B. DEVELOPMENT AND EVALUATION OF ALTERNATIVES

Size: px
Start display at page:

Download "B. DEVELOPMENT AND EVALUATION OF ALTERNATIVES"

Transcription

1 Chapter 2: Project Alternatives A. INTRODUCTION This chapter summarizes an intense 3-year effort to consider and recommend options to solve pressing existing and future transportation problems on Manhattan s East Side. Section B addresses the evaluation process, in which a great number of alternatives were evaluated to select the four project alternatives for consideration in this MIS/DEIS. Section C describes the four project alternatives and Section D presents preliminary cost estimates. The evaluation of the long and reduced long list of alternatives is presented in full detail in two reports: Development of Alternatives, Volume 1 (October 1996), and Evaluation of Alternatives, Volume 2 (September 1997). The refined engineering evaluation and details of the two project build alternatives are presented in the Final Engineering Report, in Appendices D, E, and F to this document. B. DEVELOPMENT AND EVALUATION OF ALTERNATIVES APPROACH The basic alternatives development and evaluation approach for the MESA study was to consider all options suggested, evaluating each against the project s goals and objectives (see Chapter 1, Section G). MTA New York City Transit (NYCT) and the project team accepted recommendations from other agencies, the PAC, members of civic groups, and the public, in addition to those being generated by the study s planners and engineers. From a large list, these alternatives were grouped (some suggestions were essentially the same as others) and organized into a somewhat smaller list, called the long list of alternatives. This was subjected to a coarse screen using relatively broad criteria, which eliminated those options that could not reasonably be built and combined others together to form several new full combination alternatives. Preliminary findings were discussed with the TAC, PAC, MTA Long Range Planning Framework working group, community boards, and the general public, and then further modified. The end result was a reduced long list of alternatives. Using much more detailed criteria, including engineering and preliminary cost analysis, traffic, environmental and socioeconomic information, and transportation modeling, the reduced long list was reviewed in three successive screens. This phase included substantial refinement to the options as required by the more detailed analyses undertaken. The work was closely supervised by NYCT engineering staff, and it was coordinated with other state and city agencies, as appropriate, and again discussed in the public outreach program. The evaluation concluded that four alternatives would be addressed in detail in this MIS/DEIS: No Build; Transportation Systems Management (TSM); new Second Avenue subway north of 63rd Street with access to the Broadway express tracks down to Lower Manhattan; and the same subway supplemented by new light rail transit (LRT) serving the Lower East Side and Lower Manhattan. 2-1

2 Manhattan East Side Transit Alternatives MIS/DEIS SCREENING THE LONG LIST OF ALTERNATIVES To evaluate the long list of alternatives, a coarse screen was used, containing enough information to determine whether a given alternative met the project goals and objectives or whether a critical flaw or obstacle would prevent an alternative from being implemented. As part of this initial screen, and based on the study goals and objectives, each alternative was evaluated as an independent entity in terms of its ability to satisfy the following major issues in the study area (see Figure 1-1):! Accessibility, Capacity and Market Areas Served: The evaluation process addressed such issues as: providing increased mass transit into and within the transportation corridor; attracting new ridership to mass transit; and providing expanded mass transit services to currently underserved zones in the study area including the Lower East Side and the Upper East Side, particularly east of Second Avenue.! Economic Feasibility, Cost Effectiveness, and Equity Issues: The evaluation addressed such issues as: whether the proposed technology is known to be practical and implementable; whether at a preliminary level the expected benefits outweigh the order-ofmagnitude costs and whether the impacts of the candidate alternative, both positive and negative, are equitably distributed among those communities that will experience the impacts.! Environmental and Community Compatibility Issues: All alternatives had to comply with the Clean Air Act and State Implementation Programs, respond to the needs of the immediate and larger community, and expand mass transit in the study corridor while protecting the physical and social environment.! Street and Subsurface Transportation and Transit Congestion Issues: All alternatives were required to alleviate crowding on existing transit lines, highway corridors and, specifically, the East Side transportation corridor; reduce travel times; and maintain or improve adequate parking and loading areas throughout the project corridor. If the alternative adequately addressed these issues, it was then subject to a series of questions, as follows:! Does this alternative stand alone? If the alternative adequately addressed the study goals and objectives and was able, by itself, to address the major transportation problems in the study area, it was considered a stand-alone alternative.! If not, would this alternative better address study area issues if it were combined with another alternative? Each does not stand alone alternative was further evaluated to determine whether it could be combined with other alternatives to form one alternative that addressed the study goals and objectives. Potential components of the TSM alternative were also identified in this way.! If the alternative does not stand alone, can it be considered a routing or other type of option for a stand-alone alternative?! Are there any major flaws in the alternative that would prevent its implementation? 2-2

3 Chapter 2: Project Alternatives Once the coarse screen evaluation was nearly complete, the project team presented the alternatives to the Public Advisory Committee and held workshops and focused meetings in all five study area zones (shown on Figure 1-1). These discussions also helped to hone the long list. Long list alternatives that did not stand alone were either eliminated or combined with other alternatives to help create well-rounded solutions to the transit and transportation issues on the East Side of Manhattan. If, during the screening process, the issues related to an alternative appeared too complex for a quick screen, a white paper was prepared for that alternative. The intent of the white paper was to provide the team with more information on an alternative so that the benefits or impediments could be assessed and a well informed decision (i.e., whether the alternative would be screened out or whether it may be combined with another alternative to better satisfy the study area needs) could be made. The long list alternatives are described briefly below, along with the conclusions of their evaluation (see also Table 2-1 on page 2-9). 1. RAPID TRANSIT ALTERNATIVES * A. Original Full 1974 Alignment of the Second Avenue Subway The Original Full 1974 Alignment of the Second Avenue Subway would extend from Water Street north, primarily along Chrystie Street and Second Avenue, and over a new crossing of the Harlem River to the Bronx. This alternative would meet project goals and thus remained as a stand-alone alternative. It was also determined that two other subway options could serve as routing options under this alternative; these are alternatives 1D and 1G, described below. B. Second Avenue Subway North Second Avenue Subway North (from East Midtown to East Harlem) was eliminated as a standalone alternative because it would provide accessibility and increased capacity only to the northern sections of the study area. It was retained as a possible component of a combination alternative. Ultimately, this alternative became a key component of the Build alternatives as the East Side subway extension. C. Second Avenue Subway South Second Avenue Subway South (between East Midtown and Lower Manhattan) was eliminated as a stand-alone alternative because it would serve only the southern portion of the study area, would be difficult to implement, and would not be cost-effective compared to other alternatives that would provide similar improvements. D. Second Avenue Subway Eastward Alignment This subway alternative would veer eastward along East Broadway, move north beneath Avenue B to East 10th Street and then return to Second Avenue, thus serving the Lower East * Rapid transit lines were initially considered for any of the avenues east of Lexington Avenue. Second Avenue was chosen early on as being the most appropriate because (1) a route on Third Avenue would too closely duplicate the Lexington Avenue Line s service area; (2) a subway route on First Avenue would be difficult because of the Queensboro Bridge, the street configuration near the United Nations, and the Queens-Midtown Tunnel; and (3) no other route could make use of the tunnel sections already built for the original Second Avenue subway. 2-3

4 Manhattan East Side Transit Alternatives MIS/DEIS Side. Because its only difference from 1A is the alignment in the Lower East Side, it was added as a routing option to the Second Avenue Subway Original Alignment. E. Second Avenue Subway with Southbound Connection To/From Grand Central Terminal This connection from Grand Central Terminal southward to Lower Manhattan (either a subway spur or direct commuter rail link) was eliminated from further analysis because it addressed only a small portion of the study area riders (primarily commuters from Westchester and Connecticut) and its costs were high compared with other alternatives that would provide a similar benefit. F. Second Avenue Subway 43rd Street Interline Connection This alternative would connect a Second Avenue subway across 42nd Street to the Broadway line. With a stop at Grand Central, this would allow commuters a second express train to Lower Manhattan. This option was not a stand-alone alternative because it would not adequately address access or capacity issues for the southern portions of the study area. It was also eliminated as a possible component to a combination alternative because of its high cost compared to other alternatives that would provide similar transportation benefits. G. Second Avenue Subway 43rd Street New Jersey Connection This alternative would connect the full Second Avenue Subway to an east-west subway along 43rd Street. Although it did not specifically address the issues defined for the MESA study area, it was under consideration in the Access to the Region s Core (ARC) study. It was therefore included as a routing addition in the full subway option (1A, above), and remained under active consideration until it was dropped by the ARC study. 2. LEXINGTON AVENUE SUBWAY SERVICE IMPROVEMENTS A. Lexington Avenue Subway Signal Improvements Signal improvements on the Lexington line would theoretically help to increase capacity, by allowing more trains per hour to proceed safely along the route. However, this benefit would be marginal, since it would not affect significantly the dwell times of trains in the stations, an important issue, particularly at the transfer stations. Like all suggested improvements to the Lexington Avenue line, this alternative would not make rapid transit more accessible to the underserved portions of the study area. It was therefore eliminated as a stand-alone alternative. However, in combination with other service improvements aimed at reducing dwell time problems, it was thought that the alternative might be a useful component of the TSM Alternative. This possibility was ruled out because the costs far outweighed the benefits. Such signal improvements would be made over the long term, independent of the MESA study, but not within the study s timeframe. B. Lexington Avenue Subway Platform Extensions Extending platforms on the Lexington Avenue line would permit NYCT to lengthen the trains from 10 to 12 cars, carrying up to 20 percent more passengers through the system. Despite this increase in capacity, the improvement would not make transit more accessible to the underserved portions of the study area. Furthermore, compared with the costs of extending the plat- 2-4

5 Chapter 2: Project Alternatives forms, the benefits would be minimal. It was therefore eliminated from further study as a standalone alternative. In addition, because of the high expected cost of implementation and the difficulty expected in terms of its construction (the modifications would affect virtually all platforms along the entire line [4, 5, and 6 trains]), the alternative was not considered suitable for inclusion in the TSM Alternative or reasonable as a component of a combination alternative. This alternative was eliminated from further consideration in this study. C. Lexington Avenue Subway Segmented Connections to Other Subway Lines (Conversion of Northern Lexington Avenue Subway Lines to B Division Service) This alternative would connect the northern half of the Lexington Avenue line (either the express or local tracks) with the Broadway line through a new tunnel connection to the 63rd Street tunnel near where the two lines cross at Lexington Avenue. Because the two lines carry different sized trains (Broadway line B Division trains are larger than Lexington Avenue A Division trains), the Lexington Avenue line north of 63rd Street would be converted to the larger B Division cars. This is theoretically possible because the tunnels north of 42nd Street were originally built to wider B Division standards. Service on the Lexington Avenue line south of 59th Street would remain in A Division configuration and terminate in the vicinity of 59th Street. This alternative was intended to increase capacity by adding the Broadway express tracks to the system and by increasing the capacity of the trains themselves. This alternative would not stand alone, because it would not address many of the access and service issues of the study area. It was not evaluated for any combination or enhancement options because it would not improve transit accessibility for the midtown core, and it would be extremely costly and disruptive to rail operations. D. Lexington Avenue Subway Local Service Extension to Lower Manhattan An extension of the Lexington Avenue subway local service to Lower Manhattan was eliminated as a stand-alone alternative, because it would address only a portion of study area transportation issues; however, it was included as a component of combination Alternative 10D. E. Lexington Avenue Subway Skip-Stop Operation Lexington Avenue Subway Skip-Stop Operation was eliminated as a stand-alone alternative because it would only minimally address study area transportation issues, but it was retained as a potential component either of a combination alternative or of the TSM Alternative. 3. NEW METRO-NORTH STATIONS IN THE BRONX AND UPPER MANHATTAN The alternative to add Metro-North railroad stops in the Bronx and Upper Manhattan was eliminated as a stand-alone alternative because it would offer limited access improvements to underserved portions of the study area and would not increase capacity materially. Also, because the costs would be very high, particularly compared with the benefits accrued, this option was also eliminated from consideration as a component of the TSM Alternative. 2-5

6 Manhattan East Side Transit Alternatives MIS/DEIS 4. BUS ALTERNATIVES A. Bus Service on Dedicated Avenue This option would dedicate either First or Second Avenue to two-way bus service, limiting private traffic essentially to local deliveries. This would allow the buses to increase speed and reduce travel time. This alternative would meet the study goals, and was therefore retained for further review as one stand-alone alternative with two routing options. B. Bus Service on Paired Avenues This service would provide two primary bus lanes each on First and Second Avenue, in a design similar but superior to those provided on Madison Avenue. Local deliveries and drop-offs would be permitted in a special curbside standing lane; bus stops would be built out into this lane, so that buses would never have to enter the standing lane to pick up and drop off passengers, and the likelihood of illegal standing in bus stops would be greatly reduced. This somewhat selfenforcing option was found to address most project goals and was thus retained in the reduced long list of alternatives. C. Trolley Bus on Dedicated Busway Trolley-bus in a dedicated busway was retained as a stand-alone alternative since it satisfied preliminary evaluation criteria. This alternative could be considered a technology option to either Alternative 4A or 4B. D. FDR Drive Busway A dedicated lane for buses and high occupancy vehicles on the FDR Drive was eliminated as a stand-alone alternative because it would not address many of the problems in the study area. It would only serve a limited portion of the study area, catering instead to longer-distance commuters. However, it was retained as a candidate for possible inclusion in the TSM Alternative. 5. LIGHT RAIL TRANSIT ALTERNATIVE A. Light Rail Transit Service on Dedicated Avenue LRT on an avenue dedicated to its two-way service would extend from South Ferry to 125th Street in this alternative. This system would meet many of the project goals, and so was retained in the first reduced long list. B. Light Rail Transit Service on Paired Avenues LRT service from South Ferry to 125th Street on First and Second Avenues was also considered. This alternative met the basic project goals and so was retained in the reduced long list. 6. PRIVATE FRANCHISED JITNEY SERVICE Private franchise jitney service is a flexible service with various possible routings and higher capacities than taxi cabs. It would not, however, provide enough capacity to relieve transit or onstreet traffic congestion. Therefore, it was eliminated as a stand-alone alternative but retained as a candidate for inclusion in the TSM Alternative. 2-6

7 Chapter 2: Project Alternatives 7. FERRY SERVICE ON EAST RIVER WITH SHUTTLE BUS SERVICE Ferry service on the East River with shuttle bus service would offer new transit service to a limited market area, but would not materially reduce crowding on the Lexington Avenue subway; and would only partially address the accessibility needs identified in the study area. Therefore, it was eliminated as a stand-alone alternative but was retained as a candidate for inclusion in the TSM Alternative because of its expected net benefits. 8. NEW EAST RIVER STOPS ON EXISTING EAST-WEST SUBWAY SERVICE New East River stops on three existing east-west subway lines were proposed in this alternative at the following locations: First Avenue at 63rd Street on the Q route; First Avenue at 59th Street on the Broadway line; First Avenue at 42nd Street on the 7 route; and Avenue C at 14th Street on the L route. This alternative would improve subway accessibility in currently underserved areas but would not provide any congestion relief to the study area s north-south transit corridors, thereby limiting potential service improvements to many portions of the MESA project corridor. It was therefore eliminated as a stand-alone alternative. In addition, due to considerable expense and construction difficulties, and marginal effect on the study area, most of the options within this alternative were eliminated from further consideration in the study. However, because of public interest, the proposed station on the L route at 14th Street and Avenue C was retained for possible inclusion in the TSM Alternative. 9. TRANSPORTATION SYSTEM MANAGEMENT IMPROVEMENTS The TSM improvements alternative, by definition, will remain as a stand-alone alternative through the end of the entire evaluation process. The components of the TSM have evolved as the study has progressed. At the close of the coarse screen, the TSM Alternative could have potentially included the following:! Bus lane operational improvements;! Express and local bus operations improvements such as stop-spacing;! Lexington Avenue skip-stop operation (Alternative 2E);! FDR Drive busway/hov (Alternative 4D);! Ridesharing on the FDR Drive;! Private jitney service particularly from the Upper East Side to Lower Manhattan and from Midtown to Lower Manhattan (Alternative 6);! Ferry service on the East River with shuttle bus service (Alternative 7);! Subway station improvements;! New subway passenger transfers between Broadway/Lafayette Street (B, Q, D, and F lines) and Bleecker Street station northbound (No. 6) and between 63rd Street on the B and Q lines and the Lexington Avenue station at 59th-60th Street (No. 6 and the R and N lines);! New L station at 14th Street and Avenue C (part of Alternative 9); and! Traffic engineering improvements. 10. COMBINATION ALTERNATIVES The idea of the combination alternatives is to combine viable options that cannot otherwise stand alone to meet project goals. The combination alternatives were as follows: 2-7

8 Manhattan East Side Transit Alternatives MIS/DEIS! Alternative 10A. Second Avenue subway north of 42nd Street and LRT service from East Midtown south to the Lower East Side and Lower Manhattan;! Alternative 10B. Second Avenue subway north of 63rd Street and a busway from East Midtown south to the Lower East Side and Lower Manhattan;! Alternative 10C. Second Avenue subway north of 63rd Street and LRT service in the Lower East Side and Lower Manhattan;! Alternative 10D. Second Avenue subway north of 63rd Street, with extension of the Lexington Avenue Local (No. 6 route) subway service beyond the Brooklyn Bridge stop and bus service improvements in the Lower East Side. 11. ELEVATED TRANSIT Elevated transit was considered along Second or First Avenues. Such an option would meet the study s transportation goals, but its visual impact and community compatibility (third goal) issues would be potentially significant; community reaction to this option was also quite negative. This alternative would not fulfill several of the project goals. It was therefore eliminated from further consideration. 12. NO BUILD ALTERNATIVE The No Build alternative will be carried through the entire study. It is the option that decision makers will take if they decide to reject the TSM and other Build alternatives. It consists of all transportation facilities and services likely to exist in the future study year (2020), and is discussed further in Section C of this chapter. These elements would also be included in the TSM and other Build alternatives. CONCLUSIONS: PRELIMINARY REDUCED LONG LIST OF ALTERNATIVES Given the elimination of some and combination of others from the long list, the preliminary reduced long list of alternatives was renumbered, as shown in Table 2-1. EVALUATING THE REDUCED LONG LIST OF ALTERNATIVES The preliminary reduced long list of alternatives was narrowed through three successive screens in Task 5, as shown in Figure 2-1 and described below. SCREEN 1: CONFIRMATION OF FEASIBILITY The first screen dealt with final confirmation of feasibility. During this screen, preliminary engineering drawings were prepared, as necessary, to identify those alternatives that were clearly infeasible. As a result of this analysis, the extension of the No. 6 line from City Hall to Lower Manhattan, a component of Alternative 10, was eliminated. Because of existing development both above and below ground, the new alignment would have to cross five other subway lines, or be so deep that it would avoid these lines altogether. Given the relatively shallow depth of rock in Lower Manhattan, a deep alignment, even if it were possible, would have to be constructed using the very disruptive cut-and-cover method. Feasible elements of Alternative 10 were included in other alternatives, and the list was reduced by one, to become the final reduced long list considered in Screen 2 (see Table 2-2). 2-8

9 Chapter 2: Project Alternatives Table 2-1 Summary of Coarse Screen Matrix Elimi- Could Be New Old # Long List TSM nated Combined # Reduced Long List 1 Second Avenue Subway A Original Alignment 3 Original Alignment B North of 63rd Street X C South of 63rd Street X D Eastward Alignment 3 Original Alignment Routing Option E Connection to GCT X F 43rd Street Inter-line X G New Jersey Connection 3 Original Alignment Routing Option 2 Lexington Avenue Line A Signal Improvements X X 4 Paired with Bus B Platform Extensions X C X Scheme (segmented X connections) D Local Service Extension to X Lower Manhattan E Skip Stop X X 3 New Metro North Stations X 4 Bus/Trolley/HOV 4 Bus Alternative A Bus on Dedicated Avenue 4 Bus Routing Option B Bus on Paired Avenues 4 Bus Routing Option C Trolley on Dedicated Ave 5 Trolley on Dedicated Avenue D HOV Lane on FDR Drive X 5 Light Rail Transit 6 LRT Alternative A LRT on Dedicated Avenue 6 LRT Routing Option B LRT on Paired Avenues 6 LRT Routing Option 6 Private Franchised Jitney X 7 Ferry Service on East River X with Shuttle Bus 8 New East River Stops X 9 TSM Improvements 2 TSM Alternative 10 Combination Alternatives 7 Subway North with LRT to the south 11 Elevated Transit X 12 No Action 1 No Action 8 Subway North with bus to the south 9 Subway North with LRT in Lower East Side and Lower Manhattan 10 Subway North, Extend Local to Lower Manhattan, Bus Improvements 2-9

10 Manhattan East Side Transit Alternatives MIS/DEIS No. Name Description Table 2-2 Reduced Long List of Alternatives 1 No Build Includes all transportation facilities and services likely to exist in the forecast year (such as 63rd Street/Queens Boulevard line connection). Free transfers between buses and subways are included in the No Build Alternative. All elements of this alternative are included in the other alternatives. 2 Transportation Systems Refers to a set of low-to-moderate cost improvements that are more readily Management implementable than major capital cost alternatives. In this study, TSM improvements may be in the range of several million dollars or more. The TSM Alternative is refined in later evaluations as lower-cost improvements that do not pass the screening process are added. 3 Second Avenue Subway with Refers to a new subway line following the original Second Avenue subway Options (Eastern Alignment, alignment along Second Avenue, Chrystie Street, St. James Place, and New Jersey Connection) Water Street with station spacing every 10 to 15 blocks. One potential Eastern Alignment Option would veer eastward in the East Village and Lower East Side along 10th Street, Avenue B, and East Broadway. The potential New Jersey Connection Option would add an east-west branch connecting Grand Central and New Jersey. 4 Bus Service on Dedicated or Would create a two-way busway along an avenue or a one-way pair of Paired Avenues with busways on two avenues. In most of the study area, First and Second Resignalization of Lexington Avenues would be used; local streets would be used in the Lower East Avenue Line Side and Lower Manhattan. Signals on the Lexington Avenue line would be updated to provide additional train through-put capacity. 5 Trolley Bus on Dedicated Would run Trolley Bus service on First or Second Avenue, powered by Busway overhead electrical wires. Trolley buses could be linked together to provide more passenger capacity. 6 Light Rail Service on Dedi- Proposes an LRT line in a separated right-of-way along the entire length of cated or Paired Avenues the study area. In the dedicated option, the LRT line would run two-way on adjacent tracks on First or Second Avenues and on local streets in Lower Manhattan. In the paired avenues option, the LRT would run south on one avenue and north on another, except south of Houston Street where the line would run in both directions on parallel tracks on as yet to be determined streets. 7 Northern Segment of Second Proposes a new East Side subway extension along Second Avenue from Avenue Subway with LRT in the northern edge of the study area to 63rd Street, and a LRT system, either Eastern Midtown, Lower East on dedicated or paired avenues, in East Midtown (south of 63rd Street), the Side, and Lower Manhattan Lower East Side, and Lower Manhattan. 8 Northern Segment of the Proposes a new East Side subway extension along Second Avenue from Second Avenue Subway with the northern edge of the study area to 63rd Street, and a dedicated Bus Service in East Midtown, busway, either on dedicated or paired avenues, in East Midtown (south of the Lower East Side, and 63rd Street), the Lower East Side, and Lower Manhattan. Lower Manhattan 9 Northern Segment of the Proposes a new East Side subway extension along Second Avenue from Second Avenue Subway with the northern edge of the study area to 63rd Street or Grand Central Terminal LRT in the Lower East Side and a LRT system, either on dedicated or paired avenues, in the Lower East and Lower Manhattan Side and Lower Manhattan. 2-10

11 Chapter 2: Project Alternatives SCREEN 2: DEFINITION AND EVALUATION OF ROUTING OPTIONS The second and third screens addressed a number of issues regarding feasibility and impact for the seven remaining build alternatives in continuously increasing detail; the No Build and TSM Alternatives were carried straight through the process. The second screen required that the alternatives be more completely defined. The reduced long list contained rather generic alternatives: the general routes were known, but the specifics had not been resolved. The exact locations of the termini were unknown, several alternatives did not specify a particular street (First or Second Avenue, Avenue B, C, or D, e.g.), and sites for storage and maintenance yards had not been identified. This screen, then, involved substantially more refinement in defining the routing, alignment, and engineering options for each alternative. The engineering options addressed particular areas along the alternatives alignments and tunneling methods as follows: Engineering Options 63rd Street Flexing Connection. For alternatives involving a connection between the East Side subway extension on Second Avenue north of 63rd Street and the previously constructed 63rd Street subway, there were three configuration options: a two-track station ( two track ); a four-track station with two tracks joining the 63rd Street subway and two proceeding south for a possible extension at a later date ( four track ); and a two-track station with two tail tracks continuing south for a possible extension at a later date ( two track with tail ). Northern Connection to the Lexington Line. For alternatives involving a connection between the East Side subway extension and the Pelham Line (No. 6) subway, there were four configuration options: a station parallel to the Lexington Avenue 125th Street station with a connecting passage for passenger transfers ( parallel station ); a station perpendicular to the Lexington Avenue 125th Street station with a connecting passage for passenger transfers ( perpendicular station ); a connection to the Lexington Avenue Harlem River tubes at Lexington Avenue ( connection ); and a new tunnel under the Harlem River at Second Avenue ( new tunnel ). Transition from Second Avenue to Lexington Avenue. For alternatives involving a transition from the new 125th Street station and the existing tunnel segments beneath Second Avenue, there were three crossover configuration options: an S curve immediately south of 125th Street Station with a crossover between the two curves ( between the two curves ); an S curve several blocks south of the 125th Street station with a crossover immediately south of the 125th Street station ( south of 125th ); and an S curve immediately south of the 125th Street station with a crossover immediately north of the 125th Street station ( north of 125th ). Canal Street Flip. For alternatives involving use of the Broadway line, there were two options at Canal Street: direct service to lower Manhattan requiring track reconfiguration and platform construction to permit the express trains to continue directly to lower Manhattan and route the local over the Manhattan Bridge ( flip ); and indirect service to Lower Manhattan requiring a transfer from express to local service at Union Square or Canal Street to continue southward in Manhattan without flip ). Tunneling Method. For alternatives involving tunnel construction, there were three tunneling options: cut-and-cover ; tunnel-boring machine ( boring ); and mining. 2-11

12 Manhattan East Side Transit Alternatives MIS/DEIS Screen 2 Criteria The second screen also set criteria for this level of evaluation. In the evaluation, the alternatives and their routing options were grouped by mode so that they could be evaluated against similar modes (subway to subway, bus to bus, LRT to LRT). The evaluation criteria are summarized as follows:! Total cost: This was a comparative analysis, showing the relative range of costs between same-mode options.! Average speed: In this comparison, a fast speed was 15 to 20 mph, medium was 10 to 15 mph, and slow was less than 10 mph.! Potential for free subway-to-subway transfer.! Impacts on the existing transit system. These include such effects as the elimination, rerouting, reduction, or increase of existing routes due to a new service. A substantial, irreparable adverse impact was required for this criterion alone to eliminate an alternative.! Other service changes to the existing system. This criterion examined various operational changes that would be necessary to accommodate a new service. These would not eliminate an alternative unless they were found to be prohibitive.! Use of existing tunnels. A subway or LRT routing option s use of existing tunnels with available capacity was considered a plus.! Engineering complications. Potential engineering difficulties were identified at this stage; these were important to the elimination of certain options.! Unresolved issues. Issues such as the potential termini of alignments, turnaround problems, intermodal connections, and connections with other MISs in the region were identified; these were either resolved through further analysis or identified as potentially unresolvable.! Potential for public/community support. Alternatives were rated as low, medium, high, or very high in potential community support, depending essentially on community-related impacts, such as disruption (e.g., if curb-side deliveries were to be substantially limited), and increased traffic congestion.! Expanded rapid transit area. Each option was evaluated for its ability to provide rapid transit service to a previously underserved area.! Ridership. Early model results helped to provide a comparative analysis of the ridership levels that might be attracted to each option within a given mode of travel.! Street/Operations Impacts. This criterion more clearly defined the effect an alternative would have after it was constructed. Subway options, all underground, received a low impact rating, while the surface transportation systems received varying ratings.! Legal issues. Problems in jurisdiction, property taking, easements, and other legal issues were identified. These did not necessarily eliminate an alternative, unless they were deemed to make an option unimplementable. 2-12

13 Chapter 2: Project Alternatives! Construction impacts. Methods of construction were reviewed and rated; cut-and-cover, the most disruptive form of subway construction was to be kept to a minimum, for example.! Possibility of phased construction. Given the reality that limitations on the availability of capital funds year by year might require the phasing of construction, those alternatives that did not allow for reasonable phasing were eliminated.! Implementation. Alternatives were defined by how quickly they could be in service. Shortterm is less than 5 years, medium term is 5 to 10 years, and long-term is greater than 10 years. As a result of this screen, several of the reduced long list alternatives were reconfigured and recombined and two were eliminated. Specifically, the bus options (Alternative 4) were, on closer analysis, not suitable as stand alone alternatives. The option of priority lane service on First and Second Avenues was determined to be the least disruptive, most flexible and best preferred option by the community, and so it was included as an option in Alternative 2: TSM Alternative. The electric trolley bus option (Alternative 5) was also carried as an option of the TSM Alternative. Of the subway options in Alternative 3, the full north-south subway was continued to the next screen as Alternative 3A and the eastward alignment was reconfigured as a Lower East Side subway shuttle with connections to existing subways and combined with a North Subway (new construction along Second Avenue, connecting at 63rd Street to the Broadway express tracks and at 125th Street to the Pelham Bay line) as Alternative 3C for further analysis. All other suboptions (full subway eastward alignment, connections to other lines, connections to a new east-west transit line, e.g.) were eliminated based on cost-effectiveness and impact factors. Two LRT options were also continued as Alternatives 6A and 6B. The two-way LRT on a single avenue was determined to be the least disruptive and most cost effective option. It could follow a straight route to/from Lower Manhattan, passing through the Lower East Side along First Avenue/Allen Street, or it could turn eastward on 14th Street to Avenue D through the East Village and Lower East Side before going underground in an existing tunnel to bypass Chatham Square and back onto the downtown routing on Water Street. Combination Alternative 7, which paired the subway north of 63rd Street with the LRT south from 63rd Street as in Alternative 6B was eliminated because it would not perform appreciably better than alternatives with shorter LRT segments and was thus not cost-effective. Combination Alternatives 8 and 9 were continued; Alternative 8 consists of the subway north of 63rd Street (as in Alternative 3A) with the enhanced bus service included in the TSM Alternative. Preliminary model results found it to produce significant improvements to crowding on the Lexington Avenue line and the bus treatments would provide improvements in other study area subareas. Alternative 9 is Alternative 8 plus the LRT through the Lower East Side and Lower Manhattan described in Alternative 6B. The shorter list of alternatives is presented in Table 2-3. SCREEN 3: QUANTITATIVE AND QUALITATIVE EVALUATION OF ALTERNATIVES The final screen involved an analysis of specific quantitative and qualitative data for each of the remaining alternatives. Preliminary model output was available, as were ridership and travel time 2-13

14 Manhattan East Side Transit Alternatives MIS/DEIS and capital cost estimates; these formed the basis for a partial cost benefit analysis, as shown in Table 2-4. Qualitative screening criteria were added at this stage, including a definition of accessibility, potential for displacement, service to low income, minority, and transit-dependent populations, community character effects, such as impacts on land use/public policy, visual character, open space, historic resources, and archaeological resources, hazardous materials issues, traffic impacts, impact on parking and goods delivery, air quality impacts, compatibility with existing transit system, and a general analysis of construction impacts. As a result of this analysis, three of the five remaining Build alternatives (Alternatives 3A, 3C, and 6) were eliminated. As shown in Table 2-4, Alternatives 3A and 3C had the highest capital and operating costs and high cost factors (dollars per hour saved or hours spent in a less crowded subway car). Alternative 6 was eliminated because of its substantial potential impacts in the major issues categories. These alternatives performed well in improving accessibility, but other, less expensive or disruptive alternatives performed well in this category too. The evaluation also found that the proposed bus lanes fit the definition of the TSM alternative, and thus were moved from the Build alternatives. This would allow a clearer comparison among the project alternatives. More detailed engineering analysis subsequent to the screening process eliminated the connection to the existing Pelham Bay route north of 125th Street in Alternatives 8 and 9. Although this northward connection and the full subway south of 63rd Street were eliminated from further consideration in this study, the preliminary engineering of Alternatives 8 and 9 would not prevent these options from being built at a later time. In addition, the two-track/two tail track option at 63rd Street, and the Canal flip, allowing the new route to proceed on the Broadway line express tracks directly to Lower Manhattan, were included in the Build alternatives. 2-14

15 Chapter 2: Project Alternatives No. Name Description Table 2-3 Reduced Long List of Alternatives 1 No Build Includes all transportation facilities and services likely to exist in the forecast year (such as 63rd Street/Queens Boulevard line connection). Free transfers between buses and subways are included in the No Build Alternative. All elements of this alternative are included in the other alternatives. 2 Transportation Systems A set of low-to-moderate cost improvements that are more readily implementable Management (TSM) than major capital cost alternatives, yet can provide solutions in both the short and long term. In this study the TSM could include bus service changes, priority bus lanes, passenger/train control improvements, free transfers, station improvements, and other possible measures. 3A Second Avenue Subway Refers to a new subway line running between Pelham Bay Park in the Bronx with 125th Street-Pelham and Whitehall Street in Manhattan. This alternative would make use of the Connection existing Pelham Bay line (No. 6 route) north of the 125th Street Station on the Lexington Avenue line. New subway construction would connect the existing Pelham line and Lexington local tunnels to the new Second Avenue subway near 112th Street. Lexington Avenue local service would terminate at 125th Street. The subway would connect to the 63rd Street (B, Q lines) subway. The Second Avenue subway would continue south beneath Second Avenue, Chrystie Street, St. James Place, Pearl, and Water Streets to its terminus at Whitehall. This alternative would be combined with bus route improvements on the Lower East Side. 3C 6A Broadway/Pelham Routing This two-part alternative would introduce new subway service to residents of of the Second Avenue East Harlem, the Upper East Side, and the Lower East Side. The individual parts Subway with Lower East of this alternative would: Side Subway Shuttle 1. Make use of the existing Pelham Bay line (No. 6 route) north of the 125th Street station on the Lexington Avenue line. New subway construction would connect the existing Pelham line and Lexington local tunnels to the new Second Avenue subway near 112th Street. The Second Avenue subway would continue south beneath Second Avenue to a connection with the western leg of the 63rd Street route (B, Q lines). From there, it would continue south on the Broadway express tracks (previously the N express), and cross the East River via the Manhattan Bridge. 2. Introduce new subway service to the Lower East Side by using the 14th Street L route, which would extend between 14th Street/Avenue C and the Chambers Street station on the J/M/Z lines. New construction would be required under Avenue C, as well as portions of East Broadway and Canal. New connections would be made to the Canarsie line (L) and to the Nassau Street route s (J/M/Z) Chambers Street station, where the line would terminate. Light Rail Transit (LRT) on Proposes a two-track LRT route in a center-of-street right-of-way between the First Avenue Metro-North Station at 125th Street/Park Avenue and Whitehall Street in Lower Manhattan. The routing would extend between Park and First Avenues via 125 Street and between 125th and Houston Streets via First Avenue. At Houston Street, the LRT would extend south along Allen Street, connect to the Nassau Street subway (J/M/Z) via a tunnel under Canal Street, return to the surface after the Chambers Street station via Frankfort Street, and continue on St. James Place and Water Street to its terminus at Whitehall Street. 2-15

16 Manhattan East Side Transit Alternatives MIS/DEIS No. Name Description Table 2-3 (Continued) Reduced Long List of Alternatives 8 Broadway/Pelham Routing This two-part alternative would introduce new subway service to residents of of the East Side Subway East Harlem and the Upper East Side and improved bus service to East Midtown Extension with Enhanced and the Lower East Side South of 63rd Street. The individual parts of this Bus Service South of 63rd alternative would: Street 1. See Alternative 3C, part 1, above. 2. Provide a two-lane dedicated bus lane on First and Second Avenues to serve the area between 63rd and 14th Streets in East Midtown. Bus routing changes and improved service would be implemented in the Lower East Side and Lower Manhattan. 9 Broadway/Pelham Routing This three-part alternative would provide new subway service to residents of of the East Side Subway the Upper East Side, new LRT service to people living in the Lower East Side, Extension with LRT in the and improved bus service to people living in the East Side and Lower East Side Lower East Side and south of 63rd Street. The individual parts of this alternative would: Lower Manhattan 1. See Alternative 3C, part 1, above. 2. See Alternative 8, part 2, above. 3. Introduce a two-track LRT route in the Lower East Side and Lower Manhattan that would extend from 14th Street/Union Square to Whitehall Street in Lower Manhattan. This alternative would provide LRT service in the center of the street east of Union Square along 14th Street to Avenue D, pass under the Williamsburg Bridge on Avenue D before turning west on Delancey Street, south on Pitt Street and East Broadway to Canal Street. The LRT would dip below ground and enter into the now-unused Canal Street subway and make use of an abandoned connection between the Canal Street subway and the Nassau Street route (J/M/Z) to the Chambers Street station. The LRT would resurface on Dover/Frankfort Street just west of Pearl/Water Streets, where it would then continue south to its terminus at Whitehall Street. 2-16

17 Table 2-4 Refined Long List Alternatives Evaluation Summary 2-17 Potential Impacts Annual Costs* Dollars Per on Hour Partial Less Benefit/ Hour Crowd Cost Alternative Capital O&M Total Saved ed Ratio Conclusion 1. No Build NA NA NA NA NA NA Continued 2. Transportation System Management NA NA NA NA NA NA Bus added 3A. Full Length Second Avenue Subway Eliminated 3C. North Subway/Lower East Side Subway Shuttle Eliminated 6A. Full Length LRT Eliminated 8. North Subway/Bus Combination Continued; bus to TSM 9B/9C. North Subway/LRT and Bus Combinations Continued; bus to TSM * Annual costs are presented in millions of 1997 dollars; NA = not applicable in this analysis. = substantial benefit; = moderate benefit; = no change, little impact; = moderate adverse impact potential; = high to very high adverse impact potential Population Accessibility Employment Accessibility Traffic Impacts Air Quality Parking/Goods Delivery Transit System Compatibility Open Space Direct Open Space Indirect Historic Resources Archeology

18 Manhattan East Side Transit Alternatives MIS/DEIS The No Build, TSM, and Alternatives 8 and 9 remain as project alternatives and are discussed in Section C of this chapter. They have been renumbered as No Build, TSM, Build Alternative 1 (was Alternative 8), and Build Alternative 2 (was Alternative 9). C. PROJECT ALTERNATIVES INTRODUCTION The screening and evaluation of a full range of alternatives, summarized above, resulted in four alternatives being carried forward in the MIS/DEIS. As described below, these comprise No Build, TSM, and two Build alternatives. These latter options were subjected to further engineering analysis, which refined them again, as necessary. The engineering effort was guided by five engineering design goals:! Maximize the number of people transported in the study corridor for the funds expended.! Minimize the property/environmental impacts in the study corridor.! Maximize convenience and connectivity for the potential passengers of the system.! Minimize the operational/maintenance impacts on the existing subway system.! Provide for maximum flexibility for subway modifications in the future. Engineering criteria were also applied to both subway and light rail options as follows:! Horizontal and vertical alignments! Construction methods i.e., cut-and-cover vs. tunneling (e.g., deep bore, mining)! Constructibility! Stations! Ventilation! Drainage! Traction power and electrical distribution! Signaling! Maintenance/storage facilities! Property impacts! Utilities! Environmental impacts! Total project cost estimates NO BUILD ALTERNATIVE The No Build Alternative consists of those improvements in the city s transportation system instituted after 1995 (the base year for the MESA study) that would be in place by This includes completion of MTA operating agency initiatives to bring the system into a state of good repair (such as the purchase of new subway cars, rehabilitation of certain stations, track improvements, etc.) and three specific changes. The first improvement, which took place on July 4, 1997, was introduction of the MetroCard. The second, also a policy initiative, was a system- 2-18

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Early Scoping Meeting for Alternatives Analysis (AA) May 17, 2011 Introduction Key players Local lead agency: Metro Federal lead agency:

More information

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives

Preliminary Definition of Alternatives. 3.0 Preliminary Definition of Alternatives 3.0 What preliminary alternatives are being evaluated? The alternatives for the East San Fernando Valley Transit Corridor project that were considered for screening include the No Build Alternative, Transportation

More information

I-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY

I-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY EXECUTIVE SUMMARY The purpose of this report is to document the results of the Tier 1 and Tier 2 Screening of alternatives for the I-20 East Transit Initiative. The two-tier screening process presented

More information

Stakeholders Advisory Working Groups (SAWGs) Traffic and Transit SAWG Meeting #7

Stakeholders Advisory Working Groups (SAWGs) Traffic and Transit SAWG Meeting #7 Presentation Tappan Zee Bridge/I-287 Corridor Environmental Review December 4, 2008 Slide 1 Title Slide Slide 2 This presentation discusses the contents of the Transit Mode Selection Report. Slide 3 The

More information

4.0 TIER 2 ALTERNATIVES

4.0 TIER 2 ALTERNATIVES 4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation

More information

Chapter 2: Project Alternatives A. INTRODUCTION

Chapter 2: Project Alternatives A. INTRODUCTION Chapter 2: Project Alternatives A. INTRODUCTION Numerous alternatives have been developed and analyzed for a new Second Avenue Subway since the project was first conceived nearly 75 years ago. Although

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

North Shore Alternatives Analysis. May 2012

North Shore Alternatives Analysis. May 2012 North Shore Alternatives Analysis May 2012 Agenda Study Process and Progress to Date Short List Alternatives Screening Traffic Analysis Conceptual Engineering Ridership Forecasts Refinement of Service

More information

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit

FINAL. Sound Transit Long-Range Plan Update. Issue Paper S.1: Tacoma Link Integration with Central Link. Prepared for: Sound Transit Sound Transit Long-Range Plan Update Issue Paper S.1: Tacoma Link Integration with Central Link Prepared for: Sound Transit Prepared by: Quade & Douglas, Inc. FINAL March 2005 Foreword This issue paper

More information

Chapter 9: Transportation (Rail Transit) D. RAIL TRANSIT

Chapter 9: Transportation (Rail Transit) D. RAIL TRANSIT Chapter 9: Transportation (Rail Transit) D. RAIL TRANSIT EXISTING CONDITIONS The subway lines in the study area are shown in Figures 9D-1 through 9D-5. As shown, most of the lines either serve only portions

More information

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY

More information

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.

Executive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections

More information

Troost Corridor Transit Study

Troost Corridor Transit Study Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit

More information

Energy Technical Memorandum

Energy Technical Memorandum Southeast Extension Project Lincoln Station to RidgeGate Parkway Prepared for: Federal Transit Administration Prepared by: Denver Regional Transportation District May 2014 Table of Contents Page No. Chapter

More information

Metro Green Line to LAX Alternatives Analysis. March 2012

Metro Green Line to LAX Alternatives Analysis. March 2012 Metro Green Line to LAX Alternatives Analysis 1 2 The Crenshaw/LAX Project Foundation for Metro Green Line to LAX 8.5 mile extension Metro Exposition Line (Crenshaw Exposition) to Metro Green Line (Aviation/LAX

More information

Waco Rapid Transit Corridor (RTC) Feasibility Study

Waco Rapid Transit Corridor (RTC) Feasibility Study Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM

More information

Chapter 4 : THEME 2. Transportation

Chapter 4 : THEME 2. Transportation Chapter 4 : THEME 2 Strengthen connections to keep the Central Area easy to reach and get around 55 Figure 4.2.1 Promote region-wide transit investments. Metra commuter rail provides service to the east,

More information

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development

Public Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation

More information

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014

Midtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014 Midtown Corridor Alternatives Analysis Policy Advisory Committee Meeting February 12, 2014 Today s Agenda Introductions Outreach efforts and survey results Other updates since last meeting Evaluation results

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM

NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM NEW HAVEN HARTFORD SPRINGFIELD RAIL PROGRAM Hartford Rail Alternatives Analysis www.nhhsrail.com What Is This Study About? The Connecticut Department of Transportation (CTDOT) conducted an Alternatives

More information

Transit Access to the National Harbor

Transit Access to the National Harbor Transit Access to the National Harbor December 2014 Table of Contents Executive Summary... 3 Introduction and Project Purpose... 6 Methodology.. 9 Definition of Alternatives..... 9 Similar Project Implementation

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 28, 2009 SUBJECT: DON MILLS STATION ACTION ITEM RECOMMENDATIONS It is recommended that the Commission: 1. Endorse the

More information

Welcome. Green Line in Your Community

Welcome. Green Line in Your Community Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay

More information

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Transit Coalition September 26, 2012 2 Study Area Pacific Electric Rightof-Way/West Santa Ana Branch (PEROW/ WSAB) extends

More information

Attachment 5 Eglinton West LRT Planning and Technical Update

Attachment 5 Eglinton West LRT Planning and Technical Update Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to

More information

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, 2006 SUBJECT: Scarborough Rt Strategic Plan RECOMMENDATIONS It is recommended that the Commission: 1. Endorse

More information

5. OPPORTUNITIES AND NEXT STEPS

5. OPPORTUNITIES AND NEXT STEPS 5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours

More information

Green Line LRT: Beltline Segment Update April 19, 2017

Green Line LRT: Beltline Segment Update April 19, 2017 Green Line LRT: Beltline Segment Update April 19, 2017 Quick Facts On April 11, 2017, City Council approved Administration s recommendation for the Green Line to be underground in the Beltline from 2 Street

More information

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Bi-County Transitway/ Bethesda Station Access Demand Analysis Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction

More information

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council:

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council: Corporate NO: R279 Report COUNCIL DATE: DECEMBER 18, 2006 REGULAR COUNCIL TO: Mayor & Council DATE: December 15, 2006 FROM: General Manager, Engineering FILE: 8710-20 (Heritage) SUBJECT: Update on Community

More information

The Engineering Department recommends Council receive this report for information.

The Engineering Department recommends Council receive this report for information. CORPORATE REPORT NO: R161 COUNCIL DATE: July 23, 2018 REGULAR COUNCIL TO: Mayor & Council DATE: July 19, 2018 FROM: General Manager, Engineering FILE: 8740-01 SUBJECT: Surrey Long-Range Rapid Transit Vision

More information

Synthesis of Cal Poly Senior Projects Relating to Public Transportation in San Luis Obispo County

Synthesis of Cal Poly Senior Projects Relating to Public Transportation in San Luis Obispo County Synthesis of Cal Poly Senior Projects Relating to Public Transportation in San Luis Obispo County In partial fulfillment of CE 424 Professor Eugene Jud By David Thornhill November 14, 2007 Purpose The

More information

What We Heard Report - Metro Line NW LRT

What We Heard Report - Metro Line NW LRT What We Heard Report - Metro Line NW LRT by Metro Line NW LRT Project Team LRT Projects City of Edmonton April 11, 2018 Project / Initiative Background Name Date Location Metro Line Northwest Light Rail

More information

Alternatives Analysis Findings Report

Alternatives Analysis Findings Report 6.0 This chapter presents estimates of the potential capital, operations and maintenance costs associated with the alternatives carried forward for detailed evaluation. The methodology used to develop

More information

Restoration of Historic Streetcar Services in Downtown Los Angeles

Restoration of Historic Streetcar Services in Downtown Los Angeles Restoration of Historic Streetcar Services in Downtown Los Angeles Alternatives Analysis Community Update Meeting August 2, 2011 Introduction Key players Local lead agency: Metro Federal lead agency: Federal

More information

Will the L Train Shutdown be a Missed Opportunity or Model for the Future?

Will the L Train Shutdown be a Missed Opportunity or Model for the Future? Will the L Train Shutdown be a Missed Opportunity or Model for the Future? Here s how to improve plans for the L train before it s too late The MTA has said it will shutdown the L train for 15 months starting

More information

Policy Advisory Committee Meeting November 13, 2013

Policy Advisory Committee Meeting November 13, 2013 Midtown Corridor Alternatives ti Analysis Policy Advisory Committee Meeting November 13, 2013 Today s Agenda Introductions Follow up from September meeting Alternatives review Process update Key evaluation

More information

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT

EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING

More information

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Green Line LRT: Beltline Recommendation Frequently Asked Questions Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria

More information

East River Tunnel. Index

East River Tunnel. Index Natural geography has Long Island equally convenient to Midtown and Lower Manhattan. However, built geography, specifically Pennsylvania tation, clearly favors Midtown. LIRR passengers commute to Lower

More information

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS)

T-THIRD PHASE 3 CONCEPT STUDY C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) A: 2014 SFMTA TRANSIT SERVICE INFORMATION B: SFMTA TRAFFIC COUNT DATA C: DETAILED DESCRIPTIONS OF CONCEPT ALIGNMENTS D: CONSTRUCTABILITY ANALYSIS AND COST ESTIMATES (HNTB CONSULTANTS) E: LAND USE AND VALUE

More information

COMPARATIVE SCREENING RESULTS REPORT

COMPARATIVE SCREENING RESULTS REPORT Metro-North Penn Station Access Major Investment Study/Draft Environmental Impact Statement COMPARATIVE SCREENING RESULTS REPORT Prepared for Metro-North Railroad Prepared by Parsons Brinckerhoff Quade

More information

Needs and Community Characteristics

Needs and Community Characteristics Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by

More information

MTA Long Island Rail Road (LIRR) and MTA Metro-North Railroad (MNR) System-wide Service Standards

MTA Long Island Rail Road (LIRR) and MTA Metro-North Railroad (MNR) System-wide Service Standards MTA Long Island Rail Road (LIRR) and MTA (MNR) System-wide Service Standards The following system-wide service standards apply to LIRR and MNR operations. 1. Service Availability Service Availability is

More information

Executive Summary. Phase 2 Evaluation Report. Introduction

Executive Summary. Phase 2 Evaluation Report. Introduction , Executive Summary Executive Summary Introduction TransLink and the Province of British Columbia sponsored a multi-phase study to evaluate alternatives for rapid transit service in the Broadway corridor

More information

Transit Access Study

Transit Access Study West of Hudson Regional Transit Access Study Open House presentation July 20, 2010 1 Agenda Progress To date Summary of Level 2 Alternatives and Screening Service Plans Bus and Rail Operating and Capital

More information

The Eastern Connector Study November, 2007 planning for the future

The Eastern Connector Study November, 2007 planning for the future The Eastern Connector Study November, 2007 planning for the future In late 2006, Albemarle County and the City of Charlottesville jointly initiated the Eastern Connector Corridor Study. The Project Team

More information

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population

More information

4.2 Series Station Option Description

4.2 Series Station Option Description 4.2 Series Station Option Description The series station proposal features a new set of side platforms constructed approximately 250 feet north of the existing platforms. The two new platforms would extend

More information

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION

6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments

More information

NICTI Alternatives Analysis

NICTI Alternatives Analysis EXECUTIVE SUMMARY Development of Detailed Alternatives Report Prepared for: Northern Illinois Commuter Transportation Initiative City of Rockford, Illinois Prepared by: 222 South Riverside Plaza, Suite

More information

Crenshaw-Prairie Transit Corridor Study Public Meetings

Crenshaw-Prairie Transit Corridor Study Public Meetings Crenshaw-Prairie Transit Corridor Study Public Meetings Darby Park: Wednesday, February 20, 2008 6:30 8:00 PM US Bank Community Room: Thursday, February 21, 2008 6:30 8:00 PM Nate Holden Performing Arts

More information

Independence Institute Denver West Parkway, Suite 185 Golden, Colorado i2i.org/cad.aspx BRT = BTR

Independence Institute Denver West Parkway, Suite 185 Golden, Colorado i2i.org/cad.aspx BRT = BTR Independence Institute 14142 Denver West Parkway, Suite 185 Golden, Colorado 80401 303-279-6536 i2i.org/cad.aspx BRT = BTR Bus-Rapid Transit Is Better Than Rail: The Smart Alternative to Light Rail Joseph

More information

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit

More information

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]

APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] Jackson/Teton Integrated Transportation Plan 2015 Appendix I. Fixed-Guideway Transit Feasibility Jackson/Teton County Integrated Transportation Plan v2

More information

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps

PEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Why Peachtree? Why Now? I. THE CONTEXT High Level View of Phasing Discussion Potential Ridership Segment 3 Ease

More information

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What

More information

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY

BROWARD BOULEVARD CORRIDOR TRANSIT STUDY BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,

More information

Tier 2 Screening and Selection522. of the Short List Alternatives KISSIMMEE CORRIDOR. Downtown CRA. US 192 Alternatives Analysis

Tier 2 Screening and Selection522. of the Short List Alternatives KISSIMMEE CORRIDOR. Downtown CRA. US 192 Alternatives Analysis LAKE COUNTY ORANGE COUNTY Ticket and Transportation Center Walt Disney / Reedy Creek Improvement District CR 535 John Young Parkway 441 17 92 Florida s Turnpike VE 92 mee Hall JOHN YOUNG PKY 192 OAK ST

More information

TORONTO TRANSIT COMMISSION REPORT NO.

TORONTO TRANSIT COMMISSION REPORT NO. Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION

More information

Figure 2-14: Existing Bus Routing at Irwindale Station

Figure 2-14: Existing Bus Routing at Irwindale Station 494 W oothill Blvd 69 N Irwindale Ave 185 Irwindale E 1st St 3 6 feet igure 2-14: Existing Bus Routing at Irwindale 39 Proposed Bus Route 494 W oothill Blvd Proposed Discontinued Bus Route Proposed New

More information

Proposed Program of Interrelated Projects

Proposed Program of Interrelated Projects DALLAS AREA RAPID TRANSIT Proposed Program of Interrelated Projects Federal Transit Administration Capital Investment Program Summer 204 INTRODUCTION The current federal transportation bill, Moving Ahead

More information

METRO Orange Line BRT American Boulevard Station Options

METRO Orange Line BRT American Boulevard Station Options METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN

More information

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report

Office of Transportation Bureau of Traffic Management Downtown Parking Meter District Rate Report Office of Transportation Bureau of Traffic Management 1997 Downtown Parking Meter District Rate Report Introduction The City operates approximately 5,600 parking meters in the core area of downtown. 1

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING

IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING IV. ENVIRONMENTAL IMPACT ANALYSIS K.2. PARKING ENVIRONMENTAL SETTING The following analysis summarizes the findings and conclusions of the Traffic Analysis (Traffic Study), prepared by The Mobility Group,

More information

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars.

Note: The October 2007 version of this report has been updated in this December 2008 report to present costs in year 2007 dollars. Sound Transit Phase 2 South Corridor LRT Design Report: SR 99 and I-5 Alignment Scenarios (S 200 th Street to Tacoma Dome Station) Tacoma Link Extension to West Tacoma Prepared for: Sound Transit Prepared

More information

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

US 81 Bypass of Chickasha Environmental Assessment Public Meeting US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments

More information

Mississauga Bus Rapid Transit Preliminary Design Project

Mississauga Bus Rapid Transit Preliminary Design Project Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.

More information

August 26, Main-McVay Transit Study Stakeholder Advisory Committee. John Evans, LTD David Reesor, City of Springfield

August 26, Main-McVay Transit Study Stakeholder Advisory Committee. John Evans, LTD David Reesor, City of Springfield August 26, 2014 TO: FROM: RE: Main-McVay Transit Study Stakeholder Advisory Committee John Evans, LTD David Reesor, City of Springfield Range of Possible Transit Solutions At the July 29, 2014 Stakeholder

More information

ANDERSON PROPERTY SITE ANALYSIS

ANDERSON PROPERTY SITE ANALYSIS ANDERSON PROPERTY SITE ANALYSIS Introduction The Montgomery County Department of Transportation (MCDOT) initiated a feasibility study in the fall of 2012 to evaluate the need for transit service expansion

More information

I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P B SEH No

I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P B SEH No TECHNICAL MEMORANDUM TO: FROM: Transit Advisory Group Jeff Rhoda DATE: RE: I-494/I-35 Interchange Vision Layout Development - BRT Station Concepts S.P. 2785-330B SEH No. 123252 04.00 I-494/I-35W Interchange

More information

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary

Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County. Executive Summary Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Highway 18 BNSF Railroad Overpass Feasibility Study Craighead County Executive Summary October 2014 Prepared

More information

Project Purpose and Need B. IDENTIFICATION OF THE PROPOSED PROJECT

Project Purpose and Need B. IDENTIFICATION OF THE PROPOSED PROJECT Chapter 1: Project Purpose and Need A. INTRODUCTION The Federal Transit Administration (FTA) and the Metropolitan Transportation Authority (MTA), in cooperation with MTA New York City Transit (NYCT), propose

More information

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE 5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the

More information

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR

Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR Chapter 9 Recommended Locally Preferred Alternative and Alternatives for Evaluation in Draft SEIS/SEIR 9.0 RECOMMENDED LOCALLY PREFERRED ALTERNATIVE AND ALTERNATIVES FOR EVALUATION IN DRAFT SEIS/SEIR

More information

appendix 4: Parking Management Study, Phase II

appendix 4: Parking Management Study, Phase II appendix 4: Parking Management Study, Phase II A4-1 A4-2 Eastlake Parking Management Study Final Phase 2 Report Future Parking Demand & Supply January 6, 2017 Submitted by Denver Corp Center III 7900 E.

More information

CEDAR AVENUE TRANSITWAY Implementation Plan Update

CEDAR AVENUE TRANSITWAY Implementation Plan Update CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,

More information

METRONext. Vision & Moving Forward Plans. Board Workshop. December 11, DRAFT For Preliminary Discussion Only

METRONext. Vision & Moving Forward Plans. Board Workshop. December 11, DRAFT For Preliminary Discussion Only METRONext Vision & Moving Forward Plans Board Workshop December 11, 2018 Disclaimer This presentation is being provided solely for discussion purposes by the Board of Directors of the Metropolitan Transit

More information

Midtown Corridor Alternatives Analysis Initial Screening Analysis

Midtown Corridor Alternatives Analysis Initial Screening Analysis Midtown Corridor Alternatives Analysis Initial Screening Analysis 7/24/2013 Prepared by the SRF Consulting Group Team for Table of Contents Purpose... 1 Initial Screening Analysis Methodology... 1 Screening...

More information

Measure R Funded Transit Projects

Measure R Funded Transit Projects Measure R Funded ransit Projects Crenshaw/LAX ransit Corridor New Potential LAWA erminal & Ground Access Facilities ypes of Connections Direct Light Rail ransit (LR) Branch Metro goes to the airport Metro

More information

Public Transportation Problems and Solutions in the Historical Center of Quito

Public Transportation Problems and Solutions in the Historical Center of Quito TRANSPORTATION RESEARCH RECORD 1266 205 Public Transportation Problems and Solutions in the Historical Center of Quito JACOB GREENSTEIN, Lours BERGER, AND AMIRAM STRULOV Quito, the capital of Ecuador,

More information

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Letter EL652 City of Mercer Island. Page 1. No comments n/a Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists

More information

4. Transportation Plan

4. Transportation Plan The sizes of the most suitable sites are indicated in Table 4.3.6.2. Table 4.3.6.2: Site Sizes and Potential Development Area Potential Development Site Site Size (m 2 ) Area m 2 (3 Floors) D1 29,000 87,000

More information

Operating & Maintenance Cost Results Report

Operating & Maintenance Cost Results Report Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June

More information

Submission to Greater Cambridge City Deal

Submission to Greater Cambridge City Deal What Transport for Cambridge? 2 1 Submission to Greater Cambridge City Deal By Professor Marcial Echenique OBE ScD RIBA RTPI and Jonathan Barker Introduction Cambridge Futures was founded in 1997 as a

More information

Community Advisory Committee. October 5, 2015

Community Advisory Committee. October 5, 2015 Community Advisory Committee October 5, 2015 1 Today s Topics Hennepin County Community Works Update Project Ridership Estimates Technical Issue #4:Golden Valley Rd and Plymouth Ave Stations Technical

More information

The capital cost estimates do not include allowances for: ROW acquisition. Third-party mitigation works. Hazardous materials handling.

The capital cost estimates do not include allowances for: ROW acquisition. Third-party mitigation works. Hazardous materials handling. Mode Selection Report 7 Cost Evaluation The cost evaluation criteria used in the evaluation of the transit modes are: Capital cost. operating costs. Fare revenue. Net cost per passenger/passenger-mile.

More information

Spadina Subway Extension Downsview Station to Steeles Avenue Environmental Assessment

Spadina Subway Extension Downsview Station to Steeles Avenue Environmental Assessment Spadina Subway Extension Downsview Station to Steeles Avenue Environmental Assessment APPENDIX Q SUBWAY OPERATIONS REPORT Spadina Subway Extension Downsview Station to Steeles Avenue Environmental Assessment

More information

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017 East San Fernando Valley Transit Corridor Information Session, October 10, 2017 1 Welcome and Meeting Purpose Introductions Metro Transit Corridors Planning Metro Real Estate Metro Community Relations

More information

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan

CITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan Date: Wednesday, June 24, 2014 Location: Ann Arbor District Library Attendees: 40 citizen attendees Ann Arbor Station Environmental Review Public Meeting Meeting Notes Meeting #2 The second public meeting

More information

CROSSING RAIL PROJECT (P4) RAIL

CROSSING RAIL PROJECT (P4) RAIL GRAND CROSSING RAIL PROJECT (P4) Community Advisory Group October 10, 2012 1:30 pm Grand Crossing Park Field House 7655 S. Ingleside Avenue, Chicago GRAND CROSSING RAIL PROJECT (P4) Community Advisory

More information

Attachment D Environmental Justice and Outreach

Attachment D Environmental Justice and Outreach Attachment D Environmental Justice and Outreach ATTACHMENT D Environmental Justice and Outreach Indicate whether the project will have disproportionately high and adverse impacts on minority or low income

More information

vision42

vision42 vision42 www.vision42.org vision42 auto-free light rail boulevard for 42nd Street Roxanne Warren, AIA, Chair George Haikalis, ASCE, Co-Chair Institute for Rational Urban Mobility,Inc. www.vision42.org

More information

Halifax Commuter Rail: A Fresh Concept

Halifax Commuter Rail: A Fresh Concept Building Owners & Managers Association (BOMA) Nova Scotia PO Box 1597, Halifax NS B3J 2Y3 902-425-3717 info@bomanovascotia.com bomanovascotia.com Halifax Commuter Rail: A Fresh Concept The Green Interconnected

More information

Sepulveda Pass Corridor Systems Planning Study

Sepulveda Pass Corridor Systems Planning Study Los Angeles County Metropolitan Transportation Authority Sepulveda Pass Corridor Systems Planning Study Streets and Freeways Subcommittee January 17, 2013 1 Sepulveda Pass Study Corridor Extends for 30

More information

Funding Scenario Descriptions & Performance

Funding Scenario Descriptions & Performance Funding Scenario Descriptions & Performance These scenarios were developed based on direction set by the Task Force at previous meetings. They represent approaches for funding to further Task Force discussion

More information

MTA Capital and Planning Review

MTA Capital and Planning Review MTA Capital and Planning Review The Bond Buyer's 5th Annual Metro Finance Conference November 15, 2007 Evolution of the Capital Plan 1 Plan Evolution First five-year plan approved in 1982 to rescue system

More information

Fixing the Line s Canarsie Tunnel. Manhattan CB6 11/5/2018

Fixing the Line s Canarsie Tunnel. Manhattan CB6 11/5/2018 Fixing the Line s Canarsie Tunnel Manhattan CB6 11/5/2018 Interborough Bus Service 80+ buses in the peak hour in the peak direction over the Williamsburg Bridge Projected to carry 17% of riders 1 Bus Priority

More information