

More information

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION 100 KVA AND LARGER (CONCRETE PADS ONLY) 27.05-01 CABLE AND CONDUIT ENTRANCE SINGLE-PHASE PAD-MOUNTED TRANSFORMER INSTALLATION

More information

Electric Service Guide. Commercial & Industrial

Electric Service Guide. Commercial & Industrial Electric Service Guide Commercial & Industrial January 1, 2017 Contact MID s Electric Engineering Department (electric.standards@mid.org) with any questions about this Service Guide. Check MID s website

More information

Requirements for Secondary Voltage Revenue Metering (750 V and less)

Requirements for Secondary Voltage Revenue Metering (750 V and less) Requirements for Secondary Voltage Revenue Metering (750 V and less) To view the latest revision of this document go to: http://www.bchydro.com/ext/metering/ January 28, 2010 Copyright 2008 by BC Hydro.

More information

Electric Service Guides 2017

Electric Service Guides 2017 Electric Service Guides 2017 Electric Service Guide Residential January 1, 2017 Contact MID s Electric Engineering Department (electric.standards@mid.org) with any questions about this Service Guide.

More information

CON EDISON EQUIPMENT

CON EDISON EQUIPMENT CON EDISON EQUIPMENT Con Ed Navtech Size Volts Amps List Spec. Cat. No Description Price 205 N-205 10x10x5 100 $72.00 205 RTN-205 10x10x5 100 190.00 215 N-215 24x12x8 200 144.00 215 RTN-215 24x12x8 200

More information

ENTRANCE EQUIPMENT ER D PAGE 1 OF 5

ENTRANCE EQUIPMENT ER D PAGE 1 OF 5 PAGE 1 OF 5 USE: Requirements for entrance equipment. PREVIOUS REVISION 07-01-98 ORIGINATED 03-94 PREVIOUS NUMBER ER 100 (12-01-81) LATEST REVISION: Updated meter socket labeling specification and instrument

More information

2. DEFINITIONS. 2.3 APPROVED Acceptable to the authority enforcing the National Electric Code

2. DEFINITIONS. 2.3 APPROVED Acceptable to the authority enforcing the National Electric Code 2. DEFINITIONS 2.1 ACCEPTABLE Acceptable to the Company. 2.2 ADVANCED METER A meter that is capable of remote reading, and is capable of storing electric consumption data at specified time intervals of

More information

SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING

SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING Obtain acceptance and specific details from the local Company office. 1. Service entrance duct (see Note 1). Company

More information

A. Submit manufacturer's literature and technical data before starting work.

A. Submit manufacturer's literature and technical data before starting work. SECTION 16425 SWITCHBOARD PART 1 GENERAL 1.01 SUMMARY A. Related Section: 1. 16450 - Grounding. 1.02 SUBMITTALS A. Submit manufacturer's literature and technical data before starting work. B. Submit Shop

More information

Pretest Module 24 Three-phase Service Entrance

Pretest Module 24 Three-phase Service Entrance Pretest Module 24 Three-phase Service Entrance 1. What is the most widely used three-phase service entrance system? 2. What are the three most common voltage combinations for three-phase, four-wire systems?

More information

SPRINGVILLE CITY ELECTRICAL REQUIREMENTS & STANDARDS MANUAL

SPRINGVILLE CITY ELECTRICAL REQUIREMENTS & STANDARDS MANUAL POWER DEPARTMENT EFFECTIVE AS OF FEBRUARY 1, 2008, REVISED JULY 1, 2013 STANDARDS ARE SUBJECT TO REVIEW TABLE OF CONTENTS Section 1 General Requirements Purpose...1.1 Codes and Ordinances...1.1 Changes

More information

ELECTRIC POLICY INTRODUCTION CHAPTER I GENERAL

ELECTRIC POLICY INTRODUCTION CHAPTER I GENERAL INTRODUCTION This policy has been adopted by the Board of Public Works as a guide to obtaining electric service and to set forth the services available, conditions for service, and standards for materials

More information

2016 METER SERVICES SPECIFICATION GUIDE

2016 METER SERVICES SPECIFICATION GUIDE 2016 METER SERVICES SPECIFICATION GUIDE 802.01.ST (10-16) CONTENTS Introduction 2 Disclaimers 2 LES contacts 3 Definitions 4 LES Meter Services department requirements for approval of connection to LES

More information

TEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES

TEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES INFORMATION BULLETIN / PUBLIC - ELECTRICAL CODE REFERENCE NO.: LAMC 93.0230 Effective: 3-24-69 DOCUMENT NO. P/EC 2002-006 Revised: 11-17-00 Previously Issued As: RGA #7-69 TEMPORARY ELECTRIC WIRING FOR

More information

Electric Service Guide. Residential

Electric Service Guide. Residential Electric Service Guide Residential January 1, 2017 Contact MID s Electric Engineering Department (electric.standards@mid.org) with any questions about this Service Guide. Check MID s website (www.mid.org)

More information

Transmission & Distribution Glossary of Electrical Terms

Transmission & Distribution Glossary of Electrical Terms Transmission & Distribution Glossary of Electrical s Breaker Panel Bushing Circuit Circuit Breaker Conductor Conduit Consumption Current Distribution Electricity (Static vs. Current) Electron Feeder The

More information

TEMPORARY ELECTRICAL SERVICE

TEMPORARY ELECTRICAL SERVICE ENERGY SERVICES ENGINEERING 840 Northgate Drive Telephone (509) 942-7403 Fax (509) 942-7405 P.O. Box 190 Richland, WA 99352 www.ci.richland.wa.us/energyservices TEMPORARY ELECTRICAL SERVICE A. INTRODUCTION

More information