Research Brief. Feasibility study into raising and lowering pantographs while trains are in motion. T778 - July Overview. Aims.

Size: px
Start display at page:

Download "Research Brief. Feasibility study into raising and lowering pantographs while trains are in motion. T778 - July Overview. Aims."

Transcription

1 Research Brief Feasibility study into raising and lowering pantographs while trains are in motion Overview Currently, raising the pantograph on the move on the GB railway is not standard practice, being undertaken only under limited circumstances and at low speeds by some train operators. For dual electrified trains the pantograph raise/lower transition between DC and AC electrification is typically undertaken at a standstill. The practice of raising the pantograph while the train is in motion is, however, applied regularly on the continent, and at high speeds. This research was intended to identify any risks that occur while raising and lowering pantographs on the move in the context of GB railways. There are several potentially significant operating benefits to be gained from routinely applying such a practice. Aims Findings On behalf of the Future Electrification Group (FEG), which is a sub-group of the Vehicle/Train Energy System Interface Committee (V/TE SIC), this research aimed to establish the acceptability of pantograph raising and lowering on the GB railway. This would allow, in regular operation of electric hybrid trains to traverse discontinuities in contact wire, which could enable simplification and cost reduction of the OLE layout. Risks of Pantograph Raising/Lowering at Speed The research has shown that it is viable to lower pantographs at line speed and, while avoiding some identified criteria, to raise them at speeds of up to 80mph. This could lead to time savings, and it also enables discontinuous electrification to be considered; coasting with a lowered pantograph can allow restricted clearance features to be negotiated, and operating flexibility is increased by coasting past obstructions. The simulations showed that the worst case was raising the pantograph onto a registration point at 125mph, the maximum predicted peak forces generated being 560N. RSSB R&D Programme Block 2 Angel Square 1 Torrens Street London EC1V 1NY research@rssb.co.uk default.aspx 1

2 Feasibility study into raising and lowering pantographs while trains are in motion Additional simulations were carried out, including raising two and three pantographs simultaneously, and raising the pantograph onto a gradient. These simulations gave very similar results to the single pantograph on plain wire scenarios, there being no significant change to the forces generated. As a result of the high predicted forces, vertical impact tests were carried out to ascertain the force required to damage pantograph contact strips. These tests showed single-piece bonded carbon type collector strips (as fitted to the class 91 and 390) to have a typical vertical impact resistance of 1500N or better. Consideration of the initial contact force characteristic in relation to the contact wire uplift generated by normal running has concluded that excessive contact wire uplift will not occur at pantograph raising. A limited number of arc damaged bonded, rolled-in, and clipped carbons were tested, which had impact resistances between 965N and 1560N. However, because of the low number of samples tested, and consequential uncertainty of the minimum impact resistance of these types, a general speed restriction of 80mph is recommended; whilst raising the pantograph at speeds up to 125mph is acceptable for undamaged bonded carbons. An analysis of the potential risks of pantograph raising at speed identified the following key risks, and corresponding mitigations: Raising the pantograph at speed onto specific features such as neutral sections, section insulators, and cross contacts will produce higher forces with increased risk of carbon damage. This is mitigated by appropriate planning of 'pantograph raising zones'. Windy conditions can affect train/pantograph aerodynamics and cause movement to OLE wires, potentially leading to high contact forces and wire uplifts when raising pantographs at speed. This is mitigated by limiting speeds for raising and lowering pantographs in high wind conditions; further research would be required to support the removal of these limitations. Ice conditions can damage pantograph carriers potentially weakening them. Research will be required to establish appropriate restrictions. Possible deterioration of pantograph components (eg bearings, chains, and Automatic Drop Device (ADD) components) as a result of more frequent pantograph raise/ lower cycles. This will require that accelerated life 'type' 2 RSSB

3 tests be carried out to ascertain pantograph maintenance requirements when operated under such regimes. Deliverables Method This research produced the report Feasibility study into raising and lowering pantographs while trains are in motion'; this report outlines the methodology, findings, and recommendations for industry members. The report contributes knowledge to those considering future electrification options for the GB railway. The feasibility of raising and lowering pantographs while trains are in motion was evaluated by means of: Surveying other railways' experience where this practice is used, and instances where trials have been undertaken on GB Rail. Liaison with rail operators in the GB and overseas, who currently raise the pantograph in motion. Liaison with contact strip and pantograph manufacturers. Modelling the forces generated when the pantograph is raised onto the contact wire. Assessment of the risks of damaging either the contact strips or overhead line components. Identifying additional risks of damage to the pantograph mechanism and/or contact wire. The quantification of the effect on combined pantograph and OLE (contact) system reliability. Stakeholders Experience A questionnaire was submitted to GB and European train operators to ascertain railway industry experience of raising the pantograph at speed. The responses showed that, on GB rail infrastructure, pantographs have, on occasion, been raised at speeds of up to 100 mph; whereas train operators in Europe will do this at speeds of up to 225 mph. Next Steps This research and its findings have been reviewed and accepted by the FEG. This research has fully addressed the key risks associated with raising and lowering pantographs while the train is in motion. It has shown that the use of a bonded carbon design of carrier can be safely raised against plain OLE at speeds of up to 125mph (except in wind or ice conditions). RSSB 3

4 Feasibility study into raising and lowering pantographs while trains are in motion Table 1 - Pantograph raise speeds, by train operator Train operating company experience Train operators Train speed at which pan raised (mph) East coast (GB) 20 Northern Rail (GB) 20 Virgin Rail (GB) 60 Hitachi (GB) (while on test by manufacturer) 62 Mentor test train (GB) 100 Eurostar (Continental Europe and GB High Speed 1) 170 Amtrak (US) 60 DB (Germany) 185 SNCF (France) 225 This research project concluded that increased speed limits could be established for pantograph raising in high wind conditions; but further research and testing would be required to establish appropriate limits. Previously within Module AC, Rule 12.1 controlled lowering the pantograph on the move to avoid damage. Rule 16.4 allowed coasting at 20mph with lowered pantographs to pass an area of damaged infrastructure, then unless otherwise specified by train operating company instructions, to stop before raising the pantograph. The V/TE SIC has accepted that the results of this research indicate that there is no technical reason that pantographs cannot be lowered at line speed and can be raised at up to 80mph in planned operational circumstances. On behalf of the V/TE SIC, RSSB has agreed to progress the submission of a proposal for a Rule Book change for review and progression by the industry members of the Traffic Operation and Management Standards Committee. Since industry does not currently plan to raise pantographs at higher speeds (above 80mph), the FEG has agreed no further action is required to investigate the effect of raising at greater speeds. Accelerated pantograph life 'type' tests were also recommended, however the FEG concluded that further testing would not be 4 RSSB

5 required since existing maintenance regimes will be used to identify any emerging abnormalities. This research project concluded that speed limits should be established for pantograph raising in ice conditions. When introducing new designs of carrier strip or revised carbon grades with reduced metal impregnation, vertical impact testing should be carried out to confirm their suitability. Further testing will be required if plain carbon is used as part of the Energy TSI. These tests should be carried out by the carbon manufacturers. Tests conducted as part of this project have provided enough evidence to propose that no further testing is required for existing grades and the practical application will be done via compatibility assessments and in-service running. The research also noted that further simulation should be conducted for operation on other OLE types where the characteristics vary significantly from those of Mk IIIB OLE. This is limited to the heavy ex 1500V DC OLE previously installed on Manchester - Sheffield - Wath (MSW), Great Eastern (GE) and Shenfield - Chelmsford - Southend (SCS) electrifications, which represent 3-5% of the existing OLE network. This was accepted by the FEG, and RSSB has agreed that this will be incorporated into Guidance within Standards Project 09/013. Contact For more information please contact: Head of Engineering Research R&D Programme RSSB research@rssb.co.uk RSSB 5

Research Brief. Simulation and verification of results from 125mph current collection modelling for two pantographs. T841 - January 2011.

Research Brief. Simulation and verification of results from 125mph current collection modelling for two pantographs. T841 - January 2011. Research Brief Simulation and verification of results from 125mph current collection modelling for two pantographs Overview On behalf of the Vehicle / Train Energy System Interface Committee (V/TE SIC),

More information

Research Brief. Impact of higher 25kV fault currents. T873 - October Background. Aims

Research Brief. Impact of higher 25kV fault currents. T873 - October Background. Aims Research Brief Impact of higher 25kV fault currents Background Increasing the maximum fault levels at traction feeder stations has the potential to reduce the costs of electrification schemes. The potential

More information

ENE Standards Committee Chairman s presentation. Presented by David Knights 25 th January 2018

ENE Standards Committee Chairman s presentation. Presented by David Knights 25 th January 2018 ENE Standards Committee Chairman s presentation Presented by David Knights 25 th January 2018 1. Key issues from the last six months (UK standards) 1. Electrical clearances remain an issue: RSSB has agreed

More information

Research Brief. Investigation into the use of bio-diesel fuel on Britain's railways. T697 - August Overview

Research Brief. Investigation into the use of bio-diesel fuel on Britain's railways. T697 - August Overview Research Brief Investigation into the use of bio-diesel fuel on Britain's railways Overview In 2006 RSSB and the Association of Train Operating Companies (ATOC) started an investigation into the use of

More information

Compatibility Between Electric Trains and Electrification Systems

Compatibility Between Electric Trains and Electrification Systems Compatibility Between Electric Trains and Electrification Systems Synopsis Process for managing change that affects the compatibility between electric trains and electrification systems Submitted by Signatures

More information

Energy. June A guide to RSSB research

Energy. June A guide to RSSB research Energy June 2014 A guide to RSSB research Energy RSSB Copyright 2014 Rail Safety and Standards Board. This publication may be reproduced free of charge for research, private study, or for internal circulation

More information

The Project North West Electrification Programme

The Project North West Electrification Programme Assessment of Technical Specifications for Interoperability on Projects Background The European Union has mandated moving towards interoperable railways to lower boundaries for cross-eu running of trains.

More information

Council of the European Union Brussels, 18 July 2014 (OR. en)

Council of the European Union Brussels, 18 July 2014 (OR. en) Council of the European Union Brussels, 18 July 2014 (OR. en) 11932/14 ADD 1 TRANS 367 COVER NOTE From: European Commission date of receipt: 9 July 2014 To: General Secretariat of the Council No. Cion

More information

Control, Safe Use and Operation of Excavators, Loaders and Earth Moving Equipment

Control, Safe Use and Operation of Excavators, Loaders and Earth Moving Equipment Control, Safe Use and Operation of Excavators, Loaders and Earth Moving Equipment Page 1 of 14 Part A Synopsis A standard detailing the requirements for the control, safe use and operation of excavators,

More information

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 ENERGY

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 ENERGY THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 25 ENERGY Away from the mainline, there could be additional lower-spec energy options alongside AC electrification, including battery-power

More information

Electrification and Power Supply. Andrea Nardinocchi Technological Design Department Italferr S.p.A., Rome, Italy

Electrification and Power Supply. Andrea Nardinocchi Technological Design Department Italferr S.p.A., Rome, Italy Electrification and Power Supply Andrea Nardinocchi Technological Design Department Italferr S.p.A., Rome, Italy 1 RAILWAY POWER SUPPLY Electrification systems in Europe Electrification design criteria

More information

Uncontrolled When Printed Document to be superseded on 01/12/2012 Superseded by GERT8000-HB15 Iss 2 published on 01/09/2012

Uncontrolled When Printed Document to be superseded on 01/12/2012 Superseded by GERT8000-HB15 Iss 2 published on 01/09/2012 GE/RT8000/HB15 Rule Book Handbook 15 Duties of the machine controller (MC) and on-track plant operator Handbook 15 Issue 1 Valid from June 2011 Published by: RSSB Block 2 Angel Square 1 Torrens Street

More information

SAFEINTERIORS Train Interior Passive Safety for Europe

SAFEINTERIORS Train Interior Passive Safety for Europe SAFEINTERIORS Train Interior Passive Safety for Europe SAFEINTERIORS John Roberts September 2008 Project Summary Proposal full title: Train Interior Passive Safety for Europe Proposal acronym: SAFEINTERIORS

More information

Rapid Response. Lineside Signal Spacing. Railway Group Standard GK/RT0034 Issue Three Date September 1998

Rapid Response. Lineside Signal Spacing. Railway Group Standard GK/RT0034 Issue Three Date September 1998 Rapid Response Railway Group Standard Lineside Signal Spacing Synopsis This Standard specifies the minimum distance that must be provided between the first signal displaying a cautionary aspect and the

More information

Electromobility for Heavy-Duty Vehicles. Long Beach Convention Center, May 15-17, 2012 ACT Expo 2012

Electromobility for Heavy-Duty Vehicles. Long Beach Convention Center, May 15-17, 2012 ACT Expo 2012 Electromobility for Heavy-Duty Vehicles Long Beach Convention Center, May 15-17, 2012 ACT Expo 2012 Siemens AG 2012. All Siemens rights reserved. AG 2010 Forecast: The demand for mobility keeps rising

More information

Rail Safety and Standards Board

Rail Safety and Standards Board Rail Safety and Standards Board Certificate of Derogation from a Railway Group Standard (under 8.3 of the Railway Group Standards Code) Derogation Number: Applicant: Subject Matter of Derogation: RGS Number:

More information

RELEASED UNDER THE OFFICIAL INFORMATION ACT 1982

RELEASED UNDER THE OFFICIAL INFORMATION ACT 1982 Subject MINISTERIAL BRIEFING NOTE Rapid Transit in Auckland Date 1 November 2017 Briefing number BRI-1133 Contact(s) for telephone discussion (if required) Name Position Direct line Cell phone 1 st contact

More information

Powering Sydney s Future

Powering Sydney s Future Powering Sydney s Future Frequently Asked Questions December 2017 Project background Q: Why is this project needed? A: Inner Sydney is one of the most critical parts of the NSW electricity network. However,

More information

SAFEINTERIORS Train Interior Passive Safety for Europe

SAFEINTERIORS Train Interior Passive Safety for Europe SAFEINTERIORS Train Interior Passive Safety for Europe SAFEINTERIORS John Roberts November 2006 Project Summary Proposal full title: Train Interior Passive Safety for Europe Proposal acronym: SAFEINTERIORS

More information

Fast track to Sustainable Mobility. SNCF V350 CATENARY CERTIFICATION with respect to the TSI-ENE

Fast track to Sustainable Mobility. SNCF V350 CATENARY CERTIFICATION with respect to the TSI-ENE Fast track to Sustainable Mobility SNCF V350 CATENARY CERTIFICATION with respect to the TSI-ENE 1 The French Railway Network 3630 km of highspeed tracks 300 km at 270km/h 2730 km at 300km/h 600 km at 320km/h

More information

Interim Advice Note 137/10. The use of Stepped Speed Limits at Roadworks. Interim Advice Note 137/10 Stepped Speed Limits

Interim Advice Note 137/10. The use of Stepped Speed Limits at Roadworks. Interim Advice Note 137/10 Stepped Speed Limits Interim Advice Note 137/10 The use of Stepped Speed Limits at Roadworks IAN 137/10 Page 1 of 5 Nov 10 Interim Advice Note 137/10 The Use of Summary This document provides an introduction to (SSL) on the

More information

TRADE ENGINEERING. Solutions for Success. Products for the Ralway. Slip Ring Units

TRADE ENGINEERING. Solutions for Success. Products for the Ralway. Slip Ring Units TRADE ENGINEERING Carbon exhibits many operational and financial advantages over metallic materials as a linear current collector, and the benefits to user Systems are becoming increasingly apparent as

More information

Technical Memorandum. To: From: Date: October 14 th, 2018 Project #: 1302 Project Name: Subject: Distribution:

Technical Memorandum. To: From: Date: October 14 th, 2018 Project #: 1302 Project Name: Subject: Distribution: Technical Memorandum To: Tom Hanrahan Jeff Sharp From: Date: October 14 th, 2018 Project #: 1302 Project Name: Subject: Distribution: Barrie Lockhart Road LP Conformity Review Scott Young Sorbara Group

More information

Technical Strategy Leadership Group

Technical Strategy Leadership Group Agenda item: 4(a) MEETING: Technical Strategy Leadership Group DATE: 5 th June 2014 SUBJECT AUTHOR VT SIC Annual report Andy Doherty 1 Purpose 1.1 This paper presents a summary of the activities of the

More information

GEAR 2030 Working Group 1 Project Team 2 'Zero emission vehicles' DRAFT RECOMMENDATIONS

GEAR 2030 Working Group 1 Project Team 2 'Zero emission vehicles' DRAFT RECOMMENDATIONS GEAR 2030 Working Group 1 Project Team 2 'Zero emission vehicles' DRAFT RECOMMENDATIONS Introduction The EU Member States have committed to reducing greenhouse gas emissions by 80-95% by 2050 with an intermediate

More information

Summary of survey results on Assessment of effectiveness of 2-persons-in-the-cockpit recommendation included in EASA SIB

Summary of survey results on Assessment of effectiveness of 2-persons-in-the-cockpit recommendation included in EASA SIB Summary of survey results on Assessment of effectiveness of 2-persons-in-the-cockpit recommendation included in EASA SIB 2015-04 23 May 2016 EXECUTIVE SUMMARY The European Aviation Safety Agency (EASA)

More information

Proposed Dounreay - Mybster 275 kv / 132 kv

Proposed Dounreay - Mybster 275 kv / 132 kv Background Scottish Hydro-Electric Transmission Ltd (SHETL) is proposing a new 275 kilovolt (kv) (1 kilovolt = 1000volts) double circuit overhead line (OHL) between the Dounreay sub station and the new

More information

Improvements of Existing Overhead Lines for 180km/h operation of the Tilting Train

Improvements of Existing Overhead Lines for 180km/h operation of the Tilting Train Improvements of Existing Overhead Lines for 180km/h operation of the Tilting Train K. Lee, Y.H. Cho, Y. Park, S. Kwon Korea Railroad Research Institute, Uiwang-City, Korea Abstract The purpose of this

More information

UIC/ UNIFE Technical Recommendations (TecRec)

UIC/ UNIFE Technical Recommendations (TecRec) UIC/ UNIFE Technical Recommendations (TecRec) An Introduction and Overview Enno Wiebe, Manager Research Projects and Programmes, UIC European Standardisation and Regulation 2 11th UIC Sustainability Conference,

More information

Positive Energy Roads CALL FOR PROPOSALS

Positive Energy Roads CALL FOR PROPOSALS Positive Energy Roads CALL FOR PROPOSALS Deadline for submission of proposals: February 15 th, 2019 1 PURPOSE AND STRATEGIC SIGNIFICANCE 1.1 Introduction The World Road Association (PIARC) has established

More information

Best Practices in Intercity Rail An Infrastructure Manager s Perspective. Nigel Ash Managing Director, Network Rail Consulting TRB January 2014

Best Practices in Intercity Rail An Infrastructure Manager s Perspective. Nigel Ash Managing Director, Network Rail Consulting TRB January 2014 Best Practices in Intercity Rail An Infrastructure Manager s Perspective Nigel Ash Managing Director, Network Rail Consulting TRB January 2014 Outline Network Rail in Context Page 4 Britain s Classic High

More information

(Non-legislative acts) DECISIONS

(Non-legislative acts) DECISIONS 14.5.2011 Official Journal of the European Union L 126/1 II (Non-legislative acts) DECISIONS COMMISSION DECISION of 26 April 2011 concerning a technical specification for interoperability relating to the

More information

2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding

2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding 2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding By George Ardavanis, PhD Keywords: overhead catenary system (OCS), electric multiple unit (EMU), grounding and bonding (G&B), overhead contact line (OCL),

More information

M&EE Networking Group

M&EE Networking Group Published to RSSB Standards Catalogue Web page on 05/12/2015 COP0008 Issue 6 August 2015 Code of Practice for Tandem Lifting with Two Excavator Cranes M&EE Networking Group No COP0008 Published to RSSB

More information

Train Group Control for Energy-Saving DC-Electric Railway Operation

Train Group Control for Energy-Saving DC-Electric Railway Operation Train Group Control for Energy-Saving DC-Electric Railway Operation Shoichiro WATANABE and Takafumi KOSEKI Electrical Engineering and Information Systems The University of Tokyo Bunkyo-ku, Tokyo, Japan

More information

Deviation from a Railway Group Standard

Deviation from a Railway Group Standard Deviation from a Railway Group Standard (In accordance with the Railway Group Standards Code, Issue Four, part 7 and the Standards Manual, part 16) Deviation number: 16-073-DEV 1. Problem statement There

More information

Mechanical Trainstop Systems

Mechanical Trainstop Systems Mechanical Trainstop Systems Synopsis This document defines the functional requirements for mechanical trainstop systems and the requirements relating to their use on both track and trains. Signatures

More information

HarmonHy (SES ) Harmonization of Standards and Regulations for a Sustainable Hydrogen and Fuel Cell Technology

HarmonHy (SES ) Harmonization of Standards and Regulations for a Sustainable Hydrogen and Fuel Cell Technology (SES6-513542) Harmonization of Standards and Regulations for a Sustainable Hydrogen and Fuel Cell Technology a "Specific Support Action" under the 6 th Framework Programme of the European Commission Areas

More information

Module AC. AC electrified lines

Module AC. AC electrified lines GE/RT8000/AC Rule Book Module AC AC electrified lines Issue 1 April 2009 Comes into force 06 June 2009 Published by: Rail Safety & Standards Board Block 2 Angel Square 1 Torrens Street London EC1V 1NY

More information

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN SPN High Value Project PO Route RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN Document History Version Date Details Originator V0.1 20/06/2013 Initial version Chris Winch V0.2

More information

STUDY ON EURO 5 SOUND LEVEL LIMITS OF L-CATEGORY VEHICLES

STUDY ON EURO 5 SOUND LEVEL LIMITS OF L-CATEGORY VEHICLES Transmitted by the expert from the European Commission Informal document GRB-66-15 (66th GRB, 4-6 September 2017, agenda item 10) STUDY ON EURO 5 SOUND LEVEL LIMITS OF L-CATEGORY VEHICLES 66 th GRB meeting,

More information

What is model validation? Overview about DynoTRAIN WP5. O. Polach Final Meeting Frankfurt am Main, September 27, 2013

What is model validation? Overview about DynoTRAIN WP5. O. Polach Final Meeting Frankfurt am Main, September 27, 2013 What is model validation? Overview about DynoTRAIN WP5 O. Polach Final Meeting Frankfurt am Main, September 27, 2013 Contents Introduction State-of-the-art on the railway dynamic modelling Suspension modelling

More information

Control, Safe Use and Operation of Road-Rail Plant

Control, Safe Use and Operation of Road-Rail Plant Control, Safe Use and Operation of Page 1 of 13 Part A Synopsis A Standard detailing the requirements for the control, safe use and operation of road-rail plant in the railway environment. Approval and

More information

Rail Industry Standard for 750 V and 1500 V DC Overhead Lines and corresponding Rolling Stock requirements

Rail Industry Standard for 750 V and 1500 V DC Overhead Lines and corresponding Rolling Stock requirements for 750 V and 1500 V DC Overhead Lines and corresponding Rolling Stock requirements Synopsis This document specifies requirements and associated rationale and guidance at the interface between energy subsystems

More information

REDUCING THE OCCURRENCES AND IMPACT OF FREIGHT TRAIN DERAILMENTS

REDUCING THE OCCURRENCES AND IMPACT OF FREIGHT TRAIN DERAILMENTS REDUCING THE OCCURRENCES AND IMPACT OF FREIGHT TRAIN DERAILMENTS D-Rail Final Workshop 12 th November - Stockholm Monitoring and supervision concepts and techniques for derailments investigation Antonella

More information

Great Western electrification project Frequently asked questions

Great Western electrification project Frequently asked questions Great Western electrification project Frequently asked questions What are the benefits of electrification? Cleaner, quieter, more frequent and reliable trains will provide extra seats with new trains introduced

More information

Rolling Stock Subsystem and Interfaces to AC Energy Subsystem

Rolling Stock Subsystem and Interfaces to AC Energy Subsystem Rolling Stock and Interfaces to AC Energy Synopsis This document defines the interface requirements to the AC energy system for all rolling stock operating over the AC electrified railway. Copyright in

More information

Investigation into the Department for Transport s decision to cancel three rail electrification projects. Report. Department for Transport

Investigation into the Department for Transport s decision to cancel three rail electrification projects. Report. Department for Transport A picture of the National Audit Office logo Report by the Comptroller and Auditor General Department for Transport Investigation into the Department for Transport s decision to cancel three rail electrification

More information

Deviation from a Railway Group Standard (In accordance with the Railway Group Standards Code, Issue Four, part 7)

Deviation from a Railway Group Standard (In accordance with the Railway Group Standards Code, Issue Four, part 7) Deviation from a Railway Group Standard (In accordance with the Railway Group Standards Code, Issue Four, part 7) Deviation Number: 14/078/DEV 1. Start and End Date: From 26/06/2014 to 22/10/2018 2. Details

More information

RSC-G-004-B Guidelines For The Design Of Section 3 3 ELECTRIC TRACTION SYSTEMS 2

RSC-G-004-B Guidelines For The Design Of Section 3 3 ELECTRIC TRACTION SYSTEMS 2 3 ELECTRIC TRACTION SYSTEMS 2 3.1. SAFE FOR PEOPLE 2 3.1.1. Electric Traction System 2 3.1.2. Protection against unwanted access 2 3.1.3. Fencing 2 3.1.4. On bridges and other structures 2 3.1.5. At level

More information

COMMISSION REGULATION (EU) / of XXX

COMMISSION REGULATION (EU) / of XXX EUROPEAN COMMISSION Brussels, XXX [ ](2018) XXX draft COMMISSION REGULATION (EU) / of XXX amending Regulation (EU) No 548/2014 of 21 May 2014 on implementing Directive 2009/125/EC of the European Parliament

More information

Development of an actively controlled, acoustically optimised single arm pantograph

Development of an actively controlled, acoustically optimised single arm pantograph Development of an actively controlled, acoustically optimised single arm pantograph Authors Dr. Wilhelm Baldauf 1), Rene Blaschko 2), Dr. Wolfgang Behr 1), Dr. Christoph Heine 1), Michael Kolbe 1) 1) Deutsche

More information

Work Package 3 More electrification in Europe: directions from the ELIPTIC transferability exercise

Work Package 3 More electrification in Europe: directions from the ELIPTIC transferability exercise Work Package 3 More electrification in Europe: directions from the ELIPTIC transferability exercise Maria Vittoria Corazza, Antonio Musso, UNIROMA1 ELIPTIC Final Conference Bremen, April 26-27 th 2018

More information

LoCITY Low Emission Commercial Vehicle programme

LoCITY Low Emission Commercial Vehicle programme 1 1 DECEMBER 2016 LoCITY Low Emission Commercial Vehicle programme Tim Ward Freight and Fleet Communications and Engagement Manager Transport for London 2 Context 1952 Now 5 Impacts of air pollution Long

More information

DESIGN PRACTICE NOTE MOBILITY VEHICLE SIMULATIONS AT PEDESTRIAN CROSSINGS

DESIGN PRACTICE NOTE MOBILITY VEHICLE SIMULATIONS AT PEDESTRIAN CROSSINGS Approval Amendment Record Approval Date Version Description 21/05/2015 1 Initial issue under MTM 04/08/2016 2 Clearance for mobility vehicles amended and details for fencing and paving added PRINTOUT MAY

More information

Railway noise mitigation factsheet 01: Overview of railway noise

Railway noise mitigation factsheet 01: Overview of railway noise Railway noise mitigation factsheet 01: Overview of railway noise 1.1 Noise sources and indicative noise levels Exterior noise sources on high-speed trains can be broadly categorised as follows and are

More information

Gröna Tåget. (Eng: Green Train) Overview and Technical Aspects

Gröna Tåget. (Eng: Green Train) Overview and Technical Aspects Gröna Tåget (Eng: Green Train) Overview and Technical Aspects Evert Andersson, professor Programme coordinator - Technology everta@kth.se evertan@telia.com Background Current Swedish 12-year plan (2004-2015)

More information

Update on Electric Vehicle (EV) Test Bed Programme. Jan 2011

Update on Electric Vehicle (EV) Test Bed Programme. Jan 2011 Update on Electric Vehicle (EV) Test Bed Programme Jan 2011 Key considerations behind EVs test bedding Objectives of EVs test bed Updates on the EV test bed TIDES Plus Incentive Scheme Conclusion EV Test

More information

Uncontrolled When Printed Document comes into force 06/12/2014 Supersedes GERT8000-T10 Iss 3 on 06/12/2014

Uncontrolled When Printed Document comes into force 06/12/2014 Supersedes GERT8000-T10 Iss 3 on 06/12/2014 GE/RT8000/T10 Rule Book Module T10 Duties of a designated person () and people working on rail vehicles Issue 4 September 2014 Comes into force 06 December 2014 Published by: RSSB Block 2 Angel Square

More information

CER/EIM Position Paper Ballast Pick-up due to Aerodynamic Effects. October Version 1.0

CER/EIM Position Paper Ballast Pick-up due to Aerodynamic Effects. October Version 1.0 CER/EIM Position Paper Ballast Pick-up due to Aerodynamic Effects October 2015 Version 1.0 Introduction Aerodynamic loads on the trackbed generated by the passing of trains at high speed may cause individual

More information

GENERATOR SEAL OIL SYSTEM

GENERATOR SEAL OIL SYSTEM GENERATOR SEAL OIL SYSTEM Eskom power utility utilized Flownex SE simulation capabilities to mitigate system shutdowns caused by generator hydrogen (H 2 ) seal ring failures. Engineers modelled the hydrogen

More information

Presentation of the European Electricity Grid Initiative

Presentation of the European Electricity Grid Initiative Presentation of the European Electricity Grid Initiative Contractors Meeting Brussels 25th September 2009 1 Outline Electricity Network Scenario European Electricity Grids Initiative DSOs Smart Grids Model

More information

M&EE Networking Group

M&EE Networking Group COP0025 Issue 3 January 2015 Code of Practice for Brake Testing of RRVs M&EE Networking Group No COP0025 M&EE Networking Group Code of Practice for Issue 3 Brake Testing of RRVs Page 2 of 19 Document revision

More information

Modernising the Great Western railway

Modernising the Great Western railway Report by the Comptroller and Auditor General Department for Transport and Network Rail Modernising the Great Western railway HC 781 SESSION 2016-17 9 NOVEMBER 2016 4 Key facts Modernising the Great Western

More information

Geneva, 67th SC.2 Session October 2013 High Speed Trains Master Plan

Geneva, 67th SC.2 Session October 2013 High Speed Trains Master Plan Geneva, 67th SC.2 Session 23 25 October 2013 High Speed Trains Master Plan Work Package I Work Package II Work Package III Project Management Review of related Work Socio economic framework of the ECE

More information

The Low Carbon Vehicle Action Plan. Robert Anderson Low Carbon Fleet Advisor Cenex

The Low Carbon Vehicle Action Plan. Robert Anderson Low Carbon Fleet Advisor Cenex The Low Carbon Vehicle Action Plan Robert Anderson Low Carbon Fleet Advisor Cenex Introduction to Cenex Running projects and programmes focused on accelerating the deployment of low carbon vehicles Managing

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM OCS Requirements TM 3.2.1 Prepared by: Signed document on file 09 July 09_ Xavier de Vimal Date Checked by: Signed document on file 10 July 09_ Richard Schmedes Date Approved by: Signed

More information

Guide for the application of the CR ENE TSI

Guide for the application of the CR ENE TSI European Railway Agency According to Framework Mandate C(2007)3371 final of 13/07/2007 Reference in ERA: ERA/GUI/07-2011/INT Version in ERA: 1.00 Date: 26 August 2011 Document prepared by Document type:

More information

March 18, Samira Monshi Seungwon Noh Wilfredo Rodezno Brian Skelly

March 18, Samira Monshi Seungwon Noh Wilfredo Rodezno Brian Skelly March 18, 2013 Samira Monshi Seungwon Noh Wilfredo Rodezno Brian Skelly Overview Project Objective Stakeholder Feedback Review of Alternative Jet Fuel Supply Chain Options Under Consideration 2 Project

More information

Options for Autonomous Power for the UK (Railways)

Options for Autonomous Power for the UK (Railways) Giles Pettit, Technical Director, Stephen Kent, Research Fellow, University of Birmingham The British Context Page 1 The Four Cs Carbon Carbon (taken to include pollutants): need to cut CO2 backlash against

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

T1107 Trial of Sander Configurations and Sand Laying Rates Update

T1107 Trial of Sander Configurations and Sand Laying Rates Update T1107 Trial of Sander Configurations and Sand Laying Rates Update Presented by Liam Purcell (Ricardo Rail) & Andrew Lightoller (DB-ESG) 4 December 2017 Contents Sand on the Railway Project Objectives The

More information

International Crane Stakeholder Assembly. - Guidance - Lifting of Persons with Mobile Cranes

International Crane Stakeholder Assembly. - Guidance - Lifting of Persons with Mobile Cranes ICSA N003 International Crane Stakeholder Assembly - Guidance - Lifting of Persons with Mobile Cranes Members are: Association of Equipment Manufacturers [AEM] The Crane Industry Council of Australia [CICA]

More information

Chapter 4. HS2 Route Capacity and Reliability. Prepared by Christopher Stokes

Chapter 4. HS2 Route Capacity and Reliability. Prepared by Christopher Stokes Chapter 4 HS2 Route Capacity and Reliability Prepared by Christopher Stokes 4 HS2 ROUTE CAPACITY AND RELIABILITY Prepared by Christopher Stokes 4.1 This chapter relates to the following questions listed

More information

WATFORD LOCAL PLAN PART 2. Review of Car Parking Policy and Standards. Evidence Base. February 2012

WATFORD LOCAL PLAN PART 2. Review of Car Parking Policy and Standards. Evidence Base. February 2012 WATFORD LOCAL PLAN PART 2 Review of Car Parking Policy and Standards Evidence Base February 2012 1.0 Background 1.1 The Watford District Plan 2000 contains various policies relating to the provision of

More information

CREATING HIGH-SPEED RAILWAYS. Track, Overhead Catenary and Substations. A MAJOR RAIL INFRASTRUCTURE CONSTRUCTION AND MAINTENANCE COMPANY

CREATING HIGH-SPEED RAILWAYS. Track, Overhead Catenary and Substations. A MAJOR RAIL INFRASTRUCTURE CONSTRUCTION AND MAINTENANCE COMPANY CREATING HIGH-SPEED RAILWAYS Track, Overhead Catenary and Substations. East-European high-speed line A MAJOR RAIL INFRASTRUCTURE CONSTRUCTION AND MAINTENANCE COMPANY EXPERIENCE MAKES THE DIFFERENCE Colas

More information

Electrification Clearance Solutions

Electrification Clearance Solutions Electrification Clearance Solutions Electrification Clearance Solutions Overhead line electrification of an existing railway often presents problems at structures where the available space is limited.

More information

The DLR Project Next Generation Train (NGT)

The DLR Project Next Generation Train (NGT) > UIC Energy Efficiency Workshop, Rome > Holger Dittus The DLR Project Next Generation Train (NGT) > 04/10/2017 DLR.de Chart 1 The DLR Project Next Generation Train (NGT) Holger Dittus UIC Energy Efficiency

More information

POSITION PAPER Version 3.0

POSITION PAPER Version 3.0 POSITION PAPER Version 3.0 Revision of the Technical Specification for Interoperability / Energy (ENE) Brussels, September 26 th, 2012 1. REFERENCE DOCUMENT UNION RAIL SYSTEM - SUBSYSTEM Energy - TSI Energy

More information

BORAL CONCRETE GLENORIE

BORAL CONCRETE GLENORIE BORAL CONCRETE GLENORIE > Glenorie Progress Association meeting 14 March 2018 Glenorie RSL Club Glenorie A recap of our last discussion (Oct 2017)... Who are we? Boral Concrete (NSW/ACT) is part of the

More information

Delegations will find attached document D036128/02.

Delegations will find attached document D036128/02. Council of the European Union Brussels, 18 December 2014 (OR. en) 16977/14 TRANS 597 COVER NOTE From: European Commission date of receipt: 15 December 2014 To: No. Cion doc.: D036128/02 Subject: General

More information

French - IFSTTAR activities

French - IFSTTAR activities French - IFSTTAR activities ERMES Brussels, 26-27 September 2013 Yao LIU, Michel ANDRÉ Laboratoire Transports et Environnement 1 French activities (Ifsttar Lab. Transport & Environment) Emission factors

More information

Figure 1 Organisation of INNOTRACK

Figure 1 Organisation of INNOTRACK The EU-project INNOTRACK a description of highlights and how they have been implemented BjörnPaulsson 1, UIC, Paris France, Jay Jaiswal 2, Tata Steel Europe,Rotherham UK, Anders Ekberg 3, Chalmers, Gothenburg

More information

Police Operations: Tachograph Equipment Inspection

Police Operations: Tachograph Equipment Inspection Higher National Unit Specification General information for centres Unit code: F0N9 35 Unit purpose: This Unit is designed to enable candidates to analyse tachograph recording equipment and use the information

More information

Light Rail Review 2011

Light Rail Review 2011 Ref: LR Applrg Winter 09 v1 Light Rail Review 2011, 12 th July 2011 This meeting by invitation only, where MPs, Stakeholders etc, wwwapplrgukcouk Email lightrailuk@aolcom wwwlightrailukcom 1 Ref: LR Applrg

More information

SUBSIDIARY BODY FOR SCIENTIFIC AND TECHNOLOGICAL ADVICE Fourteenth session Bonn, July 2001 Item 3 (b) of the provisional agenda

SUBSIDIARY BODY FOR SCIENTIFIC AND TECHNOLOGICAL ADVICE Fourteenth session Bonn, July 2001 Item 3 (b) of the provisional agenda UNITED NATIONS Distr. GENERAL 11 July 2001 ENGLISH ONLY SUBSIDIARY BODY FOR SCIENTIFIC AND TECHNOLOGICAL ADVICE Fourteenth session Bonn, 16-27 July 2001 Item 3 (b) of the provisional agenda REPORTS ON

More information

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min

Draft Agenda. Item Subject Responsible Time. 4. GAS INFORMATION SERVICES PROJECT IMO 10 min. 5. OPTIONS FOR GAS BULLETIN BOARD SYSTEM IMO 15 min Gas Advisory Board Draft Agenda Meeting No. 1 Location: Parmelia Hilton, Swan B Room 14 Mill Street, Perth WA 6000 Date: 20 December 2011 Time: 11:15am 12:15pm Item Subject Responsible Time 1. WELCOME

More information

Low Emissions Towns and Cities Programme

Low Emissions Towns and Cities Programme Low Emissions Towns and Cities Programme Developing a Low Emissions Strategy for the West Midlands IAPSC 1 st December 2015 Andrew Whittles, Low Emission Strategies Ltd Content Recap of the LETCP Overview

More information

Control, Safe Use and Operation of Forklift Trucks and Sideloaders

Control, Safe Use and Operation of Forklift Trucks and Sideloaders Control, Safe Use and Operation of Forklift Trucks and Sideloaders British Railways Board Page 1 of 12 Part A Synopsis A standard detailing the requirements for control, safe use and operation of forklift

More information

Electric Roads for HDVs

Electric Roads for HDVs Electric Roads for HDVs Scania A European perspective on Barriers & Solutions for future market successes December 3 rd 2015 CEC & UC Davis Workshop siemens.com/answers Outline Agenda What problem are

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

NWE /PCR Day-Ahead Price Coupling

NWE /PCR Day-Ahead Price Coupling NWE Price Coupling Stakeholder Meeting June 14, London NWE /PCR Day-Ahead Price Coupling Market Consultation & es and timings Disclaimer: These timings are still under discussion and will be confirmed

More information

Q&A ON EMISSIONS TESTING

Q&A ON EMISSIONS TESTING Q&A ON EMISSIONS TESTING 1. How does ACEA react to the VW situation?... 1 2. How does the current lab test work?... 1 3. Why are there differences between the lab tests and real-world emissions?... 3 4.

More information

Electrification Asset Usage Charge. Presentation to TESG. Matt Skinner, Development Manager 11 th March 2013

Electrification Asset Usage Charge. Presentation to TESG. Matt Skinner, Development Manager 11 th March 2013 Electrification Asset Usage Charge Presentation to TESG Matt Skinner, Development Manager 11 th March 2013 1 Background Purpose of the charge The Electrification Asset Usage Charge (EAUC) is designed to

More information

H2020 (ART ) CARTRE SCOUT

H2020 (ART ) CARTRE SCOUT H2020 (ART-06-2016) CARTRE SCOUT Objective Advance deployment of connected and automated driving across Europe October 2016 September 2018 Coordination & Support Action 2 EU-funded Projects 36 consortium

More information

Electric Vehicles and the Environment (EVE IWG)

Electric Vehicles and the Environment (EVE IWG) Submitted by the EVE informal working group Electric Vehicles and the Environment () 1 Informal document GRPE-77-28 77 th GRPE, 6-8 June 2018 Agenda item 9 REPORT TO GRPE 77 TH SESSION Current Mandate

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM Pantograph Clearance Envelopes TM 3.2.3 Prepared by: Signed document on file 21 Mar 08 Xavier de Vimal Date Checked by: Signed document on file 15 July 09 Richard Schmedes Date Approved

More information

Track Circuit Assister Configuration for Rail Vehicles

Track Circuit Assister Configuration for Rail Vehicles Track Circuit Assister Configuration for Rail Synopsis This Standard mandates where TCAs shall be fitted onto a vehicle and how they shall be set up. It also contains the requirements for testing a TCA.

More information

June Safety Measurement System Changes

June Safety Measurement System Changes June 2012 Safety Measurement System Changes The Federal Motor Carrier Safety Administration s (FMCSA) Safety Measurement System (SMS) quantifies the on-road safety performance and compliance history of

More information

Uncontrolled When Printed Supersedes GERT8000-DC Iss 2 on 01/03/2014. Module DC. GE/RT8000/DC Rule Book. DC electrified lines. Issue 3.

Uncontrolled When Printed Supersedes GERT8000-DC Iss 2 on 01/03/2014. Module DC. GE/RT8000/DC Rule Book. DC electrified lines. Issue 3. GE/RT8000/DC Rule Book Module DC DC electrified lines Issue 3 March 2014 Comes into force 07 June 2014 Conventions used in the Rule Book Example A black line in the margin indicates a change to that rule

More information