1 Illinois Safety Program IDOT District ATSSA Workshop Roadway Departure & MASH DRAFT IDOT Facilitator: Dave Piper ATSSA Facilitator: Jim Thonn 1
2 Illinois Emphasis Area Priority Pyramid 2
3 Fatalities and Serious Injuries by EA ( ) 3
4 MASH and NCHRP 350 4
5 What is MASH? 5
6 IDOT Replacement and Upgrading For consistency, the same guidelines will be applied to all routes under Illinois Department of Transportation jurisdiction. 6
7 Replacement of Hardware (Proactive) Agencies are urged to establish a process to replace existing highway safety hardware that has not been successfully tested to NCHRP Report 350 or later criteria. (Proactive) 7
8 Upgrade Totaled Hardware Reactive 8 Agencies are encouraged to upgrade existing highway safety hardware to comply with the 2016 edition of MASH either when it becomes damaged beyond repair, or when an individual agency's policies require an upgrade to the safety hardware. (Reactive)
9 Lettings After December 31, 2017 W-beam Guardrail CURRENT DIRECTION Midwest Guardrail System (MGS) 9
10 Lettings After December 31, in. Min 42 in. Likely 10 Cast-in-Place Concrete Barrier CURRENT DIRECTION Single/Constant Slope??? NCHRP 20-07(395)
11 Lettings After June 30, W-Beam Terminals CURRENT DIRECTION Proprietary Pooled Fund Development
12 SoftStop End Terminal MSKT Drawing* *Source: IDOT Qualified Products Lists: 12
13 Lettings After December 31, Cable Barrier and Terminals CURRENT DIRECTION Proprietary Pooled Fund Development
14 Lettings After December 31, Crash Cushions CURRENT DIRECTION Proprietary
15 Lettings After December 31, Bridge Rails and Transitions CURRENT DIRECTION Single/Constant Slope NCHRP 20-07(395) MwRSF Transition and Buttress New Side Mount
16 Manufactured After December 31, Work Zone Devices Including Temporary Concrete Barrier Existing hardware may be used throughout its normal service life.
17 2017 Updated and New Standards 17
18 Standard Shoulder Inlet with Curb 18
19 Standard Steel Plate Beam Guardrail 19
20 Standard (NEW) Non-Blocked Steel Plate Beam Guardrail MAY NOT BE USED Behind a curb Within 25 ft. of a Type 5, 6, 6A, or 6B Within 12.5 ft. of a Type 1 Within 50 ft. of a Type 2 With post spacing other than 6 ft. 3 in. With wood posts With a flare 20
21 Standard Strong Post Guardrail Attached to Culvert 21
22 Standard Long-Span Guardrail Over Culvert 22
23 Standard (NEW) Weak Post Guardrail Attached to Culvert 23
24 Standard (NEW) Back Side Protection of Guardrail 24
25 Standard PCC/HMA Stabilization at Steel Plate Beam Guardrail 25
26 Standard Traffic Barrier Terminal, Type 2 26
27 Highway Standards , , Traffic Barrier Terminal, Type 6, 6A, 6B 27
28 Revised Procedures for Design, Plan Layout and Final Documentation of Traffic Barrier Terminal, Type 1 (Special) and Attached Guardrail 28
29 Design Length of Need as Usual 29 Suppose Length of Need = 200 ft. at a bridge.
30 Locate the Beginning of Length of Need of the Terminal to the Design Length of Need Point. 200 ft 25 ft 12.5 ft End of Parapet Assume: 1 The shortest length TBT T1 from the Qualified Products List. 2 The BLON is at 12.5 ft from the end of the terminal. Begin TBT T1 BLON End TBT T1 30
31 Locate any Fixed Connection Points 200 ft 36.9 ft 25 ft 12.5 ft End of Parapet End of Type 6 Begin TBT T1 BLON End TBT T1 31
32 Guardrail Connects the Terminal Ends 200 ft 36.9 ft 200 ft 36.9 ft -25 ft = ft 25 ft 12.5 ft Guardrail Plan Quantity End of Parapet End of Type 6 Begin TBT T1 BLON End TBT T1 32
33 Adjusting the Layout for the Selected Traffic Barrier Terminal(s) 200 ft ft ft 33 End of Parapet Suppose the Contractor chooses a different terminal than assumed in the plans. Its length of need begins at ft from Post 1. It provides ft length of need and this is a splice location. First attempt to place its BLON at the plan length of need point. Splice to Type 1 End of Type 1 (Post 1)
34 Adjusting the Layout for the Selected Traffic Barrier Terminal(s) 200 ft 36.9 ft ft ft End of Parapet End of Type 6 (Splice) The Type 6 terminal does not move. Plot it. Note that the Type 6 also ends at a splice location. Splice to Type 1 End of Type 1 (Post 1) 34
35 Adjusting the Layout for the Selected Traffic Barrier Terminal(s) 200 ft 36.9 ft ft ft ft End of Parapet End of Type 6 (Splice) How much guardrail is needed to meet the plan length of need point? = Splice to Type 1 End of Type 1 (Post 1) 35
36 New BDE Special Provision TRAFFIC BARRIER TERMINAL, TYPE 1 SPECIAL (BDE) Effective: January 1, 2017 Revise Article of the Standard Specifications to read: Traffic Barrier Terminal, Type 1 Special (Tangent) and Traffic Barrier Terminal, Type 1 Special (Flared). These terminals shall meet the testing criteria contained in either NCHRP Report 350 or MASH. In addition to meeting the criteria in one or both of these references, the terminals shall be on the Department s qualified product list. The terminal shall be installed according to the manufacturer s specifications. The beginning length of need point of the terminal shall be placed within 12 ft 6 in (3.8 m) of the length of need point shown on the plans. The terminal shall be delineated with a terminal marker direct applied. No other guardrail delineation shall be attached to the terminal section NOTE: No longer requires the Type 1 to provide 37.5 ft of length of need. Actual proprietary terminal length will be paid for. Qualified Product List will be updated to include this length.
37 Adjusting the Layout for the Selected Traffic Barrier Terminal(s) 200 ft ft 36.9 ft 125 ft ft ft End of Parapet End of Type 6 (Splice) The nominal length of guardrail is This could be rounded down to 125 ft or up to and meet the BDE Special Provision using standard panels. Let s round down, that s closer. Splice to Type 1 End of Type 1 (Post 1) 37
38 Adjusting the Layout for the Selected Traffic Barrier Terminal(s) Type 6 Steel Plate Beam Guardrail Type 1 1 EACH 125 FT 1 EACH 36.9 ft ft ft End of Parapet End of Type 6 (Splice) Splice to Type 1 End of Type 1 (Post 1) 38
39 Questions? 39
AASHTO Manual for Assessing Safety Hardware, AASHTO/FHWA Joint Implementation Plan Standing Committee on Highways September 24, 2015
AASHTO Manual for Assessing Safety Hardware, 2015 AASHTO/FHWA Joint Implementation Plan Standing Committee on Highways September 24, 2015 Full Scale MASH Crash Tests (NCHRP 22-14(02)) Conducted several
More informationImplementation of AASHTO s Manual for Assessing Safety Hardware (MASH) 2016
Implementation of AASHTO s Manual for Assessing Safety Hardware (MASH) 2016 Update from the Technical Committee on Roadside Safety Keith Cota, New Hampshire DOT MASH 2016 Overview Background Ballot Results/Dates
More information1962: HRCS Circular 482 one-page document, specified vehicle mass, impact speed, and approach angle for crash tests.
1 2 3 1962: HRCS Circular 482 one-page document, specified vehicle mass, impact speed, and approach angle for crash tests. 1973: NCHRP Report 153 16-page document, based on technical input from 70+ individuals
More informationCrash Testing Growth Common Roadside Hardware Systems Draft FHWA and AASHTO Requirements for Implementing MASH 2015
64 th Annual Illinois Traffic Safety and Engineering Conference October 14, 2015 Crash Testing Growth Common Roadside Hardware Systems Draft FHWA and AASHTO Requirements for Implementing MASH 2015 1 https://www.youtube.com/watch?feature
More informationGuide Rail Safety Symposium
Ministry of Transportation Guide Rail Safety Symposium MTO Provincial Roadside Safety Update Mark C. Ayton, P. Eng. Senior Engineer, Highway Design MTO Highway Standards Branch MTO Provincial Roadside
More informationSUMMARY CHANGES FOR NCHRP REPORT 350 GUIDELINES [NCHRP (02)] Keith A. Cota, Chairman Technical Committee on Roadside Safety June 14, 2007
SUMMARY CHANGES FOR NCHRP REPORT 350 GUIDELINES [NCHRP 22-14 (02)] Keith A. Cota, Chairman Technical Committee on Roadside Safety June 14, 2007 BACKGROUND Circular 482 (1962) First full scale crash test
More informationMETAL BEAM GUARDFENCE TRANSITION AND END TREATMENT IDENTIFICATION GUIDE
2016 TxDOT Design Division METAL BEAM GUARDFENCE TRANSITION AND END TREATMENT IDENTIFICATION GUIDE A guide to help TxDOT employees identify metal beam guardfence transitions and end treatments for the
More informationRoadside Safety MASH
Ministry of Transportation MEA 2016 ANNUAL WORKSHOP AND GENERAL MEETING Roadside Safety MASH MTO Design & Contract Standards Office Highway Standards Branch November 24, 2016 Roadside Safety - MASH Highway
More informationMASH 2016 Implementation: What, When and Why
MASH 2016 Implementation: What, When and Why Roger P. Bligh, Ph.D., P.E. Senior Research Engineer Texas A&M Transportation Institute June 7, 2016 2016 Traffic Safety Conference College Station, Texas Outline
More informationMedian Barriers in North Carolina
Median Barriers in North Carolina AASHTO Subcommittee on Design - 2006 June 13-16, 2006 Jay A. Bennett North Carolina DOT State Roadway Design Engineer Brian Murphy, PE Traffic Safety Engineer Safety Evaluation
More informationGuardrail/Bridgerail Recommendations for Very Low Volume Local Roads in Kansas
Guardrail/Bridgerail Recommendations for Very Low Volume Local Roads in Kansas MINK Conference September 20, 2017 Ronald J. Seitz, P.E. and Tod Salfrank The Problem The Local Road System in Kansas is Very
More informationMaine Turnpike Authority
Company Name Total Bid Amount CPM Constructors - Freeport, ME $1,309,765.25 Scott Construction Corporation - Portland, ME $1,528,840.00 Wyman & Simpson Inc. - Richmond, ME $1,674,845.00 Page 1 of 10 CPM
More informationWork Zone Safety Initiatives and Research Efforts. Irene Soria Safety Evaluation Engineer Illinois Department of Transportation Safety Engineering
Work Zone Safety Initiatives and Research Efforts Irene Soria Safety Evaluation Engineer Illinois Department of Transportation Safety Engineering TES Conference - October 17 th, 2012 Outline Work Zone
More informationVULCAN BARRIER TL-3 GENERAL SPECIFICATIONS
VULCAN BARRIER TL-3 GENERAL SPECIFICATIONS I. GENERAL A. The VULCAN BARRIER TL-3 (VULCAN TL-3) shall be a highly portable and crashworthy longitudinal barrier especially suited for use as a temporary barrier
More informationDISTRIBUTION: Electronic Recipients List TRANSMITTAL LETTER NO. (15-01) MINNESOTA DEPARTMENT OF TRANSPORTATION. MANUAL: Road Design English Manual
DISTRIBUTION: Electronic Recipients List MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards Unit ISSUED BY: Office of Project Management and Technical Support TRANSMITTAL LETTER NO.
More informationCUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS TRAFFIC CONTROL STANDARDS
CUYAHOGA COUNTY DEPARTMENT OF PUBLIC WORKS TRAFFIC CONTROL STANDARDS Supplement to O.D.O.T. TRAFFIC ENGINEERING MANUAL November 26, 2013 Revisions to the June 22, 2011 edition are noted by a vertical line
More informationSGR52 TOP-MOUNTED WEAK-POST GUARDRAIL ATTACHED TO CULVERT PLAN VIEW ELEVATION VIEW DETAIL B DETAIL A SHEET NO. DATE: 37 1/2" 953 (TYP) 150" 3810
PLAN VIEW C 150" 3810 37 1/2" 953 (TYP) A B C 8-FBB01 RWB01a FWR01 RWM04a FWR01 RWB01a RWM04a PSF01 FBX08a PSF01 FBX08a DETAIL A DETAIL B 1 of 7 12/5/2016 INTENDED USE The Top-Mounted Weak-Post Guardrail
More informationWentzville Parkway South Phase 2 & 2A
Wentzville Parkway South Phase 2 & 2A Sponsor Wentzville Project No. RB18-000034 Project Type New Road TOTAL FUNDING Phase 2 Total County Sponsor Federal $10,000,000 $8,000,000 $2,000,000 $0 Phase 2A Total
More informationMaine Turnpike Authority
Company Name Total Bid Amount R J Grondin & Sons - Gorham, ME $1,436,720.00 Shaw Brothers Construction, Inc. - Gorham, ME $1,476,398.83 Pratt & Sons, Inc. - Minot, ME $1,733,615.00 Page 1 of 13 R J Grondin
More informationSchedule 18 (Technical Requirements) DBFO Agreement EXECUTION VERSION APPENDIX B - SELECT DEPARTMENT STANDARD DRAWINGS AND REFERENCE TABLES
Schedule (Technical Requirements) DBFO Agreement EXECUTION VERSION APPENDIX B - SELECT DEPARTMENT STANDARD DRAWINGS AND REFERENCE TABLES Schedule (Technical Requirements) DBFO Agreement EXECUTION VERSION
More informationTRACC. Trinity Attenuating Crash Cushion
TRACC Trinity Attenuating Crash Cushion CSP Pacific Business Unit of Fletcher Concrete & Infrastructure Limited 306 Neilson Street Onehunga, Auckland Phone: (09) 634 1239 or 0800 655 200 Fax: (09) 634
More informationManual for Assessing Safety Hardware
American Association of State Highway and Transportation Officials Manual for Assessing Safety Hardware 2009 vii PREFACE Effective traffic barrier systems, end treatments, crash cushions, breakaway devices,
More informationChapter 4 COLLISION REDUCTION PROGRAM
Chapter 4 COLLISION REDUCTION PROGRAM Table of Contents 4.0 Background...4-3 4.1 Safety Improvement Projects SHOPP 201.010 Program...4-3 4.1.1 Spot Improvements..4-3 4.1.2 Wet Improvements...4-4 4.1.3
More informationMidwest Guardrail System Without Blockouts
Duplication for publication or sale is strictly prohibited without prior written permission of the Transportation Research Board Paper No. 13-0418 Midwest Guardrail System Without Blockouts by John D.
More informationJuly 17, In Reply Refer To: HSSD/B-176A
July 17, 2008 1200 New Jersey Avenue, SE. Washington, DC 20590 In Reply Refer To: HSSD/B-176A Mr. John Addy Hill & Smith Springvale Business and Industrial Park Bliston, Wolverhampton, West Midlands, UK,
More informationCHANGE LIST for MDOT Traffic and Safety Geometric Design Guides. May 23, 2017: The following update was made to the web site.
CHANGE LIST for MDOT Traffic and Safety Geometric Design Guides Note: Located at https://mdotjboss.state.mi.us/tssd/tssdhome.htm May 23, 2017: The following update was made to the web site. GEO-650-D Flares
More informationJune 27, In Reply Refer To: HSSD/B-176
June 27, 2008 1200 New Jersey Avenue, SE. Washington, DC 20590 In Reply Refer To: HSSD/B-176 Mr. John Addy Hill & Smith Springvale Business and Industrial Park Bliston, Wolverhampton, West Midlands, UK,
More informationPN SoftStop. Revision A June End Terminal. Product Description Assembly Manual
PN 620237 SoftStop End Terminal Product Description Assembly Manual SoftStop End Terminal Product Description Assembly Manual 2525 Stemmons Freeway Dallas, Texas 75207 Important: This Manual is to be used
More informationEvaluating The Relevancy Of Current Crash Test Guidelines For Roadside Safety Barriers On High Speed Roads
Evaluating The Relevancy Of Current Crash Test Guidelines For Roadside Safety Barriers On High Speed Roads Connie Xavier Dominique Lord Chiara Dobrovolny Roger Bligh TRB 1 st International Roadside Safety
More informationMaine Turnpike Authority
Company Name Total Bid Amount Liddell Brothers, Inc. - Halifax, MA $1,590,213.00 Northeast Traffic Control Services, Inc. - Plymouth, MA $1,932,117.00 Page 1 of 5 Liddell Brothers, Inc. Halifax, MA 202.2061
More informationKANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007
07-08001 Sheet 1 of 2 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007 SECTION 805 WORK ZONE TRAFFIC CONTROL AND SAFETY TYPICAL TRAFFIC CONTROL, 2-LANE
More informationSMART CUSHION INNOVATIONS
SMART CUSHION The World s Only Speed-Dependent Crash Attenuators SMART CUSHION INNOVATIONS MASH AND NCHRP 350 APPROVED The only attenuator that is tested to MASH and NCHRP 350 Marketed and Distributed
More informationMaine Turnpike Authority
Company Name Total Bid Amount Shaw Brothers Construction, Inc. - Gorham, ME $659,771.50 R J Grondin & Sons - Gorham, ME $690,828.50 Gendron & Gendron - Lewiston, ME $753,187.00 Gordon Contracting - Sangerville,
More informationMedian Barriers in North Carolina -- Long Term Evaluation. Safety Evaluation Group Traffic Safety Systems Management Section
Median Barriers in North Carolina -- Long Term Evaluation Safety Evaluation Group Traffic Safety Systems Management Section Background In 1998 North Carolina began a three pronged approach to prevent and
More information800 Access Control, R/W Use Permits and Drive Design
Table of Contents 801 Access Control... 8-1 801.1 Access Control Directives... 8-1 801.2 Access Control Policies... 8-1 801.2.1 Interstate Limited Access... 8-1 801.2.2 Limited Access... 8-1 801.2.3 Controlled
More informationAASHTO Policy on Geometric Design of Highways and Streets
AASHTO Policy on Geometric Design of Highways and Streets 2001 Highlights and Major Changes Since the 1994 Edition Jim Mills, P.E. Roadway Design Office 605 Suwannee Street MS-32 Tallahassee, FL 32399-0450
More informationPARAPETS / RAILS / MEDIANS / SIDEWALKS TABLE OF CONTENTS CHAPTER 25
TABLE OF CONTENTS CHAPTER 25 FILE NO. TITLE DATE TABLE OF CONTENTS AND INTRODUCTION 25.TOC-1 Table of Contents Chapter 25... 28Dec2016 25.00 Introduction Chapter 25... 28Dec2016 VDOT STANDARD PARAPETS
More informationPARAPETS / RAILS / MEDIANS / SIDEWALKS TABLE OF CONTENTS CHAPTER 25
TABLE OF CONTENTS CHAPTER 25 FILE NO. TITLE DATE TABLE OF CONTENTS AND INTRODUCTION 25.TOC-1 Table of Contents Chapter 25... 08Aug2018 25.00 Introduction Chapter 25... 03May2018 VDOT STANDARD PARAPETS
More informationsafedirection.com.au Ref: PM 017/02
DISTRIBUTOR 0 Product Manual Ref: PM 017/02 Table of Contents 1.0 Introduction... 3 2.0 The... 3 3.0 How the Functions... 4 4.0 Crash Test Performance... 4 5.0 Characteristics of Terminals... 5 5.1 Gating
More informationNortheast Autonomous and Connected Vehicle Summit
Northeast Autonomous and Connected Vehicle Summit June 12, 2018 Cathie Curtis, Director, Vehicle Programs AAMVA 1 1 Founded in 1933, the American Association of Motor Vehicle Administrators (AAMVA) represents
More informationA MASH Compliant W-Beam Median Guardrail System
0 0 0 0 0 A MASH Compliant W-Beam Median Guardrail System By A. Y. Abu-Odeh, R. P. Bligh, W. Odell, A. Meza, and W. L. Menges Submitted: July 0, 0 Word Count:, + ( figures + tables=,000) =, words Authors:
More informationAdvances in Simulating Corrugated Beam Barriers under Vehicular Impact
13 th International LS-DYNA Users Conference Session: Automotive Advances in Simulating Corrugated Beam Barriers under Vehicular Impact Akram Abu-Odeh Texas A&M Transportation Institute Abstract W-beam
More informationSafety Barrier System Conditions
Safety Barrier System Conditions MOBILE BARRIERS MBT-1 Steel Safety Barrier - Temporary The conditions for use of the MOBILE BARRIERS MBT-1 Steel Safety Barrier Temporary on the New South Wales classified
More informationTxDOT Representative
This guide was sponsored by the Federal Highway Administration (FHWA), under FHWA Contract DTFH61-10-D- 00021, Roadside Safety Systems Installers and Designers Mentor Program. The following individuals
More informationWorksite Safety Update Promoting safety in road construction
Worksite Safety Update Promoting safety in road construction No 116 February 2012 In this Edition: Temporary Safety Barrier Developments Page 1 Internal Traffic Control Plans for Improved Site Safety Page
More informationCreated by: St. Louis County
Created by: Victor Lund, PE Traffic Engineer St. Louis County Ken Johnson, PE, PTOE State WZ, etc. MnDOT Why do workers want speed limits? How effective are speed limits in work zones? New legislation
More informationPERFORMANCE ACTIVITY 603 SIGNS
PERFORMANCE ACTIVITY 603 SIGNS WORK DESCRIPTION 3 WORK DESCRIPTION 4 WORK DESCRIPTION 6 New Install Maintenance / Replace Temporary 603 SIGNS ACTIVITY DESCRIPTION Install new signs and maintain and replace
More informationSection 6H.01 Typical Applications
December 27, 2010 Draft Page 6H-1 Section 6H.01 Typical Applications Support: 01 Whenever the acronym TTC is used in this Chapter, it refers to temporary traffic control. 02 The needs and control of all
More informationAPPENDIX A Basis of Design and Design Criteria Memorandum
APPENDIX A Basis of Design and Design Criteria Memorandum Job No: Y01-500 Files are stored in: Engineering / Client / Yolo/Y01500 Buckeye and Rumsey/Rumsey CR 41 over Cache Creek, CAD files stored in:
More informationS T A T E O F M I N N E S O T A D E P A R T M E N T O F T R A N S P O R T A T I O N DATE : 02/27/06 PAGE : 1 TABULATION OF BIDS
PAGE : 1 NUMBER OF DAYS: 63 BRIDGE COUNT : 9 CONTRACT DESCRIPTION : BITUMINOUS OVERLAY & BRIDGE APPROACH PANEL REPLACEMENT CONTRACT LOCATION: LOCATED ON TH 90 FROM 0.8 MILE WEST OF THE BLUE EARTH RIVER
More informationEMERGENCY ACCESS POLICY
Cowlitz 2 Fire & Rescue Policies and Operating Guidelines Policy: EMERGENCY ACCESS POLICY Number Effective Date Approved and Issued: 4001 8/28/02 8/28/02 1.0 REFERENCE 23 CFR Part 650 Subpart C Code of
More informationDELINEATOR REFERENCE POINT 200' TYPICAL SPACING (YELLOW DELINEATORS) END OF MERGE LANE TAPER DELINEATOR REFERENCE POINT
200' TYP. 0' < EACH SIDE BOTH ROADWAYS END OF MERGE LANE TAPER TYPICAL FOR ALL 2-LANE MERGES EXCEPT WHERE THERE IS A MERGE FROM THE RIGHT AND NO OFFSET IN THE THROUGH LANES END OF MERGE LANE TAPER 200'
More informationHigh Tension Cable Barrier
High Tension Cable Barrier (and Rumble Strips) Practices & Guidelines 2017 Tri-Party Transportation Conference Red Deer, Alberta Hal Cook, P. Eng. Design, Project Management and Training Section Technical
More informationVULCAN BARRIER TL-3 GENERAL SPECIFICATIONS
VULCAN BARRIER TL-3 GENERAL SPECIFICATIONS I. GENERAL A. The VULCAN BARRIER TL-3 (VULCAN TL-3) shall be a highly portable and crashworthy longitudinal barrier especially suited for use as a temporary barrier
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM
Date: March 26, 2013 CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM To: From: The Honorable City Council c/o City Clerk, Room 395 Attention: Honorable Mitchell Englander, Chair, Public Safety Committee
More informationEngineering Report: Shasta-Trinity National Forest. Shasta McCloud Management Unit. Analysis of. National Forest System Road 37N79
Engineering Report: Shasta-Trinity National Forest Shasta McCloud Management Unit Analysis of National Forest System Road 37N79 (milepost 0.56 to 2.28) for Motorized Mixed Use Designation Forest: Shasta-Trinity
More informationSTATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. Start Dt: 05/15/17 Comp. Dt: 08/04/17. Contract Time: Min: Max:
Letting: 17012700 Letting Dt: January 27, 2017 9:30 A.M. State Proj.: 1401-171 Contract ID: Contract Description: Contract Location: Recommendation: 170002 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION
More informationEXTENDING TL-2 SHORT-RADIUS GUARDRAIL TO LARGER RADII
Research Project Number TPF-5(193) Supplement 27 EXTENDING TL-2 SHORT-RADIUS GUARDRAIL TO LARGER RADII Submitted by Cody S. Stolle, Ph.D., E.I.T. Post-Doctoral Research Associate Robert W. Bielenberg,
More informationEngineering Report: Shasta-Trinity National Forest. South Fork Management Unit. Analysis of. National Forest System Road 30N44
Engineering Report: Shasta-Trinity National Forest South Fork Management Unit Analysis of National Forest System Road 30N44 (milepost 0.00 to 0.40) for Motorized Mixed Use Designation Forest: Shasta-Trinity
More informationPlan Check Policies and Guidelines
VIII. TRAFFIC SIGNING AND STRIPING PLANS A. INTRODUCTION Traffic signing and striping plans are required for all General Plan Roads and any roadway that is 56-foot wide curb-to-curb (78 R/W) or wider.
More informationACTION TRANSMITTAL No
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 4, 2016 TO: ACTION TRANSMITTAL No. 2016-19 TAC Funding and Programming Committee PREPARED BY: Joe Barbeau, Senior
More informationEvaluation of the Midwest Guardrail System Stiffness Transition with Curb
Duplication for publication or sale is strictly prohibited without prior written permission of the Transportation Research Board Paper No. -0 Evaluation of the Midwest Guardrail System Stiffness Transition
More informationDEVELOPMENT OF A TRANSITION BETWEEN FREE-STANDING AND REDUCED-DEFLECTION PORTABLE CONCRETE BARRIERS PHASE I
Research Project Number TPF-5(193) Supplement #78 DEVELOPMENT OF A TRANSITION BETWEEN FREE-STANDING AND REDUCED-DEFLECTION PORTABLE CONCRETE BARRIERS PHASE I Submitted by Mojdeh Asadollahi Pajouh, Ph.D.
More informationAGC/MoDOT Annual COOP Meeting. Safety/Traffic Division & Specialty Contractors/Suppliers Breakout Session. December 5, 2018
AGC/MoDOT Annual COOP Meeting Safety/Traffic Division & Specialty Contractors/Suppliers Breakout Session December 5, 2018 District Work Zone Review St. Louis June 11-14, 2018 Central July 16-18, 2018 Northeast
More informationMoraga-Orinda Fire District
Moraga-Orinda Fire District Fire Prevention Division Subject: Fire Apparatus Access Roads Approved by: Fire Marshal Kathy Leonard Reference: CFC 2016, MOFD Ordinance 16-02 Standard Number: 2016.503 Effective
More informationAlberta Transportation Rumble Strips - C-TEP Lunch and Learn
Alberta Transportation Rumble Strips - C-TEP Lunch and Learn Bill Kenny P.Eng, Director: Design, Project Management and Training, Technical Standards Branch. - July 2011 What are Rumble Strips? A preventative
More informationChicago to St. Louis High-Speed Rail. IDOT District 8 Crossings. July 29, 2015
Chicago to St. Louis High-Speed Rail IDOT District 8 Crossings July 29, 2015 1 History: Chicago-St. Louis Corridor» IDOT has actively developed the Chicago to St. Louis corridor since the mid 1980 s» In
More informationEL DORADO COUNTY REGIONAL FIRE PROTECTION STANDARD
EL DORADO COUNTY REGIONAL FIRE PROTECTION STANDARD EMERGENCY APPARATUS ACCESS WAYS STANDARD #B-003 EFFECTIVE 05-05-2009 PURPOSE To establish a consistent guideline for fire access roadways required by
More informationSCDOT TRAFFIC SIGNAL SPECIAL PROVISIONS TRAFFIC CONTROL FOR TRAFFIC SIGNAL PROJECTS MAINTENANCE OF TRAFFIC
SCDOT TRAFFIC SIGNAL SPECIAL PROVISIONS TRAFFIC CONTROL FOR TRAFFIC SIGNAL PROJECTS MAINTENANCE OF TRAFFIC TRAFFIC CONTROL: The Contractor shall execute the item of Traffic Control as required by the Standard
More informationTemporary Traffic Control Plans
Temporary Traffic Control Plans US Department of Transportation Federal Highway Administration (FHWA) MUTCD 2009 EDITION Adopted by WSDOT December 19, 2011 with modifications per WAC 468-95. 2-1 Standard
More informationFREQUENTLY ASKED QUESTIONS
THE PROJECT Last updated on 9/8/16 FREQUENTLY ASKED QUESTIONS What s happening on Highway 169? The Minnesota Department of Transportation (MnDOT) is planning to rebuild and repair the infrastructure on
More informationAppendix "A" Transit Bus Stop Accessibility Criteria & Guidelines
Appendix "A" Transit Bus Stop Accessibility Criteria & Guidelines Public Works Department, Transportation Division January 2014 Transit Bus Stop Accessibility Criteria & Guidelines These criteria and guidelines
More informationMidwest Roadside Safety Facility
22860 900" D D 914 36" 1000 39 3/8" SOIL AND TARMAC CUT-OUT CONCRETE TARMAC BRIDGE DECK B PLAN VIEW C A C 15 20 [3/4"] Deck Gap BRIDGE DECK A 3900 153 1/ Impact 30V 45720 1800" 34290 13" 11430 4" RAIL
More informationDESIGNATED CONSTRUCTION ZONE SPEED FINES DOUBLE. Manitoba Infrastructure and Transportation. Infrastructure and Transportation. Traffic Engineering
CONSTRUCTION DESIGNATED ZONE SPEED FINES DOUBLE Manitoba Infrastructure and Transportation Work Zone Traffic Control Manual Provincial Roads and Provincial Trunk Highways Infrastructure and Transportation
More informationProcedure Effective date Rescinds Vehicle Placement In or Near Moving Traffic 17 November January 2005
Procedure Effective date Rescinds Vehicle Placement In or Near Moving Traffic 17 November 2008 1 January 2005 Reference Norwich Township Fire Department SOG #30 Page 1 of 6 Purpose: The purpose of this
More informationUniversal TAU-IIR Redirective, Non-Gating, Crash Cushion
TB 110927 Rev. 0 Page 1 of 5 Product Specification Universal TAU-IIR Redirective, Non-Gating, Crash Cushion I. General The Universal TAU-IIR system is a Redirective, Non-Gating Crash Cushion in accordance
More informationCONTRACT AWARD INFORMATION
COUNTY OF DUTCHESS DIVISION OF CENTRAL SERVICES Contract Administration CONTRACT AWARD INFORMATION Title: Bid No: Contract Period: Authorized Users: Guide Rail & Accessories, Drain Grates and Sign, Delineator
More informationTEXAS TRANSPORTATION INSTITUTE THE TEXAS A & M UNIVERSITY SYSTEM COLLEGE STATION, TEXAS 77843
NCHRP REPORT 350 ASSESSMENT OF EXISTING ROADSIDE SAFETY HARDWARE by C. Eugene Buth, P.E. Senior Research Engineer Wanda L. Menges Associate Research Specialist and Sandra K. Schoeneman Research Associate
More informationtested noise barrier system for bridges
_ ARMTEC.COM noise control / ACRYLITE soundstop ACRYLITE soundstop TL-4 SYSTEM PRODUCT GUIDE lightweight, Crash tested noise barrier system for bridges and elevated roadway applications Safest Noise Barrier
More informationDEFLECTION LIMITS FOR TEMPORARY CONCRETE BARRIERS
Midwest State s Regional Pooled Fund Research Program Fiscal Year 1998-1999 (Year 9) NDOR Research Project Number SPR-3(017) DEFLECTION LIMITS FOR TEMPORARY CONCRETE BARRIERS Submitted by Dean L. Sicking,
More informationDRIVEWAY STANDARDS EXHIBIT A. The following definition shall replace the definition of driveway in Section 62:
1365 S. Camino del Rio Durango, CO 81303 970-382-6363 DRIVEWAY STANDARDS Resolution 2014-40 EXHIBIT A The following definition shall replace the definition of driveway in Section 62: Driveway means a roadway,
More informationAustralian/New Zealand Standard
AS/NZS 3845:1999 Australian/New Zealand Standard Road safety barrier systems AS/NZS 3845:1999 This Joint Australian/New Zealand Standard was prepared by Joint Technical Committee CE/33, Road Safety Barrier
More informationMaine Turnpike Authority
Interchange 44 Barrier Toll Plaza Open Road Tolling Conversion Mile 44.3 201.11 CLEARING 3.50 AC 202.071 REMOVING ASBESTOS CONTAINING MATERIALS, TOLL BOOTH LAB TOPS 1.00 LS 202.081 REMOVING EXISTING BUILDING
More informationPlan Check Policies and Guidelines
Plan Check Policies and Guidelines VII. A. INTRODUCTION Traffic signing and striping plans are required for all General Plan Roads and any roadway that is 56-foot wide curb-to-curb (78 R/W) or wider. Transportation
More informationDevelopment and Implementation of the Simplified MGS Stiffness Transition
Duplication for publication or sale is strictly prohibited without prior written permission of the Transportation Research Board Paper No. 12-3367 Development and Implementation of the Simplified MGS Stiffness
More informationCTA Blue Line Study Area
1 CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING
More informationThe Design-Builder shall meet local road criteria provided by the local governing agencies.
11 ROADWAYS 11.1 General The -Builder shall conduct all Work necessary to meet the requirements of roadways. Roadway classifications include mainline, acceleration lanes, deceleration lanes, auxiliary
More informationLCDOT DETOUR PROCEDURES. and GUIDELINES
LCDOT DETOUR PROCEDURES and GUIDELINES LCDOT Traffic Department (847) 377-7400 Rev 2/3/2017 ADVANCE ROAD CLOSED SIGNS (W20-3) These signs shall be a 48" x 48" Black Legend on Fluorscent Orange Sheeting.
More informationImproving Roadside Safety by Computer Simulation
A2A04:Committee on Roadside Safety Features Chairman: John F. Carney, III, Worcester Polytechnic Institute Improving Roadside Safety by Computer Simulation DEAN L. SICKING, University of Nebraska, Lincoln
More informationSMART CUSHION INNOVATIONS
S C I P r o d u c t s I n c. The World s Only Speed-Dependent Crash Attenuators. TM SMART CUSHION INNOVATIONS N C H R P 3 5 0 A p p r o v e d M a r k e t e d a n d D i s t r i b u t e d b y W o r k A r
More informationSTATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS
STATE ND PROJECT NO. CP 0883 (14) & CP 1152 (14) SHEET NO. TOTAL SHEETS 9 31 SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT REQUIRED UNITS PER AMOUNT UNITS SUB TOTAL SIGN NUMBER SIGN SIZE DESCRIPTION AMOUNT
More informationUS 70 Corridor Planning for the Future
New Bern/James City Area - Work Session US 70 Corridor Planning for the Future Brinson Elementary School Thursday, January 31, 2008 Agenda Sign-in, in, View Maps, Talk to Project Team Public Q & A Session
More informationUpdate to NCHRP Report 350. Current Safety Issues
Workshop on the Update to NCHRP Report 350 and Current Safety Issues July 18 21, 2004 Sponsored by TRB COMMITTEE AFB20 ROADSIDE SAFETY DESIGN DoubleTree Hotel Overland Park-Corporate Woods 10100 College
More informationApplicable California Vehicle Code Sections, 2015 Edition
Applicable California Vehicle Code Sections, 2015 Edition Speed limits in California are governed by the California Vehicle Code (CVC), Sections 22348 through 22413; also, pertinent sections are found
More informationLee County DOT Traffic Section Design Standard for Sign Installation
Lee County DOT Traffic Section Design Standard for Sign Installation Traffic Section Table Of Contents Section Title 1. Sign Panel Material 2. Sign Shape 3. Posts 4. Fasteners 5. Retro reflectivity and
More informationPRODUCT DESCRIPTION. X-Tension DS. is suitable for all road types: Motorways, country roads, city streets for speed categories up to 110 km/h.
INDEX Introduction 2 Product Description 3 Installation 6 Specifications 7 Crash Tests Table 8 Reusability 9 FAQ 10 Annexes 14 Drawings 15 Pictures 16 Crash Tests Results 18 Approvals 23 INTRODUCTION Improving
More informationELMORE COUNTY HIGHWAY DEPARTMENT
Adopted 11/27/06 Effective 2/1/07 Amended 4/10/08 ELMORE COUNTY HIGHWAY DEPARTMENT 155 County Shop Road Wetumpka, Alabama 36092 Phone (334) 567-1162 Fax (334) 567-1100 Access Management Policy The Elmore
More informationLocal Road Safety Program. Marie B. Walsh, Director Louisiana LTAP January 10, 2011 Louisiana Transportation Conference
Local Road Safety Program Marie B. Walsh, Director Louisiana LTAP January 10, 2011 Louisiana Transportation Conference Local Road Safety Program Addresses the ALL public road inclusion of SAFETEA-LU Primary
More informationSTATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION - TABULATION OF BIDS. District(s): 8 30=047 Start Dt: 05/01/17 Comp. Dt:
Letting: 17030200 Letting Dt: March 02, 2017 9:30 A.M. State Proj.: 5101-14 Contract ID: Contract Description: Contract Location: Recommendation: 170020 STATE OF MINNESOTA DEPARTMENT OF TRANSPORTATION
More informationRAILROAD PREEMPTION FORMS. Mark Johnson, P.E.
RAILROAD PREEMPTION FORMS Mark Johnson, P.E. October 12, 2016 The Basic Problem Vehicles stop on tracks Need to interconnect traffic signal with railroad cabinet 2 Preemption Process: ROW Transfer 1 st