Chief Capital Management Officer s Report

Size: px
Start display at page:

Download "Chief Capital Management Officer s Report"

Transcription

1 Item 40 Chief Capital Management Officer s Report Construction Committee April 15,

2 Metro Gold Line Eastside Extension Project Update April Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro Gold Line $898.8 million On-Time/Within Budget Over 4.3 million Safe Work Hours Opened to the Public November 15, 2009 Gold Line 2

3 Metro Gold Line Eastside Extension Pomona/Atlantic Station Parking The 266-space parking structure opens to the public on April 16, MTA Media Relations will issue a press release announcing the opening to all media outlets with an emphasis in East Los Angeles, Montebello, Monterey Park and surrounding communities. Banners will be placed at the temporary parking lots directing Metro patrons to the new Atlantic Station parking structure, as the temporary parking lots will be closed after April 15, 2010 Gold Line 3

4 Metro Gold Line Eastside Extension Pedestrian Barrier Fencing Installation 1 st /Mission near the Mendez Learning Center 1 st Street between Lorena and Indiana Streets The installation of the 4 high steel picket pedestrian barrier fencing has been completed. 3 rd Street near the East LA Civic Center Gold Line 4

5 Metro Gold Line Eastside Extension End of Presentation Gold Line 5

6 Metro Orange Line Extension Project Update April 2010

7 Metro Orange Line Extension Four miles Busway and Bikeway Three routes with connection to Chatsworth Metrolink Station Four new stations Three Bridges Landscaping similar to Orange Line Budget $215.6 million Estimated completion summer 2012

8 Metro Orange Line Extension Design-Build Contract C0943: Issued Notice to Proceed to Brutoco Engineering & Construction, Inc. effective March 1, 2010 Continues to provide initial submittals Commenced design of busway, street crossings, stations and remaining bridges Staff and contractor have moved into Integrated Project Management Office

9 Metro Orange Line Extension Complete construction of new privacy fence at Chatsworth Mobil Home Park in May 2010 SCRRA to substantially complete modifications of rail signals in April 2010 LADWP to complete temporary power relocation at Chatsworth Station in April 2010 Removed 26 billboard signs. Relocated 50 businesses. Last 2 relocations by end of April 2010 Finalizing Union Pacific Easement agreement

10 Metro Orange Line Extension Rail signal modification work by SCRRA s contractor at Chatsworth Station

11 I-405 Sepulveda Pass Widening Project Project Update - April

12 I-405 Sepulveda Pass Widening Project Project Update - April 2010 Design/Build Project to close the HOV Lane gap between the 10 Freeway and 101 Freeway 10 Miles of freeway work North bound Southbound Lane Standardization (2.5 Miles - North and South ends) Widening of 12 Bridge Structures 8 Replacement Ramp Structures 3 Full Bridge Replacements Reconstruct 17 on/off ramps 18 Miles of Retaining Wall & Sound Wall $1.034 Billion Project Budget Estimated Completion

13 I-405 Sepulveda Pass Widening Project Status Current available funds are $372M Design Build Contractor Kiewit Notice to Proceed occurred June 2, 2009 Project Commencement August 31, 2009 IPO Staffing levels (end of October 2009) Kiewit 115 (+) HNTB (Kiewit's designer) 140 (+) MTA /CT 40 (+) Baseline schedule approved January 20 13

14 I-405 Sepulveda Pass Widening Project Summary Schedule 14

15 I-405 Sepulveda Pass Widening Project Funding Plan (in $ Million) Source Programmed Available Expended Unexpend. Remaining State TCRP $90.0 $42.0 $42.0 -* $48.0 State CMIA $ $614.0 Federal SAFETEA-LU $117.0 $ $ Federal ARRA $189.9 $ $ Federal RSTP $10.1 $ $10.1* - Prop C 25% $13.0 $13.0 $1.6 $9.8 - TOTALS $1,034.0 $372.0 $117.8 $252.6 $662.0 * $10.1 million currently available for termination costs; the options for securing the balance of $5.9 million include: 1. Private Placement Bonds 2. LONP against $48.0 million of future TCRP 3. Reserve $6.0 million out of Prop 1B Bond 4. Caltrans Statewide Highway Program Funding 15

16 I-405 Sepulveda Pass Widening Project Status Field work: Pothole work for design will be completed in mid-may. Drainage CCTV and cleaning is on-going and expected to be completed by the end of April Re-stripe of the N/B 405 freeway is now completed. Re-stripe of the S/B 405 will start in one week and will take 16 days to complete the work. Saw-cut and Grinding of the existing pavement will be completed end of May. 16

17 I-405 Sepulveda Pass Widening Project Status Field work: K-Rail installation is scheduled tentatively to start this week and will continue for two (2) months Sunset Bridge demo prep work is tentatively scheduled to start by mid-may and the actual bridge demo will be the end of April Sewer relocation at VA is scheduled to start April 19, 2010 Pile driving work for Wilshire Bridge 6A (SB 405 to EB Wilshire will begin May 03, 2010) Utility under-grounding work will begin later this month and will be completed in one (1) month. Under grounding of DWP overhead power lines on Sepulveda Blvd. between Montana Ave. and Sunset Blvd., started in March. Church Lane widening (between Sunset Blvd. and Sepulveda Blvd.) planned to occur in April. Sunset Bridge demolition (half at a time) planned to occur in May. 17

18 I-405 Sepulveda Pass Widening Project Status Field work: (cont d) MSE Panel fabrication began mid-march, 775 panels fabricated Soil nail wall 1836, 1992, and 2004 are scheduled to start May 1 st Design: HNTB Design continues Quality System development continues Over-the-shoulder reviews continue 18

19 I-405 Sepulveda Pass Widening Project Status Community Activities: Held meetings with 23 Homeowners in Westwood Hills to update on Sepulveda retaining wall and on individual properties. Coordinated Elected Official Briefing, monthly Community Advisory Committee (CAC) meeting and a quarterly meeting. Also, additional meetings with The Getty Center, Santa Monica Mountain Conservancy, LADWP, Bus Operations, Westwood Recreation Center and Los Angeles Homeless Service Authority. 19

20 I-405 Sepulveda Pass Widening Project Status Community Activities: (cont d) Distributed four construction notices regarding partial lane closures, CCTV drain work, K-rail placement and potholing along Sepulveda (between Montana and Sunset). Coordinated construction activities with 25 residents. Attended & presented to: Sherman Oaks Home-Owners Association Sherman Oaks Neighborhood Watch Mulholland Education Corridor Association Valley Vista Home-Owners Association 20

21 I-405 Sepulveda Pass Widening Project Status Community Activities: (cont d) Attended & presented to: Bel Air Crest Masters Association Board of Directors West LA Bureau of Traffic Brentwood Community Council UCLA Began a social media campaign: Maintained the project Facebook page with 500 friends Maintained the project Nixle account Tweeted daily about construction activities 21

22 I-405 Sepulveda Pass Widening Project Status City of Los Angeles Working on a revised master cooperation agreement Refining the submittal review/design coordination process Continued work on Reversible Lane project coordination with City of LA (COLA) County of Los Angeles Continued work on resolving Department of Public Work s design comments 22

23 I-405 Sepulveda Pass Widening Project Status Potential issues and path forward: Westwood Hills Task Force Tolling Agreement to avoid a lawsuit Project staff in negotiations with the Westwood Hills Task Force regarding the impact of realigning Sepulveda Blvd and impacts to adjacent residential properties. A mitigation plan has been presented and an agreement is anticipated by April of MWD 96 waterline Kiewit Pacific submitted a Value Engineering (VE) proposal to realign the freeway that would allow the MWD water line to remain in place. The VE is presently being reviewed by project staff. 23

24 I-405 Sepulveda Pass Widening Project Status Potential issues and path forward: (cont d) GSA (Federal Building at Wilshire) Metro continues to coordinate with GSA on utility identification and location; continued clarification of property and project alignment. Kiewit Pacific continued work on design of ramp bridges in this area. County of L.A. 12x12 Drainage Structure Kiewit has been developing options for protect in place alternatives for the Box; Metro is asking for solutions that include Box Relocation and/or Replacement. The responsibilities belong to the Contractor. The path forward for the 12x12 box between Constitution Ave. and Moraga Dr., is to be left in place and designed around and protected in place. May want to explain the path forward in your area; it is relocate foundation. 24

25 Expo Line Transit Project Exposition Light Rail Transit Project Monthly Project Status Update April 15,

26 Phase 1 Expo Line Transit Project Major Issues Project Status Schedule Contractor s latest schedule shows a 58-week project delay Although there are numerous areas of work that are behind schedule, the critical activities continue to be: La Cienega Bridge Ballona Creek Bridge Farmdale Crossing There are a number of activities that could result in further delay Changes to the Farmdale Avenue grade crossing Blue Line Tie-in S&I Facility Installation of Automatic Train Protection

27 Expo Line Transit Project Expo Phase 1 Delay Impacts Blue Line Tie-In 7 mo delay (Metro Enhancements) Ven/Rob Aerial Structure & Station 19 mo delay (Authority) La Cienega Aerial Structure 13 mo delay (DWP) Dorsey High School 4-18 mo delay (CPUC) I-110 Bridge 9 mo delay (Caltrans) LA Trade Tech 10 mo delay (CPUC) Automatic Train Protection 10 mo delay (Metro) Storage & Inspection Facility 13 mo delay (Metro)

28 Phase 1 Expo Line Transit Project Major Issues (cont.) Project Budget Project Status The awarded construction packages are currently within budget There are a number of areas that pose significant risk to the budget Project Delays Venice Robertson Aerial Station Foshay Safety Enhancements Changes to the Farmdale Avenue grade crossing Blue Line Tie-in S&I Facility Professional Services Third Parties Additional changes to Project Scope Installation of Automatic Train Protection

29 Phase 1 Expo Line Transit Project Construction Progress Flower Adams Overcrossing

30 Phase 1 Expo Line Transit Project Construction Progress Installation of Fencing and Precast Concrete ADA Truncated Tiles at the Western Avenue Station

31 Phase 1 Expo Line Transit Project Construction Progress Removal of Falsework at the La Cienega Aerial Structure

32 Phase 1 Expo Line Transit Project Construction Progress MSE Walls From La Cienega Aerial Structure to Ballona Creek Bridge Structure

33 Expo Line Transit Project February 2010 Summary of Jobs Program Activities LOCAL JOBS PROGRAM KEY ACCOMPLISHMENTS Local residents worked a total of 35.7% of the construction work hours in February 2010 and a total of 25.1% of all construction work hours on the project to date. The contractor projects that they will meet the 30% goal of construction hours worked by local residents. Local residents comprised 30% of all workers on the project in February of the 477 workers utilized on the project in the month of February were local residents.

34 Phase 2 Expo Line Transit Project Project Status Design-Build Procurement Finalizing scope and contract for the 2 most qualified design-build firms to conduct Preliminary Engineering and compete for final design and construction Technical Design Kick-Off meeting was held on March 25 with both firms Notice to proceed (NTP) for PE will be issued in mid-april Anticipate completion of Preliminary Engineering in November 2010 Third Party Coordination/Outreach Met with City of Santa Monica to discuss project status and areas of concern Met with City of Los Angeles, City of Santa Monica and CPUC to discuss atgrade crossings on the bikeway Toured Kilroy properties located adjacent to project alignment to follow up on noise and vibration discussions

Transit Project Delivery Status Report. Significant Issues

Transit Project Delivery Status Report. Significant Issues Item 1 Transit Project Delivery Status Report Significant Issues Presented By K.N. Murthy Executive Director Construction Committee 1 I-405 Sepulveda Pass Closure Construction Committee I-405 Sepulveda

More information

I-405 Sepulveda Pass Improvements Project

I-405 Sepulveda Pass Improvements Project I-405 Sepulveda Pass Improvements Project Community Meeting November 15, 2012 1 Wilshire Segment Overview of Wilshire Segment There are a total of 23 bridges being constructed on this project; almost half

More information

30-Day Look Ahead Summary August 2011

30-Day Look Ahead Summary August 2011 Wilshire Segment 30-Day Look Ahead Summary August 2011 DWP and SCE Utility Relocation Sepulveda reduced to one lane in each direction, Constitution to Ohio, 9pm to 6am Westbound Wilshire reduced to one

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 44 Program Management Project Budget and Schedule Status Project Schedules* Project 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Expo Phase I Orange Line Extension I-405 Sepulveda

More information

I-405 Sepulveda Pass Improvements Project. Community Advisory Committee July 28, 2011

I-405 Sepulveda Pass Improvements Project. Community Advisory Committee July 28, 2011 I-405 Sepulveda Pass Improvements Project Community Advisory Committee July 28, 2011 1 Wilshire Segment 2 Wilshire Segment (National to Waterford) Ramp and Wall Construction at Sepulveda/Wilshire Intersection

More information

Click to edit Master text styles

Click to edit Master text styles I-405 Sepulveda Pass Improvements Project Quarterly Community Meeting November 17, 2011 1 Wilshire Segment 2 Quarterly Community Meetings 2012 Month Meeting(s) February 16 May 17 Quarterly Quarterly August

More information

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition Countdown to the Closure Extended 3-Hour Closure of I-40 Freeway Between U.S. 0 and I-0 Planned in Mid-July for Mulholland Bridge Demolition Work Los Angeles, Calif. Plan Ahead, Avoid The Area, Or Stay

More information

I-405 Sepulveda Pass Improvements Project

I-405 Sepulveda Pass Improvements Project I-405 Sepulveda Pass Improvements Project 26, 2012 Click to edit Master title January style Community Advisory Committee 1 Community Meeting Schedule for 2012 26-Jan CAC, Final Meeting Feb 22-Mar Community

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014 Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway Update

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Laura Cornejo, DEO Regional Planner Regional Operator Metro is LA County s Regional Builder/Funder Rail Bus Service (Metro/Muni/Local)

More information

Exposition Light Rail Transit Project

Exposition Light Rail Transit Project Exposition Light Rail Transit Project Project Status Update Meeting West End Corridor Segment C Culver City Senior Center May 27, 2010 Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles

More information

Pomona Rotary December 19, 2017

Pomona Rotary December 19, 2017 Pomona Rotary December 19, 2017 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million; taking

More information

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011 Project Status Update Meeting Project Status Update Meeting Holman United Methodist Church January 27, 2011 Phase 1 Project Description Phase 1 from Downtown Los Angeles to Culver City: 8.6 mile corridor

More information

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate

More information

Sepulveda Pass Corridor Systems Planning Study Update

Sepulveda Pass Corridor Systems Planning Study Update Los Angeles County Metropolitan Transportation Authority Sepulveda Pass Corridor Systems Planning Study Update June 20, 2012 Measure R Transit Corridors One of 12 Measure R Transit Corridors approved by

More information

quarterly project status report

quarterly project status report HAYVENHURST I-405 I-405 Sepulveda Pass Pass Improvements Widening Project BURBA CHANDLER VENTURA FWY MAGNOLIA quarterly project status report BALBOA LIBBIT MAGNOLIA HASKELL 405 101 VAN NUYS BL RIVERSIDE

More information

quarterly project status report

quarterly project status report HAYVENHURST I-405 I-405 Sepulveda Pass Pass Improvements Widening Project BURBA CHANDLER VENTURA FWY MAGNOLIA quarterly project status report BALBOA LIBBIT MAGNOLIA HASKELL 405 101 VAN NUYS BL RIVERSIDE

More information

Phase 2 Exposition Metro Line Project

Phase 2 Exposition Metro Line Project Phase 2 Exposition Metro Line Project Monthly Project Status Report February 2014 TABLE OF CONTENTS PHASE 2 EXPO LINE PROJECT STATUS TABLE OF CONTENTS... 2 Phase 2 Exposition Metro Line Construction Authority

More information

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site Project Scoping Report Appendix B Project Web Site APPENDIX B Project Web Site WESTSIDE EXTENSION TRANSIT CORRIDOR STUDY February 4, 2008 News and Info of 1 http://metro.net/projects_programs/westside/news_info.htm#topofpage

More information

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014 Expo Line Project Westside/Central Metro Service Council November 2014 2 Expo Line Project Description Phase 2 Expo Line from Culver City to Santa Monica: 6.6 mile corridor 7 new Stations 64,000 Daily

More information

CITY OF BEVERLY HILLS STAFF REPORT

CITY OF BEVERLY HILLS STAFF REPORT Meeting Date: July 7, 2011 To: From: Subject: CITY OF BEVERLY HILLS STAFF REPORT Honorable Mayor & City Council Pamela Mottice Muller, Director of Emergency Management 405 Closure Attachments: 1. 1-405

More information

AIRPORT HAYVENHURST HAYVENHURST MANDEVILLE CANYON BRENTWOOD SANTA MONICA CARLYLE 20TH 17TH 17TH 14TH MONTANA 11TH LINCOLN 7TH 7TH WILSHIRE

AIRPORT HAYVENHURST HAYVENHURST MANDEVILLE CANYON BRENTWOOD SANTA MONICA CARLYLE 20TH 17TH 17TH 14TH MONTANA 11TH LINCOLN 7TH 7TH WILSHIRE HAYVENHURST I-405 I-405 Sepulveda Pass Pass Improvements Widening Project BURBA CHANDLER VENTURA FWY MAGNOLIA quarterly project status report BALBOA LIBBIT MAGNOLIA HASKELL 405 101 VAN NUYS BL RIVERSIDE

More information

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015

SOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015 SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment

More information

Metro Highway Program

Metro Highway Program Metro Highway Program ACEC November 2018 I-5 North HOV and Truck Lanes 14 miles of HOV lanes in both directions 2 miles of truck climbing lanes at the south end 7 bridge modifications at: Gavin Canyon

More information

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015 Meeting Agenda Phase 2 Construction Update Meeting Meeting Purpose and Format Construction Update Expo Bikeway

More information

Sepulveda Pass Corridor Systems Planning Study

Sepulveda Pass Corridor Systems Planning Study Los Angeles County Metropolitan Transportation Authority Sepulveda Pass Corridor Systems Planning Study Streets and Freeways Subcommittee January 17, 2013 1 Sepulveda Pass Study Corridor Extends for 30

More information

Develop ground transportation improvements to make the Airport a multi-modal regional

Develop ground transportation improvements to make the Airport a multi-modal regional Project Overview TRANSPORTATION IMPROVEMENTS WHAT ARE THE PROJECT GOALS? Transportation transportation hub. Develop ground transportation improvements to make the Airport a multi-modal regional Land Use

More information

Rolling Road (Route 638) Widening Project

Rolling Road (Route 638) Widening Project Rolling Road (Route 638) Widening Project From: 0.369 Mile North of Fairfax County Parkway (Route 286) To: Old Keene Mill Road (Route 644) State Project No. 0638-029-156, P104, R204, C504; UPC 5559 Public

More information

Business Advisory Committee. July 7, 2015

Business Advisory Committee. July 7, 2015 Business Advisory Committee July 7, 2015 1 Today s Topics Outreach Update TI #1 and 2: Target Field Station Connection to I-94: Recommendation 85 th Station Configuration 93 rd Station Configuration DEIS

More information

Corridor Management Committee. March 7, 2012

Corridor Management Committee. March 7, 2012 Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed

More information

Business Advisory Committee. November 3, 2015

Business Advisory Committee. November 3, 2015 Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal

More information

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015 Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project

More information

LAX Specific Plan Amendment Study. CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006

LAX Specific Plan Amendment Study. CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006 LAX Specific Plan Amendment Study CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006 Agenda Background on public planning process Regional planning update LAWA progress on settlement commitments

More information

Exposition Corridor Transit Project

Exposition Corridor Transit Project Exposition Corridor Transit Project Phase 2 Environmental Planning Community Meeting June 9, 2008 Exposition Corridor Transit Project Phase 2 AGENDA Remaining Grade Crossing Recommendations June 9, 2008

More information

congestion management program

congestion management program congestion management program 2550 Rail Vehicle Program March 2012 11-0319tr 2010 lacmta Q U A R T E R LY P R O J E C T S TAT U S R E P O R T 255O RAIL VEHICLE PROGRAM QUARTERLY PROJECT STATUS REPORT THE

More information

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015

Expo Light Rail Line. Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Expo Line Community Meeting Final Phase 2 Construction Update Santa Monica June 2015 Meeting Purpose and Format Meeting Purpose and Format The purpose of tonight s meeting is to: Provide a final update

More information

Chapter 7. Transportation Capital Improvement Projects. Chapter 7

Chapter 7. Transportation Capital Improvement Projects. Chapter 7 Chapter 7 Transportation Capital Improvement Projects Chapter 7 81 Chapter 7 Transportation Capital Improvement Projects Local Transportation Sales Tax Programs For over three decades, Santa Clara County

More information

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis Transit Coalition September 26, 2012 2 Study Area Pacific Electric Rightof-Way/West Santa Ana Branch (PEROW/ WSAB) extends

More information

SAN RAFAEL CITY COUNCIL AGENDA REPORT

SAN RAFAEL CITY COUNCIL AGENDA REPORT Agenda Item No: 8.b Meeting Date: December 19, 2016 Department: PUBLIC WORKS SAN RAFAEL CITY COUNCIL AGENDA REPORT Prepared by: Bill Guerin, Public Works Director City Manager Approval: File No.: 18.01.79

More information

Westside Subway Extension Final EIS/EIR. January 2011 Community Update Meetings

Westside Subway Extension Final EIS/EIR. January 2011 Community Update Meetings Westside Subway Extension Final EIS/EIR January 2011 Community Update Meetings Purpose of Tonight s Meeting Background information on planning to date Clarify Locally Preferred Alternative (LPA) under

More information

Project Status Update January 2017

Project Status Update January 2017 Project Status Update January 2017 1 What is the Purple Line? A new 16 mile east-west light rail line Operates mostly on the surface with 21 stations Connects New Carrollton in Prince George s County and

More information

Community Open Houses November 29 December 7, 2017

Community Open Houses November 29 December 7, 2017 Community Open Houses November 29 December 7, 2017 1 Community Open House Agenda 6:00 PM Open House 6:30-7:30 PM Presentation and Q&A 7:30-8:00 PM Open House Resumes after the presentation and Q&A Thank

More information

Key Project Elements Status Report

Key Project Elements Status Report Los Angeles County Metropolitan Transportation Authority Key Project Elements Status Report presented to the Corridor Advisory Committee August 18, 2016 Background Motion 22.1 elements are grouped into

More information

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE TUESDAY, DECEMBER 5, 2017 1 DISCUSSION TOPICS Update of Infrastructure Action Plan (IAP) o Sidewalk and Roadway projects

More information

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017 East San Fernando Valley Transit Corridor Information Session, October 10, 2017 1 Welcome and Meeting Purpose Introductions Metro Transit Corridors Planning Metro Real Estate Metro Community Relations

More information

Wentzville Parkway South Phase 2 & 2A

Wentzville Parkway South Phase 2 & 2A Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total

More information

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan Utility Undergrounding Strategies & Laguna Canyon Road Master Plan January 17, 2017 City Council Meeting 2 Agenda Progress since March 2016 Status of undergrounding and road widening between El Toro Rd.

More information

Study Area, Related Projects and Travel Markets

Study Area, Related Projects and Travel Markets Study Area, Related Projects and Travel Markets Study area and related projects Travel between Valley and Westside North San Fernando Valley BRT (Alignment TBD) East San Fernando Valley Transit Corridor

More information

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

SH 249 IN GRIMES COUNTY. Open House April 3, 2014 SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss

More information

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017

West Santa Ana Branch Transit Corridor. Informational Briefing Gateway Cities Service Council April 13, 2017 West Santa Ana Branch Transit Corridor Informational Briefing Gateway Cities Service Council April 13, 2017 Project Study Area 98 square miles 20 individual cities plus unincorporated LA County 1.2 million

More information

East San Fernando Valley Transit Corridor. Community Meetings April/May, 2012

East San Fernando Valley Transit Corridor. Community Meetings April/May, 2012 East San Fernando Valley Transit Corridor Community Meetings April/May, 2012 Meeting Format Sign-In/Open-House 6:00 P.M. to 6:30 P.M. Welcome/Presentation 6:30 P.M. to 7 P.M. Open-House 7:00 P.M. to 8:00

More information

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT FEBRUARY 2015

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT FEBRUARY 2015 SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT FEBRUARY 2015 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report February 2015 TABLE OF CONTENTS Project

More information

West Broadway Reconstruction/LRT Design. March 19, 2015

West Broadway Reconstruction/LRT Design. March 19, 2015 West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian

More information

Committee Report. Transportation Committee. Business Item No

Committee Report. Transportation Committee. Business Item No Committee Report Business Item No. 2015-280 Transportation Committee For the Metropolitan Council meeting of December 9, 2015 Subject: METRO Blue Line Extension (Bottineau Light Rail Transit) Revised Scope

More information

2.4 Build Alternatives

2.4 Build Alternatives Table 2-1. Future Transit Network Changes between No Build and TSM Alternatives Operator Route Group No. Route ID and Description Peak Headway (min) No Build Off-peak Headway (min) Peak Headway (min) TSM

More information

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016

Elected Officials Briefing North Metro Rail Line Update. November 10, 2016 Elected Officials Briefing North Metro Rail Line Update November 10, 2016 Dave Genova, RTD General Manager and CEO Five lines opening in 2016 Flatiron Flyer, Jan. 3 University of Colorado A Line, April

More information

Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019

Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019 Orange Line Bus Rapid Transit (BRT) Improvements San Fernando Valley Service Council April 3, 2019 1 Measure M Transit Projects in San Fernando Valley 2 1 2 Measure M Transit Projects Schedule Project

More information

Delta Kappa Gamma January 22, 2018

Delta Kappa Gamma January 22, 2018 Delta Kappa Gamma January 22, 2018 Los Angeles County s population will grow by 5.9% to 10.7 million by 2024 During that same period, the San Gabriel Valley will grow by 7.6% to more than 1.5 million;

More information

Metro Gold Line Eastside Extension Review Advisory Committee March 12, 2009

Metro Gold Line Eastside Extension Review Advisory Committee March 12, 2009 Review Advisory Committee March 12, 2009 6 Mile Alignment 1.7 Miles of Tunnel 8 Stations (6 At-grade & 2 Underground) Park & Ride Facility Direct Connection to the Pasadena Metro $898.8 million On-Time/Within

More information

DART Priorities Overview

DART Priorities Overview City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee

More information

US 67 WIDENING PROJECT

US 67 WIDENING PROJECT US 67 WIDENING PROJECT From Belt Line Rd. to I-20 History & Background The US 67 improvements from Belt Line Rd to I-20 were originally part of TxDOT s Southern Gateway project, studied as part of the

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Service/Safety Committee December 15, 2015 City Council December 21, 2015 Agenda Item: Amendment No. 1 to Engineering Services Agreement with CPS for City Project No. 7143,

More information

Why coordinate the Van Nuys and Sepulveda Pass project studies together?

Why coordinate the Van Nuys and Sepulveda Pass project studies together? Southern California's Leading Transit Advocacy Group P.O. Box 567 * San Fernando, CA 91341-0567 Voice: 818.362.7997 * Fax: 818.364.2508 www.transitcoalition.org The Transit Coalition (a project of LACBC)

More information

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1 Executive Summary Introduction The Eastside Transit Corridor Phase 2 Project is a vital public transit infrastructure investment that would provide a transit connection to the existing Metro Gold Line

More information

Balancing the Transportation Needs of a Growing City

Balancing the Transportation Needs of a Growing City Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract

More information

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012 Transit Coalition Meeting June 26, 2012 Measure R Projects 8 ½ mile light rail line from Exposition/Crenshaw Blvds. to Metro Green Line s Aviation/LAX station Six stations with two optional stations carried

More information

Janice Fortunato Senior Director Business Partnerships

Janice Fortunato Senior Director Business Partnerships Janice Fortunato Senior Director Business Partnerships What are Megaprojects? They are large-scale projects distinguished by cost, complexity and the potential impact on the community. Collectively, these

More information

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Letter EL652 City of Mercer Island. Page 1. No comments n/a Letter EL652 City of Mercer Island Page 1 No comments n/a Page 2 Response to comment EL652 1 Section 4.5.3 of the Final EIS presents the range of potential impacts of the project. This project also lists

More information

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009

SOUTH ACCESS TO THE GOLDEN GATE BRIDGE DOYLE DRIVE DOYLE DRIVE. Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 DOYLE DRIVE Doyle Drive Presentation Golden Gate Bridge Board Meeting July 24, 2009 Presentation Overview Introduction Project Acceleration Construction Contracts Construction Activities Lane and Road

More information

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)

W&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE

More information

One Gateway Plaza Los Angeles, CA

One Gateway Plaza Los Angeles, CA @ Metro Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 26 REVISED CONSTRUCTION COMMITTEE APRIL 16,2009 PROJECT: ACTION: 1-405 SEPULVEDA PASS WIDENING PROJECT ESTABLISH

More information

STH 60 Northern Reliever Route Feasibility Study Report

STH 60 Northern Reliever Route Feasibility Study Report #233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development

More information

Peninsula Corridor Electrification Project (PCEP)

Peninsula Corridor Electrification Project (PCEP) Peninsula Corridor Electrification Project (PCEP) Q2 Quarterly Update #13 October 1 December 31, 2017 JPB Board Meeting February 1, 2018 Agenda Item # 8b Electrification - Infrastructure Progression of

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 2/19/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

I-225 Rail Line Iliff and Florida Stations Information Meeting

I-225 Rail Line Iliff and Florida Stations Information Meeting I-225 Rail Line Iliff and Florida Stations Information Meeting May 15, 2013 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager Chris Hinton I-225 Rail Line Deputy Project

More information

Capital Improvement Plan Review

Capital Improvement Plan Review City of Manhattan Beach Public Works Department Fiscal Year 2014/2015 2018/2019 Capital Improvement Plan Review Community Meeting: April 10, 2014 Objectives Creating the Capital Improvement Plan Funding

More information

Purple Line Extension Section 1 Construction Community Meeting April 19, 2018

Purple Line Extension Section 1 Construction Community Meeting April 19, 2018 Purple Line Extension Section 1 Construction Community Meeting April 19, 2018 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Wilshire/Western Wilshire/La Brea Wilshire/Fairfax Wilshire/La

More information

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study

Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study Clearlake Road (State Road 501) Project Development & Environment (PD&E) Study FROM MICHIGAN AVENUE TO INDUSTRY ROAD BREVARD COUNTY, FLORIDA Financial Project ID No: 433605-1-22-01 Federal Aid Project

More information

Community Meetings June 2018

Community Meetings June 2018 Community Meetings June 2018 1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose

More information

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes 1 Welcome and Agenda Thank you for joining us! 6:00 pm Open House 6:30 pm Welcome & Presentation 7:00 pm Q&A 7:15 pm Open House Resumes 8:00 pm Meeting Concludes 2 Purpose of this Meeting Introduce project

More information

FREQUENTLY ASKED QUESTIONS

FREQUENTLY ASKED QUESTIONS THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on

More information

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017 US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master

More information

I-225 Rail Line 2 nd /Abilene Station Design Public Meeting

I-225 Rail Line 2 nd /Abilene Station Design Public Meeting I-225 Rail Line 2 nd /Abilene Station Design Public Meeting Jan. 29, 2014 FasTracks and I-225 Rail Line Update Chuck Culig I-225 Rail Line Project Manager 2 The RTD FasTracks Plan 122 miles of rail 18

More information

engineering phase and during the procurement of design build contracts.

engineering phase and during the procurement of design build contracts. CONSIDERATION OF ALTERNATIVES Below-grade trench alignment along Aviation Boulevard, adjacent to LAX south runways. miles. MOS-Century would extend from the Metro Exposition Line to the Aviation/ Century

More information

Project Scoping Open House Welcome

Project Scoping Open House Welcome Scoping Meeting Project Scoping Open House Welcome Alternatives Analysis (AA) and Draft Environmental Impact Statement/Draft Environmental Impact Report (DEIS/DEIR) Project Purpose Purpose of the Project

More information

Southern California - CHSRA

Southern California - CHSRA CALIFORNIA HIGH-SPEED RAIL Michael Gillam, Deputy Program Director Southern California - CHSRA CMAA - Construction Management Association of America July 19, 2012 CALIFORNIA S HIGH-SPEED TRAIN SYSTEM Largest

More information

Purple Line Light Rail P3 Project

Purple Line Light Rail P3 Project Purple Line Light Rail P3 Project TPB Meeting May 18, 2016 1 Topics General Project Overview The P3 Contract Details on The Successful Proposal 2 Recap of Purple Line P3 Events In November 2013 MTA initiated

More information

CPG is pleased to report the following accomplishments this quarter:

CPG is pleased to report the following accomplishments this quarter: MEMORANDUM To: From: Metrolinx Board of Directors Matthew Clark Chief Capital Officer (A), Capital Projects Group Date: February 7, 2019 Re: Capital Projects Group Quarterly Report Recommendation That

More information

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina Public Meeting & Open House July 23, 2013 Project Roadway Limits From: FM 1957 To: FM 471 MAP OR PHOTO Counties Bexar & Medina 1 I. Project History II. III. IV. Project Overview Project Alternatives Response

More information

Purple Line Extension Section 1 Construction Community Meeting January 17, 2019

Purple Line Extension Section 1 Construction Community Meeting January 17, 2019 Purple Line Extension Section 1 Construction Community Meeting January 17, 2019 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Fossils Project-wide Tunneling Wilshire/Western Wilshire/La

More information

Update on Transportation Activities in Fairfax County

Update on Transportation Activities in Fairfax County Update on Transportation Activities in Fairfax County Transportation Roundtable Dulles Area Transportation Association June 13, 2018 Tom Biesiadny, Director Fairfax County Continuing Project Implementation

More information

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007

Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 EAST-WEST CORRIDOR Challenges in a Post-Katrina Environment East-West Corridor Project Overview February, 2007 Presentation Agenda Project Overview / Purpose and Need Highway Component Transit Component

More information

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project

MOTION NO. M Preferred Alternative for the Puyallup Station Access Improvement Project MOTION NO. M2014 64 Preferred Alternative for the Puyallup Station Access Improvement Project MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee Board PROPOSED ACTION 8/14/14 8/28/14 Recommendation

More information

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013 East San Fernando Valley Transit Corridor TAC Briefing December 4, 2013 Overview Measure R Project Long Range Transportation Plan Reserves $170.1 Million 2018 Revenue Operations Date Coordination with

More information

Federal Way Link Extension

Federal Way Link Extension Federal Way Link Extension Draft EIS Summary Route & station alternatives and impacts Link Light Rail System Map Lynnwood Mountlake Terrace Lynnwood Link Extension Shoreline 14th Northgate 40 Northgate

More information

Mobility Management: Caltrain

Mobility Management: Caltrain Mobility Management: Caltrain Community Relations Committee October 4, 2017 Agenda Item 7 Presentation Outline Operating Statistics Ridership On-time Performance Fleet Reliability Capital Program Review

More information

SEPULVEDA PASS CORRIDOR

SEPULVEDA PASS CORRIDOR SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000

More information

Transportation Improvement Program (TIP) Candidate Project List for Public Review

Transportation Improvement Program (TIP) Candidate Project List for Public Review 2011-2014 Transportation Improvement Program (TIP) Candidate List for Public Review Table 1 Annual Listing Of Federal Aid Obligation For Federal Fiscal Year 2010 North Dakota s Number Transit 410083 Transit

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior

More information