Technical Standard - TS 129. Small Inverter Energy Systems (IES) - Capacity not exceeding 30kW. SA Power Networks. Published: November 2017

Size: px
Start display at page:

Download "Technical Standard - TS 129. Small Inverter Energy Systems (IES) - Capacity not exceeding 30kW. SA Power Networks. Published: November 2017"

Transcription

1 TS 130: Inverter Energy Systems (IES) - capacity up to or equal to 200 kw Technical Standard - TS 129 Small Inverter Energy Systems (IES) - Capacity not exceeding 30kW Published: November 2017 SA Power Networks SA Power Networks 2017 Page 1 of 16

2 Revision Notice: Date Details Author Authorised 30 November 2017 Replaces Small Embedded Generation Technical Guidelines A. Lee J. Ali To obtain an electronic copy of this technical standard document, please click here: SA Power Networks: SA Power Networks, ABN , a partnership of: Spark Infrastructure SA (No.1) Pty Ltd, ABN Spark Infrastructure SA (No.2) Pty Ltd, ABN Spark Infrastructure SA (No.3) Pty Ltd, ABN each incorporated in Australia CKI Utilities Development Limited, ABN PAI Utilities Development Limited, ABN each incorporated in The Bahamas 1 Anzac Highway, Keswick, South Australia, SA Power Networks Disclaimer: 1. The use of the information contained in this document is at your sole risk. 2. The Information within this document is subject to change without notice. 3. SA Power Networks, its agents, instrumentalities, officers and employees: 3.1. Make no representations, express or implied, as to the accuracy of the information contained within this document; 3.2. Accept no liability for any use of the said information or reliance placed on it; and 3.3. Make no representations, either expressed or implied, as to the suitability of the said information for any particular purpose. 4. SA Power Networks and its agencies and instrumentalities do not endorse or in any respect warrant any third-party products or services by virtue of any information, material or content referred to or included on, or linked to this document. SA Power Networks Copyright 2017: This publication is copyright protected. SA Power Networks reserves to itself all rights in such material. You shall not reproduce any content of this document by any process without first obtaining the SA Power Networks permission, except as permitted under the Copyright Act All rights reserved. SA Power Networks 2017 Page 2 of 16

3 Contents 1. Purpose Scope Technical Requirements Inverter Phase Limits Single Phase Systems Three Phase Systems SWER Systems Inverters and Grid protection devices Connection Point Isolation Switches Residual current devices (RCDs) Isolation of inverter from energy source Signs and labels Cable Identification Multiple Mode Inverter (MMI) Battery Systems Electric Vehicles Overcurrent Protection Fault level Metering Protection Requirements Anti-Islanding Under/Over Frequency Under/Over Voltage Voltage Unbalance Power Quality Response Modes Quality of Supply Voltage and Frequency Ranges of Operation Voltage Frequency Testing Compliance Monitoring and Maintenance Who you should talk to? SA Power Networks 2017 Page 3 of 16

4 Appendices Appendix A: Definitions Appendix B: References SA Power Networks 2017 Page 4 of 16

5 1. Purpose This technical standard provides designers, contractors and consultants with an understanding of the technical connection requirements for small inverter energy systems (IES), with a nameplate capacity not exceeding 30kW, connected to SA Power Networks distribution network. 2. Scope This standard outlines the equipment and installation requirements for small inverter energy systems (IES) not exceeding a total name plate rating of 30kW at a single connection point, that are intended to be connected to and capable of operating in parallel with SA Power Networks distribution network. This document shall be read in conjunction with NICC 269: Connection Requirements of Small Embedded Generation and Service and Installation Rules (S&IR), which are available at ( and shall be in accordance with the relevant AS/NZS standards (eg AS/NZS 4777 series, AS/NZS 3000, AS/NZS 5033). For large embedded generating systems, refer to TS130 : Large Inverter Energy Systems (IES) 30kW kw or TS 131: Large Inverter Energy Systems (IES) above 200kW or Rotating Generating Systems. 3. Technical Requirements 3.1 Inverter Phase Limits Single Phase Systems SA Power Networks has adopted the updated AS/NZS4777 to allow a maximum total inverter system size of 5kW for a single-phase system, however, up to 10kW of inverter capacity may be installed provided it s export limited to 5kW as shown in the tables for the different scenarios. PV Panels Scenario 1: New PV only single-phase installation PV Inverter Inverter Size Export to Grid 5kW 5kW Permitted > 5kW and 10kW 5kW Permitted > 5kW and 10kW > 5kW Not Permitted for single phase * > 10kW 5kW Not Permitted for single phase * * three-phase supply conversion may be required Grid SA Power Networks 2017 Page 5 of 16

6 For a two-phase system (ie two single phase inverters connected to different phases), each inverter must be similarly limited to 5kW export as shown in scenario 1 above. Scenario 2: New PV & battery single-phase installation PV Panels Battery Hybrid Inverter Hybrid Inverter Size Export to Grid 5kW 5kW Permitted > 5kW and 10kW 5kW Permitted > 5kW and 10kW > 5kW Not Permitted for single phase * > 10kW 5kW Not Permitted for single phase * * three-phase supply conversion may be required A battery storage system can be added to an existing PV installation provided the total size of all inverter systems is 10kW or less, and exports must be limited to no more than 5kW. If the required hybrid system is larger, a three-phase system will generally need to be installed. However, if the existing approved PV inverter allows the export to the grid in excess of 5kW, the existing PV export capability may remain (ie if the current approved PV system is 6kW then the allowable limit will remain at 6kW). To assist in managing the export requirements, a battery storage system with zero export capabilities must be installed (refer to scenario 3). Grid SA Power Networks 2017 Page 6 of 16

7 Scenario 3: Adding battery storage to existing PV single-phase installation PV Panels Battery Existing PV Inverter New Battery Size Inverter Size 5kW Up to total inverter capacity of 10kW > 5kW and 10kW Up to total inverter capacity of 10kW Three-Phase Systems For three-phase systems, the IES must have a balanced output with the unbalance between phases being no greater than 5kW. For small embedded generating systems, the maximum capacity for a three-phase system is 30kW SWER Systems PV Inverter Battery Inverter PV Export to Grid As per existing approved export limit As per existing approved export limit Battery Export to Grid Combined PV and battery export 5kW 0kW Permitted Permitted For SWER systems within the distribution network, the maximum size inverter system that will be connected is 5kW. Grid SA Power Networks 2017 Page 7 of 16

8 3.2 Inverters and Grid protection devices The inverter shall comply with the requirements of AS/NZS The IES shall incorporate a grid protection device, which shall comply with the requirements of AS/NZS The grid protection device may be integral with the inverter. The protection settings of the grid protection device shall not exceed the capabilities of the inverter. All inverters and grid protection devices must be tested by an authorised testing laboratory and certified as being compliant with AS/NZS 4777 and issued with an accreditation number. The Clean Energy Council (CEC) maintains a list of approved solar modules and inverters that meet Australian Standards for use in the design and installation of solar PV systems. 3.3 Connection Point The IES shall be connected by fixed wiring to a dedicated circuit on a switchboard. It is preferable that an IES be connected directly to the main switchboard. In installations where this is not possible, the nearest distribution board shall be used and all distribution boards between the inverter energy system and the main switchboard including the main switchboard shall be labelled. See section on labelling/signage. The rating of the inverter circuit cables and all the cables between any distribution boards and the main switchboard which carry inverter output must be rated for at least the full output of the inverter energy system in accordance with AS/NZS Isolation Switches There shall be a visible and accessible method of ensuring that the inverter energy system is disconnected from the distribution network and disconnected from the customer s installation. The main switch for the switchboard, to which the inverter energy system is directly connected, shall be a lockable switch in the OFF position, which operates in all live conductors. The operation of this switch shall also isolate the inverter energy system from that switchboard. Note: This switch is to provide isolation of the inverter energy system for persons working on other parts of the electrical installation. The switch located on the main switchboard which controls any sub-circuit from the distribution board to which the inverter energy system connects must be lockable. Note: This switch is for the use of utility staff working on the distribution network as means of isolation of the inverter energy system. The isolation switches shall be installed to the requirements governing main switches in AS/NZS 3000, irrespective from where the inverter energy system circuit emanates. 3.5 Residual current devices (RCDs) The inverter energy system shall be connected to the electrical installation on the grid side of any residual current devices. 3.6 Isolation of inverter from energy source The labelled isolation devices, with the capability of safely breaking voltage and current under both normal and fault conditions, shall be installed between any energy source and the inverter, complying with AS/NZS 3000 requirements. The ideal location for installing isolation device shall be adjacent to the inverter energy source port and be readily available. Where there are multiple inverter energy source ports, each port shall have an isolator for each connected energy source. SA Power Networks 2017 Page 8 of 16

9 Where the energy storage and the inverter are physically integral, then compliance with AS is required and for the energy source as a PV array, the isolation switches and isolation arrangements shall comply with AS/NZS For more details on Isolation Devices, refer to AS/NZS Signs and labels The IES must include warning signage to clearly indicate that the electrical installation has multiple supplies and identify which circuits are affected by these supplies. Signage shall as a minimum be placed: On the switchboard that has the inverter energy system directly connected to it On all switchboards including main switchboard and distribution board(s) between the main switchboard and the board that has the inverter energy system directly connected to it In all meter boxes containing the distributor s metering equipment Signage should describe the actual type of generation source installed. The installer of the inverter energy system shall supply and install appropriate signage on the installation in accordance with requirements as required by AS/ANZ Cable Identification AS/NZS states that, all energy source (DC or AC) cables shall be clearly identified as energy source cables at intervals not exceeding 2m. Cable identification shall be permanent, legible, indelible and include type of energy source. If fixed to a surface, the identification shall be visible after mounting. For more details on Cable and Wiring Enclosures Identification, refer to AS/NZS Multiple Mode Inverter (MMI) The IES may comprise of, one or more inverters together, with one or more Energy Sources (which may include Batteries for energy storage) and controls. Where energy storage functionality is required, then the IES shall be a Multiple Mode Inverter (MMI) type that satisfies the requirements as prescribed in AS/NZS The Multiple Mode Inverter (MMI) operates in more than one mode, for example, having Grid-Interactive Functionality when grid voltage is present, and Stand-Alone Functionality when the grid is de-energised or disconnected. Inverters with battery storage ports are considered as MMI. Specifically note that, only inverters that have been tested by an authorised testing laboratory and certified as being compliant with AS/NZS and issued with an accreditation number will be regarded as an approved inverter. SA Power Networks reserve all rights to refuse connection for any non-compliant MMI installation Battery Systems A battery storage system which has the ability operate in parallel with the grid via an inverter, regardless of whether charged directly from the grid or through energy produced from a local generation source must use a AS/NZS 4777 compliant inverter. A battery storage system which operates in parallel with the grid via an inverter is considered part of the inverter energy system and its inverter size must be included in the maximum total inverter capacity as outlined in section 4.1. SA Power Networks 2017 Page 9 of 16

10 Switches to isolate the battery storage system from the main switchboard shall be clearly identified and accessible Electric Vehicles An electric vehicle is considered an embedded generating unit if it has the capability of exporting energy into the proponent s premises or into the grid and therefore must comply with the requirements outlined in this technical standard. Electric Vehicles that are only capable of charging from the grid are not considered an embedded generating unit Overcurrent Protection For installations using a PV array as an energy source, the overcurrent protection and its locations requirements shall be determined as per AS/NZS For all other energy source(s), cabling shall be protected against overcurrent, in accordance with AS/NZS Fault level As IES systems connected via grid connected inverters generally limit the fault current contribution to their full load current or a near zero value, SA Power Networks permits the connection of inverter energy systems to the distribution network without additional fault level protection and control equipment Metering An import/export meter is a requirement for all grid connected inverter installations under the electricity regulations. 4. Protection Requirements The protection systems shall be designed in accordance with Acts, Regulations and SA Power Networks standards. The inverter grid protection shall comply with the requirements of AS Anti-Islanding In accordance with the grid protection requirements of AS Table 13, the inverter must incorporate under- and over-voltage and under- and over-frequency protection. In addition, the inverter must include at least one method of active anti-islanding protection, which will operate to disconnect the device within 2 seconds. Any additional anti-islanding protection installed by the customer must be capable of automatically reconnecting to the Network once the network voltage and frequency have been maintained with their tolerable range for a minimum of 1 minute Under/Over Frequency Under and over frequency protection must be installed at the connection point. The inverter must be disconnected from the Network for the following settings: Under-frequency (f) = 47Hz with 1 sec delay Over-frequency (f) = 52Hz with 0.2 sec delay If the frequency exceeds 50.25Hz, the inverter shall reduce the power output linearly with an increase of frequency until the +4% limit is reached. SA Power Networks 2017 Page 10 of 16

11 4.1.2 Under/Over Voltage 4.2 Voltage Unbalance Under and over voltage protection must be installed to monitor all three phases at the connection point. The inverter must be disconnected from the Network for the following settings: Under-voltage (V) = 180V with 1 sec delay Over-voltage 1 (V) = 260V with 1 sec delay Over-voltage 2 (V) = 265V with 0.2 sec delay Three phase inverters must be configured to ensure the maximum unbalance between phases is 5kW whilst connected to our distribution systems. All three phases of the inverter must simultaneously disconnect from, or connect to, our distribution system in response to protection or automatic controls (eg anti-islanding trip and subsequent reconnection). Where multiple single-phase inverters are connected to more than one phase, the inverters must be interlocked and configured to behave as an integrated multiphase inverter providing balanced output (maximum unbalance between phases of 5kW) to all connected phases whilst connected to our distribution systems. Alternatively, where inverters cannot be interlocked by internal controls, the installation must be protected by a phase imbalance relay which must immediately isolate the inverter in the absence of reasonable balance. The inverters must be physically prevented from operating independently and all installed inverters must simultaneously disconnect from, or connect to, our distribution systems in response to protection or automatic controls (eg anti-islanding trip and subsequent reconnection). 4.3 Power Quality Response Modes The Proponent/electrical contractor/installer must ensure the South Australian power quality response mode has been set in the inverter(s) and must not be changed without written approval from SA Power Networks. These settings must be validated and tested by the electrical contractor/seg installer. The South Australian power quality response modes are: Volt-VAr response mode (AS/NZS Table 11) (Mandatory) Volt-Watt response mode (AS/NZS Table 10) Settings for the power quality response modes are shown below. Reference Voltage in Volts VAr % Rated VA V (default) 31% leading (sourcing vars, 2.4%/volt) V (default) 0 V V % lagging (sinking vars, 8.8%/volt) Table 1: Mandatory: Volt-VAr response mode SA Power Networks 2017 Page 11 of 16

12 Reference Voltage in Volts Power % rated Power V (default) 100% (default) V (default) 100% (default) V (default) 100% (default) V (default) 20% (default, 5.3%/volt) Reference V nom-max Table 2: Volt-Watt response mode Voltage 258 volts Table 3: Sustained Operation for Voltage Variations Power quality response mode settings shall be the same for all inverters at site where such capabilities exist. While all new inverters shall operate with the required South Australian power quality response modes, multiple power quality response mode settings are allowed where the following is satisfied: All inverters installed on or after 1 December 2017 operate with the required South Australian power quality response modes. Inverters installed prior to 1 December 2017 which are not capable of operating with an approved power quality response mode are operating at unity power factor. Replacement inverters, including warranty replacements, shall be configured to operate with the required South Australian power quality response modes. 5. Quality of Supply The IES must not impact on the quality of supply to SA Power Networks other network users. The inverter energy systems must comply with all applicable requirements of the NER, the EDC and SA Power Networks Service and Installation Rules (S&IR), including but not limited to: Network stability Network infrastructure thermal capacity Network voltage control Generating systems reactive capability (power factor) Voltage fluctuations Harmonics Voltage balance 5.1 Voltage and Frequency Ranges of Operation The inverter and customer installation must be designed, installed, and maintained in a manner that ensures that the maximum steady state voltage at any socket outlet or fixed equipment (other than the inverter) within the installation complies at all times with the requirements of AS/NZS and AS/NZS The following specific voltage and frequency settings must be programmed into the inverter: SA Power Networks 2017 Page 12 of 16

13 5.1.1 Voltage Where the Inverter has a maximum voltage limit for sustained operation (based on averaged measurements over periods 10 minutes or less), this parameter must be set no higher than 258V (phase to neutral). If the Inverter does not have a maximum voltage limit for sustained operation setting, the anti-islanding maximum voltage trip point (based on a short-term measurement) must be set to a low enough voltage (depending on the installation characteristics), to ensure compliance. Failure to design for this requirement may expose appliances and fixed equipment to potentially damaging voltages Frequency 6. Testing (a) Minimum frequency trip point (Fmin) is 47Hz. (b) Maximum frequency trip point (Fmax) is 52Hz. If voltage and/or frequency fall outside the set limits, the generating systems must be automatically disconnected from our network. The reconnection procedure for the inverter must comply with AS/NZS Upon, or at any time after, completion of the installation of the small inverter energy system, SA Power Networks may request access to the premises at a reasonable time to conduct a test of the system for the purpose of establishing compliance. The test will consist of: 1. disconnection of the premises from our distribution system; 2. reconnection of the premises to our distribution system; and 3. inspection and such testing of the small generator as we consider necessary for compliance. 7. Compliance Monitoring and Maintenance The proponent/owner of the IES is responsible for, and must: maintain the electrical installation at the supply address in a safe condition ensure that any changes to the electrical installation at the supply address are performed by an electrician lawfully permitted to do the work and that the customer holds a Certificate of Compliance issued in respect of any of the changes ensure that the electrical installation at the supply address, including the IES installation, complies at all times with the requirements in the Network Connection Agreement ensure the protection of any SA Power Networks equipment located at the supply address seek approval prior to altering the IES capacity or inverter. SA Power Networks will advise if additional work is required and the associated cost (if any) ensure that any electrical maintenance function on the IES or any other part of the customer s electrical equipment are appropriately qualified and licensed to perform such work comply with all legislation, codes, Rules or other regulatory instruments (as amended) 8. Who you should talk to? If you have any questions or you wish to investigate the potential connection of a small embedded generator to our network seg@sapowernetworks.com.au SA Power Networks 2017 Page 13 of 16

14 Appendices Appendix A: Definitions Connection Point: Contractor: Distribution Network/Systems: DNSP: Electricity Distribution Code (EDC): Embedded Generating Unit: ESCOSA: Generating Systems: Generating Unit: Generator/Proponent (and/or Customer): Inverter: Inverter Energy Systems (IES) Large embedded generation system A connection point to a transmission or distribution network. For this document, the connection point also has the same meaning as Point of Supply as defined in AS/NZS A contractor and or their sub-contractor who is engaged by SA Power Networks to conduct works on or near SA Power Networks infrastructure. Has the meaning given to that term in the Electricity Act 1996, namely the whole or a part of a systems for the distribution of electricity, but does not include anything declared by regulation not to be a distribution network or part of a distribution network. For the purposes of these rules references to Distribution Network means the network poles, wires, underground cables, transformers, substations etc, operated by SA Power Networks, which transports electricity from the transmission systems to a connection point. Distribution Network Service Provider. Electricity Distribution Code made by ESCOSA pursuant to Section 28 of the Essential Services Commission Act A generating unit connected within a distribution network and not having direct access to a transmission network. Essential Services Commission of South Australia All generating units, inverters and the associated control and protection equipment that is located on the generator/proponent's side of the connection point. The plant used in the production of electricity, including all related equipment essential to its function as a single entity. A person/entity who engages in the activity of owning, controlling, or operating a generating system that supplies electricity to, or who otherwise supplies electricity to, a transmission or distribution network. The device that forms part of the generating system which uses semiconductor devices to transfer power between a DC source(s) or load and an AC source(s) or load. The systems comprising of one or more inverters together with one or more energy sources (which may include batteries for energy storage) and controls. An installation complying with the requirements of the Australian Standard AS/NZS 4777 series, Grid connection of energy systems via inverters, Part 1: Installation Requirements, and Part 2: Inverter Requirements; and This definition includes but is not necessarily limited to generating systems such as: photovoltaic (PV) installations; small wind turbine generating units connected via Inverter; and small fuel-cell installations. An embedded generation system greater than 30kW SA Power Networks 2017 Page 14 of 16

15 Large IES: Must: Nameplate Capacity: NER: PV: Retailer: Shall: Should: Small embedded generation system Supply: Supply address: Transmission Network: Includes but is not necessarily limited to such initiatives as: Inverter installations greater than 30 kw synchronous generating units The final mentioned category includes any commercial plant which is operated and connected in parallel with the distribution network by arrangement with SA Power Networks for demand management or for routine on-load testing. Is to be understood as mandatory. The maximum continuous output or consumption in kw of an item of equipment as specified by the manufacturer, or as subsequently modified; National Electricity Rules Photo voltaic. The generation of electrical power by converting solar radiation into direct current electricity. Means the holder of an electricity retail licence granted under the Electricity Act, 1996, who is contracted to sell electricity to the Customer at the Supply Address. Mandatory Is to be understood as non mandatory, ie advisory or recommended. A single phase or three phase inverter connected embedded generation system up to 30kW. The delivery of electricity. The address at which the proponent is connected to SA Power Networks distribution network. ElectraNet s electricity transmission network. SA Power Networks 2017 Page 15 of 16

16 Appendix B: References The following listed documents are for additional information and other documentation may be required on a project specific basis. Please Note: It is your responsibility to ensure you have complied with all applicable, SA Legislative Regulations (under Acts), ESCOSA/ENA/AEMC/IEC documentations, relevant AS/NZS standards, the SA Power Networks publications, and you have ensured their current publications, before implementing them. South Australian Legislations: Example Electricity (General) Regulations, Work Health & Safety Regulations Essential Services Commission of South Australia (ESCOSA) Codes: SA Electricity Distribution Code (EDC) SA Electricity Metering Code (EMTC) Energy Networks Association (ENA) Publications: ENA NENS 03: National Guidelines for Safe Access to Electrical and Mechanical Apparatus ENA NENS 04: National Guidelines for Safe Approach Distances to Electrical and Mech. Apparatus Australian Energy Market Commission (AEMC) Publications: National Electricity Rules (NER) Standards Australia Publications: AS Rotating Electrical Machines - General Requirements Part 0: Introduction and list of parts AS Standard voltages AS/NZS Electrical Installations (known as the wiring rules) AS/NZS Electrical Installations - Selection of cables Part 1.1: Cables for altering voltages up to and including 0.6/1 kv - Typical Australian installation conditions AS/NZS Electrical Installations - Generating sets AS/NZS Electrical installations - Testing User Guides AS/NZS Approval and test specification - General requirements for electrical AS/NZS Earth potential rise Part 1: Protection of telecommunications network users, Equipment personnel and plant AS/NZS Grid connection of energy systems via inverters Part 1: Installation requirements AS/NZS Grid connection of energy systems via inverters Part 2: Inverter requirements AS/NZS Installation and safety requirements for photovoltaic (PV) arrays SA Power Networks Documents: Manual 14: Safety, Reliability, Maintenance & Technical Management Plan Manual 18: Network Tariff & Negotiated Services Manual 32: Service and Installation Rules Technical Standards & NICC Brochures, in particular: o NICC 269: Connection Requirements of Small Embedded Generation o NICC 270: Connection Requirements of Large Embedded Generation o TS130: Large Inverter Energy Systems (IES) above 30kW and up to 200kW o TS 131: Large Inverter Energy Systems (IES) above 200 kw or Rotating Generating Systems SA Power Networks 2017 Page 16 of 16

Large Embedded Generation User Guide A

Large Embedded Generation User Guide A Large Embedded Generation User Guide A For Generating Systems AS4777 compliant and up to 200kW January 2013 SA Power Networks www.sapowernetworks.com.au Table of Contents 1. Introduction... 3 1.1 Embedded

More information

Enquiry Form for Micro and Small Generators 5MW and Less

Enquiry Form for Micro and Small Generators 5MW and Less Enquiry form Enquiry Form for Micro and Small Generators 5MW and Less Connect an embedded generator (incl. solar, wind & micro-hydro) to the TasNetworks Distribution Network Please print and complete relevant

More information

SA Power Networks Commissioning Witnessing Checklist

SA Power Networks Commissioning Witnessing Checklist SA Power Networks Commissioning Witnessing Checklist CUSTOMER NAME: SOLAR PV APPROVED CAPACITY: BATTERY APPROVED CAPACITY: kw (AC) kw (AC) OPERATING PHILOSOPHY: MAXIMUM EXPORT: Non-Export/Export kw (AC)

More information

AS/NZS :2016. Grid connection of energy systems via inverters AS/NZS :2016. Part 1: Installation requirements

AS/NZS :2016. Grid connection of energy systems via inverters AS/NZS :2016. Part 1: Installation requirements AS/NZS 4777.1:2016 Australian/New Zealand Standard Grid connection of energy systems via inverters Part 1: Installation requirements AS/NZS 4777.1:2016 AS/NZS 4777.1:2016 This joint Australian/New Zealand

More information

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Micro Embedded Generating Units (0-30 kva)

Micro Embedded Generating Units (0-30 kva) Connection Standard Micro Embedded Generating Units (0-30 kva) These standards ensure that Ergon Energy s and Energex s requirements are met. If this standard is a printed version then the Ergon Energy

More information

Basic Connection Services Application and Price Guide

Basic Connection Services Application and Price Guide Basic Connection Services Application and Price Guide 2016-17 Disclaimer TasNetworks (which, for the purposes of this disclaimer, includes all of its related bodies corporate, its officers, employees,

More information

Micro Embedded generation

Micro Embedded generation Application form Micro Embedded generation Application for new connection and supply of an embedded generator (incl. solar, wind & micro-hydro) Please print and complete relevant sections of this form

More information

Renewable Energy System - Electricity System Connection Application Form

Renewable Energy System - Electricity System Connection Application Form Renewable Energy System - Electricity System Connection Application Form If you would like assistance completing this form, please email renewables@horizonpower.com.au This is an application to connect

More information

SERVICE & INSTALLATION RULES Manual No. 32

SERVICE & INSTALLATION RULES Manual No. 32 SERVICE & INSTALLATION RULES Manual No. 32 Published: August 2017 SA Power Networks www.sapowernetworks.com.au TS 100: Electrical Design Std for Underground Distribution Cable Networks (up to & including

More information

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW) Connection Applicant (Embedded Generating Unit Owner/Proponent) Business name: ABN: Contact name: Address: Telephone number: E-mail address: Connection Applicant acting and working on behalf of the above

More information

3. Customer shall provide space for metering equipment and meter base as per Springville City Power requirements.

3. Customer shall provide space for metering equipment and meter base as per Springville City Power requirements. A. General This Customer-Owned Generation Standards for Customer-Owned Grid Connected Electric Generating Systems sets forth the requirements and conditions for interconnected non-utility-owned electric

More information

Columbia Water & Light Interconnection & Net Metering Agreement Electrical Facility

Columbia Water & Light Interconnection & Net Metering Agreement Electrical Facility Processed Date Columbia Water & Light Interconnection & Net Metering Agreement Electrical Facility Customer s Printed Name Installation Street Address Account Number Please note: Columbia Water & Light

More information

National Distributed Energy Resources Grid Connection Guidelines. Technical Guidelines for Basic Micro EG Connections

National Distributed Energy Resources Grid Connection Guidelines. Technical Guidelines for Basic Micro EG Connections National Distributed Energy Resources Grid Connection Guidelines Technical Guidelines for Basic Micro EG Connections ENA DOC 039-2019 DISCLAIMER This document refers to various standards, guidelines, calculations,

More information

Renewable sources of electricity a brief overview

Renewable sources of electricity a brief overview Micro generation 11 Renewable sources of electricity a brief overview THE SCOPE of the 17th Edition is wider and contains many new requirements, including additional requirements to ensure the safe connection

More information

Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation Edition DRAFT

Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation Edition DRAFT Date of publication: 1 November 2016Not yet published Issued by: Mark Wogan, Manager Energy Safety WorkSafe New ZealandNot yet issued Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation

More information

Louisville Gas and Electric Company

Louisville Gas and Electric Company P.S.C. Electric No. 11, Original Sheet No. 57 APPLICABLE In all territory served. AVAILABILITY OF SERVICE Available to any customer-generator who owns and operates a generating facility located on Customer

More information

Connecting your business diesel generation

Connecting your business diesel generation Connecting your business diesel generation March 2018 For connections more than 10kW 2 Contents Introduction to large distributed generation systems 3 Congestion management and safety 6 Application form

More information

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1 Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 01, 2017 1 Initial release Newfoundland

More information

Net Metering Interconnection Requirements

Net Metering Interconnection Requirements Net Metering Interconnection Requirements Customer Generation Capacity Not Exceeding 100 kw Date: 2017-07-01 Version: 1 Revision History Date Rev. Description July 1, 2017 1 Initial Release Newfoundland

More information

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities New Ulm Public Utilities Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities INDEX Document Review and History... 2 Definitions... 3 Overview... 3 Application

More information

Export limits for Embedded Generators up to 200 kva connected at Low Voltage

Export limits for Embedded Generators up to 200 kva connected at Low Voltage Export limits for Embedded Generators up to 200 kva connected at Low Voltage Standard Operating Procedure Document number: SOP 33-06 Issue number: 5 Status: FINAL Approver: J Bridge Date of approval: 3

More information

SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL

SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS - ELECTRICAL This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

More information

AS/NZS AS/NZS

AS/NZS AS/NZS TEST REORT AS/NZS 4777.2 AS/NZS 4777.3 Grid connection of energy systems via inverters Grid protection requirements Report reference number... : 13TH0287-AS/NZS 4777_0 Date of issue......: 2014-01-22 Total

More information

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018 Outlined below are the engineering documents and their associated minimum detail requirements for a Distributed Energy Resource (DER)

More information

Net +Plus Connection Code

Net +Plus Connection Code Net +Plus Connection Code LANKA ELECTRICITY COMPANY (PRIVATE) LIMITED 1.0 BACKGROUND The existing Net Metering Concept launched in the year 2010 noticed an exponential growth in the recent year and at

More information

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES 10-100 KILOWATTS IN THE STATE OF NEW JERSEY January 1, 2005 Rockland Electric Company 390 West Route 59 Spring Valley,

More information

Electricity Safety (Electrical Installations) Regulation 2005

Electricity Safety (Electrical Installations) Regulation 2005 New South Wales Electricity Safety (Electrical Installations) Regulation 2005 under the Electricity Safety Act 1945 Her Excellency the Governor, with the advice of the Executive Council, has made the following

More information

This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly. SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS (ELEC) This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

More information

Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation

Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation 86 Customhouse Quay PO Box 165, Wellington 6140 New Zealand Date of publication: 1 November 2016 Issued by: Mark Wogan, Manager Energy Safety WorkSafe New Zealand Electric Vehicle Charging Safety Guidelines

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

SAFETY FACT SHEETS. Electrical Hazards Safety Non Negotiable. G-HS-ST Electrical Hazards. G-HS-FS Version:1

SAFETY FACT SHEETS. Electrical Hazards Safety Non Negotiable. G-HS-ST Electrical Hazards. G-HS-FS Version:1 SAFETY FACT SHEETS Electrical Hazards Safety Non Negotiable G-HS-ST-00752 Electrical Hazards Safety Non-Negotiables (SNN) Zinfra Group is committed to providing a safe workplace in line with our number

More information

Definitions. Scope. Customer Generation Interconnection Requirements

Definitions. Scope. Customer Generation Interconnection Requirements Updated 02/1 Page 1 Scope The purpose of this document is to describe Idaho Power s requirements for the installation and testing of Customer Generation acilities that are interconnected with Idaho Power

More information

Technical Requirements for Renewable Energy Power System

Technical Requirements for Renewable Energy Power System Hotline: 2843 3228 Email address: RE@hkelectric.com Issued on 20 Nov 2018 1. Introduction 1.1. This document aims to provide the technical requirements for renewable energy power system (the REPS) connected

More information

TILLAMOOK PEOPLE S UTILITY DISTRICT

TILLAMOOK PEOPLE S UTILITY DISTRICT TILLAMOOK PEOPLE S UTILITY DISTRICT DISTRIBUTION INTERCONNECTION PROCEDURE Inverter Based Generators 25 kw and Smaller This document contains the interconnection requirements for inverter based generators,

More information

RULES & REGULATIONS FOR RENEWABLE GENERATION SYSTEMS 2. SUMMARY OF APPLICATION AND INTERCONNECTION PROCESS

RULES & REGULATIONS FOR RENEWABLE GENERATION SYSTEMS 2. SUMMARY OF APPLICATION AND INTERCONNECTION PROCESS RULES & REGULATIONS FOR RENEWABLE GENERATION SYSTEMS 1. PURPOSE This document describes the technical requirements for connecting Renewable Generation Systems ( RGS ) up to 150kW, or larger if approved

More information

Substation Lightning Protection. Document Number: 1-11-FR-11

Substation Lightning Protection. Document Number: 1-11-FR-11 Substation Lightning Protection Document Number: 1-11-FR-11 VERSION 1.0 June 2018 This functional requirements document is in line with the organisation's 1-11-ACS-11 Substation Lightning Protection Asset

More information

Key elements of the AS3000 Wiring standards and some of the recent changes.

Key elements of the AS3000 Wiring standards and some of the recent changes. Key elements of the AS3000 Wiring standards and some of the recent changes. Dean of Engineering Steve Mackay Worked for 30 years in Industrial Automation 30 years experience in mining, oil and gas, electrical

More information

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS 1. PURPOSE AND SCOPE OF THIS DOCUMENT... 3 2. DEFINITIONS...

More information

Contents. 1 Introduction. 2. Advisory and Information Systems. 3. Supply. 3.1 Quality of Electric Supply. 3.2 Interference with other Customers

Contents. 1 Introduction. 2. Advisory and Information Systems. 3. Supply. 3.1 Quality of Electric Supply. 3.2 Interference with other Customers DISTRIBUTION CODE Contents 1 Introduction 2. Advisory and Information Systems 3. Supply 3.1 Quality of Electric Supply 3.2 Interference with other Customers 3.3 Application for the Supply of Electricity

More information

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM Page 1 of 19 Table of Contents 1.0 SCOPE...4 2.0 PURPOSE...4 3.0 LIMITATIONS...5 4.0 GENERAL INTERCONNECTION

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd Embedded Generation - Technical Access Standards Embedded Generation - 5 MW or Greater ELE SP 0003 Public 1 October 2014 TABLE OF CONTENTS TABLE OF CONTENTS Abbreviations...

More information

CLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001

CLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001 CLP POWER HONG KONG LIMITED SUPPLY March 2001 ADVISORY SERVICE Advice concerning matters relating to the supply of electricity may be obtained free of charge from the Company. OTHER COMPANY PUBLICATIONS

More information

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _

Application for Operation of & Net Metering for Member-Owned Generation Name: Mailing Address: City: County: State: Zip Code: _ Application for Operation of & Net Metering for Member-Owned Generation -------------- OWNER/APPLICANT INFORMATION Name: Mailing Address: City: County: State: Zip Code: _ Phone Number: Email Address:.Representative:

More information

Photovoltaic Solar Plan Review

Photovoltaic Solar Plan Review PAIGE B. VAUGHAN, CBO Director of Building and Safety Phone (310) 605-5509 Fax Line (310) 605-5598 E-mail:lbutler@comptoncity.org Building & Safety Department Photovoltaic Solar Plan Review Plan Check

More information

Connecting your home or small business generation

Connecting your home or small business generation Connecting your home or small business generation For connections 10kW or less March 2018 2 Contents Introduction to small distributed generation systems 3 Congestion management and safety 6 Application

More information

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING Third Revised Sheet 55a Cancels Second Revised Sheet 55a A. ELIGIBLE CUSTOMER-GENERATOR RULE NO. 17 NET ENERGY METERING Net energy metering is available to eligible customer-generators, defined as, permanent

More information

NS194B Guidelines for Rotating Machines Connected to the Ausgrid Network. October 2014

NS194B Guidelines for Rotating Machines Connected to the Ausgrid Network. October 2014 Guidelines for Rotating Machines Connected to the Ausgrid Network October 2014 SUMMARY Network Standard outlines the requirements other than control and protection that a rotating machine should fulfil

More information

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620

Policy Bulletin No. 25 Net Metering. Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620 Policy Bulletin No. 25 Net Metering Public Utility District No. 1 of Klickitat County 1313 South Columbus Goldendale, WA 98620 Interconnection Standards For Residential Net Energy Metering With Electric

More information

Substation LV AC Supplies. Document Number: 1-11-FR-04

Substation LV AC Supplies. Document Number: 1-11-FR-04 Substation LV AC Supplies Document Number: 1-11-FR-04 VERSION 1.0 June 2018 This functional requirements document is in line with the organisation's 1-11-ACS-04 LV AC Supplies Asset Class Strategy Intellectual

More information

Title Low Voltage Distribution and Installations Earthing References and Definitions. Reference Number PDS 03 (ARTC Standard: EP SP)

Title Low Voltage Distribution and Installations Earthing References and Definitions. Reference Number PDS 03 (ARTC Standard: EP SP) Discipline Engineering Standard NSW Category Electrical Title Low Voltage Distribution and Installations Earthing References and Definitions Reference Number PDS 03 (ARTC Standard: EP 12 00 00 02 SP) Document

More information

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase

DISTRIBUTED RESOURCE GENERATION Feed-In-Tariff Single Phase PAGE 1 OF 7 USE: Requirements and guidelines for interconnection of single phase customer owned, (DR) Distributed Resource generation source, to NIPSCO s electric system, configured for. LATEST REVISION:

More information

2016 Photovoltaic Solar System Plan Review List

2016 Photovoltaic Solar System Plan Review List Building Division 555 Santa Clara Street Vallejo CA 94590 707.648.4374 2016 Photovoltaic Solar System Plan Review List GENERAL PROJECT INFORMATION PLAN CHECK NO DATE JOB ADDRESS CITY ZIP REVIEWED BY PHONE

More information

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES

RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES RULES FOR CUSTOMER INTERCONNECTION OF ELECTRIC GENERATING FACILITIES Last Revised Date: October 15, 2015 Contents Chapter 1 - Purpose and Scope 2 Chapter 2 - Application of Rules 2 Chapter 3 - Definitions

More information

Guidelines for connection of generators:

Guidelines for connection of generators: Guidelines for connection of generators: Greater than 30 kva, and not greater than 10 MW, to the Western Power distribution network January, 2017. EDM 32419002 / DM 13529244 Page 1 of 14 Contents 1 INTRODUCTION...

More information

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna 800 021 ------------------------------------------------------------------------------------------------------------- ROOFTOP

More information

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION Work Order No: File Reference: 16/2/1 This application form for the connection of small scale embedded generation is for small

More information

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection 28/10/2010 Guideline for Parallel Grid Exit Point Connection Page 2 of 11 TABLE OF CONTENTS 1 PURPOSE... 3 1.1 Pupose of the document... 3 2 BACKGROUND

More information

London Hydro Connection Checklist

London Hydro Connection Checklist London Hydro Connection Checklist Applicants should be aware not to incur expenses prior to London Hydro approving the connection of the facility to the grid. Payment of Connection Fee: $1000 plus HST

More information

DISCONNECT SWITCH REQUIREMENTS FOR DISTRIBUTED GENERATION CUSTOMERS

DISCONNECT SWITCH REQUIREMENTS FOR DISTRIBUTED GENERATION CUSTOMERS Prepared by: SXZO DISCONNECT SWITCH REQUIREENTS FOR DISTRIBUTED GENERATION CUSTOERS 060559 Department: Electric Distribution Section: Design and Construction Approved by: D.Jantz (DWJ7) Date: 8/15/17 Rev.

More information

MAINTENANCE AND TESTING OF ENTITY WORKS, ELECTRICAL INSTALLATIONS AND ELECTRICAL EQUIPMENT CS-OHS-32

MAINTENANCE AND TESTING OF ENTITY WORKS, ELECTRICAL INSTALLATIONS AND ELECTRICAL EQUIPMENT CS-OHS-32 CS ENERGY OPERATIONS PROCEDURE FOR MAINTENANCE AND TESTING OF ENTITY WORKS, ELECTRICAL INSTALLATIONS AND ELECTRICAL CS-OHS-32 Responsible Officer: Electrical Services Engineering Manager Error! Bookmark

More information

To complete the process for a net metering interconnection, please follow the steps below:

To complete the process for a net metering interconnection, please follow the steps below: We appreciate your interest in Rocky Mountain Power s net metering program. Before purchasing any net metering equipment, we recommend you review the requirements for interconnecting a net metering system

More information

ENGINEERING SPECIFICATION

ENGINEERING SPECIFICATION December 206 ENGINEERING SPECIFICATION No. of 6 DATE: 2-9-6 CATEGORY SUBJECT TABLE OF CONTENTS. Overview... 2 2. General Requirements for Service... 3 3. Definitions... 3 4. Abbreviations... 5 5. References

More information

REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDING 50 kw

REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDING 50 kw REQUIREMENTS FOR PARALLEL OPERATION FOR CUSTOMERS WITH GENERATION NOT EXCEEDG 50 kw FOREWARD Requirements for Parallel Operations for Customers with Generation Not Exceeding 50 kw is intended to be used

More information

NET METER REQUEST FORM

NET METER REQUEST FORM Form No. 3651 02/17 NET METER REQUEST FORM In order to receive a Net Meter, please provide the information requested below, sign and return only this coversheet by mail to the address below. NorthWestern

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS XXV. NET METERING A. Applicability and Availability 1. The terms Net Metering Service, Demand Charge-based Time-of- Use Tariff, Net Metering Customer, Customer, Time-of-Use Customer, Time-of-Use Tier,

More information

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program As part of our commitment to support renewable energy, Kissimmee Utility Authority

More information

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5

Northeastern Rural Electric Membership Corporation Schedule DG-2 Columbia City, Indiana Page 1 of 5 Columbia City, Indiana Page 1 of 5 SCHEDULE DG-2 LARGE POWER DISTRIBUTED GENERATION I. AVAILABILITY This Distributed Generation Rate is available to any member in good standing of Northeastern REMC (Northeastern)

More information

Guidance for Low Voltage Electrical Installations

Guidance for Low Voltage Electrical Installations Guidance for Low Voltage Electrical Synopsis This document provides information in support of GI/RT7007 Low Voltage Electrical. Signatures removed from electronic version Submitted by Anne E Blakeney Standards

More information

Model Standing Offer for Micro Embedded Generator Basic Connection Services

Model Standing Offer for Micro Embedded Generator Basic Connection Services Model Standing Offer for Micro Embedded Generator Basic Connection Services MICRO EMBEDDED GENERATORS BASIC CONNECTION SERVICES NEW CONNECTION WITH MICRO EMBEDDED GENERATOR EXISTING CONNECTION WITH NEW

More information

REQUIREMENTS FOR GRID INTERCONNECTION OF RENEWABLE GENERATION SYSTEMS

REQUIREMENTS FOR GRID INTERCONNECTION OF RENEWABLE GENERATION SYSTEMS REQUIREMENTS FOR GRID INTERCONNECTION OF RENEWABLE GENERATION SYSTEMS 1. PURPOSE This document describes the general provisions and technical requirements for connecting Renewable Generation Systems (

More information

Australian/New Zealand Standard

Australian/New Zealand Standard AS/NZS 3001:2008 (Incorporating Amendment No. 1) AS/NZS 3001:2008 Australian/New Zealand Standard Electrical installations Transportable structures and vehicles including their site supplies AS/NZS 3001:2008

More information

Major Customer Connections. Preliminary Enquiry Form Embedded Generation > 30 kw

Major Customer Connections. Preliminary Enquiry Form Embedded Generation > 30 kw Major Customer Connections Preliminary Enquiry Form Embedded Generation > 30 kw MARCH 2018 Privacy Notice Ergon Energy is collecting information (including personal information) on this form for the purposes

More information

Construction and Connection of Street Light Assets

Construction and Connection of Street Light Assets Construction and Connection of Street Light Assets 1. INTRODUCTION... 2 2. FURTHER INFORMATION... 3 3. DEFINITIONS... 3 3.1 Designer... 3 3.2 Street Light Asset Owner... 3 3.3 Road Owner... 4 3.4 Developer...

More information

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.

DER Commissioning Guidelines Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1. Community Scale PV Generation Interconnected Using Xcel Energy s Minnesota Section 10 Tariff Version 1.3, 5/16/18 1.0 Scope This document is currently limited in scope to inverter interfaced PV installations

More information

Title High Voltage and 1500 System Earthing References and Definitions. Reference Number PDS 02 (RIC Standard: EP SP)

Title High Voltage and 1500 System Earthing References and Definitions. Reference Number PDS 02 (RIC Standard: EP SP) Discipline Engineering Standard NSW Category Electrical Title High Voltage and 1500 System Earthing References and Definitions Reference Number PDS 02 (RIC Standard: EP 12 00 00 01 SP) Document Control

More information

Connecting to the network information pack Version 5

Connecting to the network information pack Version 5 Connecting to the network information pack Version 5 Updated: Contents 1.0 What is a new connection or connection alteration?... 3 2.0 Connection enquiry... 3 3.0 Connection application... 3 3.1 Processing

More information

Electrical Testing Company Pty Ltd / / AS/NZS 3003:2011 Body (Rev E)

Electrical Testing Company Pty Ltd /  / AS/NZS 3003:2011 Body (Rev E) AS/NZS 3003:2011 Electrical Testing Company Pty Ltd / www.electricaltestingcompany.com.au / AS/NZS 3003:2011 Body (Rev E) Body Protected Electrical Areas (shall comply with Section 2 and Section 3 of the

More information

TANZANIA BUREAU OF STANDARDS

TANZANIA BUREAU OF STANDARDS EDC 5 (5235) P3 Mini-Grid Systems DRAFT TANZANIA STANDARD (Draft for comments only) Part 2: Application of Inverters TANZANIA BUREAU OF STANDARDS TBS 2017 First Edition 2017 T able of content 1 2 3 4 5

More information

Consumer Guidelines for Electric Power Generator Installation and Interconnection

Consumer Guidelines for Electric Power Generator Installation and Interconnection Consumer Guidelines for Electric Power Generator Installation and Interconnection Habersham EMC seeks to provide its members and patrons with the best electric service possible, and at the lowest cost

More information

Net Metering Program

Net Metering Program Net Metering Program Chapter 1 Purpose and Scope. The purpose of this chapter is to establish rules for determining the terms and conditions governing the interconnection of electric generation facilities

More information

SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & INTERCONNECTION AGREEMENT

SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & INTERCONNECTION AGREEMENT SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION CUSTOMER GUIDELINES, APPLICATION & INTERCONNECTION AGREEMENT INTERCONNECTION AGREEMENT FOR SOLAR PHOTOVOLTAIC DISTRIBUTED GENERATION THIS AGREEMENT MUST ACCOMPANY

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION IEC/TS 62257-7-3 TECHNICAL SPECIFICATION Edition 1.0 2008-04 Recommendations for small renewable energy and hybrid systems for rural electrification Part 7-3: Generator set Selection of generator sets

More information

Umatilla Electric Cooperative Net Metering Rules

Umatilla Electric Cooperative Net Metering Rules Umatilla Electric Cooperative Net Metering Rules Version: July 2017 Umatilla Electric Cooperative NET METERING RULES Rule 0005 Scope and Applicability of Net Metering Facility Rules (1) Rule 0010 through

More information

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008 NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0

More information

This page is purposely left blank

This page is purposely left blank Section 1. Information contained within this section shall be read in conjunction with all sections of this manual This page is purposely left blank Cover Issue: 03.01.2011 Page 2 of 2 1.1 Contents Section

More information

Compatibility Between Electric Trains and Electrification Systems

Compatibility Between Electric Trains and Electrification Systems Compatibility Between Electric Trains and Electrification Systems Synopsis Process for managing change that affects the compatibility between electric trains and electrification systems Submitted by Signatures

More information

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS Prof. Suryanarayana Doolla Department of Energy Science and Engineering Indian Institute of Technology Bombay OUTLINE Intoduction Grid

More information

APPLICATION Net Energy Metering Interconnection For Solar And/Or Wind Electric Generating Facilities Of 30 Kilowatts Or Less

APPLICATION Net Energy Metering Interconnection For Solar And/Or Wind Electric Generating Facilities Of 30 Kilowatts Or Less IMPORTANT NOTES: Customers may not operate their Generating Facility while interconnected to the PG&E system until they receive written permission from PG&E. For a non-exporting Generating Facility, RES-BCT

More information

Controlling the Speed of Tilting Trains Through Curves

Controlling the Speed of Tilting Trains Through Curves Controlling the Speed of Tilting Trains Through Curves Synopsis This document mandates the means by which Tilting Trains may be operated at higher speeds than nontilting trains around curves. Signatures

More information

Equipotential Bonding of Rail Vehicles to Running Rail Potential

Equipotential Bonding of Rail Vehicles to Running Rail Potential Railway Group Standard Equipotential Bonding of Rail Vehicles to Running Rail Potential Synopsis This standard mandates the requirements for equipotenial bonding of rail vehicles to comply with the Electricity

More information

Australian/New Zealand Standard

Australian/New Zealand Standard AS/NZS 3112:2011 AS/NZS 3112:2011 Australian/New Zealand Standard Approval and test specification Plugs and socket-outlets AS/NZS 3112:2011 This Joint Australian/New Zealand Standard was prepared by Joint

More information

Draft Guideline for the connection of smallscale inverter based distributed generation. EEA Asset Management Forum 22 June 2016 Dr Richard Strahan

Draft Guideline for the connection of smallscale inverter based distributed generation. EEA Asset Management Forum 22 June 2016 Dr Richard Strahan Draft Guideline for the connection of smallscale inverter based distributed generation EEA Asset Management Forum 22 June 2016 Dr Richard Strahan Outline 1. Introduction and Issues to Address 2. Methodology

More information

CrownSAFE Procedure. Electrical Safety CS-P Objective. 2. Scope. 3. Definitions

CrownSAFE Procedure. Electrical Safety CS-P Objective. 2. Scope. 3. Definitions 1. Objective To minimise the risk of injury to all Crown employees, contractors and visitors who conduct work on and use electrical plant, equipment, furniture and fittings. 2. Scope This procedure applies

More information

Northeastern Rural Electric Membership Corporation Columbia City, Indiana

Northeastern Rural Electric Membership Corporation Columbia City, Indiana Page 1 of 5 SCHEDULE ADG - 1 AGGREGATED DISTRIBUTED GENERATION SERVICE I. AVAILABILITY This Aggregated Distributed Generation Schedule is available to any member in good standing of Northeastern REMC (Northeastern),

More information

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION

EXTRA ORDINARY 16 AASHAADHA, 1937(S) BIHAR ELECTRICITY REGULATORY COMMISSION REGISTERED NO. PT.-40 The B Bihar Gazett te EXTRA ORDINARY PUBLISHED BY AUTHORITY 16 AASHAADHA, 1937(S) (NO.PATNA 737) PATNA, TUESDAY, 7 TH JULY 2015 BIHAR ELECTRICITY REGULATORY COMMISSION NOTIFICATION

More information

Inverter Advancements in UL1741 and UL 62109

Inverter Advancements in UL1741 and UL 62109 Inverter Advancements in UL1741 and UL 62109 2015 UL LLC Scott Picco Staff Engineer Distributed Energy Resources Equipment UL LLC Renewable Energy Standards for safety of Power Conversion Equipment USA

More information

To complete the process for a net metering interconnection, please follow the steps below:

To complete the process for a net metering interconnection, please follow the steps below: We appreciate your interest in Pacific Power s net metering program. Before purchasing any net metering equipment, we recommend you review the requirements for interconnecting a net metering system to

More information

NZQA registered unit standard version 1 Page 1 of 6

NZQA registered unit standard version 1 Page 1 of 6 Page 1 of 6 Title Demonstrate knowledge of theory and legislation for registration of electrical appliance servicepersons Level 3 Credits 3 Purpose This unit standard covers the theory assessment required

More information