1 NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL SYSTEMS AND CONSTRUCTION NQF LEVEL 3 NOVEMBER 2009 ( ) 24 November (X-Paper) 09:00 12:00 This question paper consists of 6 pages.

2 ( ) -2- NC720(E)(N24)V TIME: 3 HOURS MARKS: 100 INSTRUCTIONS AND INFORMATION Answer ALL the questions. Read ALL the questions carefully. Number the answers according to the numbering system used in this question paper. Write neatly and legibly.

3 ( ) -3- NC720(E)(N24)V QUESTION 1: WIRE AND COMMISSION A SINGLE-PHASE DOMESTIC INSTALLA- TION 1.1 The SANS (10142) Code of Practice has regulations about the installation and wiring of components. What is stated with regard to the following: Colours to be used to identify the live, neutral and earth conductors in a domestic installation (3) You must be able to reach any point of the distribution board for switching purposes. What is the minimum and maximum height from floor level that any point of control in the distribution board can be installed? The minimum current rating of domestic socket outlets The minimum prospective short-circuit rating for switchgear in single-phase domestic installations Name the conductors that are disconnected by the isolating switch (isolator) of a stove or a geyser (2) Is the isolating switch designed to trip on over-current or earth fault? What do you understand by the term point of control? 1.2 The distribution board of a domestic installation, having the following circuits, has to be wired: 1 x 20 A plug circuit 1 x 10 A light circuit 1 x 35 A stove circuit 1 x 20 A geyser circuit Draw a neat, fully labelled wiring diagram of the above-mentioned distribution board and indicate ALL the components and wiring. (10) QUESTION 2: TEST AND INSPECT A SINGLE-PHASE DOMESTIC INSTALLATION 2.1 Name FOUR compulsory electrical tests to be carried out on a domestic installation before a Certificate of Compliance can be issued. (4) 2.2 With the aid of a fully labelled sketch, explain how you would conduct an insulation resistance test between the live and neutral conductors. Indicate the acceptable readings. (10)

4 ( ) -4- NC720(E)(N24)V 2.3 The following readings were obtained after conducting tests on a domestic installation. Analyse the readings and state whether they are ACCEPTABLE or UNACCEPTABLE. Write only the answers in the ANSWER BOOK next to the question numbers ( ) TEST READING ACCEPTABLE/ UNACCEPTABLE Earth and bonding continuity < 0,2 ohms test Insulation resistance test (live to earth conductors ) 10 ohms Polarity test (switch in closed position) 0 ohm Insulation resistance test (between neutral and live conductors) 1 mega-ohm Earth-leakage test (domestic) 100 ma Voltage test at distribution board (no-load) 150 V

5 ( ) -5- NC720(E)(N24)V QUESTION 3: FAULT FINDING ON ALTERNATING-CURRENT (AC) AND DIRECT- CURRENT (DC) SYSTEMS 3.1 The following faults were reported when a stove was tested. Choose a possible cause from COLUMN B that matches a fault in COLUMN A. Write only the letter (A F) next to the question number ( ) in the ANSWER BOOK. FAULT POSSIBLE CAUSE Element works on high only Element trips earth-leakage relay when switched on A B element conductor broken (coil) faulty stove switch V at terminals of element but element does not heat up No voltage at stove switch, but voltage up to fuse box supply Oven temperature cannot be regulated C D E short-circuit between earth and element conductors (coils) faulty thermostat or oven switch blown fuse 3,1,6 No voltage on load side of stove circuit breaker but 220 V on supply side F faulty circuit breaker 3.2 Various instruments may be used when testing circuits Name the measuring instrument used to measure ampère and explain how this instrument is connected in a circuit. (2) Name the measuring instrument used to measure volt and explain how this instrument is connected in a circuit. (2) 3.3 A single-phase transformer is not working properly. Briefly explain the voltage and continuity tests that can be done on this transformer. (4) 3.4 A single-phase AC motor (with capacitor) is not working properly. List the tests you would perform on the motor windings and capacitor and the testing or measuring instruments you would use. (6)

6 ( ) -6- NC720(E)(N24)V QUESTION 4: LOW-VOLTAGE NETWORKS 4.1 What is the maximum supply voltage for a low-voltage network? 4.2 Briefly describe a TN-S earthing system. (3) 4.3 Name THREE types of earthing systems used in low-voltage installations. (3) 4.4 You are required to test whether a network's earthing system is functioning properly. Name TWO tests that can be done before switching on the supply. (2) 4.5 Name FOUR steps that you would follow when you electrically disconnect a circuit from the network (isolation of apparatus). (4) 4.6 A redspot fuse has to be replaced. Explain how you would isolate, remove and activate the new fuse. (7) QUESTION 5: UNDERSTAND AND MAINTAIN LIGHTING SYSTEMS 5.1 All fluorescent lamps need a device to control the flow of current through them. Name this device. 5.2 Name FOUR different types of lamps and where they can be used. (8) 5.3 A fluorescent lamp has broken in your classroom. State the safety precautions you would take when disposing of the lamp. (5) 5.4 When a ripple relay is activated by the supplier of electricity, the supply to the geyser is interrupted. How does the supplier activate the ripple relay? 5.5 Electricity can be saved through the efficient use of energy. Name FIVE practices that can be implemented in a home to save energy. (5) TOTAL: 100

NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL SYSTEMS AND CONSTRUCTION NQF LEVEL 2 NOVEMBER 2009

NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL SYSTEMS AND CONSTRUCTION NQF LEVEL 2 NOVEMBER 2009 NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL SYSTEMS AND CONSTRUCTION NQF LEVEL 2 NOVEMBER 2009 (12041032) 12 November (X-Paper) 09:00 12:00 This question paper consists of 6 pages. (12041032) -2- NC710(E)(N12)V

More information

NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL SYSTEMS AND CONSTRUCTION NQF LEVEL 4 NOVEMBER 2009

NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL SYSTEMS AND CONSTRUCTION NQF LEVEL 4 NOVEMBER 2009 NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL SYSTEMS AND CONSTRUCTION NQF LEVEL 4 NOVEMBER 2009 (12041034) 12 November (Y-Paper) 13:00 16:00 This question paper consists of 6 pages. (12041034) -2- NC730(E)(N12)V

More information

NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL WORKMANSHIP NQF LEVEL 4 NOVEMBER 2009

NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL WORKMANSHIP NQF LEVEL 4 NOVEMBER 2009 NATIONAL CERTIFICATE (VOCATIONAL) ELECTRICAL WORKMANSHIP NQF LEVEL 4 NOVEMBER 2009 (12041014) 25 November (X-Paper) 09:00 12:00 A non-programmable scientific calculator may be used. This question paper

More information

ELECTRICAL INSTALLER EXAMINATION 18 November 2017 QUESTION AND ANSWER BOOKLET

ELECTRICAL INSTALLER EXAMINATION 18 November 2017 QUESTION AND ANSWER BOOKLET Candidate Code No. EIN15 For Board Use Only Result Date Int Result Date Int ELECTRICAL INSTALLER EXAMINATION 18 November 2017 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed: Three

More information

NATIONAL CERTIFICATE (VOCATIONAL) AUTOMOTIVE REPAIR AND MAINTENANCE NQF LEVEL 2 NOVEMBER 2009

NATIONAL CERTIFICATE (VOCATIONAL) AUTOMOTIVE REPAIR AND MAINTENANCE NQF LEVEL 2 NOVEMBER 2009 NATIONAL CERTIFICATE (VOCATIONAL) AUTOMOTIVE REPAIR AND MAINTENANCE NQF LEVEL 2 NOVEMBER 2009 (6021032) 12 November (X-Paper) 09:00 12:00 This question paper consists of 9 pages. (6021032) -2- NC240(E)(N12)V

More information

ELECTRICAL APPLIANCE SERVICEPERSON (QUALIFIED) EXAMINATION

ELECTRICAL APPLIANCE SERVICEPERSON (QUALIFIED) EXAMINATION 23 June 2018 Time Allowed: 2 Hours ELECTRICAL APPLIANCE SERVICEPERSON (QUALIFIED) EXAMINATION Check the label on the back of this paper to ensure you have your paper. INSTRUCTIONS READ CAREFULLY You have

More information

Using Electricity. Prepared in Jan 1999 Second editing in March 2000

Using Electricity. Prepared in Jan 1999 Second editing in March 2000 Using Electricity Prepared in Jan 1999 Second editing in March 2000 Learning objectives At the end of this unit you should be able to : 1. show understanding of the use of fuses and fuse rating. 2. give

More information

ELECTRICAL SERVICE TECHNICIAN EXAMINATION 25 November 2017 QUESTION AND ANSWER BOOKLET

ELECTRICAL SERVICE TECHNICIAN EXAMINATION 25 November 2017 QUESTION AND ANSWER BOOKLET Candidate Code No. EST 2075 For Board Use Only Result Date Int Result Date Int ELECTRICAL SERVICE TECHNICIAN EXAMINATION 25 November 2017 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed:

More information

NATIONAL CERTIFICATE (VOCATIONAL) AUTOMOTIVE REPAIR AND MAINTENANCE NQF LEVEL 4 NOVEMBER 2009

NATIONAL CERTIFICATE (VOCATIONAL) AUTOMOTIVE REPAIR AND MAINTENANCE NQF LEVEL 4 NOVEMBER 2009 NATIONAL CERTIFICATE (VOCATIONAL) AUTOMOTIVE REPAIR AND MAINTENANCE NQF LEVEL 4 NOVEMBER 2009 (6021034) 12 November (Y-Paper) 13:00 16:00 This question paper consists of 8 pages. (6021034) -2- NC260(E)(N12)V

More information

ELECTRICIAN S THEORY EXAMINATION 11 September 2010 QUESTION AND ANSWER BOOKLET

ELECTRICIAN S THEORY EXAMINATION 11 September 2010 QUESTION AND ANSWER BOOKLET Candidate Code No. ET36 For Board Use Only Result Date Int Result Date Int ELECTRICIAN S THEORY EXAMINATION 11 September 2010 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed: Three

More information

ELECTRICAL SERVICE TECHNICIAN EXAMINATION 16 September 2017 QUESTION AND ANSWER BOOKLET

ELECTRICAL SERVICE TECHNICIAN EXAMINATION 16 September 2017 QUESTION AND ANSWER BOOKLET Candidate Code No. EST 2074 For Board Use Only Result Date Int Result Date Int ELECTRICAL SERVICE TECHNICIAN EXAMINATION 16 September 2017 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed:

More information

ELECTRICAL INSTALLER THEORY EXAMINATION 21 June 2014 QUESTION AND ANSWER BOOKLET

ELECTRICAL INSTALLER THEORY EXAMINATION 21 June 2014 QUESTION AND ANSWER BOOKLET Candidate Code No. EIN 08 For Board Use Only Result Date Int Result Date Int ELECTRICAL INSTALLER THEORY EXAMINATION 21 June 2014 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed: Three

More information

Class X Chapter 09 Electrical Power and Household circuits Physics

Class X Chapter 09 Electrical Power and Household circuits Physics EXERCISE- 9 (A) Question 1: Write an expression for the electrical energy spent in flow of current through an electrical appliance in terms of current, resistance and time. Solution 1: Electrical energy,

More information

EST Electrical Service Technician Answer Schedule

EST Electrical Service Technician Answer Schedule EST 2075 - Electrical Service Technician Answer Schedule Notes:1. means that the preceding statement/answer earns 1 mark. 2. This schedule sets out the accepted answers to the examination questions. A

More information

ELECTRICIAN S THEORY EXAMINATION 19 June 2010 QUESTION AND ANSWER BOOKLET

ELECTRICIAN S THEORY EXAMINATION 19 June 2010 QUESTION AND ANSWER BOOKLET Candidate Code No. ET34 For Board Use Only Result Date Int Result Date Int ELECTRICIAN S THEORY EXAMINATION 19 June 2010 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed: Three hours

More information

Using Electricity. Summary Notes. 1. From the Wall Socket Household appliances. Earth wire and safety.

Using Electricity. Summary Notes. 1. From the Wall Socket Household appliances. Earth wire and safety. Using Electricity Summary Notes Section Content 1. From the Wall Socket Household appliances. Earth wire and safety. 2. Alternating and Direct Battery and transformer. Current Circuit diagrams. Current

More information

Chapter 21 Practical Electricity

Chapter 21 Practical Electricity Chapter 21 Practical Electricity (A) Electrical Power 1. State four applications of the heating effect of electricity. Home: o Used in electric kettles o Used in electric irons o Used in water heaters

More information

ELECTRICAL SERVICE TECHNICIAN EXAMINATION 22 November 2014 QUESTION AND ANSWER BOOKLET

ELECTRICAL SERVICE TECHNICIAN EXAMINATION 22 November 2014 QUESTION AND ANSWER BOOKLET EST 2063 Candidate Code No. For Board Use Only Result Date Result Date Int ELECTRICAL SERVICE TECHNICIAN EXAMINATION 22 November 2014 QUESTION AND ANSWER BOOKLET Time Allowed: Two Hours INSTRUCTIONS READ

More information

Electrical Protection

Electrical Protection Electrical Protection Excessive current in any electrical circuit is hazardous and not desired, and these maybe caused by the following; 1. Overloads, and 2. Short-circuits. Overload Currents: These are

More information

ES5. Candidate Code No. For Board Use Only. Result Date Int. Result Date Int

ES5. Candidate Code No. For Board Use Only. Result Date Int. Result Date Int ES5 Candidate Code No. For Board Use Only Result Date Int Result Date Int ELECTRICAL WORKERS REGISTRATION BOARD ELECTRONIC SECURITY THEORY/REGULATIONS EXAMINATION 19 November 2005 QUESTION AND ANSWER BOOKLET

More information

Ordinary Level Physics SOLUTIONS: EFFECTS OF AN ELECTRIC CURRENT

Ordinary Level Physics SOLUTIONS: EFFECTS OF AN ELECTRIC CURRENT Ordinary Level Physics SOLUTIONS: EFFECTS OF AN ELECTRIC CURRENT Safety Features and kilowatt hours The unit of energy is called the kilowatt hour One kilowatt hour is the amount of energy used by a 1000

More information

UNIT-I ALTERNATORS PART-A

UNIT-I ALTERNATORS PART-A UNIT-I ALTERNATORS 1. What principle is used in Alternators? 2. What are the requirements of an alternator? 3. Mention the types of alternator rotor. 4. What is hunting in alternators? 5. What are the

More information

9. Effects of an electric current

9. Effects of an electric current Leaving Cert Physics Long Questions 2017-2002 9. Effects of an electric current Please remember to photocopy 4 pages onto one sheet by going A3 A4 and using back to back on the photocopier Contents Ordinary

More information

Course Semester Subject Code Subject Name B.E EEE(M) V UAEE507 MARINE ELECTRICAL TECHNOLOGY UNIT-I

Course Semester Subject Code Subject Name B.E EEE(M) V UAEE507 MARINE ELECTRICAL TECHNOLOGY UNIT-I Course Semester Subject Code Subject Name B.E EEE(M) V UAEE0 MARINE ELECTRICAL TECHNOLOGY 0 What is Megger? Mention the Uses of Megger How the smoke detecters are working? What is the use of OCR in generator?

More information

ELECTRICIAN S THEORY EXAMINATION 20 June 2015 QUESTION AND ANSWER BOOKLET

ELECTRICIAN S THEORY EXAMINATION 20 June 2015 QUESTION AND ANSWER BOOKLET Candidate Code No. ET54 For Board Use Only Result Date Int Result Date Int ELECTRICIAN S THEORY EXAMINATION 20 June 2015 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed: Three hours

More information

Year 11 GCSE PHYSICS REVISION QUESTIONS PAPER 1. Higher Level. Energy and Electricity

Year 11 GCSE PHYSICS REVISION QUESTIONS PAPER 1. Higher Level. Energy and Electricity Year 11 GCSE PHYSICS REVISION QUESTIONS PAPER 1 Higher Level Energy and Electricity Moulsham High School 1 1. A domestic electricity bill for the Smith family is shown. The unit of electricity is the kilowatt

More information

Electrical Energy and Power Ratings

Electrical Energy and Power Ratings Section 1 - From the Wall Socket Electrical Energy and ower Ratings Batteries and the mains are sources of electrical energy. Electrical appliances can then convert this into other forms of energy. e.g.

More information

2000 Cooper Bussmann, Inc. Page 1 of 9 10/04/00

2000 Cooper Bussmann, Inc. Page 1 of 9 10/04/00 DO YOU KNOW THE FACTS ABOUT SINGLE-POLE INTERRUPTING RATINGS? YOU MAY BE IN TROUBLE! Typical plant electrical systems use three-phase distribution schemes. As an industry practice, short-circuit calculations

More information

ELECTRICIAN S THEORY EXAMINATION 21 June 2014 QUESTION AND ANSWER BOOKLET

ELECTRICIAN S THEORY EXAMINATION 21 June 2014 QUESTION AND ANSWER BOOKLET Candidate Code No. ET49 For Board Use Only Result Date Int Result Date Int ELECTRICIAN S THEORY EXAMINATION 21 June 2014 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed: Three hours

More information

PHASE CONVERTERS OPERATING & MAINTENANCE INSTRUCTIONS. MODEL NO: PC40 and PC60. PART Nos:

PHASE CONVERTERS OPERATING & MAINTENANCE INSTRUCTIONS. MODEL NO: PC40 and PC60. PART Nos: PHASE CONVERTERS MODEL NO: PC40 and PC60 MODEL PART No: NO: 6012805 PC20 and PC40 6012810 PC60 PART Nos: 6012800 6012805 6012810 OPERATING & MAINTENANCE INSTRUCTIONS 0107 Specifications PC20 PC40 PC60

More information

ELECTRICIANS REGULATIONS EXAMINATION 29 June 2013 QUESTION AND ANSWER BOOKLET

ELECTRICIANS REGULATIONS EXAMINATION 29 June 2013 QUESTION AND ANSWER BOOKLET ER52 Candidate Code No. For Board Use Only Result Date Result Date Int ELECTRICIANS REGULATIONS EXAMINATION 29 June 2013 QUESTION AND ANSWER BOOKLET Time Allowed: Three hours INSTRUCTIONS READ CAREFULLY

More information

9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc.

9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc. Chapter 3 TRANSMISSION SYSTEMS 1 Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution

More information

SLOVAK UNIVERSITY OF TECHNOLOGY Faculty of Material Science and Technology in Trnava ELECTRICAL ENGINEERING AND ELECTRONICS.

SLOVAK UNIVERSITY OF TECHNOLOGY Faculty of Material Science and Technology in Trnava ELECTRICAL ENGINEERING AND ELECTRONICS. SLOVAK UNIVERSITY OF TECHNOLOGY Faculty of Material Science and Technology in Trnava ELECTRICAL ENGINEERING AND ELECTRONICS Róbert Riedlmajer TRNAVA 2007 Unit 14 - Fundamentals of power system protection

More information

ES5 Security Theory/Regulations Answer Schedule

ES5 Security Theory/Regulations Answer Schedule ES5 Security Theory/Regulations Answer Schedule Notes:1. means that the preceding statement/answer earns 1 mark. 2. This schedule sets out the expected answers to the examination questions. The marker

More information

Chapter Assessment Use with Chapter 22.

Chapter Assessment Use with Chapter 22. Date Period 22 Use with Chapter 22. Current Electricity Understanding Concepts Part A Use each of the following terms once to complete the statements below. ampere electric current potential difference

More information

LEP ASSESSMENT REVIEW

LEP ASSESSMENT REVIEW LEP ASSESSMENT REVIEW FOR SURNAME: NAME: ASSESSMENT DATE: Candidate: Assessor: Final Mark NOTE: Question 1 is a negative marking system. Start with 35 marks and marks are deducted from 35 if mistakes or

More information

BHARAT HEAVY ELECTRICALS LIMITED, JHANSI

BHARAT HEAVY ELECTRICALS LIMITED, JHANSI BHARAT HEAVY ELECTRICALS LIMITED, JHANSI DESIGN, MANUFACTURING, TESTING, SUPPLY INSTALLATION AND COMMISSIONING OF 11KV VACUUM CIRCUIT BREAKER NOTE : 1 VENDOR must submit complete information against clause

More information

Installation and Construction Notes for EVSE4

Installation and Construction Notes for EVSE4 Installation and Construction Notes for EVSE4 You need to read and understand this if you want to build an EVSE that will be safe and need to pass a building inspectors review. Before beginning this process

More information

1 Safety instructions. 2 Intended use. 3 Product characteristics. 4 Operation. System Universal LED dimming insert Standard

1 Safety instructions. 2 Intended use. 3 Product characteristics. 4 Operation. System Universal LED dimming insert Standard Order no.: 5400 00 Operating instructions 1 Safety instructions Electrical devices may only be mounted and connected by electrically skilled persons. Serious injuries, fire or property damage possible.

More information

ELECTRIC POWER AND HOUSEHOLD CIRCUITS

ELECTRIC POWER AND HOUSEHOLD CIRCUITS ELECTRIC POWER AND HOUSEHOLD CIRCUITS HEATING EFFECT OF CURRENT Heating effect of electricity is one of the widely-used effects in the world. When electric current is passed through a conductor, it generates

More information

Boardworks Ltd Mains Electricity

Boardworks Ltd Mains Electricity 1 of 22 Boardworks Ltd 2016 Mains Electricity Mains Electricity 2 of 22 Boardworks Ltd 2016 Direct current 3 of 22 Boardworks Ltd 2016 There are two main types of electric current: direct current (DC)

More information

Essential Electricity Homework Exercise 1

Essential Electricity Homework Exercise 1 Homework Exercise 1 1. For each of the following electrical symbols, copy the symbol into you jotter and label it using the words below. Word bank resistor, voltmeter, battery, ammeter, bulb V A 2. State

More information

ELECTRICAL INSPECTOR EXAMINATION 14 November 2015 QUESTION AND ANSWER BOOKLET Time Allowed: Three hours

ELECTRICAL INSPECTOR EXAMINATION 14 November 2015 QUESTION AND ANSWER BOOKLET Time Allowed: Three hours Candidate Code No. IT 32 For Board Use Only Result Date Int Result Date Int ELECTRICAL INSPECTOR EXAMINATION 14 November 2015 QUESTION AND ANSWER BOOKLET Time Allowed: Three hours INSTRUCTIONS READ CAREFULLY

More information

Fault Finding. Standard/Fundamental Faults

Fault Finding. Standard/Fundamental Faults Fault Finding There is a generally recognised method of approaching faultfinding, which is referred to as the 5-Point Fault Finding approach... the most important factor in this method concerns attaining

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) (Corr.1 June 2018) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements

More information

Electrical Workplace Safety

Electrical Workplace Safety Electrical Workplace Safety Alan Kelly 23 rd September 2015 Objectives To provide an understanding of Electrical terms and the concepts of electricity To introduce Electrical Protective Devices and provide

More information

GUIDE TO MAINTENANCE PRACTICES FOR DISTRIBUTION NETWORKS IN THE DISTRIBUTION SECTOR OF THE NAMIBIAN ELECTRICITY SUPPLY INDUSTRY

GUIDE TO MAINTENANCE PRACTICES FOR DISTRIBUTION NETWORKS IN THE DISTRIBUTION SECTOR OF THE NAMIBIAN ELECTRICITY SUPPLY INDUSTRY PART B-04 TITLE: DISTRIBUTION SUBSTATIONS SPECIFICATION NO: B-04 INCEPTION DATE: AFTER GAZETTING (WORKING DOCUMENT FOR A 2 YEAR PERIOD) AMENDMENTS/REVISIONS DATE PAGE PARAGRAPH DESCRIPTION ORIGINATOR APPROVED

More information

LED AC DRIVERLESS FLOODLIGHTS WITH PIR FOR MODEL: FLAC10BPIR, FLAC20BPIR, FLAC30BPIR & FLAC50BPIR

LED AC DRIVERLESS FLOODLIGHTS WITH PIR FOR MODEL: FLAC10BPIR, FLAC20BPIR, FLAC30BPIR & FLAC50BPIR INTRODUCTION The LED AC Driverless Floodlights with PIR include a hanging / mounting bracket and a 100cm cable. SPECIFICATION LED 800-4000lm IP65 180-240V IK07 6000K 50Hz >80 Ra 10W- 50W Dimensions: FLAC10BPIR:

More information

RE-PR3-E-86&105 3-Phase Panel Mount 86 and 105kW

RE-PR3-E-86&105 3-Phase Panel Mount 86 and 105kW Page 1 of 6 3-Phase Panel Mount 86 and 105kW Features: Benefits: 0-10Vdc, 0-5Vdc, 4-20mA or manual via potentiometer control input Over temperature protection with auto reset Enclosed panel mounting Efficient

More information

to allow a current in one circuit to operate a switch in another circuit to protect a circuit by melting if the current becomes too large

to allow a current in one circuit to operate a switch in another circuit to protect a circuit by melting if the current becomes too large 1 What is the function of a relay? to allow a current in one circuit to operate a switch in another circuit to prevent an electric shock by earthing a metal case to protect a circuit by melting if the

More information

UNIT 3: GENErAL ELECTriCAL SySTEM DiAGNOSiS

UNIT 3: GENErAL ELECTriCAL SySTEM DiAGNOSiS Electrical/Electronic Systems UNIT 3: GENErAL ELECTriCAL SySTEM DiAGNOSiS LESSON 3: TEST electrical circuits I. Types of electrical circuit tests and electrical faults A. Different types of electrical

More information

1 Safety instructions. 2 Intended use. 3 Product characteristics. 4 Operation. LB management. Universal touch dimmer insert LED

1 Safety instructions. 2 Intended use. 3 Product characteristics. 4 Operation. LB management. Universal touch dimmer insert LED Art. no.: 1711DE Operating instructions 1 Safety instructions Electrical devices may only be mounted and connected by electrically skilled persons. Serious injuries, fire or property damage possible. Please

More information

The graphs show the voltage across two different types of cell as they transfer the last bit of their stored energy through the torch bulb.

The graphs show the voltage across two different types of cell as they transfer the last bit of their stored energy through the torch bulb. Q1. A small torch uses a single cell to make the bulb light up. (a) The graphs show the voltage across two different types of cell as they transfer the last bit of their stored energy through the torch

More information

ANALOGUE INSULATION-CONTINUITY and VOLTAGE METER

ANALOGUE INSULATION-CONTINUITY and VOLTAGE METER 99 Washington Street Melrose, MA 02176 Phone 781-665-1400 Toll Free 1-800-517-8431 Visit us at www.testequipmentdepot.com BST-IT26 ANALOGUE INSULATION-CONTINUITY and VOLTAGE METER INSTRUCTION MANUAL Index

More information

1 This instrument must only be used by a competent and trained person and operated in strict accordance with the instructions.

1 This instrument must only be used by a competent and trained person and operated in strict accordance with the instructions. 1 This instrument must only be used by a competent and trained person and operated in strict accordance with the instructions. KYORITSU will not accept liability for any damage or injury caused by misuse

More information

POWERSOURCEPURE INSTRUCTIONS. Pure Sine Wave Inverter. RINV1200P REINV1200P RINV2200P REINV2200P

POWERSOURCEPURE INSTRUCTIONS. Pure Sine Wave Inverter.  RINV1200P REINV1200P RINV2200P REINV2200P POWERSOURCEPURE Pure Sine Wave Inverter RINV1200P REINV1200P RINV2200P REINV2200P INSTRUCTIONS Retain these instructions for future reference www.ringautomotive.co.uk OVERVIEW The Ring Pure Sine Wave (PSW)

More information

Electrical Awareness and Considerations

Electrical Awareness and Considerations Electrical Awareness and Considerations By David Taylor FIHE MIET IEng Objectives Awareness of specifications. Awareness of Distribution Network Operators (DNO) earthing arrangements. Awareness of basic

More information

USER MANUAL. 10KV Digital High Voltage Insulation Tester. Model MG500. Additional User Manual Translations available at

USER MANUAL. 10KV Digital High Voltage Insulation Tester. Model MG500. Additional User Manual Translations available at USER MANUAL 10KV Digital High Voltage Insulation Tester Model MG500 Additional User Manual Translations available at www.extech.com Introduction Thank you for selecting the Extech Instruments Model MG500.

More information

Science Part B Chapter 4- Electrical Energy. Lesson 1-

Science Part B Chapter 4- Electrical Energy. Lesson 1- Science Part B Chapter 4- Electrical Energy Lesson 1- Most atoms have equal numbers of protons, which are positively charged, and electrons, which are negatively charged. These atoms have no charge; they

More information

ELECTRICIANS REGULATIONS EXAMINATION 23 November 2013 QUESTION AND ANSWER BOOKLET

ELECTRICIANS REGULATIONS EXAMINATION 23 November 2013 QUESTION AND ANSWER BOOKLET ER54 Candidate Code No. For Board Use Only Result Date Result Date Int ELECTRICIANS REGULATIONS EXAMINATION 23 November 2013 QUESTION AND ANSWER BOOKLET Time Allowed: Three hours INSTRUCTIONS READ CAREFULLY

More information

Trade of Metal Fabrication. Module 1: Basic Fabrication Unit 15: Electricity Phase 2

Trade of Metal Fabrication. Module 1: Basic Fabrication Unit 15: Electricity Phase 2 Trade of Metal Fabrication Module 1: Basic Fabrication Unit 15: Electricity Phase 2 Table of Contents List of Figures... 5 List of Tables... 6 Document Release History... 7 Module 1 Basic Fabrication...

More information

INTERACTIVE SCIENCE 2A

INTERACTIVE SCIENCE 2A INTERACTIVE SCIENCE 2A Workbook Solutions (Enrichment Edition) Chapter 8 MAKING USE OF ELECTRICITY Part A Sectional Exercise 8.1 & 8.2 Concept checking p.35 1. False 2. True 3. False 4. True 5. True Questions

More information

Effective discrimination of protective devices

Effective discrimination of protective devices Effective discrimination of protective devices In the event of a fault occurring on an electrical installation only the protective device nearest to the fault should operate,leaving other healthy circuits

More information

Question Set(2017) Switch Gear & protection(5 th SEm) 9. Explain the construction and operating principle with proper diagram:

Question Set(2017) Switch Gear & protection(5 th SEm) 9. Explain the construction and operating principle with proper diagram: Question Set(2017) Switch Gear & protection(5 th SEm) 1. What is fault in power system? Classify the fault. What are the bad effects of fault? 2. Define with example: Symmetrical fault and unsymmetrical

More information

CLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001

CLP POWER HONG KONG LIMITED. SUPPLY RULES March 2001 CLP POWER HONG KONG LIMITED SUPPLY March 2001 ADVISORY SERVICE Advice concerning matters relating to the supply of electricity may be obtained free of charge from the Company. OTHER COMPANY PUBLICATIONS

More information

2.0 CONSTRUCTION 3.0 OPERATION. SA-1 Generator Differential Relay - Class 1E 2.5 TRIP CIRCUIT

2.0 CONSTRUCTION 3.0 OPERATION. SA-1 Generator Differential Relay - Class 1E 2.5 TRIP CIRCUIT 41-348.11C SA-1 Generator Differential Relay - Class 1E 2.0 CONSTRUCTION The type SA-1 relay consists of: Restraint Circuit Sensing Circuit Trip Circuit Surge Protection Circuit Operating Circuit Amplifier

More information

Fatima Michael College of Engineering & Technology

Fatima Michael College of Engineering & Technology B.E/ B.Tech. DEGREE EXAMINATION, NOVEMBER/DECEMBER 2012 Fifth semester Automobile engineering AT 2302/AU52/1O122 AU 504 AUTOMOTIVE ELECTRICAL AND ELECTRONICS (Regulation 2008) Answer All Questions PART

More information

ELECTRICIANS REGULATIONS EXAMINATION 25 June 2011

ELECTRICIANS REGULATIONS EXAMINATION 25 June 2011 ER42 Candidate Code No. For Board Use Only Result Date Result Date Int ELECTRICIANS REGULATIONS EXAMINATION 25 June 2011 Int QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed: Three

More information

Electrical Wiring Practices

Electrical Wiring Practices Chapter 2 Electrical Wiring Practices and Diagrams MElec-Ch2-1 Overview Safety Standards Wiring Considerations Wire Terminations Coaxial Cable Wiring Installations Wiring Diagrams MElec-Ch2-2 Safety Lethal

More information

User's Manual Digital High Voltage Insulation Tester Model

User's Manual Digital High Voltage Insulation Tester Model 99 Washington Street Melrose, MA 02176 Phone 781-665-1400 Toll Free 1-800-517-8431 Visit us at www.testequipmentdepot.com Back to the Extech 380375 Product Page User's Manual Digital High Voltage Insulation

More information

BATTERY OPERATED DIGITAL MILLI-OHMMETER

BATTERY OPERATED DIGITAL MILLI-OHMMETER BATTERY OPERATED DIGITAL MILLI-OHMMETER C 1 P 1 P 2 C 2 MAX. DC20V MICROPROCESSOR CONTROLLED AC DC HOLD M A X M I N AUTO-HOLD Hz mv km ka ms DIGITAL MILLIOHM METER 2000 200.0 20.00 2000m Test Current Range

More information

1 Safety instructions

1 Safety instructions Order No. : 2385 00 Operating instructions 1 Safety instructions Electrical devices may only be mounted and connected by electrically skilled persons. Serious injuries, fire or property damage possible.

More information

On_Disc. 2 o/c1 BS 7671 applies to a lift installations b highway equipment c equipment on board ships d electrical equipment of machines.

On_Disc. 2 o/c1 BS 7671 applies to a lift installations b highway equipment c equipment on board ships d electrical equipment of machines. 1 PAPER 4 Sample Questions - C&G 2382 17th Edition full paper D 1 o/c 1 - A recommendation for the interval to the first periodic inspection shall be made by: a the installation electrician. b the main

More information

DC POWER SUPPLY ALIMENTATION C.C.

DC POWER SUPPLY ALIMENTATION C.C. DC POWER SUPPLY ALIMENTATION C.C. ISO-TECH IPS 303A 201-3424 ISO-TECH IPS 601A 201-3446 SAFETY TERMS AND SYMBOLS These terms may appear in this manual or on the product: WARNING. Warning statements identify

More information

- Wiring Brochure Universal Reset Module 422e

- Wiring Brochure Universal Reset Module 422e - Wiring Brochure Universal Reset Module 422e W 422e 01/08 1 Information Brochure hoose controls to match application 2 Application Brochure Design your mechanical applications 3 Rough In Wiring Rough-in

More information

BATTERY BOOSTER/CHARGER MODEL NO: DIGICAR 900

BATTERY BOOSTER/CHARGER MODEL NO: DIGICAR 900 BATTERY BOOSTER/CHARGER MODEL NO: DIGICAR 900 PART NO: 6261205 OPERATION & MAINTENANCE INSTRUCTIONS LS0715 INTRODUCTION Thank you for purchasing this CLARKE Battery booster / charger which is suitable

More information

Name: Paisley Grammar Physics Department UNIT 2 USING ELECTRICITY PUPIL PACK. National 4/5 Physics. Study Guides Summary Notes Homework Sheets

Name: Paisley Grammar Physics Department UNIT 2 USING ELECTRICITY PUPIL PACK. National 4/5 Physics. Study Guides Summary Notes Homework Sheets Name: National 4/5 Physics Paisley Grammar Physics Department UNIT 2 USING ELECTRICITY PUPIL PACK Study Guides Summary Notes Homework Sheets USING ELECTRICITY Working at Home TO THE PUPIL Each day you

More information

This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly. SUPPLEMENTAL CORRECTION SHEET FOR SOLAR PHOTOVOLTAIC SYSTEMS (ELEC) This is intended to provide uniform application of the codes by the plan check staff and to help the public apply the codes correctly.

More information

Instruction Manual. Q Series 2 Motor Control Modules - OEM

Instruction Manual. Q Series 2 Motor Control Modules - OEM A382-21-880 Issue B Instruction Manual Q Series 2 Motor Control Modules - OEM Pump/ Q Motor Control Module Item Number pumping system Electrical supply 24 V d.c. control 24 V a.c. control QDP40 200-230

More information

PURE PHYSICS ELECTRICITY & MAGNETISM (PART I)

PURE PHYSICS ELECTRICITY & MAGNETISM (PART I) PURE PHYSICS ELECTRICITY & MAGNETISM (PART I) 1 A student walks across a thick carpet and becomes positively charged as his shoes rub on the carpet. When he touches the metal handle of a door, negative

More information

Electricity Unit Review

Electricity Unit Review Science 9 Electricity Unit Review Name: General Definitions: Neutral Object Charge Separation Electrical Discharge Electric Current Amperes (amps) Voltage (volts) Voltmeter Ammeters Galvanometer Multimeter

More information

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655) - (SMUD FORM 2655) A. Applicability: This Generating Facility Interconnection Application (Application) shall be used to request the interconnection of a Generating Facility to Sacramento Municipal Utility

More information

Electrical Equipment and Terminology

Electrical Equipment and Terminology Youth Explore Trades Skills Description Understanding the language of the electrical trade and knowing what electrical equipment is named and its purpose are very important. Anyone who is exposed to a

More information

CHAPTER V RESIDENTIAL WIRING

CHAPTER V RESIDENTIAL WIRING CHAPTER V RESIDENTIAL WIRING 5.1. THE SERVICE ENTRANCE Buildings and other structures receive the electrical energy through the service entrance. In residential wiring, the electric company supply this

More information

Scheme - I. Sample Question Paper

Scheme - I. Sample Question Paper Program Name Program Code Course Title Sample Question Paper : Diploma in Industrial Electronics : IE : Electrical Machines and Transformers Max. Marks : 70 Time : 3 Hrs. Q1. ATTEMPT ANY FIVE OF THE FOLLOWING.

More information

ELECTRICIANS REGULATIONS EXAMINATION 30 June 2012 QUESTION AND ANSWER BOOKLET

ELECTRICIANS REGULATIONS EXAMINATION 30 June 2012 QUESTION AND ANSWER BOOKLET ER47 Candidate Code No. For Board Use Only Result Date Result Date Int ELECTRICIANS REGULATIONS EXAMINATION 30 June 2012 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Int Time Allowed: Three

More information

Fusing Equipment. Kearney Fuse Links. general. Internal Construction. tin element

Fusing Equipment. Kearney Fuse Links. general. Internal Construction. tin element Fusing Equipment Kearney Fuse Links Electrical Apparatus 327-40 general Cooper Power Systems Kearney fuse links can be applied to a variety of applications requiring overcurrent protection of distribution

More information

TRANSMISSION SYSTEMS

TRANSMISSION SYSTEMS TRANSMISSION SYSTEMS Transmitting large amounts of electric energy over long distances is accomplished most efficiently by using high-voltages. Without transformers the widespread distribution of electric

More information

Service Entrance Methods

Service Entrance Methods Service Section Typical switchboards consist of a service section, also referred to as the main section, and one or more distribution sections. The service section can be fed directly from the utility

More information

PHYSICS FORM 5 ELECTRICITY AT HOME. These are electrical devices that opens the circuit in the event that the current exceeds a certain maximum value.

PHYSICS FORM 5 ELECTRICITY AT HOME. These are electrical devices that opens the circuit in the event that the current exceeds a certain maximum value. 1. Domestic wiring is done in parallel. The reason being in the event that one resistor (load eg. Appliance, lightbulb) is non-functional, then the entire circuit will not become open. 2. With the parallel

More information

NABTEB Past Questions and Answers - Uploaded online

NABTEB Past Questions and Answers - Uploaded online NATIONAL BUSINESS AND TECHNICAL EXAMINATIONS BOARD (NABTEB) ELECTRICAL INSTALLATION AND MAINTENANCE WORKS (041) MAY/JUNE, 2005 Question: 1(a) 1(b) What is Stroboscopic effect? With the aid of a diagram,

More information

1. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces.

1. The term withstand means the unit will remain in place without separation of any parts from the device when subjected to the seismic forces. SECTION 262816 - ENCLOSED SWITCHES AND CIRCUIT BREAKERS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Fusible switches. 2. Nonfusible switches. 3. Receptacle switches. 4. Shunt trip switches. 5.

More information

- Wiring Brochure Zone Manager 335

- Wiring Brochure Zone Manager 335 - Wiring Brochure W 335 12/08 1 Information Brochure Choose controls to match application 2 Application Brochure Design your mechanical applications Rough-in Wiring Rough-in wiring instructions 3 4 Wiring

More information

High Demand Questions QUESTIONSHEET 1 (a) Teresa set up the circuit shown in the diagram. The ammeter reading was 0.4 A.

High Demand Questions QUESTIONSHEET 1 (a) Teresa set up the circuit shown in the diagram. The ammeter reading was 0.4 A. High Demand Questions QUESTIONSHEET 1 (a) Teresa set up the circuit shown in the diagram. The ammeter reading was 0.4 A. A 4 Ω (i) What is the value of the current through the 4Ω resistor? (ii) What is

More information

- Wiring Brochure Zone Manager 336

- Wiring Brochure Zone Manager 336 - Wiring Brochure W 336 12/08 1 Information Brochure Choose controls to match application Application Brochure Design your mechanical applications 2 3 Rough-in Wiring Rough-in 4 Wiring Brochure Wiring

More information

Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation Edition DRAFT

Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation Edition DRAFT Date of publication: 1 November 2016Not yet published Issued by: Mark Wogan, Manager Energy Safety WorkSafe New ZealandNot yet issued Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation

More information

Books. Code of Practice for In-Service Inspection and Testing of Electrical Equipment (3rd edition) By IET Publication

Books. Code of Practice for In-Service Inspection and Testing of Electrical Equipment (3rd edition) By IET Publication Books Code of Practice for In-Service Inspection and Testing of Electrical Equipment (3rd edition) By IET Publication Available: 2008 Format: Paperback Product Code: PWR08630 ISBN: 978-0-86341-833-4 Pagination:

More information

Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation

Electric Vehicle Charging Safety Guidelines Part 2: Selection and Installation 86 Customhouse Quay PO Box 165, Wellington 6140 New Zealand Date of publication: 1 November 2016 Issued by: Mark Wogan, Manager Energy Safety WorkSafe New Zealand Electric Vehicle Charging Safety Guidelines

More information

Total duration of course = 3 Months (12 weeks) Total training hours = 400 hrs.

Total duration of course = 3 Months (12 weeks) Total training hours = 400 hrs. 1 TRAINING OBJECTIVES: In order to reduce the unemployment and poverty in the society, the curriculum is designed to impart the technical knowledge and skill to those who are literate and.can not do the

More information

Electrical. Earthing & Bonding. Installation Techniques. Learning Notes MODULE 2.2 UNIT PHASE:2

Electrical. Earthing & Bonding. Installation Techniques. Learning Notes MODULE 2.2 UNIT PHASE:2 Electrical Learning Notes MODULE 2.2 UNIT 2.2.6 Installation Techniques Earthing & Bonding PHASE:2 Table of Contents INTRODUCTION... 3 DEFINITIONS... 4 EARTHING... 5 TYPES OF SYSTEM EARTHING... 10 EQUIPOTENTIAL

More information