1 REC Training Programme on Power Factor Improvement and Reactive Power Management 8 11 July, 2014 at CIRE, Hyderabad CENTRAL INSTITUTE FOR RURAL ELECTRIFICATION RURAL ELECTRIFICATION CORPORATION LIMITED

2 REC Training Programme on Power Factor Improvement and Reactive Power Management 8 11 July, 2014 at CIRE, Hyderabad CENTRAL INSTITUTE FOR RURAL ELECTRIFICATION RURAL ELECTRIFICATION CORPORATION LIMITED

3 INTRODUCTION Power supply quality, continuity and reliability even under contingencies are the hallmark efficient Distribution and Transmission utilities respectively. Voltage excursions, consumer services fered and frequency variations define the Quality power supply. Degraded quality supply begets consumers' ire whereas heavy losses cripple the finances the utilities, besides raising the tariff power. Low Voltages are, by and large, the result imbalance between the reactive power demand and supply. The reactive power demand arises not only from inductive load points, but also from system components like transformers and lines resulting in the following: Poor Power factor leading to bad voltage prile and increased losses. Overloading network components due to the drawl higher current. Introduction harmonics in the system due causing saturation system components and distortions in the supply wave form, detrimental to the equipment. Long EHV transmission lines also generate reactive power, due to the capacitance the line, during the light load conditions. The capacitive output the line is almost constant except for variations in the voltage whereas during peak load reactive power loss, proportional to the square the current far exceeds the line's reactive power generation. The low receiving end voltage adversely affects the stability the line and/or its power transmission capability. The reactive power demand needs to be met, preferably at the point where it arises to obviate problems stated above effectively and economically. Reactance lines also has to be compensated in long transmission lines for enhancing steady state transmission capability and stability. In respect power factor improvement, shunt capacitors are the most versatile, flexible, economical, and fastest to be installed. Series capacitors mostly serve as automatic voltage regulators besides enhancing transmission capability and stability. Thyristor controlled capacitors and reactors have been fast acting and cost effective. However, the life the capacitors depends on proper operating conditions and effective maintenance. Considering the importance Reactive power management in the Power systems, with nearly 70% the energy generated being consumed by the inductive load, CIRE proposes to conduct a 4 day training programme on Power factor Improvement and Reactive Power Management from 8th to 11th July, 2013, in its campus. PROGRAMME OBJECTIVES To study effective methods improving Power factor and voltage regulations and thereby reducing system losses. Learn means for reduction in line reactance for improving Transmission line loading capabilities. To provide insight into the design and Operation and maintenance aspects various equipment in usage for reactive power compensation. To study the effective methods their installation, testing and commissioning, operation and maintenance and protection system equipment associated with Reactive power management, to ensure enhancement life expectancy. Analyse various causes failure and suggest remedial measures PROGRAMME CONTENTS Fundamental principles, definitions, useful formulae, functions and applications capacitors Effect Reactive power: Concepts Technical loss reduction and Power factor and Voltage prile Improvement with Reactive power compensation Equipment for Reactive Power Compensation (a) Capacitors, (b) Shunt Reactor, (c) Series reactor (d) Series Capacitors and (e) Static Var Compensation.

4 Salient features Selection site, erection, testing & commissioning to operation and maintenance related equipment. 11kv and LT switched capacitors and automatic switching Capacitors Capacitor bank formation and Neutral grounding. Associated switch gear, control gear and protection for power capacitors and capacitor banks. Salient features series capacitor, its erection and operation and maintenance Salient features Shunt and series reactors. Operation and maintenance and testing and commissioning and protection Shunt Reactors. Case studies capacitor bank/ shunt reactor failures. Field visit. PARTICIPANT LEVEL Junior and middle level executives Utilities dealing with Distribution, Transmission, High Energy Consuming Industries, private Entrepreneurs Independent Power Producers and Research/Academic Institutions. PEDAGOGY The programme will be conducted in an interactive environment, with faculty acting as facilitators to create a participative learning environment along with Field Visit. Resources persons from respective field are identified as guest speakers. DURATION & VENUE 4 days from 8 to 11 July, 2014 at CIRE Campus, Sivarampally, Aramghar 'X'Road, Hyderabad. The programme is residential. PROGRAMME FEE Category Course fee per partcipants Service Tax ( 12.36%) Total Course fee/participants without Group Discount Residential* Rs. 18,000 Rs. 2,225 Rs. 20,225 10% Non Residential**, Rs. 15,000 Rs. 1,854 Rs. 16,854 10% * includes Boarding and Accommodation in addition to tuition, courseware & other facilities, field visit, etc. No Pickup or drop facility will be provided by CIRE ** Excludes Boarding and Accommodation. No Pick-up or drop facility will be provided by CIRE *** only on Participation basis Course fee shall be paid in the form a demand draft in favor Central Institute Rural Electrification payable at Hyderabad in advance or at least at the time registration. HOW TO REGISTER Please send your nominations by fax / on or before 01-Jul-2014 to the Addl. Director/Programme Coordinator, CIRE, Hyderabad (Fax No & cire.rec@gmail.com ) CERTIFICATE OF PARTICIPATION The Institute issues a certificate Participation on conclusion the programme. Group Discount for three or more Participation*** Programme Coordinator APARUP PAUL Course Advisor G. SHANKAR Additional Director

5 Route Map CIRE, Hyderabad Airport Road 14 km NH 7 CIRE Pariwar Dhaba PV Narasihma Rao Express Way LB Nagar Aramghar X Roads Mehadipatnam 12 km National Police Academy (NPA) 2km Afzalgunj, MGBS For further details please contact: APARUP PAUL, Programme Coordinator, Central Institute for Rural Electrification, Shivarampally, National Highway No.7, National Police Academy Post, Hyderabad Mobile No.: REC Central Institute for Rural Electrification Rural Electrification Corporation Limited Shivarampally, NPA Post, Hyderabad Phones Office : , , Hostel: Fax No & , cire.rec@gmail.com Balaram Graphics : Website :

ELG4125: Flexible AC Transmission Systems (FACTS)

ELG4125: Flexible AC Transmission Systems (FACTS) ELG4125: Flexible AC Transmission Systems (FACTS) The philosophy of FACTS is to use power electronics for controlling power flow in a transmission network, thus allowing the transmission line to be loaded

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS XXV. NET METERING A. Applicability and Availability 1. The terms Net Metering Service, Demand Charge-based Time-of- Use Tariff, Net Metering Customer, Customer, Time-of-Use Customer, Time-of-Use Tier,

More information

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY DRAFT Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY 2018 1. INTRODUCTION Solar energy has become the most popular renewable energy source

More information

1 Low-voltage Power-factor Correction capacitors KNK APPLICATION DESIGN

1 Low-voltage Power-factor Correction capacitors KNK APPLICATION DESIGN APPLICATION The KNK capacitors are used for power - factor correction of inductive consumers (transformers, electric motors, rectifiers) in industrial networks for voltages of up to 660 V. DESIGN Cylindrical

More information

Enhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System

Enhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System Enhancement of Power Quality in Transmission Line Using Flexible Ac Transmission System Raju Pandey, A. K. Kori Abstract FACTS devices can be added to power transmission and distribution systems at appropriate

More information

Overview of Flexible AC Transmission Systems

Overview of Flexible AC Transmission Systems Overview of Flexible AC Transmission Systems What is FACTS? Flexible AC Transmission System (FACTS): Alternating current transmission systems incorporating power electronic-based and other static controllers

More information

THE PUBLIC SERVICE COMMISSION OF WYOMING

THE PUBLIC SERVICE COMMISSION OF WYOMING NAME: Powder River Energy Corporation WY PSC Tariff No. 7 ADDRESS:, Sundance, WY 82729 THE PUBLIC SERVICE COMMISSION OF WYOMING TARIFF RATE RIDER 5th Revised Sheet No. 1 Cancels 4th Revised Sheet No. 1

More information

Reactive Power Management Using TSC-TCR

Reactive Power Management Using TSC-TCR Reactive Power Management Using TSC-TCR Kumarshanu Chaurasiya 1, Sagar Rajput 1, Sachin Parmar 1, Prof. Abhishek Patel 2 1 Student, Department of Electrical Engineering, Vadodara institute of engineering,

More information

Chapter 3.1: Electrical System

Chapter 3.1: Electrical System Part-I: Objective type Questions and Answers Chapter 3.1: Electrical System 1. The heat input required for generating one kilo watt-hour of electrical output is called as. a) Efficiency b) Heat Rate c)

More information

ABB n.v Power Quality in LV installations

ABB n.v Power Quality in LV installations ABB n.v. - 1 - Power Quality in LV installations PQ problems in LV installations 750 500 250 Volts 0-250 -500 Amps -750 3000 2000 1000 0-1000 -2000-3000 10:25:43.72 10:25:43.73 10:25:43.74 10:25:43.75

More information

Performance Analysis of Transmission Line system under Unsymmetrical Faults with UPFC

Performance Analysis of Transmission Line system under Unsymmetrical Faults with UPFC Int. J. of P. & Life Sci. (Special Issue Engg. Tech.) Performance Analysis of Transmission Line system under Unsymmetrical Faults with UPFC Durgesh Kumar and Sonora ME Scholar Department of Electrical

More information

IJRASET 2013: All Rights are Reserved

IJRASET 2013: All Rights are Reserved Power Factor Correction by Implementation of Reactive Power Compensation Methods of 220 KV Substation MPPTCL Narsinghpur Ria Banerjee 1, Prof. Ashish Kumar Couksey 2 1 Department of Energy Technology,

More information

Concepts And Application Of Flexible Alternating Current Transmission System (FACTS) In Electric Power Network

Concepts And Application Of Flexible Alternating Current Transmission System (FACTS) In Electric Power Network Concepts And Application Of Flexible Alternating Current Transmission System (FACTS) In Electric Power Network Nwozor Obinna Eugene Department of Electrical and Computer Engineering, Federal University

More information

ABB POWER SYSTEMS CONSULTING

ABB POWER SYSTEMS CONSULTING ABB POWER SYSTEMS CONSULTING DOMINION VIRGINIA POWER Offshore Wind Interconnection Study 2011-E7406-1 R1 Summary Report Prepared for: DOMINION VIRGINIA POWER Report No.: 2011-E7406-1 R1 Date: 29 February

More information

4-Day Power System Analysis, Coordination, System Studies

4-Day Power System Analysis, Coordination, System Studies 4-Day Power System Analysis, Coordination, System Studies Contact us Today for a FREE quotation to deliver this course at your company?s location. https://www.electricityforum.com/onsite-training-rfq Our

More information

Implementation of FC-TCR for Reactive Power Control

Implementation of FC-TCR for Reactive Power Control IOSR Journal of Electrical and Electronics Engineering (IOSR-JEEE) e-issn: 2278-1676,p-ISSN: 2320-3331, Volume 5, Issue 5 (May. - Jun. 2013), PP 01-05 Implementation of FC-TCR for Reactive Power Control

More information

Enhancement of Power System Stability Using Thyristor Controlled Series Compensator (TCSC)

Enhancement of Power System Stability Using Thyristor Controlled Series Compensator (TCSC) Enhancement of Power System Stability Using Thyristor Controlled Series Compensator (TCSC) Pooja Rani P.G. Research Scholar in Department of Electrical Engg. MITM, Hisar, Haryana, India Mamta Singh Assistant

More information

POWER FACTOR CORRECTION USING SHUNT COMPENSATION

POWER FACTOR CORRECTION USING SHUNT COMPENSATION International Journal of Electrical and Electronics Engineering (IJEEE) ISSN(P): 2278-9944; ISSN(E): 2278-9952 Vol. 3, Issue 3, May 2014, 39-48 IASET POWER FACTOR CORRECTION USING SHUNT COMPENSATION DHRUVI

More information

Supercapacitor Based Power Conditioning System for Power Quality Improvement in Industries

Supercapacitor Based Power Conditioning System for Power Quality Improvement in Industries Supercapacitor Based Power Conditioning System for Power Quality Improvement in Industries T. Barath, E. Anand Issack, M. Ragupathi, Gummididala V. S. Pavankumar, EEE Department Abstract-- Transmission

More information

Magnetically Controlled Reactors Enhance Transmission Capability & Save Energy Especially in Compact Increased Surge-Impedance- Loading Power Lines

Magnetically Controlled Reactors Enhance Transmission Capability & Save Energy Especially in Compact Increased Surge-Impedance- Loading Power Lines Magnetically Controlled Reactors Enhance Transmission Capability & Save Energy Especially in Compact Increased Surge-Impedance- Loading Power Lines Prof. Alexander M. Bryantsev, Moscow Power Institute,

More information

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION Presentation by Engr. O. C. Akamnnonu Chief Executive Officer, Ikeja Electricity Distribution Company AGENDA WORK THROUGH

More information

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements Applicability 1 Section 502.3 applies to: the legal owner of a generating unit directly connected to the transmission system with a maximum authorized real power rating greater than 18 MW; the legal owner

More information

Estimating the cost of electrification technology options to aid electricity access scale up: The case of Ghana

Estimating the cost of electrification technology options to aid electricity access scale up: The case of Ghana The African Electrification Initiative Practitioner Workshop, Dakar, Senegal November 14 th 16 th, 2011 Estimating the cost of electrification technology options to aid electricity access scale up: The

More information

Controllable reactor with HTS control winding Dr. Torbjörn Wass, ABB Corporate Research, Västerås, Sweden

Controllable reactor with HTS control winding Dr. Torbjörn Wass, ABB Corporate Research, Västerås, Sweden Controllable reactor with HTS control winding Dr. Torbjörn Wass, ABB Corporate Research, Västerås, Sweden ABB AB, Corporate Research - 1 Topic The design and construction of a small scale prototype of

More information

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT Prof. Chandrashekhar Sakode 1, Vicky R. Khode 2, Harshal R. Malokar 3, Sanket S. Hate 4, Vinay H. Nasre 5, Ashish

More information

MPSEZ Utilities Private Limited Truing up for FY and Determination of Tariff for FY

MPSEZ Utilities Private Limited Truing up for FY and Determination of Tariff for FY ANNEXURE: TARIFF SCHEDULE Tariff Schedule for Adani Ports and SEZ Ltd License area of MPSEZ Utilities Pvt. Ltd. Effective from 1 st April, 2018 General Conditions 1. This tariff schedule is applicable

More information

CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR

CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR 100 CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR 6.1 INTRODUCTION Conventional energy resources are not sufficient to meet the increasing electrical power demand. The usages of

More information

Smart Grid Foundation Course

Smart Grid Foundation Course Introduction: The 21st century electric grid is witnessing several disruptive changes. After 100 years of centralized power generation and creation of massive electric grids, the shift is now towards de-centralized

More information

International Journal of Emerging Technology and Innovative Engineering Volume 2, Issue 4, April 2016 (ISSN: )

International Journal of Emerging Technology and Innovative Engineering Volume 2, Issue 4, April 2016 (ISSN: ) International Journal of Emerging Technology and Innovative Engineering Volume 2, Issue 4, April 2016 (ISSN: 2394 6598) Date of Publication: 25.04.2016 TRANSIENT FREE TSC COMPENSATOR FOR REACTIVE LOAD

More information

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice

UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow. Public Notice UP Electricity Regulatory Commission Vidyut Niyamak Bhawan, Vibhuti Khand, Gomti Nagar, Lucknow No.UPERC/ Secy/JD(G)/2018/ dated : 20 th August, 2018 Public Notice The Commission is in process of reviewing

More information

Powerframes - Power Electronics

Powerframes - Power Electronics Powerframes - Power Electronics 70 series The study of power electronic devices, motor drives and circuits is an essential part of any course on power electrical systems. The Series 70 Power Electronics

More information

Sl. No. Subject Description Level of Study 01 Power Different types of converters, inverters. 6 th Sem Electronics 02 Power System I& II

Sl. No. Subject Description Level of Study 01 Power Different types of converters, inverters. 6 th Sem Electronics 02 Power System I& II Course Name: Power System III Course Code: EE70A Credit: Prerequisites: Sl. No. Subject Description Level of Study 0 Power Different types of converters, inverters. 6 th Sem Electronics 0 Power System

More information

Variable Speed-Drive Troubleshooting

Variable Speed-Drive Troubleshooting Variable Speed-Drive Troubleshooting This course is Designed, Developed, and will be Delivered under ISO 29990:2010 Standards 10-14 October 2016 Vietnam 24-MAR-16 Variable Speed-Drive Troubleshooting Why

More information

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC)

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC) TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC) Nazneen Choudhari Department of Electrical Engineering, Solapur University, Solapur Nida N Shaikh Department of Electrical

More information

INTRODUCTION. In today s highly complex and interconnected power systems, mostly made up of thousands of buses and hundreds of generators,

INTRODUCTION. In today s highly complex and interconnected power systems, mostly made up of thousands of buses and hundreds of generators, 1 INTRODUCTION 1.1 GENERAL INTRODUCTION In today s highly complex and interconnected power systems, mostly made up of thousands of buses and hundreds of generators, there is a great need to improve electric

More information

CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION

CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 150 KW Also Serves as Application for Category 2 Net Metering

More information

DESIGN CONSIDERATIONS FOR APPLICATION OF SHUNT CAPACITORS IN HEAVY HATER PLANT (TUTICORIN)

DESIGN CONSIDERATIONS FOR APPLICATION OF SHUNT CAPACITORS IN HEAVY HATER PLANT (TUTICORIN) DESIGN CONSIDERATIONS FOR APPLICATION OF SHUNT CAPACITORS IN HEAVY HATER PLANT (TUTICORIN) -A.R. Subraaanian -R.A.A. Palani -J. Thomson A new 3.3 K.V. 4200 KVAR auto switching capacitor bank has been installed

More information

Management of Congestion in the Deregulated Energy Market

Management of Congestion in the Deregulated Energy Market International Journal of Scientific and Research Publications, Volume 6, Issue 7, July 2016 284 Management of Congestion in the Deregulated Energy Market Onwughalu, M.k Department of Electrical and Electronic

More information

SANTA CLARA CITY RENEWABLE NET METERING & INTERCONNECTION AGREEMENT

SANTA CLARA CITY RENEWABLE NET METERING & INTERCONNECTION AGREEMENT SANTA CLARA CITY RENEWABLE NET METERING & INTERCONNECTION AGREEMENT This Net Metering and Interconnection Agreement ( Agreement ) is made and entered into as of this day of, 2018, by the City of Santa

More information

Electric Utility Contact Information Indiana Michigan Power

Electric Utility Contact Information Indiana Michigan Power CATEGORY 2 GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 20 KW BUT LESS THAN OR EQUAL TO 150 KW Also Serves as Application for Category 2 Net Metering

More information

Powerframes - Power Electronics

Powerframes - Power Electronics Powerframes - Power Electronics 70 series The study of power electronic devices, motor drives and circuits is an essential part of any course on power electrical systems. The Series 70 Power Electronics

More information

Induction Generator: Excitation & Voltage Regulation

Induction Generator: Excitation & Voltage Regulation Induction Generator: Excitation & Voltage Regulation A.C. Joshi 1, Dr. M.S. Chavan 2 Lecturer, Department of Electrical Engg, ADCET, Ashta 1 Professor, Department of Electronics Engg, KIT, Kolhapur 2 Abstract:

More information

Reactive Power Compensation using 12 MVA Capacitor Bank in 132/33 KV Distribution Substation

Reactive Power Compensation using 12 MVA Capacitor Bank in 132/33 KV Distribution Substation Reactive Power Compensation using 12 MVA Capacitor Bank in 132/33 KV Distribution Substation Yogesh U Sabale 1, Vishal U Mundavare 2, Pravin g Pisote 3, Mr. Vishal K Vaidya 4 1, 2, 3, 4 Electrical Engineering

More information

Medium Voltage. Power Factor Correction Reactive Compensation Harmonic Filters. Electrical Power Quality Management at its best.

Medium Voltage. Power Factor Correction Reactive Compensation Harmonic Filters. Electrical Power Quality Management at its best. Medium Voltage Power Factor Correction Reactive Compensation Harmonic Filters POWER QUALITY Electrical Power Quality Management at its best. From electricity generation, transmission, thru its distribution

More information

Microcontroller Based Power Factor Correction Using SCR

Microcontroller Based Power Factor Correction Using SCR Proceedings of International Conference on Innovation & Research in Technology for Sustainable Development (ICIRT 2012), 01-03 November 2012 124 Microcontroller Based Power Factor Correction Using SCR

More information

Dynamic Control of Grid Assets

Dynamic Control of Grid Assets Dynamic Control of Grid Assets ISGT Panel on Power Electronics in the Smart Grid Prof Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent Power Infrastructure Consortium School

More information

PQC - STATCON The ultra fast Power Quality Compensator

PQC - STATCON The ultra fast Power Quality Compensator PQC - STATCON The ultra fast Power Quality Compensator PQC - STATCON The ultra fast power quality compensator PQC - STATCON is based on IGBT voltage source inverter technology. It is a shunt connected

More information

TECHNICAL TERMS AND ABBREVIATIONS

TECHNICAL TERMS AND ABBREVIATIONS THIRD REVISED SHEET NO. 3.1 CANCELS SECOND REVISED SHEET NO. 3.1 TECHNICAL TERMS AND ABBREVIATIONS ALTERNATING CURRENT (A-C): AMPERE: BASE RATES: BRITISH THERMAL UNIT (BTU): CAPACITOR or CAPACITANCE: CAPACITY

More information

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description Final Draft Report Assessment Summary Hydro One Networks Inc. : Refurbish 115/44 kv, 25/33/42 MVA DESN Station CAA ID Number: 2007-EX360 1.0 General Description Hydro One is proposing to replace the existing

More information

Expert Course Faculty Leader. Testimonials 25 FEB 01 MARCH 2019, KUALA LUMPUR MALAYSIA. 11 th Successful Run in Asia!

Expert Course Faculty Leader. Testimonials 25 FEB 01 MARCH 2019, KUALA LUMPUR MALAYSIA. 11 th Successful Run in Asia! 11 th Successful Run in Asia! MASTERCLASS IN RELAY PROTECTION IN POWER SYSTEMS Comprehensive and interactive course on relay protection in power systems, incorporating fault analysis, protection requirements,

More information

TRANSMISSION PLANNING CRITERIA

TRANSMISSION PLANNING CRITERIA CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003-3502 Effective Date: TRANSMISSION PLANNING CRITERIA PURPOSE This specification describes Con Edison s Criteria for assessing

More information

Integration of Large Wind Farms into Electric Grids

Integration of Large Wind Farms into Electric Grids Integration of Large Wind Farms into Electric Grids Dr Mohammad AlZoubi Introduction Development WHAT IS NEXT!! Over the next 12 years, Europe must build new power capacity equal to half the current total.

More information

Net Metering Service. Customer Information Package

Net Metering Service. Customer Information Package Net Metering Service Customer Information Package March 20, 2017 Net Metering - The means of measuring the difference between the electricity supplied by an electric utility and the electricity generated

More information

GENERATOR INTERCONNECTION APPLICATION

GENERATOR INTERCONNECTION APPLICATION GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 150 KW BUT LESS THAN OR EQUAL TO 550 KW Also Serves as Application for Category 3 Net Metering (Note:

More information

HVDC MATIARI -LAHORE TRANSMISSION PROJECT ABDUR RAZZAQ CHEEMA, EX-GENERAL MANGER (GRID SYSTEM CONSTRUCTION PROJECTS) NTDC

HVDC MATIARI -LAHORE TRANSMISSION PROJECT ABDUR RAZZAQ CHEEMA, EX-GENERAL MANGER (GRID SYSTEM CONSTRUCTION PROJECTS) NTDC HVDC MATIARI -LAHORE TRANSMISSION PROJECT ABDUR RAZZAQ CHEEMA, EX-GENERAL MANGER (GRID SYSTEM CONSTRUCTION PROJECTS) NTDC SEQUENCE OF PRESENTATION OVERVIEW GENERATION PROPOSED IN SOUTH (2011) EVACUATION

More information

Low Voltage Power Factor Corrections

Low Voltage Power Factor Corrections Low Voltage Power Factor Corrections Capacitors Contents General information on Iskra Capacitors Type Page Introduction 4 1. Single-phase capacitor type KNK5015 230 550 V, 1,67.5 kvar 2. Three-phase capacitors

More information

Dynamic Control of Grid Assets

Dynamic Control of Grid Assets Dynamic Control of Grid Assets Panel on Power Electronics in the Smart Grid Prof Deepak Divan Associate Director, Strategic Energy Institute Director, Intelligent Power Infrastructure Consortium School

More information

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map EH2741 Communication and Control in Electric Power Systems Lecture 3 Lars Nordström larsn@ics.kth.se 1 Course map 2 1 Outline 1. Repeating Power System Control 2. Power System Topologies Transmission Grids

More information

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill)

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill) GENERATOR INTERCONNECTION APPLICATION Category 2 (Combined) For All Projects with Aggregate Generator Output of More Than 20 kw but Less Than or Equal to 150 kw Also Serves as Application for Category

More information

ELECTRICAL EQUIPMENT : TRANSFORMERS, INVERTERS, RECTIFIERS, UNINTERRUPTABLE POWER SYSTEMS, GENERATORS. UAE, Sharjah, Copthorne Hotel Sharjah

ELECTRICAL EQUIPMENT : TRANSFORMERS, INVERTERS, RECTIFIERS, UNINTERRUPTABLE POWER SYSTEMS, GENERATORS. UAE, Sharjah, Copthorne Hotel Sharjah Training Course : ELECTRICAL EQUIPMENT : TRANSFORMERS, INVERTERS, RECTIFIERS, UNINTERRUPTABLE POWER SYSTEMS, GENERATORS Training Course For One Week In UAE, Sharjah, Copthorne Hotel Sharjah Which Be Held

More information

PRESENTER PETER NJENGA CHIEF ENGINEER, CUSTOMER SERVICE, KENYA POWER EAST AFRICAN POWER INDUSTRY CONVENTION 2012

PRESENTER PETER NJENGA CHIEF ENGINEER, CUSTOMER SERVICE, KENYA POWER EAST AFRICAN POWER INDUSTRY CONVENTION 2012 PRESENTER PETER NJENGA CHIEF ENGINEER, CUSTOMER SERVICE, KENYA POWER EAST AFRICAN POWER INDUSTRY CONVENTION 2012 Introduction Power reliability Power Quality Harmonics Distortion Poor power factor Circuit

More information

Statcom Operation for Wind Power Generator with Improved Transient Stability

Statcom Operation for Wind Power Generator with Improved Transient Stability Advance in Electronic and Electric Engineering. ISSN 2231-1297, Volume 4, Number 3 (2014), pp. 259-264 Research India Publications http://www.ripublication.com/aeee.htm Statcom Operation for Wind Power

More information

Three Phase Capacitors KNK

Three Phase Capacitors KNK Three Phase Capacitors KNK Features Connection profile Φ 90 and 116 mm 2-16 mm 2, Φ 136 mm 2-25 mm 2 *Use of flexible conductors only with ferrules Capacitors equipped with discharge resistors Rated power

More information

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008 NB Power Customer Service and Distribution June 2008 Prepared by: Steven Wilcox Revised by: Steven Wilcox TABLE OF CONTENTS 1.0 Introduction 4 2.0 NB Power Policy on Independent Power Production 4 3.0

More information

Application Notes Getting concrete: PFC at SIW Co., Thailand

Application Notes Getting concrete: PFC at SIW Co., Thailand Power Factor Correction Getting concrete: mediumvoltage PFC successfully replaced by low-voltage PFC at Siam Industrial Wire Co., Thailand Siam Industrial Wire is a member of NatSteel Holdings and a wholly

More information

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Interconnection Feasibility Study Report GIP-084-FEAS-R2 Interconnection Feasibility Study Report GIP-084-FEAS-R2 System Interconnection Request #84 50 MW Wind Generating Facility Pictou County (L-7004) August 17, 2007 Control Centre Operations Nova Scotia Power

More information

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom Grid code Compliance and Renewable Energy Projects Mick Barlow, Business Development Director, S&C Electric, United Kingdom Why Grid Codes? Permit the development of and operation of an efficient and economical

More information

Michigan Renewable Energy Case Study

Michigan Renewable Energy Case Study Michigan Renewable Energy Case Study NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION TBILISI, GEORGIA JANUARY 27-31, 2014 GREG R. WHITE, COMMISSIONER

More information

Session 1: Implementing SDG 7 and Achieving Target 7.1 CAMBODIA CHHE LIDIN

Session 1: Implementing SDG 7 and Achieving Target 7.1 CAMBODIA CHHE LIDIN Session 1: Implementing SDG 7 and Achieving Target 7.1 CAMBODIA Seminar on Supporting Sustainable Development Goal 7, Target 7.1 By 2030 ensure universal access to affordable, reliable and modern energy

More information

kvah Billing - Frequently Asked Questions (FAQs)

kvah Billing - Frequently Asked Questions (FAQs) kvah Billing - Frequently Asked Questions (FAQs) 1. What is kvah billing? a. Electrical Energy has two components viz. Active Energy (kwh) and Reactive Energy (kvarh). Vector sum of these two components

More information

Louisville Gas and Electric Company

Louisville Gas and Electric Company P.S.C. Electric No. 11, Original Sheet No. 57 APPLICABLE In all territory served. AVAILABILITY OF SERVICE Available to any customer-generator who owns and operates a generating facility located on Customer

More information

ABB November 16, 2016 Slide 1

ABB November 16, 2016 Slide 1 Xuemei Wang, Power Quality Center, Xi an ABB Capacitor Company Ltd, November, 2016 ABB Power World 2016 Power Quality Solution in Distribution Net Work ABB November 16, 2016 Slide 1 Power Quality Basic

More information

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code: Generating Facility Level 2 or 3 Interconnection Review (For Generating Facilities with Electric Nameplate Capacities no Larger than 20 MW) Instructions An Interconnection Customer who requests a Utah

More information

Power Quality Improvement Using Statcom in Ieee 30 Bus System

Power Quality Improvement Using Statcom in Ieee 30 Bus System Advance in Electronic and Electric Engineering. ISSN 2231-1297, Volume 3, Number 6 (2013), pp. 727-732 Research India Publications http://www.ripublication.com/aeee.htm Power Quality Improvement Using

More information

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program. Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative

More information

Electrical Equipment and Safety: Operation, Control, Maintenance and Troubleshooting

Electrical Equipment and Safety: Operation, Control, Maintenance and Troubleshooting Electrical Equipment and Safety: Operation, Control, Maintenance and Troubleshooting Page 1 of 6 Why Attend This course covers the theoretical and practical operation of common electrical equipment and

More information

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less) Interconnection Customer Contact Information Name Alternative Contact Information (if different

More information

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES

D.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES 220 CMR 18.00: NET METERING Section 18.01: Purpose and Scope 18.02: Definitions 18.03: Net Metering Services 18.04: Calculation of Net Metering Credits 18.05: Allocation of Net Metering Credits 18.06:

More information

P UBLIC S ERVICE C OMMISSION

P UBLIC S ERVICE C OMMISSION COMMISSIONERS W. KEVIN HUGHES CHAIRMAN STATE OF MARYLAND HAROLD D. WILLIAMS ANNE E. HOSKINS JEANNETTE M. MILLS MICHAEL T. RICHARD P UBLIC S ERVICE C OMMISSION IN THE MATTER OF THE EXPLORATION INTO THE

More information

UTTARAKHAND POWER CORPORATION LIMITED

UTTARAKHAND POWER CORPORATION LIMITED UTTARAKHAND POWER CORPORATION LIMITED PUBLIC-NOTICE In terms of the provisions of section 45 of the Electricity Act, 2003, the consumers and the general public are hereby informed of the tariff and charges

More information

Paper ID: EE19 SIMULATION OF REAL AND REACTIVE POWER FLOW ASSESSMENT WITH FACTS CONNECTED TO A SINGLE TRANSMISSION LINE

Paper ID: EE19 SIMULATION OF REAL AND REACTIVE POWER FLOW ASSESSMENT WITH FACTS CONNECTED TO A SINGLE TRANSMISSION LINE SIMULATION OF REAL AND REACTIVE POWER FLOW ASSESSMENT WITH FACTS CONNECTED TO A SINGLE TRANSMISSION LINE Prof. Mrs. Shrunkhala G. Khadilkar Department of Electrical Engineering Gokhale Education Society.

More information

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Presented By: Bob Uluski Electric Power Research Institute. July, 2011 SMART DISTRIBUTION APPLICATIONS &THEIR INTEGRATION IN A SMART GRID ENVIRONMENT Presented By: Bob Uluski Electric Power Research Institute July, 2011 Key Smart Distribution Applications What are the major

More information

Net Metering & Compensation Seminar

Net Metering & Compensation Seminar Net Metering & Compensation Seminar November 2, 2017 Eversource Energy Hadley, MA Changes Are Here Market Net Metering Credit was introduced: 60% Market equal to 60% of distribution, transition, transmission

More information

Working Principle of Power Saver as per Manufacture:

Working Principle of Power Saver as per Manufacture: Analysis the Truth behind Household Power Savers Introduction: A House hold power saving devices has recently received a lot of attention from both consumers and manufacturers. It is generally used in

More information

National Conference on Latest Trends in Design & Testing of Transmission Line Components

National Conference on Latest Trends in Design & Testing of Transmission Line Components Book-Post National Conference on Latest Trends in Design & Testing of Transmission Line Components 22-23 November 2010 To, Mr. M. Selvaraj Engineering Officer / Co-ordinator Mechanical Engineering Division

More information

Tariff Design Issues: Approaches for Recovering Grid and System Costs

Tariff Design Issues: Approaches for Recovering Grid and System Costs Tariff Design Issues: Approaches for Recovering Grid and System Costs DG Energy - Workshop on Renewable Energy Self-Consumption Andreas Jahn Senior Associate 27 th March 2015 The Regulatory Assistance

More information

Technology Innovation Leadership TRAINING CALENDAR

Technology Innovation Leadership TRAINING CALENDAR Technology Innovation Leadership TRAINING CALENDAR 2017-18 Courses Offered 2017-2018 Sr. No. Category Program Title Objective / Contents Period Participants Location Faculty 1 Common Module for all products

More information

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014 Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting December 18, 2014 Agenda 1. Introductions 2. TCPC Policies 3. BHCE Planning Department Update 4. 2014 LTP Study Results 5. Stakeholder

More information

NYCA LOLE Violations (Methods D and E )

NYCA LOLE Violations (Methods D and E ) Proposals for Cost Allocation of Regulated Reliability Solutions Associated with NYCA LOLE Violations (Methods D and E ) Presented by Jerry Ancona National Grid For Discussion by NYISO Electric System

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Journal of American Science 2015;11(11)   Integration of wind Power Plant on Electrical grid based on PSS/E Integration of wind Power Plant on Electrical grid based on PSS/E S. Othman ; H. M. Mahmud 2 S. A. Kotb 3 and S. Sallam 2 Faculty of Engineering, Al-Azhar University, Cairo, Egypt. 2 Egyptian Electricity

More information

SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES

SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES SIEMENS POWER SYSTEM SIMULATION FOR ENGINEERS (PSS/E) LAB1 INTRODUCTION TO SAVE CASE (*.sav) FILES Power Systems Simulations Colorado State University The purpose of ECE Power labs is to introduce students

More information

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-226-FEAS-R3 Interconnection Feasibility Study Report GIP-226-FEAS-R3 System Interconnection Request #226 70 MW Wind Generating Facility Kings County (L-6013) 2010 07 21 Control Centre Operations Nova Scotia Power

More information

A Review on Reactive Power Compensation Technologies

A Review on Reactive Power Compensation Technologies IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 11, 2017 ISSN (online): 2321-0613 A Review on Reactive Power Compensation Technologies Minal Dilip Sathe 1 Gopal Chaudhari

More information

Performance Analysis of 3-Ø Self-Excited Induction Generator with Rectifier Load

Performance Analysis of 3-Ø Self-Excited Induction Generator with Rectifier Load Performance Analysis of 3-Ø Self-Excited Induction Generator with Rectifier Load,,, ABSTRACT- In this paper the steady-state analysis of self excited induction generator is presented and a method to calculate

More information

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian Shunt Capacitor Bank Protection in UHV Pilot Project Qing Tian 2012-5 INTRODUCTION State Grid Corp. of China, the largest electric power provider in the country, has first build a 1000 kv transmission

More information

DYNAMIC BEHAVIOUR OF SINGLE-PHASE INDUCTION GENERATORS DURING DISCONNECTION AND RECONNECTION TO THE GRID

DYNAMIC BEHAVIOUR OF SINGLE-PHASE INDUCTION GENERATORS DURING DISCONNECTION AND RECONNECTION TO THE GRID DYNAMIC BEHAVIOUR OF SINGLE-PHASE INDUCTION GENERATORS DURING DISCONNECTION AND RECONNECTION TO THE GRID J.Ramachandran 1 G.A. Putrus 2 1 Faculty of Engineering and Computing, Coventry University, UK j.ramachandran@coventry.ac.uk

More information

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid India need regulations for energy storage to implement grid ancillary services

More information

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0 ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES 2018-04-24 - Revision 0 EUB Decision 2007-071 Board Direction 52 For questions or comments regarding

More information