1 Connect. Thrive. Develop.
2 Why go to the Riverfront? KC Streetcar is a proven catalyst for development & connecting people to Downtown. < $2 billion in adjacent development: new businesses, hotels, apartments & amenities < 10 surface parking lot conversions to new active uses < 40% increase in downtown residential density < 2 million passenger trips 5,830 daily average trips
3 To connect people to the Riverfront & connect the Riverfront to Downtown. Berkley Riverfront Existing & Planned Amenities: < Events, Fesitivals & Concerts < Lighted Sand Volleyball Courts < Sports Courts, Yoga & Pilates < Retail & Offices < Luxury Apartments < Resort-style Pool & Sundeck < Walking & Biking Trails < Dog Park & Hangout
4 Opportunities to Connect <Integrate with bus routes & potential future bicycle/pedestrian connections <Streamline Riverfront & Downtown access; offer parking alternatives <Allow for future Streetcar expansions
5 What makes a Streetcar route feasible? COST TO BUILD Considerations <Will it require a new bridge? <What is the length of track? NEW BRIDGE TRACK LENGTH STEEP GRADE COST TO OPERATE <Are riders going out of their way? <Can we maintain route timetables? SAFETY TIMING Level of Difficulty <Travel time & number of streetcars Not Feasible Difficult required to support the route NOISE USABILITY Challenging Preferred
6 Streetcar Options Considered FRONT STREET Berkley Riverfront 3rd Street New Bridge < An 870 foot bridge over Missouri River New Bridge 71 railroad tracks is expensive < The steep grade causes safety issues and excessive wear-and-tear on streetcars 5th Street DELAWARE STREET Grand Boulevard Existing Bridge MAINTENANCE LINE KC Streetcar Maintenance Facility LYDIA AVENUE < Additional track length CAMPBELL STREET increases costs < And a 1,0 foot bridge is even more expensive TH STREET 6TH STREET Main Street River Market Grand Boulevard Columbus Square You Are Here 3rd Street Option 5th Street Option Existing Streetcar Maintenance Line Railroad Track New Bridge Streetcar Stop 2 Level of Difficulty Not Feasible Difficult Challenging Preferred
7 Streetcar Options Considered FRONT STREET Berkley Riverfront Grand Boulevard < Use of existing bridge is Missouri River 71 less expensive < Grades are manageable Loop End Existing Bridge Grand Boulevard Existing Bridge MAINTENANCE LINE Railroad Tracks KC Streetcar Maintenance Facility < More track required for loop around end < Curved track is more expensive & can be noisy 4TH STREET DELAWARE STREET River Market Grand Boulevard CAMPBELL STREET 2 < Additional stop requires more money TH STREET Main Street Columbus Square You Are Here Loop End Track Existing Streetcar Maintenance Line Railroad Track Existing Bridge Streetcar Stop Level of Difficulty Not Feasible Difficult Challenging Preferred
8 Streetcar Options Considered FRONT STREET Berkley Riverfront Grand Boulevard < Shorter distance with less Missouri River 71 track to construct < Use of existing bridge is less expensive < Grades are manageable Existing Bridge Grand Boulevard Existing Bridge MAINTENANCE LINE Railroad Tracks KC Streetcar Maintenance Facility Stub End Preferred Route < Less track to construct < Easier to expand to the 4TH STREET DELAWARE STREET River Market Grand Boulevard CAMPBELL STREET 2 east in the future < Less noise TH STREET Main Street Columbus Square You Are Here Stub End Track Existing Streetcar Maintenance Line Railroad Track Existing Bridge Streetcar Stop Level of Difficulty Not Feasible Difficult Challenging Preferred
9 Streetcar Study Summary Level of Difficulty WHAT MAKES A ROUTE FEASIBILE? Not Feasible Difficult Challenging Preferred OPERATIONS SAFETY COST FUTURE EXPANSIONS Usability Maintain Timing Steep Grade Dangerous Condition New Bridge Track Length Curved Track Construction Schedule Add On vs. Reconstruct O L GRAND BLVD. W/ LOOP END GRAND BLVD. W/ STUB END
10 23 Bike, Pedestrian & Bus Connections 34X 36X Existing Connections: Potential Transfer Station Berkley Riverfront Potential Park-n-Ride locations 77 FRONT STREET HEART OF AMERICA BRIDGE 132 < Bike & Pedestrian: Safe access via 133 Town of Kansas Bridge & Lydia Ave. Missouri River 1 Berkley Park-And-Ride 71 < KCATA Routes: _ Route 77 over the Grand Blvd. Bridge _ Many routes converge at 3rd & Grand _ Routes 23, 34X & 36X pass near the Riverfront on I-2/I- Study Recommendations: DELAWARE STREET Study recommends dedicated bike & pedestrian path Town of Kansas Bridge Grand Boulevard Existing Bridge MAINTENANCE LINE Proposed Streetcar Route KC Streetcar Maintenance Facility LYDIA AVENUE 142 < Transfer stations between streetcar & buses on the Riverfront Potential Transfer Station CAMPBELL STREET 2 < Dedicated pedestrian & bike path along Grand Blvd. Bridge < Parking options on the Riverfront such as Park-n-Ride to connect via streetcar to downtown neighborhoods TH STREET 6TH STREET Main Street River Market MAX Grand Boulevard Columbus Square 24 You Are Here Bike/Pedestrian Lane Existing Bike Lanes Bus Routes Existing Streetcar Maintenance Line Railroad Track Existing Bridge Streetcar Stop
11 How will the proposed Funding strategy would Streetcar route be funded? not take away from other city services such as: street maintenance, < Revenues generated from new development on the Riverfront < State / Federal programs and grants bus funds, or recently approved GO Bond funds < Multi-modal grants < Existing funding streams
12 Next steps: Streetcar to the Riverfront Ongoing Study Phase Financial Design Construction Testing Operations <Which route is more feasible? <How much will it cost? <Identify local & federal funding opportunities <Where should station stops be located? <What type of shelter should be installed at each stop? <Where do power poles go? <Communication with those along the route who will be affected by the construction. <Utility coordination (such as electric, water, gas, cable, etc.) <Dry-run testing & careful consideration for rider safety. <Riders are ready to board! <Ongoing maintenance is provided
Develop ground transportation improvements to make the Airport a multi-modal regional
Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use
More informationvision42
vision42 www.vision42.org vision42 auto-free light rail boulevard for 42nd Street Roxanne Warren, AIA, Chair George Haikalis, ASCE, Co-Chair Institute for Rational Urban Mobility,Inc. www.vision42.org
More informationCTfastrak Expansion. Stakeholder Meeting #4 Manchester Town Hall June 3, 2016
CTfastrak Expansion Stakeholder Meeting #4 Manchester Town Hall June 3, 2016 Today s Agenda Phase I Update 2016 Service Plan Implementation Schedule & Cost Update Phase II Services Timeline Market Analysis
More informationTempe Streetcar. March 2, 2016
Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use
More informationDowntown Transit Connector. Making Transit Work for Rhode Island
Downtown Transit Connector Making Transit Work for Rhode Island 3.17.17 Project Evolution Transit 2020 (Stakeholders identify need for better transit) Providence Core Connector Study (Streetcar project
More informationChapter 4 : THEME 2. Transportation
Chapter 4 : THEME 2 Strengthen connections to keep the Central Area easy to reach and get around 55 Figure 4.2.1 Promote region-wide transit investments. Metra commuter rail provides service to the east,
More informationBreakout Session. The Mobility Challenges of Our Growing & Sprawling Upstate
Breakout Session The Mobility Challenges of Our Growing & Sprawling Upstate The Mobility Challenges of Our Growing & Sprawling Upstate Why is our suburban and sprawling development pattern a challenge
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationClick to edit Master title style
Nelson/Nygaard Consulting Associates SERVICE IMPROVEMENT STRATEGIES September 22, 2015 1 PROJECT OVERVIEW & WORK TO DATE 1. Extensive stakeholder involvement Throughout 2. System and market assessment
More informationCEDAR AVENUE TRANSITWAY Implementation Plan Update
CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,
More informationKANSAS CITY STREETCAR
KANSAS CITY STREETCAR KAREN CLAWSON MID-AMERICA REGIONAL COUNCIL KANSAS CITY STREETCAR Regional Context Alternatives Analysis Kansas City Streetcar Project KANSAS CITY REGION KANSAS CITY REGION KANSAS
More informationService Quality: Higher Ridership: Very Affordable: Image:
Over the past decade, much attention has been placed on the development of Bus Rapid Transit (BRT) systems. These systems provide rail-like service, but with buses, and are typically less expensive to
More informationIMPROVEMENT CONCEPTS
IMPROVEMENT CONCEPTS for the South Novato Transit Hub Study Prepared by: January 11, 2010 DKS Associates With Wilbur Smith Associates IMPROVEMENT CONCEPTS Chapter 1: Introduction 1. INTRODUCTION The strategic
More informationDraft Results and Open House
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi
More informationState Avenue Corridor Bus Rapid Transit (BRT)
State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!
More informationWAKE TRANSIT PLAN Summer 2018
WAKE TRANSIT PLAN Summer 2018 Planning for growth WAKE COUNTY s population already exceeds ONE MILLION and grows by more than 60 people a day. That s 23,000 people a year or basically another Morrisville.
More informationRevised Evaluation Scores. System Preservation
Revised Evaluation s System Preservation This page provides a summary of any revisions made to the draft scores presented at the October th Attributable Funds mmittee meeting. The information below highlights
More informationappendix 4: Parking Management Study, Phase II
appendix 4: Parking Management Study, Phase II A4-1 A4-2 Eastlake Parking Management Study Final Phase 2 Report Future Parking Demand & Supply January 6, 2017 Submitted by Denver Corp Center III 7900 E.
More informationRestoration of Historic Streetcar Services in Downtown Los Angeles
Restoration of Historic Streetcar Services in Downtown Los Angeles Early Scoping Meeting for Alternatives Analysis (AA) May 17, 2011 Introduction Key players Local lead agency: Metro Federal lead agency:
More informationMidtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014
Midtown Corridor Alternatives Analysis Policy Advisory Committee Meeting February 12, 2014 Today s Agenda Introductions Outreach efforts and survey results Other updates since last meeting Evaluation results
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program
More informationThe South Waterfront District and the Portland Aerial Tram
The South Waterfront District and the Portland Aerial Tram How infrastructure investment can catalyze redevelopment and remove barriers to healthy lifestyles Role of transportation infrastructure in creating
More informationSUPPORTING TOD IN METRO CHICAGO
www.rtachicago.org SUPPORTING TOD IN METRO CHICAGO Tuesdays at APA November 18, 2014 OVERVIEW OF RTA 2 11/18/2014 Tuesdays at APA: Supporting TOD in Metro Chicago RTA Region 8.5 million people 3,700 square
More informationNeeds and Community Characteristics
Needs and Community Characteristics Anticipate Population and Job Growth in the City Strongest density of population and jobs in Ann Arbor are within the Study Area Population expected to grow 8.4% by
More informationAppendix C. Parking Strategies
Appendix C. Parking Strategies Bremerton Parking Study Introduction & Project Scope Community concerns regarding parking impacts in Downtown Bremerton and the surrounding residential areas have existed
More informationHelp shape your community investment in Wake Transit. Fiscal Year 2019 Draft Work Plan Summary
Help shape your community investment in Wake Transit Fiscal Year 2019 Draft Work Plan Summary Wake County, growth and transit The Triangle is one of the fastest-growing regions in the nation. Wake County
More informationFor LEASE. Doug Deurwaarder Brad Carnese
For LEASE Brad Carnese 503 279 1750 brad.carnese@cushwake.com Mark Carnese 503 279 1764 mark.carnese@cushwake.com Doug Deurwaarder 503 279 1752 doug.deurwaarder@cushwake.com customblocksportland.com Landlord
More informationFor LEASE. customblocksportland.com
For LEASE customblocksportland.com LL is in receipt of a Conditional Use Permit with the City of Portland, that will allow for a wide range of creative office usage BUILDING HIGHLIGHTS BUILDING AMENITIES
More informationSnelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1
Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationThree ULTra Case Studies examples of the performance of the system in three different environments
Three ULTra Case Studies examples of the performance of the system in three different environments airport application: London Heathrow : linking business and staff car parks through the access tunnel
More informationNortheast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study
Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for
More informationPUBLIC TRANSPORTATION
PUBLIC TRANSPORTATION PROJECT TITLE U-MED DISTRICT MULTI-MODAL IMPROVEMENTS- PHASE II Transit Vehicles and Upgrades MUNICIPALITY OF ANCHORAGE Capital Improvement Program PROJECT LIST BY DEPARTMENT Public
More informationKenosha-Racine-Milwaukee (KRM)
Kenosha-Racine-Milwaukee (KRM) Commuter Rail #147925 November 6, 2009 1 Guidance of KRM Commuter Rail Studies Intergovernmental Partnership Technical Steering Committee Temporary and Limited Authority
More information4 Circulation & Transportation
4.1 Mobility Network The mobility network at the new St. Paul s hospital and health campus is comprised of an interconnected system of sidewalks, cycle paths, transit routes and roadways. Figure 4-1: Indicative
More informationFederal Way Link Extension
Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate
More informationPublic Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development
Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation
More informationLeadership NC. November 8, 2018
v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the
More informationTroost Corridor Transit Study
Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit
More informationTraveling around Town
Multimodal Transportation Planning: Traveling around Town Grades 6-8 30-45 minutes THE CHALLENGE Develop a plan to improve the multimodal transportation network in a fictional town by: Learning about the
More informationSTRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016
STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit
More informationRecommendation for 2017 PSRC Funding Transportation Policy Board - June 8, 2017
Recommendation for 2017 PSRC Funding Transportation Policy Board - June 8, 2017 Background PSRC s 2017 funding: Rural Town Centers and Corridor program Regional FTA competition May - Board released projects
More informationExecutive Summary October 2013
Executive Summary October 2013 Table of Contents Introduction... 1 Rider Transit and Regional Connectivity... 1 Plan Overview... 2 Network Overview... 2 Outreach... 3 Rider Performance... 4 Findings...
More informationConverting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada
Converting BRT to LRT in the Nation s Capital Ottawa, Canada John Manconi City of Ottawa Ottawa, Canada 1 The Challenge *Mackenzie King Bridge Ottawa, AM peak period 2 The Challenge Ottawa s population
More informationGreen Line Long-Term Investments
Enhancements Short-term improvements to keep Austin moving. Investments Long-term projects to support our future. Mobility Hubs MetroRapid MetroRail MetroExpress Connectors Circulators Project Connect
More informationBROWARD BOULEVARD CORRIDOR TRANSIT STUDY
BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,
More informationFY 2017 Proposed Work Session Follow-Up. April 4, 2016
Subject: DES Update on Parking Meter Tour FY 2017 Proposed Work Session Follow-Up April 4, 2016 The following information is provided in response to a request made by Mr. Vihstadt via email on March 7,
More informationStatus of Plans March Presented by CAPITOL REGION COUNCIL OF GOVERNMENTS
Status of Plans March 2011 Presented by CAPITOL REGION COUNCIL OF GOVERNMENTS Transit project update Project rationale The system New Britain Hartford Busway New Haven/Hartford/ Springfield Passenger Rail
More informationCITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6
2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY
More informationTHE WAY WE MOVE LRT FOR EVERYONE
THE WAY WE MOVE LRT FOR EVERYONE 2 LRT for Everyone LRT FOR EVERYONE Light rail is about more than transit; it s about transforming Edmonton. As the city grows, so do its transportation needs. LRT is an
More informationI-35W Past, Present, and Future: METRO Orange Line
I-35W Past, Present, and Future: METRO Orange Line 2018 State Public Transportation Partnerships Conference Charles Carlson Director, BRT Projects Metro Transit Charles.Carlson@metrotransit.org Metro Transit:
More informationThe Future of Transportation on the Caltrain Corridor
The Future of Transportation on the Caltrain Corridor 11.30.16 1 2 Today What is happening Vision Recommendations What is costs How to pay for it 3 The Caltrain Corridor is home to the world s innovation
More informationTRAIN, BUS & TRANSIT
TRAIN, BUS & TRANSIT Input Metra 1 Metra does not want to add parking because of space; maxed out on number of cars per train. Developments on Rt. 59 will affect. 2 Should do studies regarding what the
More informationCORE AREA SPECIFIC PLAN
only four (A, B, D, and F) extend past Eighth Street to the north, and only Richards Boulevard leaves the Core Area to the south. This street pattern, compounded by the fact that Richards Boulevard is
More informationWest Broadway Transit Study. Community Advisory Committee September 17, 2015
West Broadway Transit Study Community Advisory Committee September 17, 2015 Introductions Community Engagement Summer Outreach Fall Outreach Technical Analysis Process Update Alternatives Review Economic
More informationAn Overview of High Speed Rail. David Randall Peterman Congressional Research Service
An Overview of High Speed Rail David Randall Peterman Congressional Research Service 1 Defining High Speed Rail in the U.S. What is High Speed Rail? Allusions to world-class European and Asian systems
More informationMBTA Key Bus Route. Community Meeting Route 1 - Boston
MBTA Key Bus Route Improvement Program Community Meeting Route 1 - Boston United South End Settlement Agenda Welcome and introductions Safety briefing/accommodations Key Bus Route Program overview Existing
More informationLeveraging Land Use Changes through Transportation Funding
Leveraging Land Use Changes through Transportation Funding Railvolution 2005 September 10, 2005 James Corless Senior Planner What is the MTC region? 9 7 101 26 San Francisco Bay Area counties Million people;
More informationMaryland Gets to Work
I-695/Leeds Avenue Interchange Reconstruction Baltimore County Reconstruction of the I-695/Leeds Avenue interchange including replacing the I-695 Inner Loop bridges over Benson Avenue, Amtrak s Northeast
More informationBi-County Transitway/ Bethesda Station Access Demand Analysis
Bi-County Transitway/ Bethesda Station Access Demand Analysis Prepared for: Washington Metropolitan Area Transit Authority Office of Planning and Project Development May 2005 Prepared by: in conjunction
More informationHerding Cats; Strategies used for KC Downtown Streetcar Utility Coordination ASCE Transportation Conference
Herding Cats; Strategies used for KC Downtown Streetcar Utility Coordination ASCE Transportation Conference November 9, 2016 Kansas City Streetcar Project overview Current status Scope of water and sewer
More informationMajor Widening/New Roadway
Revised Evaluation s Major Widening/New Roadway This page provides a summary of any revisions made to the draft scores presented at the October th Attributable Funds Committee meeting. The information
More informationRevised Strategy for Downtown Parking
Revised Strategy for Downtown Parking December 4, 2017 Council Workshop Presented by Jennifer McCoy, P.E., City Traffic Engineer City-Owned Parking Today 3,500 metered parking spaces Parking meters charge
More information1 Downtown LRT Connector: Draft Concept
Downtown LRT Connector: Draft Concept Plan November 2010 We re moving forward. Get involved. On June 21, 2010, City Council approved a street-level downtown LRT route, including a connector for the future
More informationPace Bus Depot Location Analysis
Pace Bus Depot Location Analysis Key Notes 1. Options refer to conceptual sketches prepared by Kimley Horn. 2. The depot is assumed to accommodate Pace routes as they currently exist: 17 routes on the
More information2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS. Eastside Transportation Partnership September 9, 2016
2016 PSRC REGIONAL & KING COUNTYWIDE EASTSIDE FUNDING AWARDS Eastside Transportation Partnership September 9, 2016 1 2 PSRC 2016 Project Selection Process 2018-2020 Estimated FHWA Funds Available: (Summary)
More informationRapid Transit and Land-Use Integration a Reality
City of Charlotte Rapid Transit and Land-Use Integration a Reality Transportation Oversight Committee Carolyn Flowers CEO Charlotte Area Transit System April 29, 2010 Charlotte Region Statistics Mecklenburg
More informationI-35W & Lake Street Station
I-35W & Lake Street Station 2017 CMAQ Funding Proposal April 16, 2014 Charles Carlson Metro Transit BRT/Small Starts Project Office www.metrotransit.org/orangeline Addressing Corridor Challenges 7+ Hours/day
More informationBCA Benefits and Assumptions Summary
2016 TIGER Application - Plymouth Multimodal BCA Benefits and Assumptions Summary The Plymouth Multimodal generates a variety of benefits, ranging from monetary such as increased transit fare revenue,
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationDenver Metro Association of Realtors
Denver Metro Association of Realtors North Metro Rail Line October 2, 2014 1 The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service 31 new Park-n-Rides;
More informationUNION STATION MASTER PLAN STUDY
UNION STATION MASTER PLAN STUDY The Chicago Department of Transportation has begun a comprehensive study of issues related to Chicago s Union Station, the Union Station Master Plan. Opened in 1925, Union
More informationPEACHTREE CORRIDOR PARTNERSHIP. Current Status & Next Steps
PEACHTREE CORRIDOR PARTNERSHIP Current Status & Next Steps PEACHTREE CORRIDOR PARTNERSHIP Why Peachtree? Why Now? I. THE CONTEXT High Level View of Phasing Discussion Potential Ridership Segment 3 Ease
More informationVAN NESS AVENUE BUS RAPID TRANSIT
VAN NESS AVENUE BUS RAPID TRANSIT Commission of the Environment Policy Committee May 22, 2014 Peter Gabancho Project Manager III Capital Programs & Construction SFMTA 1 Conceptual Visual Simulation Center-Running
More informationAssessing Streetcar Feasibility in Your Community. Rail~Volution. Thomas Brennan Nelson\Nygaard Nygaard Consulting September 9, 2005
Assessing Streetcar Feasibility in Your Community Rail~Volution Thomas Brennan Nelson\Nygaard Nygaard Consulting September 9, 2005 Recapturing the heart of America! Historic and modern streetcars are making
More informationMaking. Connections: Access, Connectivity and Parking at the Downtown SMART Station. Petaluma SMART Station Area TOD Master Plan.
Petaluma SMART Station Area TOD Master Plan Photo by Scott Hess, see http://cityofpetaluma.net/ Making June 23, 2011 Connections: Access, Connectivity and Parking at the Downtown SMART Station Petaluma
More informationCalgary Transit and the Calgary Transportation Plan Chris Jordan, M.Sc., P.Eng. Coordinator, Strategic Transit Planning, Calgary Transit
Calgary Transit and the Calgary Transportation Plan Chris Jordan, M.Sc., P.Eng. Coordinator, Strategic Transit Planning, Calgary Transit 1. Plan It Calgary the new Municipal Development Plan and Calgary
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationTSPLOST 2018 Project Request $ 1,531,000 Estimated Annual Operating Impact $ 0
TSPLOST 2018 Project Statements from Submitted Projects Project # 01, 01 Airport Capital Improvements Program (CIP) Matching Funds, will include the construction of numerous FAA and GDOT funded projects
More informationBackground Information about the Metrobus 29 Lines Study
Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and
More informationSUMMARY OF COMMENTS AT PUBLIC OPEN HOUSES SCOPING OF ALTERNATIVES GATEWAY CORRIDOR ALTERNATIVES ANALYSIS
SUMMARY OF COMMENTS AT PUBLIC OPEN HOUSES SCOPING OF ALTERNATIVES GATEWAY CORRIDOR ALTERNATIVES ANALYSIS A second series of four public open houses was held for the Gateway Corridor Alternatives Analysis
More informationTransportation Infrastructure Investment Program moving
moving CALGARY What is TIIP? Ten Year Transportation Capital Program Last approved by Council in 2005 Defines: Major infrastructure projects Lifecycle programs What is TIIP? Represents current planned
More informationSan Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors
Transportation Committee November 17, 2016 Agenda Item No. 5, Update on the San Rafael Transit Center Relocation San Rafael Transit Center Relocation Study Update 11/17/16 Golden Gate Bridge, Highway &
More informationEUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT
EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING
More informationACTION TRANSMITTAL
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: February 12, 2014 TO: FROM: PREPARED BY: SUBJECT: REQUESTED ACTION: RECOMMENDED MOTION: ACTION TRANSMITTAL 2014-14 Transportation
More informationWelcome. Green Line in Your Community
Welcome Green Line in Your Community Today's session will provide you with information about Administration's recommendation for connecting the Green Line in the Beltline to Victoria Park and Inglewood/Ramsay
More informationCharlotte-Mecklenburg Region Rapid Transit and Land-Use Integration
Charlotte-Mecklenburg Region Rapid Transit and Land-Use Integration Legislative Committee on Urban Growth and Infrastructure Carolyn Flowers CEO Charlotte Area Transit System March 23, 2010 Charlotte Region
More informationDART Priorities Overview
City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee
More informationMETRO Orange Line BRT American Boulevard Station Options
METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN
More informationCommunity Open Houses November 29 December 7, 2017
Community Open Houses November 29 December 7, 2017 1 Community Open House Agenda 6:00 PM Open House 6:30-7:30 PM Presentation and Q&A 7:30-8:00 PM Open House Resumes after the presentation and Q&A Thank
More informationReston Transportation Strategy July 9, 2018
Reston Transportation Strategy July 9, 2018 Background: On February 11, 2014, the Board of Supervisors adopted the Reston Phase I Comprehensive Plan Amendment for the core areas of Reston between Sunset
More informationPlanning for Tomorrow
1 Regional Growth Planning for Tomorrow City of Des Moines Transportation Master Plan Connect Downtown What did Des Moines residents have to say? 4 Non-rider survey feedback Is public transit important
More informationCITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan
Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting
More informationJTA S MOBILITY CORRIDORS. Improving System Performance Through Urban Design
JTA S MOBILITY CORRIDORS Improving System Performance Through Urban Design Overview Agenda Overview of Jacksonville & JTA Catalysts for a Transit Driven Complete Streets Program Process Countermeasures
More informationMidtown Corridor Alternatives Analysis Key Issues Memo
Midtown Corridor Alternatives Analysis Key Issues Memo 1/4/2013 Prepared by the SRF Consulting Group Team for Table of Contents Introduction... 1 1. Markets... 1 External Markets... 1 Intra-Corridor Travel...
More informationAnalysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville
Analysis of Radial and Trunk Feeder Transit System Configurations in Downtown Charlottesville 1. Introduction During the stakeholder input sessions of Charlottesville Area Transit s (CAT) Transit Development
More informationROCHESTER, MINNESOTA
ROCHESTER, MINNESOTA Rochester Public Works TRANSIT AND PARKING DIVISION Transit and Parking Manager Tony Knauer tknauer@rochestermn.gov SERVICE ATTITUDE CONSISTENCY - TEAMWORK ROCHESTER TRANSIT & PARKING
More informationPoint A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017
Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master
More informationRail alignment and benefits (rab) study
Rail alignment and benefits (rab) study previously known as railyard alternatives & i-280 boulevard study June 5, 2018 CONNECTING CALIFORNIA 4,300 lane miles + 115 Airport gates would be needed to create
More informationMay 23, 2011 APTA Bus & Paratransit Conference. Metro ExpressLanes
May 23, 2011 APTA Bus & Paratransit Conference Metro ExpressLanes Program Overview > Conversion of HOV lanes to HOT lanes on I-10 and I-110 > Multi-modal Integrated Corridor Emphasis > 1 of 6 Nationwide
More information