1 S REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: FILE CODE: A02-30/PW SUBJECT: NORTHFIELD DRIVE AT HIGHWAY 85 INTERCHANGE MODIFICATIONS RECOMMENDATION: For information. REPORT: ION, the Region of Waterloo s Rapid Transit service, is moving forward, with construction starting in 2014 and operation beginning in As part of the early ION functional design, the Highway 85 interchanges at Northfield Drive were proposed as full-movement, signalized intersections. Since then, Regional staff have been working with the Ministry of Transportation of Ontario (MTO) to develop a design that will maintain access to/from Highway 85, provide safe and efficient traffic operations, accommodate active transportation and provide efficient RT service in the area. The evaluation was based on the following general considerations: Changes to area traffic patterns Traffic operations and safety at subject and adjacent interchanges LRT operations and safety GRT operations and safety Accommodation of active transportation The design evaluation has resulted in the need for the following modifications on Northfield Drive at the Highway 85 interchanges: The northbound and southbound Highway 85 interchanges at Northfield Drive will become right-in and right-out only The Kumpf Drive/Barta at Northfield Drive intersection will become right-in and right-out only A U-turn will be provided at the intersections of Northfield Drive/Parkside Drive and Northfield Drive/Colby Drive Accommodation of cycling lanes, sidewalks, and pedestrian crossing facilities on Northfield Drive between the rail corridor and Colby Drive are currently being evaluated A Public Information Centre (PIC) to present these modifications has been scheduled as follows: Date: June 27, 2013 (Drop-in from 4 to 8 p.m.) Location: Albert McCormick Community Centre Address: 500 Parkside Drive, Waterloo Letters were sent out to residents and businesses in the adjacent neighbourhoods in the City of Page 1 of 19
2 Waterloo on June 14, 2013 inviting them to participate in the PIC. Newspaper advertisements will also be inserted in the Waterloo Chronicle (June 19, 2013), the Kitchener Post (June 21, 2013) and the Record (June 21, 2013). Road signs advertising the PIC were posted between June 13 and 28, Feedback, opinions and input received at the PIC will be used by staff when they make their final recommendation to Council. The revised design will be reflected in the RT Request for Proposal (RFP). CORPORATE STRATEGIC PLAN: The report supports Focus Area 3.1 of Council s Strategic Focus: Develop an implementation plan for light rail transit including corridor and station area planning. FINANCIAL IMPLICATIONS: In June 2011, Council approved the implementation of the RT project, including LRT and abrt, with estimated capital costs of $818 million, in 2014 dollars, with capital funding to be provided by the Province (up to $300 million), the federal government (one third of eligible project costs to a maximum of $265 million) and the Region ($253 million). The RT project and improvements to conventional transit are financed through an annual tax rate increase of 1.5% for a period of 7 years. The costs associated with the Northfield Drive at Highway 85 Interchange Modifications are contained within the DBFOM contract and will be included in that component of the overall project. Costing of this component will not be fully calculated until the RFP closes and the preferred proponent is selected. OTHER DEPARTMENT CONSULTATIONS/CONCURRENCE: Transportation Planning, Planning Housing and Community Services ATTACHMENTS Attachment A Northfield Drive at Highway 85 Interchange Modifications Attachment B Invite Letter Attachment C PIC Presentation Boards Attachment D Public Comment Form PREPARED BY: Danielle Tobey, Planner, Rapid Transit APPROVED BY: Thomas Schmidt, Commissioner, Transportation and Environmental Services Page 2 of 19
3 Colby Drive NB Ramp HWY 85 Bridge SB Ramp Kumpf Drive Rail Corridor Page 3 of 19
4 Refer To: File No: Date: Danielle Tobey D10-40/PCCM June 14, ext Dear Resident/Owner: Re: Public Information Centre Northfield Drive at Highway 85 Interchange Modifications ION, the Region of Waterloo s Rapid Transit service, is moving forward, with construction starting in 2014 and operation beginning in As part of the early ION functional design, the Highway 85 interchanges at Northfield Drive were proposed as full-movement, signalized intersections. Recent refinements to the design, however, have identified the following modifications on Northfield Drive, between Parkside and Colby Drive, at the Highway 85 interchanges: The northbound and southbound Highway 85 interchanges at Northfield Drive will become rightin and right-out only The Kumpf Drive/Barta at Northfield Drive intersection will become right-in and right-out only A U-turn will be provided at the intersections of Northfield Drive/Parkside Drive and Northfield Drive/Colby Drive Accommodation of cycling lanes, sidewalks, and pedestrian crossing facilities on Northfield Drive between the rail corridor and Colby Drive are currently being evaluated A Public Information Centre (PIC) to present these modifications has been scheduled as follows: Date: June 27, 2013 (Drop-in from 4 to 8 p.m.) Location: Albert McCormick Community Centre Address: 500 Parkside Drive, Waterloo If you are unable to attend, but wish to obtain information about the project, please contact the undersigned at ext Yours truly, Danielle Tobey Planner, Rapid Transit Division Page 4 of 19
5 Page 5 of 19
6 Page 6 of 19
7 Page 7 of 19
8 Page 8 of 19
9 Page 9 of 19
10 Page 10 of 19
11 Page 11 of 19
12 Page 12 of 19
13 Page 13 of 19
14 Page 14 of 19
15 Page 15 of 19
16 Page 16 of 19
17 Page 17 of 19
18 Page 18 of 19
19 Page 19 of 19
Late Starter. Tuesday, November 6, 2018
Late Starter Tuesday, Please note the following item(s) was not included with your agenda as this item(s) was received after the agenda package was printed. Planning and Works Committee Report TES-RTS-18-09,
More informationRegion of Waterloo Transportation and Environmental Services Rapid Transit
Region of Waterloo Transportation and Environmental Services Rapid Transit To: Chair Jim Wideman and Members of the Planning and Works Committee Date: September 30, 2014 File Code: A02-30/PW Subject: ION
More information5 VAUGHAN METROPOLITAN CENTRE AND SURROUNDING AREAS TRANSPORTATION STUDY PROGRESS
5 VAUGHAN METROPOLITAN CENTRE AND SURROUNDING AREAS TRANSPORTATION STUDY PROGRESS The Transportation Services Committee recommends the adoption of the recommendations contained in the following report
More informationMEMORANDUM. TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit. Date: May 24, Summary
TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Date: May 24, 2016 MEMORANDUM To: From: Subject: File No: Chair Tom Galloway and Planning and Works Committee Thomas Schmidt Revised Bombardier Vehicle
More informationSTRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016
STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit
More informationMOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project
MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation
More informationMississauga Bus Rapid Transit Preliminary Design Project
Mississauga Bus Rapid Transit Preliminary Design Project PUBLIC INFORMATION CENTRE OCTOBER 2008 WELCOME The Mississauga Bus Rapid Transit (BRT) Project Thank you for attending this Public Information Centre.
More informationSOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015
SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment
More informationCITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6
2016 2019 CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6 STRATEGIC AREA OF FOCUS: SUB-PRIORITY: STRATEGY: INITIATIVE: INITIATIVE LEAD(S): BUILDING A SUSTAINABLE CITY
More informationWelcome. Public Open House Schedule. Super 8 West Kelowna 1655 Westgate Rd, West Kelowna. West Kelowna. Wednesday, March 2, :00 p.m. 8:00 p.m.
Welcome Thank you for attending this Community Engagement on improvements to the Boucherie Road and Westlake Road intersections on Highway 97 in the Central Okanagan. Public Open House Schedule Location
More informationLetter EL652 City of Mercer Island. Page 1. No comments n/a
Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists
More informationMETRO Orange Line BRT American Boulevard Station Options
METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN
More informationSTH 60 Northern Reliever Route Feasibility Study Report
#233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development
More information2 MAJOR MACKENZIE DRIVE WEST JOG ELIMINATION AT HUNTINGTON ROAD CITY OF VAUGHAN
2 MAJOR MACKENZIE DRIVE WEST JOG ELIMINATION AT HUNTINGTON ROAD CITY OF VAUGHAN The Transportation Services Committee recommends the adoption of the recommendations contained in the following report dated
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: May 28, 2009 SUBJECT: DON MILLS STATION ACTION ITEM RECOMMENDATIONS It is recommended that the Commission: 1. Endorse the
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationRapid Transit Implementation Working Group #4 February 9, 2017
Rapid Transit Implementation Working Group #4 February 9, 2017 Agenda 1. Business Case Update 2. Rapid Transit Master Plan Overview 3. Corridor Concepts 4. Public Consultation Event 5. Schedule Outlook
More informationThe Eastern Connector Study November, 2007 planning for the future
The Eastern Connector Study November, 2007 planning for the future In late 2006, Albemarle County and the City of Charlottesville jointly initiated the Eastern Connector Corridor Study. The Project Team
More informationARE DIAMONDS LRT S BEST FRIEND? AT-GRADE LRT CROSSING AT A DIAMOND INTERCHANGE
ARE DIAMONDS LRT S BEST FRIEND? AT-GRADE LRT CROSSING AT A DIAMOND INTERCHANGE NATE LARSON HDR SEATTLE, WA ABHISHEK DAYAL VALLEY METRO PHOENIX, AZ ITE WESTERN DISTRICT ANNUAL MEETING JULY 16, 2013 Presentation
More informationWelcome to Open House #5 Scarborough Rapid Transit
Welcome to Open House #5 Scarborough Rapid Transit Welcome to the Scarborough Rapid Transit (SRT) Conversion and Extension Study, including Kennedy Station improvements. Tonight s event provides details
More informationDATE: March 21, 2017 REPORT NO. PW TYPE OF REPORT CONSENT ITEM [ ] ITEM FOR CONSIDERATION [ X ] 2.0 TOPIC
PUBLIC WORKS COMMISSION PUBLIC WORKS COMMISSION DATE: March 21, 2017 REPORT NO. PW2017-022 TO: FROM: Chair and Members Committee of the Whole Operations and Administration E. (Beth) Goodger, General Manager
More informationCommittee Report. Transportation Committee. Business Item No
Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope
More information5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE
5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE The Rapid Transit Public/Private Partnership Steering Committee recommends the
More informationExhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup
Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: September 27, 2012 SUBJECT: NOTICE OF AWARD PROCUREMENT AUTHORIZATION - ARTICULATED BUSES INFORMATION ITEM RECOMMENDATION
More informationACTION TRANSMITTAL No
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior
More informationThe Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee
The Regional Municipality of Halton Report To: From: Chair and Members of the Planning and Public Works Committee Jim Harnum, Commissioner, Public Works Date: October 5, 2016 Report No. - Re: PW-36-16
More informationTypes of Rapid Transit
Types of Rapid Transit Light Rail Transit (LRT) Electric trains running along tracks in a rapidway separate from regular traffic. Bus Rapid Transit (BRT) Transit buses (regular and articulated) operating
More informationO-Train Confederation Line Stage 1
O-Train Confederation Line Stage 1 Presented to: Regional Public Works Commissioners of Ontario June 23, 2017 by Steve Cripps, Director, O-Train Construction The Need Ottawa s population is projected to
More informationThat an annual one-week curbside battery collection program BE REFERRED to the 2019 budget process for consideration.
Page 1 Subject: Curbside Battery Collection Report to: Waste Management Planning Steering Committee Report date: Monday, Recommendations That an annual one-week curbside battery collection program BE REFERRED
More informationOperating & Maintenance Cost Results Report
Operating & Maintenance Cost Results Report Prepared for: Hennepin County Regional Railroad Authority Prepared by: Connetics Transportation Group Under Contract To: Kimley-Horn and Associates FINAL June
More informationDEPUTATION TO THE COMMITTEE OF THE WHOLE of the TOWN OF THE BLUE MOUNTAINS. ANDREA MACECEK AND GLENN BIER for the RESIDENTS OF WOODLAND PARK ROAD
DEPUTATION TO THE COMMITTEE OF THE WHOLE of the TOWN OF THE BLUE MOUNTAINS ANDREA MACECEK AND GLENN BIER for the RESIDENTS OF WOODLAND PARK ROAD MAY 15, 2017 Woodland Park Road residents and the Board
More informationSEPULVEDA PASS CORRIDOR
SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000
More informationCEDAR AVENUE TRANSITWAY Implementation Plan Update
CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,
More informationTask Force Meeting January 15, 2009
Task Force Meeting January 15, 2009 Study Update August 14 th Task Force Meeting Update on Traffic Projections and Financial Feasibility Study presented by Kane County and WSA staff The presentation summarized
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationFederal Gas Tax Program. Transportation Committee May 7, 2014
5.2 Federal Gas Tax Program Transportation Committee May 7, 2014 Federal Gas Tax Transfer Program Original head agreement signed in 2005 (Canada-BC-UBCM) Purpose: provide local governments with stable,
More informationItem No Halifax Regional Council June 21, 2016
P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. 14.2.2 Halifax Regional Council June 21, 2016 TO: Mayor Savage and Members of Halifax Regional Council SUBMITTED BY: Councillor Tim Outhit, Chair,
More informationCS File: Community Services Department E-1400
~OShawa. CS-12-69 Report To: From: Community Services Committee Item: Jag Sharma, Commissioner File: Community Services Department E-1400 Date of Report: CS-12-59 May 2, 2012 Date of Meeting: May 10, 2012
More informationDesignation of a Community Safety Zone in Honey Harbour in the Township of Georgian Bay
TO: FROM: Chair and Members Engineering and Public Works Committee Mark Misko, C.E.T. Manager, Roads Maintenance and Construction DATE: March 23, 2016 SUBJECT: REPORT NO: Designation of a Community Safety
More informationAn Asset Management Plan for Transit And Access Transit Fleet
Header Title ATTACHMENT 1 Building Better Transit: An Asset Management Plan for Transit And Access Transit Fleet 2 June 2016 Transit & Access Transit Fleet INTRODUCTION The Saskatoon Transit fleet is currently
More informationThe Regional Municipality of York. Purchase of Six Battery Electric Buses
1. Recommendations The Regional Municipality of York Committee of the Whole Transportation Services January 10, 2019 Report of the Commissioner of Transportation Services Purchase of Six Battery Electric
More informationDeveloping Toronto s Transit Network Plan to 2031
RE:EX16.1 Developing Toronto s Transit Network Plan to 2031 Executive Committee Meeting June 28, 2016 March 2016 City Council Direction SmartTrack: Approved SmartTrack/GO Regional Express Rail (RER) Integration
More informationTORONTO TRANSIT COMMISSION REPORT NO.
Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: October 24, 2012 SUBJECT: DOWNTOWN RAPID TRANSIT EXPANSION STUDY (DRTES) PHASE 1 STRATEGIC PLAN ACTION ITEM RECOMMENDATIONS
More informationDeveloping Toronto s Transit Network Plan to Public Information Meeting June 21, 2016
Developing Toronto s Transit Network Plan to 2031 Public Information Meeting June 21, 2016 March 2016 City Council Direction SmartTrack: Approved SmartTrack/GO Regional Express Rail (RER) Integration options
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Purchase Sixty (60) Low Floor Wheel-Trans Mini-Buses Date: September 5, 2017 To: From: TTC Board Chief Executive Officer Summary This report recommends
More informationMinistry of Transportation of Ontario's Off-Peak Deliveries Initiative and Noise By-law
Public Report To: From: Report Number: Corporate Services Committee Jacqueline Long, Interim Commissioner, Corporate Services Department & HR CORP-15-23 Date of Report: March 19, 2015 Date of Meeting:
More informationBackground Information for MPRB Community Advisory Committee for 2010 Southwest Light Rail Transit Project DEIS Comment Letter Section 2
Background Information for MPRB Community Advisory Committee for 2010 Southwest Light Rail Transit Project DEIS Comment Letter Section 2 1 2. SW LRT Corridor Overview Source: http://www.southwesttransitway.org/home.html
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF MAY 27, 2014
Item 3, Report No. 25, of the Committee of the Whole (Working Session), which was adopted without amendment by the Council of the City of Vaughan on May 27, 2014. 3 PROPOSED RESIDENTIAL PARKING SOLUTIONS
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationWhat We Heard Report - Metro Line NW LRT
What We Heard Report - Metro Line NW LRT by Metro Line NW LRT Project Team LRT Projects City of Edmonton April 11, 2018 Project / Initiative Background Name Date Location Metro Line Northwest Light Rail
More informationCITY CLERK. Warrants for All-Way Stop Sign Control and 40 km/h Maximum Speed Limits
CITY CLERK Clause embodied in Report No. 9 of the, as adopted by the Council of the City of Toronto at its Special Meeting held on July 30, 31 and August 1, 2002. 10 Warrants for All-Way Stop Sign Control
More informationTransit City Etobicoke - Finch West LRT
Delcan Corporation Transit City Etobicoke - Finch West LRT APPENDIX D Microsimulation Traffic Modeling Report March 2010 March 2010 Appendix D CONTENTS 1.0 STUDY CONTEXT... 2 Figure 1 Study Limits... 2
More informationREPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE
September 7, 2016 REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT ON COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE PURPOSE To update Council on Kamloops
More informationSales and Use Transportation Tax Implementation Plan
Sales and Use Transportation Tax Implementation Plan Transportation is more than just a way of getting from here to there. Reliable, safe transportation is necessary for commerce, economic development,
More informationJanice Fortunato Senior Director Business Partnerships
Janice Fortunato Senior Director Business Partnerships What are Megaprojects? They are large-scale projects distinguished by cost, complexity and the potential impact on the community. Collectively, these
More informationTroost Corridor Transit Study
Troost Corridor Transit Study May 23, 2007 Kansas City Area Transportation Authority Agenda Welcome Troost Corridor Planning Study Public participation What is MAX? Survey of Troost Riders Proposed Transit
More information4.0 SUMMARY OF ARTERIAL INTERSECTIONS CONGESTION ANALYSIS AND IMPROVEMENT CONCEPTS
4.0 SUMMARY OF ARTERIAL INTERSECTIONS CONGESTION ANALYSIS AND IMPROVEMENT CONCEPTS 4.1 SUMMARY The Arterial Intersection Congestion Analysis Report, dated May 29, 2012, was approved by the SR-91/I-605/I-405
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program
More informationNew Buck O Neil (U. S. 169) Crossing Benefit-Cost Analysis. Kansas City, Missouri
New Buck O Neil (U. S. 169) Crossing Benefit-Cost Analysis Kansas City, Missouri New Buck O Neil (U. S. 169) Crossing Benefit-Cost Analysis prepared for Kansas City, Missouri prepared by Burns & McDonnell
More informationAttachment 5 Eglinton West LRT Planning and Technical Update
Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to
More information1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS
1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS The Transit Committee recommends the adoption of the recommendations contained in the
More information6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION
June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More information4 COSTS AND OPERATIONS
4 COSTS AND OPERATIONS 4.1 INTRODUCTION This chapter summarizes the estimated capital and operations and maintenance (O&M) costs for the Modal and High-Speed Train (HST) Alternatives evaluated in this
More informationMississauga Transit 2009 Budget
Mississauga Transit 2009 Budget Budget Committee Presentation December 2, 2008 Revenue Ridership Forecasted 2008 Total Rides Including transfers 11% growth in the last 24 months Transit Service Area Business
More informationOATAC On March 14, 2018 the E-Bike Working Group met at the Northview Community Centre.
OATAC-18-10 E-bike Working Group Report March 23, 2018 On March 14, 2018 the E-Bike Working Group met at the Northview Community Centre. There were seven members of the O.A.T.A.C. in attendance. Councillor
More informationPacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis
Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Transit Coalition September 26, 2012 2 Study Area Pacific Electric Rightof-Way/West Santa Ana Branch (PEROW/ WSAB) extends
More information2030 Multimodal Transportation Study
2030 Multimodal Transportation Study City of Jacksonville Planning and Development Department Prepared by Ghyabi & Associates April 29,2010 Introduction Presentation Components 1. Study Basis 2. Study
More informationGTA West Corridor Planning and EA Study Stage 1
GTA West Corridor Planning and EA Study Stage 1 Draft Development Strategy Presentation to Peel Goods Movement Task Force April 8 2011 Study Areas 2 Unique Approach Unprecedented two-stage EA process:
More informationPROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis
TECHNICAL MEMORANDUM DATE: September 10, 2014 PROJECT 5861.03 NO: PROJECT: Wilkinson Road Corridor Improvement Traffic Management Planning Project SUBJECT: Traffic Analysis TO: Steve Holroyd - District
More informationFeasibility of Establishing an E85 Fuelling Station in Oshawa
(Oshawa Report To: From: Subject: Strategic Initiatives Committee Bob Duignan City Manager Item: SIC-09-54 File: B-1100-0082 Feasibility of Establishing an E85 Fuelling Station in Oshawa PUBLIC REPORT
More informationEnvironment and Infrastructure Services
Agenda Item 5 Staff Report for Committee of the Whole Meeting Department: Division: Subject: Environment and Infrastructure Services Environment Services Waste Collection Contract Purpose: To provide Council
More informationTRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury
TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury Open House Presentation January 19, 2012 Study Objectives Quantify the need for transit service in BWG Determine transit service priorities based
More informationTown of Londonderry, New Hampshire NH Route 28 Western Segment Traffic Impact Fee Methodology
Town of Londonderry, New Hampshire NH Route 28 Western Segment Traffic Impact Fee Methodology Prepared by the Londonderry Community Development Department Planning & Economic Development Division Based
More informationBUS RAPID TRANSIT (BRT) MISSISSAUGA SEGMENT IMPLEMENTATION PLAN
APPENDIX 1 CITY OF MISSISSAUGA BUS RAPID TRANSIT (BRT) MISSISSAUGA SEGMENT IMPLEMENTATION PLAN Executive Summary McCORMICK RANKIN May 2003 Introduction This executive summary highlights the findings and
More informationState Avenue Corridor Bus Rapid Transit (BRT)
State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!
More informationTransportation Committee Revised Project Scope and Cost Estimate. November 23, 2015
Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project
More informationCREATING CONNECTIONS IN THE CITY OF KITCHENER
CREATING CONNECTIONS IN THE CITY OF KITCHENER GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS KITCHENER CITY COUNCIL SEPTEMBER 25, 2017 CONGESTION
More informationEglinton East LRT Project Update and Next Steps
EX34.1 REPORT FOR ACTION Eglinton East LRT Project Update and Next Steps Date: May 7, 2018 To: Executive Committee From: Interim Deputy City Manager, Cluster B and Chief Planner and Executive Director,
More informationMemorandum of Understanding
Memorum of Understing Between The City of Lake Forest, Metra, Amtrak, Illinois Department of Transportation, Wisconsin Department of Transportation to Collaborate in Improving Passenger Motorist Safety
More informationITEM 13 - NOTICE May 20, 2009
ITEM 13 - NOTICE May 20, 2009 Notice of Proposed Amendment to the 2009 CLRP and FY 2010-2015 TIP to include the Closure of the I-395 Southbound Exit Ramp to 3rd Street NW, the Reconfiguration of the Southbound
More informationCity Council Report 915 I Street, 1 st Floor Sacramento, CA
City Council Report 915 I Street, 1 st Floor Sacramento, CA 95814 www.cityofsacramento.org File ID: 2018-00913 July 3, 2018 Consent Item 17 Title: Supplemental Agreement: Ramona Avenue Extension Project
More informationBusiness Advisory Committee. November 3, 2015
Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal
More informationMetro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner
Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning
More informationCREATING CONNECTIONS IN WATERLOO REGION
CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX
More informationEGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT)
WELCOME TO OUR PUBLIC OPEN HOUSE EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT) Preliminary Planning for a Transit Project Assessment Open House Martin Grove Road to Pearson International Airport September
More informationLocation Concept Plan Amendment Recommendation Approved 2011 Concept Plan
Valley Line West LRT Concept Plan Recommended Amendments Lewis Farms LRT Terminus Site Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan Lewis Farms LRT terminus site, 87 Avenue/West
More information4 YORK REGION TRANSIT COMPUTER AIDED DISPATCH/AUTOMATIC VEHICLE LOCATION SYSTEM FOR CONVENTIONAL TRANSIT BUSES - UPDATE
4 YORK REGION TRANSIT COMPUTER AIDED DISPATCH/AUTOMATIC VEHICLE LOCATION SYSTEM FOR CONVENTIONAL TRANSIT BUSES - UPDATE The Transit Committee recommends: 1. The presentation by Rajeev Roy, Manager, Transit
More informationMARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018
MARTA s blueprint for the future COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018 TODAY S AGENDA About MARTA Economic development/local impact More MARTA Atlanta program Program summary/timeline
More informationPLANNING, HOUSING AND COMMUNITY SERVICES Transportation Planning
REGION OF WATERLOO PLANNING, HOUSING AND COMMUNITY SERVICES Transportation Planning TO: Chair Wideman and Members of the Planning and Works Committee DATE: March 4, 2008 FILE CODE: D10-20/RT SUBJECT: RAPID
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationDraft Results and Open House
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi
More informationAppendix A-M Public Information Centre 4 Materials
Appendix A-M Public Information Centre 4 Materials NOTICE OF PUBLIC INFORMATION CENTRE #4 RAPID TRANSIT CORRIDORS MASTER PLAN ENVIRONMENTAL ASSESSMENT STUDY The City of London is entering a new chapter
More informationACTION: ESTABLISH LIFE-OF-PROJECT BUDGET FOR UP TO 100 NEW COMPO BUSES
QD Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net oplo OPERATIONS COMMITTEE June 16, 2011 SUBJECT: PURCHASE REPLACEMENT
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationTRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit
REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit TO: Members of Council DATE: June 15, 2011 FILE CODE: A02-30/PW SUBJECT: RECOMMENDED RAPID TRANSIT IMPLEMENTATION OPTION RECOMMENDATION:
More informationWelcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,
Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present
More informationThe ION Story. November 2015
The ION Story November 2015 Planning For The Future The Region of Waterloo has been planning for rapid transit for more than a decade ION will: Limit urban sprawl; ease traffic congestion Protect environmentally-sensitive
More informationDRAFT Subject to modifications
TREASURE COAST REGIONAL PLANNING COUNCIL M E M O R A N D U M DRAFT To: Council Members AGENDA ITEM 7A From: Date: Subject: Staff September 17, 2010 Council Meeting High Speed Rail Update Introduction The
More informationMidtown Corridor Alternatives Analysis. Policy Advisory Committee Meeting February 12, 2014
Midtown Corridor Alternatives Analysis Policy Advisory Committee Meeting February 12, 2014 Today s Agenda Introductions Outreach efforts and survey results Other updates since last meeting Evaluation results
More information