DEPARTMENT OF ELECTRICAL ENGINEERING DIT UNIVERSITY HIGH VOLTAGE ENGINEERING

Size: px
Start display at page:

Download "DEPARTMENT OF ELECTRICAL ENGINEERING DIT UNIVERSITY HIGH VOLTAGE ENGINEERING"

Transcription

1 1 DEPARTMENT OF ELECTRICAL ENGINEERING Introduction to High Voltage Testing It is essential to ensure that the electrical equipment is capable of withstanding the overvoltages that are met within the service. The overvoltages maybe either due to natural causes like lightning or system originated ones such as switching impulse or power frequency transient voltages. Hence testing for overvoltages is necessary. The overvoltage tests are classified into two groups: (i) Power frequency voltage test. (ii) Impulse voltage test. These tests together ensure the overvoltage withstand capability of an apparatus. Terms related with High Voltage Testing The following terms are most commonly associated with high voltage testing which have been explained briefly below: (i) Disruptive discharge voltage It is defined as the voltage which produces the loss of dielectric strength of insulation. It is that voltage at which the electrical stress in the insulation causes a failure which includes the collapse of voltage and passage of current. It causes a permanent loss of strength in solids whereas in liquids or gases only temporary loss maybe caused. (ii) Flashover When a discharge takes place between two electrodes (in a gas, liquid or solid) over the surface of the dielectric but not through the volume of the insulator then it is called flashover. It is mostly temporary failure of insulation of the insulator. The dielectric strength of the insulator is recovered completely once the adverse conditions which resulted in flashover are removed. (iii) Puncture If a discharge occurs in an insulator through the entire volume such that once the adverse conditions which caused discharge are removed the dielectric strength is not fully recovered. It is mostly permanent failure of insulation. (iv) Withstand Voltage The voltage which is to be applied to a test object under specified conditions without causing flashover or puncture of the insulator is known as withstand voltage. (v) Fifty Percent Flashover Voltage It is the voltage which has a probability of 50% flashover when applied to the test object. This is normally applied in impulse tests in which loss of insulation strength is temporary. (vi) Hundred Percent Flashover Voltage It is the voltage that causes a flashover at each of its applications under the specified conditions when applied to test object. (vii) Creepage Distance It is the shortest distance on the contour of external surface of the insulator unit or between two metal fittings on the insulator. (viii) Reference Atmospheric Conditions The electrical characteristics of the insulators and other apparatus are normally referred to the reference atmospheric conditions. Atmospheric Conditions Indian Standards British Standards Temperature 27 0 C 20 0 C Pressure 760 Torr 760 Torr Absolute Humidity 17 gm/m 3 11 gm/m 3 Tests on Insulators: The tests normally conducted on insulators are (i) type tests and (ii) routine tests. The type tests are intended to prove or check the design features and quality. The routine tests are intended to check the quality of the individual test piece. The type tests involves quality testing of equipment at the design and development level i.e. samples of the product are taken and are tested when a product is being developed and designed or an old product is to be redesigned and developed. The routine tests are meant to ensure the reliability of individual test objects, quality and consistency of materials used in their manufacture. The following tests are carried out on all insulators:

2 2 DEPARTMENT OF ELECTRICAL ENGINEERING (i) 50% dry impulse flashover test (ii) Impulse withstand test (iii) Dry flashover and dry one minute test (iv) Wet flashover and wet one minute test (v) Temperature cycle test (vi) Electromechanical test (vii) Mechanical test (viii) Porosity test (ix) Puncture test (x) Mechanical routine test (i) 50% Dry Impulse Flashover Test: This test is carried out on a clean insulator mounted as in normal working condition. An impulse voltage of 1.2/50 µs waveshape and of an amplitude which can cause 50% flashover of the insulator is applied i.e. out of the total number of impulses applied at least 50% of the impulses should cause flashover. The polarity of the impulse voltage is then reversed and the procedure is repeated. There must be at least 20 applications of the impulse in each case and the insulator must not be damaged. The magnitude of the impulse voltage should not be less than that specified in standard specifications. (ii) Impulse Withstand Test: In this test, the insulator is subjected to standard impulse 1.2/50 µs waveshape of specified value under dry conditions with both positive and negative polarities. If five consecutive applications do not cause any flashover and puncture, the insulator is deemed to have passed impulse withstand test. If out of five two applications cause flashover the insulator is deemed to have failed the test. (iii) Dry Flashover & Dry One Minute Test: The power frequency voltage is applied to the insulator and the voltage is increased to the specified value and maintained for one minute. The voltage is then increased gradually until flashover occurs. The insulator is then flashed over atleast four more times. The voltage is increased to reach flashover voltage in about 10 seconds. The mean of atleast five consecutive flashover voltages must not be less than the value specified in specifications. (iv) Wet Flashover & Wet One Minute Test: If the test is carried out under artificial rain it is called wet flashover test. The insulator is subjected to spray of water of following characteristics Precipitation rate 3 ± 10% mm/min. Direction 45 O to vertical Conductivity 100 µs ± 10% Temp. Of water ambient + 15 O C Initially a voltage which is 50% of one minute rain test is applied to the insulator and water of above specifications is sprayed for two minutes. The voltage is then raised to one minute test voltage in approximately 10 seconds and maintained there for one minute. The water is continuously sprayed on the insulator during the application of the voltage. The voltage is then further increased gradually till flashover occurs and the insulators is then flashed atleast four more times such that the time taken to reach flashover voltage in each case is 10 seconds. The flashover voltage must not be less than the value specified in specifications. (v) Temperature Cycle Test: The insulator is immersed in a hot water bath whose temperature is 70 o higher than normal water bath for T minutes. It is then taken out and immediately immersed in normal water bath for T minutes. After T minutes, the insulator is again

3 immersed in hot water bath for T minutes. The cycle is repeated three times and it is expected that the insulator should withstand the test without damage to the insulator or glaze. Here T = (15 + W/1.36) where W is the weight of the insulator in kg. (vi) Electromechanical Test: This test is carried out only on suspension or tension type of insulator. The insulator is subjected to a tension which is 2.5 times the specified maximum working tension maintained for one minute. Also simultaneously 75% of the dry flashover voltage is applied. The insulator should withstand this test without any damage. (vii) Mechanical Test: This test is a bending test applicable to pin type and line post insulators. The insulator is subjected to a load three times the specified maximum breaking load for 1 minute. There should be no damage to the insulator. (viii) Porosity Test: In this test the insulator is broken and immersed in a 0.5% alcohol solution of Fuchsin under a pressure of kn/m 2 for 24 hours. The broken insulator is taken out and further broken. It should not show any sign of impregnation. (ix) Puncture Test: In this test an impulse overvoltage is applied between the pin and the lead foil bound over the top and side grooves in case of pin insulator and between the metal fittings in case of suspension type insulators. The voltage is 1.2/50 µs with a magnitude twice the 50% impulse flashover voltage and negative polarity. Twenty such applications are applied. The procedure is then repeated for 2.5, 3, 3.5 times the 50% impulse flashover voltage and it is continued till the insulator is punctured. The insulator must not puncture at a voltage which is equal to or less than the voltage specified in the specifications. (x) Mechanical Routine Test: In this test the insulator is suspended vertically or horizontally and a tensile load 20% in excess of the maximum specified working load is applied for one minute. There should be no damage to the insulator string. Testing of Bushing: The bushing is an integral component of high voltage machines. It is used to bring high voltage conductors through the grounded tank or body of the electrical equipment without excessive potential gradients between the conductor and the edge of the hole in the body. In case of transformer the bushing extends into the surface of oil at one end and the other end is carried above the tank to a height sufficient to prevent breakdown due to surface leakage. The following tests are carried out on bushings: (i) Power factor test (ii) Impulse withstand test (iii) Chopped wave and switching surge test (iv) Partial discharge test (v) Momentary withstand test at power frequency (vi) One minute wet withstand test at power frequency (vii) Visible discharge test at power frequency (viii) Temperature rise and thermal stability test (i) Power Factor Test: The bushing is installed as in service or immersed in oil. The H.V. terminal of the bushing is connected to H.V. terminal of the Schering bridge and the tank or earth portion is connected to the detector of the bridge. The capacitance and power factor of the bushing is measured at different voltages as specified in the relevant specifications. The measured capacitance and power factor should be within the range specified. (ii) Impulse Withstand Test: In this test the bushing is subjected to impulse waves of both polarity and magnitude as specified in the standard specification. Five consecutive full waves of standard waveform (1.2/50 µs) are applied and if two of them cause flashover, the bushing is said to be 3

4 defective. If only one flashover occurs then ten additional applications are made. If no flashover occurs, bushing is said to have passed the test. (iii) Chopped Wave & Switching Surge Test: In this test chopped wave and switching surge of appropriate specifications are applied on H.V. bushings five times each. If two of them cause flashover then the bushing is said to be defective. If only one flashover occurs, ten additional applications are made. If no flashover occurs then the bushing is said to have passed the test (iv) Partial Discharge Test: This test is carried out in order to determine whether there is deterioration or not of the insulation used in bushing. This is done by using internal or partial discharge arrangement as shown in fig.1. The shape of the discharge is an indication of nature and severity of the defect in the bushing. C x r x R 3 C T D Band pass filter Amplifier Display Unit (CRO or Counter) r D C D C 4 R 4 Cx Test piece rx Internal resistance of test piece CD Dummy sample rd Internal resistance of dummy sample CT Filter capacitor D Power frequency detector Fig.1 Partial discharge arrangement for testing of bushing (v) Momentary Withstand Test at Power Frequency: This test is done as per the Indian standard specifications IS: 2099 applied to bushings. In this test the specified test voltage is applied for a minimum time of approximately 30 seconds. The bushing should not flashover or puncture. However at present this test is replaced by impulse withstand test. (vi) One Minute Wet Withstand Test at Power Frequency: It is the most common and routine test. In this test, the voltage specified is applied to the bushing mounted as in the service with rain arrangement. A properly designed bushing has to withstand the voltage without flashover for one minute. (vii) Visible Discharge Test at Power Frequency: This test is done to determine whether the bushing is likely to give radio interference in service when the voltage specified in IS: 2099 is applied. No discharge other than that from the arcing horns or grading rings should be visible to the observer in a dark room. The test arrangement is same as that of the withstand test but this test is conducted in a dark room (viii) Temperature Rise & Thermal Stability Test: The purpose of this test is to ensure that the bushing in service for long does not have an excessive temperature rise and also does not go into the thermal runaway condition of the insulation used. The temperature rise test is carried out in free air with an ambient temperature below 40 0 C at a rated power frequency a.c. current. The steady temperature rise above the ambient air temperature at any part of the bushing should not exceed 45 0 C. This test is carried out for such a long time till the temperature is substantially constant. 4

5 The thermal stability test is done for bushings rated for 132 kv and above. This test is carried out with the bushing immersed in oil at a maximum temperature as in service and the voltage applied is 80% of the nominal system voltage. The thermal stability test is a type test but in case of large sized H.V. bushings, it maybe necessary to make them routine tests. Testing of Surge Diverters: The lightning arrestor or surge diverter is the most reliable apparatus to protect the power system against lightning and switching surges. A surge diverter has to be a non conductor for operating power frequency voltages and should behave as short circuit for impulse voltages. The following tests are conducted on a lightning arrestor: (i) Power frequency sparkover test (ii) 100% standard impulse sparkover test (iii) Front of wave sparkover test (iv) Residual voltage test (v) Long duration impulse current test (vi) Operating duty cycle test (vii) Other test (mechanical test, pollution test, pressure relief test etc.) (i) Power Frequency Sparkover Test: It is a routine test. In this test a power frequency voltage which is 1.5 times the rated power frequency withstand voltage is applied across the lightning arrestor five times successively. If there is no flashover in all five applications then the arrestor is said to have passed the test. A series resistance is also inserted in the circuit to limit the current in case a flashover occurs. This test is generally done both under dry and wet conditions. (ii) 100% Standard Impulse Sparkover Test: This test is conducted to ensure that the arrestor operates positively when an overvoltage of impulse nature occurs. In this test an impulse voltage of standard specifications is applied to the lightning arrestor ten times successively. The arrestor should sparkover at each application. The test is conducted with both positive and negative polarity waveforms. (iii) Front of Wave Sparkover Test: This test is conducted in order to ensure that the surge diverter flashes over for very steep fronted waves of high peaks. This test is conducted using an overvoltage having a rate of rise of 100 kv/µs per 12 kv of the rating. The estimated maximum steepness of the waves is specified in standards and specifications. The test is done by conducting 100% sparkover voltage test for increasing magnitudes of standard impulse wave. The time to sparkover is measured. The volt time characteristics of diverter is plotted. The intersection of the line with slope of vertical steepness of front with volt time characteristics of the arrestor gives the front of a wave sparkover voltage. (iv) Residual Voltage Test: This test is conducted on a pro rated diverter of ratings in the range 3 to 12 kv only. The voltage developed across the non linear resistor units during the flow of surge currents through the arrestor is called the residual voltage. A pro rated arrestor is a complete, suitably housed section of an arrestor including series gaps and non linear resistors in same proportion as in the complete arrestor. A standard impulse current of rated magnitude is applied and the voltage developed across the diverter is recorded using a suitable voltage divider and CRO. The magnitudes of the currents are approximately 0.5, 1.0 and 2.0 times the rated currents. From the oscillogram, a graph is drawn between the current magnitudes and the voltage developed across the diverter pro rated unit. From the graph, the residual voltage corresponding to the exact rated current is obtained. The diverter is said to pass the test if V R < rv 2 2 5

6 Where V R is residual voltage of pro rated unit 2 V r is multiplying factor = RM where V RM is maximum permissible residual voltage V 1 V 1 is rating of complete unit V 2 is rating of pro rated unit tested (v) Long Duration Impulse Current Test: This test is also done on pro rated units of 3 to 12 kv. The circuit used to generate a rectangular impulse wave consists of an artificial transmission line with lumped inductances and capacitances. The duration of the current pulse t is given by 2( n 1) LC where n = number of stages of sections used and L, C are inductance & capacitance of each unit. The rectangular wave is generated if the surge impedance of the diverter is equal to LC at the test current. As per the specifications, 20 applications are made with specified current in five groups. The interval between the successive applications is about 1 minute. It is usual to record the waveforms in first two and last two applications of the current wave. The diverter is said to have passed the test if the following conditions are satisfied: (a) The power frequency sparkover voltage before and after the application of the current wave does not differ by more than 10%. (b) The voltage and current waveforms of the diverter do not differ significantly in two applications. (c) The non linear resistance elements in the diverter do not show any sign of puncture or external flashover. (d) The voltage across the diverter at first and last application does not differ by more than 8%. (vi) Operating Duty Cycle Test: This test is conducted on pro rated units of diverter and it gives better closeness to actual conditions. The diverter is kept energized at its rated power frequency supply voltage. The rated impulse current wave is applied first at a phase angle of about 30 0 from a.c. voltage zero. If the power frequency current is not established then the angle at which current impulse wave is applied is advanced in steps of 10 0 upto 90 0 or peak position of supply voltage wave till follow on current is established. During the follow on current period, the peak voltage across the diverter should be less than or equal to the rated peak voltage. Twenty applications of the impulse current at the selected points on the voltage wave are made in four groups. The time interval between each application is 1 minute and between successive groups it is about half an hour. The arrestor is said to have passed the test if the following conditions are met: (a) The average power frequency sparkover voltage before and after the test does not differ by more than 10%. (b) The residual voltage at the rated current does not vary by more than 10%. (c) The follow on power frequency current is interrupted each time. (d) There is no flashover or puncture to the pro rated unit. (vii) Other Test: The following tests are generally conducted on diverters used on EHV systems: (a) Mechanical test (b) Pressure relief test (c) Voltage withstand test on insulator housing of surge diverter (d) Switching surge flashover test (e) Pollution test 6

7 Testing of Isolators & Circuit Breakers: The tests conducted on circuit breakers and isolators give common characteristics for both. However these characteristics though directly relevant to the testing of circuit breaker are of not much relevance as far as testing of isolators are concerned because the isolators are not used for interrupting high currents. The following tests are conducted on circuit breakers and isolators: (i) Dielectric test (ii) Impulse test (iii) Short circuit test (iv) Thermal test (v) Asymmetrical test (i) Dielectric Test: This test consists of overvoltage withstand tests of power frequency, lightning and switching impulse voltages. These tests are done for both internal and external insulation with the switch or circuit breaker in both open and closed positions. In the open position, the test voltage levels are 15% higher than the test voltages used when the circuit breaker is in closed position. Due to this there is always a possibility of line to ground flashover which is avoided by mounting the circuit breaker on insulators above the ground. (ii) Impulse Test: In this test the lightning impulse wave of standard shape is applied to the circuit breaker similar to the insulators. In addition switching overvoltages are also applied to assess their performance under overvoltages due to switching operations. (iii) Short Circuit Tests: These are the most important tests carried out on circuit breaker since these tests assess the primary performance of these devices i.e. their ability to safely interrupt the fault current. These tests consist of determining the making and breaking capacities at various load current and rated voltages. In case of isolators, the short circuit tests are conducted only with the limited purpose to determine their capacity to carry the rated short circuit current for a given duration and no breaking, making current test is done. The different methods of conducting short circuit tests are as follows: (a) Direct Testing in Networks or in Fields The circuit breakers are sometimes tested for their ability to make or break the circuit under normal load conditions or under short circuit conditions in the network itself. This is done during period of limited energy consumption or when the electrical energy is diverted to other sections of the network which are not connected to the circuit under test. In this type of testing there is not much flexibility. (b) Direct Testing in Short Circuit Test Lab In order to test the circuit breaker at different voltages and at different short circuit currents, short circuit laboratories are provided. The fig.2 shows a schematic layout of a short circuit testing laboratory. It consists of a short circuit generator in association with a master circuit breaker, resistors, reactors and measuring devices. The rating of the master circuit breaker is always higher than the circuit breaker under test. A make switch is used to initiate the short circuit. The master circuit breaker isolates the test device from the source at the end of a predetermined time set on a test sequence controller. The master circuit breaker can also be tripped if the test device fails to operate properly. 7

8 G Fig.2 Schematic dig. of short ckt. testing lab for direct testing (c) Synthetic Testing of Circuit Breaker Due to very high interrupting capacities of circuit breakers, it is not economical to have a single source to provide the required short circuit current and rated voltage. Instead a combination of the effects of two sources, one of which supplies a.c. current and the other the high voltage is used. In the initial period of short circuit test, the a.c. current source supplies the heavy current at low voltage and then the recovery voltage is simulated by a source of comparatively high voltage of small current capacity. The fig.3 shows the schematic diagram of a synthetic testing station where Vc low voltage, high current generator Lc current controlling inductance MCB master circuit breaker Lv voltage waveform controlling choke Cv capacitor to give necessary recovery voltage Co capacitor to control the frequency of transient recovery voltage MCB Making Switch Aux CB LV LC VC CO CB under Test CV Fig.2 Schematic dig. of short ckt. testing lab for synthetic testing With the auxiliary circuit breaker and the test circuit breaker closed, the closing of the making switch causes the current to flow in the test circuit breaker. At some instant say to, the circuit breaker begins to operate. The trigger gap closes at the instant just before the generator current becomes zero and the higher frequency current from discharging capacitor CV flows through the arc. At the instant when generator current becomes zero, the master circuit breaker clears the circuit leaving only current from CV. At the zero of this current full test voltage will be available. (d) Composite Testing In this method, the circuit breaker is first tested for its rated breaking capacity at a reduced voltage and afterwards for rated voltage at a low current. This method does not give a proper estimate of breaker performance and hence is not much preferred. 8

9 Testing Procedure for Short Circuit Test The circuit breakers are tested for their breaking capacity (B) and making capacity (M). The following procedure is to be adopted while conducting the short circuit tests on circuit breakers as per the specifications: B 3 B 3 B at 10% of rated symmetrical breaking capacity B 3 B 3 B at 30% of rated symmetrical breaking capacity B 3 B 3 B at 60% of rated symmetrical breaking capacity B 3 MB 3 MB at 100% of rated symmetrical breaking capacity B 3 MB 3 MB at 100% of rated symmetrical breaking capacity Here B and M represent breaking and making operations respectively. MB denotes making operation followed by breaking operation without any intentional time lag. 3 denotes time in minutes between successive operations of an operating duty. (iv) Thermal Test: These tests are made to check the thermal behaviour of the circuit breakers. In this test the rated current is passed continuously through all three phases of the switchgear for a long enough period to achieve steady state conditions. When the normal rated current is less than 800 A then the temperature rise above the ambient temperature should not exceed 40 0 C. In case of currents of magnitude 800 A and above the temperature rise above the ambient temperature should not exceed 50 0 C. (v) Asymmetrical Test: In this one test cycle is repeated for the asymmetrical breaking capacity in which the d.c component at the instant of contact separation is not less than 50% of the a.c. component. Testing of Cables: The high voltage power cables have proved quite useful especially in case of HVDC transmission. The following tests are done on a cable: (i) Bending test (ii) Loading cycle test (iii) Thermal stability test (iv) Dielectric thermal resistance test (v) Life expectancy test (vi) Dielectric power factor test (vii) Power frequency withstand voltage test (viii) Impulse withstand voltage test (ix) Partial discharge test However before performing the above mentioned tests, the cable sample has to be carefully prepared especially for electrical tests. This is essential to avoid any excessive leakage or end flashovers which otherwise may occur during testing and hence may give wrong information regarding the quality of cable. The length of the sample cable varies between 50 cm to 10 m. The terminations are usually made by shielding the ends of cable with stress shields so as to relieve the ends from excessive high electrical stresses. (i) Bending Test: In case of this test, the cable is bend round a cylinder of specified diameter to make one complete turn. It is then unwound or rewound in the opposite direction. This cycle is repeated three times. It is to be noted that a voltage test should be made before and after this test. The diameter of the cylinder depends on the diameter of the cable under bending test as follows: 9

10 Diameter of cylinder = 16 X diameter of cable (ii) Loading Cycle Test: In this test the cable in the form of loop alongwith its accessories is subjected to 20 load cycles with a minimum conductor temperature 5 0 C in excess of the design value and the cable is energized to 1.5 times the working voltage. The cable should not show any signs of damage. (iii) Thermal Stability Test: This test is conducted after the loading cycle test. The cable is energized with a voltage 1.5 times the working voltage for a cable of 132 kv rating (the multiplying factor i.e. 1.5 decreases with increase in operating voltage) and the loading current is so adjusted that the temperature of the core of the cable is 5 0 C higher than its specified permissible temperature. The current should be maintained at this value for six hours. (iv) Dielectric Thermal Resistance Test: The ratio of the temperature difference between the core and sheath of the cable and the heat flow from the cable gives the thermal resistance of the sample of the cable. It should be within the specified limits as per the specifications. (v) Life Expectancy Test: The life tests are carried out for reliability studies in service. In order to determine the expected life of the cable under normal stress, accelerated life tests using increased voltages are performed on actual cable lengths. It has been observed that the relation between the expected life of the cable in hours and voltage stress is given by g = Kt (Vn) where g = maximum electrical stress t = expected life of cable in hours K = constant depending on field conditions and materials n = life index depending on the material (vi) Dielectric Power Factor Test: This test is done using the high voltage Schering Bridge. The power factor is measured for different values of voltages e.g. 0.5, 1.0, 1.5 and 2.0 times the rated operating voltages. The maximum value of power factor at normal working voltage does not exceed a specified value. The fig.3 shows the arrangement used for dielectric power factor. A shielding shown by is used which is connected to ground to eliminate the effect of stray capacitances. r x C x C S D R 4 R 3 C 3 Fig.3 Schematic dig. of Schering bridge Test Voltages: The following tables give the test voltages required for different transmission voltages for high voltage testing. Table 1 Test voltages for a.c. equipments System nominal Power frequency Impulse withstand Switching surge 10

11 Voltage (rms) withstand voltage (rms) voltage withstand voltage Table 2 Test voltages for d.c. equipments Nominal Voltage D.C. withstand voltage ±400 ±600 ± Impulse withstand voltage Switching surge withstand voltage If the insulation requirement for a particular voltage are required to be studied in a research and development lab then table 3 and table 4 gives the voltage levels required in lab. Table 3 Test voltages for a.c. system voltage System nominal Power frequency Voltage (rms) withstand voltage (rms) Impulse withstand voltage Switching surge withstand voltage Table 4 Test voltages for d.c. systems Nominal Voltage D.C. withstand voltage ±400 ±600 ± Impulse withstand voltage Switching surge withstand voltage

EE 741 Over-voltage and Overcurrent. Spring 2014

EE 741 Over-voltage and Overcurrent. Spring 2014 EE 741 Over-voltage and Overcurrent Protection Spring 2014 Causes of Over-voltages Lightning Capacitor switching Faults (where interruption occurs prior to zero current crossing) Accidental contact with

More information

VEIKI-VNL Electric Large Laboratories Ltd. H-1158-Budapest, Vasgolyó utca 2-4. HUNGARY

VEIKI-VNL Electric Large Laboratories Ltd. H-1158-Budapest, Vasgolyó utca 2-4. HUNGARY VEIKI-VNL Electric Large Laboratories Ltd. H-1158-Budapest, Vasgolyó utca 2-4. HUNGARY VEIKI-VNL Ltd. VEIKI-VNL Electric Large Laboratories Ltd. is an independent accredited testing member laboratory of

More information

GENERAL. CONSTRUCTION External

GENERAL. CONSTRUCTION External Surge Arresters VariSTAR Type AZG4 Surge Arresters for Systems through 400 kv IEC 20-kA; Line Discharge Class 4 Electrical Apparatus I235-84 GENERAL VariSTAR AZG4 Surge Arresters incorporate the latest

More information

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI

MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI MAHALAKSHMI ENGINEERING COLLEGE TIRUCHIRAPALLI 621213 QUESTION BANK --------------------------------------------------------------------------------------------------------------- Sub. Code : EE2402 Semester

More information

25kV 200A Loadbreak Bushing Insert and Elbow Design Test Report. Report Number:

25kV 200A Loadbreak Bushing Insert and Elbow Design Test Report. Report Number: 25kV 200A Loadbreak Bushing Insert and Elbow Design Test Report Report Number: Date: RN-R7604 9/16/2013 Table of Contents I. OBJECTIVE... 2 II. SUMMARY... 2 III. CONCLUSION... 2 IV. CABLE DATA... 2 V.

More information

HIGH VOLTAGE SURGE ARRESTER SPECIFICATION

HIGH VOLTAGE SURGE ARRESTER SPECIFICATION HIGH VOLTAGE SURGE ARRESTER SPECIFICATION Applications: (Polymer housed MOA for 110kv) (The polymer housed MOA for 10kv) (Porcelain housed MOA for 220kv) (35kv MOA without gaps for middle phase) (110kv

More information

CERTIFICATE OF ACCREDITATION

CERTIFICATE OF ACCREDITATION CERTIFICATE OF ACCREDITATION In terms of section 22(2)(b) of the Accreditation for Conformity Assessment, Calibration and Good Laboratory Practice Act, 2006 (Act 19 of 2006), read with sections 23(1),

More information

CERTIFICATE OF ACCREDITATION

CERTIFICATE OF ACCREDITATION CERTIFICATE OF ACCREDITATION In terms of section 22(2) (b) of the Accreditation for Conformity Assessment, Calibration and Good Laboratory Practice Act, 2006 (Act 19 of 2006), read with sections 23(1),

More information

Technical Specification for 33 KV 200 AMPs,H.G,Fuse set.

Technical Specification for 33 KV 200 AMPs,H.G,Fuse set. Technical Specification for 33 KV 200 AMPs,H.G,Fuse set. 1. SCOPE:- This specification covers the manufacture, testing and supply of 33KV 200 Amps, H.G. Fuse sets 2. The 33 KV H.G. Fuses shall be suitable

More information

Eskom s unique type test requirements for lightning surge arrester ground lead disconnectors

Eskom s unique type test requirements for lightning surge arrester ground lead disconnectors Eskom s unique type test requirements for lightning surge arrester ground lead disconnectors Author & Presenter: R Theron M.Eng Chief Engineer Co-author: H Geldenhuys Phd Corporate Specialist (Technology

More information

SLOVAK UNIVERSITY OF TECHNOLOGY Faculty of Material Science and Technology in Trnava ELECTRICAL ENGINEERING AND ELECTRONICS.

SLOVAK UNIVERSITY OF TECHNOLOGY Faculty of Material Science and Technology in Trnava ELECTRICAL ENGINEERING AND ELECTRONICS. SLOVAK UNIVERSITY OF TECHNOLOGY Faculty of Material Science and Technology in Trnava ELECTRICAL ENGINEERING AND ELECTRONICS Róbert Riedlmajer TRNAVA 2007 Unit 14 - Fundamentals of power system protection

More information

www. ElectricalPartManuals. com CPL Station Arrester Controlled Protective Level Page 1 Indoor-Outdoor Altitude 0-10,000 feet KV

www. ElectricalPartManuals. com CPL Station Arrester Controlled Protective Level Page 1 Indoor-Outdoor Altitude 0-10,000 feet KV December, 1975 New nformation and Supersedes DB 38-131 Pages 1-4, dated May 1972, and 38-121 D WE A, Pages 1-4, dated April1974 E, D, C/1981/ DB Westinghouse Electric Corporation Distribution Apparatus

More information

Question Set(2017) Switch Gear & protection(5 th SEm) 9. Explain the construction and operating principle with proper diagram:

Question Set(2017) Switch Gear & protection(5 th SEm) 9. Explain the construction and operating principle with proper diagram: Question Set(2017) Switch Gear & protection(5 th SEm) 1. What is fault in power system? Classify the fault. What are the bad effects of fault? 2. Define with example: Symmetrical fault and unsymmetrical

More information

15kV 200A Loadbreak Fuse Elbow Design Test Report. Report Number:

15kV 200A Loadbreak Fuse Elbow Design Test Report. Report Number: 15kV 200A Loadbreak Fuse Elbow Design Test Report Report Number: Date: RN-R2601 9/3/2015 Table of Contents 1. Partial Discharge Test Fuse Elbow... 2 2. AC Withstand Voltage Test - Fuse Elbow... 3 3. DC

More information

Study of Fault Clearing by A Circuit Breaker In Presence of A Shunt Capacitor Bank

Study of Fault Clearing by A Circuit Breaker In Presence of A Shunt Capacitor Bank Day 2 - Session V-B 299 Study of Fault Clearing by A Circuit Breaker In Presence of A Shunt Capacitor Bank Murali Kandakatla, B. Kondala Rao, Gopal Gajjar ABB Ltd., Maneja, Vadodara, India Thane Introduction

More information

Characteristics of LV circuit breakers Releases, tripping curves, and limitation

Characteristics of LV circuit breakers Releases, tripping curves, and limitation Characteristics of LV circuit breakers Releases, tripping curves, and limitation Make, Withstand & Break Currents A circuit breaker is both a circuit-breaking device that can make, withstand and break

More information

Independent Testing Laboratory for High Voltage Equipment

Independent Testing Laboratory for High Voltage Equipment T E S T I N G L A B O R A T O R Y Independent Testing Laboratory for High Voltage Equipment 1 CHALLENGING ENVIRONMENT The primary concern for utilities is to ensure grid reliability, efficiency, and security.

More information

Surge Arresters. UltraSIL Housed VariSTAR Station Class Surge Arresters GENERAL CONSTRUCTION

Surge Arresters. UltraSIL Housed VariSTAR Station Class Surge Arresters GENERAL CONSTRUCTION Surge Arresters UltraSIL Housed VariSTAR Station Class Surge Arresters Electrical Apparatus 235-88 GENERAL Cooper Power Systems has set a new standard of excellence for polymerhoused station class surge

More information

023 : 2006 CEB STANDARD. 12kV & 36kV LOAD BREAK SWITCHES CEYLON ELECTRICITY BOARD SRI LANKA

023 : 2006 CEB STANDARD. 12kV & 36kV LOAD BREAK SWITCHES CEYLON ELECTRICITY BOARD SRI LANKA 023 : 2006 CEB STANDARD 12kV & 36kV LOAD BREAK SWITCHES CEYLON ELECTRICITY BOARD SRI LANKA Specification for 12kV & 36kV LOAD BREAK SWITCHES CEB Standard 023 : 2006 CEYLON ELECTRICITY BOARD No. 50, Sir

More information

Resin Impregnated Paper Bushing, Oil to Air, Type GSB Technical guide

Resin Impregnated Paper Bushing, Oil to Air, Type GSB Technical guide 1ZSC000563-AAC en, Rev. 2 Resin Impregnated Paper Bushing, Oil to Air, Type GSB Technical guide This Technical Guide has been produced to allow transformer manufacturers, and their designers and engineers,

More information

VariSTAR Type AZE station-class surge arresters for systems through 345 kv IEEE certified

VariSTAR Type AZE station-class surge arresters for systems through 345 kv IEEE certified Surge s Catalog Data CA235022EN Supersedes TD235009EN September 2014 COOPER POWER SERIES VariSTAR Type AZE station-class surge arresters for systems through 345 kv IEEE certified General Eaton s Cooper

More information

Gas Insulated Substation Testing and Application

Gas Insulated Substation Testing and Application Gas Insulated Substation Testing and Application Course No: E02-020 Credit: 2 PDH Velimir Lackovic, Char. Eng. Continuing Education and Development, Inc. 9 Greyridge Farm Court Stony Point, NY 10980 P:

More information

Longest Life Product for Electric Furnace Applications! 100,000 Operations No Routine Maintenance Required!

Longest Life Product for Electric Furnace Applications! 100,000 Operations No Routine Maintenance Required! DB 750-205 January 2007 Supercedes: December 2006 Now available with Vacuum Interrupter Monitor VBT Switch 15kV - 69kV VBU-T Switch 69kV - 230kV Longest Life Product for Electric Furnace Applications!

More information

Product Description: Objective and Certification: Test Samples and Test Cable:

Product Description: Objective and Certification: Test Samples and Test Cable: Product Description: The CableMate 2LBE loadbreak elbow connector and 2LBI loadbreak bushing insert are fully-shielded, fully submersible, insulated plug-in terminations for connecting underground cables

More information

Capacitor Related Definitions

Capacitor Related Definitions Capacitor Related Definitions July 2005 This is an assembly of definitions used in various standards related to power capacitors. The listing is intended to include all of the definitions in IEEE Standards

More information

TECHNICAL DESCRIPTION

TECHNICAL DESCRIPTION DC Circuit Breaker TECHNICAL DESCRIPTION TRK5650523200 Ed.1 of 23/07/13 CONTENTS 1. INTRODUCTION... 2 2. DESCRIPTION... 2 2.1 Description of circuit breaker... 2 2.2 Operating mode... 2 2.3 Variants and

More information

Overview Overvoltage protection

Overview Overvoltage protection A P P L I C AT I O N N OT E 1.0 Overview Overvoltage protection The APPLICATION NOTES (AN) are intended to be used in conjunction with the APPLICATION GUIDELINES Overvoltage protection Metal-oxide surge

More information

Bus bar Bushings up to 1.1kV and from 1.6kA to 4kA for Liquid Filled Transformers:

Bus bar Bushings up to 1.1kV and from 1.6kA to 4kA for Liquid Filled Transformers: 4 (Four) Pole Monoblock: Bus bar Bushings up to 1.1kV and from 1.6kA to 4kA for Liquid Filled Transformers: Designed and manufactured in accordance with EN 50336:2002 and BS 2562: 1979 1 Introduction:

More information

FUSE TECHNOLOGY Ambient temperature

FUSE TECHNOLOGY Ambient temperature This fuse technology guide will discuss basic fuse operating, application, and selection criteria concepts. The intended purpose of this section is to aid designers with the operation and characteristics

More information

Electrical Test of STATCOM Valves

Electrical Test of STATCOM Valves 21, rue d Artois, F-75008 PARIS 619 CIGRE 2016 http : //www.cigre.org Electrical Test of STATCOM Valves Baoliang SHENG 1, Christer DANIELSSON 1, Rolf NEUBERT 2, Juha TURUNEN 3, Yuanliang LAN 4, Fan XU

More information

CERTIFIED TEST REPORT

CERTIFIED TEST REPORT CP No.: CP0316 Rev. 01 Page: 1 of 22 CERTIFIED TEST REPORT COOPER POWER SYSTEMS FOUR POSITION SECTIONALIZING LOADBREAK SWITCH 12.5 ka Momentary and Making Rating REV. 01 DATE: December 3, 2004 ORIGINAL

More information

Issued by : Switchgear Contracts Division LARSEN & TOUBRO LIMITED Powai Works, Mumbai October December 1996

Issued by : Switchgear Contracts Division LARSEN & TOUBRO LIMITED Powai Works, Mumbai October December 1996 Issued by : Switchgear Contracts Division LARSEN & TOUBRO LIMITED Powai Works, Mumbai 400 072. October December 1996 Prospect/ Retrospect IS/IEC Specification In the previous three issues of L&T Current

More information

DYNACOMP. The top-class reactive power compensator

DYNACOMP. The top-class reactive power compensator DYNACOMP The top-class reactive power compensator Dynacomp vs Electromechanical switching of capacitors Electromechanical switching of capacitors The Dynacomp : the top-class dynamic compensator Transients

More information

3.2. Current Limiting Fuses. Contents

3.2. Current Limiting Fuses. Contents .2 Contents Description Current Limiting Applications................. Voltage Rating.......................... Interrupting Rating....................... Continuous Current Rating................ Fuse

More information

H U B B ELL L ABOR ATORIES CAPABILITY GUIDE

H U B B ELL L ABOR ATORIES CAPABILITY GUIDE H U B B ELL L ABO R ATO R I E S CAPABILITY GUIDE INTRODUCTION Hubbell Power Systems, Inc. manufactures a wide variety of products for the electric utility, telecommunications, civil construction, transportation,

More information

ANSI Design Test Report ANSI Glass Bells Catalog # PSN21156

ANSI Design Test Report ANSI Glass Bells Catalog # PSN21156 ANSI Design Test Report ANSI 52-11 Glass Bells Catalog # PSN21156 This design test report records the results of laboratory tests performed on the ANSI 52-11 Glass Bells which met or exceeded all performed

More information

The University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 2

The University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 2 The University of New South Wales School of Electrical Engineering and Telecommunications Industrial and Commercial Power Systems Topic 2 SWITCHBOARDS Overview Also called Switchgear and Controlgear Assembly

More information

Pretest Module 29 High Voltage Unit 1

Pretest Module 29 High Voltage Unit 1 Pretest Module 29 High Voltage Unit 1 1. Is a person qualified to work on high-voltage installations when this module is completed? 2. What is the code definition of high-voltage? 3. What is the IEEE definition

More information

The galvanic separation of the primary or actuating circuit and the load circuits

The galvanic separation of the primary or actuating circuit and the load circuits RELAY BASICS Relays are electro magnetically operated switches. An actuating current on a coil operates one or more galvanically separated contacts or load circuits. The electro mechanical relay is a remote

More information

MEDIUM VOLTAGE NETWORKS

MEDIUM VOLTAGE NETWORKS MEDIUM VOLTAGE NETWORKS LIGHTNING ARRESTERS & INSULATORS SICAME GROUP OUR EXPERIENCE With 25 years of experience in the field of over protection for medium lines, DERVASIL designs and manufactures zinc

More information

Technical Specification for Pole Mounted Capacitor Rack

Technical Specification for Pole Mounted Capacitor Rack Technical Specification for Pole Mounted Rack Page 1 1. Scope and Function a) Pole mounted capacitor racks shall be installed on a distribution feed as an economical means of applying capacitor units to

More information

SWITCHGEAR FOR SERVICE UP TO 36kV (CABLE AND OVERHEAD CONDUCTOR CONNECTED)

SWITCHGEAR FOR SERVICE UP TO 36kV (CABLE AND OVERHEAD CONDUCTOR CONNECTED) PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Issue 3 2012 SWITCHGEAR FOR SERVICE UP TO 36kV (CABLE AND OVERHEAD CONDUCTOR CONNECTED) www.energynetworks.org 2012 Energy Networks

More information

CONTENTS About the company 1. Low-voltage arresters LVA type 2. Metal-oxide surge arresters for distribution systems. 3.

CONTENTS About the company 1. Low-voltage arresters LVA type 2. Metal-oxide surge arresters for distribution systems. 3. CONTENTS About the company 4 1. Low-voltage arresters LVA type 5 2. Metal-oxide surge arresters for distribution systems. 6 2.1 PA-DM type 6 Dimensions of arresters of PA-DM 9 2.2 PA-DH types 10 Dimensions

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) (Corr.1 June 2018) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements

More information

List of Mandatory Commercial Documents ITEM DESCRIPTION REQUIRED ITEM DRAWING DOCUMENTS NAME REQUIRED ITEM TEST DOCUMENTS NAME

List of Mandatory Commercial Documents ITEM DESCRIPTION REQUIRED ITEM DRAWING DOCUMENTS NAME REQUIRED ITEM TEST DOCUMENTS NAME Terms and Conditions : 1) Before proceed please confirm material documents and test documents are available with you. 2) Vendor Document Verification Registration Fee Rs.5000 + payment gateway charges,

More information

High Voltage Surge Arresters Buyer s Guide Section Transmission Line Arrester PEXLINK

High Voltage Surge Arresters Buyer s Guide Section Transmission Line Arrester PEXLINK High Voltage Surge Arresters Buyer s Guide Section Transmission Line Arrester PEXLINK Definitions Transmission Line Arresters Backflashover Occurs when lightning strikes the tower structure or overhead

More information

Type HS PEXLIM-P Surge Arresters Maximum System Voltage 123 kv to 800 kv

Type HS PEXLIM-P Surge Arresters Maximum System Voltage 123 kv to 800 kv Type HS PEXLIM-P Surge Arresters Maximum System Voltage 123 kv to 800 kv HS PEXLIM-P Metal Oxide Surge Arrester HS PEXLIM-P Surge Arresters are used for the protection of switchgear, transformers and other

More information

High Voltage and Extra High Voltage Cables

High Voltage and Extra High Voltage Cables High Voltage and Extra High Voltage Cables GUIDE TO THE SELECTION OF EHV AND HV CABLES EHV and HV cables are specially designed on the basis of the project data. To determine appropriate design of a high

More information

Impulse Voltage Test System, Q Structure, kV

Impulse Voltage Test System, Q Structure, kV TCDYQ Series Impulse Voltage Test System, Q Structure, 200-3600kV Applications: Shunt reactors Power transformers Distribution transformer Instrument transformers Cables (type tests) Bushings Arresters

More information

INTRODUCTION. The plug-in connection on the cables and lightning arrestors, allows for easy installation and replacement.

INTRODUCTION. The plug-in connection on the cables and lightning arrestors, allows for easy installation and replacement. INTRODUCTION The Power Systems 44 kv MiniSub TM is the most compact system at this voltage available. Utilizing a deadfront termination and lightning arrestor setup, it eliminates the line top or side

More information

Zinc Oxide Surge Arrester EXLIM R

Zinc Oxide Surge Arrester EXLIM R Zinc Oxide Surge Arrester EXLIM R Protection of switchgear, transformers and other equipment in high systems against atmospheric and switching overs. For use when requirements of lightning intensity, energy

More information

I Surge Arresters. UltraSIL Polymer-Housed VariSTAR Type U3 Surge Arrester for Systems through 275 kv IEC 10 ka; Line Discharge Class 3 GENERAL

I Surge Arresters. UltraSIL Polymer-Housed VariSTAR Type U3 Surge Arrester for Systems through 275 kv IEC 10 ka; Line Discharge Class 3 GENERAL Surge Arresters UltraSIL Polymer-Housed VariSTAR Type U3 Surge Arrester for Systems through 275 kv IEC 10 ka; Line Discharge Class 3 Electrical Apparatus I235-93 GENERAL UltraSIL Polymer-Housed VariSTAR

More information

Overview about research project Energy handling capability

Overview about research project Energy handling capability Cigré WG A3.25 meeting San Diego October 16, 2012 Max Tuczek, Volker Hinrichsen, TU Darmstadt Note: all information beginning from slide 21 are provisional results in the frame of Cigré WG A3.25 work,

More information

Maximum temp. rise in oil by 40 thermometer above design ambient (deg C) specified time Short circuit rating (Sec) for As per IS 2026

Maximum temp. rise in oil by 40 thermometer above design ambient (deg C) specified time Short circuit rating (Sec) for As per IS 2026 TECHNICAL PERTICULAR FOR 1.6 MVA 6.6/0.433 KV SERVICE TRANSFORMER 1.00.00 GENERAL 1.01.00 Service SERVICE 1.02.00 Make ASHOK/VOLTAMP/DANKE/CGL 1.03.00 Type CORE 1.04.00 Location OUTDOOR 1.05.00 Specification

More information

School of Electrical and Information Engineering. ELEC High Voltage. University of Sydney. Dr Keith Mitchell. Engineering

School of Electrical and Information Engineering. ELEC High Voltage. University of Sydney. Dr Keith Mitchell. Engineering University of Sydney School of Electrical and Information Engineering Dr Keith Mitchell ELEC 5205 - High Voltage Engineering ELEC 5205 - High Voltage Engineering 3. Switchgear Types of Power System Switchgear

More information

ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com. Energy. Fast.

ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com. Energy. Fast. ZF SERIES HV GAS INSULATED SWITCHGEAR (GIS) tgood.com Energy. Fast. TGOOD produces over 5000 switchgear units annually for projects around the globe PRODUCT OVERVIEW High performance alternative to air

More information

WESTERN ELECTRICITY SUPPLY COMPANY OF ORISSA, WESCO. GUARANTEED TECHNICAL PARTICULARS 1 of 2

WESTERN ELECTRICITY SUPPLY COMPANY OF ORISSA, WESCO. GUARANTEED TECHNICAL PARTICULARS 1 of 2 Sl. No. WESTERN ELECTRICITY SUPPLY COMPANY OF ORISSA, WESCO GUARANTEED TECHNICAL PARTICULARS 1 of 2 REQUIREMENTS 11 Kv, 200 Amps, A.B Switches. Particulars 1 Maker's name and Country of origin. 2 Type

More information

013 : 2009 CEB SPECIFICATION MOULDED CASE CIRCUIT BREAKERS

013 : 2009 CEB SPECIFICATION MOULDED CASE CIRCUIT BREAKERS 013 : 2009 CEB SPECIFICATION MOULDED CASE CIRCUIT BREAKERS FOR OVERHEAD NETWOKS CEYLON ELECTRICITY BOARD SRI LANKA Specification for MOULDED CASE CIRCUIT BREAKERS FOR OVERHEAD NETWOKS CEB Specification

More information

Technical Specification For Outdoor Substation Harmonic Filter Banks

Technical Specification For Outdoor Substation Harmonic Filter Banks Technical Specification For Outdoor Substation Harmonic Filter Banks One of Three 5th, 11th & 23rd, 34.5 kv, Rated Harmonic Filter Assemblies Provided for a Central Venezuela Heavy Oil Production Field

More information

VariSTAR Type AZG2 Surge Arrester, 10,000 A, Line Discharge Class 2 IEC (99-4)

VariSTAR Type AZG2 Surge Arrester, 10,000 A, Line Discharge Class 2 IEC (99-4) CP9817 PAGE: 1 of 16 CERTIFIED TEST REPORT VariSTAR Type AZG2 Surge Arrester, 10,000 A, Line Discharge Class 2 IEC 60099-4 (99-4) 0711 Supersedes 0601 Cooper Industries. All Rights Reserved. CP9817 PAGE:

More information

Technical Specification of 11KV 200Amp. (3-Pole/2-Pole) Air Break Switch Scope Description of the materials Standards Insulator make

Technical Specification of 11KV 200Amp. (3-Pole/2-Pole) Air Break Switch Scope Description of the materials Standards Insulator make Technical Specification of 11KV 200Amp. (3-Pole/2-Pole) Air Break Switch 1. Scope:- This specification covers manufacturing, testing and supply of 11KV 200Amp. 50Hz Air Break switches for outdoor installation

More information

Miniature circuit breaker Application guide

Miniature circuit breaker Application guide Miniature circuit breaker Application guide Miniature Miniature circuit circuit breakers breakers Application S200 guide Introduction The circuit breaker plays an important role in providing over-current

More information

Zinc-Oxide Surge Arrester TEXLIM Q-C

Zinc-Oxide Surge Arrester TEXLIM Q-C Zinc-Oxide Surge Arrester TEXLIM Q-C Protection of switchgear, transformers and other equipment in high systems against atmospheric and switching overs. in areas with very high lightning intensity where

More information

FAQ S. Main Switchboard Design Criteria. ENGINEERED SOLUTIONS FOR ALL YOUR SWITCHBOARD NEEDS

FAQ S. Main Switchboard Design Criteria.   ENGINEERED SOLUTIONS FOR ALL YOUR SWITCHBOARD NEEDS FAQ S Main Switchboard Design Criteria h ENGINEERED SOLUTIONS FOR ALL YOUR SWITCHBOARD NEEDS www.electricalswitchboards.com.au Main switchboard Design criteria Q: What is the Australian standard for main

More information

A New Synthetic Test Circuit For the Operational Tests of HVDC Thyristor Modules

A New Synthetic Test Circuit For the Operational Tests of HVDC Thyristor Modules Paper presented at IEEE PELS APEC Conference on March -8,, at Anaheim, USA. Conf. Proceedings pp.-6 A New Synthetic Test Circuit For the Operational Tests of HVDC Thyristor Modules B.L. Sheng E. Jansson

More information

1ZSC AAA en, Rev. 6. Resin impregnated paper bushing, oil to SF 6., type GSBK Technical guide

1ZSC AAA en, Rev. 6. Resin impregnated paper bushing, oil to SF 6., type GSBK Technical guide 1ZSC563-AAA en, Rev. 6 Resin impregnated paper bushing, oil to SF 6, type GSBK Technical guide Original instruction The information provided in this document is intended to be general and does not cover

More information

HIGH VOLTAGE MODULE TEST SYSTEM

HIGH VOLTAGE MODULE TEST SYSTEM HIGH VOLTAGE MODULE TEST SYSTEM 4.0/4 Module Test Systems n AC, DC, and impulse testing n Factory testing n R&D n Education / training MODULES FOR VOLTAGE GENERATION Test transformers for 100 and 200 kv

More information

Small wonder. Station service voltage transformers for small power requirements

Small wonder. Station service voltage transformers for small power requirements Small wonder Station service voltage transformers for small power requirements MATHEW PAUL An estimated 1.3 billion people worldwide have no access to electricity. In small communities, this is often due

More information

Grounding Of Standby & Emergency Power Systems

Grounding Of Standby & Emergency Power Systems July / August 2007 ELECTRICAL LINE 53 Grounding Of Standby & Emergency Power Systems By Andrew Cochran Power continuity is essential in many industrial and commercial installations where a trip out due

More information

EXPERIMENT CALIBRATION OF 1PHASE ENERGY METER

EXPERIMENT CALIBRATION OF 1PHASE ENERGY METER EXPERIMENT CALIBRATION OF PHASE ENERGY METER THEORY:- Energy Meters are integrating instruments used to measure the quantity of electrical energy supplied to a circuit in a given time. Single phase energy

More information

THP145 HYBRID GAS INSULATED SWITCHGEAR (HGIS) Energy, Fast! tgood.com

THP145 HYBRID GAS INSULATED SWITCHGEAR (HGIS) Energy, Fast! tgood.com THP145 HYBRID GAS INSULATED SWITCHGEAR (HGIS) Energy, Fast! tgood.com TGOOD produces over 5000 switchgear units annually for projects around the globe SOLUTION OVERVIEW For use in affordable air insulated

More information

APPARATUS AND MATERIAL REQUIRED Resistor, ammeter, (0-1.5A) voltmeter (0-5V ), battery, one way key, rheostat, sand paper, connecting wires.

APPARATUS AND MATERIAL REQUIRED Resistor, ammeter, (0-1.5A) voltmeter (0-5V ), battery, one way key, rheostat, sand paper, connecting wires. ACTIVITIES ACTIVITY 1 AIM To assemble the components of a given electrical circuit. APPARATUS AND MATERIAL REQUIRED Resistor, ammeter, (0-1.5A) voltmeter (0-5V ), battery, one way key, rheostat, sand paper,

More information

/12/$ IEEE. M. Bashir M.Sc student, Student Member, IEEE Ferdowsi University of Mashhad Mashhad, Iran

/12/$ IEEE. M. Bashir M.Sc student, Student Member, IEEE Ferdowsi University of Mashhad Mashhad, Iran Effect of Increasing the Grounding Grid Resistance of a Ground System at a Substation on the Safety and Transient Overvoltage on the Interior Equipments M. Bashir M.Sc student, Student Member, IEEE Ferdowsi

More information

CERTIFIED TEST REPORT. Cooper Power Systems. 25 kv Class 200 Amp 15.2/26.3 kv SEPARABLE CONNECTOR SYSTEM

CERTIFIED TEST REPORT. Cooper Power Systems. 25 kv Class 200 Amp 15.2/26.3 kv SEPARABLE CONNECTOR SYSTEM CP No.: CP9806 Page: 1 of 35 CERTIFIED TEST REPORT Cooper Power Systems 25 kv Class 200 Amp SEPARABLE CONNECTOR SYSTEM Includes Cooper POSI-BREAK Loadbreak Elbow and Insulated Protective Cap April 3, 1998

More information

ANSI DESIGN TEST REPORT Report No. EU 1512-HR-00.5 Type PDV 100 Optima Heavy Duty Distribution Class Surge Arrester

ANSI DESIGN TEST REPORT Report No. EU 1512-HR-00.5 Type PDV 100 Optima Heavy Duty Distribution Class Surge Arrester ANSI DESIGN TEST REPORT Report No. EU 1512-HR-00.5 Type PDV 100 Optima Heavy Duty Distribution Class Surge Arrester This report records the results of the design tests made on Type PDV 100 Optima Distribution

More information

A novel synthetic test system for thyristor level in the converter valve of HVDC power transmission

A novel synthetic test system for thyristor level in the converter valve of HVDC power transmission A novel synthetic test system for thyristor level in the converter valve of HVDC power transmission Longchen Liu 1, Ke Yue 2, Lei Pang 2, Xinghai Zhang 1, Yawei Li 1 and Qiaogen Zhang 2 1 State Grid Sichuan

More information

Surge Arresters. UltraSIL Polymer-Housed Evolution (10 ka) Surge Arresters. General. Construction. features

Surge Arresters. UltraSIL Polymer-Housed Evolution (10 ka) Surge Arresters. General. Construction. features Surge s Electrical Apparatus 235-99 General Cooper Power Systems set the standard for design, manufacturing and delivery of polymeric distribution arresters with the UltraSIL polymerhoused arrester family.

More information

Voltage limiting device HVL

Voltage limiting device HVL Datasheet Voltage limiting device HVL 60-0.3 1 2 3 3 Equivalent circuit of voltage limiting device Type HVL 60-0.3 1 MO-surge arrester 2 Trigger electronics 3 Thyristor Product Description The HVL 60-0.3

More information

High Voltage Engineering

High Voltage Engineering High Voltage Engineering Course Code: EE 2316 Prof. Dr. Magdi M. El-Saadawi www.saadawi1.net E-mail : saadawi1@gmail.com www.facebook.com/magdi.saadawi 1 Contents Chapter 1 Introduction to High Voltage

More information

Outdoor live tank SF6 circuit breaker EDT with integrated current transformer up to 72.5 kv

Outdoor live tank SF6 circuit breaker EDT with integrated current transformer up to 72.5 kv Outdoor live tank SF6 circuit breaker EDT with integrated current transformer up to 72.5 kv SF6 circuit breaker EDT with integrated current transformer ABB is a world leader in live tank circuit breaker

More information

CHAPTER 3 CAUSES AND EFFECTS OF ELECTRICAL FAULTS

CHAPTER 3 CAUSES AND EFFECTS OF ELECTRICAL FAULTS 22 CHAPTER 3 CAUSES AND EFFECTS OF ELECTRICAL FAULTS 3.1 INTRODUCTION A large number of asynchronous motors are used in industrial processes even in sensitive applications. Consequently, a defect can induce

More information

NXPLUS C Single busbar. Maintenance-free for lifetime

NXPLUS C Single busbar. Maintenance-free for lifetime NXPLUS C Single busbar Maintenance-free for lifetime Energy Distribution Welcome! Page 2 Content Overview Technical data Typicals Panel design Circuit-Breaker panel Busbar Operation Metering Low-voltage

More information

TECHNICAL SPECIFICATION OF 11KV SF6 / VCB METAL ENCLOSED, INDOOR (PANEL TYPE) / OUTDOOR RING MAIN UNIT (RMU). (IEC standard equipment)

TECHNICAL SPECIFICATION OF 11KV SF6 / VCB METAL ENCLOSED, INDOOR (PANEL TYPE) / OUTDOOR RING MAIN UNIT (RMU). (IEC standard equipment) TECHNICAL SPECIFICATION OF 11KV SF6 / VCB METAL ENCLOSED, INDOOR (PANEL TYPE) / OUTDOOR RING MAIN UNIT (RMU). (IEC standard equipment) 1 SCOPE OF SUPPLY This specification covers design, manufacture, shop

More information

Transformer bushings, type GOH. Technical guide

Transformer bushings, type GOH. Technical guide Transformer bushings, type GOH Technical guide This Technical Guide has been produced to allow transformer manufacturers, and their designers and engineers, access to all the technical information required

More information

Guideline No.: E-07(201610) E-07 TRANSFORMERS. Issued date: October 28,2016. China Classification Society

Guideline No.: E-07(201610) E-07 TRANSFORMERS. Issued date: October 28,2016. China Classification Society Guideline No.: E-07(201610) E-07 TRANSFORMERS Issued date: October 28,2016 China Classification Society Foreword: This Guide is a part of CCS Rules, which contains technical requirements, inspection and

More information

Voltage limiting device HVL

Voltage limiting device HVL Datasheet Voltage limiting device HVL 120-0.3 1 2 3 3 Equivalent circuit of voltage limiting device Type HVL 120-0.3 1 MO-surge arrester 2 Trigger electronics 3 Thyristor Product Description The HVL 120-0.3

More information

CHAPTER 3. Experimental Test Set-Up

CHAPTER 3. Experimental Test Set-Up 57 CHAPTER 3 Experimental Test Set-Up 3.0 Introduction The electrical performance of porcelain insulators in the presence of pollution and moisture is improved by coating with room temperature vulcanizing

More information

Safe, fast HV circuit breaker testing with DualGround technology

Safe, fast HV circuit breaker testing with DualGround technology Safe, fast HV circuit breaker testing with DualGround technology Substation personnel safety From the earliest days of circuit breaker testing, safety of personnel has been the highest priority. The best

More information

Resin Impregnated Paper Bushing, Oil to SF 6. , Type GSBK

Resin Impregnated Paper Bushing, Oil to SF 6. , Type GSBK 1ZSC563-AAA en, Rev. 2 Resin Impregnated Paper Bushing, Oil to SF 6, Type GSBK Technical guide This Technical Guide has been produced to allow transformer manufacturers, and their designers and engineers,

More information

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks D. M. Nobre W. L. A. Neves B. A. de Souza Departamento de Engenharia Elétrica - UFPB Av. Aprígio Veloso, 882 Bodocongó 58.109-970,

More information

1ZSE en, Rev. 7. Transformer bushings, type GOB Technical guide

1ZSE en, Rev. 7. Transformer bushings, type GOB Technical guide 1ZSE 2750-102 en, Rev. 7 Transformer bushings, type GOB Technical guide This Technical Guide has been produced to allow transformer manufacturers, and their designers and engineers, access to all the technical

More information

Live Tank Circuit Breakers Buyer s Guide

Live Tank Circuit Breakers Buyer s Guide Live Tank Circuit Breakers Buyer s Guide Live Tank Circuit Breakers Buyer s Guide Edition 2, 2003-06 0-1 Contents Table of Contents Products Chapter-Page Introduction A-2 Explanations B-1 Puffer, Auto-Puffer

More information

(Under Two Part Bid System) Tender No: NFV/ PUR/ BEC K for VCB

(Under Two Part Bid System) Tender No: NFV/ PUR/ BEC K for VCB Annexure-V (Under Two Part Bid System) Tender No: NFV/ PUR/ BEC 160546 K for VCB Technical specification for NIT SL NO 1 S.No. Description NFL requirement as per NIT Vendors Comment [Agreed / If not agreed,

More information

TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH

TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. PAGE 1 OF 7 TECHNICAL SPECIFICATION FOR 11 KV AUTOMATIC CAPACITOR SWITCH 1.0 SCOPE:

More information

MEDIUM VOLTAGE PRODUCTS. Fault Current Limiters I S. -limiter and FC-Protector The worldʼs fastest switching devices

MEDIUM VOLTAGE PRODUCTS. Fault Current Limiters I S. -limiter and FC-Protector The worldʼs fastest switching devices MEDIUM VOLTAGE PRODUCTS The worldʼs fastest switching devices 2 FAULT CURRENT LIMITERS THE WORLDʼ S FASTETST SWITCHING DEVICES The worldʼs fastest switching devices ABBʼs fault current limiters disconnect

More information

Power & High Voltage Joslyn Hi-Voltage Overhead Reclosers & Switches H-220. Series HVI Hi-Velocity Interrupter Attachment

Power & High Voltage Joslyn Hi-Voltage Overhead Reclosers & Switches H-220. Series HVI Hi-Velocity Interrupter Attachment Use load interrupter attachments to enable loop sectionalizing, line dropping, load breaking and transformer-magnetizing current interruption. Increase the capability of your disconnect switches by adding

More information

B kv T&D GAS INSULATED SWITCHGEAR

B kv T&D GAS INSULATED SWITCHGEAR GAS INSULATED SWITCHGEAR B 105 170 300 kv The increasing demand for electrical power in cities and industrial centers necessitates the installation of a compact and efficient distribution and transmission

More information

Effective discrimination of protective devices

Effective discrimination of protective devices Effective discrimination of protective devices In the event of a fault occurring on an electrical installation only the protective device nearest to the fault should operate,leaving other healthy circuits

More information

Energy Transmission & Distribution Services - Italy. SVEPPI laboratory...our services for your success. Answers for energy.

Energy Transmission & Distribution Services - Italy. SVEPPI laboratory...our services for your success. Answers for energy. Energy Transmission & Distribution Services - Italy SVEPPI laboratory...our services for your success. Answers for energy. ...our services for your success ENERGY - T&D Services Experience teaches us that

More information

DynaVar Arresters IEC Line Discharge Classes 2, 3, 4 & 5

DynaVar Arresters IEC Line Discharge Classes 2, 3, 4 & 5 Section 204-1 204 DynaVar Arresters IEC Line Discharge Classes 2, 3, 4 & 5 Web: http://www.hubbellpowersystems.com E-mail: hpsliterature@hps.hubbell.com Printed in USA RGS 1M 204-2 Table of Contents Page

More information