MEDGRID. Lot 1: Western corridor Phase 4 presentation. F. M. Echavarren, L. Rouco M. Rivier, A. Ramos, L. Olmos Universidad Pontificia Comillas

Size: px
Start display at page:

Download "MEDGRID. Lot 1: Western corridor Phase 4 presentation. F. M. Echavarren, L. Rouco M. Rivier, A. Ramos, L. Olmos Universidad Pontificia Comillas"

Transcription

1 MEDGRID Lot 1: Western corridor Phase 4 presentation F. M. Echavarren, L. Rouco M. Rivier, A. Ramos, L. Olmos Universidad Pontificia Comillas J. Dubois, V. Lambillon, L. Rese Tractebel Engineering PARIS,

2 Contents Introduction, objectives, methodology Identification of interconnection scenarios +1 GW & +2 GW presented today Assessment of the investment costs of interconnection links Assessment of the investment tcosts associated dto the internal reinforcements within each involved country (Algeria, Morocco, Portugal, Spain) Identification and assessment of several technical options for each interconnection scenario 2

3 1 Introduction, objectives, methodology

4 Objectives & assumptions Objective To assess the grid investment costs associated to an increase of +1GW, +2GW, +3GW of transit from West Maghreb (WMA) (Morocco and Algeria) towards France through the Iberian Peninsula (IB) South to North flows Reference scenario: Main assumptions Networks to be analyzed are the Moroccan, Algerian, Portuguese and Spanish ones The French network is not considered, although the required interconnection links between Spain and France are included. Catalonian part of Spain and South East part of France (Marseille) Basque part of Spain and the south part of Bretagne (Nantes) 4

5 Methodology Build the reference scenario Network TYNDP, National Plans & TSO inputs Expansion Planning scenario Summer peak demand with high renewable generation in the south of Spain Compute the NTC value between West Maghreb and Spain France border, for the reference 22 scenario. Available transit over the commercial transactions already foreseen in MW between Spain & France since the FR SP 4GW NTC are fully loaded by Portuguese Spain renewable export requirements 700 MW between Morocco & Spain (N 1 criterion on the AC cable) 0 MW between Algeria & Spain WesternMaghreb France NTC is therefore considered to be zero. The reference base case for the study: 4 GW of exchanges SP FR 0 GW of exchanges MO SP 5

6 Methodology Identification of possible WMA IB FR interconnection scenarios SP FR; MO SP; MO PT; DZ SP Assessment of the investment costs for each interconnection link solution Assessment of the investment cost of associated to internal reinforcements needed in each country to cope with a +1GW, +2GW, +3GW exportation or transit AC load flow calculations in both N and N 1 conditions (+ N 2 for some double circuit) following countries security standards Dynamic analyses are out of scope Identification and assessment of several technical options for each interconnection scenario 6

7 2 Id tifi ti f Identification of interconnection scenarios

8 Analyzed Options To increase the interconnection capacity, different options are analyzed: Use of the existing AC MO SP cables New MO SP AC cable Converting part of the current MO SP to an HVDC connection New MO SP HVDC connection New MO PT HVDC connection New DZ SP HVDC connection New SP FR HVDC connections Options are built upon combination of these alternatives for each +1GW, +2GW, +3GW case study 15 scenarios have been developed to cover a wide range of possibilities and compare costs 8

9 Considered Scenarios Exportation Scenario level # +1 1GW +2 2GW South-North links Transit over Interconections [MW] Production origin Algérie Maroc 1 Maroc Espagne A/1B/1C 1bis Maroc Portugal D 2 Algérie Espagne A 3 Maroc Espagne A/3B/3C/3D 4 Maroc Espagne A/4B/4C/4D 5 Maroc Espagne 1000 Maroc Portugal A/5B 6 Maroc Espagne 1000 Maroc Portugal A/6B 7 Maroc Espagne 1000 Algérie Espagne A/7B Technical Solution Option 9

10 Considered Scenarios Exportation Scenario level # +3 GW South-North links Transit over Interconections [MW] Production origin Algérie Maroc 8 Maroc Espagne Maroc Espagne 2000 Maroc Portugal Maroc Espagne 2000 Maroc Portugal Maroc Espagne 2000 Algérie Espagne Maroc Espagne 1000 Algérie Espagne Maroc Espagne 1000 Algérie Espagne Maroc Espagne Maroc Portugal Algérie Espagne 1000 Maroc Espagne Maroc Portugal Algérie Espagne 1000 Technical Solution Option 10

11 West Maghreb Iberian Peninsula interconnection options 11

12 3 Assessment of interconnection links

13 MO SP interconnection Length (km) Extension to Cabra total submarine km M Technology Invest. Costs M AC line 400kV 135 1GW HVDC LCC bipolar 400 kv 200 1GW HVDC VSC bipolar 350 kv 185 1GW HVDC VSC symmetrical 350 kv 240 Convert to 1GW HVDC link LCC bipolar 500 kv 140 VSC bipolar 350 kv 193 VSC symmetrical 350 kv

14 MO PT interconnection Length (km) total submarine Technology Invest. Costs M 1GW HVDC LCC bipolar 500 kv 430 1GW HVDC VSC bipolar 400 kv 515 1GW HVDC VSC symmetrical 400 kv

15 DZ SP interconnection Length (km) Terga- Carril total submarine Technology Invest. Costs M 1GW HVDC LCC bipolar 500 kv 485 1GW HVDC VSC bipolar 400 kv 580 1GW HVDC VSC symmetrical 400 kv

16 SP FR interconnection Routes Length (km) Total Submarine Vandellós - Aramon Gatica - Cordemais Technology Invest Costs M 1GW HVDC LCC bipolar 500 kv 735 1GW HVDC VSC bipolar 400 kv 820 1GW HVDC VSC symmetrical 400 kv

17 4a Assessment of internal reinforcements SPAIN

18 Analysis Spain Analysis N 1 and N 2 for some double circuits Focus on the Andalucia zone Two scenarios of exchanges with Portugal GW Injection of +1GW & +2GW in several alternative 400kV nodes Arcos de la Frontera Guillena Candidates Valdecaballeros to link with Guadalquivir Medio (Guadame) Morocco Puerto de la Cruz Romica Olmedillo Candidates Litoral Ribina Carril to link with Algeria 18

19 SPAIN internal reinforcements 19

20 SPAIN Internal reinforcements +1GW Connection point Description Costs M Pto Cruz (+1GW MO SP) Tavira (+1GW MO PT) 400KV AC single circuit line PtoCruz Pinar 76 TajoEncantanda 140 km Upgrading 400kV AC line to double circuit 53 5,3 34 km 20

21 SPAIN Internal reinforcements +2GW Connection point Description Costs M Pto Cruz (+2GW MO SP) 400KV AC double circuit line PtoCruz Pinar 110 TajoEncantanda 140 km 400KV AC single circuit itline PtoCruz 55 Pinar ArcosFrontera 94km 21

22 4b Assessment of internal reinforcements PORTUGAL

23 PORTUGAL internal reinforcements +1GW Description Costs M Upgrading 150kV to 400KV AC sing. circ. line + 150kV line 122km 70 Upgrading 1 circ. to 2 circ 400KV AC 34km 23

24 4c Assessment of internal reinforcements Morocco & Algeria

25 TITLE OF THE PRESENTATION Objectives & Methodology 09 5 Objective is to evaluate the reinforcements required in Morocco and Algeria to evacuate power from generation sites to submarine cables. Reinforcement depends on Power transferred, location of generation sites and connections of submarine cables. Study is performed for the 15 scenarios identified Definition of reinforcements required on basis of: Distribution of generation and exportation as defined in scenario AC load flow calculations in both N and N-1 conditions Respect voltage magnitude constraints and branch overload criteria defined by the TSOs Determination of losses for each scenario on basis of OPF Dynamic analyses are out of scope 25

26 Interconnection Options for Morocco Tavira Meloussa Tarifa Dar Chaoui 26

27 Additional Generation Algeria: spread among 9 different power plants Morocco: occo concentrated ce in Agadir, Laayoune and Tizgui 27

28 Internal Network Reinforcements Algeria and Morocco Internal Reinforcements.14 8 Algeria (+1GW, +2GW) Minimal reinforcement needed (total cost of 4MEUR) Transmission i losses are not highly impacted by the additional generation/export (between 2 and 4% of power exchanged) Reason: Highly meshed network and distributed generation 28

29 TITLE OF THE PRESENTATION Internal Reinforcements 09 9 Morocco (+1GW) Investment required: 340km of 400kV line Cost of investment around 120MEUR Losses around 8% of power exchanged Reason: Generation far from submarine cable Relatively linear and weak HV network 29

30 TITLE OF THE PRESENTATION Internal Reinforcements 09 0 Morocco (+2GW + 3GW) Significant investments in network reinforcements: scenarios with up to 3000 km of new OHLs Cost between 600MEUR and 1000MEUR Level of transmission losses are very high Level of losses are prohibitive in certain scenarios (up to 20% of power exchanged) Additional problems may arise in these scenarios (such as power system stability issues) Reason: Generation far from submarine cable Relatively linear and weak HV network 30

31 Summary of Internal Reinforcements Country LI/TF Bus 1 Bus 2 Vnom [kv] ID Length [km] MVA Cost [MEUR] +1 GW +2 GW +3 GW Scenario LI OUALILI TIZGUI X X X OUALILI TIZGUI LI X X X X X X X X X X X OUALILI TIZGUI LI OUALILI TIZGUI X X X X X X LI OUALILI TIZGUI OUALILI TIZGUI X X LI OUALILI D.CHAOUI X X X X X X X X X X LI OUALILI BOURDIM X X OUALILI BOURDIM LI X X OUALILI BOURDIM LI TIZGUI CHEMAIA X X X X X X X X Morocco LI MEDIOUNA OUALILI X X X X X X MEDIOUNA OUALILI LI X X MEDIOUNA OUALILI LI MELOUSSA OUALILI X X X X LI MELOUSSA OUALILI MELOUSSA OUALILI X X LI MELOUSSA TAHADART X X LI TAHADART D.CHAOUI X X LI CHEMAIA AGADIR X X LI C.T.M T.MELLIL X X X X X X X X LI CIMAT MGHILA X X LI FOUARAT SK ARBAA X X X X X Algeria TF MACTAA MACTAA 220/ X X X X X X X X X X X Total Cost [MEUR]

32 Summary of Transmission Losses Morocco Algeria Scenario Total Losses [MW] Total Losses [%] Diff. from Ref. [MW] Diff. from Ref. [%] Additional Losses over Additional Generation [%] Scenario Total Losses [MW] Total Losses [%] Diff. from Ref. [MW] Diff. from Ref. [%] Additional Losses over Additional Generation [%] Ref % % % % 8.3% % % % % 12.7% % % 19.5% % % 12.4% % % 18.9% % % 7.4% % % % % 10.8% % % 10.7% % % 16.2% % % 11.5% % % 8.1% % % 6.8% % % 11.4% % % 16.4% Ref % 1.01% % 0.00% % % % % 1.90% % % % % 4.10% % % % % 4.10% % % 1.90% % % 2.15% % % % % % % 4.20% % % 2.30% % % 2.85% % % 2.90% % % 2.40% % % 4.35% 32

33 5 Identification and assessment of several technical options for each interconnection scenario

34 Sc Description Investment Costs M 2ª (**) (--) DZ-SP: Invest 1GW HVDC 500kV VSC SYM. link SP-FR 735 DZ-SP 520 DZ GW Sc Description Investment Costs M 1A MO-SP: Usethe SP-FR 735 (*) current 2x700 MO 120 MVA AC lines SP 75 1B (**) MO-SP: Invest 1x700MWVA 400kV AC line 1C MO-SP: Invest (**) 1GW HVDC 350kV VSC SYMMET. link 930 SP-FR 735 MO 120 MO-SP 135 SP SP-FR 735 MO 120 MO-SP 200 SP Sc Description Investment Costs M 1D MO-PT: Invest SP-FR GW (**) 1GW HVDC MO-PT GW (-) 500kV VSC PT 70 SYMMET. link SP 6 (*) () Triggering of 300MW for NTC 1GW (**) NTC MA-IB 1.4GW (-) Extra invest. 75M SP if no trig. when MO-PT fails Instituto (--) Extra de Investigación invest. 75M Tecnológica SP & 115 M MO if no trig. when DZ-SP fails MO

35 +2 GW (*) () Triggering of 600MW for NTC 2GW +2GW Sc Description Investment Costs M 3A MO-SP: Invest SP-FR ª 1x700MW AC MO-SP 135 (*) additional line 3B 4B MO SP MO-SP: Convert SP-FR 1470 current 2x700 MW MO-SP 280 AC in 1x700 MW MO AC + 2GW HVDC SP 165 BIPOLAR link C MO-SP: Invest 4C 1GW HVDC (*) 350kV LCC BIPOLAR link 3D 4D MO-SP: Convert current 2x700 MW +1GW +1GW AC in 3GW HVDC SP-FR 1470 MO-SP 185 MO SP SP-FR 1470 MO-SP 450 MO VSC SYMMET. SP

36 +2 GW (*) () Trig of 300MW for NTC 2GW (**) NTC MA-IB 2.4GW (-) Extra invest. 95M SP if no trig. when MO-PT fails Sc Description Investment Costs M 5A 6A (*) MO-SP: use current 2x700MW AC MO-PT: invest 1GW HVDC link BIPOLAR SP-FR 1470 MO-PT 420 MO PT 70 SP 80 5B MO-SP: Invest SP-FR B 1x700MW AC MO-PT 450 (**) additional line SP-FR 135 (-) 2x700MW AC MO-PT: invest 1GW HVDC link PT 70 +2GW SYMMET. SP 80 +1GW +1GW MO

37 +2 GW (*) () Trig of 300MW for NTC 2GW (**) NTC MA-IB 2.4GW (--) Extra invest. 75M SP & 115 M MO if no trig. when DZ-SP fails +1GW +1GW Sc Description Investment Costs M 7A (*) MO-SP: use current 2x700MW AC DZ-SP: invest 1GW HVDC link BIPOLAR SP-FR 1470 DZ-SP 485 MO 215 SP B MO-SP: Invest SP-FR 1470 (**) 1x700MW AC DZ-SP 520 (--) additional line MO-SP 135 2x700MW AC MO 215 DZ-SP: invest 1GW SP 75 HVDC link SYMMET

38 Thank you! 38

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS Interconnection Feasibility Study Report GIP-023-FEAS-R1 Generator Interconnection Request # 23 100 MW Wind Generating Facility Inverness (L6549), NS February 16, 2006 Control Centre Operations Nova Scotia

More information

Interconnection between Arab countries

Interconnection between Arab countries Interconnection between Arab countries Eng. Fawzi Kharbat Secretary General AUE Enabling renewable energy in the electricity systems workshop 16 April 2014 Tunis 1 Arab Union of Electricity Date of Establishment:

More information

Regional Cooperation Infrastructure Development and Operation. EU Energy Governance. Olaf Ziemann Member of ENTSO-E s System Operations Committee

Regional Cooperation Infrastructure Development and Operation. EU Energy Governance. Olaf Ziemann Member of ENTSO-E s System Operations Committee Regional Cooperation Infrastructure Development and Operation EU Energy Governance 30 April 2014, Berlin Olaf Ziemann Member of ENTSO-E s System Operations Committee About ENTSO-E 41 TSOs from 34 countries

More information

Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances

Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances Ukujima Photovoltaic Park 400 MW Stable Integration of a 400MW Photovoltaic Farm into the Japanese Power System Challenges and Chances 29 Juli 2014 Page 1 Characteristics of the Project Parameter Detail

More information

Renewable Energy Development in the Mediterranean Region Renewable Energy Investments In The Mediterranean And Beyond

Renewable Energy Development in the Mediterranean Region Renewable Energy Investments In The Mediterranean And Beyond Dott. Matteo Codazzi Milano, 30.10.2017 Renewable Energy Development in the Mediterranean Region Renewable Energy Investments In The Mediterranean And Beyond Milano, CESI has a solid track record in RES

More information

North-South Interconnections in Central-East and South- East Europe

North-South Interconnections in Central-East and South- East Europe European Network of Transmission System Operators for Electricity North-South Interconnections in Central-East and South- East Europe Building power bridges between Eastern and Western Europe; relieving

More information

France-Spain. Public participation leaflet. across the Bay of Biscay. August interconnection.

France-Spain. Public participation leaflet. across the Bay of Biscay. August interconnection. Electricity France-Spain across the Bay of Biscay Public participation leaflet August 017 www.inelfe.eu The sole responsibility of this publication lies with the author. The European Union is not responsible

More information

HVDC Solutions. for Integration of the Renewable Energy Resources. Marcus Haeusler HVDC Lead Engineer. siemens.com/energy/power-transmission

HVDC Solutions. for Integration of the Renewable Energy Resources. Marcus Haeusler HVDC Lead Engineer. siemens.com/energy/power-transmission HVDC Solutions for Integration of the Renewable Energy Resources Marcus Haeusler HVDC Lead Engineer siemens.com/energy/power-transmission Agenda Principles of HVDC operation HVDC converter types HVDC configurations

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment For NPCC Governmental / Regulatory Affairs Advisory Group May 21 st, 2009 ON IT Executive Summary Engineers from Con

More information

Transmission Grid Development & Investment Planning on EHV Level in Germany

Transmission Grid Development & Investment Planning on EHV Level in Germany Transmission Grid Development & Investment Planning on EHV Level in Germany February, 27th, 2018 Michael Jesberger 1 Kilometer (km) = 0,602 miles 1 Euro = 1,22 $ (Februry, 8th, 2018) March 2016 TenneT

More information

New Power Flow Controller for Congestion Management and Reliability Improvement in Transmission and Distribution Systems

New Power Flow Controller for Congestion Management and Reliability Improvement in Transmission and Distribution Systems New Power Flow Controller for Congestion Management and Reliability Improvement in Transmission and Distribution Systems Alberto Del Rosso EPRI CIGRE US National Committee 204 Grid of the Future Symposium

More information

Raphael Görner, Head of Marketing & Sales, Grid Systems Germany Building bridges with HVDC Solar Energy for Science

Raphael Görner, Head of Marketing & Sales, Grid Systems Germany Building bridges with HVDC Solar Energy for Science Raphael Görner, Head of Marketing & Sales, Grid Systems Germany 20.05.2011 Building bridges with HVDC Solar Energy for Science May 20, 2011 Slide 1 Europe 20XX Scenario ABB s DC grid vision already in

More information

Introduction to transmission network characteristics - technical features. Slobodan Markovic EKC Athens,

Introduction to transmission network characteristics - technical features. Slobodan Markovic EKC Athens, Introduction to transmission network characteristics - technical features Slobodan Markovic EKC Athens, 06.03.2017 1 MAIN ISSUES The map shows the region that will be included in the network modelling

More information

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui Transmission Grid Reinforcement with Embedded VSC-HVDC Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui Outline Introduction HVDC-Light Transmission Technologies Embedded VSC-HVDC for AC Grid

More information

Cigre SC B4 Activities Towards HVDC Grids. HVDC Grid Workshop Belgium

Cigre SC B4 Activities Towards HVDC Grids. HVDC Grid Workshop Belgium Cigre SC B4 Activities Towards HVDC Grids Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics HVDC Grid Workshop Belgium 2014 1 Contents Why build HVDC Grids? Types of HVDC

More information

TABLE OF CONTENTS. Table of contents. Page ABSTRACT ACKNOWLEDGEMENTS TABLE OF TABLES TABLE OF FIGURES

TABLE OF CONTENTS. Table of contents. Page ABSTRACT ACKNOWLEDGEMENTS TABLE OF TABLES TABLE OF FIGURES Table of contents TABLE OF CONTENTS Page ABSTRACT ACKNOWLEDGEMENTS TABLE OF CONTENTS TABLE OF TABLES TABLE OF FIGURES INTRODUCTION I.1. Motivations I.2. Objectives I.3. Contents and structure I.4. Contributions

More information

HVDC Systems in India

HVDC Systems in India HVDC Systems in India Outline Introduction HVDC Systems presently in operation Main Data/Salient Features Upcoming Projects Future Challenges Transmission Network - Present 765kV/400kV lines: about 1,03,000

More information

Interconnection System Impact Study Report Request # GI

Interconnection System Impact Study Report Request # GI Executive Summary Interconnection System Impact Study Report Request # GI-2008-23 34 MW Solar Generation Ranch at Hartsel, Colorado Public Service Company of Colorado Transmission Planning August 19, 2010

More information

Deliverable Detailed Project Description 09 - TREY Turkey - Egypt

Deliverable Detailed Project Description 09 - TREY Turkey - Egypt Deliverable 2.1.2 Detailed Project Description 09 - TREY Turkey - Egypt EC DEVCO - GRANT CONTRACT: ENPI/2014/347-006 Mediterranean Project Task 2 Planning and development of the Euro-Mediterranean Electricity

More information

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection B. Bagen, D. Jacobson, G. Lane and H. M. Turanli Manitoba

More information

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016 The role of Transmission System Operator in Belgium and in Europe Vlerick Alumni Event 26 January 2016 Agenda Introduction Infrastructure management Controlling the system Developing the EU Market 1/25/2016

More information

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR # Executive Summary Firm point to point transmission service has been requested by Transmission Service Request (TSR) #75669514, under the SaskPower Open Access Transmission Tariff (OATT). The TSR consists

More information

HVDC Interconnectors Benefits and Challenges

HVDC Interconnectors Benefits and Challenges HVDC Interconnectors Benefits and Challenges Electric Power Control Center Workshop Bled, Slovenia 18th May 2015 Ole Gjerde Content of Presentation Background Experience Benefits Challenges Future A Changing

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

The Role of Offshore Wind

The Role of Offshore Wind The Role of Offshore Wind Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Richard Proctor ENI

More information

Click to edit title 18. Fachforum Netzbau und Betrieb

Click to edit title 18. Fachforum Netzbau und Betrieb The North Sea Off-Shore Grid a Vision to be Realised? Click to edit title 18. Fachforum Netzbau und Betrieb Köln, Click to 6.-7. edit Mai sub-title 2010 Dr. Matthias Luther transpower stromübertragungs

More information

The Development of Competitive Renewable Energy Zones in Texas

The Development of Competitive Renewable Energy Zones in Texas The Development of Competitive Renewable Energy Zones in Texas Warren Lasher Manager, System Assessment 4/23/2008 North American Electric Grids The ERCOT Region is one of 3 NERC grid interconnections.

More information

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation Prepared by: Entergy Services, Inc. T & D Planning L-ENT-17A 639 Loyola Avenue New Orleans, LA 70113 Rev Issue Date

More information

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar OFFSHORE WIND FARM CONNECTIONS TO THE GRID Energy to Quality S.L. Santiago Arnaltes Gómez Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the

More information

EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE

EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE EIPC HIGH LEVEL TRANSMISSION COST ESTIMATION TASK #5: DOE PROJECT NO. DE-OE0000343 Background: To support the SSC in assessing the results of the macroeconomic analysis and reaching consensus on the three

More information

Improving the integration of electricity networks: Prospects of the European Network of Transmission System Operators for Electricity (ENTSO-E)

Improving the integration of electricity networks: Prospects of the European Network of Transmission System Operators for Electricity (ENTSO-E) Improving the integration of electricity networks: Prospects of the European Network of Transmission System Operators for Electricity (ENTSO-E) 1. Context: ENTSO-E, 10/20/40 year views, network codes 2.

More information

100 MW Wind Generation Project

100 MW Wind Generation Project A subsidiary of Pinnacle West Capital Corporation 100 MW Wind Generation Project CUSTOMER FINAL Feasibility Study Results By Transmission Planning, APS December 21, 2007 Executive Summary This Feasibility

More information

Long distance bulk transmission

Long distance bulk transmission Long distance bulk transmission Dr. Yanny Fu, KEMA Consulting 6 October 2010 Experience you can trust. 2 Contents Transmission technologies AC and DC Overhead lines and underground/submarine cables Transmission

More information

European Wind Integration Study (EWIS) Towards a Successful Integration of Wind Power into European Electricity Grids

European Wind Integration Study (EWIS) Towards a Successful Integration of Wind Power into European Electricity Grids European Wind Integration Study (EWIS) Towards a Successful Integration of Wind Power into European Electricity Grids EWIS Concluding Discussion 13th April 2010, Brussels Network Strengthening findings

More information

DIgSILENT Pacific PowerFactory Technical Seminar

DIgSILENT Pacific PowerFactory Technical Seminar DIgSILENT Pacific PowerFactory Technical Seminar Topic: The Wonders of Optimal Power Flow Presenter: Wayne Ong Venue: Sydney Novotel Central / Brisbane Marriott Hotel Date: 16 th and 30 th November 2017

More information

Europe s % Interconnection Target:

Europe s % Interconnection Target: Europe s 2030 15% Interconnection Target: Challenges & solutions for a timely project implementation Presentation for Power Transmission Tech 2015 Dr. Volker Wendt, Director Public Affairs, Europacable

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

Solar Electricity for Regional Consumption or Export: Which way to lean?

Solar Electricity for Regional Consumption or Export: Which way to lean? 6/1/21 Euro-Mediterranean Energy Market Integration Project Germany France Lebanon Belgium Solar Electricity for Regional Consumption or Export: Which way to lean? Dr. Albrecht Kaupp Team Leader The contents

More information

The Long-Range Transmission Plan

The Long-Range Transmission Plan The Long-Range Transmission Plan 2015 2025 Matt Koenig Presentation to ESPWG / TPAS October 29 th, 2015 Long-Range Transmission Plan Driver of the Plan is to maintain local reliability 10-year planning

More information

DESERT POWER: GETTING CONNECTED

DESERT POWER: GETTING CONNECTED DESERT POWER: GETTING CONNECTED Starting the debate for the grid infrastructure for a sustainable power supply in EUMENA 3 DESERT POWER: GETTING CONNECTED Starting the debate for the grid infrastructure

More information

Spain Industry structure Existing capacity and generation

Spain Industry structure Existing capacity and generation 2.4.33 Spain 2.4.33.1 Industry structure Spain was one of the first countries in Europe to have liberalised its electricity sector. Generation facilities in Spain operate either under the Spanish ordinary

More information

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection Feasibility Study Report GIP-222-FEAS-R3 Interconnection Feasibility Study Report GIP-222-FEAS-R3 System Interconnection Request #222 48 MW Steam Generating Facility Pictou County (53N) 2010 07 30 Control Centre Operations Nova Scotia Power Inc.

More information

Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC

Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC Dr. Magnus Callavik, Power Systems HVDC, Aug 29, 2011 Developments in Multiterminal HVDC Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC EPRI s High Voltage

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

The Electric Power System

The Electric Power System The Electric Power System - Sweden- Swedish Power System 1 2 Basic facts 2014 Area: 450 295 km 2 Population: 9.6 Million Number of electricity consumers: 5.3 Million Number of TSOs: 1 Number of DSOs: 170

More information

Cascading Fault in AC/DC Hybrid Power Grid Xinzhou Dong

Cascading Fault in AC/DC Hybrid Power Grid Xinzhou Dong Cascading Fault in AC/DC Hybrid Power Grid Xinzhou Dong Tsinghua University, Beijing, China 30 th March, San Francissico, USA 1 2 3 4 5 Background Cascading Fault in AC/DC Hybrid Grid Model and Simulation

More information

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector HVDC Innovative Technology for Smart Grids and Super Grids CEO Power Transmission Solutions, Siemens Energy Sector BritNed: Pre-launch Press Event Maasvlakte, March 31, 2011 Siemens AG 2011 Energy Sector

More information

Electric Power Research Institute, USA 2 ABB, USA

Electric Power Research Institute, USA 2 ABB, USA 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Congestion Reduction Benefits of New Power Flow Control Technologies used for Electricity

More information

Grid Development and offshore meshed Infrastructure: Outlook on the TYNDP

Grid Development and offshore meshed Infrastructure: Outlook on the TYNDP Grid Development and offshore meshed Infrastructure: Outlook on the TYNDP Baltic InteGrid Conference 27. February 2019 Antje Orths 27. February 2019 Drivers in European Grid Development Objectives of EU

More information

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems Advanced Power Transmission Solutions Power Transmission and Distribution Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in Systems s Development of Power Markets Increasing

More information

City of Palo Alto (ID # 6416) City Council Staff Report

City of Palo Alto (ID # 6416) City Council Staff Report City of Palo Alto (ID # 6416) City Council Staff Report Report Type: Informational Report Meeting Date: 1/25/2016 Summary Title: Update on Second Transmission Line Title: Update on Progress Towards Building

More information

The Green Line Project

The Green Line Project The Green Line Project Presentation to the ISO-NE Planning Advisory Committee New England Independent Transmission Company, LLC December 18, 2007 1 500 kv DC transmission system with transfer capability

More information

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008 PJM enerator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study 504744 September 2008 PJM Interconnection 2008. All rights reserved R60 Robison Park-Convoy 345kV Impact Study eneral

More information

MILLIGAN SOLAR PROJECT

MILLIGAN SOLAR PROJECT February 16, 2009 Page 1 of 18 A subsidiary of Pinnacle West Capital Corporation MILLIGAN SOLAR PROJECT FINAL Feasibility Study Report APS Contract 52115 Prepared by: Arizona Public Service Company Transmission

More information

National Committee Kosovo. SEERC October 2017 Istanbul

National Committee Kosovo. SEERC October 2017 Istanbul National Committee Kosovo SEERC October 2017 Istanbul CIGRE National Committee KOSOVO The CIGRE National Committee of Kosovo was recognized by the Administrative Council of CIGRE, consulted by correspondence

More information

Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC

Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC Björn Jacobson, ABB Power Systems HVDC, Oct. 4, 2011 Developments in Multiterminal HVDC Drivers, Building Blocks (Cables, Offshore), EU and US Eamples, Grid- Enabled HVDC, LCC-MTDC IEEE EPEC 2011 Winnipeg,

More information

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation Feasibility Study Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection J.E.D. Solid Waste Management Facility Holopaw Substation September 2013 1 of 12 Table of Contents GENERAL... 3 SHORT

More information

SET Plan The 10th Year Anniversary Central European Energy Conference 2017

SET Plan The 10th Year Anniversary Central European Energy Conference 2017 MARKET COUPLING: UKRAINIAN WAY SET Plan The 10th Year Anniversary Central European Energy Conference 2017 UKRENERGO 2 TRANSMISSION COMPANY (state-owned, consists of 8 regional systems) Substations 137

More information

Chapter 1. Overview of HVDC applications

Chapter 1. Overview of HVDC applications ELEC0445 - High Voltage Direct Current grids Part 1. Line Commutated Converters Chapter 1. Overview of HVDC applications Patricia Rousseaux t.vancutsem@ulg.ac.be Thierry Van Cutsem www.montefiore.ulg.ac.be/~vct

More information

Report. the feasibility of

Report. the feasibility of Report on the feasibility of Additional Interconnection between India and Bangladesh Joint Technical Team (JTT) of India and Bangladesh July 2016 Contents 1.0 Background 1 2.0 Additional power export to

More information

Connection Engineering Study Report for AUC Application: AESO Project # 1674

Connection Engineering Study Report for AUC Application: AESO Project # 1674 APPENDIX A CONNECTION ASSESSMENT Connection Engineering Study Report for AUC Application: AESO Project # 1674 Executive Summary Project Overview FortisAlberta Inc. (FortisAlberta) submitted a System

More information

HVDC links in AC power system

HVDC links in AC power system HVDC links in AC power system Pierre Bornard Deputy CEO RTE New challenges & drivers ❷ HVDC fundamentals INELFE example HVDC integration / issues HVDC integration / R&D role The European Power System:

More information

9 th IFIC Workshop Athens 26 & 27 January 2012

9 th IFIC Workshop Athens 26 & 27 January 2012 9 th IFIC Workshop Athens 26 & 27 January 2012 Session on Best Practices for Grid Access and Permitting Procedures The Greek Experience and Practice A. Koronides HTSO tkoronides@desmie.gr THE EXISTING

More information

Feasibility Study Report

Feasibility Study Report Report For: Fresh Air Energy II, LLC ( Customer ) Queue #: Service Location: Chester County, SC Total Output Requested By Customer: 74.5 MW Commercial Operation Date Requested By Customer: 1/7/2019 Feasibility

More information

Analysis of options for the future allocation of PV farms in South Africa

Analysis of options for the future allocation of PV farms in South Africa Analysis of options for the future allocation of PV farms in South Africa M.P.E. GmbH International Engineering and Consulting company with offices in Germany (Tübingen) and U.K. (London). Services: Grid

More information

Getting Smart Evolution to the Smart Grid April 2008

Getting Smart Evolution to the Smart Grid April 2008 Getting Smart Evolution to the Smart Grid April 2008 Thomas F Garrity Vice President, Sales and Business Development Siemens Power T&D, Inc. Electrical energy is the backbone of our society Page 2 Mar-07

More information

SPS Planning Criteria and Study Methodology

SPS Planning Criteria and Study Methodology SPS Planning Criteria and Study Methodology SPS subscribes to the Southwest Power Pool ("SPP") Reliability Criteria, which incorporates compliance with the appropriate North American Electric Reliability

More information

Click to edit Master title style

Click to edit Master title style Challenges in grid planning and market integration moving towards the digital energy shift Trondheim, 28 April 2017 Information Technology and Electrical Engineering the digital energy shift Click to edit

More information

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027) February 2013 Contents I. Introduction 1 II. Status of Electricity Supply and Demand 2 1. Electricity Demand 2 2. Electricity

More information

Belt & Road Initiative and China- Korea-Japan Power Grid Interconnection

Belt & Road Initiative and China- Korea-Japan Power Grid Interconnection 2017.10 Belt & Road Initiative and China- Korea-Japan Power Grid Interconnection Outline Belt and Road Initiative Interconnection Overview Prefeasibility Study Outcomes Way forward 1 1. Belt and Road Initiative

More information

Connecting Belgium and Germany using HVDC: A Preliminary Study

Connecting Belgium and Germany using HVDC: A Preliminary Study 1 Connecting Belgium and Germany using HVDC: A Preliminary Study S. Cole, Member, IEEE, D. Van Hertem, Member, IEEE, R. Belmans, Fellow, IEEE Abstract Although Belgium and Germany are neighbouring countries,

More information

Achievement and experience in service of long length HV DC electrical links by insulated power cables

Achievement and experience in service of long length HV DC electrical links by insulated power cables Achievement and experience in service of long length HV DC electrical links by insulated power cables Marco Marelli, Italy Foz do Iguaçu September 6 th, 2013 1 HVDC Systems 2 3 4 5 HVDC Cables Service

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

European System Disturbance on 4 November 2006

European System Disturbance on 4 November 2006 European System Disturbance on 4 November 2006 Mattia Marinelli; matm@elektro.dtu.dk Center for Electric Power and Energy DTU Risø Campus University of California Santa Cruz 6 th Aug 2014 Summer School

More information

MVDC link in a 33 kv distribution network

MVDC link in a 33 kv distribution network 24th International Conference & Exhibition on Electricity Distribution (CIRED) 12-15 June 2017 Session 3: Operation, control and protection MVDC link in a 33 kv distribution network Chao Long 1, Jianzhong

More information

i-pcgrid Workshop 2017

i-pcgrid Workshop 2017 i-pcgrid Workshop 2017 Potential Impacts of Flexible Ramping Need on Transmission Planning March 2017 Chifong Thomas Director, Transmission Planning and Strategy Smart Wires Inc. USA Flexible Capacity

More information

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) Report-BCTC-R009A Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) December 8, 2005 Prepared by Wenyuan Li

More information

EUROPEAN GRID CONFERENCE European Parliament Brussels:

EUROPEAN GRID CONFERENCE European Parliament Brussels: EUROPEAN GRID CONFERENCE European Parliament Brussels: Grid Infrastructure: Super, Smart or SuperSmart? by Konstantin Staschus, Ph.D. 10 November 2011 Secretary-General of ENTSO-E konstantin.staschus@entsoe.eu

More information

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents

Engineering Study Report: FortisAlberta Inc. Plamondon 353S Capacity Increase. Contents APPENDIX A CONNECTION ASSESSMENT : FortisAlberta Inc. Plamondon 5S Capacity Increase Contents Executive Summary.... Introduction... 6. Project... 6.. Project Overview... 6.. Load Component... 6.. Generation

More information

HVDC Back-to-Back Interconnections Enabling reliable integration of power system

HVDC Back-to-Back Interconnections Enabling reliable integration of power system HVDC Back-to-Back Interconnections Enabling reliable integration of power system Dr Liliana Oprea FICHTNER GmbH&Co KG Swiss Chapter of IEEE PES Baden-Dättwil, 4 September 2013 Table of Contents Need for

More information

Peter Lundberg, Global Product Manager, November 2016 ABB Power Systems Offshore wind connection

Peter Lundberg, Global Product Manager, November 2016 ABB Power Systems Offshore wind connection Peter Lundberg, Global Product Manager, November 2016 ABB Power Systems Offshore wind connection Slide 1 Integrity, Health, Safety and Environment Always most important our core values Integrity Code of

More information

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT ART320W 320 MW Wind Powered Project Prepared for: El Paso Electric Company Prepared by: TRC Engineers, LLC 249 Western Avenue Augusta, ME 04330

More information

IET AC-DC The Role of FACTS and HVDC in the future Pan-European Transmission System Development. London, October 20th, 2010

IET AC-DC The Role of FACTS and HVDC in the future Pan-European Transmission System Development. London, October 20th, 2010 IET AC-DC 2010 The Role of FACTS and HVDC in the future Pan-European Transmission System Development London, October 20th, 2010 A. L Abbate, G. Migliavacca - RSE (former ERSE) U. Häger, C. Rehtanz, S.

More information

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Interconnection Feasibility Study Report GIP-IR373-FEAS-R1 Generator Interconnection Request 373 109.5 MW Wind Generating Facility South Canoe Lake, NS Mar. 2, 2012 Control Centre Operations Nova Scotia

More information

American Electric Power s Energy Storage Deployments

American Electric Power s Energy Storage Deployments American Electric Power s Energy Storage Deployments 1 2 American Electric Power : Company Profile The Evolution of the Electric Utility System Before Smart Grid: One-way power flow, simple interactions,

More information

Facilities Study for Alberta to US Available Transfer Capability

Facilities Study for Alberta to US Available Transfer Capability Facilities Study for Alberta to US Available Transfer Capability Report No: NPP2002-05 June 3, 2002 System Planning & Grid Operations, Transmission Line of Business Engineering Services Executive Summary

More information

Power Systems Fundamentals

Power Systems Fundamentals Power Systems Fundamentals Yachi Lin Senior Manager, Transmission Planning New York Independent System Operator Market Overview Course September 20, 2017 Rensselaer, NY 2017 New York Independent System

More information

Question Question 1.2-8

Question Question 1.2-8 Question 1.2-7 A dc transmission line running through a forest terrain is vulnerable to forest fires. If it is a bipolar line then both poles can be affected at the same time. What steps can be taken to

More information

CUSTOMER/ TWIN ARROWS PROJECT

CUSTOMER/ TWIN ARROWS PROJECT A subsidiary of Pinnacle West Capital Corporation CUSTOMER/ TWIN ARROWS PROJECT V1 Facility Study Report APS Contract 52149 Prepared by: Arizona Public Service Company Transmission & Distribution Asset

More information

Consulting Agreement Study. Completed for Transmission Customer

Consulting Agreement Study. Completed for Transmission Customer Completed for Transmission Customer Proposed Resource & Transmission Carbon County, MT & 230 kv Transmission in North Wyoming August 2016 Table of Contents 1.0 Description... 1 2.0 Overall Assumptions...

More information

High Voltage Direct Current Systems

High Voltage Direct Current Systems GE Grid Solutions High Voltage Direct Current Systems imagination at work Today s Environment Globally the utility environment is becoming more complex and utilities are having to manage new challenges

More information

Transmission Networks Developments and the Role of Interconnections with Neighbouring Countries

Transmission Networks Developments and the Role of Interconnections with Neighbouring Countries Transmission Networks Developments and the Role of Interconnections with Neighbouring Countries Tomasz Siewierski Electricity Market Research Group Technical University of Lodz, Poland Energy in Poland,

More information

Dynamic Control of Grid Assets

Dynamic Control of Grid Assets Dynamic Control of Grid Assets Panel on Power Electronics in the Smart Grid Prof Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent Power Infrastructure Consortium School

More information

Elia Ancillary Services: Black-Start

Elia Ancillary Services: Black-Start Elia Ancillary Services: Black-Start 2018-2020 Bidding instructions and awarding criteria Table of contents 1 General information... 2 1.1 Minimal need of ELIA... 2 1.2 «Black-Start» Electrical zones...

More information

Cigre and Trends in Power Electronics for the Grid. Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics

Cigre and Trends in Power Electronics for the Grid. Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics Cigre and Trends in Power Electronics for the Grid Bjarne Andersen Chairman of Cigre Study Committee B4 HVDC and Power Electronics Contents SC B4 Activites Present Status of HVDC System Technology Active

More information

Life Needs Power, Hannover Messe, April 24, 2018 The role of smart and strong grids in Europe s energy transition

Life Needs Power, Hannover Messe, April 24, 2018 The role of smart and strong grids in Europe s energy transition The European Association of the Electricity Transmission and Distribution Equipment and Services Industry Life Needs Power, Hannover Messe, April 24, 2018 The role of smart and strong grids in Europe s

More information

TURKISH POWER SYSTEM OVERVIEW AND INTERCONNECTION WITH GEORGIAN POWER SYSTEM TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS)

TURKISH POWER SYSTEM OVERVIEW AND INTERCONNECTION WITH GEORGIAN POWER SYSTEM TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS) TURKISH POWER SYSTEM OVERVIEW AND INTERCONNECTION WITH GEORGIAN POWER SYSTEM TURKISH ELECTRICITY TRANSMISSION CORPORATION (TEIAS) 1 CONTENT MAIN FUNCTIONS OF TEIAS TURKISH POWER SYSTEM OVERVIEW EXISTING

More information

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE Yunqi WANG, B.T. PHUNG, Jayashri RAVISHANKAR School of Electrical Engineering and Telecommunications The

More information

Electricity industry structure and key players

Electricity industry structure and key players Electricity industry structure and key players Growth in capacity, production and consumption, 2006 2017 Expected demand and addition to generation capacity, 2018 2027 Growth in transmission network and

More information

Innovative technologies ready for the Supergrid

Innovative technologies ready for the Supergrid Innovative technologies ready for the Supergrid The Roadmap to the Supergrid Technologies EEF lunchtime discussion Feb 6, 2013 in Strasbourg Presented by Dr. Magnus Callavik, ABB (Convenor of WG 2 - Technology)

More information