5. Contractor Information 3M Model 2300 Series System Layout Checklist

Size: px
Start display at page:

Download "5. Contractor Information 3M Model 2300 Series System Layout Checklist"

Transcription

1 5. Contractor Information 3M Model 2300 Series System Layout Checklist This checklist contains the information necessary to provide the environment required to successfully install your new Model 2300 system. 4 1/2 in. [114 mm] 36 in. [914 mm] Alarm Light Alarm Light Patron Counter/ Diagnostic Display 67 1/2 in. [1,71 m] 67 1/2 in. [1,71 m] Power Cord 38 in. [965 mm] Power Requirements 3M Detection Systems are sophisticated computer based devices which require high quality surge and noise free electrical power for optimum performance. Energy Profile 1. Single phase power is required. 2. Designed for worldwide use with internal (manual) switch selection for voltage from 100 to 240 VAC, 50 or 60 Hz. 3. Maximum RMS current draw: a. 100/120 VAC: 0.8A b. 210/240 VAC: 0.4A 4. Power cord: the Model 2300 is supplied with a 16 ga., 3-wire, S-rating, 14-foot [4,26 m] long, NEMA 5-15P plug type power cord. The customer must supply an electrical outlet within the power cord length. 5. A dedicated circuit is not required but is recommended to prevent overloading and loss of security. 6. A minimum circuit capacity of 15A is recommended. 7. Circuit loading must not exceed 50% of the rated circuit current to ensure voltage stability System Placement Relative to Interfering Objects The system must be placed in an environment free of certain types of electrical interference. Check the following list of items to verify your system will be located an adequate distance from sources of electrical interference. Computers (CRT) Model 2301 with Baseplate C For optimum performance, computer terminals should be placed at least 3 feet [914 mm] from the closest lattice. Multiple computers will generally require a greater distance from the Increase the distance for each additional computer by 1.5 feet [457 mm]. For example, if there are 5 computers within 10 feet [3 m]; the minimum distance for each computer is as follows: Computer #1: 3 feet [914 mm] Computer #2: 4.5 feet [1,37 m] Computer #3: 6 feet [1,82 m] Computer #4: 7.5 feet [2,26 m] Computer #5: 9 feet [2,74 m] Model 2302 Direct Mount Computers that are more than 10 feet [3 m] away from the 2300 should not be a problem. January

2 Copy Machines Energy Management Large Metal Objects (LMO) Metal Framed Doors, Windows and Counters Protected Material Walls (Steel Studs) System Accessories Alarm/Disable Box Distance Between Systems Exit Control Hardware Copy machines are not allowed within 5 feet [1,5 m] of the closest lattice. Heating, ventilation and Air Conditioning Energy Management Systems may generate high levels of electronic noise which can reduce the performance level of the Model Please contact EAS Technical Service for more information. Large metal objects are not allowed within 2 feet [609 mm] of a lattice. Examples include: refrigerators, heavy support beams, heating/air conditioning duct work. ADA (Americans with Disabilities Act) requires a 4-foot [1,2 m] clear space at exit doors for wheelchair maneuvering space. This is the recommended system placement. The closest lattice of the Model 2300 system should be located at least 3 feet [914 mm] from a metal door frame. Books and other protected articles should be at least 3 feet [914 mm] from the closest point of the security system. Plan layout so that patrons will not congregate or wait in line within 3 feet [914 mm] of a lattice. Walls with steel studs are not allowed within 3 feet [914 mm] of the closest lattice. We recommend the use of wood 2 x 4s for wall studs within 3 feet [914 mm] of the system. The optional alarm/disable box is wired to the lattice base. Our standard installation includes 27 feet [8,3 m] of ¼-inch [6 mm] diameter wire. Additional wire length can be purchased at an upcharge for time and material. Use wire mold or ½-inch [13 mm] diameter conduit to protect the wiring. The minimum distance between two Model 2300 systems is 12 inches [304 mm]. The minimum distance to a Model 1365, 1370, or 1850 system is 12 inches [304 mm]. More than two Model 1365, 1370, 1850, or 2300 systems require 18 inches [456 mm] between them. The minimum distance to a Model 3800 system is 30 feet [9,14 m]. The minimum distance to a Model 3500 is 20 feet [6,1 m]. All metal exit control hardware must be located a minimum of 12 inches [304 mm] from each lattice. If a metal rail is placed parallel to the lattice, it must be placed at least 2 feet [609 mm] away from the lattice. Metal railings surrounding the system using two or more horizontal members must be a minimum of 3 feet [914 mm] from each lattice. Alvarado, Accent, and Lawrence are approved vendors for exit control hardware.! Library Systems 3M Center, Bldg N-14 St. Paul, MN January % Pre-consumer waste paper 10% Post-consumer waste paper 3M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M

3 Contractor Installation Instructions for 3M Model 2301/2302 Buried Power Materials Required Note Read all installation instructions before starting procedures. If there are any questions, call 3M Technical Service option #6. Item Supplier 1. Steel floor box, conduit, and associated wiring Electrical Contractor 2. Floor box cover plate, gasket, and carpet ring if needed Electrical Contractor 3. AC power cord (part of Model 2301/2302 System) 3M 4. Device to cut trench in floor Contractor 5. Material to fill in around and cover conduit after trench is cut Contractor Installation Procedure 1. Install a steel floor box. Position box per Model 2301/2302 Contractor Layout Plan and Figure 1. Floor box is typically 5 inches x 5 inches [127 x 127 mm], with a 4 inch [101 mm] cover flange. Some variations from the different suppliers utilize boxes with pre-pour and after-pour level adjustments. If necessary, request assistance from a 3M Service Technician in positioning floor box. 2. Complete wiring from floor box to Amp circuit, preferably dedicated for the security system. 3. At system installation, terminate system power cord to circuit wires, install gasket, cover plate, and carpet ring if required. Allow an extra 2 feet [609 mm] of power cord to be stored in the Model 2300 pedestal. 4. The 3M Service Technician will energize and check out the system.! Library Systems 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper 3M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January

4 Contractor Installation Instructions for 3M Model 2301 Floor Mounted System with Buried Cables (36 in. Corridor) Note Read all installation instructions before starting this installation procedure. If there are any questions, contact 3M Library Systems, Technical Service, , option #6. If AC power wiring is also buried, see Contractor Installation Instructions for 3M Model 2301/2302, Buried Power. Materials Required Item Supplier 1. Model 2301 and mounting hardware 3M 2. Rigid non-metallic conduit, inches [38-50 mm] I.D. as defined in Figure 1 Contractor 3. Concrete as required to pour floor Contractor 4. Device to cut trench in floor (for existing construction) Contractor 5. Materials to hold conduit in position while pouring floor Contractor 6. Finish flooring Contractor Installation Procedure These instructions will be used by 3M installers and the contractor to ensure proper installation of the Model 2301 Detection System and buried cables. 1. At the request of the contractor, the 3M installer will visit the site to examine the site for an acceptable environment and to locate the system in an acceptable location. System setup and testing may be required to verify the location is acceptable. 2. Using the Model 2301 Contractor Layout Plan, the contractor will position and install the Panel-to-Panel Conduit and AC Power Conduit for each system. See Figure 1. For installation details for buried AC power, see Contractor Installation Instructions for 3M Model 2301/2302 Buried Power. The Panel-to-Panel Conduit must have a minimum I.D. of inches [38-50 mm] to accept cables. If this conduit has an I.D. of less than 1.5 inch [38 mm] there will be an additional charge at installation. 3. Each bend radius in 1.5 inch [38 mm] conduit must be typical to the electrical industry. Water type 90 bends or fittings are not acceptable. 4. The contractor must avoid placing conduit or reinforcing rods in the anchor area of the mounting feet. Concrete in the area under the system mounting hardware must be a minimum of 3.5 inches [89 mm] thick for anchoring. 5. The contractor will complete the sub floor and finished floor in the installation area and will complete the AC power wiring to the site. 6. The 3M installer will install the system, anchors, and panel-to-panel wiring. 7. The contractor will provide an electrician for AC power wiring hookup to the system power cord. 8. The 3M installer will energize the system and will complete operational checks and adjustments. 5-4 January 2000

5 3M Model 2301 Floor Mount (36 in., Corridor) Figure 1 See Model 2301 Contractor Layout Plan for exact location of conduits. Location is critical because conduits must enter openings in system mounting hardware. Notes 1. Maximum depth of inches [38-50 mm] I.D. conduit is 18 inches [457 mm] due to length of panel-to-panel cables. 2. Panel-to-panel conduit must extend 1/4-1/2 inch [6-12 mm] above the finished floor. 3. Conduit and reinforcing rod must not interfere with anchor bolt locations. 4. Floor box for AC power must be located on the same side of the system as the patron counter. 5. For existing floors, the floor must be core drilled or trenched to accept buried conduits. Trench width should be kept to a minimum to avoid weakening the concrete in the anchor area. 6. Floor in area of mounting harware must be flat, level, and high quality concrete. Minimum concrete thickness is 3.5 inches [89 mm]. 7. See "3M Model 2300 System Layout Checklist" for minimum distances to interfering objects. January

6 5-6 January 2000 This page intentionally left blank.

7 Model 2301 Contractor Layout Plan - Buried Panel to Panel Wiring Conduit 36" Corridor Width Note: The Installation and Accurate Placement of this Conduit is the Customers/Contractors Responsibility in. [6-12 mm] Notes: 1. Power source can be from either side of M If underground power is required, use a Flush Mount Floor Box, terminate the power cord in floor box. See "Installation Instructions - Under Floor Power". 3. Floor must be level and flat in area under mounting foot for each panel, and a minimum of 3 1/2 inches [89 mm] thick. CL Conduit Radius to be Typical to Electrical Industry Standards Section A-A 1 1/2-2 in. [38-50 mm] I.D. Rigid Non-Metallic Conduit CL Conduit and reinforcing rod must not be located in anchor hole area under mounting foot. Cable supplied for buried wiring is adequate for conduit buried a maximum depth of 18 inches [457 mm] in. [1,02 m] 0.6 in. [15 mm] inch corridor complies with ADA guidelines for corridor widths. Electrical Supply Flush Service Floor Box Hardwired to Power Cord 4.1 in. [104 mm] A Perimeter of System Mounting Foot, for Reference Only! Floor to Be Flat and Level In This Area. 4 x 4 in. [101 x 101 mm] Cutout for Panel - Panel Conduit/Wire 21 in. [533 mm] A See Model 2300 Layout Checklist for Minimum Distances to Interfering Object. 2.5 in. [63,5 mm] min. System Depth = 38 in. [965 mm] 1 1/2-2 in. [38-50 mm] I.D. Electrical Conduit Non-Metalic System Width = 45 in. [1,14 m] CL 10.5 in. [266 mm] For Further Information or Assistance, Please Contact: 3M Library Security Systems 3M Center Bldg N-14 St. Paul, Minnesota Library Systems 3/8 in. [9,5 mm] diameter anchor locations (8), holes to be drilled by 3M technician. Keep electrical conduit and reinforcing rod clear from this area. 5 ft. [1,52 m] min. System C to Door L 4.5 in. [114 mm] A 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January

8 5-8 January 2000 This page intentionally left blank.

9 Contractor Installation Instructions for 3M Model 2302 Floor Mounted System with Buried Cables (36 in. Corridor) Note Read all installation instructions before starting this installation procedure. If there are any questions, contact 3M Library Systems, Technical Service, , option #6. If AC power wiring is also buried, see Contractor Installation Instructions for 3M Model 2301/2302, Buried Power. Materials Required Item Supplier 1. Model 2302 and mounting hardware 3M 2. Rigid non-metallic conduit, inches [38-50 mm] I.D. as defined in Figure 1 Contractor 3. Concrete as required to pour floor Contractor 4. Device to cut trench in floor (for existing construction) Contractor 5. Materials to hold conduit in position while pouring floor Contractor 6. Finish flooring Contractor Installation Procedure These instructions will be used by 3M installers and the contractor to ensure proper installation of the Model 2302 Detection System and buried cables. 1. At the request of the contractor, the 3M installer will visit the site to examine the site for an acceptable environment and to locate the system in an acceptable location. System setup and testing may be required to verify the location is acceptable. 2. Using the Model 2302 Contractor Layout Plan, the contractor will position and install the Panel-to-Panel Conduit and AC Power Conduit for each system. See Figure 1. For installation details for buried AC power, see Contractor Installation Instructions for 3M Model 2301/2302 Buried Power. The Panel-to-Panel Conduit must have a minimum I.D. of inches [38-50 mm] to accept cables. If this conduit has an I.D. of less than 1.5 inch [38 mm] there will be an additional charge at installation. 3. Each bend radius in 1.5 inch [38 mm] conduit must be typical to the electrical industry. Water type 90 bends or fittings are not acceptable. 4. The contractor must avoid placing conduit or reinforcing rods in the anchor area of the mounting feet. Concrete in the area under the system mounting hardware must be a minimum of 3.5 inches [89 mm] thick for anchoring. 5. The contractor will complete the sub floor and finished floor in the installation area and will complete the AC power wiring to the site. 6. The 3M installer will install the system, anchors, and panel-to-panel wiring. 7. The contractor will provide an electrician for AC power wiring hookup to the system power cord. 8. The 3M installer will energize the system and will complete operational checks and adjustments. January

10 3M Model 2302 Floor Mount (36 in., Corridor) Figure 1 See Model 2302 Contractor Layout Plan for exact location of conduits. Location is critical because conduits must enter openings in system mounting hardware. Notes 1. Maximum depth of inches [38-50 mm] I.D. conduit is 18 inches [457 mm] due to length of panel-to-panel cables. 2. Panel-to-panel conduit must extend 1/4-1/2 inch [6-12 mm] above the finished floor. 3. Conduit and reinforcing rod must not interfere with anchor bolt locations. 4. Floor box for AC power must be located on the same side of the system as the patron counter. 5. For existing floors, the floor must be core drilled or trenched to accept buried conduits. Trench width should be kept to a minimum to avoid weakening the concrete in the anchor area. 6. Floor in area of mounting hardware must be flat, level, and high quality concrete. Minimum concrete thickness is 3.5 inches [89 mm]. 7. See "3M Model 2300 System Layout Checklist" for minimum distances to interfering objects January 2000

11 Model 2302 Contractor Layout Plan - Buried Panel to Panel Wiring Conduit 36" Corridor Width Note: The Installation and Accurate Placement of this Conduit is the Customers/Contractors Responsibility in. [6-12 mm] Notes: 1. Power source can be from either side of M If underground power is required, use a Flush Mount Floor Box, terminate the power cord in floor box. See "Installation Instructions - Under Floor Power". 3. Floor must be level and flat in area under mounting foot for each panel, and a minimum of 3 1/2 inches [89 mm] thick. CL Conduit Radius to be Typical to Electrical Industry Standards 40.5 in. [1,02 m] Section A-A CL 1 1/2-2 in. [38-50 mm] I.D. Rigid Non-Metallic Conduit 40.5 in. [1,02 m] 0.6 in. [15 mm] CL 4. Conduit and reinforcing rod must not be located in anchor hole area under mounting foot. 5. Cable supplied for buried wiring is adequate for conduit buried a maximum depth of 18 inches [457 mm] inch corridor complies with ADA guidelines for corridor widths. Electrical Supply Flush Service Floor Box Hardwired to Power Cord 4.1 in. [104 mm] A Perimeter of System Mounting Foot, for Reference Only! Floor to Be Flat and Level In This Area. 4 x 4 in. [101 x 101 mm] Cutout for Panel - Panel Conduit/Wire 21 in. [533 mm] A See Model 2300 Layout Checklist for Minimum Distances to Interfering Object. 2.5 in. [63,5 mm] min. 1 1/2-2 in. [38-50 mm] I.D. Electrical Conduit Non-Metalic System Depth 38 in. [965 mm] System Width 85.5 in. [2,17 m] CL 10.5 in. [266 mm] For Further Information or Assistance, Please Contact: 3M Library Security Systems 3M Center Bldg N-14 St. Paul, Minnesota Library Systems 3/8 in. [9,5 mm] diameter anchor locations (12), holes to be drilled by 3M technician. Keep electrical conduit and reinforcing rod clear from this area. 5 ft. [1,52 m] min. System C to Door L 4.5 in. [114 mm] A 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January

12 5-12 January 2000 This page intentionally left blank.

13 3M Model 3500 Series System Layout Checklist This checklist contains the information necessary to provide the environment required to successfully install your new Model 3500 Detection System in. 8.5 in in. 8.5 in in in. 42 to 60 in. from floor to electrical enclosure base (within 10 feet of AC power receptacle) 42 to 60 in. from floor to electrical enclosure base (within 10 feet of AC power receptacle) 0.75 in. I.D. minimum nonmetallic Conduit 25 feet Cable maximum 1.25 to 2 in. I.D. nonmetallic Conduit 18 in. maximum depth 0.75 in. I.D. minimum nonmetallic Conduit 25 feet Cable maximum 1.25 to 2 in. I.D. nonmetallic Conduit For conduit spacing, conduit type and system location specifications see the Contractor Layout Plan and System Layout Check List. EAS-359C For conduit spacing, conduit type and system location specifications see the Contractor Layout Plan and System Layout Check List. 18 in. maximum depth EAS-358C Power Requirements 3M Detection Systems are sophisticated computer based devices which require high quality, surge and noise free electrical power for optimum performance. Energy Profile 1. Single-phase power is required. 2. Designed for global use with internal (manual) switch selection for voltages from 100 to 240 VAC, 50 or 60Hz. 3. Maximum RMS current draw: a. 100/120 VAC: 2 Amp b. 210/240 VAC: 1 Amp 4. The Model 3500 is supplied with a 16 gauge, 3-wire, S-rating, 10 ft. long, NEMA 5-15P plug type power cord. A power receptacle is required at the Electronic Enclosure, within the power cord length. 5. A dedicated circuit is not required but is recommended to prevent overloading and loss of security System Replacement Relative to Interfering Objects The system must be placed in an environment free of certain types of electrical interference. Check the following list of items to verify your system will be located at an adequate distance from sources of electrical interference. Computers (CRT) Doors/Windows Large Metal Objects Protected Materials Telephones Copiers AC Power Panels For optimum performance, computer terminals should be placed at least 7 ft. from the closest detection panel. If necessary, the computer terminal may be located between 4 and 7 ft. from the closest detection panel; however, the computer terminal may require a special shield, which is available at an additional cost. Metal framed windows, doors, counters, shelves, steel stud walls, and metal reinforced walls, must be a minimum of 18 in. from the detection panels. Large metal objects such as I beams, HVAC ducting, safes, etc., must be a minimum of 18 in. from the detection panels. Books and other protected items must be at least 3 ft. from the detection panels. Telephones must be a minimum of 7 ft. from the detection panels. Copiers must be a minimum of 5 ft. from the detection panels. AC Power panels must be a minimum of 5 ft. from the detection panels. January

14 Audio Systems Traffic Control Electronic Enclosure System Separation Stereo s, microphones, and audio amplifiers, must be a minimum of 10 ft. from the detection system. Traffic control posts must be a minimum of 12 in. from the panels. Metal Hardware railings with more than one horizontal member must be a minimum of 18 in. from the detection panels. The Model 3500 Electronic Enclosure must be a minimum of 4 ft. from the detection panels and not more than 25 ft. wire run distance. The Electronic Enclosure must be visible from the detection panels for service. The Electronic Enclosure must be within 10 ft. of the power receptacle. Model 3500 Systems separated by less than 20 ft. will require a sync cable connecting the Electronic Enclosures. The minimum separation between two Model 3500s is 24 in. The minimum distance to t Model 3800 is 10 feet [3,0 m.]. The minimum distance to a Model 2300 is 20 feet [6,0 m.]. The minimum distance to a 1300 Series or M1850 is 20 feet [6,0 m.].! Library Systems 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper 3M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January 2000

15 Contractor Installation Instructions for 3M Model 3501 Direct Mounted System with Buried Cables (36-inch Corridor Width) Materials Required Note Read all installation instructions before starting procedures. If there are any questions, call 3M Technical Service option #6. Item Supplier 1. Model 3501 and mounting hardware. 3M 2. Rigid non-metallic conduit (Panel to Panel Cables) in. ID Contractor as defined in Figure Rigid non-metallic conduit (Panel to Electronic Enclosure).75 in. ID Contractor as defined in Figure Conduit (if required for synchronizing multiple systems) from Electronic Contractor Enclosure to Electronic Enclosure by the best route. Conduit size of 1/2 in. is adequate. Required only with multiple systems within 20 ft. 5. Concrete to pour floor. Contractor 6. Device to cut trench in floor (for existing floors). Contractor 7. Materials to hold the conduit in position while pouring floor. Contractor 8. Finished floor. Install before Detection System. Contractor Installation Procedure These instructions will be used by 3M installers and the site contractor to ensure proper installation of Model 3501 Detection System and buried cables. 1. At the request of the contractor, architect, or 3M, the 3M installer will visit the site to examine the site for an acceptable environment and to locate the system in an acceptable location. The contractor and/or architect should be present. 2. Using the Model 3501 Contractor Layout Plan, the contractor will position and install the Panel to Panel conduit and the Panel to Electronic Enclosure conduit for each system. See Figure 1 for correct conduit size and location. If the conduit has an ID less than defined in Figure 1, there will be an additional charge at installation, and possibly the conduit will need replacement. Metallic conduit can be substituted for non-metallic if required by code. 3. Bend radius in conduits must be typical to the electrical industry. Water type 90 s are not acceptable - as cable connectors may not pass through them. 4. The contractor must avoid placing conduit or reinforcing rods in the anchor area under the mounting foot. Concrete in the area under the system must be of high quality and a minimum of 3.5 in, thick for anchoring. 5. The contractor will complete the sub floor and the finished floor in the installation area, and will provide an AC receptacle for power within 10 ft. of the Electrical Enclosure location. January

16 6. The 3M installer will install the panel cables, electronic enclosure cables, mounting system, and the detection panels. 7. The 3M installer will energize the system and complete operational checks and adjustments in. [315 mm] 8.5 in. [216 mm] 42 to 60 in. [1067 to 1524 mm] from floor to electrical enclosure base (within 10 feet of AC power receptacle) in. [296 mm] 0.75 in. [19 mm] I.D. minimum nonmetallic Conduit 25 feet [7620 mm] Cable maximum 1.25 to 2 in. [32 to 50 mm] I.D. nonmetallic Conduit For conduit spacing, conduit type and system location specifications see the Contractor Layout Plan and System Layout Check List. 18 in. [457 mm] maximum depth EAS-359C Figure 1.! Library Systems 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper 3M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January 2000

17 January

18 5-18 January 2000 This page intentionally left blank.

19 Contractor Installation Instructions for 3M Model 3502 Direct Mounted System with Buried Cables (36-inch Corridor Width) Note Read all installation instructions before starting procedures. If there are any questions, call 3M Technical Service option #6 Materials Required Item Supplier 1. Model 3502 and mounting hardware. 3M 2. Rigid non-metallic conduit (Panel to Panel Cables) in. ID Contractor as defined in Figure Rigid non-metallic conduit (Panel to Electronic Enclosure).75 in. ID Contractor as defined in Figure Conduit (if required for synchronizing multiple systems) from Electronic Contractor Enclosure to Electronic Enclosure by the best route. Conduit size of 1/2 in. is adequate. Required only with multiple systems within 20 ft. 5. Concrete to pour floor. Contractor 6. Device to cut trench in floor (for existing floors). Contractor 7. Materials to hold the conduit in position while pouring floor. Contractor 8. Finished floor. Install before Detection System. Contractor Installation Procedure These instructions will be used by 3M installers and the site contractor to ensure proper installation of Model 3502 Detection System and buried cables. 1. At the request of the contractor, architect, or 3M, the 3M installer will visit the site to examine the site for an acceptable environment and to locate the system in an acceptable location. The contractor and/or architect should be present. 2. Using the Model 3502 Contractor Layout Plan, the contractor will position and install the Panel to Panel conduit and the Panel to Electronic Enclosure conduit for each system. See Figure 1 for correct conduit size and location. If the conduit has an ID less than defined in Figure 1, there will be an additional charge at installation, and possibly the conduit will need replacement. Metallic conduit can be substituted for non-metallic if required by code. 3. Bend radius in conduits must be typical to the electrical industry. Water type 90 s are not acceptable - as cable connectors may not pass through them. 4. The contractor must avoid placing conduit or reinforcing rods in the anchor area under the mounting foot. Concrete in the area under the system must be of high quality and a minimum of 3.5 in. thick for anchoring. January

20 5. The contractor will complete the sub floor and the finished floor in the installation area, and will provide an AC receptacle for power within 10 ft. of the Electrical Enclosure location. 6. The 3M installer will install the panel cables, electronic enclosure cables, mounting system, and the detection panels. 7. The 3M installer will energize the system and complete operational checks and adjustments in. [315 mm] 8.5 in. [216 mm] 42 to 60 in. [1067 to 1524 mm] from floor to electrical enclosure base (within 10 feet of AC power receptacle) in. [296 mm] 0.75 in. [19 mm] I.D. minimum nonmetallic Conduit 25 feet [7620 mm] Cable maximum 1.25 to 2 in. [32 to 50 mm] I.D. nonmetallic Conduit For conduit spacing, conduit type and system location specifications see the Contractor Layout Plan and System Layout Check List. 18 in. [457 mm] maximum depth EAS-358C Figure 1.! Library Systems 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper 3M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January 2000

21 January

22 5-22 January 2000 This page intentionally left blank.

23 3M Model 3800 System Layout Checklist This checklist defines the environment required to successfully install the Model 3800 Detection system. Compliance with these requirements will ensure that the Model 3800 performs as designed. Any compromising of these requirements may result in reduced effectiveness of your 3M system. Always follow applicable federal, state, and local codes when planning and completing installation of this equipment. Power Requirements 1. Single phase 50 or 60 Hz power source. 2. System operates on 110/120 VAC within the United States, and is designed for worldwide use. Manual internal voltage select switches allow the system to operate on any power provided worldwide. 3. Maximum current draw is as follows: /120 VAC: 4A 5A 5.5A 6.5A 200/240 VAC: 2A 2.5A 2.8A 3.2A 4. The system includes a 14-foot [4,2 m] power cord attached to the electronics chassis. The customer is responsible for providing an electrical outlet within the power cord length. Electrical cable length is measured in wire run feet, not straight line distance. The power cord may be plugged into an outlet or hardwired to an electrical box. 5. The electronics chassis is attached to the end panel (panel A). 6. For additional details on power wiring, conduits, options, etc., see the Model 3800 Installation Specifications and Contractor Installation Instructions for A dedicated circuit is not required but is recommended to prevent overloading and loss of security. A minimum circuit capacity of 15A is required. Circuit loading must not exceed 50% of the rated circuit current to ensure voltage stability. System Placement Relative to Interfering Objects Doors (Metal framed) ADA (Americans with Disabilities Act) requires a 4-foot [1,2 m] clear space at exit doors for wheelchair maneuvering space. If necessary, the system may be located between 3 and 4 feet [914 mm and 1,2 m] from a metal framed door; however, the door may require strapping (metal connectors across joints) to maintain optimum performance. Strapping is available at an additional charge for time and material to the customer. A system with an exit gate requires a 4-foot [1,2 m] setback from the end of the open gate arm to the door to meet ADA and to allow clearance for gate arm swing. This means that the detection panels must be set back at least 96 inches [2,43 m] from the door. January

24 Exit Control Hardware Alvarado, Accent, and Lawrence are approved vendors for exit control hardware. The first post for an exit control system provided by one of the above vendors can be no closer than 12 inches [304 mm] in one of the locations specified in the diagram below: C Exit control posts and railings from other vendors must be kept a minimum of 2 feet [609 mm] from the system since this hardware has not been tested with the 3M Library Security system. - Metal railings surrounding the system using two or more horizontal members must be a minimum of 3 feet [914 mm] from a detection panel. Computers (CRT) For optimum performance, computer terminals should be placed at least 7 feet [2,13 m] from the closest detection panel. If necessary, the computer terminal may be located between 4 and 7 feet [1,2 and 2,13 m] from the closest detection panel; however, the computer terminal may require a metal shield which is available at an additional cost. Any distance less than 4 feet [1,2 m] from the closest detection panel is not allowed. Large Metal Objects (LMO) Counters with metal frames and metal merchandise display shelves Large metal objects are not allowed within 2 feet [609 mm] of a detection panel. Examples include: large metal shelves, refrigerators, heavy support beams, safes, heating/air conditioning duct work. Counters that have a metal frame which forms a continuous, electrically conductive loop should not be located within 3 feet [914 mm] of a detection panel. Windows (Metal framed) For optimum performance, a 3M Library system should be placed at least 3 feet [914 mm] from a metal framed window. Walls (Steel stud) Cash Registers Book Carts Protected Material Power Panel Boxes Stereo Components 5-24 January 2000 Walls with steel studs are not allowed within 3 feet [914 mm] of the closest detection panel. We recommend the use of wood for wall studs within 3 feet [914 mm] of the system. For optimum performance, cash registers should be placed at least 3 feet [914 mm] from the closest detection panel. Plan layout so that there is not an obvious location for customers to leave book carts within 3 feet [914 mm] of detection panels. Books and other protected articles should be at least 3 feet [914 mm] from the closest point of the security system. Plan layout so that patrons will not congregate or wait in line within 3 feet [914 mm] of a detection panel. Power distribution boxes must be at least 6 feet [1,8 m] from detection panels. Stereo speakers, amplifiers, tape decks, and record players, are not allowed within 10 feet [3,0 m] of the detection panels. Compact disk players are not affected by the library system.

25 Copy Machines Credit Card Readers Copy machines are not allowed within 5 feet [1,5 m] of the closest detection panel. Credit card readers should be placed a minimum of 10 feet [3,0 m] from the closest detection panel. System Accessories Distance Between Systems The minimum distance between two Model 3800 systems is 4 feet [1,2 m]. The minimum distance to a Model 1365 or Model 1850 is 75 feet [22,8 m]. The minimum distance between a Model 2300 and a Model 3800 is 30 feet [9,14 m]. The minimum distance to a Model 3500 is 10 feet [3.0 m.].! Library Systems 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper 3M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January

26 Contractor Installation Instructions for 3M Model 3800 Buried Power Materials Required Note Read all installation instructions before starting procedures. If there are any questions, call 3M Technical Service. option #6. Item Supplier 1. Steel floor box, conduit, and associated wiring Electrical Contractor 2. Floor box cover plate, gasket, and carpet ring if needed Electrical Contractor 3. AC power cord (part of Model 3800 System) 3M 4. Device to cut trench in floor Contractor 5. Material to fill in around and cover conduit after trench is cut Contractor Installation Procedure 1. Install a steel floor box. Position box per Model 3801, 3802, 3803 or 3804 Contractor Layout Plan and figure 1. Floor box is typically 5 inches x 5 inches [127 x 127 mm], with a 4 inch [101 mm] cover flange. Some variations from the different suppliers utilize boxes with "pre-pour" and "after-pour" level adjustments. If necessary, request assistance from a 3M Service Technician in positioning floor box. 2. Complete wiring from floor box to Amp circuit, preferably dedicated for the security system. 3. At system installation, terminate system power cord to circuit wires, install gasket, cover plate, and carpet ring if required. Allow an extra 2 feet [609 mm] of power cord to be stored in the 3800 electronics chassis. 4. The 3M Service Technician will energize and check out the system January 2000

27 M3800 Panel Panel Mounting Foot Electronic Chassis System Power Cord 5/16 in. [7,9 mm] O.D. 90 Cord Fitting 1/2 in. [12,7 mm] NPT Cover Plate 1/2 in. [12,7 mm] NPS Plug Size Panel to Panel Conduit Steel Floor Box with Leveling Screws 1/2 in. [12,7 mm] Conduit M3800 Panel/Mounting Foot Electronics Chassis 3 in. [76 mm] Floor Box (Center on Panel Below Electronics Chassis) C L C L A! Library Systems 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper 3M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January

28 Contractor Installation Instructions for 3M Model 3801 Floor Mounted System with Buried Cables (36 in. and 42 in. Corridors) Note Read all installation instructions before starting this installation procedure. If there are any questions, contact 3M Library Systems, Technical Service,, option #6. If AC power wiring is also buried, see Contractor Installation Instructions for 3M Model 3800 Buried Power. Materials Required Item Supplier 1. Model 3801 and mounting hardware 3M 2. Rigid non-metallic conduit, 1.25 inch [31,7 mm] I.D. as defined in figure 1 Contractor 3. Concrete as required to pour floor Contractor 4. Device to cut trench in floor (for existing construction) Contractor 5. Materials to hold conduit in position while pouring floor Contractor 6. Finish flooring Contractor Installation Procedure These instructions will be used by 3M installers and the contractor to ensure proper installation of the Model 3801 Detection System and buried cables. 1. At the request of the contractor, the 3M installer will visit the site to examine the site for an acceptable environment and to locate the system in an acceptable location. System setup and testing may be required to verify the location is acceptable. 2. Using the Model 3801 Contractor Layout Plan, the contractor will position and install the Panel-to-Panel Conduit and AC Power Conduit for each system. See figure 1. For installation details for buried AC power, see Contractor Installation Instructions for 3M Model 3800, Buried Power. The Panel-to-Panel Conduit must have a minimum I.D. of 1.25 inch [31,7 mm] to accept cables. If this conduit has an I.D. of less than 1.25 inch [31,7 mm] there will be an additional charge at installation. 3. Each bend radius in 1.25 inch [31,7 mm] conduit must be typical to the electrical industry. Water type 90 o bends or fittings are not acceptable. 4. The contractor must avoid placing conduit or reinforcing rods in the anchor area of the mounting feet. Concrete in the area under the system mounting hardware must be a minimum of 3.5 inches [89 mm] thick for anchoring. 5. The contractor will complete the sub floor and finished floor in the installation area and will complete the AC power wiring to the site. 6. The 3M installer will install the system, anchors, and panel-to-panel wiring. 7. The contractor will provide an electrician for AC power wiring hookup to the system power cord. 8. The 3M installer will energize the system and will complete operational checks and adjustments January 2000

29 3M Model 3801 Floor Mount (36 in. and 42 in. Corridors) Figure 1 Dimension A Table Corridor Width A 36 in.* 38.5 in. [977 mm] 42 in.* 44.5 in. [1,13 m] * 36 inch and 42 inch corridors comply with ADA guidelines for corridor widths. See Model 3801 Contractor Layout Plan for exact location of conduits. Location is critical because conduits must enter openings in system mounting hardware. Notes 1. Maximum depth of 1.25" [31,7 mm] I.D. conduit is 18 inches [457 mm] due to length of panel-to-panel cables. 2. Panel-to-panel conduit must not extend more than 3/8 inch [9,5 mm] above the finished floor. 3. Conduit and reinforcing rod must not interfere with anchor bolt locations. 4. Floor box for AC power must be located on the same side of the system as the electronics chassis. 5. For existing floors, the floor must be core drilled or trenched to accept buried conduits. Trench width should be kept to a minimum to avoid weakening the concrete in the anchor area. 6. Floor in area of mounting hardware must be flat, level, and high quality concrete. Minimum concrete thickness is 3.5 inches [89 mm]. 7. See 3M Model 3800 System Layout Checklist for minimum distances to interfering objects.! Library Systems 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper 3M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January

30 5-30 January 2000 This page intentionally left blank.

31 Model 3801 Contractor Layout Plan - Buried Wiring and Power (36 in. and 42 in. Corridor Widths) Mounting Foot Electrical Supply Flush Service Floor Box Hardwired to Power Cord Electronic Chassis 21 in. x 3.5 in. A 2.5 in. [63,5 mm] min. CL Conduit Radius to be Typical to Electrical Industry Standards Panel-to-Panel Wire Inlet 1 in. x 3 in. [25 mm x 76 mm] Section A-A "A" Corridor Width 1 1/4 in. [31,7 mm] I.D. Rigid Non-Metallic Conduit Anchor Holes (4 per Foot) CL in. [6-12 mm] A 2.5 in. [63,5 mm] 6.25 in. [158 mm] in. [260 mm] Dimension "A" and "B" Table Corridor Width "A" "B" 36 in. 42 in. 13 in. [330 mm] CL 38.5 in. [977 mm] 44.5 in. [1,13 m] 26 in. [660 mm] 41 in. [1,04 m] 47.0 in. [1,25 m] Notes: 1. Power source can be from either side of M Power cord length is 14 feet [4,2 m]. 3. If underground power is required, use a Flush Mount Floor Box, terminate the power cord in floor box. See "Installation Instructions - Under Floor Power". 4. Floor must be level and flat in area under mounting foot for each panel, and a minimum of 3 1/2 inches [89 mm] thick. 5. Conduit and reinforcing rod must not be located in anchor hole area under mounting foot. 6. Cable supplied for buried wiring is adequate for conduit buried a maximum depth of 18 inches [457 mm] inch and 42 inch corridors comply with ADA guidelines for corridor widths. 8. Remember to allow space for electronic chassis, air flow and service. For further information or assistance, please contact: 3M Library Systems 3M Center, Bldg N-14 St. Paul, Minnesota ft. [1,5 m] min. System CL to Door 4 ft. [1,2 m] min. System to Door Mounting Foot Outline "B" For Installation Opening Width Requirements, add 10.5 in. [266 mm] to the "B" dimension for attached electronic chassis, cooling air requirements, and panel servicing. Important: See Model 3800 System Layout Checklist for minimum distance to interfering objects. 3 Library Systems 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper A Ò3MÓ, ÒTattle-TapeÓ and ÒSelfCheckÓ are trademarks of 3M. Printed in U.S.A. 3M January

32 5-32 January 2000 This page intentionally left blank.

33 Contractor Installation Instructions for 3M Model 3802 Floor Mounted System with Buried Cables (36 in. and 42 in. Corridors) Note Read all installation instructions before starting this installation procedure. If there are any questions, contact 3M Library Systems, Technical Service,, option #6. If AC power wiring is also buried, see Contractor Installation Instructions for 3M Model 3800, Buried Power. Materials Required Item Supplier 1. Model 3802 and mounting hardware 3M 2. Rigid non-metallic conduit, 1.25 inch [31,7 mm] I.D. as defined in figure 1 Contractor 3. Concrete as required to pour floor Contractor 4. Device to cut trench in floor (for existing construction) Contractor 5. Materials to hold conduit in position while pouring floor Contractor 6. Finish flooring Contractor Installation Procedure These instructions will be used by 3M installers and the contractor to ensure proper installation of the Model 3802 Detection System and buried cables. 1. At the request of the contractor, the 3M installer will visit the site to examine the site for an acceptable environment and to locate the system in an acceptable location. System setup and testing may be required to verify the location is acceptable. 2. Using the Model 3802 Contractor Layout Plan, the contractor will position and install the Panel-to-Panel Conduit and AC Power Conduit for each system. See figure 1. For installation details for buried AC power, see Contractor Installation Instructions for 3M Model 3800, Buried Power. The Panel-to-Panel Conduit must have a minimum I.D. of 1.25 inch [31,7 mm] to accept cables. If this conduit has an I.D. of less than 1.25 inch [31,7 mm] there will be an additional charge at installation. 3. Each bend radius in 1.25 inch [31,7 mm] conduit must be typical to electrical industry. Water type 90 o bends or fittings are not acceptable. 4. The contractor must avoid placing conduit or reinforcing rods in the anchor area of the mounting feet. Concrete in the area under the system mounting hardware must be a minimum of 3.5 inches [89 mm] thick for anchoring. 5. The contractor will complete the sub floor and finished floor in the installation area and will complete the AC power wiring to the site. 6. The 3M installer will install the system, anchors, and panel-to-panel wiring. 7. The contractor will provide an electrician for AC power wiring hookup to the system power cord. 8. The 3M installer will energize the system and will complete operational checks and adjustments. January

34 3M Model 3802 Floor Mount (36 in. and 42 in. Corridors) Figure 1 Corridor Width A 36 in.* 38.5 in. [977 mm] 42 in.* 44.5 in. [1,13 m] Dimension A Table * 36 inch and 42 inch corridors comply with ADA guidelines for corridor widths. See Model 3802 Contractor Layout Plan for exact location of conduits. Location is critical because conduits must enter openings in system mounting hardware. Notes 1. Maximum depth of 1.25 inch [31,7 mm] I.D. conduit is 18 inches [457 mm] due to length of panel-to-panel cables. 2. Panel-to-panel conduit must not extend more than 3/8 inch [9,5 mm] above the finished floor. 3. Conduit and reinforcing rod must not interfere with anchor bolt locations. 4. Floor box for AC power must be located on the same side of the system as the electronics chassis. 5. For existing floors, the floor must be core drilled or trenched to accept buried conduits. Trench width should be kept to a minimum to avoid weakening the concrete in the anchor area. 6. Floor in area of mounting hardware must be flat, level, and high quality concrete. Minimum concrete thickness is 3.5 inches [89 mm]. 7. See 3M Model 3800 System Layout Checklist for minimum distances to interfering objects.! Library Systems 3M Center, Bldg N-14 St. Paul, MN % Pre-consumer waste paper 10% Post-consumer waste paper 3M, Tattle-Tape and SelfCheck are trademarks of 3M. Printed in U.S.A. 3M January 2000

35 Model 3802 Contractor Layout Plan - Buried Wiring and Power (36 in. and 42 in. Corridor Widths) Mounting Foot Electrical Supply Flush Service Floor Box Hardwired to Power Cord Electronic Chassis 21 in. x 3.5 in. A Conduit Radius to be Typical to Electrical Industry Standards Section A-A "A" Corridor Width "A" Corridor Width 1 1/4 in. [31,7 mm] I.D. Rigid Non-Metallic Conduit CL CL CL Panel-to-Panel Wire Inlet 1 in. x 3 in. [25 mm x 76 mm] Anchor Holes (4 per Foot) 6.25 in. [158 mm] in. [260 mm] in. [6-12 mm] A 2.5 in. [63,5 mm] 13 in. [330 mm] CL 26 in. [660 mm] Notes: 1. Power source can be from either side of M Power cord length is 14 feet [4,2 m]. 3. If underground power is required, use a Flush Mount Floor Box, terminate the power cord in floor box. See "Installation Instructions - Under Floor Power". 4. Floor must be level and flat in area under mounting foot for each panel, and a minimum of 3 1/2 inches [89 mm] thick. 5. Conduit and reinforcing rod must not be located in anchor hole area under mounting foot. 6. Cable supplied for buried wiring is adequate for conduit buried a maximum depth of 18 inches [457 mm] inch and 42 inch corridors comply with ADA guidelines for corridor widths. 8. Remember to allow space for electronic chassis, air flow and service. 5 ft. [1,5 m] min. System CL to Door 3 Library Systems 3M Center, Bldg N-14 St. Paul, MN in. [63,5 mm] min. 4 ft. [1,2 m] min. System to Door Mounting Foot Outline 40% Pre-consumer waste paper 10% Post-consumer waste paper 2-23 "B" For Installation Opening Width Requirements, add 10.5 in. [266 mm] to the "B" dimension for attached electronic chassis, cooling air requirements, and panel servicing. Important: See Model 3800 System Layout Checklist for minimum distance to interfering objects. For further information or assistance, please contact: 3M Library Systems 3M Center, Bldg N-14 St. Paul, Minnesota Dimension "A" and "B" Table Corridor Width "A" "B" 36 in. 42 in in. [977 mm] 44.5 in. [1,13 m] 79.5 in. [2,01 m] 91.5 in. [2,32 m] A Ò3MÓ, ÒTattle-TapeÓ and ÒSelfCheckÓ are trademarks of 3M. Printed in U.S.A. 3M January

36 5-36 January 2000 This page intentionally left blank.

37 Contractor Installation Instructions for 3M Model 3803 Floor Mounted System with Buried Cables (36 in. and 42 in. Corridors) Note Read all installation instructions before starting this installation procedure. If there are any questions, contact 3M Library Systems, Technical Service,, option #6. If AC power wiring is also buried, see Contractor Installation Instructions for 3M Model 3800, Buried Power. Materials Required Item Supplier 1. Model 3803 and mounting hardware 3M 2. Rigid non-metallic conduit, 1.25 inch [31,7 mm] I.D. as defined in figure 1 Contractor 3. Concrete as required to pour floor Contractor 4. Device to cut trench in floor (for existing construction) Contractor 5. Materials to hold conduit in position while pouring floor Contractor 6. Finish flooring Contractor Installation Procedure These instructions will be used by 3M installers and the contractor to ensure proper installation of the Model 3803 Detection System and buried cables. 1. At the request of the contractor, the 3M installer will visit the site to examine the site for an acceptable environment and to locate the system in an acceptable location. System setup and testing may be required to verify the location is acceptable. 2. Using the Model 3803 Contractor Layout Plan, the contractor will position and install the Panel-to-Panel Conduit and AC Power Conduit for each system. See figure 1. For installation details for buried AC power, see Contractor Installation Instructions for 3M Model 3800, Buried Power. The Panel-to-Panel Conduit must have a minimum I.D. of 1.25 inch [31,7 mm] to accept the system cables. If this conduit has an I.D. of less than 1.25 inch [31,7 mm] there will be an additional charge at installation. 3. Each bend radius in 1.25 inch [31.7 mm] conduit must be typical to electrical industry. Water type 90 o bends or fittings are not acceptable. 4. The contractor must avoid placing conduit or reinforcing rods in the anchor area of the mounting feet. Concrete in the area under the system mounting hardware must be a minimum of 3.5 inches [89 mm] thick for anchoring. 5. The contractor will complete the sub floor and finished floor in the installation area and will complete the AC power wiring to the site. 6. The 3M installer will install the system, anchors, and panel-to-panel wiring. 7. The contractor will provide an electrician for AC power wiring hookup to the system power cord. 8. The 3M installer will energize the system and will complete operational checks and adjustments. January

Preinstallation Worksheet 3M Detection Systems Please complete this form and fax it to 3M at

Preinstallation Worksheet 3M Detection Systems Please complete this form and fax it to 3M at Preinstallation Worksheet 3M Detection Systems Please complete this form and fax it to 3M at 1-800-795-9091. Today s date Sales consultant Account name Key contact name Phone No. Installation location

More information

Detection System Model 8800 Series

Detection System Model 8800 Series Detection System Model 8800 Series rchitect/contractor Information Package 3M Library Systems 3M Center, Building 225-4N-14 St. Paul, Minnesota 55144-1000 www.3m.com/library 78-8126-7738-9_B Copyright

More information

Site Planning Guide. Staff Workstation Model M Library Systems. Printed in U.S.A. 3M 1999 July

Site Planning Guide. Staff Workstation Model M Library Systems. Printed in U.S.A. 3M 1999 July Site Planning Guide Staff Workstation Model 995 3M Library Systems 3M Center, Building 209-1W-09 St. Paul, MN 55144-1000 800-328-0067 www.3m.com\\library Printed in U.S.A. 3M 1999 July 75-0500-2837-4 The

More information

Creating An Accessible World ELVORON CPL.

Creating An Accessible World ELVORON CPL. Creating An Accessible World ELVORON CPL Design And Planning Guide www.garaventalift.com Please note: Dimensions provided in this Guide are for REFERENCE ONLY and should not be used for site preparation

More information

#366. Gate Operator Pre-Installation and Site Planning. Introduction

#366. Gate Operator Pre-Installation and Site Planning. Introduction Gate Operator Pre-Installation and Site Planning Introduction Although each manufacturer s equipment has unique design characteristics and functions, gate operators are somewhat similar in many installation

More information

Installation Instructions Studio Makeup Station

Installation Instructions Studio Makeup Station Installation Instructions Studio Makeup Station 30" and 36" Models 5-light 30" Studio Makeup Station 8-light 30" Studio Makeup Station 6-light 36" Studio Makeup Station 9-light 36" Studio Makeup Station

More information

VACUUM AIR TUBE mm (4.5") DIA. TUBE SYSTEM OPERATOR UNIT (OVERHEAD DELIVERY) 15160, 15161, OR CUSTOMER UNIT (UNDERGROUND)

VACUUM AIR TUBE mm (4.5) DIA. TUBE SYSTEM OPERATOR UNIT (OVERHEAD DELIVERY) 15160, 15161, OR CUSTOMER UNIT (UNDERGROUND) 6 OPERATOR UNIT (OVERHEAD DELIVERY) 60, 6, OR 62 CUSTOMER UNIT (UNDERGROUND) L4 ( 4 ") 4 ") OPTIONAL UPPER SHROUD COVER AND LOWER TELLER UNIT COVER WHEN REQUIRED TO CONCEAL VAT 42 OPERATOR UNIT. 4mm (4

More information

UNDERGROUND SERVICES - SECONDARY

UNDERGROUND SERVICES - SECONDARY UNDERGROUND SERVICES - SECONDARY Contents - Underground Services... U-1 General Requirements for Underground Service...U-2 Names of Parts for Underground Service... U-3 Service Termination in a Service

More information

OPTEVA 378 ENHANCED CASH RECYCLER TERMINAL FRONT LOAD LOBBY UNIT PLAN VIEW FRONT VIEW SIDE VIEW

OPTEVA 378 ENHANCED CASH RECYCLER TERMINAL FRONT LOAD LOBBY UNIT PLAN VIEW FRONT VIEW SIDE VIEW L00 CALL -800--600 OPTEVA 8 ENHANCED CASH RECYCLER TERMINAL WITH mm ( ") UL SAFE 4 ( 6 ") 4 ( 6 ") CONSULT WITH DIEBOLD INSTALLATION/SERVICE BRANCH FOR ADDITIONAL DETAILS AND INFORMATION. PLEASE SEE PLANNING

More information

Elvoron Home Elevator

Elvoron Home Elevator Creating An Accessible World Elvoron Home Elevator Design And Planning Guide www.garaventalift.com Please note: Dimensions provided in this Guide are for REFERENCE ONLY and should not be used for site

More information

ELVORON HOME ELEVATOR

ELVORON HOME ELEVATOR Creating An Accessible World ELVORON HOME ELEVATOR PLANNING GUIDE www.garaventalift.com Please note: Dimensions provided in this Guide are for REFERENCE ONLY and should not be used for site preparation

More information

Elvoron CPL. Planning Guide

Elvoron CPL. Planning Guide Elvoron PL Planning Guide Please note: Dimensions provided in this Guide are for reference only and should not be used for site preparation or construction. 2 Table of ontents Elvoron PL... 4 omponent

More information

SECTION LIFT ARM PARKING GATES

SECTION LIFT ARM PARKING GATES St. Anthony of Padua Catholic Church Phase I The Woodlands, Texas JRA Proj. No. 15004 Issued for Bidding - 1/20/2016 SECTION 11 12 33.13 LIFT ARM PARKING GATES PART 1 - GENERAL 1.01 SUMMARY A. Section

More information

7 Single Family Service

7 Single Family Service 7 Single Family Service 7. General The location of the service entrance on the Customer s premises is an important consideration. For clearance and location information see section 5 (Clearances). Consult

More information

Electric Vehicle Charging Station

Electric Vehicle Charging Station EVoReel Electric Vehicle Charging Station INSTALLATION GUIDE AND USER MANUAL Model: Dual Output Pedestal Mount 30A EVoReel EVSE Model Numbers: With Basic EVSE: EV072-400-002A; With Intelligent ievse: EV072-410-002A;

More information

Home Elevator. Planning Guide

Home Elevator. Planning Guide Home Elevator Planning Guide Please note: Dimensions provided in this Guide are for REFERENCE ONLY and should not be used for site preparation or construction. 2 Table of Contents Elvoron Home Elevator...4

More information

P RO W ALL V ENTILATION H OODS INSTALLATION INSTRUCTIONS

P RO W ALL V ENTILATION H OODS INSTALLATION INSTRUCTIONS P RO W ALL V ENTILATION H OODS INSTALLATION INSTRUCTIONS CONTACT INFORMATION Wolf Customer Service: 800-332-9513 Website: wolfappliance.com As you follow these instructions, you will notice WARNING and

More information

For Conduit Inspections

For Conduit Inspections Underground Conduit Standards - Table of Content 5/8/2017 Section S22 Underground Conduit Standard Index: Description: 00 Table of Content 01 General Notes 02 Definition of Terms 03 Primary Riser Conduit

More information

Eaton Corp. - Marina Power and Lighting, Inc. General Specifications for Lighthouse Power Pedestal

Eaton Corp. - Marina Power and Lighting, Inc. General Specifications for Lighthouse Power Pedestal DRILL \ PUNCH OUT TO SIZE REQUIRED DRILL \ PUNCH OUT TO SIZE REQUIRED Lighthouse Power Pedestal - Specifications Lighthouse Power Pedestal Dimensions Height: 44.00" (1117.60 mm) Width: 13.67" (347.22 mm)

More information

Installation Instructions: ACCENT HIGH OUTPUT SYSTEM

Installation Instructions: ACCENT HIGH OUTPUT SYSTEM Installation Instructions: ACCENT HIGH OUTPUT SYSTEM READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS WILL VOID YOUR WARRANTY! INSTALLATION TIPS

More information

SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING

SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING Obtain acceptance and specific details from the local Company office. 1. Service entrance duct (see Note 1). Company

More information

OPTEVA 923 IN LOBBY TELLER (ILT) PLAN mm (60") WIDE PLAN - STAND ALONE FRONT VIEW SIDE VIEW PAGE 1 OF 5 CALL NOTE:

OPTEVA 923 IN LOBBY TELLER (ILT) PLAN mm (60) WIDE PLAN - STAND ALONE FRONT VIEW SIDE VIEW PAGE 1 OF 5 CALL NOTE: OPTEVA 9 IN LOBBY TELLER (ILT) mm ( ") U.L. SAFE L4 CALL -8-999-6 CONSULT WITH DIEBOLD INSTALLATION/SERVICE BRANCH FOR ADDITIONAL DETAILS AND INFORMATION. PLEASE SEE PLANNING AND SITE PREPARATION GUIDE

More information

Installation Manual. For. Alumavator and Platinum. Vertical Installation. Elevator Boat Lifts

Installation Manual. For. Alumavator and Platinum. Vertical Installation. Elevator Boat Lifts Installation Manual For Alumavator and Platinum Vertical Installation Elevator Boat Lifts Page 2 Safety Precautions 1. Your boat lift is a heavy duty piece of equipment. It is important that all persons

More information

Sentinel Field Satellite Controller Metal Pedestal, Plastic Pedestal and Wall Mount Models Installation Instructions

Sentinel Field Satellite Controller Metal Pedestal, Plastic Pedestal and Wall Mount Models Installation Instructions WARNING HIGH VOLTAGE 115V 4 M AP Sentinel Field Satellite Controller Metal Pedestal, Plastic Pedestal and Wall Mount Models Installation Instructions Important: For your protection and the safety of the

More information

Installation Instructions: ACCENT SYSTEM

Installation Instructions: ACCENT SYSTEM Installation Instructions: ACCENT SYSTEM READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS WILL VOID YOUR WARRANTY! INSTALLATION TIPS Read this entire

More information

Bruno VPL-3300B Series

Bruno VPL-3300B Series Bruno VPL-3300B Series Unenclosed Application - Design and Planning Guide MADE IN USA www.bruno.com Bruno VPL-3300B Series Unenclosed Application Design and Planning Guide Bruno VPL-3300B Series Unenclosed

More information

TELETOM PREINSTALLATION MANUAL

TELETOM PREINSTALLATION MANUAL TELETOM PREINSTALLATION MANUAL MANUAL ORGANIZATION SAFETY CONTENTS SECTION 1 INTRODUCTION...1-1 DESCRIPTION...1-1 PRE-INSTALLATION RESPONSIBILITIES...1-2 BERCHTOLD RESPONSIBILITIES...1-2 OWNER RESPONSIBILITIES...1-3

More information

7. Residential Single-Family and Duplex Buildings (Dwellings)

7. Residential Single-Family and Duplex Buildings (Dwellings) Sin g le -F a mily a n d Du p le x Bu ild in g s 2016 Electric Service Requirements, 2 nd Edition Section 7 Section 7 Residential Single-Family and Duplex Buildings (Dwellings) Directory Page 7.1 General

More information

Sentinel Field Satellite Controller

Sentinel Field Satellite Controller WARNING HIGH VOLTAGE 115V M AP Sentinel Field Satellite Controller Installation Instructions Important: For your protection and the safety of the product user, please comply with all Caution and Warning

More information

CHAPTER 1C PREPARING FOR INSTALLATION

CHAPTER 1C PREPARING FOR INSTALLATION CPI Canada Inc. Preparing for Installation 1C CHAPTER 1C PREPARING FOR INSTALLATION CONTENTS: 1C.1.0 INTRODUCTION... 1C-2 1C.2.0 GENERATOR POWER REQUIREMENTS... 1C-2 1C.2.1 32 kw Single Phase... 1C-2 1C.2.2

More information

Mizer Single Pump and Starter Box

Mizer Single Pump and Starter Box Mizer Single Pump and Starter Box Table of Contents Line Diagram... 2 Overview... 3 Booster Pump Specifications... 3 Water... 3 Electrical... 3 Models... 3 Mounting... 4 Electrical... 6 Motor Rotation...

More information

Installation Instructions

Installation Instructions Installation Instructions MX3635-01 Rev. E Models HydraSwing 40s HydraSwing 40F 4,000 lb (1,814 kg) 10-15 seconds HydraSwing 40 4,000 lb (1,814 kg) 15-20 seconds HydraSwing 40 Twin 4,000 lb (1,814 kg)/leaf

More information

Instruction Manual. Blink HQ Charger. Charge on. a CarCharging Company

Instruction Manual. Blink HQ Charger. Charge on. a CarCharging Company Instruction Manual Blink HQ Charger a CarCharging Company 2014 by Blink Network, LLC No part of the contents of this document may be reproduced or transmitted in any form or by any means without the express

More information

Professional Series 1/2HP 2 YEAR WARRANTY CONVERTIBLE JET PUMP REPAIR PARTS

Professional Series 1/2HP 2 YEAR WARRANTY CONVERTIBLE JET PUMP REPAIR PARTS Model T033 CONVERTIBLE JET PUMP /HP 900 GPH Suction lift Head of 5 (7.5m) in shallow well mode Professional Series YEAR WARRANTY Suction: /4 Discharge: NPT Maximum pressure: 85 PSI US GPH LPH 5 900 3400

More information

General safety and installation information.

General safety and installation information. Read these instructions before connecting and using your PowerBright Pure Sine Power Inverters. Failure in observing this warning may result in injury to persons and damage to equipment. General safety

More information

Eaton Corp. - Marina Power and Lighting, Inc. General Specifications for Lighthouse-SS Power Pedestals

Eaton Corp. - Marina Power and Lighting, Inc. General Specifications for Lighthouse-SS Power Pedestals Lighthouse-SS Power Pedestal Dimensions Height: 44.00" (1117.60 mm) Width: 9.565" (242.95 mm) Depth: 9.875" (250.83 mm) Lighthouse-SS Base Diagram Ø0.50" MOUNTING HOLE (TYP.) 9.5625" 8.0625" 7.3125" C:\Documents

More information

Installation Manual. For. High Speed Alumavator and Platinum. 10 and 23 Degree. Elevator Boat Lifts

Installation Manual. For. High Speed Alumavator and Platinum. 10 and 23 Degree. Elevator Boat Lifts Installation Manual For High Speed Alumavator and Platinum 10 and 23 Degree Elevator Boat Lifts Page 2 Safety Precautions 1. Your boat lift is a heavy duty piece of equipment. It is important that all

More information

General Specifications for Lighthouse Power Pedestal

General Specifications for Lighthouse Power Pedestal Dimensions Height: 44.00 11 (1117.60 mm) Width: 13.67" (347.22 mm) Depth: 13.75" (349.25 mm) Lighthou98 Base Diagram ---13,75 1 --- Approximate Weight: 30 lbs. (13.6 kg) Multiply base dimensions by 25.4

More information

WPS-2800 SERIES HIGH POWER VOICE & SIREN SYSTEM

WPS-2800 SERIES HIGH POWER VOICE & SIREN SYSTEM ENGINEERING COMPANY INC. Route 45, Winthrop Road, Chester, Connecticut 0642 Phone: (800) 63SIREN Phone: (860) 526-9504 Fax: (860) 526-4078 Internet: www.whelen.com Sales e-mail: iowsales@whelen.com Customer

More information

Pentahead bolts See note 2. Conduit run as specified. Company facility. Refer to drawing SS8.6-2 or SS8.6-3 STANDARD SERVICE INSTALLATION

Pentahead bolts See note 2. Conduit run as specified. Company facility. Refer to drawing SS8.6-2 or SS8.6-3 STANDARD SERVICE INSTALLATION PULL BOX F SECONDARY SYSTEM Typical grade Pentahead bolts See note 2 Conduit run as specified Plastic or fiberglass for grass areas or Polymer concrete for light duty areas (see notes 2, 3, & 4) Company

More information

INSTALLATION INSTRUCTIONS K SERIES LINER INSERT

INSTALLATION INSTRUCTIONS K SERIES LINER INSERT Read and Save These Instructions All Hoods Must Be Installed By A Qualified Installer INSTALLATION INSTRUCTIONS K SERIES LINER INSERT Read All Instructions Thoroughly Before Beginning Installation WARNING

More information

TABLE OF CONTENTS SPECIFICATIONS 3 INSTALLATION 4. Direct Mount 4. Ducted Installations 5. Installing Plenum 5. Machine Mount Stand 5.

TABLE OF CONTENTS SPECIFICATIONS 3 INSTALLATION 4. Direct Mount 4. Ducted Installations 5. Installing Plenum 5. Machine Mount Stand 5. TABLE OF CONTENTS PAGE SPECIFICATIONS 3 INSTALLATION 4 Direct Mount 4 Ducted Installations 5 Installing Plenum 5 Machine Mount Stand 5 Ceiling Mount 6 Pedestal Stand 7 Drain Installation 7 Electrical 8

More information

install o IIVIPORTANT - Savethese -&WARNING - -&WARNING - This appliance must -&WARNING - Before beginning the Mode_s PB970, PB975

install o IIVIPORTANT - Savethese -&WARNING - -&WARNING - This appliance must -&WARNING - Before beginning the Mode_s PB970, PB975 install m ctric Ran Mode_s PB970, PB975 I[_ Questions? Call 800.GE.CARES (800.432.2737) or Visit our Website at: ge.com I BEFORE YOU BEGIN Read these instructions completely and carefully. o IIVIPORTANT

More information

Installation Manual. For. PWC 3000 Boat Lifts

Installation Manual. For. PWC 3000 Boat Lifts Installation Manual For PWC 3000 Boat Lifts Page 2 Safety Precautions 1. Your boat lift is a heavy duty piece of equipment. It is important that all persons that may operate this unit have read and understood

More information

INSTALLATION GUIDE AND USER MANUAL

INSTALLATION GUIDE AND USER MANUAL Electric Vehicle Charging Station INSTALLATION GUIDE AND USER MANUAL SAE J1772 AC Level 2 EVSE Model: 30A EVoCharge EVSE Wall Mount P/N: EV072-300-001A Version 2.0 IMPORTANT Read this manual thoroughly

More information

INSTALLATION GUIDE AND USER MANUAL

INSTALLATION GUIDE AND USER MANUAL Electric Vehicle Charging Station INSTALLATION GUIDE AND USER MANUAL Model: 30A EVoCharge EVSE Model Number: EV072-300-001A Product Safety Certification: UL and cul Listed Description: SAE J1772 AC Level

More information

Bruno VPL-3300B Series

Bruno VPL-3300B Series Bruno VPL-3300B Series 3-Gate Application - Design and Planning Guide www.bruno.com Bruno VPL-3300B Series 3-Gate Application Design and Planning Guide Bruno VPL-3300B Series 3-Gate Application Table of

More information

D9-3. No. WIRING DIAGRAM CONNECTIONS FOR UNDERGROUND SELF CONTAINED METERS JRH JED krich95 LINE LINE ABCN SOURCE SOURCE GROUND GROUND STUD STUD SOURCE

D9-3. No. WIRING DIAGRAM CONNECTIONS FOR UNDERGROUND SELF CONTAINED METERS JRH JED krich95 LINE LINE ABCN SOURCE SOURCE GROUND GROUND STUD STUD SOURCE SOURCE 20V 240V STUD (PER NEC) A customer supplied and installed teaser wire is required from the neutral lug to a 5th terminal mounted on the left side of the meter block between the line and load terminals.

More information

Installation and Operations Manual

Installation and Operations Manual Installation and Operations Manual SEI 150/48-SEL-XXX DC-UPS SEI Incorporated 5115 Pegasus Court, Suite Q Frederick, Md 21704 Phone 301-694-9601 Fax 301-694-9608 Email Info@seipower.com Web http://www.seipower.com

More information

10 Commercial, Industrial, Agricultural Services

10 Commercial, Industrial, Agricultural Services 10 Commercial, Industrial, Agricultural Services This section describes the Power Company requirements for commercial, industrial, and agricultural services. This section covers single phase and three

More information

ELVORON HR DESIGN AND PLANNING GUIDE

ELVORON HR DESIGN AND PLANNING GUIDE ELVORON HR DESIGN AND PLANNING GUIDE Hydraulic Home Elevator Quality Elevators by Garaventa www.garaventaelevator.com Table of Contents Elvoron HR - Hydraulic Residential Elevator... 2 Technical Reference:...

More information

330mm (13") MAXIMUM WALL THICKNESS IN AREA OF UNIT. 330mm (13") MAXIMUM WALL THICKNESS IN AREA OF UNIT (30 HEIGHT NOTE SEE W ALL OPENING

330mm (13) MAXIMUM WALL THICKNESS IN AREA OF UNIT. 330mm (13) MAXIMUM WALL THICKNESS IN AREA OF UNIT (30 HEIGHT NOTE SEE W ALL OPENING L08 CALL -800--600 R DIEBOLD 0 FULL FUNCTION TERMINAL 40mm ( 6") CEN I SAFE - " OR " DISPLAY THROUGH THE WALL 0mm (") SAFE CONSULT WITH DIEBOLD INSTALLATION/SERVICE BRANCH FOR ADDITIONAL DETAILS AND INFORMATION.

More information

THE AquaBlast & RocketRide FUNSLIDES

THE AquaBlast & RocketRide FUNSLIDES THE AquaBlast & RocketRide FUNSLIDES ASSEMBLY AND INSTALLATION INSTRUCTIONS * * C A U T I O N * * S.R. SMITH AquaBlast TM & RocketRide TM FUNSLIDES TM ARE MANUFACTURED FOR INSTALLATION AND USE ON RESIDENTIAL

More information

203mm (8") MAXIMUM WALL THICKNESS IN AREA OF UNIT. 203mm (8") MAXIMUM WALL THICKNESS IN AREA OF UNIT (30 HEIGHT NOTE SEE W ALL OPENING

203mm (8) MAXIMUM WALL THICKNESS IN AREA OF UNIT. 203mm (8) MAXIMUM WALL THICKNESS IN AREA OF UNIT (30 HEIGHT NOTE SEE W ALL OPENING L0 CALL -800--600 R DIEBOLD 0 FULL FUNCTION THROUGH THE WALL 0mm ( VESTIBULE TERMINAL 40mm ( 6") CEN I SAFE - " OR " DISPLAY CONSULT WITH DIEBOLD INSTALLATION/SERVICE BRANCH FOR ADDITIONAL DETAILS AND

More information

OMEGA PLANNING GUIDE. Curved Inclined Platform Lift. Applicable Codes: ASME A17.1 ASME A18.1 CAN/CSA B355 CAN/CSA B m Part No.

OMEGA PLANNING GUIDE. Curved Inclined Platform Lift. Applicable Codes: ASME A17.1 ASME A18.1 CAN/CSA B355 CAN/CSA B m Part No. OMEGA Curved Inclined Platform Lift PLANNING GUIDE Applicable Codes: ASME A17.1 ASME A18.1 CAN/CSA B355 CAN/CSA B613 31-m07-2014 Part No. 000822 Copyright 2014 Savaria Corporation All rights reserved.

More information

Installation Instructions: HYPERION R-Lite SYSTEM

Installation Instructions: HYPERION R-Lite SYSTEM Installation Instructions: HYPERION R-Lite SYSTEM READ THIS MANUAL BEFORE PROCEEDING WITH THE INSTALLATION. FAILURE TO FOLLOW THE INSTALLATION INSTRUCTIONS WILL VOID YOUR WARRANTY! INSTALLATION TIPS Read

More information

ZG 521 Padvault Three-Phase Transformer

ZG 521 Padvault Three-Phase Transformer E n g in e e r :R.An th o n Ap p r o v e r :Jo s h u a Jo n e s 2 0 De c 1 7 2 0 De c 1 7 ZG 521 Padvault Three-Phase Transformer ZG 521 Padvault Three-Phase Transformer 1. Scope This material specification

More information

Indianapolis Power & Light Company

Indianapolis Power & Light Company Indianapolis Power & Light Company Electric Service and Meter Manual The Electric Service & Meter Manual is not copyrighted and permission is hereby given to reproduce this document. However, the Indianapolis

More information

INSTALLATION INSTRUCTIONS K-SERIES UNDER CABINET HOOD

INSTALLATION INSTRUCTIONS K-SERIES UNDER CABINET HOOD Read and Save These Instructions All Hoods Must Be Installed By A Qualified Installer INSTALLATION INSTRUCTIONS K-SERIES UNDER CABINET HOOD Read All Instructions Thoroughly Before Beginning Installation

More information

U-18. Company furnishes and installs: 10. Service lateral and connectors. 11. Conduit package, Amperes.

U-18. Company furnishes and installs: 10. Service lateral and connectors. 11. Conduit package, Amperes. SERVICE TERMINATION IN A TERMINATION COMPARTMENT DIRECT BURIED OR CONCRETE ENCASED LATERAL ALL 1-PHASE VOLTAGES, 400-800 AMPERES ALL 3-PHASE VOLTAGES, 400-3000 AMPERES ONLY Obtain acceptance for 1-phase

More information

Pro Island Ventilation Hoods

Pro Island Ventilation Hoods INSTALLATION GUIDE Pro Island Ventilation Hoods READ AND SAVE THESE INSTRUCTIONS Contents Wolf Pro Island Ventilation Hoods................. 3 Safety Instructions............................ 4 Installation

More information

WARNING: FAILURE TO FOLLOW THESE RULES MAY RESULT IN SERIOUS PERSONAL INJURY CAUTION: INSTALLATION LOCATION:

WARNING: FAILURE TO FOLLOW THESE RULES MAY RESULT IN SERIOUS PERSONAL INJURY CAUTION: INSTALLATION LOCATION: 2 Please read the safety and installation instructions carefully to help ensure a correct and SAFE installation of your Second Wind Ultraviolet Germicidal Photo-catalytic Air Purifier. WARNING: FAILURE

More information

Installing Your 220v J-POD Kit

Installing Your 220v J-POD Kit Installing Your 220v J-POD Kit NOTE: There are two J-POD versions depending on your pump voltage - 110 volt and 220 volt. MAKE SURE YOU HAVE THE RIGHT VOLTAGE J-POD FOR YOUR. Using software and hardware

More information

Lifting height 5.5" - 72" with adapters " Height overall 165" Width between columns 122" Drive through 109" Width overall 151.

Lifting height 5.5 - 72 with adapters  Height overall 165 Width between columns 122 Drive through 109 Width overall 151. Model Number TP12KC-D Capacity 12,000 lbs. Lifting height 5.5" - 72" with adapters 79.625" Height overall 165" Width between columns 122" Drive through 109" Width overall 151.125" Arm extension 37.5" -

More information

SECTION WELDING FUME EXHAUST SYSTEM

SECTION WELDING FUME EXHAUST SYSTEM SECTION 233500 WELDING FUME EXHAUST SYSTEM PART 1 - GENERAL 1.1 WORK INCLUDES Welding fume exhaust system and controls Accessories Additional System Equipment Engineering Support Commissioning 1.2 RELATED

More information

AUXILIARY BATTERY BOX INSTALLATION INSTRUCTIONS

AUXILIARY BATTERY BOX INSTALLATION INSTRUCTIONS AUXILIARY BATTERY BOX INSTALLATION INSTRUCTIONS The original TOMMY GATE hydraulic lift Assembling the Auxiliary Battery Box 1. Remove the cover from the auxiliary battery box by removing the two nuts and

More information

GE Industrial Solutions. Limitamp * AR. Arc Resistant Medium Voltage Motor Control. Installation Guide

GE Industrial Solutions. Limitamp * AR. Arc Resistant Medium Voltage Motor Control. Installation Guide GE Industrial Solutions Limitamp AR Arc Resistant Medium Voltage Motor ontrol Installation Guide Table of ontents Introduction...3 Opening Medium Voltage oor...3 Medium Voltage oor Latches... Isolation

More information

accqpulse Velocity Profiler Sensor Installation Guide

accqpulse Velocity Profiler Sensor Installation Guide accqpulse Velocity Profiler Sensor Installation Guide Instruction Sheet #69-7403-012 Released May 2016 Overview This instruction guide is for the installation of the accqpulse shallow water and deep water

More information

AMPLIFIER A OR B SELECTOR

AMPLIFIER A OR B SELECTOR M O D E L ABA-1D ABA-1D AMPLIFIER A OR B SELECTOR NILES INSTALLATION & OPERATION GUIDE ABA-1D Speaker/Amplifier Selector S P E A K E R / A M P L I F I E R S E L E C T O R TABLE OF CONTENTS Introduction

More information

Installation Manual. Rev

Installation Manual. Rev Installation Manual ChargePro 620 Charging Station is a trademark of SemaConnect, Inc. All other products or services mentioned are the trademarks, service marks, registered trademarks or registered service

More information

Operating Instructions

Operating Instructions DuroSite & SafeSite Area Light with Adapters Important Information: These instructions contain safety information, read and follow them carefully. Dialight will not accept any responsibility for injury,

More information

INSTALLATION INSTRUCTIONS MODELS S S SHALLOW WELL & CONVERTIBLE JET PUMPS PAGE 3 PAGE 8

INSTALLATION INSTRUCTIONS MODELS S S SHALLOW WELL & CONVERTIBLE JET PUMPS PAGE 3 PAGE 8 INSTALLATION INSTRUCTIONS WWW.BURCAM.COM 2190 Blvd. Dagenais West LAVAL (QUEBEC) CANADA H7L 5X9 MODELS 503132S 503332 503232S 503732 TEL : 514.337.4415 FAX : 514.337.4029 info@burcam.com Your pump has

More information

YOUR FULL LINE SOURCE FOR PVC ELECTRICAL PRODUCT

YOUR FULL LINE SOURCE FOR PVC ELECTRICAL PRODUCT CANTEX INC. 301 Commerce Ste 2700 Fort Worth, Texas 76102 817-215-7000 Fax: 817-215-7001 Conduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes YOUR FULL

More information

UNDERGROUND SERVICE. Items to consider. There will be charges from ComEd if you convert from overhead to underground service.

UNDERGROUND SERVICE. Items to consider. There will be charges from ComEd if you convert from overhead to underground service. UNDERGROUND SERVCE tems to consider f your trenching route has to be dug by hand, or if a cable must be installed under a paved surface, additional charges apply. f your service cable has to be moved later

More information

WattStation Wall Mount User Manual

WattStation Wall Mount User Manual GE Energy WattStation Wall Mount User Manual imagination at work Table of Contents 1. Grounding Instructions...3 1.1 Safety and Compliance...3 1.2 Grounding Instructions...3 2. Installation Instructions...3

More information

34.00 METERING GENERAL LABELING MULTIPLE METER ENCLOSURES ON A SINGLE PREMISE

34.00 METERING GENERAL LABELING MULTIPLE METER ENCLOSURES ON A SINGLE PREMISE 4. METERING GENERAL LABELING MULTIPLE METER ENCLOSURES ON A SINGLE PREMISE 4.-4 4. SELF-CONTAINED METERING, SINGE-PHASE INSTALLATION DETAILS /4 VOLT SINGLE-PHASE UNDERGROUND RESIDENTIAL SERVICE AND METER

More information

Haworth prices in this book will increase on March 1, 2017 by 4% Intuity Benching North America Specification Guide / Price List June 2015

Haworth prices in this book will increase on March 1, 2017 by 4% Intuity Benching North America Specification Guide / Price List June 2015 Haworth prices in this book will increase on March 1, 2017 by 4% Intuity Benching North America Specification Guide / Price List June 2015 Electronic Update Page Intuity Benching Price List The table below

More information

CONV-B2000 Conversion Frame Installation / Inspection Manual Approved Under Dispenser SCCS (Spill Containment & Control System)

CONV-B2000 Conversion Frame Installation / Inspection Manual Approved Under Dispenser SCCS (Spill Containment & Control System) CONV-B2000 Conversion Frame Installation / Inspection Manual Approved Under Dispenser SCCS (Spill Containment & Control System) A CONVERSION FRAME EVALUATION FORM IS REQUIRED TO ORDER This can be downloaded

More information

DIAMOND DOOR PRODUCTS TECHNICAL DETAILS MARCH 2010

DIAMOND DOOR PRODUCTS TECHNICAL DETAILS MARCH 2010 DIAMOND DOOR PRODUCTS TECHNICAL DETAILS 1. Table of Contents 2. Overall Specifications 3. Warranty 4. Door Overall Dimensions Standard locations 5. Door Construction 6. Total Preassembled Dimensions 7.

More information

(1032 mm) 30.5 (775 mm) 44 ( mm)

(1032 mm) 30.5 (775 mm) 44 ( mm) ALVARADO EDCX-EK Waist High Turnstile Technical Specifications Dimensions Unit Height: Unit Width: Unit Depth: 40.625 (1032 mm) 30.5 (775 mm) 44 (1117.6 mm) Materials Cabinet: Formed and welded 14 gauge

More information

Operating Instructions Type MPT 53

Operating Instructions  Type MPT 53 Operating Instructions www.turnstiles.us Type MPT 53 Contents 1. Delivery... 2 2. Safety...3-4 3 Description and operation... 5 4. Technical Data 6 5. oundation...6-9 6. Assembly and installation...10-13

More information

Eaton Corp. - Marina Power and Lighting, Inc. General Specifications for Hatteras Light Pedestals

Eaton Corp. - Marina Power and Lighting, Inc. General Specifications for Hatteras Light Pedestals Hatteras Light Power Pedestal Dimensions Height: 31.00" (787.40 mm) Width: (190.50 mm) Depth: (190.50 mm) Hatteras Light Base Diagram Approximate Weight: 14 lbs. (6.4 kg) 1.73" UL FILE # E133781 Ø0.41

More information

91 (2311 mm) (1581mm) (1375 mm)

91 (2311 mm) (1581mm) (1375 mm) ALVARADO MSTX Maximum Security Turnstile Technical Specifications Dimensions Unit Height: Unit Width: Unit Depth: 91 (2311 mm) 62.25 (1581mm) 54.125 (1375 mm) Materials Yoke: (Curved Section) Yoke Guard

More information

OWNERS MANUAL JANUARY 2007 ISO

OWNERS MANUAL JANUARY 2007 ISO Manufacturer of Dimensions TM Inverters 4467 White Bear Parkway St. Paul, MN 55110 Phone: 651-653-7000 Fax: 651-653-7600 E-mail: inverterinfo@sensata.com Web: www.dimensions.sensata.com 121231B OWNERS

More information

STABILINE. Surge Protective Devices. PT1 Series Type 2 SPD. Installation, Operation and Maintenance Manual

STABILINE. Surge Protective Devices. PT1 Series Type 2 SPD. Installation, Operation and Maintenance Manual STABILINE Surge Protective Devices PT1 Series Type 2 SPD Installation, Operation and Maintenance Manual Thank you for purchasing the PT1 Series STABILINE Surge Protective Device... another Superior product!

More information

Electric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections. Minnesota North Dakota South Dakota

Electric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections. Minnesota North Dakota South Dakota Electric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections Page 1 of 7 17-02-420 Electric Service Conversion Overhead-to-Underground Overview and process of converting residential

More information

ACSI MODEL 1440 POWER SUPPLY INSTALLATION INSTRUCTIONS

ACSI MODEL 1440 POWER SUPPLY INSTALLATION INSTRUCTIONS II 1400-8 Features: ACSI MODEL 1440 POWER SUPPLY INSTALLATION INSTRUCTIONS Filtered/Regulated 24 Volts DC Up to Full 2 Amps Load Capacity Class 2 Rated Outputs Overload, Over Voltage, and Short Circuit

More information

T57 SERIES LOW ENERGY OPERATOR INTRODUCTION FEATURES BENEFITS PATENTS TABLE OF CONTENTS

T57 SERIES LOW ENERGY OPERATOR INTRODUCTION FEATURES BENEFITS PATENTS TABLE OF CONTENTS INTRODUCTION A reliable ADA solution for moderate traffic applications, the T57 Low Energy Operator comprises Norton s heavy-duty 1601 door closer. The use of a hydraulic closer ensures quiet and consistently

More information

ADI-125/750 ADI-125/1500 ADI-125/2500

ADI-125/750 ADI-125/1500 ADI-125/2500 Manufacturer of Dimensions TM Inverters 4467 White Bear Parkway St. Paul, MN 55110 Phone: 651-653-7000 Fax: 651-653-7600 E-mail: inverterinfo@sensata.com Web: www.dimensions.sensata.com 121094B OWNERS

More information

LE MODELS: SHIPPING, RIGGING, LIFTING, ASSEMBLY MANUAL

LE MODELS: SHIPPING, RIGGING, LIFTING, ASSEMBLY MANUAL 4510 Helgesen Drive, Madison, WI 53718 (608) 221-4499, (800) 627-4499, Fax: (608) 221-2824 LE MODELS: SHIPPING, RIGGING, LIFTING, ASSEMBLY MANUAL This manual provides an overview of shipping, rigging,

More information

The Power of Reliability INSTRUCTION MANUAL

The Power of Reliability INSTRUCTION MANUAL The Power of Reliability INSTRUCTION MANUAL SAFETY & WARNINGS Read this manual carefully and understand all Warnings and Cautions before connections are made to the Inverter. If unsure about any aspects

More information

9. Non-Residential Services (Commercial, Industrial, and Agricultural)

9. Non-Residential Services (Commercial, Industrial, and Agricultural) Section 9 2016 Electric Service Requirements, 3rd Edition Section 9 Non-Residential Services Directory Page 9.1 General Requirements 68 9.2 Direct-Connect Metering, Single Installations 69 9.3 Direct-Connect

More information

INSTALLATION INSTRUCTIONS FOR DSP9600/9100 WHEEL BALANCER

INSTALLATION INSTRUCTIONS FOR DSP9600/9100 WHEEL BALANCER Form 5063T, 06-05 Supersedes Form 5063T, 02-04 INSTALLATION INSTRUCTIONS FOR DSP9600/9100 WHEEL BALANCER This document provides the information needed to install the DSP9600/9100 Wheel Balancer. NOTE:

More information

Model Description Vac. Max rating Pedestal Only: 36 Utility Pedestal W/O Disconnect General Duty Series:

Model Description Vac. Max rating Pedestal Only: 36 Utility Pedestal W/O Disconnect General Duty Series: MAPA Products MPD-XX / Pedestal Disconnect 30, 60, 100 amp February 2014 Pedestal Disconnect Installation Instructions Parts List MAPA Products Fusible Rainproof Pedestal Mounted Safety Switch provides

More information

SL210i/SL212i Compact Inbay Control

SL210i/SL212i Compact Inbay Control SL210i/SL212i Compact Inbay Control February 2010 by Rotary Lift. All rights reserved. CO7473.1 (800 Series) (1Ø & 3Ø 208V-240V) (3Ø 480V) SL210i Moveable Pad Capacity 8,000 lbs. SL210i Capacity 10,000

More information

DRIVE: 1 hp motor; 1750 rpm, single phase, 120 VAC, 60 Hz, 13.4 Full Load Amps, 1.15 service factor, continuous duty

DRIVE: 1 hp motor; 1750 rpm, single phase, 120 VAC, 60 Hz, 13.4 Full Load Amps, 1.15 service factor, continuous duty Residential Vertical Platform Lift Technical Specifications rev: 4/02/2008 ISO No. 404.96 MODEL NUMBER: Series, Model VPL-3153 & VPL-3175 U.S. F.D.A. CLASSIFICATION: Class II CLASSIFICATION NUMBER: 890.3930

More information

RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS SECTION VI RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS

RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS SECTION VI RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS SECTION VI SERVICE REQUIREMENTS This section discusses the requirements for establishing electric service to new residential subdivisions in Palo Alto. Subdivisions are normally constructed on dedicated

More information

Checker Unload Checkstand Installation Instructions

Checker Unload Checkstand Installation Instructions Front-End Checkouts Commercial Refrigeration Equipment Display Merchandisers Store Fixtures Checker Unload Checkstand Installation Instructions Attention Store Manager: Please find enclosed in this packet

More information

Installation Instructions X-Force UTV Lift (000 Series) Capacity 2,275 lbs (1,035 kg)

Installation Instructions X-Force UTV Lift (000 Series) Capacity 2,275 lbs (1,035 kg) Installation Instructions X-Force UTV Lift (000 Series) Capacity 2,275 lbs (1,035 kg) Read entire manual before assembling, installing, operating, or servicing this equipment. LP20640 IN20793 September

More information

Speed Sensor. Inputs: Safety Information. Outputs. Wiring Diagram. Electrical Data: NOTICE

Speed Sensor. Inputs: Safety Information. Outputs. Wiring Diagram. Electrical Data: NOTICE Speed Sensor ã Read and understand equipment operators manual before operating or performing maintenance. Failure to do so could result in serious injury or death. Safety Information Failure to follow

More information