1 Grid Energy Storage: Policies John Martin, P. Eng. Senior Tariff and Special Projects Advisor Alberta Electric System Operator (AESO) IEEE Northern Canada Section PES/IAS Chapter Seminar, 21 Nov 2017, Edmonton, Alberta
2 Topics Electric industry framework Existing policies applicable to energy storage Current activities to revise existing policies and develop new policies Please ask questions during slides! Public 2
3 Alberta s electricity regulations and policies do not specifically address energy storage Public 3
4 You re wondering where existing policies are sufficient and where more clarity is needed Public 4
5 The existing electric industry framework does provide some guidance Public 5
6 The existing framework is evolving to more directly address energy storage Public 6
7 Opportunities exist for you to participate in changes to address energy storage Public 7
8 Energy storage doesn t clearly fit within today s electric industry framework Public 8
9 The existing framework reflects a traditional electric system structure Public 9
10 In Alberta, the current electric industry structure was created in the late 1990s 1996 Wholesale competition Legislated hedges and unit obligation prices Transmission Administrator 2001 Retail competition Auction of power purchase arrangements 2004 Independent system operator Public 10
11 Today s structure reflects traditional electric industry functions Generation Transmission Distribution Retail $2.6 billion $2.1 billion $1.5 billion $0.4 billion Competitive Market Cost-of-Service Regulation Performance-Based Regulation Competitive Market Public Costs estimated for
12 A set of interrelated acts and regulations establish the industry structure Alberta Utilities Commission Act Fair, Efficient and Open Competition Regulation Hydro and Electric Energy Act Transmission Regulation Micro-Generation Regulation Electric Utilities Act Public 12
13 The two-directional flows associated with energy storage do not align with the one-directional flows underlying the electric industry structure Public 13
14 In a traditional electric industry structure, electricity flows from generators to loads Direct Connected Consumers Generators Transmission Facility Owners Distribution System Owners Distribution Connected Consumers Public 14
15 Money flows in the opposite direction, from loads to generators AESO Retailers Direct Connected Consumers Generators Transmission Facility Owners Distribution System Owners Distribution Connected Consumers Public 15
16 Energy storage doesn t clearly fit this onedirectional structure Public 16
17 Energy storage must comply with existing requirements even if applicability is unclear Public 17
18 Legislation sets general requirements, although not specifically for energy storage Hydro and Electric Energy Act requires approval of the Commission to construct and operate a power plant Battery storage facility was found to be a power plant in Commission Decision , Installation of a Battery System at ENMAX Place Electric Utilities Act establishes the AESO as the sole provider of system access service on the transmission system to exchange electric energy and ancillary services Public 18
19 Alberta Utilities Commission Rule 007 sets out requirements for facility applications AUC Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Public 19
20 AESO connection process sets out requirements for system access service Market participants must identify the requirements of their projects and assist the AESO in placing the projects into an appropriate project category Market participants must apply to the AESO to be registered as a pool participant for the provision of energy or ancillary services or for the purchase of energy Public 20
21 Limitations of policies are being addressed and new policies are being developed Public 21
22 Legislation can provide some policy guidance Public 22
23 A market participant is generally able to act freely on owned property Requirements for construction and operation of a power plant do not apply to a person generating or proposing to generate electric energy solely for the person s own use, unless the Commission otherwise directs. Hydro and Electric Energy Act, section 13(1) The Commission may designate the whole or any part of an electric system as an industrial system. Hydro and Electric Energy Act, section 4(1) Public 23
24 Regulated functions must be separated from competitive functions There would appear to be no barriers to deployment of energy storage facilities as a non-regulated generation asset that could provide energy and ancillary services. Legislative or policy changes may be required to clarify whether energy storage technologies would be regulated as transmission or distribution assets or be left unregulated and deployed in the competitive generation market. Alberta Smart Grid Inquiry, 31 Jan 2011, page 15 Public 24
25 Costs must be attributed in accordance with legislation and rate design principles The rates must reflect the prudent costs that are reasonably attributable to each class of system access service. Electric Utilities Act, section 30(2) Costs of the transmission system must be wholly charged to loads and exporters Transmission Regulation, section 47(a)(i) Rate design must satisfy principles of economic efficiency, equity, stability, and practicality Commission Decision , section 5 Public 25
26 ISO rules set out requirements for participation of energy storage in competitive energy and ancillary services markets Public 26
27 Technical and operating requirements apply to facilities connected to the transmission system Public 27
28 Market rules govern participation in the energy and ancillary services markets The AESO has a duty to facilitate the operation of markets for electric energy in a manner that is fair and open and that gives all market participants wishing to participate in those markets and to exchange electric energy a reasonable opportunity to do so. Electric Utilities Act, section 17(b) Rule amendments to facilitate the integration of energy storage facilities are in final stage of consultation Public 28
29 Rules governing participation in competitive markets continue to be reviewed for technology neutrality Defined term added in 2016 energy storage facility means a facility with technologies capable of storing and releasing electric energy References to generating unit and load in operating reserve rules are being replaced with technology-neutral definitions for resources Public 29
30 ISO tariff governs a connection to the transmission system for the exchange of energy and ancillary services Public 30
31 From an operating perspective, different facilities can have a similar Impact on the transmission system Generator Load (5) (10) Generator and Load Storage (5) (5) Public 31
32 Modelling suggests energy storage systems can withdraw from the transmission system to charge at any time 30% Percentage of Hours Discharging (Charging) at 95% of Rated Capacity 20% 10% 0% (10%) (20%) (30%) (40%) (50%) Hour of Day Frequency of Discharge at 95% of Rated Capacity Frequency of Charge at 95% of Rated Capacity Public 32
33 AESO comparability study found similarities between storage and load-generation sites Net Supply to (Withdrawal From) Transmission System (MW) (50) (100) Energy Storage (left axis) (150) Load-Generation Site (right axis) Day 0 Public 33
34 Industry participants can help with existing policy revision and new policy development Public 34
35 Participate in AESO tariff development Public 35
36 ISO tariff proceeding provides opportunity to examine rate treatment [C]ost causation supports the application of Rate DTS [Demand Transmission Service] to energy storage facilities, in hours in which the energy storage facilities are withdrawing electricity from the transmission system (charging). In hours in which the energy storage facilities are supplying electricity to the transmission system, Rate STS [Supply Transmission Service] would apply. Public 36
37 Many of the components of Rate DTS can be avoided or reduced through managed operation of an energy storage facility Average 20 MW Load-Only 100% Avoid System Peak 37% Own Your Substation 22% Contract for Both DTS and STS 21% Hold Charge to 10 MW 12% Connection Charge Ancillary Services Charges $0 $50,000 $100,000 $150,000 $200,000 $250,000 $300,000 $350,000 Monthly Rate DTS Charges Public 37
38 Energy storage projects in the connection process accelerate identification of issues Identify project Connection study scope Connection proposal NID and facility application Application filings and Commission approvals Construct and prepare to energize Energize, commission and close Public 38
39 Participate in AESO rule development Public 39
40 AESO is in final stage of amending operating reserve rules Section 205.3, Restatements for Operating Reserve Section 205.4, Regulating Reserve Technical Requirements and Performance Standards Section 205.5, Spinning Reserve Technical Requirements and Performance Standards Section 205.6, Supplemental Reserve Technical Requirements and Performance Standards Public 40
41 AESO has formal consultation process for rules and standard development AESO creates new ISO rules or amends existing ISO rules as needed To facilitate the safe, reliable and economic operation of the Alberta Interconnected Electric System To promote a fair, efficient and openly competitive wholesale market for electricity in Alberta Rules consultation process will be inclusive, transparent, fair and efficient and will be understood and accepted by all parties Public 41
42 Opportunities also exist to engage in consultation on capacity market development and other market initiatives Public 42
43 Continue to explore and advocate for integration of energy storage in the Alberta context Public 43
44 Energy storage may deliver stacked value but must be within legislated boundaries Market Benefit System Benefit Provider Benefit Energy Market Price Ancillary Services Market Price Renewable Generation Integration Generation Infrastructure Wires Infrastructure Adapted from State of Charge: Massachusetts Energy Storage Initiative Study (Sep 2016) Capacity Market Price Cost of Storage Revenue to Storage Provider Public 44
45 Declining costs suggest storage will become more economically feasible Decline From Previous Year, % 0% -5% -10% -15% -20% -25% -30% -35% Adapted from Large-Scale Energy Storage Systems report by GTM Research (Oct 2017) Storage Battery Balance of Storage System Public 45
46 Some studies suggest optimal storage capacity is 10% of system load 10% 1,200 MW in Alberta Hossein Safaeia and David W. Keith, How much bulk energy storage is needed to decarbonize electricity?, Energy & Environmental Science (Sep 2015) Mark Z. Jacobsen, et al., Low-cost solution to the grid reliability problem with 100% penetration of intermittent wind, water, and solar for all purposes, Proceedings of the National Academy of Sciences (Dec 2015) Public 46
47 The existing electric industry framework does provide some guidance Public 47
48 The existing framework is evolving to more directly address energy storage Public 48
49 Opportunities exist for you to participate in changes to address energy storage Public 49
50 Thank you John Martin
Net Metering in Illinois. Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014
Net Metering in Illinois Eric P. Schlaf Senior Economic Analyst Illinois Commerce Commission January 31, 2014 Topics What is Net Metering Benefits of Net Metering Net Metering in US Net Metering in Illinois
More informationConsumer Guidelines for Electric Power Generator Installation and Interconnection
Consumer Guidelines for Electric Power Generator Installation and Interconnection Habersham EMC seeks to provide its members and patrons with the best electric service possible, and at the lowest cost
More informationParticipation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market
Beacon Power Corporation Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market Prepared for: New York Business Issues Committee May 21, 2008 Safe Harbor
More informationENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE
ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of January 1, 2018 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential
More informationD.P.U A Appendix B 220 CMR: DEPARTMENT OF PUBLIC UTILITIES
220 CMR 18.00: NET METERING Section 18.01: Purpose and Scope 18.02: Definitions 18.03: Net Metering Services 18.04: Calculation of Net Metering Credits 18.05: Allocation of Net Metering Credits 18.06:
More informationENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE
ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE RATES IN EFFECT AS OF APRIL 1, 2018 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential
More informationFITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM
Sheet 1 FITCHBURG GAS AND ELECTRIC LIGHT COMPANY SCHEDULE NM Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services
More informationENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE
ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of September 1, 2015 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff
More informationDesigning Distributed Generation Tariffs Well
Designing Distributed Generation Tariffs Well RAP Webinar May 29, 2014 Presented by Carl Linvill, Jim Lazar, & John Shenot The Regulatory Assistance Project 50 State Street, Suite 3 Montpelier, VT 05602
More informationENERGY STORAGE IN TEXAS. Robert J. King Good Company Associates
ENERGY STORAGE IN TEXAS Robert J. King Good Company Associates Austin-based firm specializing in clean energy, Services include: Policy & Regulatory Business Development Coalition Building Analysis & Technical
More informationDecision on Merced Irrigation District Transition Agreement
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson, Vice President Policy & Client Services Date: March 13, 2013 Re: Decision on Merced Irrigation
More informationEITF Issue 15-A, Application of the Normal Purchases and Normal Sales Scope Exception to Certain Electricity Contracts within Nodal Energy Markets
EITF Issue 15-A, Application of the Normal Purchases and Normal Sales Scope Exception to Certain Electricity Contracts within Nodal Energy Markets Education Session January 22, 2014 1 Overview and agenda
More informationEconomics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017
Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017 Presentation Outline Understanding LPEA s expenses and what drives them Economics of net metering
More informationNEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)
NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. (0) 0 0 IN THE MATTER OF the Electrical Power Control Act,, SNL, Chapter E-. (the EPCA ) and the Public
More informationReview of Reliability Must-Run and Capacity Procurement Mechanism BBB Issue Paper and Straw Proposal for Phase 1 Items
Review of Reliability Must-Run and Capacity Procurement Mechanism BBB Issue Paper and Straw Proposal for Phase 1 Items Stakeholder Meeting January 30, 2018 Keith Johnson Infrastructure and Regulatory Policy
More information(2) Scope. 220 CMR applies to all Distribution Companies subject to the jurisdiction of the Department.
D.P.U. 11-10-A 220 CMR 18.00: NET METERING Section 18.01: Purpose and Scope 18.02: Definitions 18.03: Net Metering Services 18.04: Calculation of Net Metering Credits 18.05: Allocation of Net Metering
More informationOVERVIEW OF UNIFORM TRANSMISSION RATES
Exhibit H1 Tab 1 Schedule 1 Page 1 of 2 1 OVERVIEW OF UNIFORM TRANSMISSION RATES 2 3 4 5 6 7 8 9 Transmission rates in Ontario have been established on a uniform basis for all transmitters in Ontario since
More informationMicrogrids A Regulatory Perspective
Microgrids A Regulatory Perspective Overview of the Regulatory Implications of Microgrid Implementation in California J. David Erickson 1 Agrion Microgrid Task Force April 3, 2013 Disclaimer: This is not
More informationENERGY STRATEGY FOR YUKON. Independent Power Production Policy
ENERGY STRATEGY FOR YUKON Independent Power Production Policy May 20, 2014 Page 2 of 11 BACKGROUND The Government of Yukon released the Energy Strategy for Yukon in January 2009. The strategy sets out
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More informationNet Metering Policy Framework. July 2015
Net Metering Policy Framework July 2015 Table of Contents 1.0 BACKGROUND... 2 2.0 POLICY OBJECTIVE... 2 3.1 Eligibility... 3 3.1.1 Renewable Generation... 3 3.1.2 Customer Class... 3 3.1.3 Size of Generation...
More informationOverview of ISO New England and the New England Wholesale Power Markets
Overview of ISO New England and the New England Wholesale Power Markets Boston Chapter of IEEE PES Technical Meeting June 15, 2010 Stephen J. Rourke Vice President, System Planning About ISO New England
More informationBC Hydro writes in compliance with Exhibit A-4 to provide its Final Submission in respect of the Application (Exhibit B-1).
Ken Duke Solicitor & Counsel Phone: 604-623-3623 Fax: 604-623-3606 bchydroregulatorygroup@bchydro.com April 30, 2014 Sixth Floor 900 Howe Street Vancouver, BC V6Z 2N3 Dear Ms. Hamilton: RE: (BCUC) British
More informationRATE ORDER 2015 UNIFORM ELECTRICITY TRANSMISSION RATES January 08, 2015
Ontario Energy Board Commission de l énergie de l Ontario IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B); AND IN THE MATTER OF a motion by the Ontario Energy Board to
More informationPUBLIC Law, Chapter 539 LD 1535, item 1, 124th Maine State Legislature An Act To Create a Smart Grid Policy in the State
PLEASE NOTE: Legislative Information cannot perform research, provide legal advice, or interpret Maine law. For legal assistance, please contact a qualified attorney. Emergency preamble. Whereas, acts
More informationFITCHBURG GAS AND ELECTRIC LIGHT COMPANY NET METERING SCHEDULE NM
Sheet 1 FITCHBURG GAS AND ELECTRIC LIGHT COMPANY SCHEDULE NM Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests net metering services
More informationTHE PUBLIC SERVICE COMMISSION OF MARYLAND
THE PUBLIC SERVICE COMMISSION OF MARYLAND Report on the Status of Net Energy Metering In the State of Maryland Prepared for the General Assembly of Maryland Pursuant to 7-306(i) of the Public Utilities
More informationDistributed Solar Policy Case Study: NEVADA
Distributed Solar Policy Case Study: NEVADA National Conference of State Legislatures National Association of State Energy Officials September 28, 2017 Angela Dykema Nevada Governor s Office of Energy
More informationReforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017
Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017 1 CPUC Staff Rate Design Proposals Restructure the High-Voltage TAC
More informationCity of Lethbridge ELECTRIC UTILITY. Electric Distribution Tariff Rate Schedule
City of Lethbridge ELECTRIC UTILITY Electric Distribution Tariff Rate Schedule City of Lethbridge Bylaw 5789 Effective: January 1, 2013 City of Lethbridge Infrastructure Services Electric Utility Document
More informationThe Role of DSO as Facilitator of the Electricity Markets in Macedonia. Key aspects and considerations
The Role of DSO as Facilitator of the Electricity Markets in Macedonia Key aspects and considerations 30 th of May, 2017 Renewable Energy Production in Macedonia (1/5) Supportive Measures Installed capacity
More informationThe Commonwealth of Massachusetts
The Commonwealth of Massachusetts DEPARTMENT OF PUBLIC UTILITIES D.P.U. 12-81-A January 18, 2013 Investigation by the Department of Public Utilities on its own Motion Commencing a Rulemaking pursuant to
More informationRhode Island Division of Public Utilities and Carriers & Office of Energy Resources. Power Sector Transformation
1 Rhode Island Division of Public Utilities and Carriers & Office of Energy Resources Power Sector Transformation Notice of Inquiry into the Electric Utility Business Model and Request for Stakeholder
More informationENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE
ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE Rates in effect as of July 1, 2011 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100 Distribution Tariff Residential
More informationENERGY STRATEGY FOR YUKON. Net Metering Policy DRAFT FOR CONSULTATION
ENERGY STRATEGY FOR YUKON Net Metering Policy DRAFT FOR CONSULTATION February 2011 Page 1 of 4 BACKGROUND The Yukon government released the Energy Strategy for Yukon in January 2009. The Energy Strategy
More informationEric Johnson, Director, External Affairs, ISO New England
To: From: NECPUC and NESCOE Eric Johnson, Director, External Affairs, ISO New England Date: January 22, 2016 Subject: How Energy Storage Can Participate in New England s Wholesale Electricity Markets Interest
More informationREGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST
REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST MEGAN O REILLY COALITION FOR CLEAN AFFORDABLE ENERGY EPE IRP STAKEHOLDER
More informationStatewide Joint IOU Study of Permanent Load Shifting Workshop #2: Expanding the Availability of Permanent Load Shifting in California
Statewide Joint IOU Study of Permanent Load Shifting Workshop #2: Expanding the Availability of Permanent Load Shifting in California Wednesday, November 10, 2010 Snuller Price, Eric Cutter, Priya Sreedharan,
More informationEnergy Storage in the Smart Grid
Energy Storage in the Smart Grid Haresh Kamath Program Manager, Energy Storage and Distributed Generation NEDO Forum 2015 13 Feb 2015 Together Shaping the Future of Electricity EPRI s Mission Advancing
More information4-6 October 2016 The NEC, Birmingham, UK. cleanenergylive.co.uk
4-6 October 2016 The NEC, Birmingham, UK cleanenergylive.co.uk #celive #seuk @CleanEnergyLive cleanenergylive.co.uk #celive #seuk @CleanEnergyLive UK Energy storage policy A defining issue Clean Energy
More informationGood Practices for Grid Connection: European Wind Industry perspective. Iván Pineda EWEA Research Officer Grids and Internal Electricity Market
Good Practices for Grid Connection: European Wind Industry perspective Iván Pineda EWEA Research Officer Grids and Internal Electricity Market Sofia, 20 November 2012 Presentation outline Guiding principles
More informationUniversity of Alberta
Decision 2012-355 Electric Distribution System December 21, 2012 The Alberta Utilities Commission Decision 2012-355: Electric Distribution System Application No. 1608052 Proceeding ID No. 1668 December
More information2lr1344 CF 2lr1396. Drafted by: Heide Typed by: Rita Stored 02/02/12 Proofread by Checked by By: Senator Pinsky A BILL ENTITLED
C Bill No.: Requested: Committee: CF lr Drafted by: Heide Typed by: Rita Stored 0/0/ Proofread by Checked by By: Senator Pinsky A BILL ENTITLED AN ACT concerning Electricity Community Energy Generating
More informationNational Agency for Energy Regulation
National Agency for Energy Regulation Legislation in Energy Sector Institutional Capacity of Energy Sector Wholesale and Retail Market Development Third Party Access to Network Viability and Security of
More informationGuideline on Energy Storage
Purpose Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs DEPARTMENT OF ENERGY RESOURCES SOLAR MASSACHUSETTS RENEWABLE TARGET PROGRAM (225 CMR 20.00) GUIDELINE Guideline
More informationAll-Energy 2016, Glasgow. Contributing funding partners:
Can storage help reduce the cost of a future UK electricity system? Results from a project on opportunities from the deployment of energy storage, contributed to by government, industry & academic partners
More informationIncentives and Opportunities Signalled by Transmission Charges in Scotland. Iain Wright 03 September 2018
Incentives and Opportunities Signalled by Transmission Charges in Scotland Iain Wright 03 September 2018 COMMON WEAL is a non-profit think-anddo tank based in Glasgow which campaigns for greater social
More informationOverview of S.L Competitive Energy Solutions for North Carolina
Overview of S.L. 2017-192 Competitive Energy Solutions for North Carolina JENNIFER MCGINNIS CHRIS SAUNDERS STAFF AT TORNEYS, LEGISLATIVE ANALYSIS DIVISION 1 Overview Product of extensive stakeholder process
More informationGlobal Trends in the Political Economy of Smart Grids
Global Trends in the Political Economy of Smart Grids 23rth of September 2016 Responding to Crises UN Wider Cherrelle Eid, Rudi Hakvoort & Martin de Jong C.Eid@tudelft.nl Delft University of Technology,
More informationKANSAS CITY POWER AND LIGHT COMPANY P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No.
P.S.C. MO. No. 7 Fourth Revised Sheet No. 39 Canceling P.S.C. MO. No. 7 Third Revised Sheet No. 39 PURPOSE: The purpose of the Solar Subscription Pilot Rider (Program) is to provide a limited number of
More informationPage 1 of 5. 1 The Code Administrator will provide the paper reference following submission to National Grid.
Grid Code Review Panel Issue Assessment Proforma Operational Metering for Embedded Small Power Stations PP 11/35 1 A Panel Paper by John Lucas (ELEXON) & Steve Curtis (NGET) Summary Currently it is unclear
More informationUnderstanding Impacts of Distributed Solar Generation on Cost Recovery and Rates IAMU Annual Energy Conference Preconference Seminar
Understanding Impacts of Distributed Solar Generation IAMU Annual Energy Conference Preconference Seminar David A. Berg, PE Principal November 3, 2015 Your Presenter David Berg, PE Principal Dave Berg
More informationa) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load
Memorandum To: Municipal Light Advisory Board; Municipal Light Board; file From: Belmont Light Staff Date: June 19, 2014 Re: Solar PV Distributed Generation 1. Background & Summary Belmont Light supports
More informationEffects of Smart Grid Technology on the Bulk Power System
Effects of Smart Grid Technology on the Bulk Power System Rana Mukerji Senior Vice President Market Structures New York Independent System Operator Union College 2013 Environmental Science, Policy & Engineering
More informationSubmission to the IESO re: RDGI Fund Virtual Net Metering Investigation Topic
1. Introduction The Canadian Solar Industries Association (CanSIA) is a national trade association that represents the solar energy industry throughout Canada. CanSIA s vision is for solar energy to be
More informationENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE
Page 2 of 22 ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE RATES IN EFFECT AS OF APRIL 1, 2018 Page 2 of 22 Page 3 of 22 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description
More informationTHE GENERAL ASSEMBLY OF PENNSYLVANIA HOUSE BILL
PRINTER'S NO. THE GENERAL ASSEMBLY OF PENNSYLVANIA HOUSE BILL No. Session of 0 INTRODUCED BY QUINN, DONATUCCI, SCHLOSSBERG, D. MILLER, FREEMAN, STURLA, SCHWEYER, BARRAR AND SIMS, JANUARY, 0 REFERRED TO
More informationThe Role of Electricity Storage on the Grid each location requires different requirements
Functional Requirements for Energy on the Utility Grid EPRI Renewable Council Meeting Bill Steeley Senior Project Manager Dan Rastler Program Manager April 5-6, 2011 The Role of Electricity on the Grid
More informationPROMOTING THE UPTAKE OF ELECTRIC AND OTHER LOW EMISSION VEHICLES
Chair Cabinet Economic Growth and Infrastructure Committee Office of the Minister of Transport Office of the Minister of Energy and Resources PROMOTING THE UPTAKE OF ELECTRIC AND OTHER LOW EMISSION VEHICLES
More informationMichigan Renewable Energy Case Study
Michigan Renewable Energy Case Study NARUC ENERGY REGULATORY PARTNERSHIP WITH GEORGIAN NATIONAL ENERGY AND WATER SUPPLY REGULATORY COMMISSION TBILISI, GEORGIA JANUARY 27-31, 2014 GREG R. WHITE, COMMISSIONER
More informationNERSA CONSULTATION PAPER PROCESS. Moefi Moroeng Specialist: Wholesale Electricity Trading
NERSA CONSULTATION PAPER PROCESS Moefi Moroeng Specialist: Wholesale Electricity Trading 1 AGENDA Energy Regulator Overview Regulation of the Electricity Supply Industry Current Structure of the Electricity
More informationJEA Distributed Generation Policy Effective April 1, 2018
Summary This JEA Distributed Generation Policy is intended to facilitate generation from customer-owned renewable and non-renewable energy generation systems interconnecting to the JEA electric grid. The
More informationDemand Charges to Deal With Net Energy Metering: Key Considerations
Demand Charges to Deal With Net Energy Metering: Key Considerations Amparo Nieto Vice President Presented at EUCI Residential Demand Charges Symposium Calgary, Canada December 1, 2015 Key Rate Design Principles
More informationLegal Considerations Related to Distributed Energy Resources
Legal Considerations Related to Distributed Energy Resources Steve Pincus Associate General Counsel Steve Shparber Counsel Markets & Reliability Committee April 18, 2016 Overview of FERC Jurisdiction FERC
More informationSchedule SP SOLAR PURCHASE (Experimental)
I. APPLICABILITY & AVAILABILITY This Schedule is available in conjunction with the Company s Solar Purchase Program ( Program ) and is applicable only where the Customer elects to receive Electricity Supply
More informationWhat is the Future of Competitive Markets? Some Fundamental Preliminaries and View from Events in the PJM Market
What is the Future of Competitive Markets? Some Fundamental Preliminaries and View from Events in the PJM Market Paul M. Sotkiewicz, Ph.D President December 7, 2016 What are the ideal properties of competitive
More informationNet Energy Metering and Interconnections. Community Solar in the District of Columbia
Net Energy Metering and Interconnections Community Solar in the District of Columbia Presented by: Virginia Burginger August 4, 2016 1 Welcome Overview of Community Net Metering in the District of Columbia
More informationENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE
Page 1 of 19 ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE RATES IN EFFECT AS OF JANUARY 1, 2017 Page 2 of 19 EPC DISTRIBUTION TARIFF RATE SCHEDULE Rate Code Rate Description Page D100
More informationINTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY
INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY Table of Contents Chapter 1. Purpose and scope. Pg 3 Chapter 2. Application
More informationMASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY NET METERING PROVISION
Sheet 1 of 28 Applicability The following tariff provisions shall be applicable to a Host Customer, as defined herein, that requests Net Metering services from the Distribution Company, with the exception
More informationIllinois Solar Energy Association. Residential Rate Design Webinar August 25, 2016
Illinois Solar Energy Association Residential Rate Design Webinar August 25, 2016 Illinois Policy Update SB 1585: Exelon/ComEd Bill ISEA working w/ Clean Jobs Coalition to fix of Renewable Portfolio Standard
More informationTechnical Conference: Alternative Utility Cost Recovery Mechanisms
Technical Conference: Alternative Utility Cost Recovery Mechanisms Maryland Public Service Commission October 20, 2015 Janine Migden-Ostrander RAP Principal The Regulatory Assistance Project 50 State Street,
More informationNet Consumption (GWh)
GEORGIAN ENERGY MARKET Over the last 20 years Georgia s power market has evolved from a vertically integrated single buyer utility, to a competitive regional power market model. The Georgian wholesale
More informationThank you for your time and attention to this matter. Please feel free to contact me if you have any questions regarding the filing.
Mary L. Cottrell, Secretary March 27, 2009 Page 1 Stacey M. Donnelly Counsel September 23, 2009 Mark D. Marini, Secretary Department of Public Utilities One South Station Boston, MA 02110 Re: D.P.U. 09-03
More informationPlanning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014
Planning Distributed Generation for Transmission Savings 1 By Kenneth Sahm White and Stephanie Wang 2 March 19, 2014 The Clean Coalition recommends that state regulators and utilities account for potential
More informationThe difference of the wholesale electricity market and operational methods in Japan, the United States and Europe
The difference of the wholesale electricity market and operational methods in Japan, the United States and Europe Junichi OGASAWARA The Institute of Energy Economics, Japan Japanese Electricity Market
More informationEnergy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque
Energy Regulation : Australian Experience Engr.Khondkar Abdus Saleque 14/11/2014 Australian Energy Regulator Australia is a federal Country with Six Sates and two territories Victoria, NSW, Queensland,
More informationNational Seniors Association 18 October 2010 Jo Benvenuti David Stanford
National Seniors Association 18 October 2010 Jo Benvenuti David Stanford About CUAC The National Energy Market what it means Victorian Issues Price Bushfire Royal Commission Victorian Gov Climate Change
More informationGEODE Report: Flexibility in Tomorrow s Energy System DSOs approach
1 GEODE Report: Flexibility in Tomorrow s Energy System DSOs approach Report was prepared by Working Group Smart Grids of GEODE GEODE Spring Seminar, Brussels, 13th of May 2014 Hans Taus, Wiener Netze
More informationFacilitated Discussion on the Future of the Power Grid
Facilitated Discussion on the Future of the Power Grid EPRI Seminar: Integrated Grid Concept and Technology Development Tokyo Japan, August 20, 2015 Matt Wakefield, Director Information, Communication
More informationNational Perspective on Net Metering and Related Policies
National Perspective on Net Metering and Related Policies Distributed Generation Meeting Hosted by Minnesota Department of Commerce Division of Energy Resources Presented by Lisa Schwartz Oct. 11, 2012
More informationSolar Plus: A Holistic Approach to Distributed Solar PV Eric O'Shaughnessy, Kristen Ardani, Dylan Cutler, Robert Margolis
Solar Plus: A Holistic Approach to Distributed Solar PV Eric O'Shaughnessy, Kristen Ardani, Dylan Cutler, Robert Margolis NREL is a national laboratory of the U.S. Department of Energy, Office of Energy
More informationReactive Power Requirements and Financial Compensation. Addendum to Draft Final Proposal
Reactive Power Requirements and Financial Compensation July 21, 2016 Table of Contents 1. Introduction... 3 2. Changes to Proposal... 4 3. Plan for Stakeholder Engagement... 4 4.... 4 6. Next Steps...
More informationHOUSE BILL No Koch
Introduced Version HOUSE BILL No. 1320 DIGEST OF INTRODUCED BILL Citations Affected: IC 8-1-40; IC 36-7-5.3. Synopsis: Generation of electricity by distributed generation. Provides that the utility regulatory
More informationEconomics and Barriers to Solar Photovoltaic Applications in Barbados
Economics and Barriers to Solar Photovoltaic Applications in Barbados Roland R Clarke PhD Clarke Energy Associates www.clarkeenergy@aol.com clarkeenergy@aol.com Presented to Alternative Energy: Pathways
More informationCapacity Market Rules for Energy Storage Resources
Capacity Market Rules for Energy Storage Resources Zachary T Smith Manager, Capacity Market Design ICAPWG August 23 rd, 2018 Agenda Background Energy Storage Resource (ESR) overview Capacity Market Rules
More informationDecision Blaze Energy Ltd. Application for an Exemption under Section 24 of the Hydro and Electric Energy Act.
Decision 2014-108 Application for an Exemption under Section 24 of the Hydro and Electric Energy Act April 17, 2014 The Alberta Utilities Commission Decision 2014-108: Application for an Exemption under
More informationWhat, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center
What, Why, and Where? Brian Lips Senior Project Manager for Policy NC Clean Energy Technology Center bclips@ncsu.edu About the 50 States of Solar Quarterly publication detailing state and utility distributed
More informationDemand Response - An End-to-End Approach from Markets to Consumers
Demand Response - An End-to-End Approach from Markets to Consumers Rana Mukerji Senior Vice President Market Structures New York Independent System Operator EPRI PDU Sector Council Meeting Boston, MA September
More informationNet Metering and Solar Incentive Proposed Framework
Net Metering and Solar Incentive Proposed Framework STAKEHOLDER MEETING JUNE 11, 2014 June 12, 2014 1 Meeting Agenda June 11, 2014 2-3pm. Review framework. Today s Meeting is to EXPLAIN a compromise framework
More informationImplementing Net Metering to Meet Policy Objectives
Implementing Net Metering to Meet Policy Objectives EUEC 2015 February 16, 2015 Joseph Daniel & Dr. Tommy Vitolo, Synapse Energy Economics jdaniel@synapse energy.com Synapse Energy Economics Founded in
More informationA member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.
Electric Tariff _2nd Revised Sheet No. 72 Filed with Iowa Utilities Board Cancels _1st Sheet No. _72 Cooperative is a member of Central Iowa Power Cooperative (CIPCO), a generation and transmission cooperative
More informationNew Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities
New Ulm Public Utilities Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities INDEX Document Review and History... 2 Definitions... 3 Overview... 3 Application
More informationTopic Small Projects (< 100 kw) Large Projects (>100 kw)
New Hampshire Public Utilities Commission Docket No. DE 16-576 Development of New Alternative Net Metering Tariffs and/or Other Regulatory Mechanisms and Tariffs for Customer-Generators Joint Settlement
More informationAddressing ambiguity in how electricity industry legislation applies to secondary networks
In Confidence Office of the Minister of Energy and Resources Chair, Cabinet Business Committee Addressing ambiguity in how electricity industry legislation applies to secondary networks Proposal 1 This
More informationBC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014
T BC Hydro OATT - Balancing Area Transmission Service Workshop January 20, 2014 1 AGENDA Topic Time Speaker Welcome and Introduction 09:00 09:15 Gord Doyle Background 09:15 10:00 Martin Huang Enforcement
More informationNext Generation Solar Incentive Program
COMMONWEALTH OF MASSACHUSETTS Charles D. Baker, Governor Karyn E. Polito, Lt. Governor Matthew A. Beaton, Secretary Judith Judson, Commissioner National RPS Summit Washington, D.C. December 1, 2016 Next
More informationThe Role of the ISO/RTO in Today s Electric Grid
The Role of the ISO/RTO in Today s Electric Grid Robert B. Burke Principal Analyst #GridWeek ISO New England Inc. Purpose Describe the role of the ISO in today s grid. Where are the ISO/RTOs Deregulation
More informationInformation Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program
Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program As part of our commitment to support renewable energy, Kissimmee Utility Authority
More information