1 Park & Ride Lot Investment Strategies Hampton Roads Transportation Technical Advisory Committee May 7, 2014 Carl E. Jackson, AICP Transportation Planning Specialist Hampton Roads District
2 VDOT Park & Ride Lot Inventory & Usage Study COMPLETED Project Team: VDOT SIR Kimley-Horn The Traffic Group Webbones SAG Timeline Began in fall of 2011 Completed early
3 Goals / Objectives of P&R Study Conduct a statewide inventory of existing Park & Ride lots Identify recommendations for new, expanded or relocated/closed lots Update/reconstruct the VDOT Park & Ride website Enhance VDOT s statewide Park & Ride Program Develop formal PNR program Evaluate & establish VDOT policies & procedures Evaluate & clarify staff roles & responsibilities Increase coordination with Department of Rail and Public Transportation (DRPT) and other agencies Improve collaboration and coordination with multi-modal partners Increase public outreach and awareness Increase public access to information 3
4 Study Deliverables 1. Lot audit and inventory database a) Pictures b) Latitude and Longitude c) Number of spaces (incl. handicapped spaces) d) Amenities e) Special comments 2. Recommendations for new, expanded, relocated lots 1. Includes recommendations from comp. plans, MPO/PDC plans, statewide plans, etc. 2. Database and maps 3. Reconstructed website and embeddable widget 4. P&R Program Goals and Objectives / Best Practices 5. Public Outreach User Survey 4
5 Deliverable: Reconstruct VDOT Website 5
6 Deliverable: Lot Audit & Inventory Update Audited 16 lots in Hampton Roads District (3 lots in Gloucester) Chesapeake Greenbrier Mall Newport News Denbigh Fringe Parking Lot Lee Hall Commuter Parking Lot Portsmouth Park & Sail Commuter Parking Lot Suffolk Magnolia Commuter Parking Lot Route 58/460 Bypass Virginia Beach Silver Leaf Station Indian River Road Isle of Wight County/Smithfield Smithfield Commuter Parking Lot Bartlett James City County Croaker Road Jamestown Center Surry County Municipal Center Jamestown-Scotland Ferry Sussex County Stony Creek York County Lightfoot Gloucester County Guinea Road Commuter Lot Hayes Road Commuter Lot Rappahannock Parking Lot 6
7 Deliverable: Lot Audit & Inventory Update Additional Lots to be added to State Inventory Norfolk LRT Park & Ride Lots Harbor Park Station Ballentine/Broad Creek Station Military Highway Station Newtown Road Station Hampton Roads Transit Hampton Transportation Center Closed lots removed from State Inventory Great Neck Commuter Parking Lot (Virginia Beach) Patrick Henry Mall Commuter Lot (Newport News) Edgehill Commuter Parking Lot (Gloucester) Abingdon Rescue Park and Ride (Gloucester) 7
8 8
9 Deliverable: User Survey Findings Hampton Roads Average time of arrival to P&R Lot 6:02am 64% of P&R lot users in HR use lots five days / week 99% of all lot users use the lots to commute to work Of users surveyed, they chose the following mode once parked at the lot 9
10 Deliverable: User Survey Findings Hampton Roads Average distance traveled to get to P&R lot is 9 miles Average time spent traveling to P&R lot is 14 minutes Average distance and time traveled from P&R lot to destination is 26 miles and 41 minutes. Average total commute is 35 miles and 55 minutes. 10
11 Deliverable: P&R Lot Recommendations Maintenance at seven lots, including paving; resurfacing; enhance with lighting, bike racks, installing drainage, replacing signage, etc. Expand lot and connect bike and pedestrian facilities Establish formal agreement for existing and proposed lots Expand park & ride services A preliminary list of detailed recommendations was vetted with TRAFFIX Oversight Subcommittee in November
12 VDOT Park & Ride Lot Investment Strategies Study Step 1: Recommendations VDOT completed a P&R Lot Inventory and Usage Study from Step 2: Priority Investment Areas (PIAs) VDOT staff compiled various data on each of the recommendations. A GIS Methodology was conducted with this data to identify Priority Investment Areas (PIAs): areas with a convergence of population density, high peak hourly traffic volumes and the proximity of the nearest existing P&R lot Major corridor that would be served by the potential P&R lot. The following data was used in this analysis: Census Population Density 2. Volume per hour along routes 3. Location of existing lots 12
13 13
14 14
15 Hampton Roads District P & R Priority List Rank Locality Lot Name Description ADT Workers 3 mi radius Workers Travel Outside Percent Travel Outside 1 VIRGINIA BEACH Indian River Road Park & Ride Expand lot by spaces % 2 VIRGINIA BEACH Silverleaf Commuter Parking Lot Expand lot by 50 spaces % 3 CHESAPEAKE New Proposed lot (Chesapeake Center) Lease agreement I-664 & Rte % 4 NEWPORT NEWS Denbigh Fringe Commuter Lot Repave & enhance lot near Rte % 5 CHESAPEAKE Greenbrier Mall Commuter Lot Expand lot by 150 spaces % 6 CHESAPEAKE New Proposed lot (Hanbury Road) Construct New lot near Chesapeake Exp % 7 NEWPORT NEWS Lee Hall Commuter Parking Lot Expand lot by 50 spaces near I % 8 NEWPORT NEWS New Proposed lot (Huntington Park) Lease agreement to use lot near Rte % 9 JAMES CITY COUNTY Croaker Road Commuter Parking Lot Pave & enhance lot near I % 10 YORK COUNTY Lightfoot Commuter Parking Lot Pave & enhance lot near I % 11 SURRY COUNTY Jamestown-Scotland Ferry Lot Pave & enhance lot near Rte % 12 PORTSMOUTH New Proposed Lot (Greenwood) Construct New lot, I-264 & Greenwood Dr % 13 PORTSMOUTH Park & Sail Commuter Parking Lot Repave & enhance lot at Court St & I % 14 ISLE OF WIGHT COUNTY Bartlett Commuter Parking Lot Repave & enhance lot near Rte % 15 ISLE OF WIGHT COUNTY Smithfield Commuter Parking Lot Expand lot at Rte 10 & Rte % 15
16 VIRGINIA BEACH Indian River Road Commuter Lot Reon Drive and Route 407 Major Corridors Service: I-64 and Indian River Road Owner/Maintenance: VDOT Transit Service: HRT Spaces: 283 Avg. Occupancy: 56% Expand Lot by Spaces Silverleaf Commuter Lot Silverleaf Drive and Route 225 Major Corridors Service: I-264 and Independence Blvd Owner/Maintenance: VDOT Transit Service: HRT Spaces: 260 Avg. Occupancy: 77% Expand Lot by 50 Spaces 16
17 CHESAPEAKE Greenbrier Mall Commuter Lot Mall Entrance and Greenbrier Pkwy Major Corridor Service: I-64 Owner/Maintenance: Private Transit Service: HRT Spaces: 50 (designated) Avg. Occupancy: 186% Expand Lot by 150 Spaces New Proposed Lot (Chesapeake Center) I-664 & Route 337/Portsmouth Blvd Major Corridor Service: I-664 Owner/Maintenance: Private Transit Service: HRT Spaces: N/A Occupancy: N/A Establish Lease Agreement New Proposed Lot (Hanbury Road) Chesapeake Exp/Hanbury Road Major Corridor Service: Rte 168 Owner/Maintenance: VDOT Transit Service: HRT Spaces: N/A Occupancy: N/A Construct New Lot 17
18 NEWPORT NEWS Denbigh Fringe Commuter Lot Route 60 and Old Courthouse Road Major Corridors Service: I-64 and Route 60 Owner/Maintenance: VDOT Transit Service: HRT Spaces: 265 Avg. Occupancy: 10% Repave and Enhance Lot Lee Hall Commuter Parking Lot Route 238 and Route 143 Major Corridors Service: I-64 and Route 143 Owner/Maintenance: VDOT Transit Service: None Spaces: 32 Occupancy: 56% Expand Lot by 50 spaces New Proposed Lot (Huntington Park) Mercury Blvd & Hornet Circle Major Corridors Service: Route 17/James River Bridge Owner/Maintenance: City Transit Service: HRT Spaces: N/A Occupancy: N/A Establish Lease Agreement 18
19 WILLIAMSBURG/JAMES CITY/ YORK/SURRY Croaker Road Commuter Lot Route 30 and Route 607 Major Corridors Service: I-64 and Route 30 Owner/Maintenance: VDOT Transit Service: WATA Spaces: 70 Avg. Occupancy: 56% Pave and Enhance Lot Lightfoot Commuter Parking Lot Route 30 and Route 199 Major Corridors Service: I-64 and Route 199 Owner/Maintenance: VDOT Transit Service: WATA Spaces: 70 Avg. Occupancy: 26% Pave and Enhance Lot Jamestown-Scotland Ferry Lot Route 31 and Route 637 Major Corridors Service: Route 31 and Jamestown Ferry Owner/Maintenance: VDOT Transit Service: WATA Spaces: 20 Avg. Occupancy: 15% Pave and Enhance Lot 19
20 PORTSMOUTH Park & Sail Commuter Lot Court Street and Crawford Street Major Corridor Service: I-264 Owner/Maintenance: VDOT Transit Service: HRT Spaces: 119 Avg. Occupancy: 13% Repave and Enhance Lot New Proposed Lot (Greenwood) I-261 and Greenwood Drive Major Corridors Service: I-264 Owner/Maintenance: VDOT Transit Service: HRT Spaces: N/A Avg. Occupancy: N/A Construct New Lot 20
21 ISLE OF WIGHT Bartlett Commuter Parking Lot Route 669 and Route 17 Major Corridor Service: Route 17 and James River Bridge Owner/Maintenance: VDOT Transit Service: HRT Spaces: 10 Occupancy: 60% Repave and Enhance Lot Smithfield Commuter Parking Lot Route 258 and Route 10 Major Corridors Service: Route 258 and Route 10 Owner/Maintenance: VDOT Transit Service: HRT Spaces: 66 Occupancy: 42% Enhance Lot 21
22 NORFOLK LRT PARK AND RIDE LOTS Harbor Park Station 176 spaces Ballentine / Broad Creek Station 105 spaces Military Highway Station 232 spaces Newtown Road Station 266 spaces HAMPTON TRANSPORTATION CENTER Address: 2 West Pembroke Avenue, Hampton Major Corridor Service: I-64/Hampton Roads Bridge Tunnel Owner/Maintenance: HRT Transit Service: HRT 138 spaces 22
23 Major Milestones / Schedule Business Plan Milestones: October 18-21, 2013 Develop district P&R list of priorities October 31, 2013 Submit a DRAFT list of each district s P&R priorities Including at least some level of MPO coordination November 29, 2013 Completion of Richmond district pilot List of coordinated priorities Online map of priorities Cost estimates Existing and recommended lots One-pager (final deliverable for this milestone) April 1, 2014 Begin stakeholder input Online map will be used to solicit input 23
24 TPO Coordination to date October 7-10, 2013: Requested feedback from TRAFFIX Oversight Subcommittee (TOS) on recommendations from Park and Ride Inventory and Usage Study October 15, 2013: Received feedback from TPO based on citizen survey from Military Commuter Study October 21, 2013: District staff sent DRAFT preliminary recommendations to VDOT central office for review November 6, 2013: District staff presented recommendations to the TRAFFIX Oversight Subcommittee and received additional local feedback. April 1-30, 2014 : District staff requested feedback from TOS on Priority Investment Recommendations. May 7, 2014: Presentation to TPO Transportation Technical Committee on Priority Investment Recommendations 24
25 Questions / Comments / Discussion? Thank you! Carl E. Jackson III, AICP Transportation Planning Specialist Virginia Department of Transportation Hampton Roads District carl.jackson@vdot.virginia.gov 25
Statewide Park & Ride Inventory and Usage Study, March 13, 2013 Liz McAdory, VDOT, Transportation & Mobility Planning Division
Statewide Park & Ride Inventory and Usage Study, 2013 March 13, 2013 Liz McAdory, VDOT, Transportation & Mobility Planning Division VDOT Park & Ride Lot Inventory & Usage Study Project Team: VDOT SIR Kimley-Horn
More informationRegional Transit Extension Studies. Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013
Regional Transit Extension Studies Hampton Roads Transportation Planning Organization Passenger Rail Task Force Meeting December 17, 2013 Topics Virginia Beach Transit Extension Study (VBTES) Naval Station
More informationHAMPTON ROADS TRANSPORTATION PROJECT PRIORITIES FOR THE 2034 LONG-RANGE TRANSPORTATION PLAN
HAMPTON ROADS TRANSPORTATION PROJECT PRIORITIES FOR THE 2034 LONG-RANGE TRANSPORTATION PLAN Prepared By: HRTPO Staff June 16, 2011 2 COMMITTED PROGRAMMED PROJECTS List of and Studies Committed are fully
More informationKendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study
Florida Department of Transportation District Six Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study What
More informationDRAFT DRAFT. Agenda Item #8. Presented to the Hampton Roads Transportation Planning Organization Board March 19, 2015
Agenda Item #8 Presented to the Hampton Roads Transportation Planning Organization Board March 19, 2015 Dale M. Stith, AICP, GISP Principal Transportation Planner Hampton Roads Transportation Planning
More informationNaval Station Norfolk Transit Extension Study. October 2014
Naval Station Norfolk Transit Extension Study October 2014 1 Employment by Transportation Analysis Zone (TAZ) Naval Station Legend Norfolk is Hampton Roads Region s largest employer C or with better PM
More informationNortheast Corridor Alternatives Analysis. Public Involvement Round 2 Input on Alternatives for Further Study
Northeast Corridor Alternatives Analysis Public Involvement Round 2 Input on Alternatives for Further Study Feb. 7-9, 2012 Agenda Review project background Progress summary Recommended alternatives for
More informationTEXAS RURAL TRANSPORTATION PLAN 2035 (TRTP 2035)
TEXAS RURAL TRANSPORTATION PLAN 2035 (TRTP 2035) Helping shape the future of rural Texas Texas Rural Transportation Plan 2035 Texas Rural Transportation Plan 2035 What is it? Component of the Statewide
More informationRichmond Area MPO Regional Priority Transportation Projects
Regional Priority Transportation Projects September 27, 2007 HANOVER GOOCHLAND ASHLAND POWHATAN RICHMOND HENRICO NEW KENT CHESTERFIELD CHARLES CITY 9211 Forest Hill Avenue, Suite 200 Richmond, Virginia
More informationArterial Bus Rapid Transit. System Policy Oversight Committee April 7, 2014
Arterial Bus Rapid Transit System Policy Oversight Committee April 7, 2014 1 Meeting Agenda Welcome and Introductions A Line - Project Status Shelter and Pylon Development Arterial BRT Branding Update
More informationDowntown Parking/Wayfinding Study. Review of Recommendations to City Council: January 16, 2018
Downtown Parking/Wayfinding Study Review of Recommendations to City Council: January 16, 2018 Tonight s Focus Objectives & Timeline Recap Study Findings Present Staff Recommendations 2018 Action items
More informationRocky Mount. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation
2020 Transportation Plan Developed by the Transportation Planning Division of the Virginia Department of Transportation in cooperation with the U.S. Department of Transportation, Federal Highway Administration
More informationWaco Rapid Transit Corridor (RTC) Feasibility Study
Waco Rapid Transit Corridor (RTC) Feasibility Study Chris Evilia, Director of Waco Metropolitan Planning Organization Allen Hunter, General Manager Waco Transit System Jimi Mitchell, Project Manager AECOM
More informationBus Stop Optimization Study
Bus Stop Optimization Study Executive Summary February 2015 Prepared by: Passero Associates 242 West Main Street, Suite 100 Rochester, NY 14614 Office: 585 325 1000 Fax: 585 325 1691 In association with:
More informationSUPPORTING TOD IN METRO CHICAGO
www.rtachicago.org SUPPORTING TOD IN METRO CHICAGO Tuesdays at APA November 18, 2014 OVERVIEW OF RTA 2 11/18/2014 Tuesdays at APA: Supporting TOD in Metro Chicago RTA Region 8.5 million people 3,700 square
More information5. OPPORTUNITIES AND NEXT STEPS
5. OPPORTUNITIES AND NEXT STEPS When the METRO Green Line LRT begins operating in mid-2014, a strong emphasis will be placed on providing frequent connecting bus service with Green Line trains. Bus hours
More informationCorridor Management Committee. March 7, 2012
Corridor Management Committee March 7, 2012 2 Today s Topics SWLRT Project Office Update Engineering Services Procurement Update Legislative Leadership Tour Annual New Starts Report Update on Proposed
More informationFREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS 2018 What is the More MARTA Atlanta program? The More MARTA Atlanta program is a collaborative partnership between MARTA and the City of Atlanta to develop and implement a program
More informationUS 81 Bypass of Chickasha Environmental Assessment Public Meeting
US 81 Bypass of Chickasha Environmental Assessment Public Meeting March 14, 2013 Introductions ODOT FHWA SAIC Meeting Purpose Present need for bypass Provide responses to 10/04/11 public meeting comments
More informationUtility work, road construction substantially done on Fourth Street
November 2010 Fourth Street in downtown is reopen to vehicle traffic between Minnesota and Broadway streets. Utility relocation and road construction are substantially complete there. Utility work, road
More informationBackground Information about the Metrobus 29 Lines Study
Background Information about the Metrobus 29 Lines Study Questions Overview of Existing Service Q. Why is the study being conducted? A. The 29 Lines provide an important connection between Annandale and
More informationSOUTHERN GATEWAY. Transportation and Trinity River Project Committee 11 May 2015
SOUTHERN GATEWAY Transportation and Trinity River Project Committee 11 May 2015 Southern Gateway Project History Began in 2001 as a Major Investment Study [ MIS ], Schematic, and Environmental Assessment
More informationThe Eastern Connector Study November, 2007 planning for the future
The Eastern Connector Study November, 2007 planning for the future In late 2006, Albemarle County and the City of Charlottesville jointly initiated the Eastern Connector Corridor Study. The Project Team
More informationMunicipal Road and Bridge Revolving Loan Fund Program Summary Rhode Island Department of Transportation
Municipal Road and Bridge Revolving Loan Fund 2014 Program Summary Rhode Island Department of Transportation The Basics The FY2014 Budget passed by the Rhode Island General Assembly included Article 20,
More informationPoint A Point B Point C Point D. Fulton County Board of Commissioners and Mayors Meeting December 14, 2017
Fulton County Board of Commissioners and Mayors Meeting December 14, 2017 Master Plan Overview Phase 1 Community Vision and Existing Transit Conditions Phase 2 Scenario Development Phase 3 Transit Master
More informationEast Link Extension. September 16, Bel-Red Conclusion to Final Design Open House Public Involvement Summary
East Link Extension September 16, 2014 Bel-Red Conclusion to Final Design Open House Public Involvement Summary Table of contents 1 Background 2 Overview 2 Notification 3 Open House Overview 4 Comment
More informationPlattsburgh Downtown Parking Study
Plattsburgh Downtown Parking Study Study Update October 2017 Powered by Purpose of Study Engage Community in Parking Discussion Assess Current Conditions Parking Demand Patron Service Levels Administration
More informationAction 6A: HRTAC FY2018 FY2023 Funding Plan
Action 6A: HRTAC 2018 2023 Funding Plan Presentation to: HRTAC Finance Committee Kevin Page, HRTAC Liang Shan, PFM June 5, 2017 PFM Financial Advisors LLC 300 S. Orange Avenue Ste 1170 Orlando, Florida
More informationJOINT FACILITIES ADVISORY COMMISSION. ART and APS Bus Parking Informational Session July 27, :30 pm
ART and APS Bus Parking Informational Session July 27, 2017 7 8:30 pm 2 Agenda Introductions & overview APS Bus Parking APS Bus Facts APS Bus Operations ART Bus Parking Story of ART and its role in County
More informationBROWARD BOULEVARD CORRIDOR TRANSIT STUDY
BROWARD BOULEVARD CORRIDOR TRANSIT STUDY FM # 42802411201 EXECUTIVE SUMMARY July 2012 GOBROWARD Broward Boulevard Corridor Transit Study FM # 42802411201 Executive Summary Prepared For: Ms. Khalilah Ffrench,
More informationThe Engineering Department recommends Council receive this report for information.
CORPORATE REPORT NO: R161 COUNCIL DATE: July 23, 2018 REGULAR COUNCIL TO: Mayor & Council DATE: July 19, 2018 FROM: General Manager, Engineering FILE: 8740-01 SUBJECT: Surrey Long-Range Rapid Transit Vision
More informationWest Broadway Reconstruction/LRT Design. March 19, 2015
West Broadway Reconstruction/LRT Design March 19, 2015 1 Meeting Agenda 6:05 6:30 PM Brief presentation What we heard Project overview 6:30 8:00 PM Visit Six Topic Areas Road and LRT design elements Pedestrian
More informationInformal Business Discussion Minutes Tuesday, May 3, :00 PM 1. Transportation
Official Informal Business Discussion Minutes Tuesday, May 3, 2016 3:00 PM Present: Charlotte J. Nash, Jace Brooks, Lynette Howard, Tommy Hunter, John Heard 1. Transportation Comprehensive Transportation
More informationTransportation Committee Revised Project Scope and Cost Estimate. November 23, 2015
Transportation Committee Revised Project Scope and Cost Estimate November 23, 2015 1 Today s Topics Revised Project Scope Revised Cost Estimate Municipal Approval Action 2 3 Revised Project Scope Project
More informationRichmond Area MPO Regional Priority Transportation Projects
Regional Priority Transportation Projects October 12, 2006 Town of Ashland Counties of Charles City Chesterfield Goochland Hanover Henrico New Kent Powhatan City of Richmond Richmond Regional Planning
More information6/6/2018. June 7, Item #1 CITIZENS PARTICIPATION
June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More informationStoughton Center Parking
Stoughton Center Parking Existing Conditions and Observations October 4, 2017 Agenda Introduction Metropolitan Area Planning Council Project Team Parking Studies Background Scope of Work Study Area Survey
More informationExecutive Summary October 2013
Executive Summary October 2013 Table of Contents Introduction... 1 Rider Transit and Regional Connectivity... 1 Plan Overview... 2 Network Overview... 2 Outreach... 3 Rider Performance... 4 Findings...
More informationProposed HRTAC FY2018 FY2023 Plan of Finance Update
Chair, MICHAEL J. HIPPLE Vice Chair, LINDA T. JOHNSON Executive Director, KEVIN B. PAGE Proposed HRTAC 2018 2023 Plan of Finance Update HRTAC 2018 2023 Six Year Operating and Capital Program of Projects
More informationPublic Meeting. City of Chicago Department of Transportation & Department of Housing and Economic Development
Public Meeting City of Chicago Department of Transportation & Department of Housing and Economic Development Funded by Regional Transportation Authority September 12, 2011 In partnership with Presentation
More informationHDR Engineering. HART North / South. Tampa Bay Applications Group Meeting May 14, 2009
HDR Engineering HART North / South BRT Corridor PD&E Tampa Bay Applications Group Meeting May 14, 2009 1 Agenda Update on Project Development and Environment (PD&E) Study Project Overview System Branding
More informationBusiness Advisory Committee. November 3, 2015
Business Advisory Committee November 3, 2015 1 Today s Topics DEIS Cost Estimate 2 Assumptions Revised Cost Estimate Revised Project Scope Cost Estimate Overview Position Statement Discussion Municipal
More informationPeninsula Corridor Electrification Project (PCEP)
Peninsula Corridor Electrification Project (PCEP) Q4 Quarterly Update #11 April 1 June 30, 2017 JPB Board Meeting August 3, 2017 Agenda Item # 8a Electrification - Infrastructure Design Build Contract
More informationCitizens Committee for Facilities
Citizens Committee for Facilities AGENDA Thursday, December 11, 2014 City Council Chambers 305 3 rd Avenue East -Twin Falls, Idaho 11:30 A.M. AGENDA ITEMS Purpose By 1. Discussion and possible action on
More informationA Transit Plan for the Future. Draft Network Plan
A Transit Plan for the Future Draft Network Plan Project Overview and Status Completed Market Analysis and Service Evaluation. Developed Plan Framework and Guiding Principles. Developed a draft Five Year
More informationElizabeth River Crossings Study June 2008
Elizabeth River Crossings Study June 2008 T08-07 HAMPTON ROADS METROPOLITAN PLANNING ORGANIZATION Chesapeake Poquoson * Clifton E. Hayes, Jr. * Charles W. Burgess, Jr. Gloucester County Portsmouth * Lane
More information4.0 TIER 2 ALTERNATIVES
4.0 TIER 2 ALTERNATIVES The Tier 2 Alternatives represent the highest performing Tier 1 Alternatives. The purpose of the Tier 2 Screening was to identify the LPA utilizing a more robust list of evaluation
More informationAppendix C. Parking Strategies
Appendix C. Parking Strategies Bremerton Parking Study Introduction & Project Scope Community concerns regarding parking impacts in Downtown Bremerton and the surrounding residential areas have existed
More informationCEDAR AVENUE TRANSITWAY Implementation Plan Update
CEDAR AVENUE TRANSITWAY Implementation Plan Update EECUTIVE SUMMARY DECEMBER 2015 Executive Summary In 2013, the Twin Cities metropolitan area s first bus rapid transit (BRT) line, the METRO Red Line,
More informationPARKING OCCUPANCY IN WINDSOR CENTER
PARKING OCCUPANCY IN WINDSOR CENTER TOWN OF WINDSOR, CONNECTICUT REPORT JUNE 2017 CONTENTS Background... 3 Other Relevant Data... 3 Parking Survey Design... 6 Parking Supply Inventory... 6 Parking Demand
More informationMay 23, 2011 APTA Bus & Paratransit Conference. Metro ExpressLanes
May 23, 2011 APTA Bus & Paratransit Conference Metro ExpressLanes Program Overview > Conversion of HOV lanes to HOT lanes on I-10 and I-110 > Multi-modal Integrated Corridor Emphasis > 1 of 6 Nationwide
More informationCITY OF ANN ARBOR, MICHIGAN 301 E. Huron St., P.O. Box 8647 Ann Arbor, Michigan
Date: Wednesday, June 18, 2014 Location: Ann Arbor District Library Attendees: 14 citizen attendees Ann Arbor Station Environmental Review Citizen Working Group Meeting Notes Meeting #3 The third meeting
More informationNEW YORK CITY CARSHARE PILOT
NEW YORK CITY CARSHARE PILOT Community Board Briefing February 2018 1 Concept and Context 1 nyc.gov/dot 2 CHALLENGE OF CONTINUED GROWTH The City must use its streets as efficiently as possible to move
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of April 24, 2004 DATE: April 14, 2004 SUBJECT: Arlington Boulevard (U.S. 50) Bridge Deck Replacement at Washington Boulevard - Overhead Utility
More informationSamTrans Business Plan Update May 2018
SamTrans Business Plan Update May 2018 SamTrans Business Plan Core Principles: 1. Sustain and enhance services for the transit-dependent 2. Expand and innovate mobility services 3. Promote programs that
More informationMetro Transit Update. Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office. John Dillery, Senior Transit Planner
Metro Transit Update Christina Morrison, Senior Planner Metro Transit BRT/Small Starts Project Office John Dillery, Senior Transit Planner Metro Transit Service Development May 16, 2013 1 Transit Planning
More informationMPO Staff Report Technical Advisory Committee: July 12, 2017
MPO Staff Report Technical Advisory Committee: July 12, 2017 RECOMMENDED ACTION: 2 nd TAC Meeting with Kimley-Horn/WSB in Updating the Street/Highway Element of 2045 Metropolitan Transportation Plan. Matter
More informationTECHNICAL COORDINATING COMMITTEE (TCC) UPDATE PRESENTATION APRIL 26, 2017
TECHNICAL COORDINATING COMMITTEE (TCC) UPDATE PRESENTATION APRIL 26, 2017 THE TRANSIT DEVELOPMENT PLAN (TDP) WILL IDENTIFY: TRANSIT NEEDS AND DESIRES OF THE COMMUNITY COMMUNITY AND AGENCY STAKEHOLDER S
More informationCTA Blue Line Study Area
1 CTA Blue Line Study Area HISTORY OF THE CTA BLUE LINE / I-290 SYSTEM Blue Line / I-290 infrastructure is 55 years old First integrated transit / highway facility in the U.S. PROJECT STUDY AREA EXISTING
More informationLeveraging Land Use Changes through Transportation Funding
Leveraging Land Use Changes through Transportation Funding Railvolution 2005 September 10, 2005 James Corless Senior Planner What is the MTC region? 9 7 101 26 San Francisco Bay Area counties Million people;
More informationParatransit Overview O & O Presentation January 11, 2018
Paratransit Overview O & O Presentation January 11, 2018 Our vision is to be a valued regional partner that drives prosperity and makes life better for our community. Our mission is to connect Hampton
More informationVDOT Unused Facilities
VDOT Unused Facilities Appropriation Act Item 457 K.1 (2010) Report to the Chairmen of House Appropriations and Senate Finance Committees Virginia Department of Transportation 1401 East Broad Street Richmond,
More informationNORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018
NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3 April 19, 2018 NHHIP OVERVIEW NHHIP divided into 3 Segments: Segment 1: I-45: Beltway 8 to I-610 (9 mi) 45 Segment 2: I-45: I-610 to I-10 (3
More informationW&OD TRAIL BRIDGE OVER LEE HIGHWAY I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237)
W&OD TRAIL BRIDGE OVER LEE HIGHWAY A COMPONENT OF THE I-66 EASTBOUND WIDENING INSIDE THE BELTWAY FROM THE DULLES CONNECTOR ROAD (ROUTE 267) TO FAIRFAX DRIVE (ROUTE 237) October 11, 2018 Bill Cuttler, PE
More informationI-20 EAST TRANSIT INITIATIVE Tier 1 and Tier 2 Alternatives Screening Report EXECUTIVE SUMMARY
EXECUTIVE SUMMARY The purpose of this report is to document the results of the Tier 1 and Tier 2 Screening of alternatives for the I-20 East Transit Initiative. The two-tier screening process presented
More informationI-405 and SR 522/NE 145th Bus Rapid Transit. Elected Leadership Groups Meeting November 30, 2018
I-405 and SR 522/NE 145th Bus Rapid Transit Elected Leadership Groups Meeting November 30, 2018 Agenda Welcome and Introductions Public Comment BRT Connection in Bothell Common Elements: Bus base, Station
More informationValley Metro Overview. ITE/IMSA Spring Conference March 6, 2014
Valley Metro Overview ITE/IMSA Spring Conference March 6, 2014 Valley Metro Who Are We? Operate Regional Transit Services Valley Metro and Phoenix are region s primary service providers Light Rail and
More informationExhibit A Sound Transit Board Resolution R Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup
Exhibit A Sound Transit Board Resolution R2016-07 Selecting the bicycle, pedestrian, and parking access improvements to be built for the Puyallup Access Improvement Project. RESOLUTION NO. R2016-07 Selecting
More informationMETRO Orange Line BRT American Boulevard Station Options
METRO Orange Line BRT American Boulevard Station Options Bloomington City Council Work Session November 18, 2013 Christina Morrison BRT/Small Starts Project Office Coordinating Planning and Design AMERICAN
More informationSTH 60 Northern Reliever Route Feasibility Study Report
#233087 v3 STH 60 Northern Reliever Route Feasibility Study Report Washington County Public Works Committee Meeting September 28, 2016 1 STH 60 Northern Reliever Route Feasibility Study Hartford Area Development
More informationSnelling Bus Rapid Transit. May 13, 2013 Technical Advisory Committee Meeting #1
Snelling Bus Rapid Transit May 13, 2013 Technical Advisory Committee Meeting #1 1 Today s meeting TAC Introductions Project Overview Arterial BRT Concept Background Snelling Corridor Plan, Funding & Schedule
More informationSH 249 IN GRIMES COUNTY. Open House April 3, 2014
SH 249 IN GRIMES COUNTY Open House April 3, 2014 Meeting Agenda Purpose of Meeting Today: Review the purpose and need for the SH 249 Grimes County project Review the proposed project and alternatives Discuss
More informationA Plan to Connect Baltimore
A Plan to Connect Baltimore What is BaltimoreLink? Improve service quality and reliability Maximize access to high-frequency transit Strengthen connections between the MTA s bus and rail routes Align the
More informationParking Management Element
Parking Management Element The State Transportation Planning Rule, adopted in 1991, requires that the Metropolitan Planning Organization (MPO) area implement, through its member jurisdictions, a parking
More informationCREATING CONNECTIONS IN THE CITY OF WATERLOO
CREATING CONNECTIONS IN THE CITY OF WATERLOO GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE METROLINX ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX METROLINX PRESENTATION TO
More informationUS 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT
US 50/SOUTH SHORE COMMUNITY REVITALIZATION PROJECT April 25, 2012 Tahoe Transportation District (TTD) Tahoe Transportation District (TTD) established 1980 as Bi-State Agency TTD Goals Implement Transportation
More informationL. A. Metro s Parking Management Program Principles Applied. October 17, 2011 Rail-Volution, Washington D.C.
Los Angeles County Metropolitan Transportation Authority L. A. Metro s Parking Management Program Principles Applied October 17, 2011 Rail-Volution, Washington D.C. What is Parking Management? Various
More informationGreen Line LRT: Beltline Recommendation Frequently Asked Questions
Green Line LRT: Beltline Recommendation Frequently Asked Questions June 2017 Quick Facts Administration has evaluated several alignment options that would connect the Green Line in the Beltline to Victoria
More information6/11/2018. June 7, Item #1 CITIZENS PARTICIPATION
June 7, 2018 Item #1 CITIZENS PARTICIPATION 1 Item #2 APPROVAL OF MINUTES Item #3 TRAC GOALS, FRAMEWORK & AGENDA REVIEW 2 COMMITTEE GOALS Learn about Southern Nevada s mobility challenges, new developments
More informationAppendix 11-B 24-HOUR RAINFALL DEPTH DATA FOR VIRGINIA
Appendix 11-B 24-HOUR RAINFALL DEPTH DATA FOR VIRGINIA Table of Contents TABLES Table 11-B.1. NRCS Implementation of NOAA s ATLAS 14 Rainfall Data for Virginia 11-B-2 FIGURES Figure 11-B-1. NRCS Rainfall
More informationConnected and Automated Vehicle Program Plan. Dean H. Gustafson, PE, PTOE VDOT Statewide Operations Engineer February 10, 2016
Connected and Automated Vehicle Program Plan Dean H. Gustafson, PE, PTOE VDOT Statewide Operations Engineer February 10, 2016 Connected Vehicle Program continues to evolve at the National Level AASHTO
More informationRegional Safety Action Plan and Safety Investigation Program
Regional Safety Action Plan and Safety Investigation Program Technical Advisory Committee Meeting #3 Insert image credit here (or delete) April 17, 2018 Number of Serious Injuries New York State Serious
More informationMobility Corridor Updates. Transit & Active Transportation Projects
Mobility Corridor Updates Transit & Active Transportation Projects Manjeet Ranu, SEO East San Fernando Valley Transit Corridor Metro Board LPA selection: June 2018 Recently awarded $200 million in Senate
More informationMarch 2, 2017 Integrating Transportation Planning, Project Development, and Project Programming
COORDINATION WITH VDOT DISTRICTS TO DELIVER IMPLEMENTABLE IMPROVEMENT PROJECTS March 2, 2017 Integrating Transportation Planning, Project Development, and Project Programming PRESENTATION OUTLINE What
More informationHarlem Avenue between 63 rd and 65 th
Harlem Avenue between 63 rd and 65 th Public Meeting #2 March 13, 2018 Summit Park District Welcome to the second Public Meeting for the preliminary engineering and environmental studies of Illinois 43
More informationM E M O R A N D U M INTRODUCTION. POTENTIAL TDM STRATEGIES Marketing & Management. Residents & Employees. Exhibit 6
Exhibit 6 M E M O R A N D U M To: From: Joe Ernst and Bryan Graves Nelson\Nygaard Date: February 6, 2015 Subject: Preliminary TDM Strategies INTRODUCTION The memorandum provides an overview of potential
More informationPolicy Advisory Committee Meeting November 13, 2013
Midtown Corridor Alternatives ti Analysis Policy Advisory Committee Meeting November 13, 2013 Today s Agenda Introductions Follow up from September meeting Alternatives review Process update Key evaluation
More informationTransit Access Study
West of Hudson Regional Transit Access Study Open House presentation July 20, 2010 1 Agenda Progress To date Summary of Level 2 Alternatives and Screening Service Plans Bus and Rail Operating and Capital
More informationParking Management Strategies
Parking Management Strategies Policy Program Potential Effectiveness (percent reduction in demand) Comments Parking Pricing Unbundling and Cash-Out Options Reduced Parking Requirements Transit/TOD Supportive
More informationWelcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date,
Welcome The City has undertaken a naming exercise for the existing and future LRT lines. The SE to West LRT, as the project has been called to date, is now called the Valley Line. We are here to present
More informationADM ASSIGNED POLICE VEHICLE PROGRAM
Newport News Police Department - Administrative Manual ADM-545 - ASSIGNED POLICE VEHICLE PROGRAM Amends/Supersedes: ADM-545 (10/05/2007) Date of Issue: 03/17/2010 I. DEFINITIONS A. Marked Police Vehicle:
More informationMajor Widening/New Roadway
Revised Evaluation s Major Widening/New Roadway This page provides a summary of any revisions made to the draft scores presented at the October th Attributable Funds Committee meeting. The information
More informationGeary Corridor Bus Rapid Transit
Geary Corridor Bus Rapid Transit Institute of Transportation Engineers Luncheon Meeting October 17, 2013 SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Geary
More informationAppendix H: Tier 2 Evaluation Methodology and Results February 2017
Appendix H: Tier 2 Evaluation Methodology and Results February 2017 Table of Contents Overview... 1 Community Transit Priorities... 1 Tier 2 Evaluation Methodology... 2 Evaluation Corridors... 2 Modal
More informationWELCOME. Transit Options Amherst - Buffalo Public Workshops
WELCOME Transit Options Amherst - Buffalo Public Workshops Sponsored by Niagara Frontier Transportation Authority Greater Buffalo Niagara Regional Transportation Council Where do you live? Where do you
More informationTransportation Sustainability Program
Transportation Sustainability Program Photo: Sergio Ruiz San Francisco 2016 Roads and public transit nearing capacity Increase in cycling and walking despite less than ideal conditions 2 San Francisco
More informationAttachment 5 Eglinton West LRT Planning and Technical Update
Eglinton West LRT Planning and Technical Update 1. Introduction In July 2016, City Council approved an Eglinton West LRT with between 8 and 12 stops between Mount Dennis and Renforth Gateway, and up to
More informationPlanning for Sustainability: Electric Vehicles
Planning for Sustainability: Electric Vehicles NYSMPO Conference June 23, 2015 Jennifer Ceponis Sr Transportation Planner Clean Communities Coordinator Clean Cities Mission To advance the energy, economic,
More informationCREATING CONNECTIONS IN WATERLOO REGION
CREATING CONNECTIONS IN WATERLOO REGION GORD TROUGHTON, DIRECTOR, CORRIDOR INFRASTRUCTURE CHRIS BURKE, DIRECTOR, SERVICE PLANNING ERIN MOROZ, DIRECTOR, COMMUNICATIONS AND COMMUNITY RELATIONS METROLINX
More informationExtending TRACKS. Preliminary design plan review underway. Public comment and approval process in May & June. Municipal Consent Process
Extending TRACKS Issue 5 Spring 2014 Preliminary design plan review underway Public comment and approval process in May & June Residents and businesses along the Southwest LRT (METRO Green Line Extension)
More information