1 VelociRFTA BRT/CNG Project West Slope CNG Collabora;ve Workshop April 13, 2012
2 Agenda RFTA Background VelociRFTA Bus Rapid Transit (BRT) RFTA CNG Due Diligence Effort RFTA CNG Decision RFTA Es;mated CNG Financing RFTA Es;mated CNG Cash Flow Ques;ons
3 Overview of the Roaring Fork Transportation Authority
4 Overview of the Roaring Fork Transportation Authority RFTA: Ø 2 nd Largest public transit system in Colorado aser Denver RTD Ø Believed to be the largest rural public transit system in the U.S. Ø 1 st Rural BRT System in the U.S Informa4on: Ø 4.14 million passengers Ø 3.68 million miles of service Ø 250 employees during peak winter season Ø 100 large transit vehicles Ø $31.8 million budget Ø 70- mile corridor Aspen to Glenwood Springs Glenwood Springs to Rifle Ø 34- mile Rio Grande Rail Corridor and Trail
5 Overview of the Roaring Fork Transporta4on Authority Rio Grande Trail near Carbondale
6 Overview of the Roaring Fork Transportation Authority RFTA provides the following types of transit services: Ø Regional commuter services in the Hwy 82 & I- 70 corridors Ø Municipal transit services under contracts with the City of Aspen and the City of Glenwood Springs Ø Skier shudle services under contract with Aspen Skiing Co. Ø Senior transporta;on services through Senior Van/Traveler Ø Maroon Bells bus tours in partnership with USFS
7 VelociRFTA Overview: How BRT Addresses Features Needed in a Modern Transit System
8 VelociRFTA Overview: Implementation Process 1. Corridor Investment Study 2003 Compared Rail vs. BRT Rail $300 + Million BRT $100 Million 2. Alterna4ves Analysis SAFETEA- LU Auth. Design goals Service goals Preferred Alterna;ve (BRT) Approximately $46 Million 3. Voter Support November 2008 Sales Tax for BRT Bonding Approval 4. Very Small Starts Applica4on 2008 Received FTA Approval in December 2008 Began Project Development 5. Project Development Program Management Consultant Retained Advanced Planning Program Defini;on Refined Branding Plan Community Outreach Jurisdic;on Coordina;on Planning Approvals NEPA Process Issued Bonds 6. Project Construc4on Prepara4on 4th Quarter 2010 Final Design Stage Vehicle Procurement Awai;ng NTP ITS Procurement Begun Service Plan Refinement Planning Approvals NEPA Process Complete FONSI Received 7. Construc4on Complete Final Design FY2011 Appropria;on FTA Construc;on Grant ROW Acquisi;on ITS Acquisi;on Construc;on Order BRT Vehicles Tes;ng of System 8. Begin Revenue Service An4cipated September 2013
9 VelociRFTA BRT Overview: Cost / Funding VelociRFTA is in the Federal Transit Administra;on (FTA) Very Small Starts Program for projects up to $50 million. Maximum $25m FTA share Project Financing: Est. Project Cost = $46.2m FTA share = $24.97m (54%) RFTA share = $21.23m (46%) Status of FTA Funding FY2010 $810k Awarded FY $24.16m Awarded Regional voters approved a sales tax increase and bonding capacity in 2008 for VelociRFTA BRT RFTA issued bonds in 2009 in order to have local matching funds available
10 VelociRFTA BRT Overview: Features of VelociRFTA Design Transit Priority Measures Transit Signal Priority (TSP) at congested intersec;ons Queue Bypass Lanes at congested intersec;ons Use of Exis;ng Bus/HOV & Exclusive Bus lanes
11 VelociRFTA BRT Overview: Features of VelociRFTA Design Branding Characteristics RFTA Reliable Practical Hardworking VelociRFTA Fast Fun Frequent
12 VelociRFTA BRT Overview: Features of VelociRFTA Design BRT Service Plan Span of Service at least 14 hours each weekday Approximately 1- hour travel ;me between Glenwood Springs and Aspen Local valley bus service to con;nue every 30 minutes BRT service levels may be modified during the off- season and according to demand
13 VelociRFTA BRT Project Background: Features of VelociRFTA Design Low- Floor Buses VelociRFTA Fleet of 18 Low- Floor Buses (Pursuing Compressed Natural Gas Op6on) (Concept)
14 VelociRFTA BRT Project Background: Features of VelociRFTA Design Information Program ITS Technology Real Time Sign Information Automated Vehicle Location Automated passenger counters Automated Annunciators Electronic Fare Collection Mobile Wi-Fi service Route Map Integration System Map Integration Schedule Integration Community Information
15 VelociRFTA BRT Project Background: Features of VelociRFTA Design BRT Sta4on Program Passenger Shelters Ticket vending Enclosed wai;ng and sea;ng area Ligh;ng Bicycle Storage Covered and uncovered Outside Sea;ng Landscaping Trash and Recycling Op;onal Elements Parking Restroom Facili;es
16 CNG Effort Due Diligence CNG Fueling Facility Field Trip Aspen Strategy Center Charre`e CNG Engine Reliability Issues: Contacted Utah Transit Authority (UTA) regarding CNG Bus Test at 6,000 feet of Eleva4on: Numerous conversa4ons with Cummins (Engine Manufacturer) Other Transit Proper4es Opera4ng Gillig CNG Buses (Idaho, California, Minnesota) Federal Transit Administra4on (FTA) Oversight CNG Capital Costs, Financing, Savings, and Cash Flow CNG Infrastructure Costs Low- Interest Bonding Lease Purchase Financing Grant Funding: Encana, SGR, Clean Fuels CNG Fuel Costs
17 CNG Effort Due Diligence CNG Project Risks Schedule (High) Capital Costs (Low): Financing (Low): Short- term Cash Flow (Moderate): Maintenance and Opera4onal Considera4ons (Low): Safety (Low) CNG Project Benefits Domes4c fuel Abundant Supply Stable price trend Less expensive overall than diesel currently (savings pay for commodity, electricity, compression O&M, infrastructure capital, and add to bo`om line Provides a hedge against higher diesel prices
18 CNG Effort Decision to go with CNG March 22 nd Board authorized RFTA to procure: 4 pilot CNG buses to be delivered in January BRT buses with CNG engine technology to be delivered June 2013 A CNG fueling sta;on to be opera;onal before January 2013 Facility safety modifica;ons to be installed before January 2013
19 RFTA CNG Effort - - Infrastructure RFTA has selected Trillium as its CNG Fueling Sta;on vendor Three proposals were received; two BAFOs were requested and evaluated Contract with Trillium will be signed in early April 2012 RFTA has selected M.W. Golden Constructors as its contractor for the GMF Safety Modifica;ons Contract with M.W. Golden Constructors will be signed in April 2012 Environmental Fact Sheet for GMF approved by FTA, February 2012 Indoor fast- fueling requires significant safety modifica;ons
20 RFTA CNG Effort - - Financing Total ini;al CNG effort capital cost es;mated at $8.35 Million RFTA received $6.7 Million alloca;on of Qualified Energy Conserva;on Bonds (QECB s) from Governor s Energy Office Effec;ve interest rate 2% - 3% because Feds pay 70% of the interest RFTA has retained Bond Counsel and is issuing RFP for a Bond Underwriter and a Financial Advisor RFTA may issue an addi;onal $1.65 million in sales tax revenue bonds using its own bonding authority RFTA also evalua;ng using lease- purchase agreement mechanism for the $1.97 Million cost of the four CNG pilot vehicles
21 CNG Project Capital Cost Summary Estimated RFTA CNG Project Revenue and Capital Costs CNG Project Element Est. Amount CNG BRT Buses $ 8,663,000 2 CNG Fueling Facility $ 2,500,000 3 Maintenance Facility Safety Modifications $ 2,813, CNG Pilot (Replacement) Buses $ 1,973,715 5 Estimated Debt Service Reserve $ 445,000 6 Cost of Issuance $ 116,233 7 Total Estimated CNG- Related Capital Costs $ 16,511,568 8 Federal Transit Adminsitration/Local Grant Funding $ (7,800,000) 9 Encana Community Investment Grant Funding $ (365,000) 10 Balance of Capital Funding Required for CNG Project $ 8,346, Available GEO Qualified Energy Conservation Bonds (QECB's) $ 6,706, Estimated QECB Shortfall $ 1,640,568 * 4 pilot buses can be lease/purchased
22 Es4mated Annual Savings from CNG DGE s vs. Diesel Gallons Summary of Estimated Total Annual Operating Cost Savings CNG Vs. Diesel Fuel Low- Range 1 Current Estimated Diesel Costs for BRT and 4 Rplcmnt Buses $ 1,389, Current "All In" CNG Costs $ 1,140, Estimated Annual Debt Service for 4 Additional CNG Replacement buses $ 198,284 4 Total Estimated Annual O & M Savings $ 51,039.91
23 Fuel Price Forecast (Diesel Vs. CNG) Average Annual Rate of Increase 1 Estimated Gallons of Diesel for 18 BRT & 4 Replacement Buses 372, ,624 0% 2 Estimated Diesel Fuel Price $ 3.73 $ % 3 Estimated Cost of Diesel Fuel $ 1,389,888 $ 1,867,893 3% 4 Estimated Diesel Gallon Equivalents (DGE's) 399, ,608 0% 5 A. Est. Amortized Debt Service (Base CNG Project/DGE) $ 1.11 $ % 6 B. Est. Price of CNG Commodity and Pipeline Costs/DGE $ 1.00 $ % 7 C. Est. Electricity Cost/DGE $ 0.13 $ % 8 D. Est. Compression O & M Costs/DGE $ 0.61 $ % 9 Estimated CNG Fuel Price Per DGE (Base CNG Project Elements) $ 2.85 $ % 10 Estimated Cost of CNG $ 1,140,564 $ 1,379,695 2% 11 Estimated Savings CNG versus Diesel Available for Other Purposes* $ 249,323 $ 488,197 7% 12 Annual Percent Increase in Savings 13 *To fund debt service on 4 CNG pilot buses and contribute to the bottom line
24 RFTA CNG Effort Ques4ons/Comments
Colorado Association of Ski Towns August 26, 2016
Colorado Association of Ski Towns August 26, 2016 1 Presentation RFTA Overview Long Range Forecast Integrated Transportation System Plan Questions Roaring Fork Transportation Authority (RFTA) RFTA Overview
More informationDurham-Orange (D-O) Light Rail Transit (LRT) Project
American Society of Civil Engineers North Carolina Section Eastern Branch Luncheon August 18, 2016 Durham-Orange (D-O) Light Rail Transit (LRT) Project 1 Presentation Agenda Project Overview Project Status
More informationI-26 Fixed Guideway Alternatives Analysis
I-26 Fixed Guideway Alternatives Analysis Public Meetings: North Charleston, January 25, 2016 Charleston: January 26, 2016 Summerville: January 28, 2016 Agenda I. Project Update II. III. IV. Screen Two
More informationGreater Cleveland Regional Transit Authority
Greater Cleveland Regional Transit Authority SUMMARY OF PROPOSED AWARD Furnishing up to Two Hundred Forty (240) Low Floor 40-ft. Coaches, Training, Special Tools and Spare Parts over a Five (5) Year Contract
More informationMARTA s blueprint for the future. COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018
MARTA s blueprint for the future COFFEE AND CONVERSATION Kyle Keahey, More MARTA Atlanta Dec. 5, 2018 TODAY S AGENDA About MARTA Economic development/local impact More MARTA Atlanta program Program summary/timeline
More informationTempe Streetcar. March 2, 2016
Tempe Streetcar March 2, 2016 Tempe Profile 40 sq. miles, highest density in state University Town, center of region Imposed growth boundaries (density increase) Mixed use growth/intensifying land use
More informationMETRO CNG Program Phase I Update. Customer Service Committee April 2014
METRO CNG Program Phase I Update Customer Service Committee April 2014 METRO CNG Program Background Bus purchase Short term solutions Long term plans Bus purchase options 2 METRO CNG Program April 2011
More informationSamTrans Business Plan Update May 2018
SamTrans Business Plan Update May 2018 SamTrans Business Plan Core Principles: 1. Sustain and enhance services for the transit-dependent 2. Expand and innovate mobility services 3. Promote programs that
More informationState Avenue Corridor Bus Rapid Transit (BRT)
State Avenue Corridor Bus Rapid Transit (BRT) Moving Forward Incrementally April 2010 State Ave. BRT Update Bus Rapid Transit Overview State Ave. Alternatives Analysis Results What s Coming Up Right Away!
More informationFasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016
July 29, 2013 Welcome to Inside RTD FasTracks a monthly e- update to keep you informed about the progress of the Regional Transportation District's FasTracks program. FasTracks News RTD s Eagle P3 Transit
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program
More informationDraft Results and Open House
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Open House Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi
More informationUS 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017
US 29 Bus Rapid Transit Planning Board Briefing February 16, 2017 Project Goals Improve the quality of transit service Improve mobility opportunities and choices Enhance quality of life Support master
More informationDraft Results and Recommendations
Waco Rapid Transit Corridor (RTC) Feasibility Study Draft Results and Recommendations Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationBroward County Intermodal Center And People Mover. AASHTO Value Engineering Conference Presentation. September 1, 2009 San Diego, CA
Project Development & Environment Study Broward County Intermodal Center And People Mover AASHTO Value Engineering Conference Presentation September 1, 2009 San Diego, CA Background P D & E Study Regional
More informationLeadership NC. November 8, 2018
v Leadership NC November 8, 2018 Planning for our region s growth The Triangle is one of the fastestgrowing regions in the nation. More than 2 million people are already part of the equation, and the
More informationGreater Cleveland Regional Transit Authority
Greater Cleveland Regional Transit Authority Summary of Proposed Award Vanpool Program Presented to: Operations Committee August 2, 2016 What is a Vanpool? A vanpool is a group of people (larger than 5)
More informationCOMMUNITY REPORT FISCAL YEAR We are making progress, are you on board? GOLD COAST TRANSIT DISTRICT
FISCAL YEAR 178 GOLD COAST TRANSIT DISTRICT COMMUNITY REPORT We are making progress, are you on board? OJAI OXNARD PORT HUENEME VENTURA COUNTY OF VENTURA GENERAL MANAGER S MESSAGE STEVEN P. BROWN DEAR
More informationCEDAR AVENUE TRANSITWAY Implementation Plan Update
CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,
More informationSEPULVEDA PASS CORRIDOR
SEPULVEDA PASS CORRIDOR PUBLIC PRIVATE PARTNERSHIP DELIVERY PRE-DEVELOPMENT AGREEMENT PDA Sepulveda Pass Mobility Issues Most congested highway segment in the U.S. 295,000 vehicles per day (2010) 430,000
More information12/5/2018 DRAFT. December 6, Item #1 CITIZENS PARTICIPATION
December 6, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More informationA Transit Plan for the Future. Draft Network Plan
A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year
More informationMetropolitan Council Budget Overview SFY
Metropolitan Council Budget Overview SFY 2016-2017 H T t ti C itt House Transportation Committee February 4, 2015 Transit connects us to the places that matter Transportation Needs Grow as the Region Grows
More informationWASHINGTON STATE ROAD USAGE CHARGE ASSESSMENT
1 WASHINGTON STATE ROAD USAGE CHARGE ASSESSMENT Anthony L. Buckley Director, Office of Innovative Partnerships Washington State Department of Transportation Overview: Washington State Infrastructure 2
More informationAPPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY]
APPENDIX I: [FIXED-GUIDEWAY TRANSIT FEASIBILITY] Jackson/Teton Integrated Transportation Plan 2015 Appendix I. Fixed-Guideway Transit Feasibility Jackson/Teton County Integrated Transportation Plan v2
More informationREPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES
TRANSIT GRADE: C- WHAT YOU SHOULD KNOW ABOUT TRANSIT FACILITIES California needs robust, flexible and reliable transit systems to reduce peak congestion on our highways, provide options for citizens who
More informationNortheast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study
Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for
More informationHDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009
HDR Engineering HART North / South BRT Corridor PD&E Tampa Bay Applications Group Meeting May 14, 2009 1 Agenda Update on Project Development and Environment (PD&E) Study Project Overview System Branding
More information6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION
June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More informationPSTA Replacement Buses
PSTA Replacement Buses Decision Making Guide for PSTA Board Update to PSTA Finance & Performance Management Committee October 21, 2015 Pinellas Suncoast Transit Authority (PSTA) St. Petersburg, Florida
More informationValley Metro: Past, Present and Future. September 11, 2014
Valley Metro: Past, Present and Future September 11, 2014 Valley Metro Who are We? Two Boards of Directors Regional Public Transportation Authority Fund and operate regional transit services Valley Metro
More informationEUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT
EUGENE-SPRINGFIELD, OREGON EAST WEST PILOT BRT LANE TRANSIT DISTRICT (BRIEF) Table of Contents EUGENE-SPRINGFIELD, OREGON (USA)... 1 COUNTY CONTEXT AND SYSTEM DESCRIPTION... 1 SYSTEM OVERVIEW... 1 PLANNING
More informationExecutive Summary. Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009.
Treasure Valley High Capacity Transit Study Priority Corridor Phase 1 Alternatives Analysis October 13, 2009 Background As the Treasure Valley continues to grow, high-quality transportation connections
More informationAgenda Item No. 6b June 24, Honorable Mayor and City Council Attention: David J. Van Kirk, City Manager
Agenda Item No. 6b June 24, 2008 TO: FROM: SUBJECT: Honorable Mayor and City Council Attention: David J. Van Kirk, City Manager Dale I. Pfeiffer, Director of Public Works RESOLUTION APPROVING THE PURCHASE
More informationThe Case for. Business. investment. in Public Transportation
The Case for Business investment in Public Transportation Introduction Public transportation is an enterprise with expenditure of $55 billion in the United States. There has been a steady growth trend
More informationCapital Needs Assessment Riders Advisory Council July2, 2008
Capital Needs Assessment 2011-2020 Riders Advisory Council July2, 2008 1 Outline I. Capital Improvement Plan History II. Capital Improvement Plan Update III. Capital Needs Assessment State of Good Repair
More informationBalancing the Transportation Needs of a Growing City
Balancing the Transportation Needs of a Growing City FY 2019 and FY 2020 Capital Budget SFMTA Board Meeting Ed Reiskin, Director of Transportation April 3, 2018 1 FY 2019-23 Capital Improvement Program
More informationI-26 Fixed Guideway Alternatives Analysis
I-26 Fixed Guideway Alternatives Analysis Steering & Technical Advisory Committees Joint Meeting January 15, 2016 @ 10:00 AM SC/TAC Meeting Winter 2016 Agenda I. Welcome & Introductions II. III. Project
More informationPAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015
PAG Environmental Planning Advisory Committee Sun Link Streetcar Update May 1, 2015 Project Facts 4-mile route, 23 stops 8 made in USA modern streetcars All electric and green Voter-approved project Connects
More informationReport for Action. Wilson Bus Garage - Upgrades. Summary. Date: March 20, 2018 To: TTC Board From: Chief Capital Officer
Report for Action Wilson Bus Garage - Upgrades Date: March 20, 2018 To: TTC Board From: Chief Capital Officer Summary The purpose of this report is to obtain authorization for the award of Contract No.
More informationArterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014
Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update
More informationExhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup
Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting
More informationCity of El Paso: Sun Metro Legislative Agenda Briefing
Tiger V TOD Operational 2017 City of El Paso: Sun Metro Legislative Agenda Briefing March 2016 Sun Metro FY 2016/17 Legislative Agenda First and foremost, thanks for the new transportation bill: Fixing
More informationRegional Transit Extension Studies. Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013
Regional Transit Extension Studies Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013 Topics Virginia Beach Transit Extension Study (VBTES) Naval Station
More informationRoma McKenzie-Campbell Amtrak, Project Manager. Caroline Ducas VHB, Senior Transit Planner. Boston, Massachusetts
DMU Implementation on Existing Commuter Rail Corridors: Opportunities, Challenges and Lessons Learned Roma McKenzie-Campbell Amtrak, Project Manager Caroline Ducas VHB, Senior Transit Planner Boston, Massachusetts
More informationKANSAS CITY STREETCAR
KANSAS CITY STREETCAR KAREN CLAWSON MID-AMERICA REGIONAL COUNCIL KANSAS CITY STREETCAR Regional Context Alternatives Analysis Kansas City Streetcar Project KANSAS CITY REGION KANSAS CITY REGION KANSAS
More informationProposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1
Proposed FY 2019-2023 Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1 The Capital Improvement Program is: A fiscally constrained, 5-year program of capital projects An implementation
More informationThe Status of Transportation Funding, Road Charge and Vehicle Miles Traveled in California
The Status of Transportation Funding, Road Charge and Vehicle Miles Traveled in California Long-Term Policy Options for Sustainable Transportation Options NCSL State Transportation Leaders Symposium October
More informationDART Priorities Overview
City of Dallas Transportation and Trinity River Project Committee DART Priorities Overview Gary C. Thomas President/Executive Director August 10, 2015 City of Dallas Transportation & Trinity River Committee
More informationPeninsula Corridor Electrification Project Cost / Schedule Update
Peninsula Corridor Electrification Project Cost / Schedule Update LPMG Meeting November 20, 2014 Context Caltrain/high-speed rail blended system - Primarily 2 track system - Minimize impacts - Shared system
More informationQUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N
QUALITY OF LIFE EXECUTIVE SUMMARY REPORT UN I O N S TAT I O N T R AV E L by TR A I N Published September 2017 2015 PROGRESS MAP This document reports FasTracks progress through 2015 BACKGROUND RTD The
More informationMerger of the generator interconnection processes of Valley Electric and the ISO;
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Karen Edson Vice President, Policy & Client Services Date: August 18, 2011 Re: Decision on Valley Electric
More informationTransit Implementation Strategy. Presentation for the Atlanta City Council
Transit Implementation Strategy Presentation for the Atlanta City Council March 7, 2011 This Legislation authorizes the IGA and New Vehicle Purchase There are two parts to this legislation: 1. IGA between
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationMemorandum. 1 Introduction. 2 O&M Cost Elements. 2.1 Service O&M Costs
To Barrow Emerson, SamTrans Melissa Reggiardo, SamTrans Date 9/13/2014 Copies Reference number From Subject Corey Wong, Arup Steve Crosley, Fehr + Peers ECR BRT Phasing Plan File reference 1 Introduction
More informationDowntown Transit Connector. Making Transit Work for Rhode Island
Downtown Transit Connector Making Transit Work for Rhode Island 3.17.17 Project Evolution Transit 2020 (Stakeholders identify need for better transit) Providence Core Connector Study (Streetcar project
More informationBART Silicon Valley. Berryessa Extension Project Community Update. October 27, 2010
BART Silicon Valley Berryessa Extension Project Community Update October 27, 2010 1 Agenda Welcome and Introductions Program and Project Background Project Status Project and Station Details Current and
More informationSolano County Transit
AGENDA ITEM: 9 BOARD MEETING DATE: FEBRUARY 18, 2016 Solano County Transit TO: PRESENTER: SUBJECT: ACTION: BOARD OF DIRECTORS ALAN PRICE, PROGRAM ANALYST II REVIEW AND APPROVE IMPLEMENTATION OF THE FUELING
More informationPublic Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development
Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation
More informationCommunity Outreach Meetings
Community Outreach Meetings BCT At A Glance 410 square miles service area More than 41.5 million annual trips 327 fixed-route buses 44 bus routes 78 Community Buses in 19 Municipalities BCT At A Glance
More informationTRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury
TRANSIT FEASIBILITY STUDY Town of Bradford West Gwillimbury Open House Presentation January 19, 2012 Study Objectives Quantify the need for transit service in BWG Determine transit service priorities based
More informationMETRONext. Vision & Moving Forward Plans. Board Workshop. December 11, DRAFT For Preliminary Discussion Only
METRONext Vision & Moving Forward Plans Board Workshop December 11, 2018 Disclaimer This presentation is being provided solely for discussion purposes by the Board of Directors of the Metropolitan Transit
More informationMetro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner
Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning
More information2/1/2018. February 1, Item #1 CITIZENS PARTICIPATION
February 1, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More informationIndependence Institute Denver West Parkway, Suite 185 Golden, Colorado i2i.org/cad.aspx BRT = BTR
Independence Institute 14142 Denver West Parkway, Suite 185 Golden, Colorado 80401 303-279-6536 i2i.org/cad.aspx BRT = BTR Bus-Rapid Transit Is Better Than Rail: The Smart Alternative to Light Rail Joseph
More informationPoint A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017
Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master
More informationORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report
ORANGE COUNTY TRANSPORTATION AUTHORITY Agreement to Purchase Compressed Natural Gas Articulated Staff Report November 8, 2012 To: From: Subject: Transit Committee Will Kempton, Chief Executive Officer
More informationCommuter Transit Service Feasibility
Commuter Transit Service Feasibility West Michigan Transit Linkages Study Submitted to: Ottawa County, Michigan Submitted by: MP2PLANNING, LLC AUGUST 2012 Table of Contents 1. Introduction... 2 2. Overall
More informationStrategic Planning for Metro s Transition to Zero Emission Buses. October 2017
Strategic Planning for Metro s Transition to Zero Emission Buses October 2017 Requirements and Guidelines/Guiding Principles Continue to replace Aging Bus Fleet (~200 Buses per Year) Upgrade current CNG
More informationRegional Transportation District. Dave Genova Interim General Manager and CEO August 21, 2015
Regional Transportation District Dave Genova Interim General Manager and CEO August 21, 2015 About RTD Created in 1969 Eight-county service area Service area: 2,340 square miles 2.8 million population
More informationRedefining Mobility Ready or not: Autonomous and connected vehicle planning and policy, now and in the future
Redefining Mobility Ready or not: Autonomous and connected vehicle planning and policy, now and in the future Randy Iwasaki November 30, 2017 WHO WE ARE The Contra Costa Transportation Authority (CCTA)
More informationFeasibility Study. Community Meeting March, North-South Commuter Rail Feasibility Study
Feasibility Study Community Meeting March, 2017 1 Agenda 1. Welcome / Introductions 2. Background / Meeting Purpose 3. Progress to Date Options Evaluated Capital/Operating Costs Ridership 4. Financial
More informationAdvancing our Fleet. Blue Springs School District. Bill Cowling Assistant Superintendent Blue Springs Schools
Advancing our Fleet Blue Springs School District Bill Cowling Assistant Superintendent Blue Springs Schools bcowling@bssd.net 816.224.1300 Steve Brown Director, Transportation Services Blue Springs Schools
More informationRegional Transportation Commission, Washoe County Lee Gibson, Executive Director Roger Hanson, Senior Planner
Regional Transportation Commission, Washoe County Lee Gibson, Executive Director Roger Hanson, Senior Planner Presentation Outline Transit System Facts Economic Challenges in the Truckee Meadows RTC Transit
More informationPurple Line Light Rail P3 Project
Purple Line Light Rail P3 Project TPB Meeting May 18, 2016 1 Topics General Project Overview The P3 Contract Details on The Successful Proposal 2 Recap of Purple Line P3 Events In November 2013 MTA initiated
More informationPUBLIC TRANSPORTATION
PUBLIC TRANSPORTATION An Overview of the Industry, Key Federal Programs, and Legislative Processes American Public Transportation Association 1 The Public Transportation Industry: What is "public transportation"?
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationFLEET SERVICES OVERVIEW and ACCOMPLISHMENTS Public Works Commission August 10, 2017
FLEET SERVICES OVERVIEW and ACCOMPLISHMENTS Public Works Commission August 10, 2017 DESCRIPTION OF FLEET OPERATION Fleet operations include vehicle and equipment maintenance, procurement and surplus services,
More informationRocky Mountain. Corridor Input Team. Alternatives Overview. TEMS, Inc. / Quandel Consultants, LLC TEMS, Inc. / Quandel Consultants, LLC
Rocky Mountain Rail Authority (RMRA) Corridor Input Team Meeting #2 Alternatives Overview December 2008 TEMS, Inc. / Quandel Consultants, LLC 0 Agenda Introductions Study Overview Alternatives Overview
More informationNational Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )
National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA ) Presenter: National Treasury 18 November 2015 90 day Action Plan In November 2014, the Ministers
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 10.5 DIVISION: Transit Services BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Requesting authorization for the SFMTA, through the Director of Transportation,
More informationMontgomery County Department of General Services DGS Delivering Green Service
Montgomery County Department of General Services DGS Delivering Green Service Montgomery County Background 500 Square Miles 1M + Residents 4,500+ Fleet Vehicles Over 1100 AFV 62 Million Miles Driven 31
More informationMOTION No. M Purchase of Five 40-foot Buses PROPOSED ACTION
MOTION No. M2015-71 Purchase of Five 40-foot Buses MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations and Administration Committee 08/06/2015 Final Action Bonnie Todd, Executive Director of Operations
More informationSTRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016
STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016 Shift Rapid Transit Initiative Largest infrastructure project in the city s history. Rapid Transit initiative will transform London s public transit
More informationVAN NESS AVENUE BUS RAPID TRANSIT
VAN NESS AVENUE BUS RAPID TRANSIT Commission of the Environment Policy Committee May 22, 2014 Peter Gabancho Project Manager III Capital Programs & Construction SFMTA 1 Conceptual Visual Simulation Center-Running
More informationNYSERDA Alternative Fuel Vehicle Programs. Patrick Bolton and Adam Ruder NYSERDA April 24, 2013
NYSERDA Alternative Fuel Vehicle Programs Patrick Bolton and Adam Ruder NYSERDA April 24, 2013 About NYSERDA Basic Facts About NYSERDA Established in 1975 by State Legislature Executive level organization
More informationI-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results. Public Meeting. Wulf Grote, Director Project Development Rick Pilgrim, Project Manager
I-10 West AA/EIS Pre-Screening and Tier 1 Analysis Results Public Meeting Wulf Grote, Director Project Development Rick Pilgrim, Project Manager March 4 & 5, 2008 Today s Agenda Overview of Alternatives
More informationTBARTA USF to Wesley Chapel Express Bus Service Operating Plan. Draft 3/25/2014
TBARTA USF to Wesley Chapel Express Bus Service Operating Plan Draft 3/25/2014 March 2014 Table of Contents 1.0 Introduction... 1 2.0 Study Area... 1 3.0 Existing Available Service... 3 4.0 Proposed Service...
More information2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION
2018 American Zero Emission Bus Conference INNOVATIVE CLEAN TRANSIT PROPOSED REGULATION L o s A n g e l e s S e p t e m b e r 1 0 th & 11 th 1 General Considerations of Staff Proposal Achieve zero emission
More informationTPA Steering Committee for Tri-Rail Extension to Northern Palm Beach County. February 26, 2018
TPA Steering Committee for Tri-Rail Extension to Northern Palm Beach County February 26, 2018 Agenda Review Committee Purpose Review Project Map Discuss Service Alternatives Capital Costs (Stations, Track,
More informationContract Award for Rideshare Services to Supplement GoLink Service
Contract Award for Rideshare Services to Supplement GoLink Service Operations, Safety and Security Committee August 14, 2018 Todd Plesko, VP Service Planning & Scheduling 1 Today s Action Approval of a
More informationMOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion
MOTION NO. M2016-66 Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Operations Committee 07/07/16
More informationLate Starter. Tuesday, November 6, 2018
Late Starter Tuesday, Please note the following item(s) was not included with your agenda as this item(s) was received after the agenda package was printed. Planning and Works Committee Report TES-RTS-18-09,
More informationSnelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1
Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule
More informationProposed FY2015 Budget and Fare Increase
Washington Metropolitan Area Transit Authority Proposed FY2015 Budget and Fare Increase Riders Advisory Council January 8, 2014 1 Washington Metropolitan Area Transit Authority What will riders see from
More informationAPPROVE VANPOOL VEHICLE SUPPLIER BENCH CONTRACTS
One Gateway Plaza Lo s Angeles, CA 90012-2952 2 13.9 2 2.200 0 Tel metro. net 55 REGULAR BOARD MEETING May 23,2013 SUBJECT: ACTION: METRO VANPOOL PROGRAM APPROVE VANPOOL VEHICLE SUPPLIER BENCH CONTRACTS
More informationWhat IS BRT, Really? Not BRT and RNY
What IS BRT, Really? 2007 Winter TexITE Meeting Presented by Jeff Arndt, TTI Not BRT and RNY 1 What is Bus Rapid Transit? A flexible, rubber-tired from of rapid transit that combines stations, vehicles,
More informationSTAFF REPORT ACTION REQUIRED
STAFF REPORT ACTION REQUIRED Procurement Authorization Amendment Purchase of 18 Forty Foot Low Floor Clean Diesel City Buses Date: July 29, 215 To: From: TTC Board Chief Executive Officer Summary This
More information